Ice Pac Governance and Decision Making Submission
Ice Pac Governance and Decision Making Submission
Its network of experts offers trusted, impartial advice to politicians and decision makers
on how to build and adapt infrastructure to create a more sustainable world.
Submission
The case for improved major project governance and decision making
But, as in other jurisdictions, the government’s ability to deliver major, and mega,
projects has failed to meet expectations over many years.
Unless delivery issues are addressed, the public are likely to lose faith that they will get
the infrastructure they have been promised. Ongoing delivery challenges would also
jeopardise the net zero transition, which needs to progress at pace.
Equally, the opportunity cost of the added cost to each individual project comes at the
expense of other infrastructure investments that could deliver substantial benefits and
an improved quality of life for the public. Non-delivery and the stop-start nature of
project prioritisation also further discourages private investment – or costs the public
more as private sector players price additional risk.
As such, the ICE welcomes the Public Accounts Committee’s inquiry on governance
and decision making on major projects.
However, this inquiry is far from the first to focus on these issues. There is plenty the
PAC can learn from both the failures and successes of domestic and international
projects including High Speed 2 which the ICE has produced a review of.
The industry and government’s own recommendations for change have, for many years,
been relatively consistent, and are numerous. The questions the inquiry might focus on
include how existing and new structures in the government advisory and assurance
system (including the National Infrastructure and Service Transformation Authority)
might help embed these learnings across major public projects.
Similarly, on the megaproject front, a McKinsey and Co. study reviewed a dataset of
more than 500 global projects above US$1 billion in resource industries and
infrastructure and found that only 5 per cent of projects were completed within their
original budget and schedule. In the completed projects, the average cost overrun was
37 per cent, and the average schedule overrun was 53 per cent2.
1
Bent Flyvberg (2014) What you Should Know about Megaprojects and Why: An Overview.
2
McKinsey and co (2017) The art of project leadership: Delivering the world’s largest projects | McKinsey.
This area has been well studied. The following sections lay out a non-exhaustive
collection of key learnings the PAC may want to consider.
In 2019, an ICE report focused on how more collaborative working, better governance,
data-led frameworks and sharing of best practice could support improvements in
project delivery, and outturn forecasting3.
Scoping projects
Scope change, scope creep or incomplete designs often occur once work has
commenced. Too often designers, risk adjusters and contractors work separately or are
not brought together at an early stage.
Going forward, infrastructure owners should complete scope, design and exploration
before commencement of work is allowed, taking steps to include contractors early.
Judging success
Government relies too much on cost (and to some extent time) to determine project
success and frequently reduces contingency to 'save' money – limiting room for
manoeuvre if new information comes to light, or if economic conditions change.
Scrutiny of projects often focuses on the process of completion against arbitrary
budgets and not the wider benefits infrastructure can deliver in the long-term.
The government and infrastructure owners must move away from capital cost as the
most important metric when assessing project benefits, recognising the importance of
whole-life economic, social and environmental value.
3
ICE (2019) ice-report-reducing-the-gap-between-cost-estimates-and-outturns-for-major-
infrastructure-projects-and-programmes.pdf
Estimates are often set at a fixed price point, before full project or programme scope
and complexity are known. Tenders are approved based on these early estimates and
contracts allocated, potentially years before scope and complexity are understood.
Principles set out in the Sourcing Playbook should be mandatory for government
infrastructure owners, this includes infrastructure owners undertaking should-cost
modelling to help inform their expectations and knowledge of appropriate tender prices
during the procurement process. The ICE has since recommended that the
Construction Playbook be mandated on a comply only basis.
Since the publication of the ICE’s paper in 2019, there have been changes in the UK
major project delivery environment – including the publication and relevant updates to
the Construction Playbook, the release of the IPA’s cost estimation guidelines and the
Labour Government’s mission-led approach, among other changes, that will require a
different approach to project governance arrangements.
4
National Audit Office (2025) Governance and decision-making on mega-projects - NAO insight
5
Office for Value for Money (2025) Terms of reference for VfM Study on the governance and budgeting
arrangements for mega projects - GOV.UK
6
Ibid.
strategic workforce or supply chain planning effectively. The 10-year
infrastructure strategy being developed by HM Treasury and NISTA will go some
way to addressing this issue, but will require long term support within and across
the major parties in the House of Commons, as well as the infrastructure sector
to realise its potential.
• cost and time overruns of mega projects have a knock-on impact on all the other
projects a department is running, and the mega project’s risks are too large for a
department to manage.
• excessive optimism in the initial estimates of the cost and timeline of projects,
which means decisions to proceed are not accompanied by sufficiently robust
and realistic assessments of affordability.
• projects being initiated before they are ready, locking in costs and timings before
the scope and benefits are defined.
A recent Boston Consulting Group report lays out how supply chain constraints are
likely to worsen in the coming years8. Key drivers include international competition for in
demand skills, a lack of coordination and joined up planning at the national level and a
lack of client-side leadership creating inefficiencies in supply chains, historically high
demand for infrastructure investment creating an environment where market players as
less likely to accept risk, siloed decision making, and poor scoping.
7
National Infrastructure Commission (2024) Cost drivers of major infrastructure projects in the UK - NIC.
8
Boston Consulting Group (2025) https://www.bcg.com/united-kingdom/centre-for-
growth/insights/uplift-in-demand-shortfall-in-supply-can-the-uk-deliver-on-its-infrastructure-
investment-ambitions/
Lessons from HS2
The Committee should consider the lessons from individual projects – both good and
bad – during the course of its Inquiry.
Last year, the ICE released a paper as part of a policy programme focussed on the
lessons that can be learnt from the cancellation of the northern leg of High Speed 2
(HS2)9.
9
ICE (2024) Learning Lessons From The Cancellation Of HS2’s Northern Leg | Institution of Civil Engineers
(ICE)
• Sufficient time is needed to assess alternative options, build in flexibility and
challenge designs and specifications.
• Give due consideration to how major projects interact with other infrastructure
to maximise benefits and minimise disruption.
The contracting approach should set up the project for best-practice delivery.
Major projects and programmes require clarity and consistency on outcomes to achieve
political and public buy-in and deliver value for money.
• An overarching transport strategy would clarify the strategic need for major
projects.
The benefits of major projects are often understated and need to be better
articulated. All of the senior decision-makers on the project had different ideas
of why HS2 was important, with some seeing it as a project focused on either
speed, capacity, economic growth or demonstrating Britain’s modernity. These
value judgements will have informed the decisions made by senior politicians.
Over time, this meant decisions were no longer aligned to any central purpose,
and the narrative over the need for HS2 was constantly shifting.
This lack of a well-embedded strategic story for HS2 meant that a significant
cohort of the public was indifferent to the project. Therefore, it did not take much
for them to become detractors, particularly as planning approval and then
construction for Phase 1 started.
In addition to these key takeaways, it was notable that the Prime Minister was in a
position to make a decision about the cancellation of the northern leg, without primary
legislation. This was despite the Department for Transport and HS2 receiving
authorisations to spend and permission to proceed through Hybrid and other bills.
Ultimately none of that matters if the UK government decides not to act on Parliament’s
instruction on investment.
The paper also notes that, among other political factors, fiscal rules set by the then
chancellor Jeremy Hunt in 2022, particularly the requirement for debt to be on course to
fall as a share of national income in five years, may have influenced the decision to
cancel HS2’s northern leg. The rule was meant to be a strong political message and a
way to ensure long-term financial sustainability. However, delaying investments
expected to deliver economic benefits and introducing more uncertainty about the
government’s commitment to major infrastructure projects undermined, rather than
supported, those objectives.
It has also been suggested that the decision to cancel may have been linked to a wider
political need which had little to do with HS2 and spiralling costs, and more to do with
the upcoming election and building an image for the Sunak government as being
distinct from other political parties, willing to challenge the status quo and committed
to investing in other projects.
The impact of shifting political priorities on the delivery of HS2 has negatively impacted
the UK’s reputation as a major project deliverer.
The ICE also notes that, while a small percentage of projects globally deliver on all three
outcomes – on time, to budget and with full benefit delivered, when they do, the
infrastructure system as a whole could do a better job at shining a light on what has
gone right.
10
Public Accounts Committee (2022) Use of evaluation and modelling in government - Committee of
Public Accounts.
As it relates to this topic, the ICE has recently made a set of recommendations on the
priorities NISTA should take forward11.
• In the context of NISTA being brought in under the wing of HM Treasury, there is a
need to ensure that independent oversight is part of the body’s governance
structure, to proactively challenge the government and that it does not shy away
from difficult questions.
• Embed best practice and raise capability across government: Mandate the use of
the Construction Playbook and Constructing the Gold Standard by government
departments on a ‘comply’ basis, rather than ‘comply or explain’.
• Inform and engage the public: Ensure the public understands the benefits of
infrastructure investment and that decision-makers understand the needs of
infrastructure users.
Conclusion
This submission represents a non-exhaustive collection of some of the
recommendations the ICE considers particularly important for the Inquiry to take on
board as it begins its work.
The challenge is how the public sector and their industry partners are able to properly
integrate these lessons into major project delivery in the years to come. There is a clear
need for a culture of accountability and excellence in delivery to time, cost and benefit
expectations, and a role for NISTA in improving assurance and bedding in global best
practice – including via the mandated use of existing guidance including the
Construction Playbook.
11
ICE (2025) What should NISTA's priorities be?
As such, this inquiry has an important role to play in focusing discussion on how the UK
can move from recommendations on paper to proper implementation, to cut costs,
deliver improved benefits, and rebuild public trust.
The ICE thanks the Committee for the opportunity to contribute to this call for evidence
and would welcome the opportunity to present this submission to the Committee.