Risk Assessment - Height Work - SEC 5 Star Format
Risk Assessment - Height Work - SEC 5 Star Format
2.Analyse Risks – Determine consequences and likelihood of each risk. Write these items onto the table next to each risk.
Severity Likelihood
Level Descriptor Level Descriptor
1 Minor 1 Improbable
2 Appreciable 2 Remote
3 Serious 3 Occasional
4 Major 4 Probable
5 Catastrophic 5 Frequent
3. Evaluate Risks –Use the grid below to identify the level of risk.
How severely could it How likely is it to be that bad?
-- + + + ++
Hurt someone or how will could it make someone? Extremely Common or
1-7=Low Risk, 8-14= Medium Risk, 15-19= High Risk, 20-25= very high risk unlikely to repeating
occur occurrences
4. Identify and evaluate existing risk controls – Identify what happens already to manage the risks and consider how well these strategies are
working (good, adequate, variable). How does this effect the level of risk? Fill these items in on the table. If you are not happy with the level of risk
at this stage proceed to step 5.
5. Further risk treatments and opportunities for improvement – What actions are needed to bring risks to an acceptable level (these actions
are incorporated into other planning processes and include responsibilities, resources and timelines)? What opportunities are there for
improvement? Write these onto the table.
5. Further risk treatments and opportunities for improvement – What actions are needed to bring risks to an acceptable level (these actions
are incorporated into other planning processes and include responsibilities, resources and timelines)? What opportunities are there for
improvement? Write these onto the table.
Risk Assessment and Analysis
Company:
Deptartment/Area Page No: 1 of 1
RA Number: Rev: 00 Date
RA Team: Reviewed by: Approved by Manager/Supervisor:
Signature: Signature:
• Substandard materials
used
• Faulty erection
• Defective access •Allow only trained and qualified persons.
device • Permit to work should be provided.
• Over loading of •Restricted Supervision to be
Falling from edge of the
platform followed. •Edge protection must
building.
• Vertigo while working be provided. •Pre task Construction
Working at Multiple injuries, fatality, and
4 at height perifing to be conducted 5 5 25 Manager/Site Yes 5 1 5
Height death due to fall from
• Lack of platform •Area below working to barricated. Engineer
inadequacy of the platform
• Inadequate area on the •Stand by man out of barrication to not
provided or dizziness
platform allowed un uthrized to enter.
• Defective platform •Always harness when working on elevated
• Defective or unguarded platform or edge of the building / opening
ladder or stair
• Faulty mounting of
ladder
1 <Improbable> - Extremely unlikely to occur 1 <Minor> - Minor: No lost time / NOT significant Index Rating
4 <Probable> - Likely to occur more than once 4 <Major> - 1 fatality; 12 - 15 (H) High