0% found this document useful (0 votes)
3 views

Tubular Framing Computation

The document details the computation of tubular framing for wall cladding, providing measurements and total lengths for various elevations including right/left, front, and rear sides. The total length of materials required is calculated to be 1487.34 meters, with a total of 248 pieces. The document includes specific dimensions for vertical and horizontal tubulars, bridging, and additional structural components.

Uploaded by

Amer Gonzales
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views

Tubular Framing Computation

The document details the computation of tubular framing for wall cladding, providing measurements and total lengths for various elevations including right/left, front, and rear sides. The total length of materials required is calculated to be 1487.34 meters, with a total of 248 pieces. The document includes specific dimensions for vertical and horizontal tubulars, bridging, and additional structural components.

Uploaded by

Amer Gonzales
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

COMPUTATION OF TUBULAR FRAMING OF WALL CLADDING

Along Right/Left -side Elevation no. of


Total length
Height pcs
AT 3.20M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 3.20 m x 6 19.2 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
49.2 M
AT 2.67M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 2.67 m x 6 16.02 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
46.02 M

AT 2.72M LENGTH

Vertical tubular = 3.40 m x 8 27.2 m


Horizontal= 2.72 m x 6 16.32 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
46.32 M
AT 2.68M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 2.68 m x 6 16.08 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
46.08 M

AT 1.75M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 1.75 m x 6 10.5 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
40.5 M

TOTAL LENGTH = 228.12 M

MULTIPLYING BY TWO SIDE ELEVATION 456.24 M

Along Front -side Elevation no. of


Total length
Height pcs
AT 2.65M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 2.65 m x 6 15.9 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
45.9 M
AT 2.40M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 2.40 m x 6 14.4 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
44.4 M
AT 2.63M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 2.63 m x 6 15.78 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
45.78 M
AT 1.42M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 1.42 m x 6 8.52 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
38.52 M
AT 2.17M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 2.17 m x 6 13.02 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
43.02 M
AT 1.42M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 1.42 m x 6 8.52 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
38.52 M
AT 2.63M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 2.63 m x 6 15.78 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
45.78 M
AT 2.40M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 2.40 m x 6 14.4 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
44.4 M
AT 2.65M LENGTH
Vertical tubular = 3.40 m x 8 27.2 m
Horizontal= 2.65 m x 6 15.9 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
45.9 M

TOTAL LENGTH = 392.22 M

Along Rear -side Elevation no. of


Total length
Height pcs

AT 5.50M LENGTH
Vertical tubular = 3.40 m x 7 23.8 m
1.80 m x 8 14.4 m
0.56 m x 14 7.84 m
Horizontal= 5.50 m x 8 44 m
Bridging = 0.15 m x 12 1.8 m
0.10 m x 10 1 m
92.84 M

AT 0.90M LENGTH
Vertical tubular = 3.40 m x 4 13.6 m
Horizontal= 0.90 m x 14 12.6 m
26.2 M

AT 7.50M LENGTH
Vertical tubular = 3.40 m x 7 23.8 m
1.80 m x 12 21.6 m
0.56 m x 26 14.56 m
Horizontal= 7.50 m x 8 60 m
Bridging = 0.10 m x 22 2.2 m
122.16 M

AT 3.30M LENGTH
Vertical tubular = 3.40 m x 7 23.8 m
0.56 m x 14 7.84 m
Horizontal= 3.30 m x 7 23.1 m
54.74 M

TOTAL LENGTH= 295.94 M


MULTIPLYING BY TWO SIDES 591.88 M

Along Rear -side Sec. Flr Entrance no. of


Total length
Height pcs

AT 4.20M LENGTH
Vertical tubular = 2.60 m x 2 5.2 m
1.80 m x 12 21.6 m
Horizontal= 4.20 m x 2 8.4 m
1.20 m x 8 9.6 m
Bridging = 0.10 m x 22 2.2 m
47 M

AT LIBRARY PARTITION
Vertical tubular = 3.40 m x 15 51 m
Horizontal= 7.75 m x 7 54.25 m
Bridging = 0.10 m x 22 2.2 m
107.45 M
x2 214.9
6
220.9

GRAND TOTAL LENGTH= 1487.34 M


NO. OF PCS.= 248 PCS
big truss small truss
0.82 0.87
0.96 0.94
1.15 1.11
1.33 1.3
1.52 1.5
1.70 1.7
1.89 1.84
2.08 2.02
2.26 1.84
2.45 1.66
2.63 1.5
2.80 1.3
3.00 1.11
24.588 0.92
3.18 0.87
4.80 7.6
12.95
45.518 28.08