Project Planning Practise Questions
Project Planning Practise Questions
Q1 A well-known major professional institution has decided to replace its existing, in-house membership database
with a package-based system. It has drawn up a short-list of 4 off-the-shelf packages, but none meet its outline
requirements completely. An outline plan for the remaining tasks in this project has been drawn up as follows:
a) Draw an Activity on Node diagram for this project, showing all dependencies and the earliest start time, latest
finish time, duration and float for each task. Highlight the critical path and calculate its duration.
b) At the end of task A it is realized that task B can be reduced from 10 to 6 weeks, but task F should be extended
from 3 to 5 weeks. Re-calculate ALL the earliest and latest start times, and floats to reflect these two changes
and identify any changes to the critical path.
Duration
Identifier Activity
(weeks)
A order and deliver the new database system and server 4
H test all software and database on the new PCs and server 1
I train users 2
Tasks A, B and C can be undertaken at the same time, but A and B must be completed before D can start. Tasks C
and D must be completed before E can begin. E must be completed before F and G can start. F and G can be
undertaken at the same time, but both must be completed before H can start. I must follow H.
Draw a network diagram (Activity-on-Node) for this project, showing (on the diagram) the earliest and latest
start dates, the earliest and latest finish dates, duration and float for each task.
Provide a node key explaining the layout and contents of the nodes used in your diagram.
Draw a Gantt chart for the same project tasks, showing each of these tasks, all dependencies and each task’s
duration.
Highlight the critical path on each diagram.
What is the total duration of this critical path?
Q3 Your company is expanding rapidly and has decided to buy in and install an off-the-shelf (O-T-S) ledger package
to replace the existing manual system. This will need new equipment and network cabling throughout the
offices. You are to manage this project. You have drawn up an outline project plan to include the following main
tasks:
Task Weeks
C Specify and order all the required new hardware and communications equipment. 3
G Specify and obtain the accounts data required to implement the system 6
K Acceptance testing 4
a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should
contain at least two levels.
b) Explain the main differences between this WBS and a product breakdown structure (PBS) diagram for the same
project.
d) At the end of week 24, tasks A, B, C, D, H, I and J have been completed on schedule, and task E is continuing on
schedule. However it is realised that task F will now take 3 weeks, starting from week 28.
Re-draw the Gantt chart to reflect this progress to date, making any necessary changes, and highlight the critical
path.
Q4 A small research organization is extending its operation and database systems to cover the whole country. This
will require extended software, additional equipment and more staff – all to be based mainly in the existing
offices.
The outline plan for this rapid growth includes the following main tasks:
Confirm the hardware sizing for the extended requirements, the software changes, the
A 3
number of new staff and the additional equipment required for them
B Order, deliver and install all additional computing and communications equipment 10
Tasks B, C and D can all run simultaneously but all are dependent on task A.
Task E is dependent on tasks B and C.
Task F is dependent only on task C.
Task G is dependent on tasks E and F.
Task H cannot start until tasks D and G are completed.
a) Draw a full activity-on-node diagram for this project, showing clearly the earliest and latest start and end dates,
and the float, for each node. No start or end nodes are required. Highlight and name the critical path, together
with the minimum duration for the project.
b) The staff recruitment and training (task D) takes two weeks longer than planned to be completed. Identify and
explain briefly the resultant changes to the activity-on-node diagram and critical path.
c) Draw a Gantt chart for the revised project, incorporating the change to task D as specified in part (b). Show all
task durations, dependencies, float and the critical path.