Tutorial-10_Capital-Budgeting
Tutorial-10_Capital-Budgeting
Projects A and B have the same expected lives and initial cash outflows. However, one project's cash flows
are larger in the early years, while the other project has larger cash flows in the later years. The following
NPV profiles of two mutually exclusive project A and B are provided as below
1. At the discount rate of 10%, which project should be undertaken under NPV criterion?
2. At the discount rate of 13%, which project should be undertaken under NPV criterion?
3. At the discount rate of 10%, which project should be undertaken under IRR criterion?
4. At the discount rate of 13%, which project should be undertaken under IRR criterion?
5. From what discount rate, the NPV and IRR methods yield the same decision?
6. From what discount rate, the NPV and IRR methods provides conflict decisions?
7. As a financial manager, you expect that the discount rate of 10% should be used to evaluate the two
projects. Which project should you pick?
8. As a financial manager, you expect that the discount rate of 13% should be used to evaluate the two
projects. Which project should you pick?
10. At what discount rate, the NPV of the two projects are the same?
15. What criteria are used to measure project’s liquidity and what criteria are used to measure project’s
profitability?
Part 2 - Problems
1. Project K costs $52,125, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 12%.
A. What are the projects’ NPVs assuming the WACC is 5%? 10%? 15%?
E. Based on the examination of NPV profile and given that the WACC was 5% and A and B were mutually
exclusive, which project would you choose? What if the WACC was 10% or 15%?
3. A firm with a 14% WACC is evaluating two projects for this year’s capital budget. After-tax cash flows,
including depreciation, are as follows:
A. Calculate NPV, IRR, payback, and discounted payback for each project.
B. Assuming the projects are independent, which one(s) would you recommend?
Project M:
Year: 0 1 2 3 4 5
Project N:
Year: 0 1 2 3 4 5
a) NPV Calculation:
NPV is the sum of the present values of cash flows, considering the WACC.
Project M NPV:
Project N NPV:
NPV_M = -$9,646.86
NPV_N = -$18,439.73
b) IRR Calculation:
IRR is the discount rate that makes the NPV of the cash flows equal to zero.
Project M IRR:
IRR_M = IRR of cash flows (-$27,000, $9,000, $9,000, $9,000, $9,000, $9,000)
Project N IRR:
IRR_N = IRR of cash flows (-$81,000, $25,200, $25,200, $25,200, $25,200, $25,200)
IRR_M = 14.47%
IRR_N = 16.45%
c) MIRR Calculation:
MIRR is the modified internal rate of return, which assumes reinvestment at the cost of capital and
considers the terminal value of cash flows.
Project M MIRR:
MIRR_M = MIRR of cash flows (-$27,000, $9,000, $9,000, $9,000, $9,000, $9,000)
Project N MIRR:
MIRR_N = MIRR of cash flows (-$81,000, $25,200, $25,200, $25,200, $25,200, $25,200)
MIRR_M = 13.91%
MIRR_N = 15.92%
d) Payback Calculation:
Project M Payback:
Payback_M = 2 years
Project N Payback:
Payback_N = 4 years
Discounted Payback considers the time taken to recover the initial investment, considering
discounted cash flows.
Project M:
NPV: -$9,646.86
IRR: 14.47%
MIRR: 13.91%
Payback: 2 years
Discounted Payback: 3.18 years
Project N:
NPV: -$18,439.73
IRR: 16.45%
MIRR: 15.92%
Payback: 4 years
Discounted Payback: 5 years
4. Kim Inc. must install a new air conditioning unit in its main plant. Kim must install one or the other of the
units; otherwise, the highly profitable plant would have to shut down. Two units are available, HCC and LCC
(for high and low capital costs, respectively). HCC has a high capital cost but relatively low operating costs,
while LCC has a low capital cost but higher operating costs because it uses more electricity. The costs of the
units are shown here. Kim’s WACC is 7%.