GreenBridge Infrastructure Practice Interview Questions
GreenBridge Infrastructure Practice Interview Questions
Energy
Finance
Practice Interview
Questions
By Category, Including Sample Responses
Table of Contents
Table of Contents
Valuation....................................................................................................................................2
Project Finance .........................................................................................................................3
Tax Equity..................................................................................................................................5
Modeling ....................................................................................................................................6
Project Knowledge ....................................................................................................................7
Industry Questions ...................................................................................................................9
1
Valuation
Valuation
1. What are some investment metrics you would consider evaluating for a project?
a. Internal Rate of Return (“IRR”) – the time value return of free cash flows. If the
resulting IRR is higher than our discount rate, then the project is attractive.
b. Net Present Value (“NPV”) – the present value of cash flows, based on a
defined discount rate, less the initial investment. If positive, the project is
attractive.
c. Multiple on Invested Capital (“MOIC”) – the cash multiple we realize on our
investment.
d. Payback Period – the time to recoup an investment.
6. What discount rate and cash flows are used to calculate enterprise value?
a. WACC is used as the discount rate to calculate enterprise value by discounting
unlevered free cash flow (cash flow to the project).
7. What discount rate and cash flows are used to calculate equity value?
a. The cost of equity is used as the discount rate used to calculate equity value by
discounting levered free cash flow (cash flow to equity).
2
Project Finance
9. What is different about a DCF when valuing a solar asset compared to a typical
company?
a. When valuing solar assets, it is common to forecast cash flows over the entire
useful life (30+ years), whereas typical companies are usually valued based on a
5-year forecast plus a terminal value.
b. Solar projects require more detailed assumptions in the forecast because they
are typically highly contracted, with known variables such as construction costs,
offtake agreements, operating service agreements, and financing agreements.
c. Solar assets are financed using a unique capital structure that includes tax equity
and project finance debt, which differs from the financing structures of typical
companies.
10. What are some typical value drivers that you might choose to evaluate in a
sensitivity analysis?
a. Sensitivity analysis typically focuses on downside scenarios, as renewable
energy projects are lower risk with limited upside potential. Additionally, industry
trends suggest assets are more likely to underperform than exceed expectations,
making risk assessment crucial. Key sensitivity drivers include:
i. Development and Construction Costs – Variability in project costs.
ii. Development and Construction Timelines – Potential delays or
acceleration.
iii. Production – Variations in energy generation compared to the P50
scenario.
iv. Operating Costs – Fluctuations in ongoing expenses.
v. Merchant Revenue Prices – Changes in energy, capacity, and REC
price forecasts.
vi. Financing – Impacts of ITC rates, tax equity terms, SOFR fluctuations,
and debt terms.
Project Finance
3
Project Finance
2. What is the typical base rate used for a project finance loan?
a. The typical base rate used for a project finance loan is the Secured Overnight
Financing Rate (“SOFR”).
8. How much interest would be owed over the life of a 5-year, $50 million loan, with
an interest rate of 5% per year?
a. Per year – $50 million * 5% = $2.5 million
b. Total term – $2.5 million * 5 years = $12.5 million
4
Tax Equity
projects solely with equity. Raising project finance debt is also cheaper than
equity. This structure allows sponsors to deploy capital into multiple projects and
boost their returns through low cost debt.
Tax Equity
4. What do projects need to comply with to get the full ITC rate?
a. To qualify for the full 30% base ITC or PTC, projects must meet the Prevailing
Wage and Apprenticeship (“PWA”) requirements. This means paying workers
prevailing wages as determined by the Department of Labor and ensuring that a
minimum percentage of total labor hours are completed by registered
apprentices.
6. How would you approach determining the tradeoff between the ITC and PTC?
a. First, assess eligibility – PTC applies only to solar and wind projects. Then,
compare the project's upfront costs and expected energy output. The ITC is more
5
Modeling
beneficial for capital-intensive projects with lower capacity factors, while the PTC
favors lower-cost projects with higher energy production. A financial model can
help compare the present value of each incentive cash flow for a more detailed
analysis.
Modeling
6
Project Knowledge
from revenue to calculate operating cash flow (cash flow to the project). After
that, we consider any tax equity cash inflows and outflows, followed by capital
expenditures to determine unlevered free cash flow. Finally, we incorporate debt
funding and repayment cash flows to calculate levered free cash flow.
Project Knowledge
1. What are P50, P90, and P99?
a. These refer to different confidence levels in production forecasts. P50 represents
the median estimate, where there is a 50% chance production will exceed this
value. P90 means there is a 90% chance production will exceed this estimate,
while P99 indicates a 99% chance of exceeding the forecast.
7
Project Knowledge
8
Industry Questions
c. Operating cost overruns – Receive quotes you can close on as you underwrite
a project, include a contingency budget such as a corrective maintenance
budget.
Industry Questions
1. What are some major trends in the renewable energy industry right now?
a. Transmission Challenges – Windy and sunny areas are often located far from
major load centers, and building transmission lines is hindered by permitting,
land control issues, and high costs.
b. Interconnection Delays – Projects can face lengthy delays in clearing
interconnection queues, with approval processes taking years and timelines for
interconnection upgrades being extended by long lead times of equipment and a
growing backlog of projects from the utility.
c. Power Demand Growth – Increased demand driven by AI and data centers, the
reshoring of manufacturing, electric vehicles, and the electrification of homes and
industries.
d. Policy Changes – Potential revisions to the IRA are creating uncertainty around
tax credits. As a result, many investors are proceeding with caution or
accelerating projects to mitigate risk.
2. What are the top tailwinds and headwinds in the renewable energy industry?
a. Tailwinds – Strong load growth, faster renewable build timelines compared to
gas, declining costs, and cost parity with traditional energy sources.
9
Industry Questions
3. How would you compare a solar asset, wind asset, and battery storage asset in
terms of risk?
a. Solar Assets – Generally the lowest risk due to predictable energy production,
lower operational complexity, and proven technology. However, risks include
weather variability, system uptime, and potential curtailment.
b. Wind Assets – Higher risk than solar due to greater production variability, and
more complex maintenance. However, onshore wind projects have the longest
operating history of all three technologies.
c. Battery Storage Assets – Typically the highest risk due to its immaturity in the
market and typical revenue dependence on merchant markets or ancillary
services. Profitability tends to be sensitive to market volatility, dispatch strategies,
and policy changes.
4. Explain the difference between the "develop and flip" business model and the IPP
business model.
a. Develop and Flip – Focuses on early-stage development activities (e.g.,
interconnection, land acquisition, and securing PPAs and permits) and selling
projects to other developers or IPPs, typically at the point in time the project
becomes construction-ready. This model requires less capital and allows
developers to realize their investments sooner.
b. IPP – Involves developing, constructing, and owning projects long-term, and
often acquiring projects from developers. While it requires significantly more
capital, the IPP captures the full value of a completed project, including tax
credits, cash flows, and the ability to leverage financing.
10