Project Schedule

The project schedule outlines a total duration of 90 days for various construction phases including site preparation, excavation, concrete work, and final touches. Key strategies include overlapping tasks where possible and prioritizing critical path activities to ensure timely progress. A buffer period is included to accommodate any unforeseen delays.

Uploaded by

waltermink19
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

Project Schedule

The project schedule outlines a total duration of 90 days for various construction phases including site preparation, excavation, concrete work, and final touches. Key strategies include overlapping tasks where possible and prioritizing critical path activities to ensure timely progress. A buffer period is included to accommodate any unforeseen delays.

Uploaded by

waltermink19
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

• PROJECT SCHEDULE

Start End
Phase Task Duration Notes
Day Day

Leveling and setting out 2 days Day 1 Day 2 Initial site preparation across all entrance gates

Provision of tools and equipment 1 day Day 3 Day 3 Equipment setup for all tasks

Temporary works support and scaffolding 2 days Day 3 Day 4 For safe access during construction
1. Preliminaries
Office accommodation setup for
2 days Day 5 Day 6 Provide facilities for consultant representatives
consultants

Water provision and rubbish removal 1 day Day 7 Day 7 Ensure clean work environment

Soil testing and signboard installation 2 days Day 7 Day 8 For quality control and visibility

Excavate and backfill foundation trenches 5 days Day 9 Day 13 For all gates and security house
2. Excavation and
Earthworks
Surface treatment and termite proofing 2 days Day 14 Day 15 Apply to all excavated areas

Lay hardcore, compact, and apply damp


3. Groundworks 3 days Day 16 Day 18 Prepare foundation layers
proof
Begin with center gate, then move to left and
Pour concrete for foundation slabs 4 days Day 19 Day 22
4. Foundation right gates
Concrete Work
Reinforcement and formwork setup 3 days Day 23 Day 25 For columns and starter columns

For all gates, following reinforcement


Pour concrete for columns and beams 7 days Day 26 Day 32
5. Structural completion
Concrete Work
Roof slab pouring and curing 5 days Day 33 Day 37 Ensures solid roof structures

6. Blockwork and
Lay block walls for entrance gates 8 days Day 38 Day 45 For all gates; 225mm load-bearing blocks
Masonry
7. Openings Install windows and doors 5 days Day 46 Day 50 Includes frames and fittings for all gates

Render and paint walls 6 days Day 51 Day 56 Apply coats to internal and external walls
8. Surface Finishing
Tile floors and install skirting 5 days Day 57 Day 61 Ceramic tiles and screeding backing

Mechanical (plumbing, toilets) 5 days Day 62 Day 66 Includes water closets and wash basins
9. Service
Installations
Electrical (lighting, ceiling fans, CCTV) 5 days Day 67 Day 71 Install electrical systems across all gates

Construct septic tanks, soakaways, and


10. External Works Septic tank and soakaway construction 7 days Day 72 Day 78
inspection chambers

11. Final Touches Install balustrades, handrails, and signage 3 days Day 79 Day 81 For accessibility and safety

Clean-up and site inspection 3 days Day 82 Day 84 Final cleaning and preparation for handover

Conduct final inspection and address snags 3 days Day 85 Day 87 Allow time for any minor adjustments
12. Project Handover
Official handover to client 1 day Day 88 Day 88 Completion of all project requirements

Provides extra time to accommodate


Buffer/Contingency Buffer period for any delays 2 days Day 89 Day 90
unforeseen challenges

Summary:

• Total Duration: 90 days, including contingency.


• Overlap Strategy: Where feasible, tasks such as setting up preliminaries, earthworks, and blockwork are completed across all gate
locations simultaneously.
• Critical Path: Tasks like excavation, structural concrete work, and service installations are prioritized for timely project progress.