Unit-4
Unit-4
- --
Structure
4.1 Introduction
Objectives
4.2 Site Investigations
4.2.1 Tnal Pit and Boring
4.2.2 F~eldTests
4.3 Bearing Capacity of Soil
4.4 Settlement of Foundations
4.5 Depth of Foundation
4.6 Excavation for Foundation
4.7 Selection and Types of Foundation
4.8 Shallow Fondations
4.8.1 Pad a Spread and Strip Footing
4.8.2 Grillage Foundation
4.8.3 Raft Foundation
4.9 Deep Foundations
4.9 1 Timher Piles
4.9.2 Steel Piles
4.9.3 Concrete Piles
4.9.4 Under-reamed Piles
4.10 Summary
4.11 Answers to SAQs
4.1 INTRODUCTION
Foundations form an imporpmt part of building construction. The forces and moments
acting on a structure have to be ultimately transmitted to the ground and this is achieved by
means of foundations. The loads on a building are transmitted downwards, floor by floor by
means of columns and/or walls. If these are directly set on the ground, the pressures under
them would be so much that either the soil will give way or large and uneven settlements
would take place. In order to prevent this, the load is spread over a wider area by means of
foundations such as footings, strips, rafts etc. At the same time, we have to ensure that the
stresses in the elements of foundation like concrete, steel masonry etc. are within the
specified limits.
The crust of the earth over which the foundation rests, consists of various types of soils
rocks having widely different characteristics and properties. Further, the presence of suboil
water affects some of these properties. Before foundations are designed, we should know
the details of the soil characteristics.
Generally, one is confronted with a situation where the desired land has been acquired and
the foundation for the proposed building has to be designed taking into consideration tbe
soil characteristics at the site. For important and heavily loaded structures, it may be
worthwhile to take into consideration the necessary soil properties and other features at the
site, before acquiring the land.
In earlier days, the design of foun&tions was based mote on experience and intuition, &
modem developments in Soil Mechanics have enabled us to understand in greater detail, (BC
properties of soil and the mechanism of load transfer from the building to the ground.
In this unit, you will learn about the various types of building foundations, wbere they m
used and their constructional details.
Objectives
After studying this unit, you should be able to
* classify the various types of building foundations,
describe the tests used for site investigation,
Building Comtructioo . establish the criteria for selecting the type of foundations, and
describe the constructional details of the commonly used foundations.
S
Distinguish between ultimate, safe and allowable bearing capacihes.
SETTLEMENT OF FOUHDATl#NS
By settlement we ean the vertical downward rnovewnts of the foulation. The effect of
f"
settlement on the tructure depends on its magnitude, bdh abolute u well as relative with
uuy be caused by :
respect to the different parts of tbc foundation. Settk~~lent
(i) the weight of the structure and the superimposed loads, Foundations
SAQ 3
Wh 1; ;ire the csuses for settlement offoundalinns 'i
These surface s
should nct intersect
Minimum
60cm for rock
9 0 c m f o r soil
L ~ l o d~ joining
e ~ower
line not steeper footing
than one vertical
to tvo horizonld
In clayey soils, a line drawn between the lower adjacent edge of the upper footing
and the upper adjacent edge of the lower footing shall not have a slope steeper than
one vertical to two horizontal as shown in Figure 4.3.
Site Clearance
Before the excavation for the preposed foundation is commenced, the site shall be
cleared of vegetation, brushwood, stumps of trees etc. Roots of the trees shall be
re~liovedto at least 30 cm below the foundation level. The pits formed due to roots
of trees, old foundations etc. shall be filled up with soil and compacted.
Setting out
A bench mark shall be established at the site by a masonry pillar and connected to
the nearest standard bench mark. Levels of the site should be taken at 5 to 10 m
intervals depending on the terrain and the importance of the building. The centre
lines of the walls are marked by stretching strings across wooden pegs driven at
the ends. The centre lines of the perpendicular walls are marked by setting out the
right ,mgle with steel tapes or preferably with a theodolite. The setting out of walls
shall be facilitated by having a permanent row of pillars (not less than 25 cm side)
parallel Lo aid at a suitable distance beyond the periphery of the build'mg so that
they do 11ot foul with the excavation. The pillars shall be located at the junctions of
the cross walls and external wall and shall be bedded suficiently deep so that they
are not disturbed during excavation for foundaiion. The centre lines of the walls
shall be extended and marked on the plastered tops of lhe pillars. The tops of the
pillars may be kept at the same level, preferably the plinth level. In rectangular or
square settings, the diagonals shall be checked to ensure accuracy of setting out.
Excavation
For small buildings, excavation is carried out manually by means of pick axes,
crow bars. spades etc. In case of large buildings and deep excavation, mechanical
earth cutting equipment can be used.
For hard soils when the depth of excavation is less than 1.5 m, the sides of the
trench do not need any external support. If tl?e soil is loose or the excavation is
deeper, some sort of shoring is required to support the sides from falling. Plankiilg
alid strutting can be intermittent or continuous depending on the nature of soil and
the depth of excavation. In the case of intermittent or "open" planking and strutting
the entire sldes of trenches are not covered. Vertical boards (known as poling
boards) of size 250 x 40 mnl of the required length can be placed wlth gaps of
about 50 cm (Figure 4.4). These shall be kept apart by horizontal waling of strong
t~mberof sectlon 100 x 100 nun at a minimum spacing of 1.2 m and strutted by a
cross piece of 100 x 100 square or 100 nun diameter. In the case of soft soils
b continuous or "close" planking is adoped and the vertical boards are kept touching
each other without any gap as shown in Figure 4.5 (a).
Buildlug Construction
'US
Figure 445 (a) :Close Planking Fig" 4 5 (b):Plmking InVery Soft and Loose Soil
original
Pumps gmund Header
\ Header surface /
Foundation Concrete
In the case of a masonry wall, the footing is generally of cement concrete mix of
ratio 1:4:8 or 1:5:10 (cement : sand : coarse aggregate). The s i 7 ~
of coarse
aggregate is limited to 40 mni. Lime concrete can also be used for this purpose.
For important works. mixing of concrete should be done in a mechanical mixer. Foundations
Concrete should be laid (not thrown) in layers not exceeding 15 cm and well
compacted. The concrete should lie protected by moist gunny bags after about 1 or
2 hours of laying. Regular curing should be started after 24 hours and be continued
for 10 days. The masonry work over the bed concrete can be started after 3 days'of
laying the concrete but curing alongwith that of masonry shall be continued.
For RCC colunm footings and raft foundations, a levelling course of lean concrete
of 75 rnm is laid in order to have an even and soil free surface for placing the
reinforcement.
SAQ 5
WnaL are the methods to lower'sub-soil water level for the purpuse ot zxcavatiori
of fouildations '?
Plain concrete
thon 1 ver tic01 -
min.thic kntss 1
If the load on the wall is heavy or the soil is of low bearing capacity, reinforced
concrete strip footing can be provided (Figure 4.8). The thickness of the strip can
be reduced towards the edge to effect economy.
Column
re inf orcem~nt
RCC footing
~ e of
d tian
concrete
Figure 4.9 : RCC Column Footing
As the bending moment decreases towards the edge, the thickness can also be
reduced accordingly. The minimum thickness at the edge shall, however, be not
less than 15 cm. Stepped footings should be avoided as sudden changes in stress
conditions are likely to be produced. The top of the footings can be sloped towards
the edge in the shape of a pyramid. Steep slopes exceeding 1 in 2 would require
formwork and hence, normally the slope is of the order of 1 in 4. In a foundation, it
is important to ensure that a minimum cover of 40 to 50 mm is provided to prevent
corrosion of reinforcement.
When two column footings are near to each other or the foundations overlap, a
combined footing can be provided. Such footings can be rectangular or trapezoidal
in plan and its position is so adjusted that its centre of gravity coincides with that
of the loads from the columns.
Foundations
SECTION SECTION
PLAN PLAN
separators
Pipe
T?r Steel column
Base late and
- - ..- . - .-
ELEVATION
The depth of roundation for a raft shall generally be not less thm 1 m. A bed of lean
concrete of 75 to 100 cm thickness is provided to facilitate laying of reinforcement and
concreting. It is econonlical to project the raft slab by about 30 to 45 cm beyond the face of
the peripheral columns.
Where possible, the raft is so prc~portionedthat its centre of gravity coincides with that of
the column loads. If this is not possible, the eccentricity has to be taken into account in the
structural design as well as in checking for the pressure on the soil.
--- ----
SOFT SOIL
SOF T - -- -- - -STRENGTH
WEAKL0I-L - - - INCREASE WITH
---
-
(a) End Bearing Pile (b) Friction Pile
Figure 4.14 :Different Types &Piles (Based on Mode of Load n m f e r )
Piles driven in soil which increasingly becomes stiff with depth derive their
bearing capacity from the friction along the surface of the pile and are known as
.friction piles as shown in Figure 4.14 (b). Normally, in a pile, part of the load is
carried by friction and part by end bearing. Piles can also be used to resist uplift
pressures on structures as also to withstand lateral forces. Such piles are called
I
anchor piles. A pile which is installed at an angle to the vertical is known as a
batter or raker pile.
1
Piles, particularly of timber have been use from ancient times and can be
'jb
considered as one of the earliest innova ons in foundation engineering. However,
it is only in the past few decades that appropriate methods have been evolved to
analyse and design piles.
I
Construction of pile foundation requires a careful choice of the type of pile and
methodology of execution taking into consideration the soil strata, the level of
subsoil water, the load characteristics of the structure, limitation of settlements and
any other special requirements. The availability of materials and equipment and
econoinic factors have also to be considered.
Building Constructio~~ Materials for Piles
Piles can be of timber, steel or concrete. The earliest types of piles used were of
tlmber while presently concrete piles are used to the maximum extent. Steel piles
are expensive and rarely used.
4.9.1 Timber Piles
These can be used for relaiively lightly loaded structures located in compressive types of
soils with high ground water level. has a high weight to strength ratio and can be
cut, shaped and handled easily. If timber piles are wholly in a submerged condition they
have a long life. If the subsoil water level is high, the piles can be cut off, at the top. below
this level and a concrete pile cap be provided as shown in Figure 4.15 (a).
MS Hoop
13mber used for the piles has to be of good quality like teak, sal, deodar etc. It should be
straight grained and free from defects. The piles shall be treated with timber preservative.
Shoe Tmber piles can be of square or round section. Round section is preferable as cutting to
square shape removes part of the outer sapwood which is absorptive to preservatives.
Figuw 4.15 (b) P~lesare driven into the soil by the drop hammer of a pile driving machine. For facilitating
Timber ,dtl, ;\.IS driving, the lower end is provided with a cast iron conical shoe and the head is prevented
HOOP and c1Shoe froln splitting by mems of a mild steel hoop [Figure 4.15 (b)].
Timber piles are relatively cheaper and easy to drive but get deteriorated and decayed
particularly when subject to alternative drying and wetting. They cannot be used for heavily
loaded structures.
Length 1 Length 1
If it has been decided to adopt precast piles for the foundation, the length of piles
has to be assessed fairly correctly, as cutting the piles or extending them cannot be
done easily. They also require large casting yards and heavy equipment for
handling and driving. However, in situations where soil is such that driving is easy
or large number of piles of predetermined length are to be provided or where
reinforcement is required from considerations of lateral pressure or tensile steel is
required to resist uplift, precast piles are advantageous. The quality of concrete in
precast piles is better as they are cast above ground under controlled conditions
and hence, such piles are sometimes preferred in aggressive soil (e.g. sulphates)
conditions.
Precast concrete piles for small loads and short lengths can be square in
cross-section with chamfered comers, while for longer length and heavier loads
they are generally of octagonal or circular section. Sometimes hollow sections are
also used which are filled with concrete after driving. The tips are pointed to
facilitate driving. As the reinforcement in the pile is mainly to resist the handling
stresses, this objective can also be achieved by prestressing. It can be either
pretensioned or post tensioned. Prestressed concrete piles are not widely used as,
.L - - - -..-
!.-.
BoildingConstrudion Pile Driving 1
Piles are commonly driven by means of a pile driver, basic elements of which are a I
frame and a hammer. The frame or trestle is generally of steel and has a pair of
vertical guides, known as leaders within which the hammer is held. Mobile units 1
are also available and are convenient when a large number of piles are to be driven. 1
The hammer could be a simple drop hammer or more efficient steam, air, diesel or
hydraulic hammers. If the fall of hammer is due to gravity alone, it is known as
single acting. If pressure is applied by steam etc., it is known as double acting.
Drop hammers weigh from 1000 to 5000 kg and fall through a distance of about 1
metre. As a rough rule, the weight of a drop or single acting hammer could be the
same as the weight of the pile. For heavy piles, this would not be possible but for
proper dtiving the hammer should weigh not less than a third of the weight of the
pile. A cast steel helmet is placed over the top of the concrete pile with a resilient
dolly on top to prevent the pile head from shattering under the impact of the
hammer blow.
The resistance to pile driving is expressed in terms of number of blows per inch of
penetration. Resistance of 6 to 8 blows per inch are specified for concrete piles.
If piles have to be driven through dense layers, jetting around the pile is resorted to
in order to loosen the soil and ease penetration. If piling is planned to be done by.
jetting, it is preferable to insert an M.S. pipe of 50 to 75 mm in diameter at the
centre of the pile while casting.
In saturated plastic clays, displacement of soil on account of driving of pile may
cause heaving of adjacent area, and in such cases piles can be placed in holes made
by augering.
Cast in-situ Concrete Piles
-
There are two types of concrete cast in-situ piles driven or bored.
Driven Cast in-situ Piles
In this type of piles, a heavy sectioned metal tube, with a detachable metal shoe
at the bottom, is driven into the ground by a drop hammer or any other type of
hammer upto the required depth. Thereafter reinforcement is placed, if required,
and ccncrete is filled into the tube and the tube simultaneously withdrawn
leaving the shoe at the bottom. In another version, a thin steel shell is driven
with the help of a mandrel, which is then withdrawn, remforcement placed, if
required, and concreting done, the shell being left permanently in the ground.
Raymond concrete pile company have developed a thin steel shell pile, known
as Raymond Pile. The casing pipes consist of either uniformly tapered or step
tapered light corrugated steel tubes. An internal mandrel is used to drive the
casing, the mandrel is then withdrawn and the shell filled with concrete.
In Franki piles, a concrete plug is formed at the bottom of the steel casing and
by repeated hammering the pipe is thrust downwards into the ground. When the
bearing stratum is reached, additional concrete is poured and the plug
hammered out of the tube to form a bulb end. Then the reinforcement cage is
lowered into fie tube, concreted and the casing withdrawn.
Vibro pile uses a detachable steel or cast iron shoe with a steel tubecasing.
With the help of a hammer, the tube with the shoe on is driven to the required
depth, reinforcement cage lowered. concreting done and the tube withdrawn
leaving the shoe at the bottom of the pile. Simplex piles are also similar to this
sort of arrangement.
Bored Cart in-situ Piles
In this system, a hole is bored into the ground, reinforcement (if required)
lowered and concreting done. Boring is generally carried out by rotary or
percussion type drilling rigs. Kelly mounted hydraulically operated grabs are
also used.
If the soil is such that the walls of the bore would cave in. casing tubes have to
be used which is subsequently extracted while concreting. Sometimes the
casing is left in the ground and the concreting done within the casing. Such
piles are known as cased piles. Another method to keep the sides of the hole in
position is by pumping bentonite slurry into the borehole as the soil is removed.
Bentonite is a clay of the monunorillonite group. Its slurry forms a membrane
along the walls of the bore hole and also a m hydrostatically to retain the
stability of the sides of the hole. After the required depth of the bore is reached
a high slump concrete is placed by means of a tremie.
For piles of small diameter and depths upto 10 m, the minimum cement content
of the concrete should be 350 kg/m3 while for larger diameter and deeper piles
it should be 400 kg/m3. Slump of concrete shall range between 100 to 180 m m
depending on the manner of concreting.
Where drilling mud is used before concreting, the bottom of the hole shall be
flushed with fresh bentonite slurry. Throughout the boring operation it has to be
ensured that the drilling mud suspension is of the required consistency.
4.9.4 Underreamed Piles
These are bored cast in situ concrete piles having one or more bulbs formed towards the
bottom by enlarging the bore hole of the pile stem. The enlargements help in providing
substantial bearing or aichaage. Such piles have been found to be useful in expansive soils
like black cotton soil as tQe bulbs provide anchorage against uplift due to swelling pressures.
The diameter of the underreamed bulbs may be of the order of 2 to 3 hmes the stem
diameter. The spacing of the bulbs is 1.25 to 1.5 times the stem diameter. The top most bulb
should be at a minimum depth of 2 times the bulb diameter.
Borings for the piles are carried out in the usual way. Thereafter the bulbs are formed by
means of an underreamer rotated by the drill rod. The excavated soil is removed by means
of buckets. The reinforcement cage is then lowered and the pile concreted. ?he cement
content and slumps shall be as indicated for bored cast in situ piles.
Bored compaction pile is a modified form of underreamed pile where, after the concrete is
poured, the reinforcement assembly, with a cone welded at the bottom is driven through the
fresh concretc with the help of a driving pipe, thereby compacting the concrete.
*t 4+-
Cover 7 5 to 100
But ket
Ieng t h
4.10 SUMMARY
The first step in deciding on the type of foundation is to carry out a detailed soil
investigation to ascertain the characteristics of the subsoil. Field tests of soil can also be
carried out for quicker results. On the basis of these tests and investigations, the depth of
foundation can be arrived at and the safe bearing capacity of the soil can be estimated.
Taking into consideration the properties of soil substrata and the load due to the proposed
building, it should be possible to decide on the type of foundation that would be suitable.
The details of shallow foundations such as pad, strip, grillage and raft have been described
in the unit. If the soil in the top layer, near the ground, does not have adequate bearing
capacity to support the superimposed load, it would be necessary to adopt pile foundations.
The details of various types of pile foundation have also been explained in this unit.