QA-01 - Control of Documented Information
QA-01 - Control of Documented Information
Change History
Rev. Clause Change(s) Made
Contents
8.0 ATTACHMENTS:.................................................................................................... 11
ORASCOM CONSTRUCTION LIMITED
1.0 Scope:
This procedure covers the Integrated Management System requirements applied by Orascom
Construction Limited; It covers documents and records and embraces the requirements of ISO
9001:2015, ISO 14001: 2015 and OHSAS 18001:2007.
2.0 Purpose:
The purpose of this document is to ensure the existence of the Document & Records Control
Management System to meet the QHSE objectives of OCL.
3.0 References:
3.1 ISO 9001:2015 : Quality Management Systems- Requirements.
3.2 ISO 14001: 2015 : Environmental Management System-Requirements.
3.3 OHSAS 18001:2007 : Occupational Health and Safety Management Systems -
Requirements
4.0 Abbreviations:
OCL : Orascom Construction Limited.
QHSE : Quality, Health, Safety and Environment.
HSE : Health, Safety & Environment.
IMM : Integrated Management Manual.
CQD : Corporate Quality Director.
CHSED : Corporate Health, Safety, & Environment Director
QCM : Quality Control Manager.
HSEM : Health, Safety, & Environment Manager.
PCM : Project Controls Manager.
ITP/PIP : Inspection and Test Plan/ Project Inspection Plan.
MS : Method Statement.
DC : Document Controller.
DCM : Document Control Manager
DMS : Document Management System
Valid Documents : Approved documents, issued for construction / implementation.
5.0 Responsibilities:
5.1 Corporate Quality Director – (CQD)
Corporate Health, Safety, & Environment Director – (CHSED):
The CQD & CHSED responsibility with regard to the Integrated Management System includes,
but is not limited to:
• Establishing the Integrated Policy and Objectives.
• Ensuring that appropriate processes are implemented to enable customer(s) / client(s)
requirements and internal objectives to be met.
• Assigning responsibilities and authorities to meet these objectives
• Ensuring that an effective management system is established, implemented and maintained
to achieve these objectives.
• Ensuring the availability of necessary resources.
• Comparing the achieved results against the set objectives.
• Deciding any action regarding the integrated QHSE policy and objectives.
• Deciding any action for improvement.
ORASCOM CONSTRUCTION LIMITED
• Apply a system to easy incorporate the data and information updates from all departments on
daily basis into the Project Central Document Library (soft and hard copies).
• Liaise with the project team for preparation of all technical submissions and ensure all
documents are submitted in accordance with the project schedule using standard templates
and in accordance with the Project Technical Document Numbering Procedure, appropriate
approval and rejection are obtained and formally recorded and that changes and revisions
are managed as part of documents control procedure.
• Review all sent and received documents in accordance with the Project Technical Document
Specifications/Procedure.
• Use the Documents Management Digital System to upload data into the standard registers to
ensure that the information is accurate and up to date.
• Monitor and update any change and modification to the technical documents. Highlight any
deviation to Engineering Manager for attention.
• Prepare required reports to support the project team by presenting the documents status and
raise the critical issues that may affect the progress of the project, through the Documents
Management Digital System or creating / customizing using Microsoft Office Package.
• Responsible for tracking and distributing the controlled copies of latest approved documents
and drawings to the appropriate staff, subcontractors and suppliers as applicable based on
approved matrix of distribution by Project Manager; and to ensure that the documents last
revision supersedes the old revisions.
• Maintain hardcopies and softcopies of documents and drawings in the project central
documents library under safe custody without any damage or deterioration with easy
traceability, make regularly backups of all the data and keep them in a secure place.
6.0 Procedure:
6.1 General Requirements of the QHSE Integrated Management System:
To meet the requirements of ISO 9001:2015, ISO 14001:2015 and OHSAS 18001:2007. OCL
has developed an Integrated Management System which includes all requirements that provide
customer confidence based on the following:
• Objectives and Policy.
• Performance implementing processes, methods and tools.
• The requirements and expectations of all interested parties, including details of statutory and
regulatory requirements.
• Resources for the development of the Integrated Management System.
The Documents & Records Control Management System comprises of the below hierarchy:
Level 1:
The Integrated Management Manual which defines the QHSE objectives and policy. It
contains a description of the elements of the Management System and their interaction. It
also refers to the system procedures that support the system at different levels.
Level 2 :
The QHSE System Procedures specifying the interaction between the ISO, OHSAS
requirements and the Management System in addition to the responsibilities for
implementation.
Level 3:
Consists of process control documents, such as the QHSE Control Procedures, Method
Statements, Project Procedures, Project Quality Plan (PQP) and Inspection & Test Plans
(ITPs)
6.2 Documentation Requirements:
6.2.1 General
The OCL Integrated Management System documentation include all QHSE documented
procedures
6.2.2 Project Quality Plan (PQP)
The Project Quality Plan(s), when generated refers to the Quality Management System
Procedures at the same time it describes the interaction between the Management
System Requirements.
6.2.3 Health, Safety, and Environmental Plan
The Health, Safety, and Environmental plan refers to the HSE Management system
procedures.
6.3 Control of Documents:
There are two types of documents:
• OCL Corporate Documents: which are the Management System Documents and
departmental procedures.
• Projects / Sites Documents: which are the process or the Construction Documents (i.e.:
Inspection and Test Plans, Method Statements, Drawings, Specifications….etc)
6.3.1 OCL Integrated Management System Procedures and Corporate QHSE documents are
controlled uniformly in accordance with this procedure.
The Document Controller in the Corporate Quality Department who is responsible for
the distribution of documents and records shall ensure that whenever a document is
ORASCOM CONSTRUCTION LIMITED
new or re-issued, it is sent to the assigned recipients. This is to avoid the use of any
obsolete documents/records.
6.3.2 In the projects it is the responsibility of DC to ensure that all OCL project personnel are
informed with the relevant documents in accordance with the “Project Distribution
Matrix” (FM-QA-01-01) which shall be approved by the project manager.
6.3.3 OCL project personnel are responsible to ensure that they are using the latest revision
of the documents for the execution of the work.
6.3.4 All OCL project Departments Heads are also responsible to ensure that their
subordinates’ use the latest valid revisions, that replaces the superseded documents.
6.3.5 For external correspondence, OCL shall use the related project forms, as per the
contract requirements.
6.3.6 Upon receipt of the controlled copy of documents from DC, the recipient shall:
a) Ensure that all the received controlled documentations are complete and correct as
listed in the transmittal and refer any variation back to the DC.
b) Sign and return the transmittal form to the DC.
c) Check for a previous copy of the documents; if the new documents use a later
revision, then the previous copy must be replaced.
6.3.7 The document Controller, in coordination with the responsible Department / Section
Heads, shall ensure that all recipients of documents return a signed copy of the
transmittal, as an evidence of their receipt. Internal Documents Transmittal form (FM-
QA-01-02) shall be used for that purpose.
6.3.8 Master documents are stamped “SITE MASTER” or “Original” and shall be retained in
DC offices, copies of the Master document will be strictly controlled by DC. When the
master is superseded, it shall be clearly marked “SUPERSEDED” on the cover sheet
and archived.
6.3.9 Master copies of drawings (Client / JV Partner, Vendor, Sub-Contractor, etc……) are
maintained in drawer cabinets on sticker files as decided by the document controller.
6.3.10 Cupboards, drawer files, stick files or box files, etc., shall be clearly identified to show
their contents.
6.3.11 All such files within DC are kept in a specific area limited to the only authorized
personnel.
6.3.12 QHSE records/documents shall be kept and filed by the Project Quality/ HSE
Departments until they are handed over to the client. Project Quality/ HSE departments
shall ensure that all QHSE records/documents are issued through DC who will retain
copies as necessary.
6.3.13 Codes and standards required at each project will be obtained by each project on as
need basis. Projects can coordinate with the Quality/ HSE departments to obtain legible
copies of any standard if required.
6.3.14 Control of confidential documents (e.g. laws or regulations) is carried out according to
the confidentiality agreements with the Owners or the Clients. These documents are
kept in the custody of the contracts manager or his designee in a locked cabinet and
issued only upon official request from the section manager and should be returned after
use. No copying of such documents is allowed unless a written permission is submitted
by the document owner.
6.3.15 Post Contract Storage
• Contract documents shall be archived and clearly marked with the contract number
and contents upon completion of the contract. Any confidential documents shall follow
section 6.3.14.
• All documentations (drawing, manuals, data books,…etc), shall be transferred to a
location specified by OCL.
ORASCOM CONSTRUCTION LIMITED
• Each box file shall be individually numbered consecutively and logged by the
Document Controller.
• Identification labels, including the contents of each box, file shall be placed on each
box / file.
6.4 Document Receipt and Register:
6.4.1 OCL applies the Documents Management System which is a computerized system for
the registration of all project documentation that shall be implemented, and controlled
by the Document Controller. The “Document Control System” developed by OCL
Information & Technology Department (IT) can be used for all registers and logs for all
documents (Also any other approved software can be used).
6.4.2 The Document Controller shall assign authority for access to the Document Control
data maintained in the computer system. This shall be achieved by limited password
restricted ‘Write’ access controlled by the Document Controller.
6.4.3 The Documents Management System is controlled by the project control department
and supported by the OCL IT Application team (refer to flow chart attachment 8.1)
6.5 Document Register:
6.5.1 On receipt, pertinent documents shall be registered by DC in the database and update
the documents registers.
6.5.2 DC is responsible issuing periodical documents register / reports or as deemed
necessary to the department / section heads to identify the current revision and status
of each document to be used.
6.5.3 It is the responsibility of the Document Controller to ensure that these registers are
correct. However, each Department / Section Head shall review these registers and
ensure to the maximum extent practical, that he has correct information, and he cannot
delegate this responsibility to the document controller.
6.5.4 Any discrepancy discovered must be reported to the Document Controller.
8.0 Attachments:
8.1 Chart of Responsibility of Documents Control Management System
8.2 Chart of Project Documents Life Cycle
8.3 Project Distribution Matrix FM-QA-01-01
8.4 Internal Documents Transmittal FM-QA-01-02
8.5 Procedure Template FM-QA-01-03
8.6 Risk Register FM-QA-00-01
Note: Attached forms are considered separate files from this procedure