Smart Tower with cpm

The document outlines a proposed tentative work program for the construction of the Vision 2041 Smart Tower, detailing tasks, durations, and timelines from July 2023 to February 2026. Key milestones include contract signing, site handover, and various construction phases for the building's structure. The program includes specific tasks related to foundation work, basement construction, and the erection of floors up to the seventh level.

Uploaded by

bbbbb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views4 pages

Smart Tower with cpm

The document outlines a proposed tentative work program for the construction of the Vision 2041 Smart Tower, detailing tasks, durations, and timelines from July 2023 to February 2026. Key milestones include contract signing, site handover, and various construction phases for the building's structure. The program includes specific tasks related to foundation work, basement construction, and the erection of floors up to the seventh level.

Uploaded by

bbbbb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Proposed Tentative Work Program for Construction of Vision 2041 Smart Tower (Vision 2021 Tower-2, STP-2)

ID Task Task Name Duration Start Finish Predecessors 2024 2025 2026
Mode Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
1 Summary 892 days Mon 24-07-23Wed 31-12-25
2 Contract Signing & Project Start 0 days Mon 24-07-23Mon 24-07-23 24-07
3 Site Hand Over 0 days Thu 03-08-23Thu 03-08-23 03-08
4 Inauguration Ceremony 0 days Wed 09-08-23Wed 09-08-23 09-08
5 PRELIMINARY WORKS 62 days Thu 03-08-23Tue 03-10-23
6 Mobilization Works 38 days Thu 03-08-23Sat 09-09-23
7 Site Cleaning Works 16 days Thu 03-08-23Fri 18-08-23
8 Site Layout Works 7 days Sun 20-08-23 Sat 26-08-23 7
9 Employer's site offices 30 days Sun 20-08-23 Mon 18-09-238SS
10 Offices and Facilities for the Contractor
30 days Sun 20-08-23 Mon 18-09-238SS
11 CCTV / Surveillance Facilities 15 days Tue 19-09-23 Tue 03-10-23 10
12 Foundation Work (Shore Pile,Earth 166 days Fri 01-09-23 Tue
Cutting & Mat Casting) 13-02-24
13 Shore Pile Layout & Mud Removal Pit10 days Fri 01-09-23 Sun 10-09-23
14 Shore Pile Boring & Casting Works 60 days Fri 01-09-23 Mon 30-10-2313SS
15 Earth Excavation & Lateral Bracing Works
40 days Tue 31-10-23 Sat 09-12-23 14
16 Leveling Dressing for Mat Casting 5 days Sun 10-12-23 Thu 14-12-2315
17 Brick Flat Soling for Mat Casting 3 days Fri 15-12-23 Sun 17-12-23 16
18 CC Works For Mat Casting 3 days Mon 18-12-23Wed 20-12-2317
19 Water Proofing Works 7 days Thu 21-12-23Wed 27-12-2318
20 Shuttering work For Mat 15 days Thu 28-12-23Thu 11-01-2419
21 MS Bar Fabrication 30 days Fri 12-01-24 Sat 10-02-24 20
22 RCC Casting in MAT 3 days Sun 11-02-24 Tue 13-02-24 21
23 Basement 04 - Basement 03 45 days Wed 14-02-24Fri 29-03-24
24 MS Bar Fabrication & Shuttering 20 days Wed Mon 22
Work for Column, Lift Wall ,Shear 14-02-24 04-03-24
Wall , Stair, Ramp etc.
25 Concreting Works for Column, Lift 5 days Tue Sat 09-03-24 24
Wall ,Shear Wall , Stair, Ramp etc. 05-03-24
26 MS Bar Fabrication For Beam & Slab 15 days Sun 10-03-24 Sun 24-03-24 25
27 Electrical Conduit Laying Work 4 days Mon 25-03-24Thu 28-03-2426
28 Concreting Works For Beam & Slab 1 day Fri 29-03-24 Fri 29-03-24 27
(Level: Basement 3)
29 Basement 03 - Basement 02 45 days Sat 30-03-24 Mon 13-05-24
30 MS Bar Fabrication & Shuttering 20 days Sat 30-03-24 Thu 28
Work for Column, Lift Wall ,Shear 18-04-24
Wall , Stair, Ramp etc.
31 Concreting Works for Column, Lift 5 days Fri 19-04-24 Tue 30
Wall ,Shear Wall , Stair, Ramp etc. 23-04-24
32 MS Bar Fabrication For Beam & Slab 15 days Wed 24-04-24Wed 08-05-2431
33 Electrical Conduit Laying Work 4 days Thu 09-05-24Sun 12-05-24 32
34 Concreting Works For Beam & Slab 1 day Mon Mon 33
(Level: Basement 2 ) 13-05-24 13-05-24
35 Basement 02- Basement -01 45 days Tue 14-05-24Thu 27-06-24
36 MS Bar Fabrication & Shuttering 20 days Tue Sun 34
Work for Column, Lift Wall ,Shear 14-05-24 02-06-24
Wall , Stair, Ramp etc.
37 Concreting Works for Column, Lift 5 days Mon Fri 07-06-24 36
Wall ,Shear Wall , Stair, Ramp etc. 03-06-24
38 MS Bar Fabrication For Beam & Slab 15 days Sat 08-06-24 Sat 22-06-24 37
39 Electrical Conduit Laying Work 4 days Sun 23-06-24 Wed 26-06-2438
40 Concreting Works For Beam & Slab 1 day Thu Thu 39
(Level: Basement 1 ) 27-06-24 27-06-24
41 Basement 01- Ground Floor 45 days Fri 28-06-24 Sun 11-08-24
42 MS Bar Fabrication & Shuttering 20 days Fri 28-06-24 Wed 40
Work for Column, Lift Wall ,Shear 17-07-24
Wall , Stair, Ramp etc.
43 Concreting Works for Column, Lift 5 days Thu Mon 42
Wall ,Shear Wall , Stair, Ramp etc. 18-07-24 22-07-24
44 MS Bar Fabrication For Beam & Slab 15 days Tue 23-07-24 Tue 06-08-24 43
45 Electrical Conduit Laying Work 4 days Wed 07-08-24Sat 10-08-24 44
46 Concreting Works For Beam & Slab 1 day Sun Sun 45
(Level: Ground Floor ) 11-08-24 11-08-24
47 Ground Floor - 1st Floor 31 days Mon 12-08-24Wed 11-09-24
48 MS Bar Fabrication & Shuttering 7 days Mon Sun 46
Work for Column, Lift Wall ,Shear 12-08-24 18-08-24
Wall , Stair, Ramp etc.
49 Concreting Works for Column, Lift 3 days Mon Wed 48
Wall ,Shear Wall , Stair, Ramp etc. 19-08-24 21-08-24
50 MS Bar Fabrication For Beam & Slab 17 days Thu 22-08-24Sat 07-09-24 49
51 Electrical Conduit Laying Work 3 days Sun 08-09-24 Tue 10-09-24 50
52 Concreting Works For Beam & Slab 1 day Wed Wed 51
(Level: 1st Floor ) 11-09-24 11-09-24
53 1st Floor - 2nd Floor 31 days Thu 12-09-24Sat 12-10-24

Project: Construction of Vision Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress

Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress

Page 1
Proposed Tentative Work Program for Construction of Vision 2041 Smart Tower (Vision 2021 Tower-2, STP-2)
ID Task Task Name Duration Start Finish Predecessors 2024 2025 2026
Mode Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
54 MS Bar Fabrication & Shuttering 7 days Thu Wed 52
Work for Column, Lift Wall ,Shear 12-09-24 18-09-24
Wall , Stair, Ramp etc.
55 Concreting Works for Column, Lift 3 days Thu Sat 21-09-24 54
Wall ,Shear Wall , Stair, Ramp etc. 19-09-24
56 MS Bar Fabrication For Beam & Slab 17 days Sun 22-09-24 Tue 08-10-24 55
57 Electrical Conduit Laying Work 3 days Wed 09-10-24Fri 11-10-24 56
58 Concreting Works For Beam & Slab 1 day Sat 12-10-24 Sat 12-10-24 57
(Level:2nd Floor )
59 2nd Floor - 3rd Floor 31 days Sun 13-10-24Tue 12-11-24
60 MS Bar Fabrication & Shuttering 7 days Sun Sat 19-10-24 58
Work for Column, Lift Wall ,Shear 13-10-24
Wall , Stair, Ramp etc.
61 Concreting Works for Column, Lift 3 days Sun Tue 60
Wall ,Shear Wall , Stair, Ramp etc. 20-10-24 22-10-24
62 MS Bar Fabrication For Beam & Slab 17 days Wed 23-10-24Fri 08-11-24 61
63 Electrical Conduit Laying Work 3 days Sat 09-11-24 Mon 11-11-2462
64 Concreting Works For Beam & Slab 1 day Tue Tue 63
(Level: 3rd Floor ) 12-11-24 12-11-24
65 3rd Floor - 4th Floor 31 days Wed 13-11-24Fri 13-12-24
66 MS Bar Fabrication & Shuttering 7 days Wed Tue 64
Work for Column, Lift Wall ,Shear 13-11-24 19-11-24
Wall , Stair, Ramp etc.
67 Concreting Works for Column, Lift 3 days Wed Fri 22-11-24 66
Wall ,Shear Wall , Stair, Ramp etc. 20-11-24
68 MS Bar Fabrication For Beam & Slab 17 days Sat 23-11-24 Mon 09-12-2467
69 Electrical Conduit Laying Work 3 days Tue 10-12-24 Thu 12-12-2468
70 Concreting Works For Beam & Slab 1 day Fri 13-12-24 Fri 13-12-24 69
(Level: 4th Floor )
71 4th Floor - 5th Floor 31 days Sat 14-12-24 Mon 13-01-25
72 MS Bar Fabrication & Shuttering 7 days Sat 14-12-24 Fri 20-12-24 70
Work for Column, Lift Wall ,Shear
Wall , Stair, Ramp etc.
73 Concreting Works for Column, Lift 3 days Sat 21-12-24 Mon 72
Wall ,Shear Wall , Stair, Ramp etc. 23-12-24
74 MS Bar Fabrication For Beam & Slab 17 days Tue 24-12-24 Thu 09-01-2573
75 Electrical Conduit Laying Work 3 days Fri 10-01-25 Sun 12-01-25 74
76 Concreting Works For Beam & Slab 1 day Mon Mon 75
(Level: 5th Floor ) 13-01-25 13-01-25
77 5th Floor - 6th Floor 31 days Tue 14-01-25Thu 13-02-25
78 MS Bar Fabrication & Shuttering 7 days Tue Mon 76
Work for Column, Lift Wall ,Shear 14-01-25 20-01-25
Wall , Stair, Ramp etc.
79 Concreting Works for Column, Lift 3 days Tue Thu 78
Wall ,Shear Wall , Stair, Ramp etc. 21-01-25 23-01-25
80 MS Bar Fabrication For Beam & Slab 17 days Fri 24-01-25 Sun 09-02-25 79
81 Electrical Conduit Laying Work 3 days Mon 10-02-25Wed 12-02-2580
82 Concreting Works For Beam & Slab 1 day Thu Thu 81
(Level: 6th Floor ) 13-02-25 13-02-25
83 6th Floor -7th Floor 31 days Fri 14-02-25 Sun 16-03-25
84 MS Bar Fabrication & Shuttering 7 days Fri 14-02-25 Thu 82
Work for Column, Lift Wall ,Shear 20-02-25
Wall , Stair, Ramp etc.
85 Concreting Works for Column, Lift 3 days Fri 21-02-25 Sun 84
Wall ,Shear Wall , Stair, Ramp etc. 23-02-25
86 MS Bar Fabrication For Beam & Slab 17 days Mon 24-02-25Wed 12-03-2585
87 Electrical Conduit Laying Work 3 days Thu 13-03-25Sat 15-03-25 86
88 Concreting Works For Beam & Slab 1 day Sun Sun 87
(Level: 7th Floor ) 16-03-25 16-03-25
89 7th Floor - 8th Floor 31 days Mon 17-03-25Wed 16-04-25
90 MS Bar Fabrication Column, Lift 7 days Mon Sun 88
Wall, Shear Wall,Stair,Ramp etc. 17-03-25 23-03-25
91 Concreting Works for Column, Lift 3 days Mon Wed 90
Wall ,Shear Wall , Stair, Ramp etc. 24-03-25 26-03-25
92 MS Bar Fabrication For Beam & Slab 17 days Thu 27-03-25Sat 12-04-25 91
93 Electrical Conduit Laying Work 3 days Sun 13-04-25 Tue 15-04-25 92
94 Concreting Works For Beam & Slab 1 day Wed Wed 93
(Level: 8th Floor ) 16-04-25 16-04-25
95 8th Floor - 9th Floor 31 days Thu 17-04-25Sat 17-05-25
96 MS Bar Fabrication & Shuttering 7 days Thu Wed 94
Work for Column, Lift Wall ,Shear 17-04-25 23-04-25
Wall , Stair, Ramp etc.
97 Concreting Works for Column, Lift 3 days Thu Sat 26-04-25 96
Wall ,Shear Wall , Stair, Ramp etc. 24-04-25
98 MS Bar Fabrication For Beam & Slab 17 days Sun 27-04-25 Tue 13-05-25 97
99 Electrical Conduit Laying Work 3 days Wed 14-05-25Fri 16-05-25 98

Project: Construction of Vision Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress

Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress

Page 2
Proposed Tentative Work Program for Construction of Vision 2041 Smart Tower (Vision 2021 Tower-2, STP-2)
ID Task Task Name Duration Start Finish Predecessors 2024 2025 2026
Mode Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
100 Concreting Works For Beam & Slab 1 day Sat 17-05-25 Sat 17-05-25 99
(Level: 9th Floor )
101 9th Floor - Roof Slab 31 days Sun 18-05-25Tue 17-06-25
102 MS Bar Fabrication & Shuttering 7 days Sun Sat 24-05-25 100
Work for Column, Lift Wall ,Shear 18-05-25
Wall , Stair, Ramp etc.
103 Concreting Works for Column, Lift 3 days Sun Tue 102
Wall ,Shear Wall , Stair, Ramp etc. 25-05-25 27-05-25
104 MS Bar Fabrication For Beam & Slab 17 days Wed 28-05-25Fri 13-06-25 103
105 Electrical Conduit Laying Work 3 days Sat 14-06-25 Mon 16-06-25104
106 Concreting Works For Beam & Slab 1 day Tue Tue
(Level: Roof Slab) 17-06-25 17-06-25
107 125 mm & 250 mm Brick Work & AAC 270 days Sun Wed
Block Works 13-10-24 09-07-25
108 Basement 1 30 days Sun 13-10-24 Mon 11-11-2458
109 Ground Floor 30 days Tue 12-11-24 Wed 11-12-24108
110 1st Floor 30 days Thu 12-12-24Fri 10-01-25 109
111 2nd Floor 30 days Sat 11-01-25 Sun 09-02-25 110
112 3rd Floor 30 days Mon 10-02-25Tue 11-03-25 111
113 4th Floor 20 days Wed 12-03-25Mon 31-03-25112
114 5th Floor 20 days Tue 01-04-25 Sun 20-04-25 113
115 6th Floor 20 days Mon 21-04-25Sat 10-05-25 114
116 7th Floor 20 days Sun 11-05-25 Fri 30-05-25 115
117 8th Floor 20 days Sat 31-05-25 Thu 19-06-25116
118 9th Floor 20 days Fri 20-06-25 Wed 09-07-25117
119 Safety Net 30 days Sat 14-12-24 Sun 12-01-2570
120 Plaster Works ( Interior) 270 days Sat 11-01-25 Tue 07-10-25
121 Basement 1 30 days Sat 11-01-25 Sun 09-02-25 110
122 Ground Floor 30 days Mon 10-02-25Tue 11-03-25 121
123 1st Floor 30 days Wed 12-03-25Thu 10-04-25122
124 2nd Floor 30 days Fri 11-04-25 Sat 10-05-25 123
125 3rd Floor 30 days Sun 11-05-25 Mon 09-06-25124
126 4th Floor 20 days Tue 10-06-25 Sun 29-06-25 125
127 5th Floor 20 days Mon 30-06-25Sat 19-07-25 126
128 6th Floor 20 days Sun 20-07-25 Fri 08-08-25 127
129 7th Floor 20 days Sat 09-08-25 Thu 28-08-25128
130 8th Floor 20 days Fri 29-08-25 Wed 17-09-25129
131 9th Floor 20 days Thu 18-09-25Tue 07-10-25 130
132 Plaster Work ( Exterior) 80 days Sun 20-07-25 Tue 07-10-25 128SS
133 Paint Works (Interior + Exterior) 80 days Sun 20-07-25 Tue 07-10-25 132SS
134 Tiles, Marble & Granite Work 80 days Sun 20-07-25Tue 07-10-25133SS
135 Door Works 80 days Sun 20-07-25Tue 07-10-25134SS
136 Grill Work 80 days Sun 20-07-25Tue 07-10-25135SS
137 Façade Works (Curtain+ACP+GFRC) 211 days Fri 14-03-25 Fri 10-10-25
138 Design & Drawing Approval 60 days Fri 14-03-25 Mon 12-05-2576SS+60 days
139 Import of the Materials and 60 days Tue Fri 11-07-25 138
Equipment from abroad 13-05-25
140 Installation of the Curtain Wall system91 days Sat 12-07-25 Fri 10-10-25 139
141 Plumbing, Sanitary Works 232 days Sat 11-01-25 Sat 30-08-25 110
142 Rainwater Harvesting Works 90 days Mon 02-06-25Sat 30-08-25 141FF
143 Gas Connection work 232 days Sat 11-01-25 Sat 30-08-25 141SS
144 Water Pump Isntallation works 60 days Wed 02-07-25Sat 30-08-25 143FF
145 Interior Works & Furniture 270 days Tue 14-01-25Fri 10-10-25
146 Design & Drawing Approval 85 days Tue 14-01-25 Tue 08-04-25 76
147 Import Material, Preparetion, And 60 days Wed Sat 07-06-25 146
Preinstallation 09-04-25
148 Installation & Setup Futniture 125 days Sun 08-06-25 Fri 10-10-25 147
149 Landscaping work 77 days Fri 25-07-25 Thu 09-10-25
150 Earthwork 10 days Sun 31-08-25 Tue 09-09-25 142
151 Soil Treatment 10 days Wed 10-09-25Fri 19-09-25 150
152 Plantation Work 20 days Sat 20-09-25 Thu 09-10-25151
153 STP (Civil + E/M) 60 days Fri 25-07-25 Mon 22-09-25
154 Civl Work 30 days Fri 25-07-25 Sat 23-08-25
155 EM Work 30 days Sun 24-08-25 Mon 22-09-25154
156 Electro-Mechanical Works 352 days Tue 14-01-25Wed 31-12-25
157 Air Conditioning System (VRF System)270 days Tue 14-01-25Fri 10-10-25
158 Drawing and Design preparation 30 days Tue Wed 146SS
and approval 14-01-25 12-02-25
159 Import of the Materials and 120 days Thu Thu 158
Equipment from abroad 13-02-25 12-06-25
160 Installation of the HVAC system 90 days Fri 13-06-25 Wed 10-09-25159
161 Ttesting & Commissioning 30 days Thu 11-09-25Fri 10-10-25 160

Project: Construction of Vision Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress

Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress

Page 3
Proposed Tentative Work Program for Construction of Vision 2041 Smart Tower (Vision 2021 Tower-2, STP-2)
ID Task Task Name Duration Start Finish Predecessors 2024 2025 2026
Mode Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
162 Fire Protection, Fire Detection and 270 days Tue Fri 10-10-25
Alarm System 14-01-25
163 Drawing and Design preparation 30 days Tue Wed 158SS
and approval 14-01-25 12-02-25
164 Import of the Materials and 120 days Thu Thu 163
Equipment from abroad 13-02-25 12-06-25
165 Piping, cabling and installation of 90 days Fri 13-06-25 Wed 164
the equipment 10-09-25
166 Installation of the FPFDA system 30 days Thu 11-09-25Fri 10-10-25 165
167 SUBSTATION WORK 210 days Tue 14-01-25Mon 11-08-25
168 Drawing and Design preparation 15 days Tue Tue 162SS
and approval 14-01-25 28-01-25
169 Import of the Materials and 120 days Wed Wed 168
Equipment from abroad 29-01-25 28-05-25
170 Installation of the Substation system
60 days Thu 29-05-25Sun 27-07-25 169
171 Commissioning of Sub-Station 15 days Mon 28-07-25Mon 11-08-25170
172 LIFT WORK 270 days Tue 14-01-25Fri 10-10-25
173 Drawing and Design preparation 30 days Tue Wed 168SS
and approval 14-01-25 12-02-25
174 Import of the Materials and 120 days Thu Thu 173
Equipment from abroad 13-02-25 12-06-25
175 Installation of the Lift 90 days Fri 13-06-25 Wed 10-09-25174
176 Commissioning of Lift 30 days Thu 11-09-25Fri 10-10-25 175
177 Solar System 270 days Tue 14-01-25Fri 10-10-25
178 Drawing and Design preparation 30 days Tue Wed 173SS
and approval 14-01-25 12-02-25
179 Import of the Materials and 120 days Thu Thu 178
Equipment from abroad 13-02-25 12-06-25
180 Installation of the equipment 90 days Fri 13-06-25 Wed 10-09-25179
181 Installation of the Solar system 30 days Thu 11-09-25Fri 10-10-25 180
182 Optical Fiber and Networking System270 days Tue 14-01-25Fri 10-10-25 178SS
183 Drawing and Design preparation 30 days Tue Wed 178SS
and approval 14-01-25 12-02-25
184 Import of the Materials and 120 days Thu Thu 183
Equipment from abroad 13-02-25 12-06-25
185 Piping, cabling and installation of 90 days Fri 13-06-25 Wed 184
the equipment 10-09-25
186 Installation of the Networking system
30 days Thu 11-09-25Fri 10-10-25 185
187 Surveillance System 270 days Tue 14-01-25Fri 10-10-25
188 Drawing and Design preparation 30 days Tue Wed 183SS
and approval 14-01-25 12-02-25
189 Import of the Materials and 120 days Thu Thu 188
Equipment from abroad 13-02-25 12-06-25
190 Piping, cabling and installation of 90 days Fri 13-06-25 Wed 189
the equipment 10-09-25
191 Installation of the Surveilence system
30 days Thu 11-09-25Fri 10-10-25 190
192 Video Conferencing, Stage Lighting 270 days Tue Fri 10-10-25
& Sound System 14-01-25
193 Drawing and Design preparation 30 days Tue Wed 188SS
and approval 14-01-25 12-02-25
194 Import of the Materials and 120 days Thu Thu 193
Equipment from abroad 13-02-25 12-06-25
195 Piping, cabling and installation of 90 days Fri 13-06-25 Wed 194
the equipment 10-09-25
196 Installation of the Stage Lighting & 30 days Thu Fri 10-10-25 195
Sound system 11-09-25
197 Integrated Building Management 270 days Tue Fri 10-10-25
System (IBMS) 14-01-25
198 Drawing and Design preparation 30 days Tue Wed 193SS
and approval 14-01-25 12-02-25
199 Import of the Materials and 120 days Thu Thu 198
Equipment from abroad 13-02-25 12-06-25
200 Piping, cabling and installation of 90 days Fri 13-06-25 Wed 199
the equipment 10-09-25
201 Installation of the IBMS System 30 days Thu 11-09-25Fri 10-10-25 200
202 Testing and Commissioning of the 30 days Sat 11-10-25 Sun 201,196,191,186,181,176,171,166,161,148,140
whole Building Systems 09-11-25
203 Project Cleaning and ready for handover
12 days Mon 10-11-25Fri 21-11-25 202
204 Final Bill Submission, Clearence & 40 days Sat 22-11-25 Wed 203
Handing Taking Over 31-12-25
205 Project End 0 days Tue 30-12-25Tue 30-12-25204 30-12
206

Project: Construction of Vision Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress

Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress