SIMINTO POND

The document outlines a project for the construction of the Derara Community Pond in Gorodola Woreda, Oromia Regional Government, with a total duration of 20 days from April 28, 2025, to May 18, 2025. Key activities include mobilization, site clearance, excavation, cartaway of excavated material, site handover, and demobilization. The contractor for the project is Liben Lark Water Work SME.

Uploaded by

Zelalem Teshome
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views

SIMINTO POND

The document outlines a project for the construction of the Derara Community Pond in Gorodola Woreda, Oromia Regional Government, with a total duration of 20 days from April 28, 2025, to May 18, 2025. Key activities include mobilization, site clearance, excavation, cartaway of excavated material, site handover, and demobilization. The contractor for the project is Liben Lark Water Work SME.

Uploaded by

Zelalem Teshome
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

State:-OROMIA REGIONAL GOVERNMENT EAST BORENA ZONE GORODOLA WOREDA

Client:-PSNP GORODOLA WOREDA


Project Location:- DERARA KEBELE
Contractor:-LIBEN LARK WATER WORK SME
PROJECT NAME DURATION START DATE END DATE
DERARA COMMUNITY POND 20 4/28/2025 5/18/2025
Days

4/28/2025
4/29/2025
4/30/2025

5/10/2025
5/11/2025
5/12/2025
5/13/2025
5/1/2025
5/2/2025
5/3/2025
5/4/2025
5/5/2025
5/6/2025
5/7/2025
5/8/2025
5/9/2025
ID DESCRIPTION Duration in days START DATE END DATE
1 mobilization 1 4/28/2025 4/28/2025 X
2 site clearance for pond Enbankment 1 4/29/2025 4/29/2025 X
excavation of ordinary at adepth of 2m and embankment
3 work 14 4/30/2025 5/13/2025 X X X X X X X X X X X X X X
4 cartaway excavated material 2 5/14/2025 5/15/2025
5 site handovering 1 5/16/2025 5/16/2025
5 demobilization 1 5/17/2025 5/18/2025