SME_Chapter 9
SME_Chapter 9
Mining
Engineering
(MN-325)
CHAPTER 9
Mine Planning and Design
Lecturer
Dr Clara Akalanya Abuntori
1
2024
Introduction
❑Mine planning is a critical process in the mining industry that involves the design and
optimization of a mining operation to extract valuable minerals or resources from the
earth efficiently and economically.
❑It encompasses a range of activities, from geological assessments to infrastructure design.
▪ Geological Assessment
▪ Resource Estimation
▪ Mine Design: Pit or Underground, Mine Layout, Equipment Selection and Waste Management.
▪ Mine Scheduling: Short-Term vs. Long-Term, Production Targets and Optimization
▪ Environmental Considerations
▪ Financial Analysis
▪ Safety and Risk Management
▪ Regulatory Compliance
▪ Continuous Improvement
▪ Monitoring and Reporting
▪ Community Engagement
2
Introduction
❑The planning of a surface mine (open or strip) is an exercise in
economics constrained by certain geological and mining engineering
aspects. The main objectives are:
▪ Cost targets for capital and operating expenditures, and unit costs
3
Introduction
Careful planning is required prior to and at all stages during mining activity. the
principal objectives of detailed planning are:
❑To establish the acceptable economic stripping ratio and hence define the shape
of the excavation and the limits of surface mining
❑To maintain an adequate amount of ore uncovered at all times to meet
production targets.
❑To develop and maintain access for equipment
❑In variable quality deposits, to ensure that the working faces available can at all
times furnish the required average grade
❑To retain flexibility to change the shape of the final pit in the light of new
geological information or changing economic circumstance.
4
Objectives of Mine Planning
The following are some major objectives from the view point of feasibility:
❑Mine the orebody so that the production cost per unit of metal is a minimum;
❑Maintain operational viability (adequate bench width and ready haulage access
for equipment)
❑Maintain sufficient exposure of ore to counter miscalculations or insufficient
data from exploration
❑Defer stripping requirements as long as possible without significant disruption
of production schedule
5
Objectives of Mine Planning
❑Follow a logical and achievable start-up schedule (for training, equipment,
procurement and deployment, logistics, etc.) that minimizes the risk of delays in
positive cashflows.
❑Maximise design pit slopes, while minimising likelihood of bank failures (provide
❑safety berms, employ rock mechanics, etc)
6
Range on Mine Plans
Short Range
❑annual plan
7
Mine Planning
Long Range Mine Planning
❑The initial step in surface mine design is the compilation of a long-range
mining plan or final pit design.
❑In reality, long-range mining plans usually change over time to reflect the
effects of a changing economy, increased knowledge of the orebody, and
improvements in mining technology.
▪ life of mine
▪ 25-year plan
▪ 5-year plan
8
Mine Planning
Short-range Mine Planning
❑Once a long-range plan has been established, it is essential to develop a series
of short-range mining plans.
❑These plans define the intermediate steps required to ascertain the final pit
limit under physical, operating, and legal constraints.
❑They also provide the pit boundary, ore grade, stripping ratio and anticipated
profit information necessary for future production forecasts and equipment
needs.
▪ annual plan
9
Mine Planning
Production Scheduling Monthly Plan
❑daily schedule ❑equipment moves.
❑weekly schedule ❑Updated weekly.
❑monthly schedule
Annual Plan Weekly Plan
❑Basis for the budget and operations for ❑To allocate resources (equipment and
the financial year. Covers from 14 to 18 manpower); identify work locations; set
months to provide overlap and continuity. production targets.
Daily Plan
Monthly Plan ❑Schedules locations and quantities for all
mine equipment
❑Operational scheduling, especially to
identify scheduled maintenance and
major
10