g Dot Roundabout Design Guide
g Dot Roundabout Design Guide
4/27/2023
Revision 2.3
Atlanta, GA 30308
This document was developed as part of the continuing effort to provide guidance within the
Georgia Department of Transportation in fulfilling its mission to provide a safe, efficient, and
sustainable transportation system through dedicated teamwork and responsible leadership
supporting economic development, environmental sensitivity and improved quality of life.
This document is not intended to establish policy within the Department, but to provide
guidance in adhering to the policies of the Department.
Your comments, suggestions, and ideas for improvements are welcomed.
DISCLAIMER
The Georgia Department of Transportation maintains this printable document and is solely
responsible for ensuring that it is equivalent to the approved Department guidelines.
Roundabout Design Guide
Revision Summary
Revision Number Revision Date Revision Summary
1.0 December 2019 N/A
2.0 11/15/2021 The revision of this document dated November
2021 incorporates:
• The preference to include turbo roundabout
features on multilane applications
• Revision and restructuring of the entire
document
• Portions of the appendices moved into the
body of the document and the addition of
sections related to:
• Acronyms and Definitions
• Roundabout types (1.1)
• Expandable design (2.1.1)
• Design vehicles (3.5)
• Roundabout shapes (3.9)
• Metering (5.3.3)
• Roundabout railroad crossings (6)
• Spiral design (Appendix E)
2.1 9/30/22 Chapter 1 – Updated GDOT hyperlinks
Chapter 3 – Revised splitter island profiles info
Chapter 4 – Added info regarding installation of
conduits
Chapter 5 – Replaced figures 5-2 through 5-5
2.2 11/9/22 Chapter 8 – Replaced figure 8-6
2.3 4/27/23 Chapter 5 - Updated figures
Page i
Roundabout Design Guide
Page ii
Roundabout Design Guide
Table of Contents
Revision Summary ............................................................................................................................... i
List of Effective Chapters ................................................................................................................... iii
Table of Contents ................................................................................................................................ v
Acronyms and Definitions .................................................................................................................. ix
Acronyms ........................................................................................................................................ ix
Definitions ........................................................................................................................................ x
Chapter 1. Introduction - Contents ................................................................................................... 1-i
1.1 Roundabout Types ............................................................................................................1-3
1.1.1 Single Lane Roundabouts ..........................................................................................1-3
1.1.2 Multilane Roundabouts ...............................................................................................1-5
Capacity and Operations - Contents ............................................................................... 2-i
2.1 Roundabout Operational Analysis Process .......................................................................2-1
2.1.1 Expandable Design ....................................................................................................2-3
2.1.2. Common Pitfalls .........................................................................................................2-4
2.2 Operational Analysis Software ..........................................................................................2-5
2.2.1. SIDRA Intersection .....................................................................................................2-5
2.2.2. GDOT’S Roundabout Analysis Tool ...........................................................................2-6
Geometric Design - Contents .......................................................................................... 3-i
3.1 Design Process and Workflow ...........................................................................................3-1
3.2 Practical Design Considerations ........................................................................................3-2
3.3 Design Criteria ...................................................................................................................3-3
3.4 Roundabout Functional Area .............................................................................................3-4
3.4.1 Driveway Access/Median Opening .............................................................................3-4
3.5 Design Vehicle ...................................................................................................................3-5
3.6 Check Vehicle ....................................................................................................................3-6
3.6.1 OSOW Permit Types ..................................................................................................3-6
3.6.2 OSOW Template Library ............................................................................................3-7
3.7 Circle Location and Alignment of Approaches ...................................................................3-8
3.8 Circle Size .......................................................................................................................3-11
3.9 Roundabout Shapes ........................................................................................................3-13
3.10 Design of Approaches .....................................................................................................3-14
3.10.1 High Speed ...............................................................................................................3-15
3.11 Entry Curves ....................................................................................................................3-19
3.12 Fastest Path ....................................................................................................................3-20
3.13 Stopping Sight Distance ..................................................................................................3-25
Definitions
Bicycle Path Diversion – Bicycle treatments at roundabouts provide bicyclists the option of traveling
through the roundabout either by riding in the travel lane as a vehicle, or by exiting the roadway and,
if available, using a shared-use path, depending on the bicyclist’s level of comfort.
Capacity – The maximum hourly rate at which persons or vehicles reasonably can be expected to
traverse a point or uniform segment of a lane or roadway during a given period under prevailing
roadway, traffic, and control conditions.
Central Island – The raised area in the center of a roundabout, around which traffic circulates. The
central island is typically circular in shape but can be modified to accommodate truck turning
movements.
Circulatory Roadway –The travel way portion of the roundabout used by vehicles to travel in a
counterclockwise fashion around the central island.
Design Exception – A design condition that does not meet AASHTO guidelines and requires specific
approval from the GDOT Chief Engineer and FHWA.
Design Speed – A selected speed used to determine the various geometric design features of a
roadway. The maximum safe speed that can be maintained over a specified section of the road when
conditions are so favorable that the design features of the road govern.
Design Variance – A design condition that does not meet GDOT policy. A design variance requires
specific approval from the GDOT Chief Engineer.
Design Vehicle – A selected motor vehicle, the weight, dimensions, and operating characteristics of
which are used as a control in road design. As defined by FHWA: the longest vehicle permitted by
statute of the road authority (state or other) on that roadway (MUTCD).
Design Year – The anticipated future traffic, typically 20 years from the base year/open year for all
GDOT projects.
Edge Line Extension (Entry Line) – A pavement marking line of demarcation separating traffic
approaching the roundabout from the traffic already in the circulating roadway. The point which a
vehicle typically yields to circulating traffic is usually defined by a wide dotted edge line extension. By
practitioners, it is commonly referred to as a yield line.
Entry Radius – The minimum radius of curvature measured along the right curb at entry of a
roundabout. Smaller radii may decrease capacity, while larger radii may cause inadequate entry
deflection.
Entry Width – The perpendicular distance from the right curb line of the entry to the intersection of
the left edge line and the inscribed circle of a roundabout.
Exit Radius – The minimum radius of curvature measured along the right curb at the exit of a
roundabout. Exit radii should then be larger than entering radii.
Exit Width – The perpendicular distance from the right curb line of the exit to the intersection of the
left edge line and the inscribed circle.
ICE – Intersection Control Evaluation is a transparent and traceable engineering study process for
intersection alternative selection to address operational and safety problems at intersections and
major access points. Intersection control selection relies on quantitative and qualitative measures of
capacity, safety and cost. The process is codified, and guidance is provided in GDOT policy.
Landscape Buffer – Placed between the curb and sidewalk to separate vehicular and pedestrian
traffic and to help direct pedestrians to cross only at the designated crossing locations and to provide
space for sign placement. Landscaping can also significantly improve intersection aesthetics and
contribute to traffic calming provided it is placed outside the required sight limits. The buffer must be
detectable by people of all abilities.
Level of Service – A qualitative rating of a road’s effectiveness relative to the service it renders to its
users (from A-best to F-worst). LOS is measured in terms of a number of factors, such as operating
speed, travel time, traffic interruptions, freedom to maneuver and pass, driving safety, comfort, and
convenience.
Path Efficiency – The balancing of paths in and through the roundabout so that each movement has
approximately the same path length. It promotes balanced speed control from opposing approaches.
See Section 3.16.
Practical Design – Designers should optimize circle size, location, and alignment of legs that
promotes balanced speed control from opposing approaches and ensure efficient movements for a
practical design.
Right turn Bypass Lane – A lane added, that bypasses the circulatory roadway, when there is a
high right turn traffic demand, or geometry requires the bypass to accommodate an acute right turn.
Sidewalk / Shared-Use Path – It is common to provide a shared-use path at the perimeter of the
roundabout to provide both pedestrians and bicyclists off-road accommodation. Standard sidewalks
are provided in lieu of a shared-use path when bicycle traffic is expected to use the roadway through
the roundabout.
Spiral (spiral lane transition) – A spiral is a geometric feature of the truck apron needed for some
multilane roundabout configurations with exclusive left-turn lanes. The spiral transitions left-turning
vehicles from the inside to the outside circulating lane to allow vehicles to exit without changing lanes
within the circulatory roadway (not to be confused with a highway curve spiral).
Splitter Island – Typically a raised median on an approach used to separate entering from exiting
traffic, deflect and slow entering traffic, and provide median refuge for pedestrians crossing the road
in two stages.
Truck Apron – The mountable portion of the central island adjacent to the circulatory roadway. It is
required to accommodate the wheel tracking of long or oversized vehicles Oversize/Overweight
vehicles (OSOW). It is usually concrete with a contrasting color to delineate the apron from the normal
vehicle path.
Truck Aprons (Outside) – A truck apron placed on the outside of the travel way, usually on corner
radii that are too tight for large trucks and OSOW trucks to track in the travel way. They can also be
incorporated into splitter islands for OSOW truck accommodation.
Introduction - Contents
Introduction - Contents .................................................................................................... 1-i
1.1 Roundabout Types ............................................................................................................1-3
1.1.1 Single Lane Roundabouts ..........................................................................................1-3
1.1.2 Multilane Roundabouts ...............................................................................................1-5
Introduction
The modern roundabout is characterized by the following basic principles:
• Generally circular shape with counterclockwise traffic flow
• Yield-at-Entry – Vehicles approaching the roundabout must wait for a gap in the circulating
flow before entering the circle.
• Slow speed environment – Through geometric curvature and entry path deflection, the traffic
is directed or channeled to the right of the central island with a curved entry path into the
circulatory roadway.
Roundabout design is a principles-based, performance-driven design process where the critical
elements of circle size, circle location and alignment of approaches are guided by safety and
operational performance criteria. Operational analysis (2.1) determines the required lane
configuration which is then followed by geometric design. Safety performance can be achieved
through a geometric design (3) that provides speed control, minimizes potential for entry-circulating
crashes and establishes priority to circulating traffic. Approach geometry and a visibility package of
signs, markings and landscaping should build driver expectation of speed reduction and yield on
entry.
This design guide presents the principles and methods of achieving practical design and optimal
roundabout operations through performance-based design. Appendix A provides examples of
practical design implementation. Appendix B provides a step-by-step on reading
oversized/overweight (OSOW) records and determining a check vehicle. Appendix C shows an
example of how to do high speed approach design. Appendix D provides instructions to undertake
design performance checks and an example of a performance checks package. Appendix E shows
examples of how to develop spiral approach design. Appendix F explains best-practice vertical design
methods in more detail.
This document is intended to supplement the GDOT Design Policy Manual (DPM) Chapter 8 and is
underpinned by NCHRP 672, Roundabouts: An Informational Guide – 2nd Edition (2010). Where
stated values and figures differ from NCHRP 672, the GDOT Roundabout Design Guide should take
precedent for GDOT roundabout design practice. This document is a guide for designers; it is
intended to answer frequently asked questions about roundabout designs. This document is not
intended as policy or design standards.
Increasingly over the last decade, roundabouts are being implemented in Georgia, partially due to
the implementation of the Intersection Control Evaluation (ICE) process/policy. The ICE tool offers
single lane and multilane roundabout alternatives as configurations to be considered when evaluating
an intersection.
The revision of this document dated November 2021 incorporates:
• the preference to include turbo roundabout features on multilane applications
• revision and restructuring of the entire document
• portions of the appendices moved into the body of the document
and the addition of sections related to:
• Acronyms and Definitions
Rev 2.1 1. Introduction
9/30/22 Page 1-1
Roundabout Design Guide
Typically, four operational performance measures are used to estimate the operational performance
of a roundabout entry: volume-to-capacity ratio, control delay, LOS, and queue length. These
measures are checked to be within the desirable ranges for each lane configuration throughout the
iterative process.
It can be beneficial to determine the approximate lane requirements before undertaking a more
detailed software analysis. NCHRP 672 Section 3.5.1 provides guidance on estimating lane
requirements. For instance, if the sum of the entering and circulating volumes for each approach is
less than 1,100 veh/h, then a single-lane roundabout is likely to operate acceptably.
Starting with the Design Year traffic turning movements, begin the analysis with a single-lane
roundabout (unless a multilane is needed to maintain lane continuity) and consider adding the
following before creating a multilane roundabout, see Figure 2-1:
• Right turn bypasses
o Right turn Partial (Yielding) Bypass Lane – A right turn yielding bypass lane with
either a curbed or a painted channelization requires approaching vehicles to yield to
traffic leaving circulatory roadway at the adjacent exit. This alternative should prevent
the right turner from making a through movement while preserving good sight lines to
the left for conflicting circulating/exiting traffic. Generally, an angle of 70 degrees or
higher is desirable.
o Right turn (Free-flow) Bypass Lane – Right turn free-flow bypass lanes allow
vehicles to bypass the roundabout and then continue in a dedicated lane or merge into
an adjacent lane. A high right turn demand when coupled with other approaching traffic
may indicate the need for a full bypass lane in order to avoid a wider, faster entry.
Right turn full bypass lanes create an additional conflict for pedestrians and bicyclists
and should only be used when needed for additional capacity.
• Hybrid layouts (including exclusive left turn lanes)
In certain situations, metering may be appropriate for a single or multilane roundabout to mitigate
delays, see Section 5.3.3.
To account for the functional area of the roundabout, the analyst should be aware of driveways near
the roundabout (see Section 3.4). Ideally, the approach roadway should have adequate storage
capacity so that the queue does not obstruct driveway access or another intersection.
Expandable Design
In some situations, the requirements for acceptable Design Year operations require a larger footprint
than the Build Year. If this is the case, the roundabout should be constructed and operated in the
Build Year lane configuration until traffic volumes dictate the need for conversion/expansion. A Design
Life analysis should be run to determine how long the reduced lane configuration is projected to
operate acceptably. We recommend 10 years for physical footprint changes, whereas 5 years might
be acceptable for a striping change. When considering an expandable design, the designer should
also evaluate the right‐of‐way and geometric needs for both the Build and Design Year lane
configurations.
If considering a single lane roundabout and if capacity analysis indicates that conversion to a
multilane roundabout is needed prior to the Design Year, then a conventional single lane ICD is likely
more desirable than a compact or mini-roundabout for expandability.
Geometric Design
3.1 Design Process and Workflow
Achieving an optimal roundabout geometry requires a thorough exploration of the ‘design space’:
location context, geometric requirements, and potential trade-offs of safety with capacity and/or cost.
Concept sketching allows initial exploration of feasibility and potential impacts before investing
significant effort in detail design elements. When sketching conceptual layouts, it is important to
produce the most cost-effective layout, with minimal tradeoffs, for a given set of constraints and
location context.
To limit the number of iterations of design, the operational analysis should be completed
before the general footprint of a roundabout is designed. Figure 3-1 summarizes this process to
align with the stages of project development for GDOT PDP Projects including roundabouts.
Roundabouts constructed using non-PDP delivery mechanisms such as: Quick Response projects,
special encroachment & driveway permits, a non-GDOT roadway, etc. may use an abbreviated
project development process.
Figure 3-1. Design Process and Workflow for GDOT PDP Roundabouts
All roundabout designs should address the capacity and safety needs of an intersection, but
designers should take a practical approach to reduce project costs. Practical design does not
compromise safety nor eliminate standards and good practice. It does focus on context, need and
purpose, and emphasizes engineering judgement.
Designers should optimize circle size, location, and alignment of legs that promotes balanced speed
control from opposing approaches and ensure efficient movements for a practical design.
Practical design is essentially design optimization with a greater emphasis on balancing cost with
capacity and safety benefits. This requires careful consideration of design trade-offs. Designers
should consult with the Office of Design Policy and the Office of Traffic Operations when considering
possible design variances implied by the list of cost saving ideas below.
Eliminating lower priority project design elements can result in lower cost and improved value without
adverse effects on safety and capacity benefits. Depending on site context, designers should consider
the following examples for a practical design:
• Remove excess curb – use curb to only confine trucks and to reduce speeds near the entries
and exits rather than along the entire project length
• Reduce splitter island length – use shorter medians (splitter islands) with added visibility
elements on the approach
• Reduce excess lighting – use pavement marking reflectors and illuminated bollards instead,
see Section 7)
• Remove excess drainage structures – construct rural shoulders and ditches instead
• Avoid multiple construction stages and temporary pavement – employ road closures and off-
site detours
• Pavement preservation – reduce the amount of pavement reconstruction by using milling &
inlay or overlay instead of full depth construction
Practical design doesn’t change the requirements to meet basic design criteria and the
variances/exceptions needed for not meeting them. However, designers can achieve cost savings by
utilizing flexibility that exists in current design guidance and standards. Practical design
considerations include but are not limited to:
• Minimizing required Right-Of-Way (ROW) by:
o using a smaller circle size
o employing ellipses to mitigate intersection skew angle or avoiding adding right turn
bypass channelization
o shifting roundabouts to avoid parking, storage tanks or other property impacts that
might cause full displacements and increase ROW costs.
• Rightsizing for traffic demands – staged expandability from single lane to multilane.
• Utilize context sensitivity by encompassing existing features such as: important trees and
landscaping
• Setting the roadway and circle to blend with the existing roadway profiles
Appendix A provides a diagram of this list (Figure A-1) and an expanded discussion of practical design
and examples of how it can be applied.
Rev 2.1 3. Geometric Design
9/30/22 Page 3-2
Roundabout Design Guide
The mindset of the designer should be that performance, not geometric conformance, guides the
geometric design. Designers must strategically keep the performance objectives of safety and
operations in mind and let them guide the selection of the applicable design details. The overall design
composition and the resulting performance matters more than the individual dimensional elements.
The initial selection of roundabout size (Section Chapter 3) as well as position and approach
alignments (Section 3.8) play a large role in achieving the following high-level core principles:
• Speed control
• Entry and exit path alignment
• Capacity (lane configuration)
• Space for trucks
• Stopping Sight Distance
• Entry and exit channelization
• Safety for vulnerable users (pedestrians and cyclists)
The following focus on fine-tuning the design while still supporting the principles above:
• Lane widths and transitions (including spirals, see Appendix E)
• Intersection Sight Distance (Section 3.14)
• Grading (Section 3.17.3)
• Traffic Control Devices (Chapter 5)
• Lighting (Chapter 7)
• Landscaping (Chapter 8)
Before beginning geometric design, it is important to determine the appropriate design vehicle for all
movements. All design vehicle selections should account for engineering judgement and take
into consideration: field observations, classification counts, local land use, site context,
known future developments, and roadway functional classification.
Table 3-1 should be used as a default/starting point for design vehicle considerations at roundabouts
to reduce impacts, based on intersection type.
State Route State Route WB-67 is a common truck configuration for state route movements
If an intersection must accommodate a large design vehicle for all turning movements, a compact
roundabout may not be practical. For sites where WB-62/WB-67 size tractor trailers are only
accommodated for mainline through movements and smaller design vehicles are used for the side
streets (e.g. access to a residential subdivision), then a compact design may be more practical.
In addition, the following should be able to navigate the roundabout without mounting any curbs (truck
aprons or blisters): emergency vehicles, single unit trucks (SU), School Bus (S BUS-36) (rural), buses
(BUS-40) (urban); see Section 3.15 of this guide for accommodating design vehicles.
150 to 170
Typical ICD *70 to 90 ft 85 to 120 ft 120 to 160 ft 160 to 190 ft 180 to 210 ft
ft
Desirable
range of
15 to 20 20 to 25 20 to 25 20 to 28 20 to 30
theoretical 20 to 25 mph
mph mph mph mph mph
fastest entry
speed
Typical Truck Traversable
Apron central 12 to 14 ft 8 to 12 ft 8 to 12 ft 12 to 14 ft 14 to 16 ft
Width** island
*ICD of less than 70 ft can be used on non-state routes (pay special attention to speed control).
**Truck apron should be determined based on design vehicles.
A reduced ICD may need to be considered to accommodate multiple features (pedestrian features
need to be added & limited ROW, etc.).
Rev 2.1 3. Geometric Design
9/30/22 Page 3-11
Roundabout Design Guide
Mini-Roundabout
Mini-roundabouts are single lane roundabouts defined by their smaller ICD with a diameter typically
less than 90 ft. They accommodate large vehicles by allowing them to drive over the fully mountable
central island, see Section 3.18.2 for typical sections on mini-roundabouts. The small footprint of a
mini-roundabout offers flexibility when working within constrained sites.
Compact Roundabout
The choice of a compact or conventional single-lane roundabout is dependent on factors such as
space available at an intersection, intersection angle (skew), class/speed of roadways and design
vehicle.
A smaller ICD has tradeoffs related to accommodation of larger design vehicles. Typically, a compact
roundabout will not accommodate a larger tractor trailer, e.g. a WB-62/WB-67, without overtracking
outside edges of pavement/curbs. But often in these cases overtrack raised truck blisters may be
used to compensate for the smaller ICD.
Single Lane Roundabout (Conventional)
A good starting point for a single-lane roundabout is an ICD of 130 feet. The ICD may be increased
or slightly decreased to accommodate right-of-way, the design vehicle and to control speeds to meet
fastest path requirements. At a 90-degree intersection that needs to accommodate a larger design
vehicle for all movements, e.g. WB-67, a good range for the ICD is 130 to 150 ft. In situations with
more than four legs or skewed intersection angles, larger ICDs or different circle shapes may be
necessary; see Section 3.9 for Roundabout Shapes.
Hybrid Roundabout
Since a hybrid roundabout is a blend of one and two circulating lanes; it has a variable circle size.
Multilane Roundabout (Case 1-3)
At multilane roundabouts, the ICD is usually determined by balancing the need to achieve entry path
deflection and provide smooth entry path alignment; see Section 3.12 and 3.16 for more information.
Typically, the addition of lanes and satisfying both design objectives requires a slightly larger diameter
than used for single-lane roundabouts. Lane configuration requirements and choice of case design
for tractor trailers (see Section 3.15.2) also influence ICD.
A primary goal of roundabout design is to make drivers aware of the roundabout with enough distance
to gradually decelerate to a slow entry speed. This is especially necessary in rural areas where driver
expectancy is free flow. Approach geometry should build driver expectation to reduce speed and yield
at entry, a fundamental operating condition to maintain priority to circulating traffic. Geometric design
of approaches that is safe and practical generally exhibits these principles:
• Approach Alignment
o Left Offset (preferred): An approach alignment offset left of the circle center (see Figure
3-8) is most beneficial (and therefore recommended) to promote gradual speed reduction
and yield at entry. This approach alignment typically generates the necessary entry path
deflection to achieve geometrically slow entry speeds. For additional information, see
NCHRP 672, Sections 6.2.1 & 6.7.1. Additional advantages to an offset left design are:
• Increased deflection – best for speed control with rural design
• Maintains clear sight of the central island
• Beneficial for accommodating large trucks (allows for larger entry radius while
maintaining deflection and speed control)
• Helps to minimize circle size
• May increase exit radius which reduces control of exit speeds/acceleration, but
improves SSD of exit crosswalk
o Radial Approach: Although not preferred, it can be used when there are ROW
constraints, alignment concerns, low speed environment, and/or low volume approaches.
• Forward Sight Distance/Stopping Sight Distance: Desirable forward visibility of the
roundabout entry, based on approach design speed.
• Central Island Visibility: Approaches should be aligned horizontally and vertically to make
the central island and yield point as conspicuous as possible.
• Splitter islands: Splitter islands extend upstream of the yield line to the point at which
entering drivers are already decelerating. Practical design may dictate otherwise, but as a
general guideline: 200 ft for speeds above 45 mph, 100 ft for speeds between 35 mph to 45
mph; and, 50 ft is acceptable for speeds below 35 mph.
o The nose of the approach splitter island should incorporate a 2 to 4 ft offset from the
face of curb to the paint line on high-speed approaches.
o Pedestrian access through the splitter island should have ADA ramps and should be
either ramped up or semi-depressed.
• “Visibility package”: Ensure sufficient use of items such as: signs, pavement marking, raised
pavement markers/delineators, landscaping and, in some cases, flashers and/or illumination
on the approach to the roundabout (see Chapter 5, 7 and 8 for more information). This can
compensate for shorter length splitter islands.
• Curb and gutter: Curb and gutter help vehicles to maintain lane and reduces speeds;
therefore, introduce it in the transitional and low speed segments of the approach. Graduation
from paved shoulder to mountable curb to vertical face curb provides an ideal transition from
rural to urban cross-section.
• Exit Taper: Exit tapers are used to consolidate a two-lane exit to one lane. Exit taper lengths
from roundabouts are based on the calculated in-lane exiting speed; therefore, the taper rate
can be significantly shorter than the design speed of the roadway. Merging taper rates should
be typically 20:1 to 30:1. The length of parallel full-width lanes beyond the circulating roadway
to beginning the merging taper varies depending on volume and other factors. See Figure 3-
9b.
Since in-lane exiting speeds are typically less than 40mph, the taper can be calculated using
MUTCD Table 6C-4’s equation:
40mph or less: 𝐿 = 𝑊𝑆 2 /60
Where:
• L = taper length in feet
• W = width of offset in feet
• S = posted speed limit, or off-peak 85th-percentile speed prior to work starting, or the
anticipated operating speed in mph
The right-side curve near the roundabout entry, also called the entry radius, helps to control entry
speeds and is typically in the range of 65 to 100-ft. A starting point for entry radius estimation is half
of the ICD. The left side radius can be larger since it has no effect on entry speed control but does
influence truck swept paths. Narrowing of the splitter island at the entry may be required to
accommodate large trucks while maintaining speed control (minimizing the entry radius and entry
width); see Figure 3-11 and Section 3.15 for truck considerations.
See Section 3.15.2 for more information about the truck case designs shown in Figure 3-15 to 3-17.
Table 3-3 describes the critical radii that make up the fastest path and provides ranges of desirable
speeds. The lower range of the table is preferred, especially where significant levels of pedestrians
are present.
See Appendix D.1 on how to draw and measure Fastest Paths using Bentley MicroStation CAD
software.
Path alignment ensures the vehicle is aligned at entry and exit with the appropriate receiving lane. At
single-lane entries, reviewing path alignment considers where the driver is being aimed; additionally,
path alignment at the entry curve slows down vehicles. For multilane roundabouts, path alignment of
both entry and circulating path should be designed with additional care due to the characteristics of
side-by-side vehicles.
Path efficiency is the balancing of paths in and through the roundabout so that each movement has
approximately the same path length. The goal of path efficiency is to provide a balanced flow (speed
control and path) for all movements. In some cases, designs might be able to have balanced paths
and balanced speed control from opposing approaches. In non-uniform geometry, the attempt to form
path efficiency may have unintended consequences due to the lack of speed reduction and increased
costs. Fixating on path efficiency may result in a design that is not practical.
When determining circle size, shape, and alignment of legs, consider path alignment and path
efficiency so that movements from every direction are balanced.
Figure 3-31 provides a method for checking and avoiding path overlap (for Case 1). For the entry and
exit path tangents, the tangent should extend from the circulating curve to the entry or exit. Path
overlap can typically be avoided if there is approximately 5 ft between the central island curb and the
extension of the splitter island curb, with the radius of that curve extension in the range of 75 to 100
ft. Another way to avoid path overlap is to add raised lane dividers to physically separate vehicles,
such as shown for Case 2 and Case 3 multilane designs.
Figure 3-32 shows path overlap in a Case 3 multilane roundabout; the raised lane separation within
the circulatory roadway should start closer to the entry to avoid this path overlap. Figure 3-33 shows
raised lane dividers on the entry that will guide traffic into the correct circulatory lane and prevent path
overlap.
Case 3 roundabouts should implement a tapered nose (aka. frog), a mountable raised divider that
will be used by large trucks, to transition the beginning of the raised lane divider and to assist in
avoiding path overlap. See Section 3.18 for tapered nose detail.
The opening width is measured where the left lane entering crosses a portion of the circulatory
roadway (see Figure 3-34). Keeping the opening width small helps to avoid path overlap; the striping
on either side of the opening is critical to guide drivers into the correct circulatory lane of a multilane
roundabout.
Since roundabout design is performance based, it is helpful to complete horizontal design and
validate it through geometric performance checks before setting construction alignments. After
horizontal alignments have been set, vertical design can start.
Vertical design is an iterative process and includes profiles, superelevation, approach grades and
drainage. The fastest-path checks should be confirmed after vertical design is complete to determine
whether the cross-slopes influence geometric entry speed predictions. For a detailed walk-through,
see Appendix F.
3.17.2 Profiles
When developing profiles, it is best to start by considering the general topography of the intersection
before getting into detail design of individual profiles (e.g. would a tipped circle, or a circle with the
circulatory roadway sloping inwards on the high side, be more practical in the given context?).
It is important to understand the existing terrain, roadway profiles and cross-slopes; keep general
grading, drainage and sight distance considerations in mind when designing. Sometimes varying
profiles are needed to accommodate adjacent properties, avoid ESAs, etc. Existing constraints and
impacts should always be considered.
For the circulatory roadway profile, visualizing the roundabout as an upside-down dish tilting on a
plane (tipped circle) is ideal. It would have one high point (HP) and one low point (LP) and a
continuous profile that closes on itself. Figure 3-41A and 3-41B illustrate a cross-section of a tipped
circle. The circulatory roadway profile should be designed from short vertical curves and tangents.
To avoid potential sight line issues, consider limiting longitudinal grade to 4%. It is recommended to
have short curves (K values for 20 to 25 mph) without flat grades for drainage purposes, especially
near the sag. Begin the profile at a point approximately halfway between the LP and the HP so that
the vertical curves will not be bisected on the profile plan sheet.
For the splitter island profiles, one option is to choose appropriate K values based on the deceleration
zone speed contours. Splitter islands can also be designed using offsets and grade callouts.
Construction cost can often be reduced by staying close to the existing surface and matching what
the existing roadway is doing at the tie-ins. Keep low points out of crosswalks to avoid grate inlets or
standing water within crossing areas. Additionally, check that the cross slope for the crosswalk is no
steeper than 5% per ADA requirements for an uncontrolled crossing (PROWAG R302.6.1). A profile
with a grade of 5% or less does not require a GDOT design variance. Break overs between splitter
island profiles and circulatory roadway cross slopes in those locations should be no more than 4%.
If using outside curb line alignments, ensure that there are smooth transitions and that proper
breakovers (< 4%) are maintained.
**Curbs for truck aprons are typically 4” with a type 9 face; however, 3” can be used in
locations with higher truck volumes.
***8” should be used for Front of Truck Apron
Figure 3-37A. Roundabout Approach Typical Section with Monolithic Splitter Island
Figure 3-39A. Roundabout with Tipped Circle Section (Truck Apron Sloped Out)
Figure 3-39B. Roundabout with Tipped Circle Section (Truck Apron Sloped In)
3.18.2 Mini-Roundabouts
Due to their smaller circle size, mini-roundabouts require a fully mountable (traversable) central
island to accommodate trucks. Special consideration should be applied to mini-roundabouts when:
• the posted speed limit is above 35mph (lack of deflection of the smaller circle)
• pedestrian generators are nearby (narrower splitter islands)
• there are more than four legs (lack of spacing between the approaches)
For a mini-roundabout to operate as intended, especially on a higher speed roadway, it is essential
that the intersection type can be recognized and that drivers have adequate forward visibility of the
intersection. For this reason, the central island at mini-roundabouts should be defined by not only
paint, but also by including a fully mountable raised concrete center island (no more than 5 inches
high). The island may have a 3” or 4” mountable curb face (monolithic or curb and gutter). See
Figure 3-45.
Internally illuminated bollards with keep-right chevrons are recommended for illumination and
visibility. These are designed to withstand vehicle overtracking and, therefore, may be installed on
the mountable central island. See Figure 3-46.
There are three general principles to optimize wayfinding for visually impaired people who rely on
nonvisual information:
• Curb ramps should be oriented so that the running slope is in the same direction as the
crosswalk and/or the edges of landscaping or ramps should be aligned in the direction of travel
on the crosswalk.
• Alignment of pedestrian crossing should be perpendicular to the edge of the travel way and
with the direction change in the refuge island to create the shortest crossing path.
• Landscaping, fences, or other features should restrict the ability of pedestrians to cross at
locations other than crosswalks, or at least make it very clear where crossing is not intended
and provide guidance to the crosswalk location.
Figure 4-3. Bicycle Path Exit and Entry without Extended Sidewalk
Figure 4-4. Bicycle Path Exit and Entry with Extended Sidewalk
5.1 Signing
Similar to conventional intersections, signing at roundabouts includes regulatory signs, warning signs
and guide signs. Section 13.2 of the GDOT Signing and Marking Design Guidelines covers signing
at roundabouts. The required signs are covered in the following sections of the Signing and Marking
Guide:
• Advanced Warning Signs W2-6 and W13-1P 13.2.1
• Yield Signs R1-2 13.2.2
• Guide Signs D1-5 or D1-3d, M5 (State Route Shields) 13.2.3
• Lane Use Signs R3-8 series or R3-6 series 13.2.4
• Pedestrian Signs W11-2 and W16-7P 13.2.5
LED bordered yield signs can be considered to improve conspicuity (and are recommended at
mini-roundabouts). Internally Illuminated Bollards with a chevron symbol should be installed in the
central island at mini-roundabouts. They can also be used for nose point treatments on splitter islands
with the R4-7 sign to improve visibility. Both LED bordered yield signs and internally illuminated
bollards need to be permitted by the GDOT TMC Signal Permitting Section.
5.2 Marking
Section 13.3 of the GDOT Signing and Marking Design Guidelines covers pavement marking at
roundabouts. The required pavement marking items are covered in the following sections of the
Signing and Marking Guide:
• Edge Line Extension (Entry Line/’Yield Line’) 13.3.1
• Yield word marking 13.3.2
• Arrows on multilane approaches 13.3.3
• Pedestrian crossing 13.3.4
D1-5 signs should be used on all State Route approaches. Context sensitivity should be used to
determine the need for installation on the local road approaches. Different text sizes should be utilized
based on approach speed for all roadways, with larger text sizes to be used on roads with posted
speeds greater than 45 MPH. Figure 5-7 shows typical dimensions and sizing for D1-5 signs as a
guide for designers.
Table 6-1 compares the different queue management devices and techniques based on the clear
storage distance (CSD) and minimum track clearance distance (MTCD). Per the MUTCD definition,
(Part 1A.13),
“CSD is the distance available for vehicle storage measured between 6 ft from the rail nearest
the intersection to the intersection stop line or the normal stopping point on the highway. The
MTCD is the length along a roadway at one or more railroad tracks and is measured from
either the gate arms or stop lines.”
Reference the FHWA-FRA Highway-Rail Crossing Handbook (3rd Ed.) “Figure 38 - Clear Storage
and Minimum Track Clearance Distance” for a diagram showing the CSD and MTCD at a railroad
crossing.
Clear Storage
Application Key Operational Characteristics
Distance
6.1 Gating
Gating is a physical barrier preventing traffic from moving forward while in use. When gates are
located outside the railroad right-of-way, the railway authority may not want to maintain the gate nor
interconnect them to preempt the crossing.
Gating may be useful when an engineering study has concluded the roundabout queue is likely to
spill back from the roundabout to the railroad crossing. Depending on the length/speed of the train
and the duration the gate is down, the traffic exiting the roundabout that is stopped at the gate may
spill back to the roundabout, effecting operations.
Figure 6-2A. Track clearance stage with gated closure for circulating flow
Figure 6-2B. Track clearance stage with gated closure for circulating flow and at track
crossing
Figure 6-2C. Track hold stage with gated closure at railroad crossing only
Rev 2.0 6. Roundabout Railroad Crossing and Preemption
11/15/21 Page 6-5
Roundabout Design Guide
Figure 6-3A. Track clearance stage with gated closures at roundabout approach entries
Figure 6-3B. Pre-empt hold stage with gated closures at approach entries and railroad
crossing
Figure 6-3C. Track hold stage with gated closures at railroad crossing only
Rev 2.0 6. Roundabout Railroad Crossing and Preemption
11/15/21 Page 6-7
Roundabout Design Guide
Lighting - Contents
Lighting - Contents .......................................................................................................... 7-i
7.1 Principles ...........................................................................................................................7-1
7.2 Pole Placement Recommendations ..................................................................................7-2
Lighting
7.1 Principles
The critical areas that require illumination are the entering/circulating conflict points, crosswalks, and
transition points from pavement to raised channelization. If the approaching roadways are not
continuously illuminated, transition lighting may be required. Refer to Section 14.3.3 of the GDOT
DPM. GDOT is exploring ways to reduce the number of light poles on roundabouts. In some rural
locations, lighting is reduced from approaches and is only used at the circulatory roadway. Using
other visibility elements, such as internally illuminated bollards and raised pavement markers, are
encouraged as a consideration for reduced lighting, subject to approval by the Office of Design Policy.
Lighting plans should be developed consistent with the guidelines presented in Chapter 14 of the
DPM and ANSI/IES RP-8 (American National Standard Practice for Design and Maintenance of
Roadway and Parking Facility Lighting).
Landscaping - Contents
Landscaping - Contents .................................................................................................. 8-i
8.1 Central Island Grading .......................................................................................................8-1
8.2 Landscaping ......................................................................................................................8-2
8.3 Color and Texture Treatments for Truck Aprons ...............................................................8-5
Landscaping
Central island grading and landscaping further improves safety performance and addresses
aesthetics of a roundabout by:
• Increasing the roundabout visibility from a distance – this is particularly important on rural or
high-speed approaches
• Blocking through sight across the circle – so drivers focus on the intersection and do not see
headlights approaching from the other side
• Blocking excessive sight distance around the circle to encourage slower speeds
8.2 Landscaping
Landscaping should be added in conjunction with grading to further improve safety performance and
address aesthetics.
Proper landscaping prevents sight distance issues by effectively blocking through sight. It naturally
slows down runoff to mitigate changing a natural area into a paved area. It also reduces the heat
island effect. Impervious material should be used as little as possible to avoid a drainage burden
on the circulatory roadway. Establishment of the landscaping, on GDOT maintained routes, is covered
by Specification Section 702 — Vine, Shrub, and Tree Planting.
Landscaping typically consists of low-lying perimeter landscaping (sod) and inner central island
landscaping (grasses, shrubs, or trees). See GDOT Construction Detail RA-1 for GDOT’s standard
low maintenance landscaping. Perimeter landscaping is needed when line of sight needs to be
retained across part of the landscaped central island. Its width should be labeled on construction plan
sets and is determined by intersection and stopping sight distance checks, as shown in Figures 8-3
and 8-4. Line of sight can be achieved within the truck apron without having to look through the central
island; in which case, the perimeter landscaping does not have to be low lying.
If maintenance resources for landscaping is limited, please contact the Office of Traffic Operations to
determine if an ultra-low maintenance option is available.
Used for mountable areas, i.e. truck aprons, etc. Use for non-mountable areas, i.e. splitter islands
Pavement Design
9.1 Pavement Type Selection
Pavement type selection at a roundabout is determined by the existing pavement type, proposed
pavement cost, projected traffic volumes, and constructability during staging. In most cases, asphalt
is the most economical and is easier to stage roundabout construction. Staging is typically
significantly simpler, and costs are typically lower, if the existing roadway can be asphalt overlaid
instead of having to construct full depth pavement. Additional preference is given to asphalt for
multilane roundabouts where the contrast of pavement marking for lane lines and directional arrows
is essential for safe operation.
Concrete pavement should be considered for roundabouts; however, the above items should be
factored into the decision and documented; see DPM Section 10.9 for more information. Consult with
OMAT and refer to the Pavement Design Manual and PDP Section 6.4.2 for additional guidelines on
pavement type selection.
Rev 2.0 10. Alternative Concepts for Staging Roundabout Construction - Contents
11/15/21 Page 10-i
Roundabout Design Guide
Stage 1
Stage 2
Stage 3
Stage 1
• Shift or close and detour traffic on south leg.
• Construct temporary widening along the
south side of the mainline for future traffic
switches.
• Complete full construction of the south leg.
• Construct as much as possible of the
roundabout quadrants and circulatory
roadway.
Stage 2
• Shift mainline traffic onto temporary
widening and open the south leg to traffic.
• Close and detour traffic from the north leg.
• Complete full construction of north leg.
• Construct as much as possible of the
roundabout quadrants and circulatory
roadway.
• Construct westbound mainline approaches.
• Construct temporary pavement for traffic
switches
Stage 3
• Shift mainline traffic on to new westbound
lanes using temporary pavement in the
islands.
• Open the north leg to traffic.
• Complete construction of eastbound
mainline approaches.
Stage 4
• Complete construction of central island and
splitter islands.
• Remove pavement under the landscaping
area and all temporary pavement and
construct outside curb and gutter after
central island is completed.
• Pave surface course of asphalt
Stage 1
• Construct all truck apron and any
widening out of existing asphalt
• Traffic remains on existing lanes.
Stage 2
• Shift traffic to roundabout control
• Construct splitter islands, curb and
gutter, etc.
• Remove excess pavement
Stage 1
• Construct widening to one side of the roadway to
accommodate traffic during the construction of the
permanent pavement in stage 3.
• Traffic remains on existing lanes.
Stage 2
• Construct one quadrant of the roundabout and as much of
the circulatory roadway as possible.
• Temporary leveling will likely be needed on existing lanes
through the intersection to keep a smooth transition.
Stage 3 & 4
• Construct the remaining
quadrants and the
circulatory roadway.
• Consider adding leveling
to roadway as needed to
avoid drainage issues.
• Use the shoulder for a
traffic lane or temporary
pavement as needed to
complete the roundabout
construction.
Stage 5
• Construct the remaining central island and splitter islands,
quadrants and the circulatory roadway.
• Traffic is on the newly constructed pavement.
• Remove all temporary pavement and construct outside
curb and gutter after central island is completed.
Stage 1
• Construct temporary pavement along one side of the
two-lane road and crossovers on the four-lane road.
• Traffic remains on existing lanes.
Stage 2
• Construct one quadrant of the roundabout and as much
of the circulatory roadway as possible.
• Construct any additional temporary pavement needed
for traffic switches.
• Restrict traffic to one lane in each direction through the
intersection.
Stage 3 & 4
• Construct the
remaining quadrants
and the circulatory
roadway.
• Use the temporary
pavement as needed
to complete the
roundabout
construction.
Stage 5
• Construct the remaining central island and splitter
islands, Quadrants and the circulatory roadway.
• Remove all temporary pavement and construct outside
curb and gutter after central island is completed.
Figure A-1 shows an example of a real project, through the course of practical design considerations,
the red-line layout was reduced to the black-line layout. Cost savings on this roundabout are in the
range of about 20%.
Appendix B. OSOW
B.1 Review of OSOW Permits
The following is a list of steps and guidance on how to source and account for the space requirements
of oversize vehicles (OSOW) in roundabouts.
Single Trip Permits
1. Request records from [email protected] at the subject intersection.
2. Tabulate truck movements by vehicle type and turning movement
a. Ignore all records relating to one-time events, such as concrete beams for construction
projects.
b. Examine all records with a length of 100-ft or more.
c. Truck type can be determined by examining the truck length, axle count, and load type.
Cross-reference records with the GDOT OSOW template library catalog; see Appendix
B.2.
i. Load type can be useful in determining vehicle type, as mobile homes or specified
loads with high centers of gravity that can indicate a lowboy trailer.
ii. In some cases, the trucking company website can give an indication as to what type
of vehicles they operate.
d. The turning movement can be determined by examining the route, given by a string of
sequential road names.
e. Vehicles over 150 ft are assumed to have rear-steer capabilities.
f. Remove redundant/repeated information (duplicated permit numbers)
3. Based on findings, design roundabout for appropriate vehicle on each movement.
Follow Table B-1 below during the review process.
ASSUMPTION REASONING
The image depicts an example of high-speed approach design with Emax as 6%, but approaches may have an Emax of 8% or 10% in some cases.
D.1.2 Measuring the Critical RADII of the Spline and their Associated Speeds
Fastest path radii are calculated by measuring the smallest radius at critical locations (R1-R5) over a
distance of 65 ft – 80 ft.
In Figure D-3, the center of a (65 ft – 80 ft diameter) circle is placed where the spline touches the
offset line at the R1 through R5 locations.
• To measure the critical radius of the spline, draw a three-point arc snapped along
the fast path spline within the confines of the circle. This helps the designer to
quickly judge the length of the arc and to maintain consistent arc lengths for all
radius measurements.
• Continue drawing arcs on either side of the circle until the smallest radius is found.
This is the critical radius for speed control (R1 through R5).
Rev. 2.0 D. Roundabout Performance Checks
11/15/21 Page D-2
Roundabout Design Guide
• Use Equations 6-1 and 6-2 provided in NCHRP 672 to convert the R1 through R5 radius
measurements to the actual critical speeds.
𝑉 = 3.4415𝑅0.3861 , 𝑓𝑜𝑟 𝑒 = +0.02
𝑉 = 3.4614𝑅0.3673 , 𝑓𝑜𝑟 𝑒 = −0.02
V = predicted speed, mph
R = radius of curve, ft
e = superelevation, ft/ft
Tip: Using a positive (favorable) 2% cross slope will provide the most conservative speed
values and is recommended for all radius-speed conversions during the horizontal design
stage. If the designer knows the entire circulatory roadway will be sloped toward the outside
of the circle, a negative 2% cross slope may be used for the R2 and R4 radius to speed
conversions.
• Often the R3 radius is large or nearly tangential, and a meaningful exiting speed cannot be
determined with Equations 6-1 and 6-2 alone. The R3 critical exiting speed should therefore
also be calculated based on vehicle acceleration from the measured R2 critical speed location
to the point of interest on the exit (typically the crosswalk) using NCHRP 672 Equation 6-4
and as illustrated in Figure D-4.
𝑉3𝑝𝑏𝑎𝑠𝑒
𝑉3 = { 1 }
√(1.47𝑉2 )2 + 2𝑎23 𝑑23
1.47
𝑉3 = exit speed, mph
𝑉3𝑝𝑏𝑎𝑠𝑒 = 𝑉3 speed predicted based on path radius, mph
𝑉2 = circulatory speed for through vehicles predicted based on path radius, mph
𝑎23 = acceleration between the midpoint of V_2 path and the point of interest along
𝑉3 𝑝𝑎𝑡ℎ = 6.9𝑓𝑡/𝑠2
𝑑23 = distance along the vehicle path between midpoint of 𝑉2 path and point of interest along
𝑉3 path, ft
In accordance with the AASHTO Green Book, object heights should be restricted to 2 ft tall within
SSD envelopes (which include Approach SSD, SSD for Bypass Lanes, Crosswalk SSD, and
Circulatory SSD), and 3.5 ft tall within ISD envelopes (which include Entering and Circulating ISD).
These envelopes should be hatched using the ‘Crosshatch Area’ tool and the ‘Pattern Area’ tool
and clearly defined using a legend.
D.2.1 Stopping Sight Distance (SSD)
See NCHRP 672, Equation 6-5 when calculating stopping sight distances.
𝑉2
𝑑 = (1.468)(t)(V) + 1.087( )
𝑎
d = stopping sight distance, ft
t = perception-brake reaction time, assumed to be 2.5s
V = initial speed, mph
A = driver deceleration, assumed to be 11.2 ft/s2
Checks should be provided for:
1. Approach SSD to the yield line and crosswalk on entry
2. Approach SSD to crosswalk on bypass lane
3. SSD to the crosswalk on exit
4. SSD around the circulatory roadway
Drawing Tips
Approach SSD to Yield Line
1. Obtain the rounded Approach SSD (d).
2. Split the entry in half and use the ‘construct line at active angle’ tool (with an angle of 0.0°) to
extend the offset arc to the yield line. This locates the center of the entry at the yield line. If
the entry is two lanes, use the pavement markings to locate the center of the entry at the yield
line.
3. Center a circle with radius (d) on the center of the entry at the yield line.
4. Offset a maximum of 6 ft from the right edge of the lane; or, for a multilane approach, split the
far-right lane in half (if smaller than 12 ft wide).
5. Draw a line from the center of the circle to the point where the circle intersects the offset lane
lines.
Note: these steps also apply to right turn partial bypass lanes with yield lines.
Approach SSD to Crosswalk
1. Obtain the rounded Approach SSD (d).
2. Center a circle with radius (d) on the intersection of the crosswalk paint line (farthest from the
yield line) and the face of curb.
3. Draw a line from the center of the circle to the point where the circle intersects with the offset
lane lines from Step 4 above.
Drawing Tips
1. Obtain the rounded Approach SSD (db) for the bypass lane (based on the bypass R5).
2. Measure db along the fast path in a few key places.
a. Draw a line crossing the path where you would like to begin measuring db.
b. Use the ‘trim elements’ tool to trim the fast path to this line.
c. From the ‘points’ toolbox (accessed by going to Tools > Toolboxes) choose the ‘Point at
a Distance Along’ tool.
i. Choose a character or cell for the point and type the distance along the line to measure
db .
ii. Click the beginning of the line where you want to start measuring db and then click the
line in the direction you want to measure. A point will be placed on the line at the
distance specified. Trim the fast path line to this point to achieve db.
Drawing Tips
1. Obtain the Crosswalk SSD (da), based on R5.
2. Trim the fast path to the near side of the crosswalk.
3. Measure da along the fast path using the same techniques described in Step 2 of the ‘Drawing
Tips’ for ‘Approach Stopping Sight Distance for Right Turn Bypass Lanes’ in the previous
section.
4. Connect the end of the fast path to the near side of the crosswalk at the face of curb to create
the sight line.
Drawing Tips
For Consistent R4 Values
1. Obtain the Circulatory SSD (d), based on R4.
2. Offset the central island face of curb 3 ft and measure d along the offset line. (Use ‘Point at
Distance Along’ tool)
3. Connect both ends of the offset line to form the sight line.
4. Repeat Steps 2 and 3 for a minimum of four intervals around the central island.
Tip: For quick placement of the sight lines, rotate the first offset arc and sight line from steps 2
and 3 around the center point of the central island to get at least four intervals around the central
island.
𝑑2 = (1.468)(𝑉𝑚𝑎𝑗𝑜𝑟,𝑐𝑖𝑟𝑐𝑢𝑙𝑎𝑡𝑖𝑛𝑔 )(𝑡𝑐 )
Drawing Tips
1. Offset the far-left lane 3 ft from the left edge of curb/paint line or 5 ft from the face of curb. Use
the ‘construct line at active angle’ tool (with an angle of 0.0°) to extend the offset arc to the
yield line.
2. Center a circle with radius 50 ft at the intersection of the yield line and active angle line. Draw
two lines from the center of the circle, one that intersects the offset arcs with the edge of the
circle and one that is perpendicular to the central island face of curb.
3. Trim the fast path of the immediate upstream entry to the line perpendicular to the central
island using the ‘trim elements’ tool.
4. Obtain the Entering ISD (d1), based on the average R1 and R2 speeds. Measure this distance
along the fast path using techniques described in Step 2 of the ‘Drawing Tips’ for ‘Approach
Stopping Sight Distance for Right Turn Bypass Lanes’.
5. Draw the Entering ISD sight line from the end of the 50 ft line to the end of the fast path.
Vehicle accommodation is checked using a vehicle analysis software such as AutoTURN. Horizontal
accommodations (2D analysis) should be checked throughout the horizontal design process for both
design vehicles and check vehicles. Vertical accommodations (3D analysis) should typically be
checked for low-clearance vehicles (often OSOW trucks referred to as a “lowboys” or “gooseneck”-
style trailers) as the roundabout moves into preliminary plan development and vertical geometrics are
developed.
D.3.1 2D Analysis
Two methods exist for analyzing horizontal truck accommodations in 2D: Freehand (referred to as
“Arc Path” in AutoTURN) and Offset Path (referred to as “Adaptive Simulation” in AutoTURN). A
typical guideline for design and check vehicles is to provide 1 ft clearance from the tire of the cab to
the curb face.
When conducting a 2D analysis, the designer should consider displaying, at a minimum, the following
envelopes: front tires, rear tires, vehicle body, and load. Displaying the body envelope is often
beneficial when analyzing vehicles with large front overhangs (common with city buses, fire trucks,
and farm equipment). Displaying the load envelope is often beneficial when analyzing vehicles with
large or long loads (common with OSOW trucks).
The Freehand Method
The Freehand method works well for determining approximate roadway width requirements and is
the only method for analyzing trucks with independent rear-steering capabilities (such as tiller-
aerial fire trucks and some OSOW trucks).
The Freehand method involves manually driving the truck through the desired turning movement.
This method considers lock-to-lock steering time, steering angle locks, and trailer angle locks, but
also accounts for a non-varying speed along the path set by the user. 9 MPH or less is desirable, 6
MPH is preferred for very large vehicles (for example, rear-steering vehicles). (Note that as the speed
increases, maneuverability and net off-tracking decreases.) With practice, paths generated with this
method can be as smooth as paths generated with the Offset Path method.
It should be noted that with the freehand method is related to the "turn wheels from stop" which, when
applied for typical design vehicles, creates a path with many kinks in it that does not reflect the path
a vehicle may actual take. For vehicles that need to use the "turn wheels from stop" feature, extra
care is needed to obtain a smooth path.
If a vehicle has independent rear-steer capabilities, care should be taken to not overstate the
maneuverability of the actual vehicle. A good rule-of-thumb is to turn the rear wheels 4-degrees for
every 17 ft of travel path. The designer should minimize rear steering.
To conduct a 3D analysis, a 2D vehicle path and a combined 3D surface are needed. The surface
should cover the entire area of the 2D path and needs to include the following areas: circulatory
roadway, truck apron, outside curb and gutter, entries, and exits. The surface should be free of
extraneous triangles and large gaps, which may affect the accuracy of the 3D analysis. It should be
noted that changes to the surface to correct one problem might result in issues in other areas.
Therefore, if changes are made to a surface, the vertical checks need to be re-analyzed.
1. Use a 3D DGN file for this analysis.
2. Select the proposed DTM surface (mesh) and the 2D AutoTURN swept path (that has already
been run).
3. Click on “Convert 2D to 3D” button to convert the 2D AutoTURN swept path to a 3D path
(make sure to keep the original 2D path when asked by AutoTURN).
This step will analyze the vehicle’s vertical profile on the proposed DTM surface and check
for areas of scrapping.
A completed 3D analysis can be seen in Figure D-11. The green hatching indicates there is
adequate vertical clearance. The red hatching indicates areas where there are potential conflicts.
Areas of concern should be reviewed in the 3D cross-section analysis, also known as “Punch
Through”. These cross-sections identify the extent of the scrapping and will help to determine where
adjustments to the grading design are needed.
1. Start by placing perpendicular lines across the red hatching areas where cross-sections will
be cut (shown as lines 101 to 108 in Figure D-11, for example).
2. Click on the “Analyze Punch Through” button.
3. Select the AutoTURN swept path and a perpendicular line from step 1.
Figure D-12 shows an example of a “Punch Through” cross-section with the vehicle’s vertical
clearances displayed (1” tolerance built-in).
This tie-in cross-slope is then transitioned back to Normal Crown at a rate that will range from 0.02%/ft
up to 0.04%/ft (Figure F-7) to limit maximum relative gradients.
This exercise is repeated for each entry and exit at the roundabout. A spreadsheet is highly
recommended for refinement of adjustments.
Check the outside EOP (produced from the proposed DTM surface) and make adjustments if there
are local low points along the gutter that shouldn’t be there. Adjustments can be made through
manipulation of the cross-slopes (or the outside EOP profile). In either case, cross-slopes (calculated
from GDOT DPM Section 4.5.4) should be maintained under 4% on the high side and 2% on the low
side of the circle. A cross-slope transition rate between 0.02%/ft and 0.04%/ft will result from this
calculation.
Cross-section corridors utilizing proper tie-ins and transitions will result in a smooth and seamless
surface with minimal gaps or overlaps, as shown in Figure F-8.
Figure F-9 shows SE changes around the circle, cross slopes, and elevation points making it easy to
check the vertical design.