DAY WISE REPORT

The document details the progress of construction activities from April 3 to April 11, 2025, including reinforcement work, concrete pouring, and brick wall construction. Observations indicate that curing is regularly performed, materials are properly aligned, and construction adheres to specified drawings. Locations for the activities are consistently noted as Sir M.V Layout, Behind Parvathamma Ramaiah, and Conventional Hall, Upkar Layout, Annapoorneshwari Nagar.

Uploaded by

23vbvarsha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views7 pages

DAY WISE REPORT

The document details the progress of construction activities from April 3 to April 11, 2025, including reinforcement work, concrete pouring, and brick wall construction. Observations indicate that curing is regularly performed, materials are properly aligned, and construction adheres to specified drawings. Locations for the activities are consistently noted as Sir M.V Layout, Behind Parvathamma Ramaiah, and Conventional Hall, Upkar Layout, Annapoorneshwari Nagar.

Uploaded by

23vbvarsha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE

03-04-2025 Steel Reinforcement work Sir M.V


reinforcement in progress for Layout,
for columns and vertical columns Behind
slab curing Bars properly tied Parvathamma
with binding wire Ramaiah
and adequately Conventional
supported. Hall, Upkar
Rebar joints Layout,
staggered and Annapoornes
positioned as per hwari Nagar.
drawing/spec.
And curing is done
regularly
04-04-2025 Concrete pouring Column Sir M.V
for columns and reinforcement, Layout,
curing is done formwork, and Behind
alignment were Parvathamma
checked and Ramaiah
approved prior to Conventional
pouring. Columns Hall, Upkar
were poured Layout,
continuously without Annapoornes
cold joints. hwari Nagar.
Formwork checked
during pouring to
avoid bulging or
leakage. And curing
is done regularly.
DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE
07-04-2025 Curing is done The required Sir M.V Layout,
and shifting materials are Behind
materials to first shifted to the first Parvathamma
floor floor and curing Ramaiah
for columns is Conventional
done regularly by Hall, Upkar
using wet burlap Layout,
bags. Annapoorneshw
ari Nagar.
DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE
08-04-2025 Curing is done Brickwork done Sir M.V Layout,
and Brick wall in English bond. Behind
construction is in Proper alignment Parvathamma
progress. and plumb Ramaiah
maintained using Conventional
spirit level and Hall, Upkar
plumb bob. Layout,
Curing is done Annapoorneshw
regularly. Curing ari Nagar.
initiated within 24
hours of
brickwork
completion.
DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE
09-04-2025 Brick wall Brickwork done Sir M.V Layout,
construction is in in English bond. Behind
progress. And Proper alignment Parvathamma
Curing is done and plumb Ramaiah
maintained using Conventional
spirit level and Hall, Upkar
plumb bob. Layout,
Before the Annapoorneshw
construction of ari Nagar.
brick wall, they
marked as per the
drawings. Curing
is done regularly.
Curing initiated
within 24 hours
of brickwork
completion
DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE
10-04-2025 Brick wall Brickwork done in Sir M.V
construction is in English bond. Proper Layout,
progress. And alignment and Behind
Curing is done plumb maintained Parvathamma
using spirit level and Ramaiah
plumb bob. Curing Conventional
is done regularly. Hall, Upkar
Curing initiated Layout,
within 24 hours of Annapoornes
brickwork hwari Nagar.
completion
DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE
11-04-2025 Brick wall Brickwork done Sir M.V
construction is in in English bond. Layout,
progress. And Proper alignment Behind
Curing is done and plumb Parvathamma
maintained using Ramaiah
spirit level and Conventional
plumb bob. Hall, Upkar
Curing is done Layout,
regularly. Curing Annapoornes
initiated within 24 hwari Nagar.
hours of
brickwork
completion