The document details the progress of construction activities from April 3 to April 11, 2025, including reinforcement work, concrete pouring, and brick wall construction. Observations indicate that curing is regularly performed, materials are properly aligned, and construction adheres to specified drawings. Locations for the activities are consistently noted as Sir M.V Layout, Behind Parvathamma Ramaiah, and Conventional Hall, Upkar Layout, Annapoorneshwari Nagar.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
9 views7 pages
DAY WISE REPORT
The document details the progress of construction activities from April 3 to April 11, 2025, including reinforcement work, concrete pouring, and brick wall construction. Observations indicate that curing is regularly performed, materials are properly aligned, and construction adheres to specified drawings. Locations for the activities are consistently noted as Sir M.V Layout, Behind Parvathamma Ramaiah, and Conventional Hall, Upkar Layout, Annapoorneshwari Nagar.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7
DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE
03-04-2025 Steel Reinforcement work Sir M.V
reinforcement in progress for Layout, for columns and vertical columns Behind slab curing Bars properly tied Parvathamma with binding wire Ramaiah and adequately Conventional supported. Hall, Upkar Rebar joints Layout, staggered and Annapoornes positioned as per hwari Nagar. drawing/spec. And curing is done regularly 04-04-2025 Concrete pouring Column Sir M.V for columns and reinforcement, Layout, curing is done formwork, and Behind alignment were Parvathamma checked and Ramaiah approved prior to Conventional pouring. Columns Hall, Upkar were poured Layout, continuously without Annapoornes cold joints. hwari Nagar. Formwork checked during pouring to avoid bulging or leakage. And curing is done regularly. DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE 07-04-2025 Curing is done The required Sir M.V Layout, and shifting materials are Behind materials to first shifted to the first Parvathamma floor floor and curing Ramaiah for columns is Conventional done regularly by Hall, Upkar using wet burlap Layout, bags. Annapoorneshw ari Nagar. DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE 08-04-2025 Curing is done Brickwork done Sir M.V Layout, and Brick wall in English bond. Behind construction is in Proper alignment Parvathamma progress. and plumb Ramaiah maintained using Conventional spirit level and Hall, Upkar plumb bob. Layout, Curing is done Annapoorneshw regularly. Curing ari Nagar. initiated within 24 hours of brickwork completion. DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE 09-04-2025 Brick wall Brickwork done Sir M.V Layout, construction is in in English bond. Behind progress. And Proper alignment Parvathamma Curing is done and plumb Ramaiah maintained using Conventional spirit level and Hall, Upkar plumb bob. Layout, Before the Annapoorneshw construction of ari Nagar. brick wall, they marked as per the drawings. Curing is done regularly. Curing initiated within 24 hours of brickwork completion DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE 10-04-2025 Brick wall Brickwork done in Sir M.V construction is in English bond. Proper Layout, progress. And alignment and Behind Curing is done plumb maintained Parvathamma using spirit level and Ramaiah plumb bob. Curing Conventional is done regularly. Hall, Upkar Curing initiated Layout, within 24 hours of Annapoornes brickwork hwari Nagar. completion DATE DISCRIPTION OBSERVATION LOCATION SIGNATURE 11-04-2025 Brick wall Brickwork done Sir M.V construction is in in English bond. Layout, progress. And Proper alignment Behind Curing is done and plumb Parvathamma maintained using Ramaiah spirit level and Conventional plumb bob. Hall, Upkar Curing is done Layout, regularly. Curing Annapoornes initiated within 24 hwari Nagar. hours of brickwork completion