The document outlines the method statement for the steel structure work at Benghazi International Airport, detailing objectives, scope, work conditions, methodology, quality requirements, and safety analyses. It includes specific procedures for the erection of structural elements, quality control measures, and safety protocols to ensure a safe and efficient construction process. The document emphasizes the importance of proper planning, equipment usage, and adherence to safety standards throughout the project.

Uploaded by

sameh zezo
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views

Vdocuments.mx Method Statement for Structural Erection

The document outlines the method statement for the steel structure work at Benghazi International Airport, detailing objectives, scope, work conditions, methodology, quality requirements, and safety analyses. It includes specific procedures for the erection of structural elements, quality control measures, and safety protocols to ensure a safe and efficient construction process. The document emphasizes the importance of proper planning, equipment usage, and adherence to safety standards throughout the project.

Uploaded by

sameh zezo
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

BENGHAZI INTERNATIONAL AIRPORT PROJECT

METHOD STATEMENT FOR STEEL STRCTURE WORK


Doc. No.: SFA-WDEC-PR-MS-0011-00

METHOD STATEMENT FOR STACKING,


PRE-ASSEMBLY, ERECTION & INSPECTION.

OF STRUCTURAL WORK.

: PREPARED BY : APPROVED BY

ENG SAMEH ABDELAZIZ ENG MOSTAFA ELJILANI

1/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT

METHOD STATEMENT FOR STEEL STRUCURE WORK


Doc. No.: SFA-WDEC-PR-MS-0011-00
CONTENTS

1. INTRODUCTION
1.1 OBJECTIVE

1.2 SCOPE

2. WORK CONDITION
2.1 WORK ENVIRONMENT

2.2 ESTIMATED QUANTITY

2.3 SCHEDULE

2.4 SPECIAL TOOLS/ INSTRUMENTS

2.5 MANPOWER / EQUIPMENT

3. WORK METHODOLOGY

3.1 CONSTRUCTION PROCESS FLOW CHART

3.2 PROCESS METHODOLOGY

4. QUALITY REQUIREMENTS

5. SAFETY ANALYSIS

2/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT

METHOD STATEMENT FOR STEEL STRUCURE WORK


Doc. No.: SFA-WDEC-PR-MS-0011-00
1. INTRODUCTION
1.1 Objective:

The purpose of this work procedure is to detail for the Erection of Structure, that shall be
followed during the execution of the project.

1.2 Scope:

The procedure covers all activities related to Erection of Structure that shall be carried out
while the execution of the project.

2. WORK CONDITION:

2.1 Work Environment:

To under stand the scope of work and decide in how many lifts the main columns are to
be positioned. This will give us a fair under standing of the total height that is to be
achieved while erecting the structure.

2.2 Estimated Quantity:

Steel structure consisting of Main Columns, Beams & Bracings 0 mtrs to .2.2.1

.El _______ mtrs (top of the structure), consisting of approx. __________ MT +

2.3 Schedule:

A tentative work execution schedule (approved schedule) needs to be prepared which


.shall give us the insight of the work involved

2.4 Special Tools / Instruments:

2.4.1 . Theodolite - 1No. (for alignment & checking of


verticality of structure)
2.4.2. Torque Wrench - 1No.
2.4.3. Water level - 1 No.
2.4.4. Plumb - 1 No.

2.5 Manpower & Equipment:

Manpower Utilization:

2.5.1.1. Erection Engineer In-charge


2.5.1.2 Erection supervisor
2.5.1.3. Erection Foreman
2.5.1.4. Structural Fitter
2.5.1.5. Rigger
2.5.1.6. Khalasi
2.5.1.7. Welder
2.5.1.8. Helper
2.5.1.9. Gas cutter

3/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT

METHOD STATEMENT FOR STEEL STRUCURE WORK


Doc. No.: SFA-WDEC-PR-MS-0011-00
2.5.1 Equipment Utilization:

2.5.2.1. Crane to suit site requirements - __ Nos.


2.5.2.2. Hydra Crane - __ Nos.
2.5.2.3. Trailers - __ Nos
2.5.2.4. Welding M/c and other Tools & tackles - __ Nos.

3. WORK METHODOLOGY:

3.1 Construction Process Flow Chart:

Handing over of Packing plate level - Base plate level and


Foundation./Check Calculation & diagonal checking
Levels, & foundation bolt arrangement
position (correction if

Transportation of column Preparation of columns


and fitment of temporary Positioning of crane
 Centerline -marking
ladder. and making lifting
 Buffing arrangements.
 Selection of -Bolts
 Rectification of Damage if any.
 Check camber, Sag & etc.

Prepare the Tempary Sign. of Method


arrangement for changing Statement by RCM,
the sling after erection. Erection YES
Arrg. of Temp. Platforms Engineer & Safety
where ever reqd. Officer

NO

Lifting the columns


Further Process as per drawings

4/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT

METHOD STATEMENT FOR STEEL STRUCURE WORK


Doc. No.: SFA-WDEC-PR-MS-0011-00

3.2 Process Methodology:

3.2.1. General Procedure

3.2.1.1. Erection of structures such as column, beams, ladders, grating and


handrail shall be as per approved drawing.

3.2.1.2. Checking the verticality of column and center to center distance between
the columns.

3.2.1.3 QA & QC shall ensure the acceptance and prepare necessary


protocols for record purpose.

3.2.1.4. Tightening of base plate bolt and release for grouting as per specification

3.2.1.5. Structures required to be fitted in position shall be bolted / welded


properly.

3.2.1.6. Temporary Erection loads or permanent loads shall not be placed on any
incomplete portions of the structures being erected.

3.2.1.7. Temporary arrangements like providing jallis etc on the columns to facilitate
guiding and positioning of the structures and for removing of the slings.

3.2.1.8. All erection activity shall be as per schedule. To maintain this,


sequential material feeding to be ensured.

3.2.2. Foundation checking

3.2.2.1 All the structural erection activities shall be carried out after the approval /
clearance of the foundations by the customer representatives.

3.2.1.2. Ensure the bench marking is transferred to the foundation.

3.2.2.3. The civil foundations for the structural shall be checked for any defects. If
there is any defect the same shall be repaired before the erection of the
structural into the foundation. The top of the concrete level shall be
recorded.

3.2.2.4. The size of the bolts, no of nuts, height of the bolt and diagonal across the
bolt holes shall be checked and shall be recorded ( Documentation through
Protocol).

3.2.2.5. The dimension between consecutive foundations shall be checked and


recorded including the diagonal across of footings as per Foundation plan.

3.2.2.6. The condition of the foundation bolt shall be checked before the
commencement of the erection.

5/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT

METHOD STATEMENT FOR STEEL STRUCURE WORK


Doc. No.: SFA-WDEC-PR-MS-0011-00
3.2.3. Preparation for lifting
3.2.3.1 Crane of suitable capacity along with all the necessary accessories shall be
employed for the erection purpose. It shall be ensured that the crane used
shall be in possession of all the safety requirements as emphasized.

3.2.3.2 To ensure having the valid crane load test certificate at site. The location of
crane and trailer positioning shall be clearly marked, prior to receiving the
structural material at site.

3.2.3.3 The lifting zones to be clearly identified in the rigging plan.

3.2.3.4 Latest revision drawing for the structure that is to be erected shall be made available
at site for ready references.

3.2.3.5 The tools and tackles will be checked for the availability of the required quantity as
per checklist.

3.2.3.6 The valid test certificates for the rigging equipments, tools and tackles shall be
ensured for the lifting requirements.

3.2.3.7 It shall be ensured that the necessary permits from Safety Engineer, Customer and
Consultant for erection are obtained prior to the commencement of the works.

3.2.3.8. Ensure the back filling is done and the area is workable as well as approachable for
working.

3.2.4. Erection of the Steel Structure

3.2.4.1 All the transporting/maneuvering/lifting operation shall be carried out under the sole
control of the designated ELWASEAD Execution Engineer / Foreman assisted by
qualified crew of the erection contractor.

3.2.4.2 Vertical columns shall be lowered on to the respective foundations, and the same
shall be aligned and in next level the vertical columns should anchored with guy
rope.

3.2.4.3 Horizontal beams shall be erected in a single piece to an extent as much as


possible. The beams shall be leveled and the top of structure elevation shall be
checked and recorded.

3.2.4.4 Ensure horizontal bracings are erected to make frame in each level before next level
of vertical column erection.

3.2.4.5 After the positioning of all the structural elements, including vertical and horizontal
bracings, the final connection shall be carried out by Bolting / welding.

3.2.4.6 If any alterations are to be carried out, then prior approval to be sought from the
Customer / Consultant before taking up the work.

3.2.4.7 After the final positioning, bolting and welding (if required) is completed, the
Structure shall be offered for Inspection to ELWAEAD QA/QC department,
Customer / Consultant representatives.

3.2.4.8 Ensure proper landing plat form is available and approachable safety.

6/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT

METHOD STATEMENT FOR STEEL STRUCURE WORK


Doc. No.: SFA-WDEC-PR-MS-0011-00

3.2.4.9 Touch up painting shall be carried out for the damaged areas and also for the
welded areas (if required).

4. QUALITY REQUIREMENTS

Quality requirements are to be written down prior to the starting the job in the FQP. The
same should get approved by all concerned. Ensuring that all the FQ requirements are
adhered is the responsibility of the FQ Engineer.

Work Procedure for Electrodes Baking / Issue

Scope:

Associated with the baking and issue of welding electrodes to be used on job, objective of
this procedure is to set the guidelines for surveillance activities structural welds etc. as
recommended by the manufacturer.

Responsibility

It is the responsibility of the Storekeeper /Welding engineer / QA & QC Engineer to ensure


proper baking and documentations.

Procedures

Ensure correct size of electrodes are procured and put in the baking oven.
Electrode packages (cartoons) shall be opened only when they are required for use.

While handling the electrodes during opening of packages, baking, holding, issue and
welding, avoid contact of oil, grease, dirt with electrodes. Do not use oily, dirty or wet gloves
and do not lay the electrodes directly on ground or in any humid place. Ensure that not more
than two days requirements of electrodes are baked at a time.

Keep the issue indents and issue register updated.

Baking and holding of electrodes

Identify baking and holding ovens separately.

Ovens shall have temperature control facility up to 350-400 deg C and 200 deg C for
baking and holding ovens respectively.
Calibrated thermometer shall be provided on each oven for monitoring temperature.

On opening a packet of electrodes, place the electrodes inside the compartment of

7/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT

METHOD STATEMENT FOR STEEL STRUCURE WORK


Doc. No.: SFA-WDEC-PR-MS-0011-00

baking oven identified for the particular type and size of electrode. A log book shall be
maintained to cover all relevant parameters like time of loading electrodes in oven,.
temperatures achievement time, baking completion time etc involved in the baking of the
electrodes

Portable Ovens

Each welder shall be provided with one portable drying oven, which shall also used
to carry electrodes from stores to the place of work. Only one type of electrode
shall kept in the portable oven.

All portable ovens when in use shall be properly energized to maintain a uniform
temperature of 100 deg C.

While in use, only limited electrodes shall be permitted to be taken out of the portable oven.
Unused cold electrode, if left at the site, shall be properly identified and moved to baking
oven for re-drying. Unidentifiable / damaged / improperly maintained electrodes shall be
removed from all working areas and disposed. All electrodes being issued to welders shall
be through “electrodes issue voucher” only. This shall contain details like welder No., WPS
No., electrodes specification, size and the issued quantity, and duly authorized by the
welding supervisor.

Welder Qualification

Scope
This procedure is meant to highlight the minimum requirement for qualification of welders.

Reference

ASME sec IX – 1998 welding and brazing qualification / IS – 816.

Responsibility

It is the responsibility QA & QC engineer for qualifying the welder and issue the identity card
before deploying them on job.

Procedure

QA & QC engineer shall request to witness to client/ consultant 24 hours in advance


indicating the welders name and location for testing.

Before testing the welders, his present and past experience on similar nature of job
shall be checked by scrutinizing his experience certificates.

The necessary tools / Equipments shall be ensured for the inspection during testing.
The root welding to be inspected by QA & QC engineer and upon finding acceptable
the welder are allowed to complete the work piece. Client / Consultant may witness
the test piece.

The welder test piece is inspected for final weld visual quality and if satisfied, suitable
identification / stamping shall be done prior to NDT / DPT.

The record of all events / parameters of welders test shall be kept during the test, as
per recommended format.

8/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT

METHOD STATEMENT FOR STEEL STRUCURE WORK


Doc. No.: SFA-WDEC-PR-MS-0011-00

SAFETY ASPECTS TO BE TAKEN UP WHILE EXECUTING THE JOB:

Sl. JOB STEPS HAZARD/REACTIO CONTROL & CHECK ACTION


No N TO FAILURE REQUIRED BY
01 Transportation -Fabricated member -All lifting tools & tackles
of fabricated loaded on trailer or and crane or hydra - Fleet I/C
member from transported by hydra should be in good
material Yard may hit to person on condition & certified by
to erection road or at the time of competent person.
site. loading.
-Regular checking of
-Failure of crane or moving vehicle
tool & tackles. - Erection
-A transportation Engineer
-Fall of materials supervisor to be made
responsible to guide the
- Hit injury. trailer & alert people
during transportation.
- Rigging
- Proper sling or belt Foreman
should be used while
lifting and shifting the
loads.

-Tag line to be tied to the


member being shifted
and guided by two people
with the help of guide
rope.

-Avoid lifting members in


bunch.

- Area should be
barricaded.

-Always use all the


required PPE’s.

- Proper stacking of
material should be done.

02 Crane - Hit injury - Proper crane to be


placement selected as per the road -Fleet I/C
- Crane failure condition & erection
procedure.
- Collapse of road -Area is to be cordoned
off
03 Erection of - Fall of person from - Fixed ladder should be - Erection
column / tie man basket( jhula) or checked for soundness Engineer
beam / fixed ladder by rigger foreman before
bracing / starting of work.
vertical
bracing / - Fall of material. - Person working on the - Rigging

9/15
platform / man basket should Foreman
handrail by anchor his safety belt on
the use of rigid material or lifeline.
crane & man
basket (jhula). - No person allowed to
work without safety
belt/lifeline.

- Only designated signal


man should give the
signals to the crane
operator.

- Always use required


PPEs

04 Other activity - Fall of person or - Ensuring proper - Erection


(bolt material due to scaffolding / jallies before Engineer
tightening / displacement of taking up any erection
welding / gas members or loose activity at height.
cutting / bolt or tack weld.
grinding - If working at height,
during - Fire & explosion make sure that the area
erection. hazard below this is cordoned
off.
- Eye injury.

05 Guide rope - Fall of structure - Wire rope of atleast - Rigging


tying for without proper tying 16mm dia to be tied with Foreman
columns. with uniform load column for proper
distribution. anchoring of the column
before releasing of crane
upon erection.

06 Area lighting - Improper area - Proper & adequate area - Safety


at erection lighting lighting to be provided Engineer./
site. - Fall hazard before taking up any Electrical
night activity. Engineer
- Ensure that job at height
is taken up at the time of
rain

07 GRINDING - Breakage of wheels - To ensure that Grinding - Erection


AT HEIGHT machine wheel guard is Engineer
- Contact with wheel in position while in use.
- Start the while in use.
machine - Grinding wheel ‘RPM’ to
- flying particles. be checked & condition of
grinding wheel is to be
- Dust hazard checked

- Fire hazard - Face shield / Safety


goggles to be used
- Scaffold collapse
- Leather hand gloves to
be ensured

- Plug top is to be
ensured

10/15
- Ensure that the power
connection is made
through ‘ELCB’

08 WELDING -Electrical shock - Ensure that the power - Erection


connection is made Engineer
- Fire hazard through ‘ELCB’
- Rigging
- Arc eye - Proper main earthling & foreman
body earthling are to be
- Unauthorized entry ensured

- Safety
- Protection Shed/cover is Engineer /
to be provided for welding Electrical
machine. Position the engineer
welding machines at a
elevated position to avoid - Safety
coming in contact with Engineer.
water.

- Welding job to be done


on dry surface

- Cable condition is to
be checked &Leather
hand gloves to be used

-To ensure availability of


Portable fire extinguisher
(CO2 / DCP)
-Proper housekeeping is
to be maintained

-welding shield is to be
used

-Area is to be cordoned
off
-Proper warning board is
to be displayed

09 GAS - Leakage in the hose - Hose joints to be - Erection


CUTTING checked by using soap Engineer
solution & hose clamps
are to be used
- Rigging
-Flash back -Flash arrestor is to be foreman
ensured at both torch end
-Back fire & cylinder end - Safety
Engineer
-Falling of cylinders -Correct size nozzle is to
be ensured
-Fire hazard
-Proper clearance is to be
- Unauthorized entry maintained between job
& nozzle

11/15
-Condition of regulator,
hose & torch to be
checked

-Proper house keeping is


to be maintained

-Stone lighter is to be
used

-Fire extinguisher is to be
kept ready

- Area to be cordoned off.

12/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT

METHOD STATEMENT FOR STEEL STRUCURE WORK Doc. No.: SFA-


WDEC-PR-MS-0011-00

COLOUMN PRE‐ASSAMBLY ( TYP )

FOUNDATION
(TYP)

13/15
Lifting Plate

Plumb
Piano Wire
Container with
waste Oil.
Guy
Rope

COLUMN VERTICALITY CHECKING ( TYP )

14/15
3/15