Vdocuments.mx Method Statement for Structural Erection
Vdocuments.mx Method Statement for Structural Erection
OF STRUCTURAL WORK.
: PREPARED BY : APPROVED BY
1/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT
1. INTRODUCTION
1.1 OBJECTIVE
1.2 SCOPE
2. WORK CONDITION
2.1 WORK ENVIRONMENT
2.3 SCHEDULE
3. WORK METHODOLOGY
4. QUALITY REQUIREMENTS
5. SAFETY ANALYSIS
2/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT
The purpose of this work procedure is to detail for the Erection of Structure, that shall be
followed during the execution of the project.
1.2 Scope:
The procedure covers all activities related to Erection of Structure that shall be carried out
while the execution of the project.
2. WORK CONDITION:
To under stand the scope of work and decide in how many lifts the main columns are to
be positioned. This will give us a fair under standing of the total height that is to be
achieved while erecting the structure.
Steel structure consisting of Main Columns, Beams & Bracings 0 mtrs to .2.2.1
2.3 Schedule:
Manpower Utilization:
3/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT
3. WORK METHODOLOGY:
NO
4/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT
3.2.1.2. Checking the verticality of column and center to center distance between
the columns.
3.2.1.4. Tightening of base plate bolt and release for grouting as per specification
3.2.1.6. Temporary Erection loads or permanent loads shall not be placed on any
incomplete portions of the structures being erected.
3.2.1.7. Temporary arrangements like providing jallis etc on the columns to facilitate
guiding and positioning of the structures and for removing of the slings.
3.2.2.1 All the structural erection activities shall be carried out after the approval /
clearance of the foundations by the customer representatives.
3.2.2.3. The civil foundations for the structural shall be checked for any defects. If
there is any defect the same shall be repaired before the erection of the
structural into the foundation. The top of the concrete level shall be
recorded.
3.2.2.4. The size of the bolts, no of nuts, height of the bolt and diagonal across the
bolt holes shall be checked and shall be recorded ( Documentation through
Protocol).
3.2.2.6. The condition of the foundation bolt shall be checked before the
commencement of the erection.
5/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT
3.2.3.2 To ensure having the valid crane load test certificate at site. The location of
crane and trailer positioning shall be clearly marked, prior to receiving the
structural material at site.
3.2.3.4 Latest revision drawing for the structure that is to be erected shall be made available
at site for ready references.
3.2.3.5 The tools and tackles will be checked for the availability of the required quantity as
per checklist.
3.2.3.6 The valid test certificates for the rigging equipments, tools and tackles shall be
ensured for the lifting requirements.
3.2.3.7 It shall be ensured that the necessary permits from Safety Engineer, Customer and
Consultant for erection are obtained prior to the commencement of the works.
3.2.3.8. Ensure the back filling is done and the area is workable as well as approachable for
working.
3.2.4.1 All the transporting/maneuvering/lifting operation shall be carried out under the sole
control of the designated ELWASEAD Execution Engineer / Foreman assisted by
qualified crew of the erection contractor.
3.2.4.2 Vertical columns shall be lowered on to the respective foundations, and the same
shall be aligned and in next level the vertical columns should anchored with guy
rope.
3.2.4.4 Ensure horizontal bracings are erected to make frame in each level before next level
of vertical column erection.
3.2.4.5 After the positioning of all the structural elements, including vertical and horizontal
bracings, the final connection shall be carried out by Bolting / welding.
3.2.4.6 If any alterations are to be carried out, then prior approval to be sought from the
Customer / Consultant before taking up the work.
3.2.4.7 After the final positioning, bolting and welding (if required) is completed, the
Structure shall be offered for Inspection to ELWAEAD QA/QC department,
Customer / Consultant representatives.
3.2.4.8 Ensure proper landing plat form is available and approachable safety.
6/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT
3.2.4.9 Touch up painting shall be carried out for the damaged areas and also for the
welded areas (if required).
4. QUALITY REQUIREMENTS
Quality requirements are to be written down prior to the starting the job in the FQP. The
same should get approved by all concerned. Ensuring that all the FQ requirements are
adhered is the responsibility of the FQ Engineer.
Scope:
Associated with the baking and issue of welding electrodes to be used on job, objective of
this procedure is to set the guidelines for surveillance activities structural welds etc. as
recommended by the manufacturer.
Responsibility
Procedures
Ensure correct size of electrodes are procured and put in the baking oven.
Electrode packages (cartoons) shall be opened only when they are required for use.
While handling the electrodes during opening of packages, baking, holding, issue and
welding, avoid contact of oil, grease, dirt with electrodes. Do not use oily, dirty or wet gloves
and do not lay the electrodes directly on ground or in any humid place. Ensure that not more
than two days requirements of electrodes are baked at a time.
Ovens shall have temperature control facility up to 350-400 deg C and 200 deg C for
baking and holding ovens respectively.
Calibrated thermometer shall be provided on each oven for monitoring temperature.
7/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT
baking oven identified for the particular type and size of electrode. A log book shall be
maintained to cover all relevant parameters like time of loading electrodes in oven,.
temperatures achievement time, baking completion time etc involved in the baking of the
electrodes
Portable Ovens
Each welder shall be provided with one portable drying oven, which shall also used
to carry electrodes from stores to the place of work. Only one type of electrode
shall kept in the portable oven.
All portable ovens when in use shall be properly energized to maintain a uniform
temperature of 100 deg C.
While in use, only limited electrodes shall be permitted to be taken out of the portable oven.
Unused cold electrode, if left at the site, shall be properly identified and moved to baking
oven for re-drying. Unidentifiable / damaged / improperly maintained electrodes shall be
removed from all working areas and disposed. All electrodes being issued to welders shall
be through “electrodes issue voucher” only. This shall contain details like welder No., WPS
No., electrodes specification, size and the issued quantity, and duly authorized by the
welding supervisor.
Welder Qualification
Scope
This procedure is meant to highlight the minimum requirement for qualification of welders.
Reference
Responsibility
It is the responsibility QA & QC engineer for qualifying the welder and issue the identity card
before deploying them on job.
Procedure
Before testing the welders, his present and past experience on similar nature of job
shall be checked by scrutinizing his experience certificates.
The necessary tools / Equipments shall be ensured for the inspection during testing.
The root welding to be inspected by QA & QC engineer and upon finding acceptable
the welder are allowed to complete the work piece. Client / Consultant may witness
the test piece.
The welder test piece is inspected for final weld visual quality and if satisfied, suitable
identification / stamping shall be done prior to NDT / DPT.
The record of all events / parameters of welders test shall be kept during the test, as
per recommended format.
8/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT
- Area should be
barricaded.
- Proper stacking of
material should be done.
9/15
platform / man basket should Foreman
handrail by anchor his safety belt on
the use of rigid material or lifeline.
crane & man
basket (jhula). - No person allowed to
work without safety
belt/lifeline.
- Plug top is to be
ensured
10/15
- Ensure that the power
connection is made
through ‘ELCB’
- Safety
- Protection Shed/cover is Engineer /
to be provided for welding Electrical
machine. Position the engineer
welding machines at a
elevated position to avoid - Safety
coming in contact with Engineer.
water.
- Cable condition is to
be checked &Leather
hand gloves to be used
-welding shield is to be
used
-Area is to be cordoned
off
-Proper warning board is
to be displayed
11/15
-Condition of regulator,
hose & torch to be
checked
-Stone lighter is to be
used
-Fire extinguisher is to be
kept ready
12/15
BENGHAZI INTERNATIONAL AIRPORT PROJECT
FOUNDATION
(TYP)
13/15
Lifting Plate
Plumb
Piano Wire
Container with
waste Oil.
Guy
Rope
14/15
3/15