1. Describe the principles of scientific management in brief.
2. List out objectives and applications of industrial engineering.
3. Define productivity. What are different kinds of productivity measures?
4. Explain briefly about Douglas McGregor theory X and theory Y on
motivation with assumptions.
5. Briefly explain the development of industrial engineering.
6. State the difference between PERT and CPM.
7. Name the different types of organizations. Describe the line and staff
organization with the help of line diagram and discuss its advantages and
disadvantages.
8. Write short note the following:
i) Reengineering
ii) MBO
iii) Scheduling
9. What is PERT? Define optimistic time, pessimistic time and most likely
time.
13. The following data gives the information about duration and cost
of various activities in project network.
Activity Normal Normal Crash Crash
duration(weeks) cost(in Rs.) duration(weeks) cost(in
Rs.)
1-2 4 4000 2 12000
2-3 5 3000 2 7500
2-4 7 3600 5 6000
3-4 4 5000 2 10000
The project overhead cost are Rs.2000 per week. Find the optimum
duration and cost associated with it Also draw least cost network.
14. Find the critical path of the following project after drawing the
complete PERT network.
Activity Precedence Pessimistic Optimistic Most likely
activity time time time
A --- 2 6 4
B --- 1 5 3
C A 4 6 5
D C 4 10 7
E B 5 7 6
F E 1 3 2
G E 2 2 2
H F 3 7 5
I G 3 9 6
J D,H,I 2 12 4
What is probability that the programme will be completed? Calculate
the standard deviation and expected project length.