Risk Management
Risk Management
1.Nature of Application
2.Experience of Staff
3.Quality of plan
4.Requirements- software and hardware
2.RISK ASSESSMENT
• A systematic process of evaluating the potential risks that may be involved in a projected activity
or undertaking.
• Risk exposure for every risk has to be calculated with the probability of occurrence.
➢ Risk exposure is expected loss due to a risk and it is defined as
Risk exposure = (probability of occurrence) X (value of damage)
OR
Risk exposure = Probability of Risk × Impact of Risk
• Probability of Risk: The likelihood that the risk will happen
• Impact of Risk: The estimated cost or loss if the risk occurs
FEW RISK EXPOSURE ASSESSMENTS ARE
❖ Risk prevention:-some risks can be prevented from occurring and can be reduced. Example:-risk of staff
being unavailable for meeting can be reduced by early scheduling.
❖ Risk acceptance: A risk that has already occurred according to the prioritization process cannot be
avoided. Accept the risk that happens and minimizes the damage and the costs of action.
❖ Risk avoidance: Some risks that happen regularly can be categorized and avoided before it occurs.
❖ Risk reduction: Risk reduction attempts to reduce the occurrence of risk whereas risk mitigation ensures
that the risk impact is much lesser when actually occurs.
Example: Earthquake
❖ Risk transfer: Certain complex risks can be transferred to other organizations where experienced
professionals can carry out the possibility of its occurrence.
RISK MONITORING
➢ Risk monitoring is a planned process of assessing whether the predicted risks occur or
not.
➢ It also collects information of the future risk analysis and attempts to determine what
has caused the particular risk.
EVALUATING RISKS USING PERT(PROGRAM
EVALUATION AND REVIEW TECHNIQUE):-
• It helps to analyze the project work schedule by focusing on each task and calculate the
minimum time required to complete the project.
❖It is a technique in which planning, scheduling, organizing, coordinating and
controlling of uncertain activities is done.
• It is similar to the Critical Path Method (CPM), but instead of using single estimation for
duration of each task, PERT requires 3 estimates:-
• Most likely time (m)=>expected time taken by task to complete under normal circumstances.
• Optimistic time(a) => the shortest time to complete the activity.
• Pessimistic time(b)=> worst possible time to complete the activity.
• PERT then combines these three estimates to form a single expected
duration
Estimated time( Te)=( a+4m+b)/6
Standard deviation(s)
• measures the uncertainty or risk in the time estimate of a task.
• s =(b-a)/6
• Smaller s → task duration is more predictable.
• Larger s → task duration is less predictable/riskier
VARIANCE= Square of s
HOW TO DRAW PERT CHART
activity_name 2
1
duration
• PERT is based on AOA(activity on arrow).
• Arrow shows dependency.
• Tasks are ranked on priority basis.
QUESTION
ANSWER
CALCULATING THE Z VALUES
It is event-oriented technique which means that It is activity-oriented technique which means that
Orientation
network is constructed on the basis of event. network is constructed on the basis of activities.
Nature of Job It has Non-repetitive nature of job. It has repetitive nature of job.
There is no chance of crashing as there is no There may be crashing because of certain time
Crashing
certainty of time. bound.