0% found this document useful (0 votes)
17 views

WaterTank Platform

This document outlines the conditions and responsibilities for contractors using the provided design drawing for construction of a water tank supporting structure. It specifies requirements for welding, steel grades, safety measures during construction, and the need for detailed fabrication drawings. The contractor is responsible for ensuring structural stability and compliance with the guidelines set forth in the document.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views

WaterTank Platform

This document outlines the conditions and responsibilities for contractors using the provided design drawing for construction of a water tank supporting structure. It specifies requirements for welding, steel grades, safety measures during construction, and the need for detailed fabrication drawings. The contractor is responsible for ensuring structural stability and compliance with the guidelines set forth in the document.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

USE OF THIS DRAWING FOR CONSTRUCTION SHALL

EXPLICITLY CONFIRM ACCEPTANCE OF FOLLOWING


1. THIS IS A DESIGN DRAWING. CONDITIONS BY CONTRACTOR.
2. EMBEDMENT LENGTH AS SPECIFIED BY HILTI. 1. OUR RESPONSIBILITY SHALL REMAIN LIMITED TO SAFE AND SOUND
3. THROAT THICKNESS OF WELD SHOULD NOT BE LESS THAN STRUCTURAL DESIGN AS TRANSMITTED BY THIS DRAWING AND WE
0.707 X WELD SIZE. SHALL NOT REMAIN RESPONSIBLE FOR
4. UNO PROVIDE 6 MM WELD ALL AROUND ALL EDGES. a) SAFETY OF OLD STRUCTURE DURING DEMOLITION.
5. ALL STRUCTURAL STEEL MUST BE PAINTED WITH ANTI b) SAFETY OF ANY ADJOINING BUILDING /PERSONS STAYING IN ADJOINING
CORROSION PAINT/GALVANIZED AS PER CLIENT BUILDING/PERSONS & PROPERTIES ON ADJOINING ROADS.
SPECIFICATION. c) SAFETY OF CONSTRUCTION WORKER/ANY PERSONNEL AT WORK SITE
6. FOR 3, 5, 6, 8, 10, 12 MM SIZE OF WELD, STRENGTH OF WELD DURING CONSTRUCTION
SHOULD BE MIN. 230, 385, 460, 615, 770, 930 N/MM RESPTY.
d) CORRECTNESS/SAFETY OF ANY TEMPORARY STRUCTURE, SCAFFOLDING,
7. REFER "ESAB" USA 2016 MANUAL OF WELDING FILLER METAL
SHUTTERING, CENTERING ERECTED @ SITE AND ANY INJURY TO ANY
DATA BOOK FOR THE WELDING DETAILS. PERSONNEL ARISING OUT OF THEIR ACCIDENTS.
8. PROVIDE WELD LENGTH AS MUCH POSSIBLE AT ALL THE
e) ACCIDENT OCCURRING DUE TO PREMATURE DESHUTTERING
PLACES UNO.
FAULTY/SUBSTANDARD CONSTRUCTION MATERIAL OR WORKMANSHIP/
9. USE PACKING PLATE OF YST 250 WHENEVER REQUIRED.
FAULTY CONSTRUCTION PROCEDURE.
10. CLOSE ALL ENDS OF HOLLOW SECTION BY 5 MM THK PLATE.
11. ANCHORING OF HILTI ANCHORS MUST BE DONE ON SITE, AS f) ANY ACCIDENT OCCURRING DUE TO CONSTRUCTION OF ELEMENTS OF
PER HILTI GUIDELINES. BUILDINGS NOT DESIGN BY US. MATERIAL OR WORKMANSHIP/FAULTY
12. THE CONTRACTOR SHOULD STUDY IT, GET AQUAINTED WITH IT CONSTRUCTION PROCEDURE.
AND PREPARE A DETAILED FABRICATION DRAWING FOR 2) SUPERVISION IF SPECIFICALLY ASKED FOR WILL BE PROVIDED TO THE
SUBMISSION TO ENGINEER. THE DRAWING SHOULD BE EXTENT OF VERIFICATION OF REINFORCEMENT ON SITE BUT
REVISED BASED ON COMMENTS FROM ENGINEER FOR FINAL RESPONSIBILITY REGARDING CORRECT & SOUND CONSTRUCTION
SUBMISSION. THE WORK SHOULD BE DONE AS PER ACTUAL SHALL SOLELY REST WITH CONTRACTOR/ BUILDER / OWNER.
LAYOUT DONE AT SITE AND FABRICATION DRAWING DULY
NOTE-1
APPROVED BY THE ENGINEER.
FORMS SHALL NOT BE RELEASED UNTIL THE CONCRETE HAS ACHIEVED
13. DIMENSIONS ON DRAWING TO BE CHECKED AT SITE. STRENGTH OF AT LEAST TWICE THE STRESS TO WHICH THE CONCRETE
14. FABRICATION TO START AFTER MAKING FULL SCALE LAYOUT MAY BE SUBJECTED AT THE TIME OF REMOVAL OF FORMWORK. THE
AT SITE. STRENGTH REFERRED TO SHALL BE THAT OF CONCRETE USING THE
15. STABILITY OF THE STRUCTURE DURING ERECTION IS SAME CEMENT & AGGREGATES & ADMIXTURE, IF ANY, WITH THE SAME
CONTRACTORS RESPONSIBILITY. PROPORTIONS & CURED UNDER CONDITIONS OF TEMPERATURE &
16. PROVIDE SEATING ANGLE/ CLEATS IF REQUIRED TO BE MOISTURE SIMILAR TO THOSE EXISTING ON THE WORK.
PROVIDED AS PER CONVINIENCE.
NOTE-2
17. PREPARATION OF FABRICATION DRAWINGS IS IN
WHILE THE ABOVE CRITERIA MENTIONED IN NOTE-1 OF STRENGTH
CONTRACTOR'S SCOPE.
SHALL BE THE GUIDING FACTOR FOR REMOVAL OF FORMWORK, IN
18. STEEL GRADES TO BE FOLLOWED AS FOLLOWS:
NORMAL CIRCUMSTANCES WHERE AMBIENT TEMPERATURE DOES NOT
HOT ROLLED SECTIONS YST = 250 MPA FALL BELOW 15°C AND WHERE ORDINARY PORTLAND CEMENT IS USED
PLATE YST = 250 MPA AND ADEQUATE CURING IS DONE, FOLLOWING STRIKING PERIOD MAY BE
BOLTS 8.8 GRADE FOLLOWED (EVEN FOR CONCRETE HAVING A FLY ASH CONTENT OF
UP TO 30%
TYPE OF FORMWORK/ PART OF STRUCTURE:
1) WALLS, COLUMNS AND VERTICAL SIDES OF BEAMS : 48 HOURS
2) SLABS (PROPS LEFT UNDER) : 3 DAYS
(PROPS TO BE REFIXED IMMEDIATELY AFTER REMOVAL OF FORMWORK)
3) BEAM SOFFITS (PROPS LEFT UNDER) : 7 DAYS
(PROPS TO BE REFIXED IMMEDIATELY AFTER REMOVAL OF FORMWORK)
4) REMOVAL OF PROPS UNDER SLABS
A) SPANNING UP TO 4.5M : 7 DAYS
B) SPANNING OVER 4.5M : 14 DAYS
5) REMOVAL OF PROPS UNDER BEAMS
A) SPANNING UP TO 6M : 14 DAYS
B) SPANNING OVER 6M : 21 DAYS

NOTES :

ELEVATION ON GRID A & B ELEVATION ON GRID 1 & 2

REFERENCE DRAWINGS

DRAWING TO BE VALIDATED BY ARCHITECT ON RECORD


WITH APPROVED PLANS FROM THE REGULATING LOCAL
GOVERNMENT AUTHORITY.
DRAWING IS VALID FOR DESIGN ADEQUACY,
PROVIDED IT IS SIGNED & STAMPED BY OUR OFFICE
TYP. BRACING CONNECTION DETAIL ARCHITECT :

CLIENT :

PURPOSE OF ISSUING THIS DRAWING

FRAMING PLAN

BASE PLATE DETAIL STRUCTURAL CONSULTANT :


TYP. FDN BOLT DETAIL . Shubham Devlekar
FOUNDATION LEVEL PLAN

PROJECT : PROPOSED WATER TANK SUPPORTING


STRUCTURE

STRUCTURE : WATER TANK SUPPORTING STEEL STRUCTURE

DRG. TITLE : STRUCTURAL


FOUNDATION &DRAWING
STEEL FRAMING
OF PROPOSED
LAYOUTWATER
& DETAILS
PLAN BRACING LOCATION TYP. BEAM CONNECTION TANK SUPPORTING STRUCTURE
DRG. NO. SHEET :01/01
ACCESS LADDER LOCATION AND DETAILS AS PER VENDOR
001 REV. - R0
TYP. COLUMN FOOTING DETAILS DATE SCALE DRAWN DESIGNED CHECKED

You might also like