0% found this document useful (0 votes)
1 views

Scheduling problem

The document provides information on project activities, including their durations and the calculation of earliest start (ES), earliest finish (EF), latest start (LS), and latest finish (LF) times for each activity. It includes a table summarizing these calculations for activities labeled A through K. Additionally, it highlights critical activities that have no float time.

Uploaded by

AmitSengupta
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1 views

Scheduling problem

The document provides information on project activities, including their durations and the calculation of earliest start (ES), earliest finish (EF), latest start (LS), and latest finish (LF) times for each activity. It includes a table summarizing these calculations for activities labeled A through K. Additionally, it highlights critical activities that have no float time.

Uploaded by

AmitSengupta
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

JADAVPUR UNIVERSITY

Name: BITHI DEBNATH Class Roll No.: 002010803010

Example – 14.4 Information on the activities for a project is as follows:


Name A B C D E F G H I J K
Activities Node 1-2 1-3 1-4 2-5 3-5 3-6 3-7 4-6 5-7 6-8 7-8
Duration (Days) 2 7 8 3 6 10 4 6 2 5 6
Draw the network and calculate the Earliest start (ES), earliest finish (EF), Latest start (LS), latest finish (LF) times
of each of the activities

5
2

3 8
1

4 6

Table Determination of earliest and latest times

Activities Duration Earliest Latest Float


i-j Name t Start Finish Start Finish EST-LST
1-2 A 2 0 2 9 11 9
1-3 B 7 0 7 0 7 0 Critical
1-4 C 8 0 8 3 11 3
2-5 D 3 2 5 11 14 9
3-5 E 6 7 13 8 14 1
3-6 F 10 7 17 7 17 0 Critical
3-7 G 4 7 11 12 16 5
4-6 H 6 8 14 11 17 3
5-7 I 2 13 15 14 16 1
6-8 J 5 17 22 17 22 0 Critical
7-8 K 6 15 21 16 22 1
JADAVPUR UNIVERSITY

Example – 14.4 Information on the activities for a project is as follows:


Name A B C D E F G H I J K
Activities Node 1-2 1-3 1-4 2-5 3-5 3-6 3-7 4-6 5-7 6-8 7-8
Duration (Days) 2 7 8 3 6 10 4 6 2 5 6
Draw the network and calculate the Earliest start (ES), earliest finish (EF), Latest start (LS), latest finish (LF) times
of each of the activities

5
2

K6 [15,21]
G4 [7,11] 8
3 7
1 [12,16] [16,22]

4 6

Table Determination of earliest and latest times

Activities Duration Earliest Latest Float


i-j Name t Start Finish Start Finish EST-LST
1-2 A 2 0 2 9 11 9
1-3 B 7 0 7 0 7 0 Critical
1-4 C 8 0 8 3 11 3
2-5 D 3 2 5 11 14 9
3-5 E 6 7 13 8 14 1
3-6 F 10 7 17 7 17 0 Critical
3-7 G 4 7 11 12 16 5
4-6 H 6 8 14 11 17 3
5-7 I 2 13 15 14 16 1
6-8 J 5 17 22 17 22 0 Critical
7-8 K 6 15 21 16 22 1

Name: AKASH KUMAR MONDAL Class Roll No.: 002010803004


Example- 14.4 Information on the activities for a project is as follows
Name A C D E G H K
Activities Node 1-2 1-3 1-4 2-5 3-5 3-6 3-7 4-6 5-7 6-8 7-8
Duration (Days) 2 8 3 6 10 6 2 5 6
Drawthe network and calculate the Earliest start (ES), earliest finish (EF), Latest start (LS), latest finish (LF)
times of each of the activities

A2 [0,2]
[9,11] D3 (2,5]
(11,14)
B7
(0,7]
[0,71 E6
(7,13]

(8,14)
IsT'ET]I9T'
Z1tt]

[C&
0,8] K6[15,21]
(3,1 ] G4 (7,11] [16,22]

[12,16]

F10 [7,17) J 5
[ 1 7 , 2 2 ]

(17,22)

[7,17]
H6 [8,14]
[11,17]

Table Determination of earliest and latest times

Activities Duration Earliest Latest Float


Name
i-j Start Finish Start Finish EST-LST
1-2 A 2 0 2 9 |oomo
11nno o
1-3 B 7 7 7 Critical
1-4 C 8 11 3
2-5 D. 3 2 5 11 14
3-5 E 6 7 13 8 14 1
3-6 F 10 7 17 7 17 Critical
3-7 4 7 11 12 16
4-6 6 14 11 17 3
5-7 2 13 15 14 16 1
6-8 J 5 17 22 17 22 Critical
7-8 6 15 21 16 22 1

Amit Sengupta, Roll 32


Tapas Bhattacharya
BEE (Evening), 5th Year 2nd Semester, Roll No – 002010803009

Problem Statement - Draw the network and calculate the earliest start (ES), earliest finish (EF), Latest start (LS),
latest finish (LF) times of each of the activities.

Example - 14.4 Information on the activities for a project is as follows;


Name A B C D E F G H I J K
Activities Node 1-2 1-3 1-4 2-5 3-5 3-6 3-7 4-6 5-7 6-8 7-8
Duration (Days) 2 7 8 3 6 10 4 6 2 5 6

Determination of ES, EF, LS and LF:

Activities Duration Earliest Latest Float


¡-j t-ij Start Finish Start Finish Total Int. Free Ind Remarks
(ES) (EF) (LS) (LF) F-t F-int F-f F-ind
1-2 2 0 2 9 11 9 9 0 0
1-3 7 0 7 0 7 0 0 0 0 Critical Path
1-4 8 0 8 3 11 3 3 0 0
2-5 3 2 5 11 14 9 1 8 0
3-5 6 7 13 8 14 1 1 0 0
3-6 10 7 17 7 17 0 0 0 0 Critical Path
3-7 4 7 11 12 16 5 1 4 4
4-6 6 8 14 11 17 3 0 3 0
5-7 2 13 15 14 16 1 1 0 0
6-8 5 17 22 17 22 0 0 0 0 Critical Path
7-8 6 15 21 16 22 1 0 1 0

You might also like