Project Management PPT
Project Management PPT
Management
(MGMT 3192)
2/12/2025 1
Chapter one
General introduction about
project
1.1. Meaning and Definition of
Project
What is project?
• Project is in general a building block of an
investment plan.
• A project can be described as a combination
of human and material resources pooled
together in an organization to achieve a
specific objective.
2/12/2025 3
Definition of Project (Cont...)
2/12/2025 4
Def. of Project (Cont…)
2/12/2025 5
Def. Project (Cont…)
2/12/2025 7
Characteristics of Project (cont…)
2/12/2025 9
Characteristics of Project (cont…)
2/12/2025 10
1.3. Project Vs Plan/Program
2/12/2025 12
Program (Cont …)
Example,
• The national goal/plan: Poverty Eradication
• Strategy: Increase productivity ( in all sectors)
• Development program: Increase agricultural
productivity
2/12/2025 13
Program (Cont …)
• Construction of hospitals
2/12/2025 14
1.4. Project Parameters
2/12/2025 15
Project Parameters (cont…)
.
Project parameters
2/12/2025 16
Project Management
2/12/2025 17
Cont…
2/12/2025 18
cont.…
2/12/2025 20
Typical Project Problems
1. Scope may not be clearly defined when
commitment is made to a client.
2. There may not be enough resources allocated
(people, money, materials, time, space, etc).
3. Conflict of interest between or among stakeholders
(ops vs. engineers, sales vs. technical support, line
vs. staff).
4. Commitment to unrealistic dates – the PM may be
too optimistic about the completion date of the
project.
5. There may be unclear roles and responsibilities.
6. Things may go wrong for some natural reasons.
2/12/2025 21
Functions of the Project Managers
Project managers perform the following major
functions/roles:
1. Plan work (scope, budget, schedule),
2. Obtain and manage resources,
3. Resolve conflicts and problems,
4. Motivate people
5. Communicate to the team, to the organization, and to the clients,
6. Set priorities,
7. Make decisions,
8. Control technical quality, budget, and schedule
9. Integrate multiple skills
2/12/2025 22
Chapter two
PROJECT CYCLE
2/12/2025 23
Meaning and definition of project life cycle
Before any project is actually realized it goes through
various planning phases
The different stages through which project planning
proceeds from inception to implementation are often
called “the project cycle”.
It is the project’s life cycle through which it advances
from infancy to maturity.
A project cycle is a sequence of events, which a project
follows.
2/12/2025 24
2.2 Project life cycle models
2/12/2025 25
2.2.1. The Baum Cycle (World Bank
Procedures)
The first basic model of a project cycle is that of Baum (1970),
which has been adopted by the world bank and initially
recognized four main stages, and at a later stage (in 1978) the
author has added an additional stage namely:
1. Identification
2. Preparation
3. Appraisal and selection
4. Implementation
5. “Evaluation”
2/12/2025 26
.
Stage 1, Identification
• The first stage in the cycle is to find potential
projects.
• Project identification amounts to finding project
idea which contribute towards achieving specified
business or development objectives.
• The activity in this stage is coming up with project
ideas
2/12/2025 27
Stage 2, Preparation (pre – feasibility or feasibility studies)
• Once projects have been identified, there begins a process of
progressively more detailed preparation and analysis of project
plans.
2/12/2025 28
.
• Decisions have to be made on the scope of the project, location
and site, soil and hydrological requirements, project size (farm or
factory size) etc.
• Resource base investigations are undertaken and alternative
forms of projects are explored.
• Complete technical specifications of distinct proposals
accompanied by full details of financial and economic costs and
benefits are the outcome of the project preparation stage.
2/12/2025 29
.
• Project design and formulation is an area in which local
for big project that cover large areas and have big
budgets.
2/12/2025 30
Stage 3: Appraisal
.
• After a project has been prepared, it is generally appropriate for a
critical review or an independent appraisal to be conducted.
• projects are appraised both in the field and at the desk level
2/12/2025 31
•
.
Appraisals should cover at least seven aspects of a project:
2/12/2025 32
d) Incentive – the appraisals see to it whether things are arranged
.
in such a way that all those whose participation is required will find
it in their interest to take part in the project.
e) Economic – the appraisal here tries to see the economic
significance of the project
f) Managerial – this aspect of the appraisal examines if the capacity
exists for operating the project and see if those responsible ones
can operate it satisfactorily.
2/12/2025 33
.
g) Organizational – the appraisal examines the project if it is
organized internally and externally into units, contract policy
institution, etc so as to allow the proposals to be carried out
properly and to allow for change as the project develops.
2/12/2025 34
.
Stage 4: Implementation
2/12/2025 35
.
• In this stage,
– Funds are actually disbursed to get the projects started and
keep running,
– A major priority during this stage is to ensure that the project is
carried out in the way and within the period that was planned.
– It is during implementation that many of the real problems of
projects are first identified
2/12/2025 36
.
Stage 5 Evaluation
• The final phase in the project cycle is evaluation.
2/12/2025 37
.
2/12/2025 38
• Evaluation should be undertaken when a project
is terminated or is well into routine operation.
• Evaluation is not limited only to completed
projects.
• It is important managerial tool in ongoing
projects.
• And formalized evaluation may take place at
several times in the life of a project.
2/12/2025 39
.
• Different people may do evaluation. For example
• Project management will be continuously
evaluating the project
• The sponsoring agency, perhaps the operating
ministry, the planning agency or an external
assistance agency – may undertake evaluation.
• In large and innovative projects, the project’s
administrative structure may provide a separate
evaluation unit
2/12/2025 40
UNIDO – Project Cycle
• UNIDO has established a project cycle comprising three distinct
phases):
1. THE PRE INVESTMENT PHASE
2. INVESTMENT PHASE AND
3. OPERATIONAL PHASE.
• Each of these three phases is divided into stages, some of which
constitute important consultancy, engineering and industrial
activities.
2/12/2025 41
.
1. The pre- investment phase comprises:
i. Project Identification
A. Opportunity studies:
B. Preliminary Screening
C. Pre-feasibility Studies
ii. Project preparation (feasibility studies)
iii. Project appraisal and investment decisions (appraisal
report).
2/12/2025 42
a) Opportunity studies:
• The identification of investment opportunities is
the starting – point in a series of investment –
related activities.
2/12/2025 43
Sources of Project Idea
2/12/2025 44
2. At micro level project idea emanates from:
• The identification of unsatisfied demand or need of the
society
• The existence of unused or underutilized natural or human
resources
• The initiative of private or public enterprise in response to
the incentives provided by the government
2/12/2025 45
b) Preliminary Screening: Once some project ideas have been put
forward, the first step is to select one or more of them as potentially
viable.
2/12/2025 46
• During preliminary selection the analyst should
eliminate project proposals that are
– Technically unsound and risky;
– Have no market for the output;
– Have inadequate supply of inputs;
– Very costly in relation to benefits;
– overambitious sales and profitability;
2/12/2025 47
• It Depends on the experience and impartiality of
the professionals applying them.
• It is, however, necessary to conduct this
screening, even with indistinct criteria, in order
to reduce to a manageable number the project
alternatives to which more work and time will
be devoted.
2/12/2025 48
c) Pre-feasibility Studies: Following the preliminary
screening, promising project options should be
investigated in a systematic manner.
• This requires the preparation of brief reports
that indicate in sufficient detail the project
versions that are still promising and suggest
which ones should be eliminated
2/12/2025 49
• A pre – feasibility study should be viewed as an
intermediate stage between a project opportunity
study and a detailed feasibility study
2/12/2025 50
• Content of the Pre-feasibility Study: To enable the relevant
authorities to decide on the merits of various project options, the
pre-feasibility study should, although briefly, discuss:
i. The structure and objectives of the project;
ii. The nature and size of the demand for the output or the needs
that would satisfy, together with the foreseen beneficiary
groups;
iii. The availability of the most important materials and human
inputs;
iv. Basic alternative technologies available and their merits and
weaknesses;
2/12/2025 51
v. Approximate investment and operation costs as well as
expected revenues and other benefits;
2/12/2025 52
ii. Project Preparation – Feasibility Studies
• If the pre-feasibility study indicates that the project is promising
and further work is justified, the project enters the stage of
preparation or feasibility study
• A feasibility study should provide all data necessary for an
investment decision.
2/12/2025 54
iii. Appraisal and Investment Decision
2/12/2025 55
2. THE INVESTMENT PHASE
• The next stage in the project is the actual implementation
of the project, followed by operation
• While in earlier stages of project planning there was more
thinking and less action, in this stage the combination
switches in favour of the latter: more action and less
thinking is needed.
2/12/2025 56
The phase is divided into the following stages:
2/12/2025 57
• Detailed engineering design will include site preparation final
selection of technology construction planning and time
scheduling, Negotiations are concerned with legal obligations
arising from the acquisition of technology, construction of
buildings, purchase and installation of machinery
5) Pre-production marketing,
2/12/2025 58
6) Recruitment and training of personnel.
7) Plant commissioning and start-up. It is usually a brief but technically
critical span in project implementation.
It links the preceding construction phase with the operational
(production) phase.
This stage covers the signing of contracts between the investor on
the one hand, and the financing institutions, consultants,
architects and supplies of raw materials and required inputs on
the other.
2/12/2025 59
3) OPERATIONAL PHASE
• This is the production phase that commences after commissioning
and start-up of production, replacement and rehabilitation, and
expansion and innovation.
• The resultant challenges of this phase are viewed from the short-
term perspective and long-term perspective.
• In the shot-term challenges may arise with regard to application
of production techniques, operation of equipment, inadequate
labour productivity due to a lack of qualified staff and labour etc.
• The long-term view relate to the chosen strategies and the
associated production and marketing costs as well as sales
revenues.
2/12/2025 60
CHAPTER THREE
2/12/2025 63
• Sources of Project Ideas:
2/12/2025 64
1. At the macro level project ideas come from
• National, sectorial, or regional plans and
strategies
• Unusual events such as drought, flood,
earthquake etc
• Multi or bilateral agreement of countries
2/12/2025 65
2. At micro level project idea emanates from:
• The identification of unsatisfied demand or
need of the society
• The existence of unused or underutilized
natural or human resources
• The initiative of private or public enterprise in
response to the incentives provided by the
government
2/12/2025 66
3.4. Opportunity Studies and Preliminary Screening
2/12/2025 67
• This preliminary screening weighs a project in terms of the following
variables:
A. Compatibility with the Promoter: The idea should be compatible with
the interest, personality and resources of the entrepreneur.
A real opportunity should fit the personality of the promoter-abilities,
training and priorities; accessible and offers a prospect of rapid growth
and high return on invested capital.
B. Compatible with Governmental Priorities : The project idea should be
within the government’s regulatory framework. In addition, it should be in
line with the country’s goals to ensure its sustainability.
2/12/2025 68
C. Availability of Inputs: The resources and inputs required for the
project must be reasonably assured. These inputs include: capital
requirements of the project, technical know-how, raw materials,
power and foreign exchange.
D. Adequacy of Markets: The size of the market for the goods or
services produced by the project must offer adequate sales
volume. In this regard, both the current and predicted demand
levels should be assessed.
2/12/2025 69
• In general assessment of the market adequacy should consider:
a. Total present domestic market
b. Competitors and their market share
c. Export markets
d. Sales and distribution system
e. Projected increase in consumption
f. Barriers to entry
g. Economic, social and demographic trends
h. Patent protection
2/12/2025 70
E. Investment costs: - Costs of raw materials transportation costs, distribution
costs, labour costs, production costs and investment costs are usually
considered. If the above costs are very high sustainability of the project is
questionable.
• Demand and supply factors: - This involves the projection of both short term
and long term requirements of the project’s output and examining the
implications of these on the project’s capacity. Many projects fail because
they have started with a very large capacity only to operate at a much lower
capacity. On the other hand, increasing the capacity of the project shortly
after it starts operation is very costly.
2/12/2025 71
F. Social and environmental considerations: - the project
should also conform to the social considerations of the
locality in which it is implemented.
2/12/2025 72
G. Reasonableness of Costs: The cost of the proposed
project should be commendable considering the benefits
expected from it.
• The following costs are considered in this regard:
– Cost of material inputs and labour
– Factory overheads
– Administrative expenses
2/12/2025 73
H. Acceptability of Risk Level: The desirability of a project is critically
dependent on the risk characterizing it.
• The following factors are used in assessing the risk level of a project:
– Technological changes
2/12/2025 74
3.5 Pre-feasibility Studies
2/12/2025 75
• In particular, the review should cover the various alternatives
identified in terms of:
– Project or corporate strategies and scope of the project
– Market and marketing concept
– Raw materials and factory supplies
– Location, site and environment
– Engineering and technology
– Organization and overhead costs
– Human resource
– Project implementation schedule and budgeting
2/12/2025 76
• In general, the pre-feasibility study involves subjective judgment of the
project in terms of:
2/12/2025 77
B. Project growth potential: - assessment of
indicators on projected increase:
In the number of customers,
Increase in the rate of acceptance of the
products,
The general economic, social and political trend
which could affect the growth potential of the
project.
2/12/2025 78
C. Investment costs: - Costs of raw materials
transportation costs, distribution costs, labour costs,
production costs and investment costs are usually
considered.
2/12/2025 79
D. Demand and supply factors:
E. Social and environmental considerations: - the
project should also conform to the social
considerations of the locality in which it is
implemented.
In addition; especially in industrial projects, due
consideration should be given to the environmental
effects of it on the surrounding.
2/12/2025 80
CHAPTER FOUR
PROJECT PREPARATION
(FEASIBILITY STUDIES)
CHAPTER FOUR
4. Project Preparation
2/12/2025 82
…Cont’d
2/12/2025 83
A. Situational Analysis and Specification of Objectives
• A situation analysis provides one with the current status of the key
aspects of the market and its participants.
2/12/2025 84
• To illustrate suppose Sony Corporation developed technology to
produce superior plasma television set and the management
wants to know where and how to market the TVs. The objectives
of the market and demand analysis may be to answer the
following questions:
• Who are the buyers of the TVs?
• What is the current demand for the TVs?
• How is the demand distributed geographically and seasonally?
• What prices will the customers be willing to pay for the superior
TVs?
2/12/2025 85
B. Collection of Secondary Information
• Information may be obtained from secondary and /or primary
sources. Secondary information is information that has been
gathered in some other context and is already available.
General sources of Secondary information:
– National level Report prepared by the Government
– Economic Survey
– Annual Reports by the Ministry
– Publication of Advertising agencies
• Secondary information should be used with great caution. Its
reliability, accuracy, and relevance for the purpose on hand should
be determined before use.
2/12/2025 86
C. Conduct of Market Survey
• Secondary information, though useful often, does not provide a
comprehensive basis for market and demand analysis.
• It needs to be supplemented with primary information gathered
through a market survey, specific to the project being appraised.
• The survey could be a census; where the entire population is
covered or a sample survey; only a proportion of the population
is covered.
• Census studies are prohibitively costly and infeasible because
proper sampling can produce the same or even more accurate
results than census studies.
2/12/2025 87
• Information sought in a market survey may cover one or more of the
following areas:
– Total demand and rate of demand growth
– Demand in different segments of the market
– Income and price elasticity of demand
– Motives for buying
– Purchasing plans and intentions
– Satisfaction with existing product
– Unsatisfied needs
– Attitude towards various products
– Social economic characteristics of buyers
– Customer preferences etc
2/12/2025 88
• Steps in a sample survey:
2/12/2025 90
D. Characterization of Market
Based on the information gathered from secondary sources
and through the market survey, the market for the
product/service may be described in terms of the following:-
Effective demand in the past and present
Methods of distribution and sales promotion
Price
Consumer
Supply and competition
2/12/2025 91
E. Demand Forecasting
2/12/2025 92
I) Qualitative Methods: This method essentially rely on the judgments
of experts
A) Jury of executive opinion method: under this method opinions are
sought from a group of managers on the expected future sales they are
then translated into sales estimates
B) Delphi method: opinions are sought from a group of experts who don’t
know the identity of each other, any divergent opinions are then mailed
back to back for further opinion until a consensus is obtained.
2/12/2025 93
II)Quantitative Method: This method essentially rely on Quantitative data
• Trend projection method:
• Time Series Projection Methods
• Exponential Smoothing Method:
• Moving Average Method:
• Casual methods
• Chain ratio method:
• Consumption level method:
2/12/2025 94
f. Uncertainties in Demand Forecasting: Demand forecasts are
subject to error and uncertainty which arise from three
principal sources:
Data about past and present market
Methods of forecasting
Environmental change
g. Market Planning. Prepare a marketing plan for the new product.
2/12/2025 95
4.2 Material Inputs and Supplies Study
2/12/2025 96
In this part of the feasibility study the following can be included:-
i. Identification of the type of material inputs and supplies to be
used in the project.
Raw material (processed and/or semi processed) are those
materials which can be agricultural products, mineral products,
livestock and forest products, marine products)
Processed Industrial material and components (metal, semi
processed materials, components and sub components)
Auxiliary materials and factory supplies (chemicals, additives,
packaging materials, paints, oil, greasing, cleaning material, etc)
Utilities: a broad assessment of utilities (power, water, )
2/12/2025 97
ii. All requirements of materials and supplies should be identified
and specified in the study considering all socio, economic,
commercial, financial, and technical factors.
iii. The source of materials availability, and price of inputs are to be
analyzed.
iv. location of the available resources, area of supply, access to
transport, transport costs and alternate usage of such materials
need to be collected.
2/12/2025 98
v. Costs of raw materials and supplies:-
The costs of materials and other supplies have to be analyzed in
detail to determine project economies.
Estimating annual operating costs for materials and supplies are
to be made explaining the price mechanisms and key factors
affecting prices.
Cost estimates may be expressed either as the cost per unit
produced or in terms of a certain production level to conduct
sensitivity analysis.
2/12/2025 99
4.3. Location, Site and Environmental Impact Assessment
4.3.1. Location
Location analysis has to identify locations suitable for the
industrial project under consideration.
Location and site are often used synonymously but must be
distinguished. The choice of location should be made from a
fairly wide geographical area, within which several alternatives
sites can be considered.
2/12/2025 100
Traditional approach to industrial location focused, on the
proximity of raw materials and market place, mainly with the
intention of minimizing transport costs.
2/12/2025 101
• Generally, the choice of location is influenced by
a variety of considerations: proximity to raw
materials and markets, availability of
infrastructure, labor situation, governmental
policies, and other factors.
2/12/2025 102
A) Proximity to Raw Materials and Markets
• Proximity to the sources of raw materials and nearness to the
market for the final products are an important considerations for
location.
• In light of a basic location model, optional location is one
where the total cost (raw material transportation cost plus
production cost plus distribution cost for the final product) is
minimized.
2/12/2025 103
• Practically, it means that:
– A resource – based project like a cement plant or a steel mill
should be located close to the source of the basic material (for
example, limestone in the case of a cement plant and iron ore in
the case of a steel plant;
– A project based on imported material may be located near a
port
– A project manufacturing a perishable product should be close to
the center of consumption.
2/12/2025 104
.
• Availability of Infrastructure: In a feasibility study, availability
of power, transportation, water, and communications should be
carefully assessed before a location decision is made.
• Labor Situation: In project where there is labor–intensive, the
labor situation in a particular location becomes important. The
key considerations in evaluating the labor situation are:
• Availability of labor, skilled, semi – skilled and unskilled
• Existing labor rates
• Labor productivity
• Labor legislation
2/12/2025 105
.
• Governmental Policies
• Policies and regulations of a government have a considerable
influence on location. In most of the cases of public sector
projects, location is directly decided by the government.
• In the case of private sector projects, location is influenced by
certain governmental restrictions and inducements. Most often
the government may forbid the setting up of industrial projects in
certain areas which suffer from urban congestion.
2/12/2025 106
.
Other factors
Climatic conditions (Information should be collected on
temperature, rainfall, flooding time) and Geophysical aspects
(soil, water levels, and a number of special site hazard such as
earthquakes and susceptibility to flooding)
General Living Conditions: the general living conditions, such as
the cost of living , housing situation, safety, and facilities for
education, health care, transportation and recreation need to
be assessed carefully.
2/12/2025 107
.
Site Selection
2/12/2025 109
• It is part of the project planning process and an integral part
of feasibility analysis.
2/12/2025 110
Objectives of Environmental Impact Assessment
2/12/2025 111
• The specific objectives of environmental impact assessment are as
follows:
– To promote a comprehensive, interdisciplinary investigation of
environmental consequences of the project
– To identify critical environmental problems requiring further
investigation
– To develop an understanding of the scope and magnitude of
incremental environmental impacts
– To identify measures for mitigation of adverse environmental
impacts and for possible enhancement of beneficial impacts.
2/12/2025 112
4.4 Production Program and Plant Capacity
4.4.1 Production program
• Production program is a plan consist of the whole range of
project activities and requirement, including production levels to
be achieved under the technical ecological, social and economic
constraints.
• The production program, range and volume of products to be
produced depend on the market requirements, proposed
marketing strategy and the availability of resources.
• A production program should define the levels of output to be
achieved during specified periods related to the sales forecast.
2/12/2025 113
• Full production level may not be possible during initial
production operation owing to various technological,
production and commercial difficulties in addition to
marketing bottlenecks.
2/12/2025 114
4.4.2 Plant capacity
2/12/2025 115
A. Feasible normal capacity refers to the capacity attainable under
normal working conditions. This may be established on the
basis of the installed capacity, technical conditions of the plant,
normal stoppages, and downtime for maintenance, holidays,
and shift patterns.
B. The nominal maximum capacity is the capacity which is
technically attainable and this often corresponds to the
installed capacity guaranteed by the supplier of the plant.
2/12/2025 116
• Plant capacity is influenced by the following factors:
– Technological requirement: For many industrial projects,
particularly in process type industries, there is a certain
minimum economic size determined by the technological factor.
For example, a cement plant should have a capacity of at least
300 tons per day in order to use to rotary kiln method:
otherwise; it has to employ the vertical shaft method which is
suitable for lower capacity.
– Input constraints : In developing countries, there may be
constraints on the availability of certain inputs. Power supply
and foreign exchange basic raw materials may be scarce;
2/12/2025 117
– Market conditions: The anticipated market for the product/service has
an important bearing on the plant capacity. If the market for the
product is likely to be very strong, a plant of higher capacity is
preferable. If the market is likely to be uncertain, it might be
advantageous to start with a smaller capacity
• Resources of the firm: both managerial and financial available resource of
a firm define a limit on its capacity decision. Obviously, a firm cannot
choose a scale of operations beyond its financial resources and managerial
capability.
Investment cost
Government Policy
2/12/2025 118
4.5. Technology and Engineering Studies
4.5.1. Assessment of technology required
• The primary goals of technology assessment are to determine and
evaluate the impacts of different technologies on the society and national
economy (cost-benefits analysis, employment and income effects,
satisfaction of human needs etc), impacts on the environment
(environmental impact assessment) and techno-economic feasibility
assessed from the point of view of the enterprise.
2/12/2025 119
4.5.2. Technology Selection
2/12/2025 121
• Plant capacity: Often, there is a close relationship between plant
capacity and production technology. To meet a given capacity
requirement perhaps only a certain production technology may
be viable.
• Principal inputs; The choice of technology depends on the
principal inputs available for the project. In some cases, the raw
materials available influence the technology chosen.
• Investment outlay and production cost: The effect of alternative
technologies on investment outlay and production cost over a
period of time should be carefully assessed.
• Use by other units: The technology adopted must be proven by
successful use by other units, preferably in the specific country.
2/12/2025 122
• Latest developments: The technology adoption must be based
on the latest developments in order to ensure that the likelihood
of technological obsolescence in the near future at least, is
minimized.
• Ease of absorption: The ease with which a particular technology
can be absorbed can influence the choice of technology.
• Sometimes a high level technology may be beyond the
absorptive capacity of a developing country which may lack
trained personnel to handle that technology.
2/12/2025 123
4.5.3. Appropriateness of technology:
2/12/2025 124
4.5.4. Acquiring Technology
2/12/2025 125
A. Technology licensing: this gives the licensee
(the one who receive the technology) the
right to use the patented technology and get
related know how on a mutually agreed
basis.
B. Outright purchase (purchase of technology):
2/12/2025 126
4.6 Human Resource and Organization
• The human resources requirement at various levels and during
different stages of the project must be defined as well as their
availability and cost.
• Human resource requirement of the project, the availability of
personnel and training needs, the cost estimates for wages,
salaries other personnel-related expenses are prepared for the
financial analysis of the project.
2/12/2025 127
Categories and Functions
2/12/2025 128
• Timing of Human Resource requirements
2. Operational phase:
2/12/2025 129
Organizational Set-Up/Design
2/12/2025 130
• Human resource requirements of the project will obviously
also depend on:
– The management structure,
– organizational layout,
– operating plan and
– other factors related to the financial and commercial
features of the project.
2/12/2025 131
• The organizational structure of an enterprise indicates the
delegation of responsibilities to the various functional units of the
company and is normally shown in a diagram.
2/12/2025 134
Assessment of supply and demand
2/12/2025 135
• Difficulties in the recruitment of key personnel (such as
managers, supervisors and skilled labor) can be dealt with in
different ways:
– Recruitment is combined with intensive training of key
personnel in order to meet quality requirements
– Foreign expertise is recruited.
• An attempt is often made to compensate for the lack of
experience of local managerial talent through the employment of
foreign personnel, either by hiring individual expatriate or by
signing management contracts with foreign companies.
2/12/2025 136
Training Plan
• Since the lack of experienced and skilled personnel can constitute
a significant bottleneck for project implementation and operation
especially in developing countries, extensive training
programmers should be designed
• Training can be provided at the factory by managerial and
technical personnel and others, by specially recruited experts or
by expatriate personnel.
2/12/2025 137
• The timing of training programs is of crucial importance since
personnel should be sufficiently trained to be able to take up
their positions as and when required.
2/12/2025 138
4.7 Financial and Economic Analysis
2/12/2025 139
4.7.2 Project Cash Flows
• Cash flows are basically either receipt of cash (cash inflow) or
payments (cash outflows)
• Typical operational cash flows for a project are shown below
A. Operational cash outflows
– Increase in fixed assets (investment)
– Operating costs (less depreciation)
– Marketing expenses
– Production and distribution losses
– Corporate (income taxes)
2/12/2025 147
B. Operational cash inflows
• Revenues from selling of fixed assets
• Sales revenues
• Other income due to plant operations
2/12/2025 148
• The two methods used to measure projects
financial worthiness are:
2/12/2025 149
1. Non-Discounted cash flow method
A) Payback period
• This is the number of year taken to recover the original (initial)
investment from annual cash flows. The lower the payback
period the better the project is
2/12/2025 150
2. cash flow discounting in financial evaluation
• The basic assumption underlying the discounted cash-flow concept is
that money has a time value.
• A sum of money available now is worth more than an equal sum
available in the future.
• This difference can be expressed as a percentage rate indicting the
relative change for a given period which, for practical reasons, is usually
a year.
2/12/2025 152
(a) Net Present Value (NPV) Method
n
Ct
NPV Io
t 1 (1 K ) t
2/12/2025 153
• Decision criteria for NPV
• NPV > 0, Accept the project – it maximizes
investors wealth
• NPV < 0, Reject the project
• NPV = 0, Indifferent
2/12/2025 154
• A firm is considering investing in a project which
costs 6,000 Br and has the following cash flows
• YR 1 2 3 4
• C.F 1500 3000 2000 2500
• The cost of capital is 10%and the project has no
salvage value. Using the NPV method advise the
firm on whether to invest in the project
2/12/2025 155
Decision: Accept the project since NPV >0
NPV = 1053.00
2/12/2025 156
Chapter Five: Project Implementation,
Monitoring and Evaluation
5.1. Organization
• The primary formal relationships for organizing are responsibility,
authority, and accountability. They enable us to bring together
functions, people, and other resources for the purpose of achieving
objectives. The framework for organizing these formal relationships
is known as the organizational structure.
• It provides the means for clarifying and communicating the lines of
responsibility, authority, and accountability.
2/12/2025 157
5.1.1. Line and Staff Organization
2/12/2025 158
Cont…
2/12/2025 160
Cont…
2/12/2025 162
Cont…
• The matrix organizational structure divides authority both by
functional area and by project. In a matrix structure, each employee
answers to two immediate supervisors: a functional supervisor and
a project supervisor. The functional supervisor is charged with
overseeing employees in a functional area such as marketing or
engineering. Project supervisors manage a specific and often
impermanent project.
• The problem with this structure is the negative effects of dual
authority similar to that of project organization. The functional
managers may lose some of their authority because product
managers are given the budgets to purchase internal resources.
• In a matrix organization, the product or business group managers
and functional managers have somewhat equal power. There is
possibility of conflict and frustration but the opportunity for prompt
and efficient accomplishment is quite high.
2/12/2025 163
Cont…
2/12/2025 165
Cont…
-Identifying deliverables and creating the work breakdown structure;
– Identifying the activities needed to complete those deliverables and
networking the activities in their logical sequence;
– Estimating the resource requirements for the activities;
– Estimating time and cost for activities;
– Developing the schedule;
– Developing the budget;
– Risk planning;
– Gaining formal approval to begin work.
• Additional processes, such as planning for communications and for
scope management, identifying roles and responsibilities,
determining what to purchase for the project and holding a kick-off
meeting are also generally advisable.
2/12/2025 166
Cont…
• For new product development projects, conceptual design of the operation of
the final product may be performed concurrent with the project planning
activities, and may help to inform the planning team when identifying
deliverables and planning activities.
Why Project Planning?
• One of the objectives of project planning is to completely define
all work required so that it will be readily identifiable to
each project participant.
• This is a necessity in a project environment because:
• -If the task is well understood prior to being performed, much of the work can
be preplanned.
• -If the task is not understood, then during the actual task execution
more knowledge is gained, in turn, leads to changes in
resource allocations, schedules, and priorities.
2/12/2025 167
Cont…
• The more uncertain the task, the greater the amount
of information that must be processed in order to ensure effective
performance.
• These considerations are important in a project environment
because each project can be different from others,
requiring a variety of different resources, but having to
be performed under time, cost, and performance
constraints with little margin for error.
• There are four basic reasons for project planning:
-To eliminate or reduce uncertainty
-To improve efficiency of the operation
- To obtain a better understanding of the objectives
- To provide a basis for monitoring and controlling work
2/12/2025 168
Cont…
2/12/2025 169
5.3 Project Control
Project Control is a formal process in project management.
The PMBOK defines Project Control with the following statement:
“A project management function that involves comparing actual
performance with planned performance and taking appropriate
corrective action (or directing others to take this action) that will
yield the desired outcome in the project when significant differences
exist.”
Project Control involves the regular review of metrics and reports
that will identify variances from the project baseline. The variances
are determined by comparing the actual performance metrics in the
execution phase against the baseline metrics assigned during the
Planning Phase.
These variances are incorporated into control processes to evaluate
their meaning.
2/12/2025 170
Cont…
If significant variances are discovered(variances that place the
completion of the project in jeopardy) adjustments are made to the
project plan.
A significant variance does not explicitly require a change to the
project plan but these variances should be reviewed to determine if
preventative action is necessary.
Controlling also includes taking preventative action in anticipation of
possible problems.
Project Control is important because it may determine the success
of the project by the stakeholders.
Project success relates to project cost, completion date, customer
expectations, performance, etc.
2/12/2025 171
Cont…
The Project Control Process
• Controlling procedure need to address such questions:
• Are we on planned track?
• Are we on expected budget?
• Are we on planned schedule?
• Are we delivering what we said we would?
• Are we meeting quality and performance standards?
• Are we meeting stakeholder expectations?
• What have we accomplished?
• Will the project objectives be met?
• What deviations/variances exist?
• What corrective actions are we taking?
2/12/2025 172
Cont…
• The project control includes project status reporting, schedule control,
cost control, quality control and risk control.
• Controlling process consists of following steps:
Establish A Baseline of Measurement:
• The baseline of measurement is actually represented by your project
plan. This includes your control schedule, project budget, and any
design or performance specifications related to project deliverables.
• The estimates embodied in these documents create the basis from
which variance is measured. The success of project measurement and
control depends on how accurate estimated baseline is? What if an
estimate is wrong? What if an element of your baseline is a poor
representation of what’s actually achievable?
• In case of variance it is difficult to know who is responsible for
variance, estimator or task performer.
2/12/2025 173
Cont…
• The baseline is derived from the cost and duration information found in
work breakdown structure and scheduling decisions.
Measuring Progress and Performance:
• Time and Budget are two quantitative measures. Many methods are
available to measure these two. Qualitative measures (i.e. technical
specification, production function, reliability etc.) are difficult to
measure. Tracking time performance is easier than monitoring budgets.
• Some of valuable and essential control techniques are:
• Gantt Chart
• Control Chart
• Critical Path Method (CPM)
• Program Evaluation and Review Technique (PERT)
• Critical Ratios
2/12/2025 174
Cont…
Analyzing the Performance:
• Almost all the projects need to be guided right throughout in order to
receive the required and expected output at the end of the project.
• Project status report must be generated on every week or every
month. Comparisons of actual and expected(planned) must be done
for proactive correction.
Variances
• Variances are deviations from plan. Think of a variance as the
difference between what was planned and what actually occurred.
There are two types of variances: positive variances and negative
variances.
• Positive variances: Positive variances are deviations from plan that
indicate an ahead-of-schedule situation has occurred or that an actual
cost was less than a planned cost.
2/12/2025 175
Cont…
• This is a good news to the project manager, who would rather hear
that the project is ahead-of-schedule or under budget.
• Positive variances bring their own set of problems, which can be as
serious as negative variances. Positive variances can allow for
rescheduling to bring the project to completion early, under budget
or both. Resources can be reallocated from ahead-of- schedule
projects to behind-schedule projects.
• Positive variances can also result from schedule slippage. Consider
budget. Being under budget means that not all dollars were
expended, this may be the direct result of not having completed
work that was scheduled for completion during the period.
• Negative variances: Negative variances are deviations from the plan
that indicate a behind-schedule situation has occurred or that an
actual cost was greater than a planned cost.
2/12/2025 176
Cont…
• Being behind a schedule or over budget is not what the project
manager wants to hear. Negative variances, just like positive
variances, are not necessarily bad news. For example, you might
have over spent because you accomplished more work during the
report period than was planned.
• But, in over spending during this period, you could have
accomplished the work at less cost than was originally planned.
• In most cases, negative time variances affect project completion
only if they are associated with critical path activities or if the
schedule slippage on non critical path activities exceeds the
activity’s total float.
• Negative cost variances can result from uncontrollable factors such
as cost increases from suppliers or unexpected equipment
malfunctions. Some negative variances can result from
inefficiencies or error.
2/12/2025 177
Cont…
Project Control Techniques
• Gantt Chart: A Gantt chart, commonly used in project management,
is one of the most popular and useful ways of showing
activities(tasks or events) displayed against time. Typically, tasks are
shown on the vertical axis, and the project time span is represented
on the horizontal axis.
• Each task has a corresponding bar that shows the time span
required for that task. The bar can be filled in to show the
percentage of the task that has been completed.
2/12/2025 178
Cont…
• Gantt Chart represents:
• What the various task/ activities are?
• When each activity begins and ends?
• How long each activity is scheduled to last?
• Where activities overlap with other activities, and by how much overlap?
• The start and end date of the whole project?
• Control Chart: Control chart is an efficient way of analyzing
performance data to evaluate a project process. Control charts, also
known as Shewhart charts named after Walter A. Shewhart. Every
process has variation. Some variation may be the result of causes which
are not normally present in the process. Some variation is simply the
result of numerous, ever-present differences in the process.
2/12/2025 179
Cont…
• The control chart is a graph used to study how a process changes
over time. Data are plotted in time order. A control chart always has
a central line for the average, an upper line for the upper control
limit (for ahead from scheduled) and a lower line for the lower
control limit(for behind the schedule).
• These lines are determined from historical data. By comparing
current data to these lines, we can draw conclusions about whether
the process variation is consistent(in control) or is
unpredictable(out of control, affected by special causes of
variation).
• One goal of using a Control Chart is to achieve and maintain process
stability.
2/12/2025 180
Cont…
• The control chart is used to:
-Monitor effects of the variables on the difference between target
and actual performance of project.
-Analyze and understand process variables
-Determine process capabilities.
• Critical Path Method: The Critical Path Method or Critical Path
Analysis is a mathematically based algorithm for scheduling a set of
project activities. It is an important tool for effective project
management. Critical path method commonly used with all form of
projects, including construction, software development, research
project, product development, engineering and plant maintenance,
among the others.
2/12/2025 181
Cont…
• Any project with the interdependent activities can apply this
technique of scheduling.
• Critical path method is based on mathematical calculations and it is
used for scheduling project activities. In the critical path method,
the critical activities of a program or a project are identified. These
are the activities that have a direct impact on the completion date
of the project.
2/12/2025 182
Cont…
Key Steps in Critical Path Method:
1. Identifying the key activities of project
2. Determining the Sequence of Activities
3. Drawing Network Diagram
4. Time estimate for each activity
5. Identifying the Critical Path: The critical path is the longest path of the
network diagram. The activities in the critical path have an effect on
the deadline of the project. If an activity of this path is delayed, the
project will be delayed.
• Program Evaluation and Review Technique: CPM assumes low
uncertainty in scheduled timings. The Program Evaluation and Review
Technique(PERT) is a network model that allows for randomness in
activity completion times. PERT was developed in the late 1950's for the
U.S. Navy's Polaris project.
2/12/2025 183
Cont…
PERT process involves following steps:
• Specifying the task/activities
• Determining the sequence of activities
• Constructing Network Diagram
• Estimate the Time
• Critical Path
• Update the PERT chart
• There are three estimation times involved in PERT; Optimistic Time
Estimate(O), Most Likely Time Estimate(M), and Pessimistic Time
Estimate (P).
• Optimistic Time Estimate: This time assumes that everything will go
according to plan and with minimal difficulties.
• Most Likely Time Estimate: This is the time that, in the mind of the
functional manager, would most often occur should this effort be
reported over and over again.
2/12/2025 184
Cont…
• Pessimistic Time Estimate: This time assumes that everything will
not go according to plan and maximum difficulties will develop.
• Critical Ratios: Schedule Performance Index(SPI) and Cost
Performance Index(CPI) ratios are critical tools in project
management.
• The budget(Cost) and the schedule (Time) are two important
considerations in any project, and since projects that overrun
budgets and time frames are not viable for organizations. SPI and
CPI ratios are generated from Earn Value System.
• Schedule Performance Index:
• The ratio of schedule efficiency that indicates the percent of work
performed out of the total work scheduled. A number less than 1
indicates that the project is behind schedule.
• SPI= EV/PV
2/12/2025 185
Cont…
• Cost Performance Index:
• The ratio of cost efficiency or value earned per unit actual cost. A
number less than 1 indicates that the project is spending more money
than budgeted.
• CPI= EV/AC
• Lastly, compare the schedule and cost performance indices to each
other to determine
• The Critical Ratio (CR), CR = SPI x CPI
• Where:
• SPI= Schedule Performance Index
• CPI=Cost Performance Index
• EV=Earned Vale (Budgeted Cost of Work Performed)
• PV= Planned Value (Budgeted Cost of Work Scheduled)
• AC=Actual Cost (Actual Cost of Work Performed)
2/12/2025 186
Cont…
5.4. Human Aspects of Project Management
For the successful execution of a project, a satisfactory human
relation is must without such a system other systems of project
management do not work well.
To achieve satisfactory human relations in the project setting, the
project manager must successfully handle problems and challenges
related to: Authority, Orientation, Motivation, Group functioning.
Authority: In project management, the project manager whose
activities cut across functional lines of command, lacks the desired
formal authority.
While the manager has formal control emanating from contracts
and agreement:" as far as outside agencies involved in project work
are concerned, in his own organization he has to be contacted with
split authority, and dual subordination.
2/12/2025 187
Cont…
His effective authority would stem from his ability to develop
rapport with the project personnel, his skill in professional
reputation and stature, his skill in communication and persuasion.
Orientation: Most of the managers, working for a project are
engineers or technologist when an engineer assumes managerial
responsibility, he faces some different type of problems, which he is
supposed to:
-Perform the task of planning, organizing, directing and controlling
the resources of the firm in the world of uncertainty.
-Adopt a more creative approach to solve non program and
unstructured problems.
-Attach greater importance to efficient utilization of resources and
resolution of human relation problem. Thus, for achieving the task
he must himself be an accomplished engineer turned manager.
2/12/2025 188
Cont…
• Motivation: The project manager works within the boundaries of a
socio-technical system. The principal behavioral factor, which he
can influence, is the motivation of the project personnel.
• In order to succeed in motivating project personnel, the project
manager must be a perceptive observer of human beings, must
have the ability to appreciate the variable needs of human being,
must have a skill in several styles of management suitable to
different situations.
• Group Functioning: For building an effective group the company
must presume a genuinely participative style of management.
• With the managerial philosophy the project manager can facilitate
the development of mutual trust and acceptance, open
communication, co-operation and project attitude.
2/12/2025 189
Cont…
• In this task the needs leadership capabilities, sensitivity to human
nature, perceptiveness, concern for welfare of others, maturity and
impartial approach. Actually this is difficult and challenging task.
2/12/2025 190
Cont…
5.5. Pre -requisites for Successful Project Implementation
• Project execution has a direct correlation to project progress and
stakeholder’s expectations but, time and cost over runs of the
project are the main hurdles in successful implementation of a
project.
• This problem is very common especially in the public sector. Due to
such time and cost over runs, projects tend to become
uneconomical, resources are not available to support other projects
and overall development is adversely affected.
• To minimize time and cost over runs and thereby to improve the
prospects of successful completion of projects, following things can
be done:
• 1)Adequate formulation of the project
2/12/2025 191
Cont…
2.Sound project organization.
3. Timely availability of funds.
4. Better contract management.
5. Use of the principle of responsibility accounting.
6. Proper planning for implementation.
7. Judicious tendering and procurement of required equipments.
8. Advance actions and effective monitoring.
2/12/2025 192
4.5 Technology and Engineering Study
Assessment of technology required
• The primary goals of technology assessment are to determine and evaluate the impacts of different technologies on the society and
national economy (cost-benefits analysis, employment and income effects, satisfaction of human needs etc), impacts on the
environment (environmental impact assessment) and techno-economic feasibility assessed from the point of view of the enterprise.
To allow the careful assessment of the suitability of the technological alternatives a logical sequence should be followed: Problem
identification, technology description and project layout, technology market and alternatives, assessment of availability, technology
forecast, assessment of the local integration, description of the social economic impact, environmental impact assessment
• Problem identification
• The technology required is defined not only by the marketing concept and the available raw material and factory supplies but also by
various social economic, ecological financial commercial and technical conditions. Problem identification should identify, describe and
assess the critical elements of the technology required. Special consideration should be given to existing or possible future constraints
on the acquisition and use of available technologies to further development needs and to the possibility of feasible technological
alternatives.
• Technology description and project layout
• The preparation of a plant layout and design is essential for every project. The first initial stage should be the preparation of a
preliminary project plan and layout on the basis of the production activities and the technologies alternative envisaged. These second
stage of project layout and design can only be drawn when the details relating to technology plant capacity and machine specification
are finalized.
• The preliminary project layout should include several charts and drawings, which need not be according to scale, but which would
define the various physical features of the plant and their relationship with one another. For most projects, functional charts and
layout drawing at this stage should include the following:
• General functional layout, defining the principal physical or location features and flow relationships of machinery and equipment, civil
works and construction and various ancillary and service facilities
2/12/2025 193
6. Production Program and Plant Capacity
The production program, range and volume of products to
be produced depend on the market requirements,
proposed marketing strategy and the availability of
resources.
A production program should define the levels of output
to be achieved during specified periods related to the
sales forecast.
2/12/2025 194
…Cont’d
(2)Delphi Method: This method is used for eliciting the opinions of a group of
experts with the help of a mail survey.
2/12/2025 203
…Cont’d
Y = a + bX
2/12/2025 204
…Cont’d
b = ∑xy – n ̅XῩ
∑x2 – n̅ X2
a = Ῡ – b̅X
Where, ̅X = Mean of X
Ῡ = Mean of Y
2/12/2025 205
…Cont’d
2/12/2025 206
…Cont’d
Ft + 1 = α Dt + (1 - α ) Ft
Where; α = weitage factor for the current demand (the smoothing parameter
which lies between 0 and 1).
Dt = demand during the present period
Ft + 1 = Forecast for next period t
Ft = Forecast of demand made for the present period
2/12/2025 207
…Cont’d
2/12/2025 208
…Cont’d
2/12/2025 209
…Cont’d
2/12/2025 210
In this part of the feasibility study the following can be included:-
i. Identification of the type of raw materials and supplies to be used in the
project.
ii. All requirements of materials and supplies should be identified and
specified in the study considering all socio, economic, commercial,
financial, and technical factors.
iii. The source of materials availability, their users and price of inputs are to
be analyzed. The interdependencies between projects, material and input
requirements and supply of these items should be considered.
- location of the available resources, area of supply, access to
transport, transport costs and alternate usage of such materials
need to be collected.
2/12/2025 211
…Cont’d
2/12/2025 212
…Cont’d
5. Location, Site and Environmental Impact Assessment
5.1. Location
Location analysis has to identify locations suitable for the
industrial project under consideration.
Traditional approach to industrial location focused, on the
proximity of raw materials and market place, mainly with the
intention of minimizing transport costs. However, the modern
view requires consideration of not only commercial, technical
and financial factors, but also of the social and environmental
impact a project might have.
A project potentially located in a number of alternative regions
(several alternative locations may have to be considered).
2/12/2025 213
The choice of location is influenced by a variety of
considerations:
Proximity to raw materials and markets
Availability of infrastructure
Availability of labor (especially for labor-intensive projects)
Technological and process characteristics
Government policies, and
Other factors like climatic conditions, ease in coping with pollution,
general living conditions, etc.
2/12/2025 214
…Cont’d
2/12/2025 215
…Cont’d
2/12/2025 216
5.2 Site Selection
Once the location is decided upon, a specific project site alternative
should be defined in the feasibility study. This will require evaluation of
the characteristics of each site.
2/12/2025 217
…Cont’d
2/12/2025 218
…Cont’d
2/12/2025 219
5.3 Environmental Impact Assessment
Is designed to develop an understanding of the environmental
consequences of newly planned or existing projects and of any
project related activities.
2/12/2025 220
6. Production Program and Plant Capacity
The production program, range and volume of products to be
produced depend on the market requirements, proposed marketing
strategy and the availability of resources.
A production program should define the levels of output to be
achieved during specified periods related to the sales forecast.
Full production level may not be possible during initial production
operation owing to various technological, production and
commercial difficulties in addition to marketing bottlenecks.
Normally a production and sales target of 40-50 percent of the
capacity for the first year is considered reasonable. Picking up
gradually, towards third or fourth year full production level can be
achieved.
2/12/2025 221
With regards to plant capacity, generally two capacity
terms used in relation to level of operation.
2/12/2025 222
7. Technology Selection
Appropriate technology selection should be made.
The advocates of appropriate technology urge that the
technology should be evaluated in terms of the following
questions:
Whether the technology utilizes local raw materials?
Whether the technology utilizes local manpower?
Whether the technology protects ecological balance?
Whether the goods and services produced satisfy to the basic
needs?
2/12/2025 223
…Cont’d
2/12/2025 224
Introduction of obsolete technologies must also be carefully considered.
Acquisition of previously discarded and disassembled production plants
should be rechecked carefully.
2/12/2025 225
8. Organization and Human Resource
2/12/2025 226
A design of the organization usually includes the following
steps:
1. Goals and objectives of the business are stated
2. Then functions are identified
3. Functions are grouped or related
4. Organizations structure or framework designed
5. All key jobs are analyzed, designed, and described
6. A recruitment and training program prepared.
2/12/2025 227
The two reasons for preparing an organization:-
1. To achieve optimal coordination and control on all project inputs.
2. To structure the investment and production costs and to determine
the costs linked with corresponding organizational units.
2/12/2025 228
Cont.
2/12/2025 229
The following factors should be given due consideration when the
availability and employment of human resources are analyzed:-
i. The general availability of relevant human resource categories in
the country and the project region.
ii. The supply and demand situation in the project region
iii. Recruitment policy and methods
iv. Training policy and program
2/12/2025 230
…Cont’d
2/12/2025 231
9. Financial and Economic Analysis:
Since reliable cost estimates are fundamental to the
appraisal of an investment project it is necessary to
check carefully all cost items that could have a
significant impact on financial feasibility.
Cost estimates cover:-
Initial investment cost
Cost of production
Marketing and distribution costs
Plant and equipment replacement costs
Working capital requirements and decommissioning at the end
of the project life.
2/12/2025 232
9.1 Initial Investment Cost
Initial investment costs are the total of fixed assets (fixed asset costs
plus pre-production expenditures) and net working capital, with fixed
assets constituting the resources required for constructing and
equipping an investment project, and net working capital
corresponding to the resources needed to operate the project totally or
partially.
2/12/2025 233
i. Preliminary capital – issue expenditures: these are expenditures incurred
during the registration and formation of the company. Eg. Legal fees,
preparation and issue of a prospectus, ad, public announcement,
brokerage commission, etc.
ii. Expenditures for preparatory studies: these includes expenditures for
pre-investment studies like opportunity and feasibility and other
expenses for planning the project.
iii. Other pre-production expenditures: like
- Salaries, fringe benefits and social security contributions of personnel
engaged during the pre-production period.
- Travel expenses
- Preparatory installations, such as work camps, temporary offices and
stores.
2/12/2025 234
iv. Cost of trial-runs, start up and commissioning expenditures. These
include:
Fees payable for supervision or start up operations,
wages, salaries, social security contributions of personnel
employed,
consumption of production materials and supplies, utilities and
other incidental start up costs.
2/12/2025 235
9.1.2 Fixed Assets
Fixed investment costs should include the following main cost items:
Land purchase, site preparation and improvements,
Building and civil works
Plant machinery and equipment including auxiliary equipment
Other assets like industrial property rights and lump sum payments
for know-how and patents.
2/12/2025 236
9.2 Production Cost
It is essential to make realistic forecasts of production and
manufacturing cots for a project proposal in order to determine the
future viability of the project.
Production costs should be determined for the different levels of
capacity utilization. The production costs are classified into four major
categories. They are:
Factory costs
Administrative overhead costs
Depreciation and cost of financing
Operating Cost (the sum of factory and administrative overhead
costs).
2/12/2025 237
9.3 Marketing Costs:
Marketing costs comprise the costs for all marketing activities and may
be divided into direct marketing costs and indirect marketing costs.
Direct marketing costs – are costs for packaging and storage, sales,
product advertisement, transport and distribution costs.
2/12/2025 238
9.4 Cash Flow Statement
The cash flow statement shows the movement of cash into and out of
the firm and its net impact on the cash balance within the firm.
2/12/2025 239
…Cont’d
2/12/2025 240
I. Discounting Methods (Criteria)
– The net present value (NPV) has certain properties that make it a very attractive
decision criterion.
– The NPV method is a discounted cash flow method. In this method all net cash
inflows are discounted to present value using the required rate of return and is
then compared with the initial outlay
– If the discounted cash flow exceeds the initial outlay it means the project
investigated is attractive since it is expected to earn more than the required rate
of return.
2/12/2025 241
Where CF= cash inflow per period (year)
r= discount rate
ICO= initial cash outlay
Decision Criteria
If NPV is greater than zero accept the project
If NPV is less than zero reject the project
Advantages
1. time value of money is considered
2. It measures the benefits directly
3. It is an objective method of selecting and evaluating projects(By
considering cash flows, NPV is not affected by the Co.’s accounting policies,
unlike net profit).
2/12/2025 242
…Cont’d
Limitations
1. The NPV method does not consider the life of the project. Hence, when
mutually exclusive projects with different lives are being considered,
the NPV rule is biased in favor of the longer term project.
2. In practice it may be difficult to determine the discount rate. This
should relate to the cost of finance, but calculating the costs of the
different elements of finance (share capital and loans)is difficult.
3. The NPV is an absolute figure and it does not consider for the size of the
project.
2/12/2025 243
…Cont’d
Example
To illustrate the calculation of the NPV consider a project
which has the following cash flow streams.
2/12/2025 244
Year Cash Flow
0 $(1,000,000)
1 200,000
2 200,000
3 300,000
4 300,000
5 350,000
The cost of capital, r, for the firm is 10%. The NPV of proposal is?
2/12/2025 245
…Cont’d
NPV=Io - 200,000+200,000+300,000+300,000+350,000
(1.10)1 (1.10)2 (11.10)3 + (1.10)4 + (1.10)5
= -Br. 5,273
The NPV represent the net benefit over and above the
compensation for the time and risk
2/12/2025 246
…Cont’d
2/12/2025 247
…Cont’d
• Hence, the question will be searching for the discounting rate that equates
the PV of the investment and cash inflows. That is why IRR is some times
called the internally generated rate of return. Mathematically, IRR will be
obtained when;
IO - PV (NCF) = O
o The primary decision rule with IRR is to accept only projects with an IRR
greater than the discount rate.
2/12/2025 248
… Cont’d
Example
To illustrate the calculation of IRR, consider the
cash flows of a project being considered by X
Company.
Year 0 1 2 3 4
2/12/2025 249
o The IRR is the value of r which satisfies the following equation:
2/12/2025 250
Cont.
2/12/2025 251
• Since this value is now less than $100,000 we conclude that the value
of r lies between 15% and 16%. For most of the purposes this
indication is sufficient, but if a more refined estimate of r is needed,
use the following procedures.
2/12/2025 252
15+0.37 = 15.37 Percent
2/12/2025 253
…Cont’d
Class Work
A project has a total outlay of Br. 500,000 with the following pattern of
cash inflow. Compute the IRR of the project
Year 1 2 3 4 5
CFs 120 120 120 150 150
(in thousands)
2/12/2025 254
…Cont’d
Solution
i. Find (guess) the starting rate
500000/120000=4.167=7%
500000/150000=3.333=15%
ii. A better approximate (guess) can be found by
PVCF ………………….481,080
Io ……………………….500,000
NPV …………………… $-18920
2/12/2025 255
…Cont’d
• Now, NPV is negative, which means the actual IRR is less than 11%. The
following are the next trials at 9% and 10%
9% 10%
120,000x2.531=303,720 x2.487=298,440
150,000x0.708=106,200 x0.683=102,400
150,000x0.650=97,000 x0.621=93,150
507,420 494,040
-500,000 -500,000
NPV……... +7,420 -5,960
2/12/2025 256
…Cont’d
iv. Now, IRR is above 9% but below 10%; apply interpolation to
approximate the true IRR,
7420 = 0.55
13380
Thus, IRR 9.55%
Exercise
A project requires a new investment of 20,000 and produces the
following cash flows. Compute the IRR of the project
2/12/2025 257
…Cont’d
Year 1 2 3 4 5
CFs 5000 4000 3000 2000 8000
NPV Vs IRR
For making choice between two projects competing for
the funds at the disposal of a concern, the NPV method
can give a better choice because it can give idea of
ranking of the projects.
2/12/2025 258
…Cont’d
Advantages of IRR
(1)Like NPV, it deals with discounted cash flows and is
based on the time value of money.
(2)The difference between the IRR and the cost of capital
indicates the additional return for risk that the project
provides.
Disadvantages of IRR
(1)If there are negative annual cash flows later than year
0, this may lead to more than one possible IRR. In such
a case, IRR must be used with great care.
(2)If a firm has to rank mutually exclusive projects,
choosing the project with the highest IRR may result in
suboptimal outcome.
2/12/2025 259
…Cont’d
C. Benefit-Cost Ration (Profitability Index)
• The profitability index, also called benefit - cost ratio, is the
ratio of the PV of the future net cash inflows to the initial
outlay of the project.
• It measures the desirability of the project and evaluates the
worth of an investment.
PI= PV (NCF)
PV (IO)
• In the application of PI, a project is accepted if PI > 1, rejected
if PI < 1 and we remain indifferent if PI = 1. It should be noted
that when PI > 1, NPV is positive; PI < 1, NPV is negative and
PI=1 when NPV is zero.
2/12/2025 260
…Cont’d
Example
After tax cash flows of a small scale tannery project is given
below. Find the profitability index if discount rate is assumed to
be 12%?
Year 0 1 2 3 4 5
2/12/2025 261
…Cont’d
Solutions
Year Cash Flow Rate = (12%) PV
1 15,000 0.893 13,395
2/12/2025 262
…Cont’d
2/12/2025 263
…Cont’d
Example 1
If a project has an investment of Br. 60,000 and annual cash inflow is Br.
15,000 per year for 10 years. Compute the PBP?
Example 2
If the project cash inflow is not in “annuity form”, cumulative cash
inflow method may be used to compute that PBP. Assuming an initial
investment of Br. 30,000 for the following stream of cash flows and
compute the PBP.
2/12/2025 264
…Cont’d
Year Cash inflows Cumulative
1 10,000 10,000
2 8,000 18,000
3 12,000 30,000
4 7,000 37,000
5 9,000 46,000
6 3,000 49,000
2/12/2025 265
Cont.
Example 3
If the project cumulative cash flow does not exactly match to
the investment outlay, but in annuity form of inflow, then
compute the PBP in the following way (assuming initial
investment of $10,000)
2/12/2025 266
…Cont’d
Year Cash inflow Cumulative
1 4,000 4,000
2 4,000 8,000
3 4,000 12,000
4 4,000 16,000
5 4,000 20,000
2/12/2025 267
…Cont’d
Example 4
In case the cumulative inflow does not exactly match
the amount of investment and the inflow is not in
annuity form use the interpolation method (assume an
investment outlay of 15,000); compute the PBP.
2/12/2025 268
…Cont’d
Year Cash in flow Cumulative
1 3,000 3,000
2 5,000 8,000
3 10,000 18,000
4 2,000 20,000
5 4,000 24,000
2/12/2025 270
…Cont’d
Example (Discounted Payback)
2/12/2025 272
…Cont’d
2/12/2025 273
…Cont’d
• Decision Criteria
– Projects which have an ARR equal to or greater than a pre-
specified cutoff rate of return ─ which is usually between 15%
and 30% ─ are accepted otherwise, rejected.
Advantages
1. It simple to calculate
2. It is based on accounting information, which is readily available, and
familiar to businessman
3. It considers benefits over the entire life of the project.
Limitations
1. It is based upon accounting profit, not cash flow
2. It does not take into account the time value of money.
2/12/2025 274