Final Itp Group 3
Final Itp Group 3
CE 416C
ADVANCED CONSTRUCTION METHODS AND EQUIPMENT
ACTIVITY NO.08
ITP
“INSPECTION AND
TEST PLAN”
Project Name :- FOUR-STOREY COMMERCIAL BUILDING
‘H’ - Hold : A point beyond which work shall not proceed without formal approval by the appropriate
inspectorate.
‘W’ - Witness : A point beyond which work may proceed without formal documented approval by any of the
inspectorate. A Inspection Request to inform the client is required, however work may proceed
after 1 hour should the client fail to respond to the IR.
‘S’ - Surveillance : A point where Consultant and others may carry out surveillance of work in progress and
documentation associated on an unscheduled basis, with no notification required by any party
and without amendment to the scheduled programme.
‘R’ - Review : The documents are to be submitted to the appropriate inspectorate for review by
Consultant/Client. Note that where a document is subject to Client approval, work shall not
proceed until Client approval has been received.
‘Rcd’ - Record : Documents required for record purposes shall be filed and retained for Project Quality records.
‘C’ - Action : Required steps shall be taken by Sub Contactor to complete the activity.
‘I’ - Inspection : A point where all evaluation / verification is made prior to commencing subsequent activity. An
IR to inform the client is required, however work may proceed without the client responding to
the IR.(Time frame for proceeding the activity without approval to be as per contract conditions.
)
Method Method
2. Compaction and pour height Section 03300,Clauses 3.04
Visual statement Statement / Every Pour W S NA
4 inspection. H, 3.04K, 3.06
/Specification Specification
Fishes of
surface
should be as
specified in
2. Section 03300,Clause 3.14
5 Surface finish evaluation. & IFC drawings
Visual the approved IR Every Pour W S NA
and as per
drawing and
project
specifications
3
. Post Pour Concrete
0
Post concrete
Section 03300 Clause 3.13 IR / Method
3. check list
1 Removal Formwork E, & Sec 03100, & IFC Visual statement /
SPLL-ALT-F-
Every Pour W S NA
drawings Specifications
CL-004 & 028
Method
Section 03300,Clause 3.07 statement /
Method
& Curing Register Manufacturer’
statement /
s
3. SPLL-ALT-F-
2 Curing Visual Recommendat
CL-028 &
Every Pour W S NA
ion of using
SPLL-ALT-F-
approved
023
Curing
Compound
VERIFYING
INSPECTION / TEST STAGE Test Method DOCUMENTS
Frequency
CRITERIA / Verifying/Contr
(Visual or Consulta
SPECIFICATION /
document
ol Forms. CHEC nt
TPI
PROCEDURE
review)
- Rapid Chloride Section 03300 Review of Lab Test Reports 28th days
4. Clause 3.09 Document / Section 03300 per
3 Permeability Test at AASHTO Clause 3.09 concrete
W S H
28 days T277 poured
Section 03300 Section 03300 Lab Test Reports 28th days
Review of
4. - Water Permeability Clause 3.09 Clause 3.09 per
Document / concrete W S H
4 Test DIN 1048 poured
Section 03300 Review of Section 03300 Lab Test Reports 28th days
4. - Initial surface Clause 3.09 Document / Clause 3.09 per
W S H
5 absorption test BS 1881 Part concrete
122 poured
Review of
Document /
5. Section 03300 Section 03300 28th and 3
1 - Modulus of Elasticity Clause 3.09 F (1)
Document
Clause 3.09
Lab Test Reports
months
R R H
Review
/ASTM C469
5. Section 03300
2 - Drying shrinkage Clause 3.09 F (2a)
5. Section 03300
3 - Wetting expansion Clause 3.09 F (2b)
LEGEND
Inspection Authorities :
ITP No. :
Revision : 00
ITP Title: Electrical Works Date : 15-03-2014
o
Page N . : 2 of 6
ACCEPTANCE INSPECTION ACTION
Test Method Verifying/Co VERIFYING
INSPECTION / TEST STAGE CRITERIA / Frequency
(Visual or DOCUMENTS Consultan
SPECIFICATION /
document
ntrol Forms. CHEC t/IDL
TPI
PROCEDURE
review)
‘H’ - Hold : A point beyond which work shall not proceed without formal approval by the appropriate
inspectorate.
‘W’ - Witness : A point beyond which work may proceed without formal documented approval by any of the
inspectorate. A Inspection Request to inform the client is required, however work may
proceed after 1 hour should the client fail to respond to the IR.
‘S’ - Surveillance : A point where Consultant and others may carry out surveillance of work in progress and
documentation associated on an unscheduled basis, with no notification required by any party
and without amendment to the scheduled programme.
‘R’ - Review : The documents are to be submitted to the appropriate inspectorate for review by
Consultant/Client. Note that where a document is subject to Client approval, work shall not
proceed until Client approval has been received.
‘Rcd’ - Record : Documents required for record purposes shall be filed and retained for Project Quality
records.
‘C’ - Action : Required steps shall be taken by Sub Contactor to complete the activity.
‘I’ - Inspection : A point where all evaluation / verification is made prior to commencing subsequent activity.
An IR to inform the client is required, however work may proceed without the client responding
to the IR.(Time frame for proceeding the activity without approval to be as per contract
conditions. )
CHEC Consultant
NO. DETAILS of REVISION
Checked Date Approved Date
A Issued for Review/ Approval
Project Name :- FOUR-STOREY COMMERCIAL BUILDING Contract No.:
ITP No. :
Revision : 00
ITP Title:- ITP for Internal and External Painting Works Date : 15-03-2014
o
Page N . : 2 of 6
ACCEPTANCE INSPECTION ACTION
Test Method Verifying/Co VERIFYING
INSPECTION / TEST STAGE CRITERIA / Frequency
(Visual or
DOCUMENTS CHE Consulta
SPECIFICATION /
document
ntrol Forms.
nt/IDL
TPI
PROCEDURE C
review)
1.0 A. GENERAL
Visual Prior to
Compliance with Project
1.1 Approval of documents Specs
/Document N/A N/A Start of H - W/R
review work
2.0
Material Delivery - Site
Inspection
Compliance with MAR Visual Specification On
Material Receiving Inspection and
2.1 and Material Delivery /Document N/A / Method Delivery to H - W/R
MTC Review note review Statement site
Internal Surface Painting-
3.0
Internal walls, Ceiling,
soffits and Steel doors,
frames
Mock Up Internal Painting - 600 x Method
600 mm or larger, applied in-situ statement / Pior to
Compliance with Project Method
3.1 walls, for QP selection and Specs
Visual Manufacturer’s
statement
Start of H - H
approval (adherence to below Recommendatio the Activity
n
procedure)
Surface prepration
1)Concrete surfaces:Removal of
loose and damaged paint, sanding Method
Suitable finish for statement /
on existing Method Each work
3.2 application of primer, Visual Manufacturer’s H - W
paint/plastered/rendered Moisture Content<12% Recommendatio
statement area
surfaces as recommended by n
selected paint
manufacturer/painting system.
‘H’ - Hold : A point beyond which work shall not proceed without formal approval by the appropriate inspectorate.
‘W’ - Witness : A point beyond which work may proceed without formal documented approval by any of the inspectorate. A
Inspection Request to inform the client is required, however work may proceed after 1 hour should the client
fail to respond to the IR.
‘S’ - Surveillance : A point where Consultant and others may carry out surveillance of work in progress and documentation associated
on an unscheduled basis, with no notification required by any party and without amendment to the scheduled
programme.
‘R’ - Review : The documents are to be submitted to the appropriate inspectorate for review by Consultant/Client. Note that where a
document is subject to Client approval, work shall not proceed until Client approval has been received.
‘Rcd’ - Record : Documents required for record purposes shall be filed and retained for Project Quality records.
‘C’ - Action : Required steps shall be taken by Sub Contactor to complete the activity.
‘I’ - Inspection : A point where all evaluation / verification is made prior to commencing subsequent activity. An IR to inform the client
is required, however work may proceed without the client responding to the IR.(Time rame for proceeding the
activity without approval to be as per contract conditions. )
CHEC Consultant
NO. DETAILS of REVISION
Checked Date Approved Date
A Issued for Review/ Approval
Project Name :- FOUR STOREY COMMERCIAL BUILDING Contract No.:
ITP No. :
Revision : 00
3.2 Verification of fire Installed per Visual / Each ceiling S Fire S S N/A
protection measures safety standards Document installation Protection
and project review Checklist
requirements
3.4 Final quality check of Free from visible Visual Each S Quality S N/A N/A
ceiling surface defects or surface inspection Checklist
issues
3.5 Check for ceiling stability Stable and Physical Each H Stability H W N/A
and structural integrity structurally inspection Report
sound
Legend:
‘H’ - Hold : A point beyond which work shall not proceed without formal approval by the appropriate
inspectorate.
‘W’ - Witness : A point beyond which work may proceed without formal documented approval by any of the
inspectorate. A Inspection Request to inform the client is required, however work may
proceed after 1 hour should the client fail to respond to the IR.
‘S’ - Surveillance : A point where Consultant and others may carry out surveillance of work in progress and
documentation associated on an unscheduled basis, with no notification required by any party
and without amendment to the scheduled programme.
‘R’ - Review : The documents are to be submitted to the appropriate inspectorate for review by
Consultant/Client. Note that where a document is subject to Client approval, work shall not
proceed until Client approval has been received.
‘Rcd’ - Record : Documents required for record purposes shall be filed and retained for Project Quality
records.
‘C’ - Action : Required steps shall be taken by Sub Contactor to complete the activity.
‘I’ - Inspection : A point where all evaluation / verification is made prior to commencing subsequent activity.
An IR to inform the client is required, however work may proceed without the client responding
to the IR.(Time frame for proceeding the activity without approval to be as per contract
conditions. )
CHEC C o n su ltan t
NO. D E T AIL S o f R E V IS IO N
Checked Date Approved Date
A Issued for Review/ Approval
P roject N am e :- F O U R -S TO R E Y C O M M E R C IA L C o ntract N o .:
B U ILD IN G
ITP No. :
Revision : 00
ITP Title:- IT P fo r Drainage System Date : 15-03-2014
Page N . : 2 of 6
o
‘H’ - Hold : A point beyond which work shall not proceed without formal approval by the appropriate
inspectorate.
‘W’ - Witness : A point beyond which work may proceed without formal documented approval by any of the
inspectorate. A Inspection Request to inform the client is required, however work may
proceed after 1 hour should the client fail to respond to the IR.
‘S’ - Surveillance : A point where Consultant and others may carry out surveillance of work in progress and
documentation associated on an unscheduled basis, with no notification required by any party
and without amendment to the scheduled programme.
‘R’ - Review : The documents are to be submitted to the appropriate inspectorate for review by
Consultant/Client. Note that where a document is subject to Client approval, work shall not
proceed until Client approval has been received.
‘Rcd’ - Record : Documents required for record purposes shall be filed and retained for Project Quality
records.
‘C’ - Action : Required steps shall be taken by Sub Contactor to complete the activity.
‘I’ - Inspection : A point where all evaluation / verification is made prior to commencing subsequent activity.
An IR to inform the client is required, however work may proceed without the client responding
to the IR.(Time frame for proceeding the activity without approval to be as per contract
conditions. )
CHEC C o n su ltan t
NO. D E T AIL S o f R E V IS IO N
Checked Date Approved Date
A Issued for Review/ Approval
P roject N am e :- F O U R -S TO R E Y C O M M E R C IA L C o ntract N o .:
B U ILD IN G
ITP No. :
Revision : 00
ITP Title:- IT P fo r Plum bing Date : 15-03-2014
Page N . : 2 of 6
o
1.0 A. Inspection of
Materials
‘H’ - Hold : A point beyond which work shall not proceed without formal approval by the appropriate
inspectorate.
‘W’ - Witness : A point beyond which work may proceed without formal documented approval by any of the
inspectorate. A Inspection Request to inform the client is required, however work may
proceed after 1 hour should the client fail to respond to the IR.
‘S’ - Surveillance : A point where Consultant and others may carry out surveillance of work in progress and
documentation associated on an unscheduled basis, with no notification required by any party
and without amendment to the scheduled programme.
‘R’ - Review : The documents are to be submitted to the appropriate inspectorate for review by
Consultant/Client. Note that where a document is subject to Client approval, work shall not
proceed until Client approval has been received.
‘Rcd’ - Record : Documents required for record purposes shall be filed and retained for Project Quality
records.
‘C’ - Action : Required steps shall be taken by Sub Contactor to complete the activity.
‘I’ - Inspection : A point where all evaluation / verification is made prior to commencing subsequent activity.
An IR to inform the client is required, however work may proceed without the client responding
to the IR.(Time frame for proceeding the activity without approval to be as per contract
conditions. )
CHEC C o n su ltan t
NO. D E T AIL S o f R E V IS IO N
Checked Date Approved Date
A Issued for Review/ Approval
P roject N am e :- F O U R -S TO R E Y C O M M E R C IA L C o ntract N o .:
B U ILD IN G
ITP No. :
Revision : 00
ITP Title:- IT P fo r Floor and W all Tile W orks Date : 15-03-2014
Page N . : 2 of
o
1.1 Material delivery Approved method N/A N/A Upon arrival at R S N/A
statement Visual site
1.2 Material storage Approved method Visual N/A N/A Daily W S N/A
statement inspection and
monitoring
1.3 B.Testing of
Materials
Testing the quality of N/A Technical
1.4 Approved method Visual/Docume As per W H/S R
materials Specification
statement/ Project nt Review required by
Specifications s Engineer
1.5 C.
INSTALLATION
Visual During
1.8 Layout works Approved drawings Visual Inspection/ N/A and after H H/W/R N
Checklist layout A
Visual
Inspectio
1.10 Floor tiles n/ During
Approved Visual Checklist N/A
installation installation W H/S/R NA
drawings/Approve
d method
statement
Approved Visual N/A
2.0 Wall tiles installation drawings/Approved Visual Inspection/ During H H/S/R NA
method statement Checklist installation
Grouting, cleaning
2.1 and protection works During and H/S W/R NA
for tiles Visual N/A
Approved method Visual after
Inspection
statement application
/
Checklist
Inspection on Visual After the
2.2
completed tile works Approved method Visual Inspection/ N/A installation H W NA
statement Checklist
2.3 D.DISPOSAL OF
WASTES
Removal of excess Approved method Project
2.4
materials and wastes statement Visual Specification Constructi During W S/R N/NA
gathered after the s on waste construction
work manageme and after the
nt disposal completion of
work
ITP No. :
Revision : 00
2.0
During Installation
2.1 Roof framing installation The dimensions of Visua/physical Continuous Framing W W W N/A
the prefabricated l Installation
roof structure shall Checklist
conform to the
approved shop
drawings.
3.5 Check for ceiling stability Stable and Physical Each Stability report S H W N/A
and structural integrity structurally sound inspection
Legend:
ITP No. :
Revision : 00
ITP Title: Inspection and Test Plan for Steel Structure & Metal Works Date : 15-03-
2014 o
Page N . : 2 of 6
INSPECTION
ACCEPTANCE
VERIFYIN ACTION
INSPECTION / TEST Test Verifying/ G Frequen
STAGE CRITERIA / Method DOCUME cy Cons
Control CH
SPECIFICATION / (Visual or
Forms. NTS
ultant/ TPI
PROCEDURE document EC IDL
review)
1.0 A. General
Review of quality
Pre-Inspection management
Each
1.1 Consultation systems and Visual
inspection
MOM
personnel
qualifications.
Before Manufacturing
Drawings and
documentation DWG,
DWG, Design, Documen Each
1.2 should be clear, Calculatio
Calculation Document legible, and easily
t review setup
n book
understandable.
Must meet the IR /
acceptance Approv
criteria specified N/A Welding ed IFC
1.3 WPS&PQR in the relevant
N/A
Book and
H H N/A
code (e.g., ASME Shop
Section IX). drawing
Qualification for Welders Drawings
Section Certificate
/Checklis Every
1.4 Accreditations 03300,Clasue Visual
t:
s
Pour
H R NA
3.04
SPLL/ALT
/CL-F-
002
Materials
During Fabrication
Components must be
aligned according to the
Visual/Dimen Each Each work
1.13 Joint Alignment Inspection design specifications,
sional inspection
Report
area
W S NA
with minimal gaps or
misalignments.
Dimensional and Visual Components must be
aligned correctly, with Visual/ Each work
1.14 Verification of Position, Alignment, minimal gaps or Dimensional
Each setup Report
area
W S NA
and Size misalignments.
Inspection of Welds for Quality, Any defects found
should be documented Each Each work
1.15 Defects, and Aesthetic and assessed for their
Visual
inspection
Report
area
I S NA
Considerations severity.
Documentation
Includes project name,
report number, date,
inspector’s name, and Each Each work N
1.20 Inspection Reports reference documents
Visual
inspection
Report
area
W S
A
(e.g., drawings,
specifications, ITP).
Tabulated or graphical
presentation of key data
points, such as Each N
1.22 Review Final Data Report inspection results, test inspection
Report NA R S
A
data, and non-
conformance rates.
VERIFYING Frequen
Pre‐Shipment Inspection DOCUMENTS cy
Test Method Verifying/Co
CRITERIA /
(Visual or
SPECIFICATION /
document
ntrol Forms. CHEC Consultant TPI
PROCEDURE
review)
Methods used to
protect the product
Method
1.23 Preservation and Packing from damage during Visual
statement
Report NA W S NA
storage and
transportation
Each Each
1.25 Loading Inspection N/A Visual
inspection
Report
work area
W NA NA
Shipping Document
1.26 N/A Each setup Packing List NA H NA NA
Control
LEGEND
Inspection Authorities :