Multiple Projects Tracking With Dashboard
Multiple Projects Tracking With Dashboard
25 6 7 3
%
0 5 10 15
Task22 Low
Total Result
t Dashboard TemplatJan 3, 2024 — Oct 16, 2024 Go to Project
7 3 5 1 5 1 82
%
10 15 20 25 30 0.0M
4
ar-2
ar-2
ar-2
ar-2
20-M
21-M
22-M
23-M
Data W T F
Due date Days left Progress Budget Actual cost
1/15/2024 -51 100% $1,000 $999
3/15/2024 -7 95% $1,000 $1,000
2/15/2024 -28 15% $23,000 $12,000
(empty) - $2,000 $0
9/5/2024 118 70% $22,000 $18,600
4/8/2024 11 30% $1,000 $1,001
5/20/2024 - 100% $43,000 $40,000
2/23/2024 -22 50% $6,000 $6,600
3/1/2024 - 100% $34,000 $33,700
9/23/2024 130 100% $11,500 $11,100
7/29/2024 - 100% $14,500 $15,700
3/20/2024 - 100% $1,800 $1,500
4/8/2025 270 30% $19,000 $21,300
4/22/2025 280 10% $3,800 $800
11/11/2024 165 25% $4,900 $2,000
9/5/2024 118 80% $5,000 $600
6/24/2024 66 $13,600 $0
(empty) - 30% $20,000 $4,000
4/10/2024 13 30% $16,000 $16,200
(empty) - $9,000 $0
10/24/2024 153 100% $43,000 $36,000
4/19/2024 - 100% $10,000 $12,000
2/27/2024 -20 5% $5,000 $4,500
1/19/2024 -47 70% $2,000 $2,000
2/20/2024 - 100% $22,000 $23,500
2/26/2024 -21 5% $23,000 $20,000
2/16/2024 -27 50% $6,000 $9,000
1/13/2025 - 100% $16,000 $16,300
64% $379,100 $310,400
22-M
ar-2
4
23-M
S
ar-2
4
24-M
S
ar-2
4
25-M
M
ar-2
4
26-M
T
ar-2
4
27-M
W
ar-2
4
28-M
T
ar-2
4
29-M
F
ar-2
4
30-M
S
ar-2
4
31-M
S
ar-2
4
1-Ap
M
T r-24
2-Ap
r-24
3-Ap
W
r-24
T
4-Ap
r-24
F
5-Ap
r-24
S
6-Ap
r-24
S
7-Ap
r-24
8-Ap
M
r-24
T
9-Ap
r-24
10-A
W
pr-2
4
11-A
pr-2
4
10-A
pr-2
4
11-A
T
pr-2
4
F
12-A
pr-2
4
13-A
S
pr-2
4
14-A
S
pr-2
4
15-A
M
pr-2
4
16-A
T
pr-2
4
Project Management Temp
Project manager Peter Maxwell Client
Project start date 1/1/2024 Sponsor
Project end date Total budget
Priority Status
Department Assignee Manager
dropdown dropdown
High In Progress Development Jenna A. Kevin J.
Medium Complete Marketing Davina B. Helen C.
Low In Review Security Jasmine C. Sasha H.
Critical! On Hold Design Tom D. Prudence P.
Blocked Content David E. Jason B.
Overdue Project management Samantha F.
Not started HR Alexander G.
QA George H.
Finance Peter I.
Support
Sales
Administration
SEO
Product management
Product 1
Product 2
Product 3
PR
Holidays Today's date: 5/1/2025
Show "i" 4
12/25/2024 notification
7/4/2024
Manage your project with
Go to Dashboard Go to Project Help
Plaky
Remaining tas 7
Total tasks 28
% Duration of project
Scroll bar: 79 Project
ALPHA
BETA
DELTA
GAMMA
OMEGA
Total Result
Remaining % of project
Duration of project
Tasks Status (empty) Number of tasks total 28
Task1 In Review Number of "Complete" task 7
Task2 In Progress Number of remaining tasks 21
Task5 On Hold
Task23 Not started Complete 25%
Task24 In Progress Remaining 75%
Task3 On Hold
Task6 Complete
Task7 Overdue
Task14 Complete
Task15 In Review
Task26 Complete
Task11 Complete
Task12 In Progress
Task16 In Progress
Task17 In Progress
Task18 On Hold
Task25 On Hold
Task27 Blocked
Task8 In Progress
Task13 On Hold
Task20 In Review
Task28 Complete
Task4 Overdue
Task9 Overdue
Task10 Complete
Task19 Overdue
Task21 Overdue
Task22 Complete
Today's date: 05/01/25
Help: How to use and custom
You may change the project title manually. There is no need to change the project start and end dates—these will u
as you change the start and end dates in the table, or as you filter the table.
Chart area:
Under the title bar, you’ll find the area showing the main project charts:
- The total completed percentage of the project,
- The status bar reflecting the number of tasks by status (hover over the bar to see what each color represents),
- The total budget spent, and
- The comparison between the planned and actual budget for the entire project.
These charts reflect the information from the table. In case they fail to present the accurate information, go to Dat
Title area2:
Under the chart area, you’ll find a field showing your project start date and project manager. These fields reflect th
table on the “Project table” tab.
Unlike the start and end dates of the project at the very top of the template that change as you update the project
data, this project start date will not change unless you change the start data in the “Project table” tab of the templ
To the right of this field, you’ll also find a “Go to Project” button that will lead you directly to the just mentioned “P
Left sidebar:
The slicers enable you to easily filter through the information in the table. You can have multiple filters applied to y
time.
The table can also be filtered using the arrow buttons at the top of each column. If you’d like to add more slicers to
And then choose which slicers you’d like to insert from the options you’re offered.
Main table:
The main table is a pivot table that reflects all the same data that exists in your “Project table” where you actually
case the table doesn’t show correct data, go to Data > Refresh
You can filter the information in the table using the arrow buttons at the top of each column or using slicers. The fi
reflected in the charts above, in the dates at the top of the page and in the Gantt chart.
Gantt chart:
The Gantt chart shows a visual representation of the start and end dates for your project tasks and their progress.
The main table is a pivot table that reflects all the same data that exists in your “Project table” where you actually
case the table doesn’t show correct data, go to Data > Refresh
You can filter the information in the table using the arrow buttons at the top of each column or using slicers. The fi
reflected in the charts above, in the dates at the top of the page and in the Gantt chart.
Gantt chart:
The Gantt chart shows a visual representation of the start and end dates for your project tasks and their progress.
The chart shows 30 days at a time. To see more days, move the scroll bar above the Gantt chart.
The weekends and holidays in the chart are marked with cross-hatching, and today’s date is marked with a blue co
line across the entirety of the chart.
The current Gantt chart is able to show up to 500 days. If you want to change the number of days shown in the Gan
the scroll bar, select “Format Control” and change the “Maximum value” to any number you want.
E.g., if your project is expected to last 2 years, you can increase the maximum value to around 750+. This will accou
with some wiggle room. This number can always be changed.
The name of the project manager and the project start date you write in this table will be reflected in the project d
main table.
Main table:
This is the main table meant to be used for tracking the actual project.
Project:
In the project field you can write down the name of each of your projects you
re tracking. When you add the name of the project next to a task that belongs to that project, you'll be able to filte
and see only the tasks related to a certain project.
Tasks:
In the tasks column you can break down each of your project into tasks/activities. Be sure to give them a short and
The column next to the “Task” column gives you a quick preview of the tasks that have been completed (will displa
tasks that are overdue (will display an X), or tasks whose deadline is 3 days or fewer away (will display a yellow “i” s
optional and you may delete it if you think it’s unnecessary.
Priority:
The priority column is where you set your subtask’s priority (low, medium, high, or critical) from the dropdown list.
To add or remove priority labels from the dropdown list, go to the “Settings” tab at the bottom left of the screen an
add/remove/change options in the “Priority dropdown” column. You may add new labels as long as there are gray
column. If you need more labels, you’ll have to insert a new row between rows 3 and 10 to get additional gray row
Priority:
The priority column is where you set your subtask’s priority (low, medium, high, or critical) from the dropdown list.
To add or remove priority labels from the dropdown list, go to the “Settings” tab at the bottom left of the screen an
add/remove/change options in the “Priority dropdown” column. You may add new labels as long as there are gray
column. If you need more labels, you’ll have to insert a new row between rows 3 and 10 to get additional gray row
Description:
This is where you add additional information and details about each subtask.
Department:
The department column is where you indicate which team is responsible for a particular task. There are options av
dropdown list.
To add or remove department options from the dropdown list, go to the “Settings” tab at the bottom left of the scr
add/remove/change options in the “Department” column. You may add new labels as long as there are gray fields
you need more labels, you’ll have to insert a new row between rows 3 and 50 to get additional gray rows.
Assignee:
The Assignee column is where you indicate which person is responsible for a particular task. There are options avai
list.
To add or remove assignee options from the dropdown list, go to the “Settings” tab at the bottom left of the screen
add/remove/change options in the “Assignee” column. You may add new labels as long as there are gray fields left
need more labels, you’ll have to insert a new row between rows 3 and 202 to get additional gray rows.
Manager:
The Manager column is where you indicate which person is responsible for the team/assignee for a particular task.
available in the dropdown list.
To add or remove manager options from the dropdown list, go to the “Settings” tab at the bottom left of the screen
add/remove/change options in the “Manager” column. You may add new labels as long as there are gray fields left
need more labels, you’ll have to insert a new row between rows 3 and 52 to get additional gray rows.
Status:
In the status column, you’ll be able to choose your subtask’s status from a dropdown list. There are currently 7 diff
available in the dropdown list.
To add or remove status options from the dropdown list, go to the “Settings” tab at the bottom left of the screen a
add/remove/change options in the “Status dropdown” column. You may add new labels as long as there are gray fi
column. If you need more labels, you’ll have to insert a new row between rows 3 and 15 to get additional gray row
Progress:
The progress column is a visual representation of each subtask’s progress. It does not pull information from any sou
updated manually. You can choose an option from the dropdown list, or type in a custom percentage.
NOTE: If you type in a custom percentage that doesn’t exist in the dropdown list, the cell will have a small triangle
and might indicate that there is an error in the cell. You may ignore this warning as this is a manually-updated colu
any of the calculations.
NOTE: If you type in a custom percentage that doesn’t exist in the dropdown list, the cell will have a small triangle
and might indicate that there is an error in the cell. You may ignore this warning as this is a manually-updated colu
any of the calculations.
The “Duration” column is where you write down the number of work days you expect your subtask to take (the cal
weekends and any designated holidays). Once you input the expected duration, the “End date” will automatically s
To add or remove holidays from the dropdown list, go to the “Settings” tab at the bottom left of the screen and add
options in the “Holidays” column. You may add new holidays as long as there are gray fields left in the column. If yo
holidays, you’ll have to insert a new row between rows 2 and 41 to get additional gray rows.
Once you have your end date, the “Days left” column will automatically calculate how many days you have left unti
your deadline has passed, how many days you are behind schedule.
Budget:
The “Budget” and “Actual cost” columns are where you can manually input your subtask budget and the actual mo
performing that task. The actual cost that exceeds the budget set out for that task will show up in red.
Important!
Please do NOT change or remove anything in the “Formulae for the dashboard” tab at the bottom left of the scre
dashboard might not work properly anymore.
nd customize this template Go to
Dashboard
Slicer
r subtask to start.
stom percentage.
r subtask to start.