UtilizationBIMforIntegrating-11052023-13
UtilizationBIMforIntegrating-11052023-13
net/publication/370682454
CITATIONS READS
7 5,088
2 authors:
All content following this page was uploaded by Ahmed Mohammed Abdelalim on 12 May 2023.
Abstract: Cost was adapted before using manual quantity surveying by spreadsheet that estimator take the quantity
from the 2D drawing and input data manually. With emerging Building Information Modelling (BIM) in
Architecture, Engineering, and Construction (AEC) industry. The concepts has changed then and BIM became
essential ruler in all phases of construction. allows project participants to design, analyse BIM, sequence, and explore
entire project model in contrast to CAD drawing, the object in BIM has also physical properties that drive object.
Traditional cost methods have been discussed and then BIM tools to show how it saved a lot of expected errors and
time along with third application have been introduced with an emphasis on construction cost estimating and its
relation to cost control without skipping 4D of scheduling as important key in decreasing or increasing the cost. Two
approaches for 4D scheduling in BIM. For the cost estimating capability, two available methods have been
discussed: i) list from the BIM tool to the estimating software such as MS Excel, ii) link BIM components to
estimating software, a case study is provided to demonstrates the cost estimating processes in BIM based on the BIM
model of a three-story training facility. The integrated cost database that builds with the model is the main key factor
for more accurate estimate and the purpose of this research is to improve the workflow of cost estimation and cost
control make it as a base for other researcher to work based on.
Keywords: Cost integration, BIM Cost estimation , Cost Data base , Worksets and Cost coding.
1. INTRODUCTION
BIM stands for Building Information modelling which is a computable representation of all physical characteristics of the
building and its related information. BIM is also known for its uniqueness of extracting data and calculations which means
what designer input can extract outputs. BIM provides a virtual view of the objects in the building with physical geometry
(2D or 3D) and other functional parameters. etc. Designers compose these BIM objects together to define a building model,
and this model incorporates both physical and functional information stored in the BIM objects. Once the building model
is completed, all the information can be generated by users for fabricating, analyzing, construction scheduling (4D BIM)
and cost estimating (5D BIM), and eventually, for facility management during operation phase of the building lifecycle.
1.1 – Cost estimate and Cost control
Cost estimate can be defined as the process of predicting cost to perform the scope of work specified by a project. Precise
cost estimation and effective cost monitoring are essential keys to construction project success. Project managers need to
rely on cost estimating workflow that enable them to initiate budgets and manage financial plans.
The Association for the Advancement of Cost Engineering (AACE) defines cost estimate as; "A predictive process used to
quantify cost and/or price of resources required by the scope of an asset investment option, activity, or project" (AACE
International 2011).
Rad (2002) defines it as "the art and science of using historical data, personal expertise, institutional memory, and the project
scope statement to predict the resource expenditure, and total cost of a project".
Page | 102
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
The cost estimate level of accuracy depends on the method that has been used and availability of cost data. With emphasize
on proper monitoring and control because without them the project may fail. Monitoring is the process of tracking various
operation during construction stage. Cost control indicates the direction of the changes in preliminary planning variable
compared with actual performance with the goal of avoiding unacceptable variations. Cost control involve ‘monitoring’
costs and recording data then analyse the data in order to take suitable actions before it become late to adjust. Once the
project starts, Control become the crucial stage for contractors which could affect substantially their profit.
For the cost control of a project, the construction plan and the associated cash flow estimates can represent the reference
basis for later project monitoring and control. With schedules, the progress of individual activities and the achievement of
milestone completions can be compared to the project schedule to monitor activity progress. Lists of contracts and services
provide the criteria for assessing and ensuring the required construction quality. The final or detailed cost estimate provides
a basis for evaluating financial performance during the project. To the extent that the costs are within the detailed cost
estimate, the project is considered to be under financial control. Exceedances in specific cost categories signal the possibility
of problems and provide an indication of exactly what problems are occurring. Certain items in the detailed estimate become
order cost elements. Expenditure incurred over the course of a project is recorded in specific job cost accounts for
comparison to the original cost estimates in each category. Thus, individual job cost accounts typically represent the basic
unit of cost control. Alternatively, labor cost accounts can be disaggregated or broken down into work items that relate to
both specific planned activities and specific cost accounts. In addition to the cost amounts, information about material
quantities and labor input is usually also stored within each work account Project budget.
2D drawings 3D models
Page | 104
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
Fig 3: The BIM application has the link with the standard codes
BIM comes with standard protocols and codes that can be chosen from as the following :
3.1 Standard protocol
National BIM Standard
• CSI (Control Sequence indicator)
• AEC UK ( Architecture , Engineering and construction UK)
• National BIM Library
• Open BIM (xBIM)
3.2 Standard classification
• MasterFormat (work result)
• UniFormat (functional elements)
• OmniClass (building elements categorizes)
• Uniclass (For all aspects of the design and construction process)
3.3 MasterFormat (work result)
So one of the ways that quantity is organized is by division through Masterformat as shown in Figure 4
Page | 105
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
Fig 6: Shows hierarchy that can be used to identify cost by building elements
Page | 106
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
In another word this Uniformat hierarchy is organized in three levels , first by major category then by major group Elements
then by group elements and then by individual elements as show in Figure 7
Page | 107
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
A contractor may use a combination of estimating methods in developing a cost for a design and build project. For example,
a client could be given a cost range for construction using the unit method and an elemental cost plan would be produced
when the client’s outline brief is received. Approximate (or builder’s) quantities are used to produce a formal tender and
when a
2. To collect cost information from a number of buildings, at various stages of development, thus improving the quality of
cost data for future projects.
The first step in cost planning is to advise a client of a budget at the beginning of the project. An example of a development
budget for construction costs is given in Figure 9 and 10
Page | 108
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
Page | 111
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
6. COST DATABASES
There is a number of ways to accurately estimate construction projects using Pre-Setup data bases either by using from
similar previous projects or manual (catalogues or books) or online or Pre setup programme that has collaboration with
BIM programmes.
Estimators have to be very cautious about using other similar projects that are old, because the cost estimation would be old
and reflecting the actual current costs.
The way that manual work is using the help of the printed book that has national average like RSMeans for North America.
For instance, to find a cost of specific material in cost data book in RSMeans like construction steel for office project. Using
the index of RSMeans cost book and narrowing in to steel or by using masterformat classification system like to flip division
5 (metals). Once the line for the required division is found and the type of the building for the steel by ton, then estimator
can take that specific price. The RSMeans for example will mention that 1 ton for structural steel for 1-3 stories for office
building is 2700$ for materials alone and 3900$ that includes the overhead and profit for installing contractor which is the
national average price. In order to adjust for specific city, estimator can go to the back of the book and use the city cost
index in the back of RSMeans which cover more than 900 locations through U.S and Canada. For example if estimator
willing to calculate the cost of material in Boston then in the back of the book the factor of percentage is 100.2 so to
calculate 1 ton for construction steel cost 1.002 x 2700$ which results in 2705 $ which is the cost of steel cost in Boston
without include overhead or contractor fees. So, estimator will go through the same process of finding the line items in the
book and transfer them into spreadsheet.
The same process for manual apply for the online but more quicker and efficient. The way it works through RSMeans online
by just entering the required data like the city and choosing the division for material.
RSMeans cost data is used with some third parties software developers who tried to make a link between BIM software (for
example: Revit) and RSMeans cost data.
Example:
Sigma estimate software plugin will try to add type codes that is empty in current project as in figure 15.
Page | 113
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
Sigma software estimate will match up the cost data prices for RSMeans with the wall type.
Figure 17: RSMeans cost data catalogue to match with the right wall type
So in Sigma estimator highlight the wall that match closely with cost data catalogue and beside it the price per unit as in the
below figure 18
Fig 18: matching the selected wall type with the plugin
The plugin also prove tracking for all missing elements that is not type coded for cost prices like in figure 19 so the
probability of any error for estimator is less.
The type codes which has been added to the wall as in the below figure 20 allow us select update from library and
automatically get the right assembly from the price book in the estimate as shown in figure 21, 22 and 23
Fig 20: Assigned code elements that can read from cost data library
Fig 21: linking assigned code elements with the library of RSMeans assemblies
Fig 22: Assemblies has now total costs for all quantities of the assigned code wall elements
Page | 115
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
Fig 24: That can include resources explanation for how total cost is being calculated
Page | 116
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
Fig 25: Model base estimate using BIM with specialized estimation software
8. IMPACT OF WORKSETS ON COST CONTROL
Multiple issues such as decrease in labour Productivity, poor recognition of construction needs, and lack of consistent and
professional construction management are hampering the construction industry.
This situation made the industry revaluate its performance and look into ways for improvement. Project integration is
essential for success; designers and constructors must collaborate and communicate effectively to keep budgets and
schedules on the right track. Technology is slowly breaking through construction management practices and new contractual
methods are emerging. One of these ways are worksets where dataset can be linked also to control the source of the major
portions and looking more closely to the elements by colours as shown below in figure 26.
Fig 26: Model base estimate using BIM with specialized estimation software
Page | 117
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
BIM improves technical work at the design stage by creating 3D models that integrate all building’s features and it better
represents the infrastructure’s requirements. Those models can also be enhanced if linked with schedule (4D) and costs
(5D); the construction can thus be better planned almost entirely at the design phase. Time and cost controls are very
important for any construction organization. Johansen and Wilson [3] questioned the necessity of intense construction
planning in the design phase; they reached a conclusion that there is reluctance within the industry to accept first planning
initiatives. Their major finding is that there is a lack of convergence between the design and construction team planning
ideas, thus preventing achievement of project success.
As WBS is activities assigned to building components in the project, these activities has duration and using such activities
concurrently can effectively reduce the cost.
As can be seen from figure 27. BIM model is used as the starting point of our process. Cash flow forecasting requires the
three processes of quantity takeoff, scheduling, and cost estimating. Stevens [6] Presented the integrated cost/schedule
performance curve that achieves cost and schedule control against project plan. Used as a visualization summary tool, it
can also be used as a model for predictions and forecasts. Perera and Imriyas [7] proposed the combined usage of MS
Access (database) and MS Project (scheduling) software as a project time and cost control system.
in construction. The author found that obtaining true values for tasks’ completion rate can be difficult and needs to be
developed along guidelines rather than actual measurements.
Cost data can be difficult to gather for the EVM model; such difficulties can thus alter the schedule variance and index.
The above referred to time, cost, and EVM control systems are proven resourceful for managing construction projects. BIM
is being increasingly present in the mind of construction practitioners. Eastman [16] presented BIM as a more integrated
design and construction process that results in better quality buildings at lower cost and reduced project
9. CONCLUSION
The overall objective of this research is to elaborate the connection between cost estimation and cost control in BIM
technology and also worksets integration in filtering the needed data for specific cost item. In feasibility stage client tries to
determine the size of the project which would meet his budget. The estimation of the project at this point is very rough.
Using BIM tools approximate building model can be linked to cost database and project price would be calculated more
Page | 118
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
efficiently along with model creation/modification process. The feature of using digitalized estimation that assemblies or
building elements can be tracked individually through highlight feature. Therefore, estimator can hide what has been
estimated and not missing what is still not estimated which will decrease errors in estimation. The variation between what
is planned as a cost and what is in the actual is the major problem that in this research building information modelling
played a role in minimizing that huge variance before. The process suggests starting from general estimating by square
meter to more detail through cost data references and stimulation the construction virtually to compare different processes.
The link that facilitate between quantities in BIM and cost data reference that results in the total price for specific proposal
is the major update for estimator in reducing their time and controlling the cost more than before.
10. RECOMMENDATION
The Integrated time and cost has the potential to improve the actual construction practices but more improvement is needed
through linking to cost data base in default with connection to worksets all together which is what is the new impact in this
research and all what it is about. Multiple benefits are identified from applying it to the actual project such as ability to
associate detailed cost values to each of the building model components during the design phase. facilitated estimating
process with automated outputs. Creation of a time and cost baseline that serves as a reference for EVM (Earned value
management) performance reporting at any time during the construction. Virtual design and construction already have
breakthrough but we can improve more based on this new system proposal, Engineering and construction managers must
promote its benefits first and drive its integration in the industry’s practices. Although, there are various benefits when
using BIM side by side with other estimation software programs for cost control, the learning curve required and the initial
cost for adapting multiple programmes could be the main barriers for the spread of this advanced technology which why
integration all of this elements in one platform is essential. In summary, the impact of BIM on cost estimation and cost
control is all about minimizing cost and accelerating progress which what this research is to accomplish.
REFERENCES
[1] Abdelalim, A.M. and Abo. elsaud, Y., 2019. Integrating BIM-based simulation technique for sustainable building
design. In Project Management and BIM for Sustainable Modern Cities: Proceedings of the 2nd GeoMEast
International Congress and Exhibition on Sustainable Civil Infrastructures, Egypt 2018–The Official International
Congress of the Soil-Structure Interaction Group in Egypt (SSIGE) (pp. 209-238). Springer International Publishing.
[2] Pearson, "Estimating in Building Construction", 7th edition , )2011(
[3] Abdelalim, A.M , Abd El-Hamid. M, Farag. S., CONSTRUCTION CONTRACTS’PRICING ACCORDING TO
CONTRACTUAL PROVISIONS AND RISK ALLOCATION.
[4] Yousri, E., Sayed, A.E.B., Farag, M.A. and Abdelalim, A.M., 2023. Risk Identification of Building Construction
Projects in Egypt. Buildings, 13(4), p.1084.
[5] Elbeltagi, E., Hosny, O., Dawood, M. and Elhakeem, A., 2014. BIM-based cost estimation/monitoring for building
construction. International Journal of Engineering Research and Applications, 4(7), pp.56-66.
[6] Hassanen, M.A.H. and Abdelalim, A.M., 2022. Risk Identification and Assessment of Mega Industrial Projects in
Egypt. International Journal of Management and Commerce Innovation (IJMCI), 10(1).
[7] Jiang, X., 2011. Developments in cost estimating and scheduling in BIM technology (Doctoral dissertation,
Northeastern University).
[8] Kim. H , Grobler.F . " Preparing a Construction Cash Flow Analysis Using Building Information Modeling (BIM)
Technology " , Journal of Construction Engineering and Project Management (2013).
[9] Hassanen, M.A.H. and Abdelalim, A.M., A Proposed Approach for a Balanced Construction Contract for Mega
Industrial Projects in Egypt.
[10] Medhat, W., Abdelkhalek, H. and Abdelalim, A.M., 2018. A Comparative Study of the International Construction
Contract (FIDIC Red Book 1999) and the Domestic Contract in Egypt (the Administrative Law 182 for the year 2018).
[11] Khedr, R. and Abdelalim, A.M., The Impact of Strategic Management on Projects Performance of Construction Firms
in Egypt.
Page | 119
Research Publish Journals
International Journal of Management and Commerce Innovations ISSN 2348-7585 (Online)
Vol. 11, Issue 1, pp: (102-120), Month: April 2023 - September 2023, Available at: www.researchpublish.com
[12] Ali Mohamed, N., Mohammed Abdel-Alim, A., Hamdy Ghith, H. and Gamal Sherif, A., 2020. Assessment and
Prediction Planning of RC Structures Using BIM Technology. Engineering Research Journal, 167, pp.394-403.
[13] Azhar, S.: Building information modeling (BIM): trends, benefits, risks, and challenges for the AEC industry.
Leadership Manag. Eng. 11(3) (2011)
[14] Abdelalim, A.M., 2019. Risks Affecting the Delivery of Construction Projects in Egypt: Identifying, Assessing and
Response. In Project Management and BIM for Sustainable Modern Cities: Proceedings of the 2nd GeoMEast
International Congress and Exhibition on Sustainable Civil Infrastructures, Egypt 2018–The Official International
Congress of the Soil-Structure Interaction Group in Egypt (SSIGE) (pp. 125-154). Springer International Publishing.
[15] Yong, N. W. Jr., Jones, S. A. and Berstein, H. M. (2008). “Building Information Modeling (BIM): Transforming
Design and Construction to Achieve Greater Industry Productivity.” SmartMarket Report, McGraw-Hill Construction,
New York.
[16] Abdelalim, A.M., El Nawawy, O.A. and Bassiony, M.S., 2016. ’Decision Supporting System for Risk Assessment in
Construction Projects: AHP-Simulation Based. IPASJ International Journal of Computer Science (IIJCS), 4(5), pp.22-
36.
[17] Jrade, A. and Lessard, J., 2015. An integrated BIM system to track the time and cost of construction projects: a case
study. Journal of Construction Engineering, 2015(3), pp.1-10.
[18] El-Kholy, A.M. and Abdelalim, A.M., 2016. A comparative study for fuzzy ranking methods in determining economic
life of equipment. International Journal of Construction Engineering and Management, 5(2), pp.42-54.
[19] Pratharnsap. T , "BIM and Cost Code", CAAD Silpakorn.
[20] Brook, M., 2016. Estimating and tendering for construction work. Taylor & Francis.
[21] Abdelalim, A.M., IRVQM; A Conceptual Framework for Integrating Risk, Value and Quality Management for
Construction Project Management.
[22] Stevens, W.M., 1986. Cost control: Integrated cost/schedule performance. Journal of Management in
Engineering, 2(3), pp.157-164.
[23] Ali Mohamed, N., Mohammed Abdel-Alim, A., Hamdy Ghith, H. and Gamal Sherif, A., 2020. Assessment and
Prediction Planning of RC Structures Using BIM Technology. Engineering Research Journal, 167, pp.394-403.
Page | 120
Research Publish Journals