0% found this document useful (0 votes)
13 views

MAKABE

The document outlines the Bills of Quantities (BOQ) for a proposed entrance building with shop frames at Makabe Parish, detailing costs for preliminaries, substructure, and superstructure works. The total cost estimate without VAT is 21,143,100 TSHS, with an additional 18% VAT bringing the total to 24,948,858 TSHS. The document includes specific quantities and rates for various construction activities and materials required for the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views

MAKABE

The document outlines the Bills of Quantities (BOQ) for a proposed entrance building with shop frames at Makabe Parish, detailing costs for preliminaries, substructure, and superstructure works. The total cost estimate without VAT is 21,143,100 TSHS, with an additional 18% VAT bringing the total to 24,948,858 TSHS. The document includes specific quantities and rates for various construction activities and materials required for the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

PROPOSED ENTRACE BUILDING WITH SHOP FRAMES AT - MAKABE PARISH

BOQ

BILLS OF QUANTITIES

APRIL, 2025
RATE
ITEM DESCRIPTION UNIT QTY AMOUNT (TSHS)
(TSHS)

BILL NO. 1: PRELIMINARIES

Mobilization and demobilization of work people, plants and


A SUM 500,000
tools

Demolition of existing structures excavation and levelling by


B SUM 300,000
mechanical means. Supervision Only

C Project Registration SUM 1,500,000

D Setting Out SUM 500,000

PRELIMINARY TO GENERAL SUMMARY 2,800,000

- 1 -
RATE
ITEM DESCRIPTION UNIT QTY AMOUNT (TSHS)
(TSHS)
BILL NO. 2: MEASURED WORKS

ELEMENT NO. 1: SUBSTRUCTURE

EXCAVATION AND EARTHWORK

A Excavation of pit for column bases and Foundation trench CM 90 7,000 630,000

B Blinding SM 34 3,000 102,000

C REINFORCEMENTS

20mm (8) Kg 235 300 70,500

16mm (50) Kg 926 300 277,800

12mm (30) Kg 323 300 96,900

8mm (30) Kg 143 300 42,900

D FORMWORK
Column bases SM 36 7,000 252,000
Column Starter SM 42 7,000 294,000
Ground beam SM 30 7,000 210,000
300,000
E CONCRETE WORK
Strip foundation CM 10 60,000 600,000
Column Bases CM 12 60,000 720,000
Column Starter CM 4 60,000 240,000
Ground beam CM 3 60,000 180,000

F 230 mm thick Plinth Wall SM 93 7,800 725,400

G Backfill and Compaction in layers SUIM 300,000

H Hardcore laying SM 84 3,000 252,000

I 100mm thick floor bed SM 84 6,000 504,000

Carried forward
Element No. 1 - Substructure 5,797,500

- 2 -
RATE
ITEM DESCRIPTION UNIT QTY AMOUNT (TSHS)
(TSHS)

ELEMENT NO. 2: SUPERSTRUCTURE - GROUND FLOOR


FRAME

Reinforced in-situ concrete; Grade 25 including


A vibration around reinforcements
Columns CM 10 60,000 600,000
Beams, Slab, and Gutter CM 22 60,000 1,320,000

Reinforcement, as described (provisional) High Yield


B steels to BS 4461
20mm (24) KG 706 300 211,800
16mm (99) KG 1,053 300 315,900
12mm (135) KG 1,436 300 430,800
8mm (110) KG 523 300 156,900

C Sawn Formwork to
Vertical sides of columns and the like SM 118 7,000 826,000
Sides and soffits of horizontal beams and gutter SM 169 7,000 1,183,000

D Walling

Blockwork; solid concrete block;BS 6073 type A,


compressive strength 4.0 N/mm2; in cement mortar (1:3)

150 mm thick wall SM 219 7,800 1,708,200

E ROOF WORK TREATED TIMBER


Truss 4x2 M 110 800 88,000
Purlin 3x2 M 80 600 48,000
Blandering 2 x 2 M 180 400 72,000
Gypsum board SM 45 2,000 90,000
Resin Coat Iron Sheets M 70 3,000 210,000

Allow for Entrace gate roof Structure and Decoration 2,500,000


F Including Masonry finishing

Carried forward
Element No. 2 - Superstructure - Ground floor 9,760,600

- 3 -
RATE
ITEM DESCRIPTION UNIT QTY AMOUNT (TSHS)
(TSHS)

Brought forward 9,760,600

FINISHING
Motor: Cement and sand (1:4) steel trowlled to smooth
hardness
A 15 mm thick to walls (indoor and outdoor) SM 586 3,500 2,051,000
B 15 mm thick to columns Nr 4 80,000 320,000

Preparation of floor
C Backings 40 mm thick to receive floor tiles SM 138 3,000 414,000

Carried forward
Element No. 2 - Superstructure - Ground floor 12,545,600

- 4 -
GENERAL SUMMARY

DESCRIPTION AMOUNT

A.BILL NO 1: PRELIMINARIES 2,800,000

B.BILL NO 2:MEASURED WORKS

Element No 1: Substructure 5,797,500

Element No 2: Superstructure

Ground floor 12,545,600

TOTAL BILL NO 2: MEASURED WORKS 18,343,100

TOTAL COST ESTIMATE(WITHOUT VAT) 21,143,100

Add: 18% VAT 3,805,758

CARRIED TO FORM OF TENDER


24,948,858