MAKABE
MAKABE
BOQ
BILLS OF QUANTITIES
APRIL, 2025
RATE
ITEM DESCRIPTION UNIT QTY AMOUNT (TSHS)
(TSHS)
- 1 -
RATE
ITEM DESCRIPTION UNIT QTY AMOUNT (TSHS)
(TSHS)
BILL NO. 2: MEASURED WORKS
A Excavation of pit for column bases and Foundation trench CM 90 7,000 630,000
C REINFORCEMENTS
D FORMWORK
Column bases SM 36 7,000 252,000
Column Starter SM 42 7,000 294,000
Ground beam SM 30 7,000 210,000
300,000
E CONCRETE WORK
Strip foundation CM 10 60,000 600,000
Column Bases CM 12 60,000 720,000
Column Starter CM 4 60,000 240,000
Ground beam CM 3 60,000 180,000
Carried forward
Element No. 1 - Substructure 5,797,500
- 2 -
RATE
ITEM DESCRIPTION UNIT QTY AMOUNT (TSHS)
(TSHS)
C Sawn Formwork to
Vertical sides of columns and the like SM 118 7,000 826,000
Sides and soffits of horizontal beams and gutter SM 169 7,000 1,183,000
D Walling
Carried forward
Element No. 2 - Superstructure - Ground floor 9,760,600
- 3 -
RATE
ITEM DESCRIPTION UNIT QTY AMOUNT (TSHS)
(TSHS)
FINISHING
Motor: Cement and sand (1:4) steel trowlled to smooth
hardness
A 15 mm thick to walls (indoor and outdoor) SM 586 3,500 2,051,000
B 15 mm thick to columns Nr 4 80,000 320,000
Preparation of floor
C Backings 40 mm thick to receive floor tiles SM 138 3,000 414,000
Carried forward
Element No. 2 - Superstructure - Ground floor 12,545,600
- 4 -
GENERAL SUMMARY
DESCRIPTION AMOUNT
Element No 2: Superstructure
- 5 -