Specification
Specification
SUMMARY OF CONTENTS
SECTION 1 - GENERAL 1 – 23
SECTION 8 - EARTHWORKS 8 – 12
SECTION 11 - ROADWORKS 11 – 21
GENERAL
1.1.1 Workmanship
1.2.1 The Scope of Works to be performed under this Contract shall comprise
the following tasks or activities summarised below:
1-1
4) Building works, finishes and fittings (Guard House, Concrete Platform and
Walkway)
a) Excavation works and raft foundation
b) Polythene sheet damp proof membrane laid under ground floor
c) To construct Guard House size 3m x 3m 2.8m high reinforced
concrete structure including foundation, footing, lightweight roof truss
covered with metal deck roof, wall finishes, floor finishes, door,
window, m&e fittings (lighting and 3 nos power point).
d) To construct 2 nos concrete platform for cabin
e) To construct concrete walkway with suitable gradient and connect to
concrete platform and new road.
1.3.5 Certificates
1-2
obtain the certificate and forward it to the Engineer within 7 days prior to the
date when the material or product is to be used in the Contract.
1.4 ABBREVIATIONS
1.5.1 Drawings
The Contractor shall submit to the Engineer for his approval drawings and a
method statement for all temporary works for sewer trenching, shoring,
1-3
jacking together with relevant design calculations prior to commencement
of that section of the Works.
All surveys shall include property boundaries and frontages. All survey
details are to tie in with boundary stones and benchmarks that are
applicable for the area.
Should the Contractor fail to supply the As-Built Plans and manhole data as
required within a reasonable period of the works, not exceeding 2 months
in any case, the Engineer shall have the right to cause such survey to be
carried out and drawings prepared by a Third Party appointed by the
Employer or Engineer. All costs and expenses incurred in connection
thereof shall be deducted from monies due or to become due to the
Contractor.
The Engineer will specify the format scales and sizes of drawings. The
Contractor is required to conform to that format and to the numbering
system derived by the Engineer.
1.6 MEASUREMENTS
1-4
standard sizes and dimensions in the imperial system of units may also be
used.
The Contractor must ascertain to his own satisfaction the scope of the
project and the nature of any other contracts that have been or may be
awarded by the Employer and the Contractor shall perform the Contract in
the light of such other contracts. Nothing herein contained shall be
interpreted as granting to the Contractor exclusive occupancy of the site of
the project. The Contractor shall not cause any unnecessary hindrance or
delay to any other contractor working on any project for the Employer.
The Contractor shall keep the Engineer and Employer informed of the
names of all subcontractors.
1.8 DISCREPANCIES
Within 14 days after the receipt of the Letter of Acceptance of Tender, the
Contractor shall submit to the Engineer for his approval a detailed program
showing the order or procedure and method in which the Contractor wishes
to carry out the Works and shall whenever required by the Engineer or his
Representative, furnish for his information particulars in writing of the
Contractor’s arrangement for carrying out the Works and of the
construction plants and temporary works, if any, which the Contractor
intend to supply or use as the case may be.
If at any time it should appear to the Engineer that the actual progress of
Works does not conform to the approved program referred to herein
1-5
If, in the opinion of the Engineer, the progress of the works is behind
schedule, the Engineer shall have the right to instruct the Contractor to
increase his plant and labour force and/or to continue work beyond normal
working hours, including night work in order to maintain the progress of the
work to his satisfaction. The Contractor is to allow here for any extra
expense (which shall include all additional expense connected with the
Employer’s and Consultants’ supervision of the Works) incurred from
complying with the Engineer’s Instruction to perform such work necessary
to adhere to the agreed Progress Schedule as no claim for extra payment
for additional labour or for working beyond normal working hours will be
entertained. In no case shall any night work be allowed without the written
permission of the Engineer.
A bar chart and critical path network diagram showing the order in which he
proposes to construct the various parts of the Works the dates on which it
is proposed that the work activities will be started and completed,
relationships between activities and the proposed dates for starting and
completing the construction of the principal Temporary Works. For the
purpose of this Contract, Temporary Works shall be defined as all works of
a temporary nature required to execute and complete the Works.
The Contractor shall supply a plant schedule listing major items of plant
and showing their time on site related to the operations described on the
bar chart.
1.9.3 Graph
The Contractor shall supply a graph showing the build-up of labour force
and supervision related to the bar chart.
Where progress has fallen behind the expected rate and the program, a
revised program must be accompanied by the Contractor's proposals for
increasing the rate of work to meet the new program. This will be required
within two weeks of the Engineer's request after acknowledgment by the
Engineer that the works are behind the expected rate and program.
1-6
The Contractor shall be deemed to have ascertained before the Tender
Date the extent and probable accuracy of the information and reference
points likely to be available to him and shall carry out all additional survey
work necessary for setting out the Works.
Elevations shown for the various parts of the work will refer to the LAND
SURVEY Datum. Where necessary, the Contractor shall establish the
necessary lines at the surface of the ground and at convenient locations for
the construction of the work. From the established base lines and Bench
Marks the Contractor shall extend the necessary lines and grades for
construction of the work and shall preserve all markers, and stakes set for
lines, Bench Marks, or measurements of the work in their proper places
until agreed by the Engineer. Any expense incurred in replacing said
stakes, which the Contractor may have failed to preserve, shall be borne by
the Contractor.
The survey of the works shall be presented in the format in the land office
standard revenue sheets. These shall from the basis on which all sewer
lines will be routed and determined on site.
Details, if any, of additional auger holes and borings which may have been
carried out by the Contractor on the location of the proposed Works should
be shown on the drawings by the Contractor and made available to the
Engineer.
1.11 RIGHTS-OF-WAY
The Contractor shall obtain consent from the property owners and shall
make his own arrangements and pay all expenses for the area, access,
wayleaves, etc. required by him to perform the work outside of the land
provided by the Employer.
The Contractor shall keep himself informed of all laws, ordinances and
regulations in any manner affecting those employed on the work, or the
materials used in the work, or in any way affecting the conduct of the work,
and of all orders and decrees of bodies or tribunals having any jurisdiction
1-7
or authority over the same. He shall at all time himself observe and comply
with, and shall require all his agents, employees and subcontractors to
observe and comply with all such applicable laws, ordinances, regulations,
orders and decrees in effect or which may become effective before
completion of this Contract, and shall protect and indemnify the Employer
against any claim of liability arising from or based upon the violation of any
such law, ordinance, regulation, order, or decree, whether by himself, his
employees, or his subcontractors.
The Contractor shall not transport plant and heavy equipment to and from
the work site until he has obtained the required permits and clearance from
the Public Works Department, the Local Authority and the Police.
All work performed within streets, roads, lanes and highways shall be in
accordance with the requirements of all relevant Local Authorities, Police
and other agencies for highway works control. It shall be the responsibility
of the Contractor to determine all requirements of said agencies and to
comply with their requirements.
All materials and work shall be available for inspection by the Engineer or
his authorized representatives and any work done in the absence of the
said Engineer or authorized representative may be subject to rejection on
interim or final inspection. The Contractor shall notify the Employer and
Engineer two working days in advance of any work to be done, in order that
inspection services may be provided.
The Engineer may at any time film operations being undertaken by the
Contractor using a video camera for proof that work is or is not being
constructed in accordance with the Specifications. The usage of such
measures will be notified to the Contractor at the time of filming. The
Contractor may also use this method to demonstrate his working method
etc.
1-8
1.14 MATERIALS IN GENERAL
The term "Materials" shall mean all materials, goods and articles of every
kind whether raw, processed or manufactured, and all equipment and plant
of every kind to be supplied by the Contractor for incorporation in the
Works.
All materials shall be new and of the kinds and qualities described in the
Contract and shall be to the satisfaction of the Engineer, that the material
offered is equal or superior to the material specified for the use to which it
is to be put and has obtained from the Engineer approval in writing to its
use. Where materials to be used for any component have not been laid
down in the specification, the Contractor shall use only those materials in
such compositions as have been proved in actual service to be the most
suitable for the particular purpose. New materials and methods may be
used only if the Engineer has given express permission.
Brand names are used herein merely to describe the nature of the desired
equipment and not used to endorse or indicate a preference for a particular
product or manufacturer. Goods, which have similar characteristics and
provide performance and quality at least equal to those specified, are
acceptable unless otherwise scheduled.
1-9
1.15.2 Tests and Samples
1-10
labor and material necessarily involved in the examination and replacement
shall be allowed to the Contractor.
The Contractor shall make his own arrangements to dispose off excavated
material to spoil tips and for possession of any additional land area he may
require for a working or accommodation space. He shall be responsible for
obtaining the consent of the owner, tenant or occupier of private land for
such use or for other temporary purposes. Before entering upon private
land, the Contractor shall confirm in writing to the Engineer that he has
obtained such consent.
The Contractor shall pay all costs, expenses, rentals, fees, compensation
or other disbursements which may be incurred by him or in negotiations
with owner, tenant or occupier and during the subsequent use by him of
such private land for temporary purposes in connection with this Contract.
The Contractor shall note that his responsibility shall apply to the whole of
the land occupied or used by him for the purpose of the Works.
The Contractor will be held responsible for all damage which he may do to
land or property outside his necessary working space. Compensation for
damage to such land or property will be assessed by the Employer for
settlement by the Contractor through the Employer.
The Employer will be entitled to withhold from any payments due to the
Contractor sufficient sums as may appear to him to be necessary to cover
the Contractor's liabilities until evidence is produced by the Contractor to
the Engineer to show that the Contractor's liabilities in this respect have
been finally settled and discharged.
1-11
1.17.2 Indemnified Claims
The Contractor shall provide and install suitable safeguards to protect such
objects from injury or damage, which objects if injured or damaged by
reason of the Contractor's operations, shall be replaced or restored to a
condition as good as when entered upon the work, or as required by the
specifications.
The owners of utilities the Contractor shall contact will include but not
limited to the following :
1-12
(v) Jabatan Pengaliran dan Saliran (JPS)
(vi) Keretapi Tanah Melayu (KTM)
(vii) Petronas with reference to gas pipelines
The Contractor shall notify utility owners affected and the Engineer
whenever utilities or services are encountered within the Contractor's work
area or proposed pipe route and shall not proceed with further work until
clearance has been obtained from the appropriate agency.
The Contractor shall not disturb any existing private sanitary facilities.
Unless otherwise indicated on the plans, all private sanitary facilities shall
be maintained by the Contractor and shall not be disturbed or disconnected
by him. The Contractor shall install temporary pipes of adequate size to
carry off sewage from any private sewer facilities cut off by construction
work. Connections to temporary pipes shall be made immediately by the
Contractor upon cutting of the existing facility. No sewage shall be allowed
to flow from any severed facility upon the ground surface or in the trench
excavation. Pipe used in temporary sewers may be clay, metal, concrete or
composition. Upon completion of work the Contractor shall replace all
severed connections and restore to operating order the existing sanitary
facilities.
The Contractor shall afford all reasonable protection to drains (of whatever
type) and culverts lying within the work site from damage during pipeline
installation. In the event of damage occuring to such drains and culverts
despite the Contractor's precautionary measures, the Contractor shall
repair or otherwise replace the same and to a standard of work approved
by the Engineer which shall not be lower than before the damage was
inflicted.
1-13
1.18.8 Fire Hydrant
The Contractor shall not draw any water from a fire hydrant for use on the
work, without first obtaining permission from the affected utility owner.
Access to all fire hydrants along the sewer alignments or within the areas of
work must be available throughout the entire period of work for the Fire
Department.
The Contractor shall make all arrangements and comply with all
requirements and regulations of the railway owner for crossing railway
lines. Any direct or consequential costs associated with such crossings
including permits, flagging and inconvenience charges, delays in obtaining
appropriate orders and procedures and/or uneconomic working
requirements (e.g. restricted work periods) shall be deemed to be included
in the Contract Price. A safe system of work shall be implemented and
which shall have the prior approval of the railway owner.
The Contractor shall make all arrangements and comply with all
requirements and regulations of Authorities responsible for over bridges
and under bridges encountered during the work.
The Contractor shall supply all requisite plant for the proper execution of
the work including scaffolding, tackle, machinery, pumps, tools, barricades,
lights or other appliances and everything necessary for the use of his
workmen, together with the carriage thereof to the spot where required and
for their erection, operation and subsequent removal. The Contractor shall
be responsible for the adequate protection of the Works and shall provide,
all footways etc. necessary for the passage of pedestrian traffic to all
buildings bounding the sites of the works, particularly with regard to the
collection of night soil. The Contractor shall provide and maintain all
necessary traffic barriers, lights and all other requirements to the
satisfaction of the Engineer, Local Authorities, Public Works Department
and Polis Di Raja Malaysia (Traffic Division).
At each point where work is being carried out on a roadway or in any other
place open to the public, the Contractor shall provide appropriate temporary
signs in accordance with the requirements for Temporary Sign specified in
the Road Traffic Ordinance, 1958 : Traffic Signs (Size, Colour and Type)
Rules, 1959 and all amendments thereof including the Traffic Signs (Size,
Colour and Type)(Amendment) Rules 1984. These signs shall comply with
1-14
the Ordinance in every respect and shall be finished in the appropriate
colours of reflective sheeting such as `Scotchlite' (Engineering Grade) or
similar. The Contractor shall comply with all the requirements of the
Railway Administration while laying sewers across railway lines.
The Contractor shall not commence work under any circumstances until the
Engineer is satisfied that an adequate number of barricades, lanterns, sign
and notices as described herein of this Specification have been provided
and are stored, ready for use, on the site.
The Contractor shall cause the least possible interference with existing
amenities, whether natural or man-made. No trees shall be felled except on
the instructions of the Engineer and clearance of the Site shall generally be
kept to the minimum necessary for the Works and Temporary Works.
Within a reasonable time (and in any case not less than 21 days) before he
intends to commence construction of any of the Temporary Works, the
Contractor shall submit full particulars, including drawings, of the same for
the approval of the Engineer. The submission to and approval by the
Engineer of any such particulars shall not relieve the Contractor of his
responsibility for the sufficiency of the Temporary Works or of his other
duties and responsibilities under the Contract. The Contractor shall make
safe and reinstate all areas affected by Temporary Works.
The Contractor shall keep the Works well drained until the Engineer
certifies that the whole of the Works is substantially complete and shall
1-15
ensure that so far as is practicable all work is carried out in the dry.
Excavated areas shall be kept well drained and free from standing water.
The Contractor shall construct, operate and maintain all temporary dams,
water courses and other works of all kinds including pumping and well-point
dewatering that may be necessary to exclude water from the Works while
construction is in progress. Such temporary works shall not be removed
without the approval of the Engineer. The Contractor is to take all
necessary precautions to avoid flotation of any partially completed
structure.
The Contractor shall make provision for the discharge or disposal from the
Works and Temporary Works of all water and waste products howsoever
arising, and the methods of disposal shall be to the satisfaction of the
Engineer and of any Authority or person having an interest in any pond or
water course over or in which water and waste products may be so
discharged.
The Contractor shall keep himself informed of all laws, ordinances, and
regulations governing the transportation, storage, and use of explosives.
The Contractor shall use the utmost care not to endanger life and property.
The Contractor shall be responsible for any and all damages resulting from
the use of explosives. No blasting shall be done which will damage
subsurface conduits or structures.
1-16
1.23.2 Access to Water Mains and Water Valves
The Contractor shall allow the free access to all water mains and water
valves by the Water Authority for purposes of operation and maintenance
of the same.
The Contractor shall at all times provide proper facilities for access and
inspection of the work by the Engineer, his representative, assistants,
inspectors, agents and representatives of public agencies and utility owners
having such jurisdiction.
The Contractor shall make all arrangements for the supply, installation,
operation, maintenance, and subsequent removal of temporary supplies of
electricity for the air conditioning, lighting and ventilation of all offices,
stores, laboratories, and other temporary buildings used by him and by the
Engineer in addition to any supplies he may require in connection with the
construction of the permanent Works. He will be responsible for the
provision of power to the sites for commissioning the Works.
1.24.3 Sanitation
The Contractor shall maintain the Site and all working areas in a sanitary
condition and in all matters of health and sanitation shall comply with the
requirements of the local Medical Officer of Health or other competent
authority.
1.24.4 Telephone
Any telephone facilities which the Contractor may install in connection with
the work shall be made available for use of the Engineer or his
representatives without charge. A separate telephone shall be provided for
the Engineer's Office.
1-17
restriction, bridge load limits and other limitations affecting transportation
and ingress and egress at the sites of work.
The Contractor shall erect, maintain, and remove suitable and approved
temporary fencing to enclose such areas of the Works and all areas of land
occupied by the Contractor within the Site as may be necessary to the
satisfaction of the Engineer. Where any temporary fencing has to be
erected alongside a public road, footpath etc., it shall be of the type
required by and shall be erected to the satisfaction of the Authority
concerned.
1.24.9 Office Equipment and Accessories for the Engineer (Not Included)
1.24.12 Signboard
The Contractor shall erect a signboard at each Site of the Project of size
2.74m x 4.08m at locations to be indicated by the Engineer. The signboard
shall be painted and the inscriptions on the boards shall be to the approval
1-18
of the Engineer. The signboard is to be erected immediately on
commencement of the Works unless otherwise approved by the Engineer.
The Contractor shall provide every assistance to the Engineer and his staff
in carrying out their duties and shall provide a sufficient supply of pegs,
poles, paint lines, spirit levels and other materials and small tools for
checking the setting out and for measurement of work. The Contractor shall
also provide for the Engineer and his staff such waterproof clothing, safety
helmets, rubber boots, torches and the like as may reasonably be required
by them, but these articles shall remain the property of the Contractor.
1.27 TEMPORARY OFFICES FOR THE S.O. AND HIS STAFF (Not Included)
The Contractor shall provide for the protection of all persons and property
at all times. The Contractor shall comply with the recommendations for safe
construction methods from the "Manual of Accident Prevention in
Construction", published by the Associated General Contractors of
America, Inc., to the extent that such provisions do not conflict with locally
applicable laws. Machinery and equipment shall be guarded in accordance
with the requirements set out in the Factories & Machinery Act 1967 or as
specified by the Factories & Machinery Department. The Contractor shall
take all necessary measures to protect the work and prevent accidents
during the construction. He shall provide and maintain sufficient night lights,
barricades, guards, temporary sidewalks, temporary bridges, danger
signals, watchmen and necessary appliances and to properly safeguard life
and property. He shall also protect all excavations, equipment and
materials with barricades and danger signals so that the public will not be
endangered.
1.28.2 Inconvenience
The Contractor shall so conduct his operations as to offer the least possible
obstruction and inconvenience to traffic, and he shall have under
construction no greater amount of work than he can handle properly with
due regard for the rights of the public. Where existing streets are not
available as detours, all traffic shall be permitted to pass through the work
with as little delay and inconvenience as possible, unless otherwise
authorised by the Engineer.
1-19
1.28.3 Trespassing
The Contractor shall be responsible for all damage or injury which may be
caused on any property by trespass by the Contractor or his employees in
the course of their employment, whether the said trespassing was
committed with or without the consent or knowledge of the Contractor.
The Contractor shall conduct his operations and activities in such a manner
that no operation shall be conducted which will emit into the atmosphere
any flying dust or dirt which might constitute a nuisance. The Contractor
shall take all measures to keep the flying dust caused by any construction
work or activities to its minimum.
The Contractor shall be responsible that all vehicles leaving the project site
must be sufficient cleaned/flushed prior to entering the public roads.
No naked light shall be used by the Contractor on or about the Site other
than in the open air without the permission in writing from the Engineer. If in
the Engineer's opinion the use of naked lights may constitute a fire hazard,
the Contractor shall take such additional precautions and provide such
additional fire fighting equipment (including breathing apparatus) as the
Engineer considers necessary.
The term "naked lights" shall be deemed to include electric arcs and oxy-
acetylene or other flames used in welding or cutting metals.
1-20
1.27.9 Site to be Kept Tidy
Throughout the progress of his work, the Contractor shall keep the Site and
all working areas in a tidy and workmanlike condition and free from rubbish
and waste materials. Any Temporary Works, Constructional Plant,
materials or other things which for the time being are not required for use
by the Contractor may with the consent of the Engineer be removed from
the Site, but otherwise shall be dispersed about the Site in an orderly
fashion and shall be properly and securely stored thereon.
The Contractor shall file with the Engineer, the names, addresses, and
telephone numbers of representatives who can be contacted locally, at any
time, in case of emergency. These representatives must be fully authorised
and equipped to correct unsafe or excessively inconvenient conditions on
short notice.
The Contractor shall arrange for gas testing equipment to be available and
used before entry to any manhole over 1.6 meters depth or any confined
space where gas may be present. In addition emergency escape sets
comprising breathing apparatus sufficient for 10 minus in gas should also
be provided. The Employer will provide information and guidance on safe
procedures which are effectively used in the United Kingdom and
adherence to their procedures will be required under the Contract.
On completion of the Works, the Contractor shall clear away and remove
from the Site all Constructional Plant, surplus materials, rubbish and
Temporary Works of every kind and leave the whole of the Site and Works
clear and in a workmanlike condition to the satisfaction of the Engineer.
Before application is made for the Employer to accept the Works, all items
of work shall be complete, ready to operate and in a clean condition. All
trash, debris, unused building material and temporary structures shall have
been removed from the site of the work. Tools and construction machinery
not needed for repair and adjustment consequent to operational tests shall
not be on the Site. The walkways, parking areas, roadways, streets and
lanes shall be completely swept and broomed.
1.29.1 Attendance
1-21
be discussed or resolved but only when requested by the Employer or
Engineer.
The Engineer will record minutes of each meeting and will furnish copies to
the Contractor within 5 working days thereafter. If the Contractor does not
submit written objection to the contents of such minutes within 7 days after
presentation to him, it shall be understood and agreed that the Contractor
accepts the minutes as a true and complete record of the meeting.
The dates, items and locations for the various meetings shall be agreed
upon and recorded at the preconstruction conference. Thereafter, changes
to the schedule shall be by agreement between the Engineer and
Contractor, with appropriate written notice to all parties involved.
J. Quality Assurance.
1-22
K. Forms and procedures for Contractor's submittals.
1-23
SECTION 4
4.1 DEFINITIONS
The following terms shall have the meanings hereby assigned to them :-
"Topsoil" means any surface materials, including turf, suitable for use in soiling
areas to be grassed or cultivated.
"Rock" means material which in the opinion of the Engineer would normally have
to be loosened either by blasting or by the use of pneumatic tools (excluding clay
spades worked on an air compressor) or by other rock quarrying methods or, if
excavated by hand, by the use of wedge and sledge hammers. An isolated solid
boulder or detached piece of rock shall qualify as Rock only if it exceeds 0.15
cubic metre in volume.
"Trench" means excavation of trenches into which pipes or excavation cables are
to be laid to levels and limits specified on the Drawings or otherwise directed by
the Engineer.
Before the surface of any part of the site is disturbed or the works thereon are
begun the Contractor shall take and record levels and cross sections along the
proposed line of excavation or any such part, in the manner specified or as
agreed with the Engineer in his presence and such levels when agreed with him
shall form the basis for measurement.
The Engineer shall have power to regulate, restrict or prohibit blasting if in his
opinion it is necessary to do so for the safety of persons or property or to
safeguard the works. No blasting shall be carried out in any part of the works
without the permission in writing of the Engineer. Such permission shall not
absolve the Contractor from any of this obligations or liabilities under the
Contract and he shall take all necessary precautions including the use of blasting
nets to avoid damage, loss or injury to persons and to public or private property.
4-1
The Contractor shall keep the Engineer fully informed at all times when blasting
is proposed to be carried out and of any details that may be required concerning
strength of charges and their positions.
The Contractor shall obtain the necessary permits and licences for the use,
storage, transport and handling of explosives and shall provide a store or stores
suitable for explosives in accordance with local regulations.
The Contractor at his own expense shall remove from the site all material
resulting from excess excavation and shall make good the same with such kind
of fill material or in such class of concrete as may be reasonably required by the
Engineer having regard to the circumstances.
All areas of the site marked on the Drawings or specified for clearance or from
which material is to be excavated or upon which filling is to be deposited shall be
cleared to the extent required by the Engineer of all buildings, walls, gates,
fences and other structures and obstructions and of all bushes, hedges, trees,
stumps, roots and other vegetation except for trees marked for preservation.
Material so cleared shall be disposed of off the site as directed by the Engineer.
4.6 TREES
4.7 STUMPS
Stumps and roots whether existing or remaining after tree felling shall where
directed by the Engineer be grubbed up and disposed of off the site. The
resulting hole shall be filled with approved material deposited in 225 mm layers
and compacted to the same dry density as the adjoining soil.
Items in the Bill of Quantities for site clearance shall include for clearing the site
all as specified including all fallen trees and their stumps. Site clearance shall be
measured as the area so cleared on plan to the Engineer's requirements and
instructions.
Where ordered by the Engineer topsoil shall be stripped, to such depths and over
such areas as he may direct, as a separate operation prior to any further
excavation which may be required.
4-2
4.10 GENERAL EXCAVATION
The ground shall be excavation by such methods and to such dimensions and
depths as shall allow for the proper construction of the works.
Where nominal `payment' limits of excavation are not shown on the drawings or
otherwise specified they shall be deemed to be the minimum net limits which
would allow the outline of the completed structure to be lowered vertically from
ground level into its final position. The Contractor shall make his own allowance
for any working space required, and any excavation outside the aforesaid limits
which has not been ordered by the Engineer whether it be excavated to suit the
Contractor's method of working or unavoidable overbreak or due to his
carelessness or error, shall be held to be excess excavation.
The line and level of trenches shall be as shown on the drawings or as directed
by the Engineer. Before commencing Trench Excavation, the route of the trench
shall be pegged out accurately and the existing ground levels shall be agreed
with the Engineer. Strong sight rails shall then be fixed and maintained at each
change of gradient, and at as many intermediate points as may be necessary.
On these rails shall be marked the centre line and the level to which the
excavation is to be carried out, such rails not more than 35 metres apart.
Trench Excavation shall be carried out by such methods and to such lines
dimensions and depths as shall allow for the proper construction of the works,
provided always that, unless the Engineer permits otherwise and subject to any
specific requirements of the Specification no Trench Excavation shall be less
than the widths stated below :-
4-3
shall be held to be Excess Excavation.
The sides of Trench Excavation shall be vertical unless the Engineer permits
otherwise.
Stones shall be removed from the trench invert and holes so formed shall be
filled with well compacted selected soft material. Where mechanical excavators
are used, the last 150 mm of the excavation shall be removed by hand to the
required depth, and the trench invert carefully trimmed true to level.
Trench Excavation shall wherever practicable be carried out in such a way that
every part of the excavation is at least 600 mm clear of the existing edge of the
carriageway. In any event the Contractor shall take special precautions, which
shall include the continuous support of the sides of the excavation, from the time
when excavation is begun until the refilling of the trench is placed, to ensure that
there is no disturbance of the adjacent road or road foundation.
For the purpose of measuring certain work in connection with Trench Excavation
"nominal limits" of Trench Excavation are stated above or as stated in the
drawings and any excavation outside these limits which have not been ordered
by the Engineer shall be held to be Excess Excavation.
The line and level of trenches shall be in accordance with the design criteria or
as may be directed by the Engineer. Before commencing trench excavations, the
route of the trench shall be marked out accurately and the natural ground levels
shall be made available to the Engineer. Strong sight rails shall then be fixed and
maintained at each change of gradient, and at as many intermediate points as
may be necessary. On these rails shall be marked the centre line and the level to
which the excavation is to be carried out, such rails being not more than fifteen
metres apart. Alternatively, the use of laser beam directional instrumentation
may be employed for the alignment of pipes in the vertical and horizontal plane.
The siting of the instrument should be checked prior to pipelaying and
conventional checks made by surveying instruments as the work proceeds.
In the event that obstructions not shown on the plans are encountered during the
progress of the work which will require alterations to the plans, the Contractor
shall have the authority to change the plans and effect the necessary deviation
from the line and/or grade with the agreement of the Engineer. The Contractor
shall not make any deviation from the specified line and/or grade without the prior
agreement of the Engineer.
All Trench Excavation and other work carried out within the limits of any road
reserve shall be completed as rapidly as possible and not more than half of the
width of the carriageway shall be obstructed at one time. A minimum width of 4
4-4
m wide or as required by the authority of traffic lanes shall have to be kept clear
for flow of traffic and where necessary the shoulder should be strengthened to
the satisfaction of the relevant Authorities at the Contractor's own cost. Road
drains and grids shall be kept free from obstruction.
Where trenches are excavated in public roads, road shoulders and footpaths of
congested areas necessitating carting spoil to distant tips, the Contractor shall
employ suitable plant to ensure that the passage of traffic past the works is not
impeded by the loading and unloading of spoil. Excavated materials shall not be
left standing on road pavement. All trenches on metalled roads shall not be left
open for more than one day and all trenches on road verges shall not be left
open for more than three days.
Tarmacadam and similar road surfaces shall be broken out neatly along the
trench line using a diamond disc road cutter to keep the edges straight and
vertical.
The Contractor shall take special precautions, including the continuous support
of the sides of the excavation from the time excavation is begun until refilling of
the trench is completed to ensure that there is no disturbance of the adjacent
road or road foundation. The Contractor shall also provide barricades to fence
off the works and approved road signboards placing at regular intervals to ensure
safety of the public and vehicles.
Trench excavation in surfaces other than roads shall include all surfaces except
those asphalt surfaces which require road reinstatement. These surfaces include
but are not limited to fields, paddy fields, pasture land and the like, footpaths,
verges, non-asphalted roads, lanes, alleys, and all private lands. Trench
excavation located in fields shall if the Engineer so requires have temporary
fencing erected around that length. Temporary fencing shall not be removed
without the Engineer's permission, which will not normally be given until the
trench excavation has been refilled and reinstated. All additional land occupied
temporarily by the Contractor must be reinstated back to satisfactory condition
immediately upon completion of that particular stretch of pipeline. The Contractor
is hereby notified that generally all sewer and force main alignments not in
streets are covered with a vegetation growth which must be removed and
disposed off the site of work. The Contractor shall have particular regard to the
safety of livestock in fields or which may be introduced to the fields, and shall
ensure that all open excavations, access routes and steep or loose slopes arising
from the Contractor's operations in these fields are adequately fenced and
protected. After the erection of temporary fencing where required, the Contractor
shall remove topsoil to such depth and over such area as may be necessary to
provide sufficient material to ensure adequate surface reinstatement of the
working areas occupied by the Contractor for construction of the pipeline.
Separate storage areas must be provided for topsoil and subsoil.
4-5
an agreement with the occupants along sewer rights-of-way for temporary living
accommodations during the period of construction in the vicinity of the work,
removal and reinstatement of the temporary building or portion affected by
construction and other conditions which may affect the occupants.
In the event that the Contractor fails to reinstate the property to the satisfaction of
the occupants along sewer rights-of-way, the Employer will be entitled to withhold
from any payments due to the Contractor sufficient sums as may appear to the
Employer to be necessary to cover the Contractor's liabilities until evidence is
produced by the Contractor to the Engineer to show that the requirements in this
respect have been finally settled and discharged.
The Contractor shall totally demolish and remove redundant structures on the
treatment works and pump station sites. Items to be removed may include
temporary wooden structures, concrete and masonry structures, concrete slabs
and footings, drains, roadway pavement, utilities and other surface
improvements. Utility companies shall be notified 30 days in advance of
demolition to allow them time to remove meters, materials and equipment for
salvage to the extent chosen by the utility companies. Items not removed by
utility companies shall be removed by the Contractor. Piping and wiring shall be
capped and disconnected in accordance with utility company requirements.
Remove all abandoned electrical conductors. All material to be demolished and
removed shall be removed from the Site to a legal disposal area. Burning will
only be permitted upon the Engineer's written approval. Contractor may salvage
any materials not required by the various utility owners and all such salvage shall
be the Contractor's property. Public sale or auction of Contractor's salvage is not
permitted on Employer's property.
Any material in the excavations which the Contractor considers may be classified
as Rock as defined in Clause 4.1 shall be notified to the Engineer before
excavation of the material is begun. The quantities of Rock or material alleged to
be Rock excavated from within the nominal limits of excavation shall be recorded
by the Engineer and the Contractor each day or at such shorter intervals as the
Engineer may require. Only such proportion of material so notified, recorded and
signed shall qualify for additional payment as Rock. Overbreak (that is
excavation outside the nominal limits of excavation) shall be kept to a minimum
and shall be held to be Excess Excavation.
Materials like shale and weathered sandstone strata may not be classified as
`Rock' within the meaning of Clause 4.1. These materials are tough and may
exceed conventional methods of excavation. Bulk excavation of these materials
shall include the use of an efficient parallelogram type ripper having a single
shank in sound working condition for attachment to a track machine also in
sound working conditions with a minimum weight of 24 tonnes and a nett power
rating of not less than 240 hp. These materials shall only be classified as `Rock'
when, in the opinion of the Engineer they cannot be ripped efficiently as
described above.
Not withstanding anything to the contrary in this Contract, the Engineer’s decision
as to whether or not the material of the excavation is to be classified as rock,
4-6
shall be final and without appeal.
The quantities of rock excavation given the Bill of Quantities are PROVISIONAL
only and do not necessarily represent the quantities that may be encountered.
Nevertheless the Contractor’s price for rock excavation will apply to whatever
quantities which are finally measured and at whatever depth the rock is
encountered and excavated.
The Contractor shall well and effectively support the sides and ends of all
excavations to prevent any fall or run from any portion of the ground outside the
excavation and to prevent settlement or damage to structure adjacent to the
excavation. Any extra excavation necessary to provide space for such support or
other working space shall be held to be Excess Excavation. If, for any reason,
any portion of the bottoms, sides or ends of any excavations shall give way the
contractor shall at his own expense take all necessary remedial measures
including the excavation and removal of all the ground thereby disturbed both
within and without the nominal limits of excavation and such extra excavation
shall be held to be Excess Excavation.
Where the Contractor elects and is permitted by the Engineer to execute trench
excavations with battered sides instead of providing support as aforesaid they
shall be excavated to stable slopes and heights at a slope of not steeper than
one to one from a point 0.3 metre above the top of the sewer pipe, and to a less
steep side slope where necessitated by ground conditions.
When excavating to specified levels for the foundation of any structure or pipes
or to specified limits for the faces of any structure required to abut against
undisturbed ground the Contractor shall not excavate the last 150 mm until
immediately before commencing the constructional work, except where the
Engineer shall permit other wise.
Should the Contractor have excavated to within 150 mm above these specified
levels or to within 150 mm of these specified limits before he is ready or able to
commence the constructional work he shall, where required by the Engineer,
excavate further so as to remove not less than 150 mm of material immediately
before commencing the constructional work and such further excavation shall be
held to be Excess Excavation.
4-7
4.22 TIMBERING
The term "Timbering" shall cover all normal methods of support including the use
timber, steel plate or such other materials as may be approved by the Engineer.
Unless otherwise provided in the Bills of Quantities, the Contractor shall allow in
his rates for excavation the supply and fixing of strong and sufficient timbering to
support the sides and/or bottom of the excavation when necessary to the
satisfaction of the Engineer and shall maintain the same until the Construction
work is sufficiently advanced in the opinion of the Engineer to permit the
timbering to be withdrawn, which shall be conducted only under personal
supervision of a competent foreman.
The Contractor shall be responsible for any failure of his timbering during fixing,
when in position, and for any injury to the work and any advice, permission or
approval given by the Engineer in respect of the removal of the timbering shall
not relieve the Contractor from the responsibility herein defined.
If, as the excavation are being filled in, it is necessary in the opinion of the
Engineer to leave in position any timber, the Contractor shall be paid for it at the
rates stated in the Bill provided that in the opinion of the Engineer the necessity
for leaving it in has not arisen from carelessness or neglect on the part of the
Contractor. Only the actual quantity of timber left-in will be paid for, payment will
not be paid for labour in cutting off at any level as directed by the Engineer nor
for the timber in ends thus cut off, nor for the disposal of additional surplus
excavated materials due to the leaving in of timber.
The Contractor shall keep the excavations clear of water by means of temporary
drains laid below the level of the permanent works and shall pump out all water
which may arise or flow into them.
The Contractor shall provide, form, fix, maintain and work, where and as directed
by the Engineer, such engines, pumps, chutes, wells, dams and both things
necessary for keeping the subsoil or accumulated water out of the excavations or
at a level below the bottom of any permanent works for such a period as the
Engineer may direct. After raising the water herein referred to, the Contractor
shall at once convey it away in such a manner as not to cause any nuisance or
injury. No new or existing pipe or culvert shall be used for the purpose of
carrying water away from the excavation without permission in writing from
Engineer. When new or existing pipes or culverts have been used for this
purposes, the Contractor shall be responsible for clearing out and removing all
silt, etc. before handing them over for their normal function. Any damage
whatsoever resulting from such use or cleaning out of new or existing pipes or
4-8
inverts shall be made good at the Contractor's expense.
All sumps and wells which may be required for the purpose for keeping the work
dry are to be sunk clear thereof, and care shall be taken to avoid undermining
any parts of the works by pumping. The Contractor shall afterwards refill and re-
install any such sumps or wells to the satisfaction of the Engineer and cost borne
by the Contractor.
If any foul or offensive matter arises or flows into the excavation or trenches, the
Contractor shall immediately remove it from the works without extra cost.
The Contractor shall provide adequate ventilation and efficient apparatus to keep
all excavations, trenches, tunnels and headings free from all gases whether
generated in the strata or arising from the use of explosives for blasting or
otherwise and he shall take precautions to ascertain that they are in a safe
condition before allowing workmen to descend.
When the specified levels or limits of excavation are reached the Engineer will
inspect the ground exposed, and if he considers that any part of the ground is by
its nature unsuitable he may direct the Contractor to excavate further. Such
further excavation shall be refilled to the specified levels or limits with concrete,
selected excavated materials or selected imported material as directed by the
Engineer but shall not be held to be Excess Excavation.
Should the material forming the bottom of any excavation, while acceptable to
the Engineer at the time of his inspection, subsequently become unacceptable to
him due to exposure to weather conditions or due to flooding or have become
puddled, soft or loose during the progress of the works, the Contractor shall
remove such damaged, softened or loosened material and excavate further by
hand. Such further excavation shall be held to be Excess Excavation.
Should the material being placed as filling or backfilling, while acceptable at the
time of selection, become unacceptable to the Engineer due to exposure to
weather conditions or due to flooding or have become puddled, soft or
segregated during the progress of the works, the Contractor shall at his own
expense remove such damaged, softened or segregated material and replace it
with fresh approved material.
4-9
The Contractor shall when placing the filling or backfilling make due allowance
for any settlement that may occur before end of the Defects Liability Period.
Where necessary, the Contractor shall at the end of the Defects Liability Period
remove any excess material or make up any deficiency of backfilling or filling to
the specified levels.
No length of trench excavation shall be started until the pipes to be laid in that
length are available on site. Trench Excavation shall be carried out expeditiously
and, subject to any specific requirements of the Contract, the refilling and surface
reinstatement of Trench Excavation shall be commenced and completed as soon
as reasonably practicable after the pipes have been laid and jointed. Joint holes
may be left unrefilled until the joints have been air tested and moulded or
protected.
Pipelaying shall follow closely upon the progress of Trench Excavation, and the
Contractor shall not permit the carrying out of Trench Excavation in unreasonably
excessive lengths until pipelaying matches up with the progress of Trench
Excavation. The Contractor shall take precautions to prevent flotation of pipes in
locations where Trench Excavations may be flooded and these precautions may
include the partial refilling of the trench leaving pipe joints exposed while awaiting
tests of the joints.
If the Engineer considers that the Contractor is not complying with any of the
foregoing requirements he may prohibit further Trench Excavation until he is
satisfied with the progress of laying and refilling of Trench Excavation.
For trench excavations to be backfilled with excavated material, soft material free
from stones of all kinds shall be deposited in 150 mm layers and thoroughly
rammed under and around the pipe with suitably shaped rammers working
alternately on either side of the pipe (particular care being taken to avoid damage
to the pipe and any sheathing) until the trench has been refilled up to the swell of
the pipe, and thereafter until the soft filling has been carried up at least 300 mm
above the top of the pipe.
The remainder of the refilling may consist of coarse material free from boulders
and clods of earth larger than 150 mm in size provided that the compacted refill
is, in the opinion of the Engineer, sufficiently dense to prevent material from the
superimposed layers being washed into the voids in such refill. This coarse
material shall be spread in layers of depth not greater than 225 mm and be
thoroughly rammed by an approved mechanical rammer or pan vibrator.
4-10
a two-tonne roller when the material is dried. Any part of the reinstated surface
that settled beyond the adjacent original ground level the Contractor shall have to
make good of the settlement to avoid formation of drains or gulleys within the
refilled trenches.
For trench excavation to be backfilled with sand material the sand material shall
be deposited in 150 mm layers on both sides of the pipe simultaneously and
thoroughly compacted and around the pipe working alternately on either side of
the pipe until the trench have been filled up to 150 mm above the top of the pipe
except for pipes laid in roads where the sand backfill shall be brought up to the
base course formation level. The sand vibrator and/or by an approved system of
water jet. The topping of the refilling for trench excavation as described above
for backfill with excavated material.
Sand filling material shall be from a source approved by the Engineer. Quarry
dust shall not be considered for use as filling material.
Where necessary the Contractor shall adjust the moisture content of the refill
material either by drying out or by adding water to assist the compaction of the
material.
Should the material to be placed as refilling, while acceptable at the time when
approved, become unacceptable to the Engineer due to exposure to weather
conditions or due to flood or have become puddled, soft segregated during the
progress of the works, the Contractor shall not use such material for refilling
trenches and shall only use fresh approved material.
Trench Excavation shall be refilled with concrete to the heights and limits as
shown on the Drawings and where directed by the Engineer.
Where in the opinion of the Engineer sufficient supply of the aforesaid soft
material for trench refilling cannot reasonably be obtained from Trench
Excavations within two hundred metres of the length of trench to be refilled
without resorting to sieving or other special means then the Engineer shall order
the Contractor :-
(a) to carry out such work as may be necessary to sieve out stones, or
(c) to excavate soft material from suitable borrow areas and transport it to the
length of trench to be refilled.
Temporary spoil tips may be used to store excavated material as required and
shall be arranged by the Contractor subject to the Engineer's approval having
regard to any particular requirements of the Contracts.
4-11
4.32 COMPACTION
Where necessary, the Contractor shall adjust the moisture content of the refill
material either by drying out or by adding water to assist the compaction of the
material. During compaction, the backfill shall have a uniform moisture content
equal to or a little above the optimum moisture content recorded in the
Compaction Test. Backfill shall be compacted to a dry density of not less than 95
per cent of the maximum dry density when tested in accordance with this
Specification.
Only material which is approved by the Engineer shall be placed in the temporary
spoil tips, topsoil being placed in separate spoil tips where so ordered. No tree
trunks, stumps, roots, branches or rubbish of any kind shall be placed in spoil
tips.
Subject to any specific requirements of the Contract, the Contractor shall make
his own arrangements for the temporary storage of any excavated material which
is required for use in refilling Trench Excavation, and backfilling to general
excavation including any necessary double handling. In this connection the
Contractor shall have regard to the working areas available to him for the
construction of the works. Any temporary tips alongside the excavations shall be
to stable slopes and heights.
The Contractor shall ensure that no excavated material which is suitable and is
required for re-use in the works is disposed off outside site.
Any excavated material not required or not suitable for use in the works shall
become the liability of the Contractor and he shall be entirely responsible for its
removal from the site and for its ultimate disposal. The Contractor shall comply
with all the regulations for the disposal of surplus excavated materials off the site
including the payment of royalties, fees, etc. which may be imposed by the
relevant Authorities.
The Contractor shall allow in his excavation prire for the removal and disposal of
all surplus excavated materials, earth, rubbish and waste matters. Suitable
material and topsoil surplus to the total requirements of the works and all
unsuitable material shall, unless the Engineer permits otherwise, be run to spoil
in tips provided by the Contractor. However, the Engineer may direct that
surplus materials be disposed of at particular locations in or around the Site and
his decision on this matter must be obtained before any surplus material is
removed from site.
4-12
The Contractor shall make all arrangements for the loading, transport, dumping,
spreading and compaction or removal of this material as above specified.
When removing surplus spoil, the Contractor shall dispatch, clear up all
carriageways, footways and verges affected by his work, and leave the site of the
works clean an tidy. If surplus spoil is tipped into or removed from private
property the operations shall be executed with the approval of and the least
possible inconvenience to, the owner and occupier of the same.
Where Trench Excavation is in road verges, fields and grassed areas the turf
previously removed will suffice for surface reinstatement providing that the grass
has not been killed during stacking and that the surface is free from all loose
stones.
After refilling Trench Excavation as specified, the Contractor shall replace all
topsoil previously removed and it shall be evenly distributed and levelled over the
full extent of the stripped area. The working space occupied by the Contractor
which was originally covered with grass if destroyed during the course of
construction shall be covered with 75 mm of topsoil, close turfed and maintained
until the new grass is properly established at the Contractor's expense. Other
areas not originally covered with grass shall be restored to their former state.
Road verges shall be restored to their original width and to a minimum fall of 1 in
24 away from the road and towards the ditch (if any). Restoration of the dip shall
be carried out unless the fact that no dip existed prior to pipelaying has been
recorded in writing and agreed to by the Engineer.
The Contractor shall restore all surfaces in a condition not inferior to that which
existed prior to commencement of works.
Any damage to the metalled road due to pipelaying work alongside road verges
or shoulders shall be reinstated to the satisfaction of the authority concerned at
no extra cost to the Government.
Where work is carried out within road reserve, the Contractor shall comply fully
with all regulations and requirements in force in that place by all relevant local
and public authorities (hereinafter referred to as Authorities).
The times of working allowed by the Authorities may or may not fall within day
light hours or within the normal working hours of the Authorities.
The Authorities may impose charges for works carried out on road verges and
metalled roads and the Contractor shall pay the Authorities and recover the cost
under the appropriate items in the Bill of Quantities.
4-13
4.37 SURFACE REINSTATEMENT IN ROADS AND FOOTPATHS
The consolidated surface shall be brought up to the same level or the adjoining
road. Any subsidence shall be filled in by the Contractor using the same
materials. The road shall be kept continuously at its proper level to the
satisfaction of the Engineer and the Authorities from the date of filling in the
trench until the surface is finally restored. All materials for this reinstatement and
subsequent maintenance shall be supplied by the Contractor.
When any section has been reinstated as specified the Contractor shall notify the
Engineer who in the presence of the Contractor shall inspect the length of
reinstated trench. The Engineer shall at this inspection indicate any further
reinstatement required and the Contractor shall complete this work to the
satisfaction of the Engineer and the authority concerned within fourteen days of
the inspection. Acceptance of reinstatement by the Engineer or the Authorities at
this inspection shall not relieve the Contractor of his responsibility for the
maintenance of surfaces as specified above.
Items in the Bill of Quantities for Restoration of Metalled Roads except where
expressly stated otherwise shall apply to road reinstatement. The charges if any
imposed by the Authorities for work carried out on metalled road shall be deemed
to be included in the relevant items in the Bill of Quantities under Restoration of
Metalled Roads.
Where the restoration is to be carried out by the Authorities, the Contractor shall
comply fully with all regulations and requirements as stipulated by the Authorities
and such restoration shall be deemed to have been restored by the Contractor.
The Contractor shall be paid in accordance to the appropriate rates in the Bill of
Quantities. Temporary reinstatement prior to final restoration shall be measured
separately in addition to permanent restoration.
If after due notice to the Contractor calling his attention to the necessity for
further reinstatement of any trenches across roads and footpaths, he has failed
to make good the reinstatement, the Government or the appropriate Authorities
may proceed with such repairs and the cost of such reinstatement shall be
deducted by the Government from any payments due to the Contractor.
Towards the end of the Defects Liability Period the Engineer will inspect the
pipeline route in the presence of the Contractor.
In the event that final road reinstatement is to be carried out by the Authorities
concerned, the Contractor shall carry out temporary reinstatement for the
vehicles to pass over it. The temporary reinstatement includes the trench to be
refilled with sand, topped with required thickness of crusher run material and
4-14
followed by a layer of tack coat and the required thickness of dense bituminous
mix wearing course. All filled materials shall be compacted by approved means.
The Contractor shall carry out final reinstatement of public roads and footpaths
only if he is instructed by the Engineer. Otherwise final reinstatement of these
roads will be carried out by the Authorities as and when agreed between the
Authorities, the Engineer and the Contractor. The Contractor shall pay the
Authorities and shall recover the cost under the appropriate items in the Bill of
Quantities. No quantities of final reinstatement beyond the limits of Trench
Excavation specified or reinstatement due to Excess Excavation, settlements
adjacent to Trench Excavations or damage to road surfaces in the course of
pipelaying shall be measured for payment.
Where land drains, mole drains or field drains are severed by Trench
Excavation they shall be kept in effective temporary operation during
construction of the pipeline. The Contractor shall submit to the Engineer for
approval a temporary drainage arrangement to ensure the water course is not
hindered during the construction.
The drain on either side of the Trench Excavation shall be cut-back for at least
300 mm and temporary pipes of suitable length and diameter shall be jointed to
the existing drain and laid resting with the ends on solid ground with suitable
stopping to prevent the subsequent run of land drainage water into the pipe
trench. During trench re-filling, the refill material shall be carefully placed and
thoroughly compacted under the temporary pipes to give them adequate
support.
At the appropriate stage of refilling the Trench Excavation the drains shall be
permanently restored to the satisfaction of the Engineer.
Information relating to the positions of all existing mains, cables, culverts, pipes,
drains or services of any kind shall be ascertained by the Contractor.
Notwithstanding any information which may be furnished by the Engineer, the
Contractor shall be responsible for ascertaining from his own inspection of the
site and from the respective supply authorities and other public authorities the
positions of all mains, pipes and cables whether underground or overhead,
within or near the site. Where services are shown on the drawings or where
there is evidence of services in the ground, the Contractor shall also determine
their exact positions. In addition the Contractor shall watch for and determine
the position of any service which may not have been marked.
Where Trench Excavation is carried out close to or across the line of sewers,
pipes, cables and other services the Contractor shall provide temporary
adequate supports to secure the services and where such sewer, pipe, cable or
other service is temporarily displaced or disturbed it shall be restored to its
4-15
original state. If restoration or any service to its original state cannot be
achieved then it shall be replaced and made good. The cost of excavating
around any service which crosses the trench, and of temporally supporting it
while pipelaying is undertaken, shall be deemed to be included in the rates for
excavation.
All damage to drains, kerbs, services etc shall be made good to the satisfaction
of the Engineer and the authorities concerned. The cost of making good any
damage shall be deemed to be included in the rates for excavation. In the event
that any damaged services shall only be repaired by the authority concerned, all
costs whatsoever relating to the repairing of the damaged service undertaken by
the authority shall be at the Contractor's expense. Where damage to a service
had already existed prior to excavation or other work, repair of the damaged
service shall be undertaken by the Contractor, if so ordered by the Engineer and
the Contractor shall be paid on Daywork for repairing such service.
Where pipes are laid under culverts they shall, subject to other provisions in the
Contract and to the Engineer's instructions, be given a concrete surround
extending for 600 mm clear on each side of the culvert, and a concrete half
haunch to the culvert shall be provided over the width of the trench cast directly
on top of the concrete surround. The cost of all work in removing any piles and
concrete bend under culverts and of temporarily supporting the culvert during
pipelaying shall be deemed to be covered by the rates for the items in the Bill of
Quantities for pipe crossing under culverts.
Where the Trench Excavation passes under barriers such as hedges, fences
and walls the Contractor shall, as a temporary measure during construction of
the pipeline, provide temporary fencing for any parts of such barriers as have
had to be removed.
After trenches have been refilled and surfaces reinstated, the Contractor shall
carry out work as the Engineer may order for permanent restoration of such
barriers. In the case of a hedge the section removed shall be replaced by new
plants of the appropriate variety and where ordered by the Engineer, the plants
shall be protected from livestock on both sides by an adequate post and barbed
wire fence. During the Defects Liability Period all hedges replanted in the above
manner shall be inspected and any dead plant replaced by the Contractor.
Where the pipeline crosses underneath rivers culverts and other watercourses
the Contractor shall be deemed to have allowed for all the additional measures
necessary for the proper construction of the pipeline including maintaining the
full flow of water.
4-16
4.43 MEASUREMENT OF GENERAL EXCAVATION
Items in the Bill of Quantities for "excavation" except where expressly indicated
otherwise shall apply to excavation where Bulk, Incidental or Trench in any
material and shall not only include for all work in connection with excavation but
shall also include for all loading and transportation, temporary fencing, double
handling, filling, backfilling and for disposal of surplus materials, the means of
disposal being the Contractor's responsibility.
Items for "Excavation in Rock" shall include for any allowance the Contractor
considers necessary to cover overbreak and the making good thereof.
Items for Trench Excavation shall apply to excavation in any material and shall
include not only for all work in connection with excavation but also for refilling of
trenches spreading and compacting excavated material over pipeline reserve as
directed and for disposal of surplus material, for temporary fencing and, in fields,
for the stripping and subsequent reinstatement of the top surface all as specified.
Trench Excavation shall be measured by length along the centre line of the
pipeline at the various depths stated in the Bill of Quantities and the Contractor
shall be deemed to have made his own assessment (subject to any specific
requirements of the Contractor) of the widths of Trench Excavations necessary
for the proper construction of the works including all allowances to provide
support for the excavations, to accommodate joints and bends in the pipeline and
to provide working space. The length of Trench Excavation shall be measured
through and including any space occupied by manholes, chambers, thrust blocks
and the like. No extra payment shall be made for trenches which are curved in
plan or elevation.
The depth of Trench Excavation for pipes shall be measured normal to the profile
of the ground along the centre line of the trench from the original ground level of
where appropriate from the ground level remaining after the completion of any
general excavation down to the specified invert level of the pipe. The
Contractors shall allow for additional excavation required for the thickness of
bedding for sewer pipe as specified and shown on the drawing.
4-17
The sides of Trench Excavation shall be deemed to be vertical in all materials
and the nominal widths defined in Clause 4.11 shall apply to any depth of trench
and whether or not bedding or surround to the pipe is specified.
Rock, shall be measured as the volume of Rock within the nominal limits of
Trench Excavation in Rock.
Excess Excavation and the backfilling thereof shall not be measured for
payment.
Trench Excavations in roads and in footpaths as specified shall be measured
(E.O. Trench Excavation) as the area calculated by multiplying the length of
trench so excavated by its nominal width. The stripping of the top surface and
the surface reinstatement of Trench Excavation in road verges, fields, etc. shall
be included in Trench Excavation and shall not be separately measured.
Crossing hedges, fences and walls shall include for all temporary measures
for dealing with such barriers as specified and shall be measured as the length of
such barriers so dealt with within the nominal width of Trench Excavation. Any
permanent measures required by the Engineer shall be ordered by him as
additional work.
Crossing rivers culverts and other watercourses shall include for all additional
measures necessary to make the crossings as specified. Only such crossings as
may be itemised in the Bill of Quantities will be measured (E.O. Trench
Excavation) for additional payment. The length of measured for payment for
crossing natural watercourses shall be defined as the width of the waterway
along the pipeline at the time of construction of the crossing (except flash floods
and floods).
Items in the Bill of Quantities for "forming embankment" for roadwork, for raising
the ground level of the site or for filling under structures shall include for the
supply, spreading, compacting and shaping all as specified.
Filling for embankment shall be measured as the volume after compaction of the
fill material placed to the limits and depth shown on the Drawings or ordered by
4-18
the Engineer. The Contractor shall be deemed to have made his own allowance
for compaction and for any "loss" of material into the ground below the
embankment.
(a) 75% of the total amount due will be paid on completion of pipelaying.
(b) The remaining 25% for any length, will be due on completion of
restoration of the final surface, including reinstatement of all surface
damage, completion of chambers, thrust blocks, etc.
Payment for the second stage shall be due only after restoration of any length
has been inspected and approved by the Engineer and by any relevant authority.
Payment for the separate items in roads, footpaths, etc. will be made at the
same time as the second stage payment for excavation.
Topsoil shall be evenly spread and trimmed over embankments and other areas
to the slopes and levels shown on the Drawings or ordered by the Engineer. The
depth after spreading and trimming shall be 75 mm unless otherwise directed,
measured normal to the surface. All clods and lumps shall be broken up and any
rubbish, stones, roots and weeds shall be removed.
4.48 TURFING
Where turf is laid on slopes steeper than 1 on 3.0, each turf shall be securely
pegged down with two cleft wooden pegs 150 mm long.
All turfed areas shall be lightly rolled with an approved roller or punned
immediately after laying, and shall be watered regularly until the grass has been
established.
Items where included in the Bill of Quantities for spreading topsoil shall include
for obtaining topsoil from spoil tips on the site, hauling and spreading all as
specified.
Items where included for turfing shall include for all work in connection with
turfing as specified, and for cutting and trimming and weeding at least once a
month until the end of the Defects Liability Defects.
4-19
expressly indicated otherwise items shall apply to sloping as well as to horizontal
surfaces.
Topsoiling and turfing of re-filled trenches shall be included in items for Trench
Excavation and shall not be separately measured for payment.
Payment for continuous turfing shall be the area covered by the turves provided.
Where spot turfing is required the distance between the centre lines of divots in
the form of a triangular pattern shall not exceed 500 mm and the percentage of
the area covered shall be agreed and payment made on the total area spot
turfed multiplied by the percentage.
(a) at fifty percent of the Contract Rate when the turfing has been carried out;
(b) at fifty percent of the Contract Rate when the Engineer is satisfied that
the grass has established itself.
Where grass fails to establish itself, the Contractor shall turf the relevant area
again at no extra cost to the Government.
The Contractor shall pay to all Authorities all deposits, fees and charges required
to be paid in relation to the execution of the works or to any temporary works.
If after due notice to the Contractor calling his attention to the necessity for the
payment of fees and/or charges to the Authorities the Contractor has failed to
make payment, the Employer shall be entitles to pay such fees and/or charges
direct to the Authorities concerned out of any moneys at any time due to the
Contractor under the contract and such payment shall be deemed to be payment
made to the Contractor under and by virtue of the Contract.
The cost of all fees and charges payable by the Contractor shall be deemed to
be included in the Contract Rates unless otherwise expressly provided for in the
Bill of Quantities.
4-20
SECTION 8
EARTHWORKS
Before the surface of any part of the Site is disturbed or the works thereon are begun,
the Contractor shall conduct all necessary checks to satisfy himself that the levels of
any such part do not differ significantly from drawings or measured directly by any of
his agents or sub-contractors. Any discrepencies which may necessitate design
changes or which may affect the full functionality of the permanent works shall be
brought to the attention of the Engineer. The levels so measured prior to
commencement of works shall be recorded and confirmed in the presence of the
Engineer.
The entire area within the limits of earthwork as indicated shall be constructed to the
lines, grades, elevations, slopes and cross sections indicated on the drawings with
added allowance for the thickness of lining and walls where required. Slopes and
drainage features shall present a neat uniform appearance upon completion of the
work and shall be approved by the Engineer. Excavated materials meeting the
requirement of fill materials may be conserved for subsequent use of placed as earth
fill immediately after excavation upon approval of the Engineer. Large rocks
unacceptable as earth fill material may be stockpiled for use as subject to all
requirements specified for being met in the specifications. The suitability of re-use of
excavated material for specific purposes shall be determined by the Engineer, and the
Contractor shall not waste or otherwise dispose of suitable excavated material. All
excavation shall be performed under the limitations and requirements set out in the
sections of this specification pertaining to control of water.
8.3 EARTHWORK
Earthwork shall include all site preparation, excavation of all materials of whatever
nature encountered, handling, hauling and compaction of required fill materials,
disposal of all excess excavated material, shoring and protection work, preparation of
subgrade, dewatering as necessary, protection of adjacent property, backfill, surface
reinstatement, and embankment to the lines and grades indicated in the drawings.
All excavation works exceeding 1.2m in depth shall be adequately supported at the
sides in a manner agreed to by the Engineer to safeguard the work and workmen, to
prevent sliding or settling of the adjacent ground, and to avoid damaging existing
improvements. The width of the excavation shall be increased if necessary to provide
space for sheeting, bracing, shoring, and
8-1
other supporting installations. The Contractor shall furnish, place and subsequently
remove such supporting installations as necessary.
When the quantities of suitable materials obtained from specified excavations are
insufficient to construct the specified fills, additional materials shall be obtained from
approved borrow areas. Borrow pits shall be excavated and finally dressed in a
manner to eliminate steep or unstable side slopes or other hazardous or unsightly
conditions. The extent and depth of borrow pits within the limits of the designated
borrow areas shall be approved by the Engineer.
The Contractor shall furnish, install and operate all necessary machinery, appliances,
and equipment to keep excavations free from water during construction and shall
dispose of water so as not to cause injury to private property, or to cause a nuisance
or menace to the public. Berms shall be provided to prevent surface water from
draining into structural excavations. Earth banks shall be suitably protected from
damage by erosion during construction.
When excavating headings, tunnels and shafts, the Contractor shall provide sufficient
spoil storage capacity to avoid the need to remove excavated material from shaft
sinking, heading or tunnel driving compounds between 19.00 hours on any day and
07.00 hours on the following day. It shall be the responsibility of the Contractor to
decide the need for, and to undertake, any ground investigation ahead of the face of
any tunnel, heading or shaft.
Excavations for headings and tunnels shall be adequately supported at all times. The
faces of all headings and tunnels, other than in solid rock, shall be fully boxed
whenever excavation has been, or will be, stopped for a period exceeding 12 hours.
All working shafts shall, unless otherwise permitted, be supplied with speaking tubes
or telephones in communication with the Works below ground. Such tubes or
telephones shall be provided with coloured light signalling systems.
Tolerances for driving headings or tunnels shall be horizontal ±75mm and vertical
±75mm in 30 metres.
8.8.1 License
The Contractor shall obtain all necessary licenses and permits for the storage,
transport, handling and use of explosives and shall provide a store or stores suitable
for explosives in accordance with local regulations.
8.8.2 Responsibility
The Contractor shall be solely responsible for injury to persons or property that may
result from his use of explosives, and the exercise of, or failure to exercise control on
the part of the Engineer shall in no way relieve him of responsibility for injury or
8-2
damage resulting from their use. He shall take all necessary safety precautions
including the use of blasting nets, shields or other safety devices to avoid damage or
loss of property, or injury to persons, during blasting operations.
8.8.3 Supervision
All blasting shall be done under the supervision of a competent blasting expert, and
subject to Malaysian regulations for blasting.
8.8.4 Storage
Only small amounts of explosives shall be kept underground, well ventilated and
under lock, the key to be only in the hands of a trustworthy person. Caps and
exploders shall not be kept in the same place as explosives. Blasts shall be properly
matted and securely covered.
The Engineer shall have power to regulate, restrict or prohibit blasting if in his opinion
it is necessary to do so for the safety of persons or property or to safeguard the
Works. No blasting shall be carried out in any part of the Works without the
permission in writing of the Engineer. Such permission shall not absolve the
Contractor from any of his obligations or liabilities under the Contract.
Electrical detonators should be able to operate safely in the area where blasting is
carried out without causing interference to radio services. Special precautions should
be taken to warn operators of radio equipment to stop transmitting in any area in
which blasting operations are in progress. Blasting operations should be discontinued
when there is the likelihood of lightning strikes.
8.9.1 Definition
Presplit and Postsplit are controlled blasting techniques. In the former, fracture
surfaces are developed along a design slope by drilling holes in the plane of the slope
and simultaneously detonating light charges in these holes prior to bulk blasting in the
main area to be excavated.
8-3
8.9.2 Objective
8.9.3 Workmanship
All materials and workmanship shall be in accordance with the appropriate current
British Standards or Codes of Practice except where the requirements of the
British Standards/Codes of practice are in conflict with this Specification in which
case the content of this Specification shall take precedence.
Before any blasting is carried out, the Contractor shall submit to the Engineer for
approval the description of the method he proposes to adopt to carry out the
controlled blasting and excavations in the bedrock giving full particulars of the
plant, equipment and material required for the drilling, charging, blasting and
excavation of rock.
The Contractor's attention is drawn to the existence of structures and homes close
to the boundary of the site. The Contractor shall take all necessary precautions to
ensure that his proposed method of blasting and excavation does not pose any
danger to the people and property adjoining the boundary of the project site. The
Contractor shall undertake full responsibility for any damage caused to the people
and property as a result of his blasting and excavation works and shall take these
aspects into account giving them utmost importance in his proposals to be
submitted to the Engineer.
Overburden
All overburden including weathered and loose rock, shall be removed prior to
drilling and a fresh working surface formed.
8-4
Panel Size
Burden
The burden shall usually be greater than 9 metres in front of the presplit
plane. The burden may be reduced on approval of the Engineer to a
minimum of 7 metres.
Position
All holes shall be drilled to lie on the design slope. The position of each hole
in a panel shall be accurately surveyed in and clearly marked on the exposed
rock surface or the soil surface before drilling commences.
Spacing
(b) Drilling
Diameter
All drill holes shall be drilled using drill bits of a single approved diameter.
Attitude
All holes shall trend at right angles to the strike of the design slope and dip at
an angle equal to that of the design slope.
Tolerance
No part of any drill hole shall deviate from its theoretical position by more
than one-fifth of the specified hole spacing measured in a direction at right
angles to the plane of the design slope nor by more than one-third of the
specified hole spacing measured in a direction parallel to the plane of the
design slope.
Length
Holes shall be drilled to a length consistent with the design and at least 1
metre below the level of any subsequent blast holes.
8-5
Lifts
The total height of the face shall be excavated in a series of lifts. The height
of each lift shall be dependent on the design layout and shall not exceed 11.5
metres. The contractor shall demonstrate his ability to drill within the
tolerances required over such lengths during the presplit trials. Failure to
satisfy the Engineer in this respect may exclude the contractor from
consideration to conduct the main contract.
Lift Offsets
Lift offsets shall be according to the design which shall generally be 1.5
metres unless otherwise instructed by the Engineer.
All holes shall have been drilled to their entire depth and shall be free of
obstructions to this depth before charging commences.
Explosives
Bottom Charges
Stemming
Stemming, if used, shall be limited to the top 0.5 to 1.0 metres of each hole.
Where overburden remains above the solid rock, as in Clause 3.2.2,
stemming shall be to within 0.5 to 1.0 metres of the soil/rock interface.
Stemming material shall be granular, dry, free-running, pass a 10mm sieve,
and fill the specified length of the hole to the collar, or to the soil/rock
interface.
Matting
8-6
8.9.6 POSTSPLIT BLASTING
Overburden
All overburden including weathered and loose rock, shall be removed prior to
drilling and a fresh working surface formed.
Panel Size
Position
All holes shall be drilled to lie on the design slope. The position of each hole in a
panel shall be accurately surveyed in and clearly marked on the exposed rock
surface or the soil surface before drilling commences.
Spacing
(b) Drilling
Diameter
All drill holes shall be drilled using drill bits of a single approved diameter.
Attitude
All holes shall trend at right angles to the strike of the design slope and dip at
an angle equal to that of the design slope.
Tolerance
No part of any drill hole shall deviate from its theoretical position by more
than one-fifth of the specified hole spacing measured in a direction at right
angles to the plane of the design slope nor by more than one-third of the
specified hole spacing measured in a direction parallel to the plane of the
design slope.
8-7
Length
Holes shall be drilled to a length consistent with the design and at least 1
metre below the level of any subsequent blast holes.
Lifts
The total height of the face shall be excavated in a series of lifts. The height
of each lift shall be dependent on the design layout and shall not exceed 11.5
metres. The contractor shall demonstrate his ability to drill within the
tolerances required over such lengths during the presplit trials. Failure to
satisfy the Engineer in this respect may exclude the contractor from
consideration to this conduct the main contract.
Lift Offsets
Lift offsets shall be according to the design which shall generally be 1.5
metres unless otherwise instructed by the Engineer.
Charging
All holes shall have been drilled to their entire depth and shall be free of
obstructions to this depth before charging commences.
Explosives
Bottom Charges
Stemming
Stemming, if used, shall be limited to the top 0.5 to 1.0 metres of each hole.
Where overburden remains above the solid rock, as in Clause 3.2.2,
stemming shall be to within 0.5 to 1.0 metres of the soil/rock interface.
Stemming material shall be granular, dry, free-running, pass a 10mm sieve,
and fill the specified length of the hole to the collar, or to the soil/rock
interface.
8-8
Matting
Detonation
Position
Bulk blast holes shall be positioned such that rock behind the presplit plane is
not adversely affected. In any event they shall not at any point come within 2
metres of the presplit plane or with 2 metre of the bench.
Pop Blasting
Any toes of hard rock remaining at the base of the design face can be
removed by 'pop' blasting providing that the small diameter holes and light
charges used do not cross the presplit plane.
Attitude
The bulk blast holes nearest the presplit plane shall be drilled parallel to the
design slope.
Length
The bulk blast holes shall terminate at least 1 metre above the level of the
bottom of the nearest presplit hole.
Charging
Reduced charging and decreased spacing shall be considered for bulk blast
holes nearest to the presplit plane.
8-9
8.9.8 Damage to Design Face
Any blasting technique which results in damage or disturbance to the design face
shall be discontinued immediately and the situation reappraised by the Engineer.
Vibration levels due to blasting shall be monitored at all times during the blasting
works. Should the vibration levels exceed the permissible vibration levels
permitted by the local governing authorities, the Engineer shall be informed of it
and all blasting works to be suspended immediately. Blasting works shall only
resume after the blast design factors are revised and approved by the Engineer
and upon an appraisal of the extent of damage caused by the incident.
Trial holes shall be excavated well ahead of the trench excavation to such depths as
necessary to determine and confirm the alignment for the trench and suitability of the
design. Trial holes will also be required to be performed by the Contractor to
determine the position of underground services, sub-soil drains or for any other
reason.
The Contractor shall arrange for the refilling and reinstatement of trial holes to be
carried out immediately after the required information is obtained. The reinstatement
of the surfaces of trial holes shall be carried out to the approval of the Engineer and to
the same standards as those specified for sewer trench reinstatement.
8.11 CLEANING UP
Upon completion of work of each section, all rubbish, debris and excess or waste
material shall be removed and the entire area involved shall be left in a neat, clean
and acceptable condition. The Contractor shall take extra precautions to ensure that
existing trees, buildings, etc. adjacent to the works are not damaged during this or
subsequent operations. The Contractor shall repair, replace all damage caused to the
trees or buildings by virtue of his negligence in this respect.
Only suitable material from approved sources shall be used for filling up to the
required platform levels in accordance with the Drawings and compacted in 225mm
thick layers. Before commencement of filling the original ground must be cleared and
any trees or organic material removed to the satisfaction of the Engineer.
Suitable material shall comprise all that which is acceptable for use in the Works
which is capable of being compacted in the manner specified in Clauses for
Compaction to form a stable fill having slopes as indicated on the design Drawings.
Except otherwise directed by the Engineer, earthfill shall be compacted in layers not
exceeding 225mm thick and shall achieve a degree of compaction specified in
8-10
Section 8.15 of this Specification. All materials used in embankments and as filling
elsewhere shall be compacted as soon as practicable after deposition.
All compacted fill material shall have a dry density corresponding to the following at
the moisture content of the sample in question:
A. for the topmost 600mm below final ground level, 95 per cent of the maximum
dry density obtained from B.S. Standard Compaction tests;
B. for the remainder below final ground level 90 per cent of the maximum dry
density obtained from B.S. Standard Compaction tests.
A. Materials from swamps, marshes or bogs, running silt peat, log, stumps,
perishable material, slurry or mud.
B. Any material:
- Consisting of such clinkers, clinker ashes, fly ashes and domestic ashes
which by virtue of their physical or chemical composition or of their
moisture content will not compact to form a suitable fill.
8.17 TURFING
All turfs shall be cut 300mm wide and at least 300mm long and 75mm thick. They
shall consist of healthy dense indigenous carpet grass firmly rooted into at least
50mm of top-soil. The turf shall be free from mimosa, lalang and any other
objectionable plants, and should be preferably laid on the day it is cut. Turf which
cannot be laid within three days of cutting may, at the discretion of the Engineer, be
used as top-soil.
Where turf is to be laid, a 100mm thick layer of approved top-soil shall be spread and
compacted on the surface to be turfed. Turf shall be firmly bedded in freshly prepared
top-soil dressing and where necessary shall be pegged down with wooden pegs. The
Contractor shall be deemed to have allowed in his rates for regular watering of newly
laid turf during dry weather until such time as it is firmly established. Any turf which
8-11
dries through lack of water before the end of the period of maintenance shall be
replaced. All turfing shall be finished to give a smooth compact surface.
Where spot turfing is employed, the turf shall not stand out above the level of the
surrounding top-soil. Turfing shall keep pace with spreading of top-soil. Spot turfing
shall be of 600mm centre to centre.
Close turfing shall consist of turfs laid so that they cover the whole area without any
space between them.
8-12
SECTION 9
CONCRETE WORKS
9.1 GENERAL
(1) The standard of materials and workmanship shall not be inferior to the
recommendations of the current :-
(2) The requirements outlined in the above documents must be read with
those of this Section of the Specification and where any conflict exists
between the recommendations of the above and of this Specification, the
requirements of this Specification shall prevail.
(3) As and when required by the S.O. the Contractor shall prepare and
submit, before commencing the work, a time- chart (additional to the
general programme) detailing the various operations for concrete work.
(4) No material shall be used in the Works until prior approval for its use has
been given by the S.O., neither shall any change in the nature, quality,
kind, type, source of supply or manufacture be made without the S.O.'s
permission.
(6) The cost of providing samples and the cost of carrying out tests required
by 9.6.1 together with the cost of supplying equipment for sampling and
site testing indicated in Columns 3 and 4 (part) of Table 1.6A of this
Section of the Specification shall be borne by the Contractor (see also
Clause 9.6.1).
(7) During the progress of the Works, consignment notes shall be supplied to
the S.O. giving details of each consignment.
(8) The use of the word "approved' in this Specification refers to the approval
of the S.O. Cross reference between certain Clauses of this Specification
have been shown in brackets following the particular item.
9-1
9.2 CONCRETE
9.2.1 Requirements
(i) The mix proportions shall be selected to ensure that the workability of the
fresh concrete is suitable for the conditions of handling and placing,
having regard to the structural element being constructed, the disposition
of reinforcement, the climatic conditions prevailing and the limitations set
by Table 1.2A of this Clause for the particular grade of concrete specified.
(iii) In all cases of mix proportioning, the added water shall be included with
due allowance for the moisture contained in the aggregate and shall be
the minimum consistent with the workability requirements. Where
difficulty is experienced in maintaining the correct workability for the
water-cement ratio outlined in Table 1.2A the use of a water reducing
additive may be permitted subject to Clause 9.2.9 where aggregates do
not conform to the moisture requirement of Clause 21.2 of BS 5337 but
are permitted for use, in the case of water- retaining structures the water
content indicated in Table 1.2A shall be reduced by 2.5 litres per 50 kg of
cement.
9-2
9.2.2 Strength
(i) The basis for assessing the strength of concrete shall be related to the
characteristic strength, defined as the strength of the concrete at 28 days,
as determined by the standard method of testing (Clause 9. 6. 1) below
which not more than 5% of the test result shall fail.
(ii) The relationship between the grade of the concrete and the characteristic
strength shall accord with Table 1.2B.
9.2.3 Mixes
(ii) If in the opinion of the S.O. the Design Mix/Standard Mix or Nominal mix
methods of proportioning will not produce concrete to satisfy the
requirements of this Specification the mix shall be specially designed.
9-3
The mix proportions shall be based on the results of a programme
of trial mixes to be carried out by the Contractor and presented not
less than 1 5 days in advance of placing the first batch of
concrete. The S.O. reserves the right to order modifications to the
grading of the aggregates and the water content in order to meet
the requirements of resistance to weathering, watertightness and
workability of the concrete.
20 0.452 0.850 6
9-4
TABLE 1.2 D - Prescribed/Standard Mixes
Weight of cement and total dry aggregates in kg to produce approximately 1 cu. M of fully
compacted concrete and percentages by weight of fine aggregate in total dry aggregates.
9-5
9.2.4 Quality Control
(ii) For each main grade of concrete 6 samples for each concreting day shall
be taken for 5 days and from each sample two cubes shall be made.
Thereafter samples of concrete shall be taken according to the following
approximate frequencies and not less than once a day for each class of
concrete being used. From each sample two cubes shall be made.
1- 5 1
5 - 10 2
Greater than 10 3
(iii) One cube from each sample shall be tested at 7 days and one at 28 days.
The relationship between the cube crushing strength at 7 and 28 days for
each grade of concrete used shall be established at an early stage and
adjustments made to the mix proportions on the basis of the 7-days
results in advance of the basis of control as outlined above.
(iv) The 28-days cube test for results for each main class of concrete shall be
examined individually in 10 consecutive sets of four and the standard
deviation and mean strength of each set calculated. The concrete mix
proportions will be acceptable if all of the following requirements are
complied with :-
(a) Not more than two results in 40 are less than the characteristic
crushing strength.
(b) No value of the average for any set of four results is less than the
characteristic strength plus one half of the design margin (Clause
9.2.2)
(c) When 40 results have been obtained and the mean strength and
standard deviation are calculated, the mean strength minus 1.64
times the standard deviation or the mean strength minus 7.5 N/sq
mm (whichever is the lesser) shall exceed the characteristic
strength (Clause 9.2.2).
(v) Where the results do not conform to the above requirements the following
action shall be taken
9-6
(a) Adjustments to the mix shall be made to obtain the
strength required.
(b) In the case where any result is less than 80% of the characteristic
strength the structural implications shall be considered and action
taken as ordered by the S.O. (as provided in Clause No. 9.5.4
(xiv)).
(vi) For those standard mixes required to be tested requirements (i) and (ii)
only will be applicable.
9.2.5 Production
(ii) The aggregate and the cement shall be thoroughly mixed in a clean
mechanical mixer for a period of time agreed with the S.O. and the water
added on the basis of the approved design.
(iii) The amount of water added shall conform to the requirement of Clause
9.2.1.
(iv) Batch mixing machines shall comply with the requirements of BS 1305.
They shall be provided in such numbers and of such capacity as to
ensure a continuous supply of freshly mixed concrete at all times during
construction.
(v) Continuous mixing machines shall be used only with the written
permission of the S.O.
9.2.6 Cement
(i) Ordinary and Rapid-hardening Portland cement shall comply with BS 12.
9-7
(iv) No extra payment will be made to the Contractor if on his own initiative he
used Rapid-hardening Portland cement.
(v) Cement shall be fresh when delivered to Site and the consignments shall
be used in the order of their delivery. The Contractor shall mark the date
of delivery on each consignment and each consignment shall be stored
separately and in such manner as to be easily accessible and identifiable.
(vi) No cement in bags or other containers shall be used unless these and the
manufacturer's seals are intact at the time of mixing.
(ix) The Contractor shall not use cement which has hardened into lumps, but
subject to removal of the lumps by screening, the S.O. may allow such
cement to be used in non-structural concrete mixes.
(x) Cement of different types shall be kept separate in storage and shall not
be mixed together in the production of concrete.
9.2.7 Aggregate
(i) Fine and coarse aggregate shall be as defined by and be of the quality
and nature required by BS 882 and BS1201 whichever is applicable. In
addition they shall be chemically inert to alkali reaction.
(iv) The Contractor shall ensure that the gradings of aggregates remain
reasonably consistent, and shall, if necessary, stockpile and include
different gradings to ensure that the overall grading remains constant for
each section of the work.
(v) Dust or flour resulting from crushing the aggregate shall not be allowed to
contaminate the stockpiles. When in the opinion of the S.O. such
contamination has taken place it shall be removed by an approved means
or otherwise the aggregates shall be rejected.
9-8
(vi) For mass concrete, in order to improve the consistency of the mix, dust or
flour resulting from crushing the aggregate, may subject to test, be
included in controlled quantities to supplement the fine aggregate.
(vii) The aggregate of various sizes shall be kept separate and away from all
possible contamination and shall be stored on a hard-standing area or in
bins, provided with proper drainage at the base of the stockpiles.
(viii) Except where aggregates have been otherwise specified on the Drawings
the grading of aggregates shall be as follows
Coarse Aggregate
(b) 20 mm max. size, graded, for all reinforced concrete in beams and
for walls and slabs with the minimum concrete cover of 40 mm or
less.
(c) 40 mm max. size, graded, for all reinforced concrete walls and
slabs with the minimum concrete cover of 60 mm or more.
Fine Aggregate :
(i) The Contractor shall supply all water, make all arrangements and pay all
charges in respect of such supply. Where water can be obtained from a
public potable water supply it shall be used.
(ii) Where water cannot be obtained from a public supply it shall be tested in
accordance with the BS 3148 and if necessary shall be treated to assure
compliance therewith.
(iii) Water for washing and curing shall be such that it will not impair either the
strength of the finished concrete or its appearance.
(i) Admixtures may be used in the works with the approval of S.O. (Table
1.6)
(ii) Where concrete additives have been approved by the S.O for use in the
works, the contractor shall ensure that careful control is exercised in
maintaining correct proportions in the mix.
9-9
(iii) Where incorrect proportioning has been carried out which in the opinion
of the S.O. will adversely influence the concrete, the concrete shall be
treated in accordance with Clause 9.5.4.
9.2.10 Displacers
9.3 REINFORCEMENT
9.3.1 Steel
(a) Plain round mild steel or high yield steel bars to conforming to BS
4449
(d) The Contractor shall obtain from his suppliers certificates of the
mechanical and physical properties of the reinforcement and shall
submit them to the S.O. for approval.
Reinforcement shall be stored on Site under cover and supported clear of the
ground and in such manner as to make identification easy. Support shall be
such that distorting of the steel is avoided and contamination and corrosion
prevented.
(i) The Contractor shall provide on Site facilities for cutting and bending
reinforcement whether he is ordering his reinforcement bent or not and
shall ensure that a token amount of straight bar is available on Site for
bending as and when directed by the S.O.
(iii) All steel reinforcement bars shall be bent accurately to the form and
dimensions shown in the drawings. Bars shall be bent cold in an
approved machine or by other approved means producing a gradual and
even motion. Bars incorrectly bent shall not be straightened or rebent but
shall be rejected.
9-10
(iv) The reinforcement shall be fixed in strict accordance with the Drawings as
regards cover, spacing and position and suitable precautions shall be
taken by the Contractor to prevent the displacement of reinforcement
during the placing and compaction of concrete.
(v) When required to support and retain the reinforcement in its correct
position the Contractor shall provide templates stools or other supports at
his own cost.
(vii) In the case of mild steel, a lap of not less than 40 diameters of the smaller
bar shall be provided at the junction of two bars for which the lap is not
specifically detailed on the drawings and, in the case of High Yield steel, a
lap of not less than 50 diameters.
(viii) All intersection of bars in walls and slabs and all connections between or
links and main bars in columns or beams shall be tied with soft iron wire
ties or with fixing clips which shall not be allowed to make contact with the
shuttering or to project materially into the specified cover.
9.4 SHUTTERING
9.4.1 Requirements
(ii) Shuttering shall be of such accuracy, strength and rigidity as to carry the
weight and pressure from the concrete to be placed on or against it,
together with all construction, wind or other loads likely to be imparted to
it, without producing deformation of the finished concrete in excess of the
tolerances outlined in Clause 9.4.5 and Table 1.4A and their design and
construction shall in all respects be subject to the approval of the S.O.
9-11
(iii) All shuttering shall be sufficiently tight, without plugging, to prevent loss of
grout during the vibration of the concrete.
(iv) Faces of shuttering shall be clean, free from projecting nails, adhering
grout and other imperfections or defects which would prevent the
specified surface finish from being attained. They shall be treated with
approved mould oil before positioning. Great care shall be exercised to
prevent reinforcement or steelwork from being contaminated by the oil
during erection of the shuttering.
(vii) Beam soffits shall be erected with an upward camber of 5 mm for each 3
metres of span.
(x) Openings for inspection of the inside of beam, wall, column and similar
shuttering and for cleaning-out purposes shall be formed so that they can
conveniently be closed before the placing of concrete.
(xi) All props shall be supported on adequate sole plates and shall not bear
directly on or against concrete. They shall be capable of being released
gently and without shock from the supported shuttering. No appliance for
supporting the shuttering shall be built into the permanent structure
without the S.O.'s prior approval. Props for upper levels, shall be placed
directly over those at lower levels, and the lower most props shall bear
upon work sufficiently mature to carry the load.
(xii) Shuttering shall be such as to allow for its removal without damaging the
concrete, and in the case of suspended floors, for the removal of the
beam sides and slab soffits without disturbing the beam-bottom boards
and their props.
(xiii) Before concreting, the areas which are intended to receive the concrete
shall be cleaned by jetting with compressed air, and all water and
extraneous material removed.
(xiv) Where timber is used for shuttering it shall be properly cured, free froril
wrap, straight, clean and free from loose knots.
9-12
(xv) Where metal forms are used for shuttering they shall be of the type
strengthened by intermediate ribs or cross bracing.
Wrought shuttering for use where the face of the finished concrete is to be
exposed shall produce a high standard of finish consistent with the best practice
as approved by the S.O. The face in contact with the concrete shall consist of
wrought and thicknessed boards tongued and grooved of not less than 30 mm
finished thickness, framed plywood or metal panels or other approved material.
Joints between boards and/or panels shall be arranged in a uniform pattern.
Special wrought shuttering shall provide the highest standard of finish where the
face of the finished concrete is to form a particular feature. The face in contact
with the concrete shall consist of large smooth sheets, unless otherwise
specified, arranged in an approved uniform pattern, with joints coinciding with
possible architectural features, sills, window heads, or change in direction or
surface. Accurate alignment of all joints shall be maintained. Wrought boarding
and standard steel panels shall not be used unless specially faced.
9.4.5 Tolerances
TABLE 1.4A
Item Tolerance (mm)
9-13
9.4.6 Striking and Removal of Shuttering
(I) The S.O. shall be informed in advance when the contractor intends to
strike any formwork.
(ii) Attention is drawn to the provisions that the concrete shall at no time be
subjected to loading, including its own weight which will induce a
compressive stress in it exceeding 0.33 of its strength at the time of
loading or of the specified 28 days strength. The assessment of the
strength of the concrete and the stresses produced by the loads shall be
subject to the agreement of the S.O.
(iv) The periods stated above are based on a constant temperature of the
concrete of 27 degree C and the use of ordinary Portland Cement. They
may be changed if other types of cement are used, subject to the S.O.'s
agreement.
(vi) For prestressed units the side forms shall be eased as early as possible
and the soffit forms shall permit deformation of the member when the
prestress is applied.
(vii) All formwork shall be removed without damage to the concrete and not to
leave wood slivers adhering to the concrete.
9.5 CONCRETING
9.5.1 Requirements
9-14
9.5.2 Transporting of Concrete
(vi) Where approval is obtained for pumping the concrete, the pump
manufacturer's recommendation shall be followed. The pumps
used shall be of adequate capacity and power to ensure delivery
of a continuous supply. The Contractor shall provide adequate
alternative arrangements for transporting the concrete in case of a
breakdown of the pumping equipment.
9-15
(ii) Concrete shall be placed within 30 minutes of mixing to uniform
level, in layers not exceeding 50 cm deep in such manner as to
avoid segregation, and each layer shall be compacted by means
of approved vibrators to form a dense material free from
honeycombing and other blemishes. Compaction by hand may be
used only with the prior approval of the S.O.
9-16
9.5.4 Concreting in Deep Lifts
(i) Limitation
(b) Deep lift construction will not be permitted where the reinforcing
bars are to be placed closer than 10 cm to one another in any
direction or, where the clear width at the point of admitting the
concrete between one layer of reinforcement and another (or
in the case of singly reinforced walls between reinforcement
and shutter) is less than 200 mm.
(c) The method shall only be used where trial sections reveal that,
in the S.O.'s opinion, it can be satisfactorily employed, in which
case the requirements of this Specification shall apply except
where they are in conflict with the requirements of this
particular clause, when the latter shall prevail.
(ii) Concrete
(b) At the same time, the mix shall be such as to limit the amount
of bleeding in the concrete, and where in the opinion of the
S.O. the quantity of free water rising to the surface is
excessive, the mix shall be corrected before further concreting
is undertaken.
(iii) Reinforcement
9-17
(b) All obstructions caused by spacer blocks or chairs shall be
eliminated so as to permit an unobstructed passage for the
concrete to the bottom of the shuttering. The Contractor may
use sliding timber spacer instead of fixed concrete or plastic
spacer blocks to position the reinforcement.
(iv) Shuttering
(v) Concreting
9-18
(d) Where excessive bleeding is in evidence, the excess water
shall be removed before placing further concrete (see sub-
clause "Concrete" of this clause).
(vi) Compaction
9-19
(b) When the air temperature is above 20 degree C loss of mixing
water by evaporation shall be considered in arriving at the
amount of water to be added to the mix (Clause 9.2.1). In
order to maintain the water/cement ratio within permissible
limits an approved water-reducing agent shall be 3 included in
the mix (Clause 9.2.9). The maximum water/cement ratios
indicated in Clause 9.2.1) may be increased with the S.O.'s
permission by 0.05 (or 2 1/2 liters/50 kg of cement) during
mixing, but on no account shall water be added to concrete
directly or indirectly once it has left the mixer.
(b) During showery weather, the Contractor shall ensure the work
can be concluded at short notice by the provision of stop ends.
On no account shall work be terminated before each section,
between one stop end and another, is complete. Adequate
covering shall be provided to protect newly placed concrete
from the rain.
9-20
(b) Holes, etc. shall be accurately marked and boxed-out before
concreting operations commence, and without the S.O.'s prior
approval, no such holes, etc. shall be formed after the
concrete has set.
(c) Exposed faces of concrete shall be kept moist after placing for
not less than 3 days if Ordinary Portland and 2 days if Rapid-
Hardening cement is used unless otherwise stated in the
plans. Membrane curing by approved materials may be used
when permitted by the S.O.
(xi) Joints
9-21
1. The position of construction joints, when not shown on
the Drawings or otherwise required by this Specification,
shall be decided on site having regard to the plant and
labour made available by the Contractor for the
manufacture, placing and compaction prevailing at the
time of concreting, the climatic conditions prevailing at
the time of concreting, the nature and size of the
shuttering, and the conditions of operation of the work.
The Contractor shall submit his proposals to the S.O. for
his approval before commencing the work.
9-22
adjacent slab and without horizontal joints.
6. Walls
(b) All waterstop and jointing materials which are not required for
immediate use shall be stored at all times in a cool place.
9-24
(f) Water stop shall be located and maintained accurately in
position and details of the proposed method of fixing shall be
submitted to the S.O. for approval. On no account shall
waterstop be secured 'by nails or any other means involving
puncture of or damage to the waterstop material.
(xiii) Finishes
(b) Smooth-trowelled
9-25
(c) Screed finishes shall be formed by levelling and screeding the
concrete to produce a uniform, plain or ridged surface as
specified.
(d) the finished concrete sizes are not in accordance with the
Drawings within permissible tolerances, or
9-26
(e) the setting-out is incorrect, or
(h) the work of making good or other remedial measures the S.O.
may indicate are not carried out to his satisfaction, or
9.6 TESTING
(i) The Contractor shall provide equipment, staff and labour for
carrying out the sampling and testing outlined in Columns 3 and 4 of
Table 1.6A, and he shall carry out any or all these tests at such
times and with such frequency as may be requested by the S.O.
(iii) All equipment at the site shall be calibrated and checked from time
to time as the S.O. may require.
(vi) The Contractor shall provide all samples required by the S.O. Those
samples to be tested in a laboratory as required by Column 5 of
Table 1.6 A shall be carefully forwarded by the Contractor to an
approved laboratory. Results of laboratory and site tests shall be
kept on site and copies of all test reports shall be forwarded in
duplicate to the S.O.'s Representative.
(i) The S.O. may direct that a loading test be made on the Works or
any part thereof if he deemed such a test to be necessary for one or
9-27
more of the following reasons
(ii) Loading tests shall be carried out in accordance with Clause 605 of
CP 1 14, or as required by the S.O.
(iii) If the results of the test are not satisfactory, the S.O. will direct that
the part of the work concerned be taken down or removed and
reconstructed to comply with the Specification, or that such other
remedial measures as he may think fit be taken to make the work
acceptable.
(iv) The S.O. may also instruct the Contractor before a loading test
takes place to take out cylindrical core specimens from the
structures concerned and have them tested. The cutting equipment
and the method of doing the work shall be to the S.O's approval.
The specimens shall be dealt with in accordance with BS 1881.
Prior to testing, the specimens shall be made available for
examination by the S.O.
9-28
TABLE 1.6 A - Sampling, Testing and - Acceptance Standard
Density “ - BS 812 )
Part 2 )
Voids “ BS 812 )
Part 2 )
Organic Impurities “ - -
9-29
Site Testing Accepted
Material Testing Sampling Standards Remarks
On In
Site Laboratory
1 2 3 4 5 6 7
Suitability BS 3148 - BS 3148 BS 3148 Not required
for potable
water
Electrolytic ) As required
Efflorescence ) for salt
containing
aggregates
or saline
water
9-30
9.7 SPECIFICATION FOR GRADE 35A CONCRETE (TO BE USED FOR WATER
RETAINING STRUCTURE)
3. Concrete for structures retaining sewage shall have a strength grade not
less than grade C35A. Strength grades higher than C35A shall be
specified as required by the DGSS.
4. Concrete for purposes other than structures retaining sewage shall have
a strength grade not less than grade C20 where unreinforced and not less
than grade C30 where reinforced. Strength grades higher than the
minimum shall be specified as required by the DGSS.
5. Concrete structures retaining sewage but not unit process structures shall
be lined with high alumina cement mortar of 20 mm minimum thickness
Where the above cement are not available, the following cements shall be
used to resist sulphate attack:
10. Sand for use with cement mortar shall comply with MS 701
9-31
11. Lime for use with mortar shall comply with BS 890
12. Mortar shall consist 1 part cement to 3 parts sand and may include 1/4
part lime
(i) 1.64 times the standard deviation of cube tests on at least 100
separate batches of concrete of nominally similar proportions of
similar materials and produced over a period not exceeding 12
months by the same plant under similar supervision, but not less
than 1/3 of the grade strength for concrete of grade 7, 10 or 15: or
7.5 N/mm2 for concrete of grade 20 or above.
Where there is insufficient data to satisfy (i) or (ii) above, the margin
for the initial mix design should be taken as two-thirds of the grade
strength of the concrete of grade 7, 10 or 15; or 15 N/mm for
concrete or grade 20 or above. This margin should be used as the
current margin only until sufficient data is available to satisfy (i) and
(ii) above. However, when the required grade strength approaches
the maximum possible strength of concrete made with a particular
aggregate, a smaller margin not less than 7.5 N/mm may have to
be permitted for the initial mix design.
(iii) Evidence should be submitted to the Engineer not less than 7 days
before the start of concrete production for each grade of concrete
showing that at the intended workability, the proposed mix
proportions and manufacturing method will produce concrete of the
required quality.
If adequate data for 'target mean strength' are not available, trial
mixes should be prepared in accordance with Clause 9.2.3 or, for
ordinary structural concrete up to grade 30, the Prescribed mixes
given in BS 5328 may be used for initial production.
9.7.2 The minimum cement content for Grade C35A concrete to resist a Class 2
Sulphate Condition shall be and maximum free water/cement ratio shall be in
accordance with Table 2.1.
9.7.3 All reinforced concrete that is required to be air entrained, shall include only air-
entraining admixtures complying with BS5075, Part 2. Admixtures containing
calcium chloride shall not be used.
9-33
Table 2.1 Concrete exposed to sulphate attack
3 0.5 to 1.9 to 3.1 1.2 to 2.5 MS 522 combined with 25% to 40%
1.0 pfa
MS 522 combined with 70% to 90% 380 0.45
ggbs
BS 4246 with at least 70% ggbs
MS 1227 with at least 25% pfa
BS 6610 with not more than 40% pfa
9-34
1) Adjustments to minimum cement content should be made for aggregates of nominal maximum size other than
20mm in accordande with 8
2) If much of the sulphate is present as low solubility calcium sulphate, analysis on the basis of 2:1 water extract
may permit a lower site classification than that obtained from the extraction of total SO 3.
Reference should be made to BRE Current Paper 2/79 for methods of analysis and to BRE Digests 250 and 276
for interpretation in relation to natural solids and fills, respectively.
NOTE 1 - Within the limits specified in this table, the sulphate resistance of combinations of ggbs and pfa with SRPC
will be at least equivalent to combinations with cement complying with MS 522.
NOTE 2 - It is recommended that the alumina content of ggbs does not exceed 15%.
ram
20 5
40 4
(ii) The air content shall be determined at the point of delivery to the
paving plant by a pressure type air meter in accordance with BS1881,
at the rate of at least one determination for each 20m length of slab of
less constructed at any one time or at least 3 times per day. If the air
content is outside the specified limits a further test shall be made
immediately on the next available load of concrete before discharging.
If the air content is still outside the limit the contractor shall
immediately adjust the air content of the concrete or improve its
uniformity before any further concrete is used in the works.
The Contractor shall give the Engineer 24 hours notice of his intention to pour
concrete in order that the formwork, reinforcement and other relevant details may
be inspected during normal working hours.
The Contractor shall not pour any concrete in any location until the Engineer has
inspected and approved the formwork and reinforcement and given his consent
for the pour to proceed. In the event of the Contractor failing to comply with this
requirement the Engineer may exercise his right to have the work in question
removed and replaced at no additional cost.
9-35
The period of 24 hours for inspection shall commence after the work is clean and
ready for concreting. In the event that the work shall not be approved, the
Contractor shall give similar notice again after the necessary correction or
modification has been carried out.
If concreting is not started within 24 hours of consent being given, consent shall
again be obtained. Concreting shall then proceed continuously over the area
between construction joints. Fresh concrete shall not be placed against the insitu
concrete which has been in position for more than 30 minutes unless a
construction joint is formed. When insitu concrete has been in place for 4 hours
no further concrete shall be placed against it for a further 20 hours.
Truck mixer units and their mixing and discharge performance shall comply with
the requirements of BS 4251. Mixing shall continue for the number and rate of
revolutions recommended in accordance with Item 9 in Appendix B, BS 4251, or
in the absence of the manufacturer's instructions, mixing shall continue for not
less than 100 revolutions at a rate of not less than 7 revolutions per minute.
Concrete when deposited shall have a temperature of not more than 250C (200C
for sections greater than 500mm thick).
Immediately after compaction and for 4 days minimum thereafter concrete shall
be protected against harmful effects of weather, including solar heat gain, rain,
wind, rapid temperature changes, frost, and from drying out. When elevated
temperature curing is used, the rate of rise in the temperature of the concrete
must not exceed 150C per hour for the first three hours and thereafter the rate of
rise and fall of temperature of the concrete must not exceed 350C per hour. The
temperature of the concrete during heat of hydration must not exceed 700C. The
method of curing employed must prevent loss of moisture from the concrete
protection and curing shall be approved in writing by the Engineer. The
proposals must cover concreting during the whole of the contract period and
have regard to the prevailing weather conditions at the time of casting.
9-36
The Contractor, where requested by the Engineer, shall provide in situ
temperature measurements to show compliance with the above requirements.
The contractor shall submit details of his proposals to cure the concrete,
including details of insulation where appropriate, seven days prior to placing and
concrete.
Table has been included as a guide to controlling early age thermal cracking-
'Particular attention should be given to the necessary different ways in the
dealing with thick and thin sections.
TABLE 2.2
The temperature differential between the core of the concrete and its external
surface shall not exceed the following:-
9-37
When other types of cement or admixtures are used, longer or shorter period
may be required by the engineer.
TABLE 2.3
Summary of the Factors which help prevent or control early-age thermal cracking
Factor Worst Choice Best Choice Comments
Aggregate Shape Rounded Angular -
Aggregate Type High Low Co-eff. expansion
Cementitions Materials PC SRPC SRPC/fa SRPC/GGBFS This is subject to many
RHPC PC/fa PC/GGBFS conditions and the present level
of knowledge (Particularly on
tensile strain capacity). Check
durability requirements.
Formwork Material
(a) Section thickness Insulated plywood GRP steel The aim is to minimise the
under about 500mm thermal gradients across the
(b) Large isolated section Steel GRP plywood insulated section.
(c) Prestressing the base Plain bars, large dia Type 2 high yield Not normally economic
Control of crack widths bars at wide small dia bars at
with reinforcement spacings close spacings
9-38
9.11 STRUCTURAL PRECAST CONCRETE
All cement, aggregate and other materials for precast concrete units with faces
which are exposed either internally or externally shall be from the same sources
throughout. Exposed surfaces of the units shall be uniform in colour and in texture.
Formwork and unformed surfaces for precast concrete units shall comply with the
requirements for F3 formed surfaces and U3 unformed surfaces except that the
dimensional variations shall not exceed the values listed below, unless otherwise
detailed on the Drawings.
Length - +/-6 mm
The positions of individual connecting bolts, bolt holes, projecting steel and other
devices in any associated group (eg. the joint of two precast units) shall be within 3
mm of their true position in the group in which they are cast. The location of any
such group shall be within 6 mm of its true position in the unit in which it is cast,
provided that such deviation does not adversely affect the proper assembly of the
whole structure.
The Contractor shall submit to the S.O. for approval, full details of his proposed
method of carrying out all operations connected with the manufacture and
assembly of precast concrete structural members, including :
- a description of the types of casting bed, mould and formwork for the
various types of members;
9-39
- the procedure for concrete casting and the method of curing the concrete;
- the procedure for transporting, handling, hoisting and placing of each type
of precast structural member;
At all stages and until completion of the work, precast members shall be
adequately protected to preserve all permanently exposed surfaces, arises and
architectural features. The protection shall not mark or otherwise disfigure the
concrete.
All units shall be laid, bedded, jointed and fixed in accordance with the lines, levels
and other details shown on the Drawings.
Dry-pack mortar jointing for packing shall consist of one part of volume ordinary
Portland cement and two and half parts by volume of fine aggregate passing a 1
mm sieve. The mortar shall be mixed with only sufficient water to make the
materials stick together when being moulded in the hands. The mortar is
thoroughly compacted.
(c) procedure for prestressing and method of checking and recording the
prestress, wire extension and anchorage slip.
All tendons, duct forming devices, anchorages and other components shall be kept
free of mud, oil (except water soluble oil applied for protection), paint, retarders,
loose rust, or other foreign matter. They shall be placed with a tolerance of +/-3
mm in concrete dimensions of 300 mm of less or +/- 6 mm in concrete dimensions
over 300 mm.
9-40
SECTION 10
METALWORK
The work of this section consists of the furnishing of all labour, materials, apparatus, and
appurtenance work in connection with metalwork in accordance with these specifications.
Work of this section shall be fully coordinated with work of other trades. Particular attention is
required for items to be embedded in concrete and masonry.
A. Reinforcing steel
B. Piping, conduits, fittings and hangers
Shop drawings shall be submitted to the Engineer for approval prior to fabrication of any work.
Shop drawings shall be based on plans, specifications, and field measurements, and shall
present complete information as to fabrication, installation and proper fitting with other
construction. Shop drawings should show all welds, fabrication and finish details, and shop
painting.
Unless otherwise specified, all work specified herein and shown on the drawings shall conform
to the applicable requirements of the following specifications and codes:
A. Fabrication and erection of structural and miscellaneous steel shall be in accordance with
the latest edition of the AISC "Speification for the Design, Fabrication and Erection of
Structural Steel for Builidngs, and Bridges."
B. Threaded Bolts and Nuts shall conform to the relevant British Standard.
C. Steel Pipes shall conform to BS 534 for water and sewage works, and BS 1387 for
galvanised iron pipes in general.
10-1
G. Grout shall be of approved factory-package non-shrink grout, non-metallic type.
J. Flux shall be of approved brand of non-corrosive or raw muriatic acid killed with zinc.
Excess flux shall be removed and surfaces neutralised after soldering.
K. Nails, Bolts, Screws and Rivets for Sheet Metalwork shall be of best type suited for the
intended purpose and shall be galvanized.
Before fabrication, all steel shall be thoroughly wire brushed, clean of all scale and rust, and
thoroughly straightened by approved methods that will not injure the materials being worked on.
Welding shall be continuous along the entire line of contact except where tack or intermittent
welding is permitted. Where exposed, welds shall be cleaned of flux and ground smooth.
Welding shall be performed by experienced tradesmen, and made with specific electrodes or
submerged are of suitable grade.
All galvanizing shall be carried out in accordance with BS 729 using the hot-dip process with
spelter, not less than 98% of which shall be pure zinc. Bolts, nuts and washers shall be
completely galvanized including threads, but galvanized coatings removed in the course of nut
fixing may be replaced with an approved zinc rich paint.
Before leaving the shop all steel not shown or specified to be galvanized shall be given one
coat of primer as specified in the Painting Section of these specifications. Final painting shall be
as specified under the Painting Section of these specifications. That portion of steel to be
embedded in concrete or masonry shall not be painted.
Iron castings shall be made from properly prepared patterns and moulds. All castings for dead
end and manhole frames and covers shall be tough grey iron, free from warps, cracks, holes,
swells, and cold shuts, and have a workmanlike finish. Before leaving the foundry all castings
must be thoroughly cleaned and subjected to a hammer inspections after which they shall be
dipped twice in a preparation of asphalt or coal tar applied at a temperature of 149 oC in such a
manner as to form a firm tenacious coating.
All manhole covers and frames when fitted shall be watertight and air-tight. Defective manhole
covers and frames shall be rejected and replaced.
10-2
10.4 STRUCTURAL STEELWORK
This Section of the Specification is intended to cover the supply of all materials, fabrication and
erection of steel bridge trusses. Workmanship and general fabrication procedure shall be in
accordance with the relevant clause in B.S. 5950.
All main structural steel members, unless otherwise specified, shall comply with the
requirements of Grade 43A of B.S. 4360. All steel materials shall be clean, free from loose rust
and loose mill scale. All members shall be straight, free from twists, cracks, flaws, laminations,
rough jagged and imperfect edges and other defects.
Mild steel electrodes for metal arc welding shall comply with the requirements of B.S. 639.
All mild steel bolts and nuts shall have an ultimate tensile strength of not less than 430 N/mm 2
and a mininum elongation of 17%. Dimensions shall comply with the requirements of B.S. 4190
or B.S. 1580 or B.S. 3643.
All plain, tapered or other specially shaped washers for bolts shall be made of steel or
malleable cast iron complying with B.S. 3410 and B.S. 4320.
A. The Contractor shall afford all facilities for the inspection of the work at all stages by the
Engineer at the Contractor's works and those of his sub-contractors. All work shall be
subjected to inspection before shipment to the Site.
B. The Contractor shall give such reasonable notice to the Engineer of the progress of the
work as will enable him to arrange for the inspection, examination and testing as
required.
C. Samples of materials and workmanship to be employed in the Works may be called for at
any time by the Engineer.
D. The Contractor shall arrange for all materials to be tested at the manufacturer's works
and when required in the presence of the Engineer. When material is obtained from a
supplier's stock the Contractor shall:
2. arrange for samples to be taken and tested to prove the requisite quality. Two
copies of all test certificates shall be forwarded to the Engineer.
E. Notwithstanding compliance with the above tests, nothing shall affect the right of the
Engineer to reject materials found not suitable after delivery to the site.
F. The Engineer reserves the right to require independent analyses and tests on the
materials by an analyst or Testing Laboratory selected by him, in order to check the
works analyses and tests. For this purpose, the Engineer will take drillings for analyses
and have pieces cut out side by side with pieces subjected to test in the workshops, in
order that a comparison of the results of the two tests can be made. Should the result of
any independent analysis or test be unsatisfactory, the material represented will be
rejected.
10-3
10.4.3 Fabrication of Steel
Cuttings may be effected by shearing, cropping or sawing. Gas cutting may only be used when
specifically authorised in writing by the Engineer. The edges of all plates shall be perfectly
straight and fair throughout. Sheared members shall be free from distortion. Edges of all
members shall be machined or ground smooth before welding is effected.
Holes for bolts shall be drilled or punched. It shall not be formed by a gas cutting process,
except with specific approval from the Engineer.
A. When directed by the Engineer and before fabrication is commenced, welding and flame
cutting procedure trials shall be carried out using representative samples of materials to
be used in the work. The samples of materials shall be selected and marked by the
Engineer when the materials for the work are inspected at the Contractor's workshop.
B. Trials on material 20mm thick shall be taken to include all materials up to, but not
exceeding 20mm thick.
C. The welding and flame cutting trials shall demonstrate to the satisfaction of the Engineer
the procedure to be adopted in the fabrication of the work which shall include:
2. The heat control techniques required to ensure that the flame cut surfaces of steel
are free from cracks, local hardness and any other defects which would be
detrimental to the finished work.
D. The trials shall include specimen weld details representative of the actual construction
which shall be welded in a manner simulating the most unfavourable conditions liable to
occur in the particular fabrication. Where primers are to be applied to the work prior to
fabrication, they shall be applied to the sample material before the procedure trials are
made. After welding, the specimens shall be held at ambient temperature for a period not
less than 72 hours, and shall then be sectioned and examined for cracks and other
defects, and shall be subject to the tests specified hereunder.
E. The following tests for fillet welds shall be carried out to B.S. 709 in accordance with
Clause 10.6:
The Contractor shall provide to the Engineer satisfactory evidence that the welders employed
have passed the tests specified in B.S. 4872 appropriate to the work being performed.
Only skilled welding operators who satisfy the appropriate welding tests specified therein shall
be employed. Notwithstanding compliance with the above requirements, the Engineer reserves
the right to have any welding operator re-tested at any time and may require that this testing be
carried out in his presence.
The welding plant shall be capable of maintaining at the weld the voltage and current specified
by the manufacturer of the electrodes, and shall comply with the requirements of B.S. 638.
10-4
10.5.3 Welding Process
Manual metal arc welding complying with B.S. 5135 shall be used for all weldings, except for
tack welds and temporary attachments. Approval in writing shall be obtained from the Engineer
if other welding methods are employed.
The acceptance of the welded work shall depend upon correct dimensions and alignment,
absence of distortion in the structure, satisfactory results from examination and testing of the
joints and the test specimens, soundness of the welds, and upon general good workmanship.
Welding other than in properly equipped fabrication shops will normally be limited to non-
structural members, except where specifically permitted by the Engineer.
Should any weld fail to comply with the above requirements, further radiographs shall be taken
to determine the extent of such defective welds. Defects shall be repaired by chipping or
melting out such defects from one or from both sides of the joint as required, and re-welding.
The method of effecting such repairs of defective welds shall be to the approval of the
Engineer. All repair welds shall be checked by repeating the original test procedures.
The tests detailed in the earlier sections shall be carried out in accordance with B.S. 709. The
test results of welded joints shall not be inferior, in any respect, to the British Standard test
requirements for the parent metal.
10.7.1 Bolts
All black bolts shall be of mild steel with well formed heads forged from one solid piece and
shall be dipped in hot boiled linseed oil, or other approved oil, as soon as they are made. The
nuts shall be a good fit on the bolts so that they can only just be turned by hand and one clear
thread shall show through the nut when it has been finally tightened up. Every bolt, unless
otherwise specified, shall be provided with a washer under the nut.
10.7.2 Washers
Mild steel flat washers shall be circular, of a diameter 2.5 times that of the bolt and 5mm
minimum thickness. Where bolt heads or nuts bear upon bevelled surfaces, they shall be
provided with square taper washers of suitable thickness to afford a seating square with the
axis of the bolt.
All holes must be correctly aligned to permit the bolts to be freely placed in position. The driving
of bolts is not permitted.
The Contractor shall be responsible for the correct lining and levelling of all steelwork on Site.
10-5
10.8.2 Stability of Structure
The Contractor shall be responsible for the stability of the structure at all stages of its erection
on Site.
No member of the structure shall be finally bolted, riveted or welded until the whole or a major
section is approved by the Engineer for line, levels and verticality. Connections shall be
completed as soon as possible after receipt of the Engineer's approval.
Structural steelwork shall conform to the requirements of B.S. 449, steel shall comply with B.S.
4360 and steel tubes for structural purposes shall comply with B.S. 1775 and shall be obtained
from a manufacturer to the prior approval of the Engineer.
Steelwork shall, when perfectly dry and free from millscale, be primed with two coats of red lead
primer before leaving the manufacturer's works and any damage to this coating shall be made
good before erection.
Welding of structural steelwork shall be carried out in accordance with B.S 5135. Only welders
who have satisfied the conditions of BS 449, Part 6 shall be employed on the fabrication and
erection of permanent Works. Structural steelwork shall be fabricated, stored, handled and
erected in accordance with Part 5 of B.S 449.
Bolts, ragbolts, nuts and washers shall conform to B.S. 4360 as regards materials for steel
bolts and B.S. 916 as regards dimensions. Each bolt shall be provided with two washers and
bolts shall be long enough to show a full thread through the nut after fixing.
Structural steelwork will be measured by net weight or length, no allowance being made for
rolling margin, bolt holes, cleats, bolts, nuts washers and weld metal (except connecting
plates).
The Contract Rates for structural steelwork shall include for the full cost of supplying, erecting,
painting the steelwork, bracings, cleats, bolts, nuts, washers and welding electrodes as may be
necessary.
All metals to be galvanised shall be of the full dimension shown or specified and all punching,
cutting, drilling, screw tapping, welding and the removal of burrs shall be completed before the
galvanising process commences.
All galvanising shall be done by the hot dip process with spelter, not less than 98% of which shall
be pure zinc. No component which is likely to come into contact with oil shall be galvanised.
10-6
Bolts, nuts and washers shall be completely galvanised including the threads but galvanising
removed in the course of nut fixing may be replaced with an approved zinc rich paint.
The galvanising shall be uniform, clean, smooth and as free from spangle as possible. It shall
weigh not less than 6.0 grams per square metre of area covered.
All galvanised metal parts shall be protected from damage due to electrolytic action, white rust
and abrasion during delivery, storage and erection. Minor damage shall be touched up with an
approved metallic compound but if, in the opinion of the Engineer the damage to the galvanising
is too severe or extensive, the part shall be removed and re-galvanised.
The Contractor shall not use fixtures and fittings for metalwork (including pipework) in which
dissimilar metals likely each other.
Wherever aluminium alloy angles, tees and bolts are required to be bedded, the Contractor shall
ensure that they are liberally coated with bituminous paint and allowed to dry prior to fixing.
Chequer plating shall be mild steel with a non slip pattern on its upper face.
Chequer plates shall be securely bolted with counter sunk screw studs to frames set in the edges
of and spanning the ducts or opening. The sizes of plates shall be such that no discernible
deflection occurs under the weight of a man standing upon it. Where it is not practicable to
provide individual frames to each plate, the plates shall be stiffened by welding galvanised steel
angles on their underside to eliminate discernible deflection.
The edges of all chequer plates shall be finished straight or to the outline of obstructions and shall
be free of burn marks of irregularities. Plates cut with a torch shall afterwards be ground to
present a straight edge.
Chequer plating shall before delivery be thoroughly wire brushed and shall be painted on each
surface and side with two coats of chromate primer and two coats of bituminous paint.
10.14 HANDRAILING
Handrailing shall be of heavy duty hot-dipped galvanised mild steel, G.I pipe or aluminimum as
shown in the drawing.
Sockets and base plates shall be welded onto the stanchions. Base plates shall have holes
drilled for fixing to concrete with three 13mm diameter rawl bolts.
Before manufacturing the handrailing, the Contractor shall submit detailed drawings to the
Engineer for his approval. The drawing shall show the position of standard joints, expansion
joints and all fixing details. Fabrication shall not start until these drawings have been approved by
the Engineer. Expansion joint shall be provided where the handrailing is more than 18 metre
long.
Handrailing will be measured in length on plan. No separate measurement will be made for
stanchions and intermediate railing. The Contract Rates for handrailing shall include for the full
cost of supplying, transport to and temporarily storing on the Site, hauling and handling, erecting,
base plates, rawl bolts, grouting and painting as necessary.
10-7
10.15 LADDERS
Ladders shall unless otherwise specified be of aluminium and obtained from an approved
manufacturer. Unless detailed on the Drawings, the Contractor shall submit to the Engineer
detailed drawings of a ladder for approval before placing any orders.
Ladders shall be of welded construction and shall not have an unsupported length of more than 3
metres. Intermediate support between the ends of the ladder shall be by means of stays
securely fixed to the nearest part of the structure. Where shown on the Drawings safety rings
shall be provided.
The Contract Rates for ladders shall include for supply, fixing, painting and for all nuts, bolts,
stays, base plates, etc. necessary for securing ladders in place.
Step irons shall be either bent from 25mm square aluminium alley. Aluminium alloy step-irons
shall be similar to the type manufactured by Norton Engineering Alloys Co. Ltd., Noton, Malton,
Yorkshire Y017 9HQ, England.
The Contract rates shall include for supply and all necessary fixing work.
10-8
SECTION 11
ROADWORKS
The preparation of formation shall be carried out only after completion of all sub-
grade drainage, piped drains, services and ducts or any other drainage work that
might affect the works, unless otherwise agreed by the S.O.'s representative and
such preparation shall be carried out immediately prior to the laying of the sub-base
or the road base where no sub-base is required.
The surface of the formation shall be substantially uniform in density throughout its
entire width and shall conform to the density requirements for compaction. It shall be
trimmed to conform to the lines, camber, grades and typical cross sections shown on
the drawings or as directed by the S.O.'s representative. Where ruts or other
objectionable irregularities occur as a result of construction traffic or other causes, the
contractor shall reshape and re-compact the formation to the required density before
the subbase or road base is placed.
Where soft spots and unsuitable material occurs, they shall be removed and
backfilled with approved stable material and compacted by not less than 4 passes of
a smooth-wheeled roller weighing not less than 1 0 ton or an equivalent vibrating
roller. The formation shall then be checked and the final trimmed surface shall be
rolled by one pass of a smoothed-wheeled roller of not less than 5 tons or an
equivalent vibratory roller prior to the laying of the sub-base or base.
The formation shall be so constructed to drain surface water to the side ditches or
other drainage system. If the contractor allows the moisture content of the completed
formation to reach a value above the permitted maximum for the compacted material,
the contractor shall allow the material to revert to an acceptable moisture content and,
if directed by the S.O.'s representative, make good the surface by recompaction
before laying the sub-base.
The formation shall be trimmed to conform to the lines, camber grades and typical
cross-sections shown in the drawings or as directed by the S.O.'s representative, and
shall lie within any specified tolerances. The surface shall be blinded with approved
fine graded material to seal the surface.
11-1
]
The trimmed formation shall be rolled by one pass of a smooth wheeled roller of not
less than 5 tons weight or an equivalent vibratory roller.
The thickness of the various layers of the pavement shall be as shown on the
drawing. However before the construction of the pavement the S.O.'s representative
shall carry out California Bearing Ratio (C.B.R.) Soaked tests as described in B.S.
1377 on the prepared subgrade to check the required thickness of pavement. The
Contractor shall provide all equipment and assistance in carrying, out such tests.
The S.O.'s representative may vary the thickness of the various layers of the
pavement as shown in the typical cross-section drawings as a result of the above
tests.
The sub-base material shall be hard, durable and clean. It shall be granular material
such as sand or crushed rock and shall be free from organic material, clay balls, and
any other deleterious substances.
The crushed rock or gravel shall conform to one of the following grading:
Alternative suitable material may be used subject to the prior approval of the S.O.'s
representative. The proposed sub-base material shall have a CBR value not less
than 20% when compacted to 95% of maximum dry density as determined by the
Modified Compaction Test. The material shall be free from vegetable matter, soft
particle or clay lumps and shall conform to one of the following grading
11-2
]
B.S. Sieve Size Percentage By Weight Passing
(A) (B)
40 mm ( 1 ½ ) 100 -
20 mm (3/4 ) 80-100 100
10 mm (3/8 ) 55-90 80-100
5 mm (3/16 ) 40-70 55-90
2.4 mm (No.7) 30-55 40-70
420 microns (No. 36) 12-30 20-40
75 microns (No.200) 5-20 8-25
The portion passing the 420 microns (No. 36) sieve shall, if it is plastic, have a liquid
limit not greater than 35 and a plasticity index greater than 11.
The sub-base shall be laid in one layer to the thickness required on the prepared
formation. It shall be thoroughly compacted with suitable and adequate compaction
equipment, approved by the S.O.'s representative.
Rolling operations shall begin from the outer edge toward the centre, gadually in a
longitudinal direction; except on super elevated curves where rolling shall begin at the
low side and progress towards the high side.
The finished sub-base shall not vary more than 3/4" plus or minus, from the grade or
level shown in the drawing.
The crusher run road base to be placed on top of the sub-base shall be wet-mix
macadam consisting of crushed aggregate laid in layers each of thickness not
exceeding 150 mm (6") and to give the specified total compacted thickness and
width, correct line and levels shown in the drawings.
The material shall be crushed rock of hard durable particles or fragments of rock
crushed to the correct size, well graded and lie within the following grading limits
shown on the next page:
Note:
1. The particle size shall be determined in accordance with the requirements of
B.S.1377.
2. The material passing the 240 micron (No.36) B.S. sieve when tested in
accordance with B.S. 1377 shall be non-pastic.
All work on the portion of the subgrade or sub-base on which the road base is to be
laid shall be properly shaped and compacted in accordance with the requirements of
this specification before the placing of the road base material. The preparation of the
11-3
]
subgrade or sub-base shall be completed at least 182.88mm ahead of the placing of
road base materials. The road base shall be constructed to the full compacted
thickness as shown in the drawing.
All material shall be placed and spread evenly to the full width of the road base. The
maximum compacted thickness of any one layer shall not exceed 150mm (6”). When
the specified compacted thickness of base course exceeds 150mm (6”) the base
shall be constructed in two or more layers of approximately equal thickness. Each
layer shall be compacted to not less than 95% of the maximum dry density of the
material tested in accordance with the requirement of Tests No.14, 15 (B) of B.S.
1377 : 1975 before the next layer is placed. At least one density test is to be carried
out for each 1200 sq. yards of each layer of the road base laid and compacted. Care
shall be taken to prevcent segregation of the material into the coarse and fine
fractions. Segregated surface of a base construction or base material contaminated
to such an extent that it no longer complies with the required specifications shall be
removed and replaced with well graded and satisfactory material.
The material shall be spread by a motor grader or any other approved mechanical
plant. When a road base is spread adjacent to concrete kerbs or gutter sections,
extreme care shall be exercised so as not to damage the kerbs or gutters. Any
damaged kerbs or gutters shall be removed and replaced, all at the Contractor’s
expense.
Compaction shall be completed as soon as possible after each layer has been spread
and shaped satisfactorily. Each year shall be thoroughly compacted with suitable
compaction equipment to the requirement specified in Table 3.1 ‘Compaction
Requirements for Granular Basecourse Materials’.
Rolling operations shall begin along the edges and progress towards to the centre
gradually in a longitudinal direction. On superelevated curves, the rolling shall begin at
the low side and progress towards the high side. The rolling operation for each layer
shall continue until all rolling marks, ridges or cracks are eliminated. Any irregularities,
segregation or loose material which may develop in the surface during or after
construction shall be corrected or removed and the defective areas made good to the
full thickness of layer and recompacted.
Before the laying of each layer of crusher run a partial width of the shoulder, not less
than 1 foot wide, shall be constructed to the top of each uncompacted layer of the
base to act as a haunch to support the edges of the crusher run base during rolling.
Road base material shall be maintained at the correct moisture content necessary for
the proper compaction. It shall be watered by sprinkling with an approved sprayer
which gives a uniform distribution of water over the whole area or if the material is too
wet, it shall be loosen and dried by any means approved by the S.O. which will
achieve the required optimum moisture content.
The surface of the aggregate roadbase shall be well drained at all times.
The furnished road base surface shall be even, free from hungry patches,
irregularities, loose material or fines and true to cross-section, lines and level. Any
irregularities on the finished base course surface of more than 12mm when measured
with a straight edge 10 feet long laid either parallel to the centre of the road or laid
transversely, shall be corrected by loosening, adding or removing material, reshaping
and recompacting.
11-4
]
Table 1.1 : Compaction Requirements for Granular Materials
Number of Pases Of
Type of Compaction Not greater Not greater Not greater
Plant Category than 115 mm than 150mm than 225mm
(4½”) layer (6”) layer (9”) layer
Smooth, Wheeled Load per 25mm width
Roller 69-136 kg (151-300 16 Unsuitable Unsuitable
lbs) 136 Kg (300 lbs) 8 16 Unsuitable
Pneumatic Typed Wheel Load
Roller Tons - - -
4-6 12 12 Unsuitable
6-8 12 12 Unsuitable
8-12 10 10 Unsuitable
more than 12 8 8 Unsuitable
Vibratory Roller Static load per mm
width of vibratory
roller kg (lb)
19-32 (41-70) 16 Unsuitable Unsuitable
32-45 (71-100) 6 16 Unsuitable
46-59 (101-130) 4 6 10
60-73 (131-160) 3 5 9
73-91 (161-200) 3 5 8
91-109 (201-240) 2 4 7
109-127 (241-280) 2 4 6
Vibrating Plate Static pressure under - - -
Compactor base plate N/mm²
(lb/in²)
0.013-0.017 (2-2½) 8 Unsuitable Unsuitable
0.017 - 0.021 (2½-3) 5 8 Unsuitable
more than 0.021 (3) 3 6 10
Virbo-Tamper Weight Kg. (cwt) - - -
50.0-63.5 (1-1¼) 4 8 Unsuitable
63.5-76.0 (1¼-½) 3 6 10
more than 76.0 (½) 2 4 8
Power Rammer or Weight Kg. (cwt)
Dropping Weight 100-510 (2-10) 5 8 Unsuitable
Compactor more than 510 (1) 5 8 12
A bituminous prime coat shall be applied to the top of the completed crusher run base
course before laying the asphaltic concrete binder course. The Contractor shall apply
the prime coat on the completed portion of the granular base course as soon as
practical. However, he shall not apply the prime coat if the moisture content in the top
50 mm (2") of the aggregate base course exceeds the higher of either:
(a) the average of the optimum moisture content as determined by the standard
compaction test, and the absorption of the plus 5 mm (3/16") sieve fraction, or
The surface shall be cleaned immediately prior to the application of the prime coat.
The bituminous material shall be applied by means of a distributor at suitable rates
but not to be less than 0.435 litres per sq. metre (0.08 gallon per sq. yd.) and at the
temperature within the range shown in table 1.2 for the particular material being used.
The surface of the dense asphaltic concrete binder course shall be cleaned
immediately prior to the application of the tack coat. The bituminous material shall be
applied by means of distributor at suitable rates but not to be less than 0.34 litres per
sq. meter (0.06 gallon per sq. yd.) and at the temperature within the range shown in
table 1.2 for the particular material used.
11-5
]
The bituminous material for the tack coat shall be either a rapid curing cut back given
in B.S. 3690:1970 or a rapid breaking emulsion. Bitumen emulsion shall be of the
anionic type unless the cationic type is explicitly required.
Anionic emulsified bitumen shall conform to the requirements for the appropriate
grade given in B.S. 434:1960.
Cationic emulsified bitumen shall conform to the requirement for the appropriate
grade given in B.S. 434 in respect of general properties. The grade and use of either
type of emulsion shall be in accordance with B.S. 2542:1960.
The S.O. may require the Contractor to provide a certificate stating that a particular
emulsion distributor has been tested within the previous six (6) months and that the
rest indicates conformity of the distributor with the requirements of B.S. 3136 for
emulsion distributors.
Grade Temperature
Cut Back New Grade
Old Grade (Approx.) °F °C
R.C. or M.C. 0 30 100-135 38-37
1 70 135-150 57-71
2 250 170-200 77-94
3 190-220 88-104
4 800 210-235 99-113
5 3000 245-270 118-132
11.11.1 Description
This work shall consist of furnishing, placing, shaping and compacting asphaltic
concrete binder course and/or wearing course on a prepare and accepted
bituminous or bitumeo primed pavement course, and shall include the careful and
thorough cleaning of surfaces which are to be covered without receiving a
bituminous tack coat. The work shall be carried out all in accordance with these
Specifications and the lines, levels, grades, dimensions and cross-sections shown
on the Drawings and/or as required by the S.O.'s representative.
11.11.2 Materials
(a) Aggregates
(i) The aggregate crushing value when tested in accordance with M.S. 30
shall be not more than 30
11-6
]
(ii) The weighted average loss of weight in the sodium sulphate soundness
test (5 cycles) when tested in accordance with AASHTO Test Method T
104 shall be not more than 12%
(iii) The flakiness index when tested in accordance with M.S. 30 shall be
not more than 30
(iv) The water absorption when tested in accordance with M.S. 30 shall be
not more than 2%
(v) The polished stone value when tested in accordance with M.S. 30 shall
be not less than 40 (only applicable to aggregates for wearing course).
(i) The weighted average loss of weight in the sodium sulphate soundness
test (5 cycles) when tested in accordance with AASHTO Test Method T
104 shall be not more than 12%.
(ii) The water absorption when tested in accordance with M.S. 30 shall be
not more than 2%.
The gradation of the combined coarse and fine aggregates, together with
ordinary Portland cement added as an adhesion and anti-stripping agent and,
if necessary, any other mineral filler, shall conform to the appropriate
envelope in Table 1.3.
The gradation envelopes in the above table are purposedly wider than the
tolerances for good works control of asphaltic concrete mixes. For each type
of mix required in the works, the Contractor shall established a job mix
formula gradation which shall consist of a single definite percentage passing
for each sieve size in the above table and shall produce a smooth curve
within and essentially parallel to the appropriate gradation envelope. This job
mix formula gradation, with the allowable tolerances for a single test as
specified in Section 1.11.3 ( c ) then becomes the job control envelope, and
11-7
]
this job control envelope must be totally within the limits of the appropriate
gradation envelope in the above table.
(b) Mineral Filler
Mineral filier shall be finely divided mineral matter such as rock dust,
limestone dust, hydrated lime, hydraulic cement, or such other suitable
material as the S.O.'s representative shall approve. At the time of use it shall
be sufficiently dry to flow freely and shall be essentially free from
agglomerations. Not less than 70% by weight shall pass the B.S. 75um
sieve.
Ordinary Portland cement for this purpose shall conform to the requirements
of M.S. 522, and shall be dry, free flowing and free from agglomerations at
the time of use.
Accordingly the Contractor shall carry out bitumen stripping tests with the
proposed aggregates to demonstrate to the complete satisfaction of the
S.O.'s representative that the aggregates will perform satisfactorily in service
with the specified bitumen binder. Such tests shall be carried out in
accordance with AASHTO Test Method T 182, or such other test methods as
the S.O.'s representative shall direct or approve. When AASHTO Test
Method T182 is used, the coated area at the end of the mixture's period of
immersion in water shall be not less than 95%.
The Contractor may propose to use an adhesion and anti- stripping agent
other than ordinary Portland cement in addition to, or wholly or partially
instead of, the ordinary Portland cement specified above. Such agent shall
be of a type approved by the S.O.'s representative, and shall be thoroughly
mixed with the bituminous binder all in accordance with the manufacturer's
instructions. In such case the agent shall be added to the bitumen binder
used in the bitumen stripping tests in the appropriate amount and manner.
Aggregate which does not perform satisfactorily in the bitumn stripping tests,
using the approved adhesion and anti-stripping agent when appropriate, shall
not be used in asphaltic concrete.
11-8
]
job mix formula for each class of mix required in the works. In order to attain
optimum quality of the mixtures, the job mix formula for each class shall be
prepared on the basis of Table 1.3 at an appropriate range of bitumen
contents. As a guide to the testing range of bitumen contents, the design
bitumen content will usually be in the appropriate range in table 1.4.
TABLE 1.4
Design Bitumen Contents
A sample of each trial mix (i.e. each combination of trial gradation and
bitumen content) shall be subject to a comprehensive Marshall method test
and analysis as follows :
(i) Preparation of specimens for the standard stability and flow test in
accordance with AASHTO Test Method T 245 using the 50 blows
per face compaction standard.
For each trial mix conforming to a proposed job mix formula, the parameters
of the above test and analysis shall conform to the requirements of the
appropriate type of mix in Table 1.5.
Air voids shall be defined as the small pockets of air between the coated
aggregate articles in a compacted asphaltic concrete mix. The portion of the
bitumen absorbed into the aggregate particles must therefore be allowed for
when calculating the air voids. For combined aggregate with a water
absorption of not more than 2.0%, the absorbed bitumen may be estimated
on the basis that the absorption of bitumen will be approximately 20% of the
water absorption.
TABLE 1.5
Test and Analysis Parameters for Asphaltic Concrete
11-9
]
Air voids in mix % 3.0 - 5.0 3.0 - 7.0
Voids in aggregate % 75 - 85 65 - 80
filled with bitumen
The Contractor shall submit to the S.O.’s representative full details of this
proposed job mix formula for each class of mix required in the work including
(iii) The mixing plant screen sizes, the smallest of which shall not be
more than 3.2mm.
(iv) The gradation analysis of the aggregate in each of the mixing plant’s
hot bins and of the mineral filler (including ordinary Portland cement
added as anti-stripping agent).
(v) The job mix formula gradation of the combined aggregate and filler.
(vi) The proportions for combining the hot bin aggregates and filler.
(viii) The dry and wet mixing times if a batch plant is to be used, or the
mixing time if a continuous mix plant is to be used.
(x) The full results of the comprehensive Marshall method tests and
analyses as described above for each trial mix used in determining
the job mix formula.
11-10
]
As directed by the S.O.’s representative, comprehensive sampling and
testing of each class of mix shall be carried out to check for satisfactory
compliance with its job mix formula, and for a satisfactory degree of
compaction.
The S.O.’s representative final approval of the job mix formulae shall bind the
Contractor to furnish asphaltic concrete mixes meeting the precise gradations
and bitumen Contents specified in these formulae within the tolerances set
forth in Table 1.6.
Modifications to a job mix formula may only be made with the approval of the
S.O.’s representative. Should the S.O.’s representative at any time have
reason to believe that the materials and methods of mixing and laying are
different from those approved, he shall so advise the Contractor, and may
order that asphaltic concrete works be discontinued pending further trials and
testing.
11.11.4 Equipment
The Contractor shall provide all the plant and equipment necessary for executing
the work in accordance with these Specifications, and shall furnish the S.O.’s
representative with such details of particular items of equipment, e.g. manufacturer
model type, capacity, weight, operating features, etc., as the S.O.’s representative
shall require.
11-11
]
(i) Power Broom
(c) Rollers
A pneumatic typed roller and two steel wheeled tandem rollers shall be
provided; however a three wheeled steel roller may be substituted for one of
the tandem rollers if the S.O.’s representative shall so approve. All rollers
shall be of recognized manufacture and shall be approved by the S.O.’s
representative.
11-12
]
sprinkler systems and pads of coconut matting to keep all tyres evenly wetted
during operation.
The roller shall be equipped with means of adjusting its total weight of
ballasting so that the load oar wheel can be varied in the range 1.0 to 2.0
tons. In operation, the ballasted weight and the tyre inflation pressure shall be
adjusted to meet the requirements of each particular operation. Each tyre
shall be kept inflated at the specified pressure such that pressure difference
between any two tyres shall not exceed 0.04 N/m2. Means shall be provided
for checking and adjusting tyre pressures at all times at the place of the
works.
The Contractor shall provide the S.O.’s representative with a calibration chart
for the roller showing the relationship between the quantity or depth of ballast
and total weight, and also a chart showing the relationship between wheel
load, tyre inflation pressure and contract pressure.
Each steel wheeled roller shall be ballasted so that its total operating weight
is in the range 8 to 10 tons and its driven roll (or rolls) shall exert a rolling
force of not less than 3.5 tons/metre of roll width. The Contractor shall
provide the S.O.’s representative with a calibration chart for each roller
showing the relationships between the quantity or depth of ballast and total
weight and rolling force.
Asphaltic concrete paving work shall only be carried out in dry weather when
the surface to be covered is dry, or if so specified, has received a bituminous
tack coat which shall have achieved a satisfactory degree of tackiness, all to
the satisfaction of the S.O.'s representative. All laying, rolling and finishing
work shall be carried out during daylight hours, unless the Contractor shall
have provided suitable flood-lighting for the job site, to the satisfaction of the
S.O.'s representative.
11-13
]
and other objectionable material, all to the satisfaction of the S.O.'s
representative.
The aggregates shall be fed into the dryer at a uniform rate proportioned in
accordance with the appropriate job mix formula. The rate of feed for each
aggregate shall be maintained within 10% of the rate prescribed, and the total
rate of feed shall be such that the plant's screens shall never be overloaded.
The aggregates shall be dried and heated so that when delivered to the mixer
they shall be at a temperature in the range 1500C to 1700C when the binder
is bitumen of penetration grade 80-100. If the binder is other than bitumen of
penetration grade 80-100, the S.O.'s representative shall specify an
appropriate range for the mixing temperature.
Immediately after heating, the aggregate shall be screened into four (or
more) fractions which shall be separately stored in the hot aggregate storage
bins in readiness for mixing.
Ordinary Portland cement and/or other mineral filler to be used in the mix
shall be stored separately and kept completely dry. Its rate of feed into the
plant shall be accurately controlled by weight or volumetric measurement, all
to the satisfaction of the S.O.'s representative.
The binder shall be heated so that when delivered to the mixer it shall be at a
temperature in the range 1400C to 1600C when the binder is bitumen of
penetration grade 80-100. If the binder is other than bitumen of penetration
grade 80-100, the S.O.'s representative shall specify an appropriate range for
the mixing temperature.
For each batch the screened hot aggregates shall be weighed out
into the aggregate weigh hopper in accordance with the proportions
prescribed in the appropriate job mix formula; the sequence of
weighing out progress down to the fines, unless the S.O.'s
representative shall otherwise approve. Mineral filler shall be
weighed out into the filler weigh hopper, where this is provided, or
added last to the aggregate weigh hopper, in accordance with the job
mix formula proportions.
11-14
]
The hot binder shall be weighed out into the binder weight bucket in
accordance with the proportions prescribed in the job mix formula.
The hot aggregates and filler shall be discharged into the pugmill and
mixed dry for the dry mixing time prescribed in the job mix formula,
which shall usually be in the range 5 to 10 seconds. The hot binder
shall then be added and wet mixing performed for the wet mixing
time prescribed in the job mix formula, this shall be sufficient so that
all particles of aggregate are uniformly coated with bitumen, and shall
usually be 45 seconds or more for dense graded mixtures.
The volume of each batch shall be such that the tips of the pugmill
paddle blades just break out of the mixture at height of their action.
The screened hot aggregates and filler shall be fed continuously from
their storage bins in accordance with the proportions prescribed in
the appropriate job mix formula, combined in the plant, and fed
continuously into the mixer. The hot binder shall be sprayed on to
the combined aggregate as it enters the pugmill at the rate required
to achieve the bitumen content prescribed in the job mix formula.
The materials shall then be carried throught the pugmill and in the
process be thoroughly mixed by the action of the paddles, and
discharged over the dam into the storage hopper. The mixing time
shall prescribed in the job mix formula; this shall be sufficient so that
all particles of aggregate are uniformly coated with bitumen, and shall
usually be 45 seconds or more for dense graded mixtures.
Asphaltic concrete shall be transported from the mixing plant to the site of
the paving works in loads of not less than 5 tons using tip-trucks. Except
where asphaltic concrete is to be hand laid, it shall be discharged directly into
the paver hopper, as required, from the tip-trucks. Care shall be taken in the
truck loading, hauling and unloading operations to prevent segregation of the
mix. During transportation, the asphaltic concrete shall be protected from
contamination by water, dust, dirt and other deleterious materials.
11-15
]
layer shall have a compacted thickness of not less than twice the nominal
maximum aggregate size of the mixture, and not more than 100 mm. Where
applicable, e.g. on superelevated sections and on carriageways with cross
slope in one direction only, laying shall commence along the lower side of the
carriageway and progress to the higher side. Laying shall not be carried out
in a downhill direction along any section of road.
Material which has cooled below the specified temperature before laying shall
not be used and shall be removed from the site of the works. The Contractor
shall provide accurate thermometers at the paving site at all times, and shall
check the temperature of asphaltic concrete in the paver hopper at regular
intervals and before laying restarts after each interruption of the paving
operation.
11-16
]
At all construction joints a thin uniform coating of bitumen emulsion of grade
RS-1 shall be brushed on to the vertically cut joint faces some 10 to 15
minutes before laying the next section of bituminous mix commences to
ensure good bonding. Also all contact surface of kerbs, gutters, manholes,
datchpits, etc., shall be similarly treated with a coating of bitumen emulsion
before bituminous mix is placed against them.
Initial (or breakdown) rolling shall be carried out with an approved steel
wheeled tandem roller or three wheeled steel roller. The principal heavy
rolling shall be carried out with an approved pneumatic typed roller
immediately following the initial operating weight of not less than 15 tons and
its tyre inflation pressure shall be not less than 0.7 N/mm2 . The final rolling
shall be carried out with an approved steel wheeled tandem roller and shall
serve to eliminate minor surface irregularities left by the pneumatic typed
roller.
All rollers shall operate in a longitudinal direction along the carriageway with
their driven wheels towards the paver. Rolling shall generally commence at
the lower edge of the paved width and progress uniformly to the higher edge,
except that where there is a longitudinal construction joint at the higher edge,
this shall be rolled first ahead of the normal pattern of rolling. Generally
successive roller passes shall overlap by half the width of the roller, and the
points at which the roller is reversed shall be staggered. However, when
operating on gradients in excess of 4%, the breakdown roller shall not pass
over any previously unrolled mix when operating in the downhill direction.
In all cases compaction shall be carried out in such a manner that each
section receives equal comparative effort, all to the satisfaction of the S.O.'s
representative.
The steel wheeled rollers shall operate at speeds of not more than 5 kph and
the pneumatic typed roller shall operate at speed of not more than 8kph. No
roller or heavy vehicle shall be allowed to stand on newly laid bituminous mix
before compaction has been completed and the material has thoroughly
coiled and set. Rolling shall continue as long as is necessary to achieve the
appropriate requirement in the following table
11-17
]
Binding Course 95-100% Marshall Density
24 hours of laying and compacting the bituminous mix, the Contractor shall
cut core samples of not less than 100 mm nominal diameter at locations
selected by the S.O.'s representative. The rate of sampling shall be 1 sample
per 500m2 Of mix laid, but not less than 2 samples for the work completed in
each paving session. These core samples shall be used by the S.O.'s
representative to determine the thickness of the compacted density of the
material in accordance with either ASTM Test Method D 1188 or ASTM Test
Method D 2726, whichever is applicable.
Asphaltic concrete binder and wearing coruses shall be finished in a neat and
workmanlike manner; their widths shall be everywhere at least those
specified or shown on the Drawings on both sides of the centre-line. For a
binder course or wearing course the average thickness over any 100 metre
length shall be not less than the required thickness, and the minimum
thickness at any point shall be not less than the required thickness minus 5
mm.
The top surface of a wearing or binder course shall have the required shape,
super elevation, levels and grades, and shall be everywhere within the
tolerances specified in Section 1.11.6.
Asphaltic concrete shall not be opened to traffic until compaction has been
completed and the material has thoroughly cooled and set in the opinion of
the S.O.'s representative. This will usually be not less than 4 hours after the
commencement of rolling. Where it is necessary to allow earlier use of the
finished surface to facilitate the movement of traffic, vehicles may be allowed
to run on the work after rolling has been completed, provided that speeds are
restricted to 30 kph or less and sharp turning movements are prohibited.
The design levels of pavement courses shall be calculated from the vertical profile,
crossfall and pavement course thickness shown on the Drawings. The level of any
point on the constructed surface of a pavement course shall be design level subject
to the appropriate tolerances in Table 1.7.
11-18
]
on the Drawings
The regularity of surfaces shall be within the relevant limits in Table 1.8.
TABLE 1.7
Tolerances in Surface Levels of Pavement Courses
Pavement Tolerance
Binder Course + 5 mm
Roadbase + 0 mm
- 20 mm
The traverse length of 300 mm and its associated maximum permissible number of
irregularities shall apply wherever the continuous length of the completed
carriageway is 300 mm or more, whether or not is constructed in shorter lengths.
Where the total length of pavement is less than 300 m the measurements shall be
taken on 75m lengths.
11-19
]
TABLE 1.8
Tolerances in Surface Levels of Pavement Courses
Class SR 1 20 9 2 1 4 mm
Class SR 2 40 18 4 2 8 mm
Class SR 3 60 27 6 3 12 mm
The class of Surface Regularity for each portion of the Works shall be as stated on the Drawings or
in the Bills of Quantities.
11.11.7.1 Road shoulders shall be constructed to lines grades, levels, dimensions and cross-
sections shown on the drawings and as directed by the S.O.
11.11.7.2 The subgrade of tire shoulder shall be stripped of all vegetation, grass, etc., before
material for the shoulder is placed.
(ii) Plasticity index not less than 6 and not more than 15.
11-20
]
(b) Lateriate, gravel, mining ballast or other suitable material conform to the
grading limits given in Table 1.9 for laterite pavement.
11.11.7.3 Shoulders shall be placed and compacted in layers not exceed 200mm thickness
before compaction. The layers shall be compacted to 95% of' maximum dry
density as determined by B.S. Heavy Compaction Test.
11.11.7.4 Payment of all cost of material and royalties at the rate determined by the State
Government shall be paid by the Contractor.
TABLE 1.9
Grading Limits For Granular Pavement Material
40 mm 100 -
20 mm 80 - 100 100
10 mm 55 - 90 80 - 100
5 mm 40 - 70 55 - 90
2.4 mm 30 - 55 40 - 70
420 microns 12 - 30 20 - 40
75 microns 5 - 20 8 - 25
11-21
]
SECTION 12
PAINTING AND PROTECTIVE COATINGS
The work included in this section consists of the furnishing of all labour, materials,
apparatus, scaffolding, and all appurtenant work in connection with the painting, in
accordance with these specifications.
A. All exposed piping and other metal surfaces, interior and exterior.
E. Exterior above ground concrete and brick masonry as specified and shown on
the design plans.
F. The interior of structures as specified in the painting schedule and shown on the
design plans.
H. Doors, woodwork, and architectural trim work as specified and shown on the
plans.
B. Plastic surfaces.
12-1
E. Electrical equipment with approved factory finish as specified in the design.
In no case shall any concrete, wood, metal, or any other surface requiring protection
be left unpainted even though not specifically defined herein.
All paint materials shall be of first quality products manufactured for the exposures
involved, as approved by the Engineer. All paints should conform to the relevant
British Standard Specifications.
12-2
12.2.6 System F Materials
The Contractor shall take the necessary steps to protect the work of other during the
time his work is in progress. Paint shall be applied only during periods of favourable
weather.
All materials specified or selected for use under these specifications shall be delivered
unopened at the job site in their original containers. Paint containers shall be opened
only when required for use. Paint shall be thoroughly stirred or agitated to uniformly
smooth consistency suitable for proper application.
In all cases, paint shall be prepared and handled in a manner to prevent deterioration
and inclusion of foreign matter. No paint shall be reduced or applied in any way
except as herein specifically called for or, if not specifically call for, then it shall be
applied in accordance with the manufacturer's recommendations.
The Contractor shall examine carefully all faces to be finished and before beginning
any of his work shall see that the work of the other trades has been left or installed in
a workmanlike condition to receive paint. Metals shall be clean, dry, and free from mill
scale, rust, grease, and oil.
12-3
12.3.4 Workmanship for Painting Works
Each coat of paint shall be applied at the proper consistency and brushed evenly, free
of brush marks, sags, runs, with no evidence of poor workmanship. Care shall be
exercised to avoid lapping paint on glass or hardward. Paint shall sharply cut to lines.
Finished paint surfaces shall be free from defects or blemishes.
Protective Covering or drop cloths shall be used to protect floor, fixtures, and
equipment.Care shall be exercised to prevent paint from being spattered onto
surfaces which are not to be painted. Surfaces from which such paint cannot be
removed satisfactorily shall be painted or repainted, as required to produce a
satisfactory finish.
12.3.6 Tints
Whenever two(2) coats of paint are specified, the first coat shall contain sufficient
powdered aluminium or carbon black to act as an indicator of proper coverage, or the
two(2) coatings must be of contrasting colour.
12.3.7 Brushing
All paint shall be applied by brush unless otherwise specifically approved by the
Engineer.
12.3.8 Instructions
12.3.9 Ventilation
The Contractor shall not permit painting to begin in enclosed places, until a forced
draft ventilation system of sufficient air volume has been placed in operation.
No exterior painting or interior finishing shall be done under conditions which may
jeopardize the appearance or quality of the painting or finishing in any way. The
Engineer shall have the right to reject all material or work that is unsatisfactory, and
require the replacement of either or both.
12-4
A. Surface Preparation to all metal surfaces shall be field sand-blasted. Weld
surface, edges, and sharp corners shall be ground to a curve and all weld
splatter removed.
Metals not subject to chemical attack, normal indoor exposure, except as specified for
buildings.
A. All surfaces shall be freed of dirt, dust, grease, or other foreign matter before
coating. Weld surfaces and rough edges shall be ground and weld splatter
removed.
C. The coating system shall have a minimum of total dry film thickness of 100
micron resulting from a prime coat and at least two finish coats.
C. The prime coat shall have a minimum thickness of 75 micron and two or more
finish coats shall have a minimum total thickness of 400 micron. The total
system shall have a minimum dry film thickness of 475 micron.
Exterior or interior brick, concrete, and concrete block work exposed to view not
subject to immersion in sewage and not subject to pedestrian traffic except as
otherwise specified. Interior surfaces not specifically indicated shall not be painted. All
12-5
concrete block surfaces to be painted shall be filled with a latex type block filler
supplied by the paint manufacturer whose products are used prior to first or prime
paint coat.
A. All surfaces shall be freed of dirt, dust, grease, and other foreign matter before
coating. Cracks and voids shall be repaired or filled with a suitable caulking
material compatible with the specified paint.
B. The first coat shall be applied to cover and provide a smooth base. The finish
coat shall be applied to a dry film with minimum thickness of 37.5 micron.
C. The filler coat may be recoated in 12 hours, the finish coat is dry for a recoat in
two hours.
A. All internal walls and slabs shall be applied with High Alumina Cement plaster
(20mm min cement:sand ratio 1:3) prior to coating.
B. All surfaces shall be cleaned of all dirt, dust, form oil, curing compounds, and
other deleterious compounds. In general, the concrete shall be reasonable
smooth, and free of pockets and cavities.
C. Prime coat shall be two parts coal tar epoxy with one part manufacturer's thinner
mixed according to the manufacturer's recommendations. The finish coats shall
be two or more coats of coal tar epoxy (undiluted) to a dry film thickness of 500
micron.
A. Surface preparation, coating system and time between coats are as specified for
System D.
A. All surfaces shall be freed of dirt, dust, grease, and other foreign matter before
coating. Cracks and voids shall be repaired or filled with a suitable caulking
material compatible with the specified paint. Efflorescence shall be neutralized
with zinc sulfate solution and allowed to dry.
12-6
B. The prime coat shall be applied to cover and provide a smooth base. The
undercoat and finish coat shall be applied to a total dry film with minimum
thickness of 75 micron.
C. Each coat shall be shall be completely dry before the next coat is applied.
B. Prime coat shall be applied to cover and provide a smooth base. Each finish
coat shall be applied to a minimum dry film thickness of 50 micron.
For interior and exterior metal not painted under Systems A, B and C.
A. For ferrous metal, specified for System B. Wash galvanized surfaces with
solvent thinner.
The following schedule shall indicate the coating system to be used. All surfaces shall
be painted except those specified deleted herein. The Engineer shall select the
colours.
All exposed pipe, including tubing, galvanized pipe, and polyvinyl chloride pipe, shall
be identified by colour code to show its function. Painted surfaces shall be colour
coded in accordance with the coding schedule and adhesively applied colour bands of
an approved tape type shall be used on plastic and any other pipe not readily
suspectible to painted finish. Piping which is not painted shall be provided with 30 cm
wide colour bands every 3m and each change of direction. Labels and arrows
showing direction of flow shall be installed on all piping every 3m and at each change
of direction. Colours and labels shall conform to the following schedule or as selected
by the Engineer where not shown or otherwise required by applicable codes and
regulations.
12-7
PROCESS PIPING COLOUR CODE SCHEDULE
The following list shall indicate the coating system. For this coating system "Piping"
shall be defined as all pipe, valves, fittings, supports, operating stems and guides.
Mechanical equipment shall include all drives, motor control panels, and all other
electrical equipment shall be selected by the Engineer. Architectural coating systems
are specified on the plans.
A. Manholes
G. Miscellaneous
12-8
SECTION 14
BRICK LAYING AND PLASTERING WORKS
14.1 BRICKS
All bricks shall be clay bricks obtained from an approved kiln and shall be of standard
size, hard, sound, well burnt and free from active lime giving a clear ring when struck
to and to BS 3921. No soft, broken, twisted or otherwise defective bricks shall be
allowed to be used.
No brick shall absorb more than 15% of its own weight when soaked in water for 24
hours. Testing of bricks shall be in accordance with BS 3921. Bricks shall be
unloaded by hand and stacked on a clean hard surface.
Cement, sand and water shall as specified under the Section 9. Mortar for brickwork
in general shall be composed of 1:3 cement and sand unless otherwise specified on
the drawings or directed by the Engineer.
14.3 BRICKWORK
A. Build all walls, piers, etc. in English bond when the thickness is 215mm or more
and in stretcher bond where the thickness of wall is 102.5mm. Sufficient bricks
for one day's work shall be well soaked in water before being laid and the
Contractor shall provide sufficient containers and water for this purpose. Bricks
shall be protected from direct sunlight by damp gunny sacks for at least 2 days
after being laid.
B. Mortar Joints shall not exceed 9.5mm in thickness. Vertical Joints of alternative
courses shall be directly above one another. Bricks shall be properly bedded in
mortar and surplus mortar struck off flush. Exposed joints on walls for rendering
shall be raked out to a depth of 12.5mm as the work proceeds, to form a key.
C. Brickwork shall be accurately set out and built true to line and face with vertical
surfaces truely plumb and horizontal joints truely level. Intersections, angles,
plasters and piers shall be properly bonded. Broken bricks may be used only to
obtain bond.
E. Build all half brickwalls in stretcher bond, reinforced at every fourth course with
approved brick reinforcement similar to "Exmet", commencing at two courses
above base of the wall.
14-1
14.4 CRAMPS
Provide and fix wrought iron cramps 38mm x 12.5mm x 300mm long at the rate of 2
cramps per window jamb and 3 cramps per door jamb. The projecting end shall be
bent down to fit over the end of the brick and the other end bent up and screwed to
jamb. Cramps shall be coated with bitumen and built in as the work proceeds.
Perform cuttings, straight or circular, rough and fair, firm all sinkings, setbacks and
projections, cut or leave chases for edges, flashings, etc., cut and leave holes through
walls and slabs for passage of pipes, wiring etc., built in fittings and fixtures and do
everything else necessary for the proper completion of the brickwork.
A. Provide and lay under all brickwalls at ground level or within 150mm above
ground level damp proof course (to the full width of the wall or more as directed
to form "Bell-Cast") composed of "Pulvex" or other equal and approved hessian-
based bituminous D.P.C. complying with BS743 and weighing not less than 3.8
kg. per square metre. It shall be lapped 150mm at joints and laid on a 19mm
thick cement/sand mortar (1:3) bed coated with bitumen or as specified.
B. In all cases of doubt the Contractor must enquire the exact location of the damp
proof courses and if he neglects to do so he will be held responsible for
amending, if required, their positions.
Roofing screeds and screeds for floors and channels shall be formed with 1:3
cement-sand mortar finished neatly to the fall and dimensions shown on the
Drawings.
The mixing shall be as specified for concrete with the water content just sufficient to
produce a dense mortar or adequate workability.
Before commencing to roof screed, the roof surface shall be thoroughly roughened by
picking or wire brushed to expose a fresh surface and cleaned. The concrete shall
then be soaked with water over-night, after which the excess water shall be removed.
A thin layer of cement grout shall, just before the screed is laid, be well brushed into
the roughened surface. The screeding shall be kept damp for a period of seven days
after laying.
A. Render all concrete floors, steps, aprons and drains in cement sand mortar of
1:3 mix or as specified, to a thickness of 19mm laid to falls as shown or directed.
Rendering shall be applied while base concrete is green. The base concrete
shall be thoroughly brushed clean and wetted before mortar is applied.
B. Set out rendering in panels not exceeding 10 sq.m. separated with 13mm
limewashed timber fillets which shall be withdrawn on completion and the space
filled with 1:3 cement mortar. Dusting with neat cement will not be permitted.
14-2
C. Form 19mm thick skirting 150mm high with 38mm radius core at bottom against
all rendered surfaces. Skirting shall finish flush with wall rendering and shall
meet it in a neat "V" joint.
D. All wall surfaces to be rendered shall be cleaned and well damped before
rendering is applied and where necessary raked to form a key. Carry all
rendering into reveals, setbacks, etc. and form all finished edges, arises and
internal angles neatly and accurately.
E. Render all walls in cement sand mix of 1:3 or as specified, applied in two coats
to a final thickness of 19mm. Steel trowelled to a smooth even surface.
14.9 PLASTERING
Mortar for plastering to soffits, beams, etc. shall be composed of one part of cement
to six parts of sand or as specified with the addition of an approved mortar plasticiser
and used strictly in two coats to a total thickness of 19mm.
14-3