04_3 Section IVC Fabrication, Erection & Stringing,Rev-9(Jan'2025)
04_3 Section IVC Fabrication, Erection & Stringing,Rev-9(Jan'2025)
SECTION-IVC
TECHNICAL SPECIFICATIONS
SECTION-IV C
TECHNICAL SPECIFICATIONS
SECTION-IV C
CONTENTS
TECHNICAL SPECIFICATIONS
SECTION- IV C
TOWER: MATERIALS, FABRICATION, ERECTION & STRINGING
1.1.2.11 To ensure effective in-process Quality control it is desirable that the manufacturer should have in house
testing facility for all tests like weight of zinc coating, shear strength and other tests etc. The manufacturer
should also have proper Quality Assurance System which should be in line with the requirement of this
specification and IS 9001 series Quality System Standard.
1.2 Design and Drawings
ii) The contractors who have already done the proto-assembly of the towers/
tower extensions or have supplied the same towers/ tower extensions
against any earlier POWERGRID’s project need not do the proto assembly.
They shall submit documentary evidence viz. proto-inspection reports,
supply records etc. in its support. However, they may do the proto-
assembly for their verification and satisfaction. Further, they shall submit
the structural drawings and BOM of tower/ tower extensions after
endorsing the projects name for further distribution by Employer.
SECTION-IV C (VOLUME-II), Rev 9 (Jan’2025) Page 4 of 48
STANDARD SPECIFICATION OF TRANSMISSON LINE
(SECTION-TOWER: MATERIALS, FABRICATION, ERECTION
& STRINGING)
Alternatively, in place of physical proto assembly (as specified in (i) and (ii) above),
contractor may also carry out proto assembly using any suitable software/3D
modelling software.
No payment shall be made to the Contractor on the account of proto-assembly
in either of the cases mentioned at (i) or (ii).
In any case, the onus of correct fabrication / fitment of tower parts shall lie with
contractor. Any defect, if found during erection at site, the same has to be
rectified by the contractor without any additional financial implication to
POWERGRID.
1.2.4 All the drawings shall have a proper name plate clearly displaying the name of
Employer on right hand bottom corner. The approval for exact format of the
nameplate shall be provided to the successful bidder for incorporation of the same
on all the drawings.
1.2.5 The Contractor is required to submit the drawings as mentioned in clause 1.5.1 for
Employer’s approval. While submitting the designs, structural drawings, bill of
materials and any other drawing pertaining to the subject transmission line, the
Contractor shall clearly indicate on each drawing POWERGRID Specification No.,
Name of the transmission line and project, letter reference No. and date on which
the submission are made. The same practice is also to be followed while submitting
distribution copies.
1.2.6 The tower accessories drawings like Number plate, Danger plate, phase plate,
Circuit Plate, Anti-climbing device, Pole plate, Step Bolt and Earthing Arrangement
have been standardized (except Bird Guard) and are enclosed in drawing section of
this specification. The contractor is required to submit distribution copies of the
above drawings after endorsing the name of the projects. However, drawing of Bird
Guard, D-shackle etc. shall be prepared by the Contractor and shall be submitted to
the Employer for approval.
1.2.7 The drawings submitted by the Contractor shall be approved/ commented by the
Employer as the case may be within fifteen (15) days of receipt of drawings in
Employer office. If the designs/ drawings are commented by the Employer, the
Contractor shall submit revised design/ drawings duly incorporating all comments
within fifteen (15) days of date of issue of comments.
The mass fabrication shall be taken up from the shop drawings. The overall
responsibility of fabricating tower members correctly lies with the Contractor only
and the Contractor shall ensure that all the tower members can be assembled/
fitted while erecting without any undue strain on them.
1.2.8 The Contractor is required to furnish the progress of submissions and approvals of
designs and drawings on twenty fifth day of every month till the completion of all
the design activities.
The details shall include description of design/ drawing, schedule date of
submission, actual date of submission, schedule date of approval, actual date of
approval, schedule date of submission of distribution copies, actual date of
submission of distribution copies, schedule date of tower test, actual date of tower
test and ‘Remarks’ column. Provision of six additional columns shall also be made
in the above progress report to indicate date of comments issued by the Employer
and details of submission of revised designs/ drawings.
1.2.9 Other than the items indicated above, some other drawings and documents such as
BOM, Shop drawings, structural drawings for towers/ extensions which are required
for the project, shall also be developed by the Contractor based on single line
diagram provided by the Employer. However, no extra cost on this account shall be
payable to the Contractor.
1.3 Tower Accessories
Arrangement shall be provided for fixing of all tower accessories to the tower at
a height between 3.5 meters and 4.5 meters above the ground level.
1.3.1 Step Bolts & Ladders
Each tower shall be provided with step bolts as per drawing enclosed in the
section of drawing. The step bolts conforming to IS 10238 of not less than 16mm
diameter and 175 mm long, spaced not more than 450 mm apart and extending
from 3.5 meters above the ground level to the top of the tower. However, the
head diameter shall be 35mm as indicated in the enclosed drawing. The step bolt
shall be fixed on two diagonally opposite legs up to top of the towers for single,
double and multi circuit towers. Each step bolt shall be provided with two nuts on
one end to fasten the bolt securely to the tower and button head at the other end
to prevent the feet from slipping away. The step bolts shall be capable of
withstanding a vertical load not less than 1.5 KN. For special river crossing towers,
ladders alongwith protection rings as per the Employer approved design shall be
provided in continuation of the step bolts on one face of the tower from 30 meters
above ground level to the top of the special structure. From 3.5m to 30m height
of super structure step bolts shall be fixed on two diagonally opposite legs.
Suitable platform using 6mm thick perforated chequered plates alongwith
suitable railing for access from step bolts to the ladder and from the ladder to
each cross-arm tip and the ground wire support shall also to be provided. The
platform shall be fixed on tower by using counter-sunk bolts.
1.3.2 Insulator Strings and Earth wire Clamps Attachments
b) The letters, figures and the conventional skull and bones of danger plates
shall conform to IS 2551 and shall be in a signal red on the front of the plate.
c) The corners of the danger, number and circuit plates shall be rounded off to
remove sharp edges.
d) The letters of number and circuit plates shall be red enameled with white
enameled background.
1.3.5.1 Bird Guard
To prevent birds perching immediately above the suspension insulator strings (I
type/ V type) and fouling the same with dropping, suitable bird guards shall be
provided on all suspension towers. In case of I string Bird Guard as per IS 5613
shall be provided at cross arm tips. In case of V string, saw type Bird Guard shall
be provided on all the members/ redundant members provided on Top and
Bottom plan of cross arm/ Girder/ BOOM/ Beam of Suspension. The typical
drawing of Bird guard is attached at the drawing section of this specification.
Suitable provision of cleat/ plate to be provided on all Suspension towers
facilitating installation of bird guard after stringing.
1.3.6 Aviation Requirements
1.3.6.1 Aviation requirements viz Span marker, night marker (obstruction light) and
painting of towers conforming to IS 5613 shall be in the scope of Contractor,
wherever indicated in BPS.
1.3.6.2.1 The scope of night markers covers the design, manufacture, testing at
manufacturers works, if any, supply, delivery, erection, testing and
commissioning of medium intensity, low intensity, lights along with storage
battery & solar panel, control panel, cables, clamps other accessories etc. as per
the provision of IS 5613 (Part-II/Section-I) regarding night & day visual aids for
denoting transmission line structures as per the requirement of directorate of
flight safety.
1.3.6.2.2 The detail of each component of medium intensity, low intensity lights &
associated accessories to be provided on the towers shall be as per the technical
specifications given in the preceding clauses and IS/ICAO, International Standards
recommended practices.
1.3.6.2.3 One set of Aviation Lights shall consist of one medium intensity light & two/four
(as applicable) low intensity lights along with all accessories such as solar panel,
control panel, batteries, cables etc.
1.3.6.2.4 Medium Intensity Light
Medium Intensity light shall be provided on the top of each tower. The medium
light should have night time intensity as per ICAO requirements in international
Standards Recommended Practices. The light on top of the structure should flash
at the rate of 20 sequences per minute. The effective intensity during night time
for the medium flashing light shall be 1600 CD. The light shall conform to ICAO
requirements/ BS 3224a and shall have weather protection conforming to IP 55.
The above lights conforming to ICAO specifications flashing red lights shall be DC
operated through a suitably sized battery bank at the operating voltage 12V/24V
DC. The burning life of the lamps shall be maximum possible in view of the
maintenance hazard of H.T. live but in no case, it should be less than 15,000
burning hours. In case of failure of the lamp before 15,000 burning hours, the
same shall have to be replaced by the Contractor free of cost even if the pendency
of contract expires. The light shall be equipped with radio suppression facility
conforming to BS800 in order to avoid any interference with signals of PLCC etc.
1.3.6.2.5 Low Intensity Lights
Two/ four (as applicable) nos. of low intensity lights are required to be put on
each of the towers. Placement drawing for the same shall be submitted by the
bidder Contractor.
The light shall be stationary lamp with minimum effective intensity of 32 CD. of
red light. The lamps shall conform to the ICAO requirement/relevant BS and shall
have weather protection of minimum IP 55 class.
Two/four nos. of L.I. lamp required for each tower shall be operated through a
suitable size common battery bank solar panel as per the requirement of
operating voltage and load current of the type of lamps being offered.
The burning life of the lamps shall be maximum possible in view of the
maintenance hazard of H.T live line, but in no case, it should be less than 15,000
burning hours. In case of failure of the lamp before 15,000 hours, the same shall
have to be replaced by the Contractor free of cost even if the pendency of
contract expires.
The low intensity lamp shall not generate any R.F. which can interfere with the
PLCC signals.
1.3.6.2.6 Storage Battery
Storage Battery required for the above purpose shall be sealed maintenance free,
valve regulate lead acid and suitable for mounting on the top of the transmission
line towers. Contractors shall offer the most optimum capacity of the Battery
Bank at 120hour discharge rate (considering 80 % percentage usage) matching
with the load requirement of the type of lamps being offered including any power
loss in the associated cables. The battery sizing shall conform to JISC 8707/
relevant Indian Standard or any other internationally recognized standard. The
SECTION-IV C (VOLUME-II), Rev 9 (Jan’2025) Page 9 of 48
STANDARD SPECIFICATION OF TRANSMISSON LINE
(SECTION-TOWER: MATERIALS, FABRICATION, ERECTION
& STRINGING)
battery shall be hermetically sealed explosion proof and self-resealing type and
free from orientation constraints. The working temperature ranges shall be
minimum 00 C and maximum 500 C. Performance certificate of the offered
batteries shall be submitted by the Contractor.
The provision for design, supply & erection of mounting arrangements for
photovoltaic modules on the transmission towers in a suitable manner to harness
maximum solar energy shall be in the scope of the Contractor.
Provision for design, supply & erection of resting platform for the erection of
battery bank in a closed enclosure with safety arrangement on the transmission
towers shall also be in the scope of the Contractor. The design and load
consideration for safety of towers due to additional plate form shall be kept in
view while designing, selecting the above.
1.3.6.2.9 Control Panels
Control panels shall consist of solar charge controller, flasher unit, sensor,
isolator, MCB, Voltmeter, Ammeter and other control gears. Panel enclosure shall
be fabricated out of 14 SWG CRCA sheet and thoroughly treated and painted.
Suitable neoprene rubber gasket and pad locking device shall be provided and the
protection class shall be of IP 55 class.
The Solar charge controller shall be most efficient and preferably fully solid
state. It shall be provided with protection to load against increase in temperature,
Surge, automatic low voltage and automatic disconnection and reconnection
during high inrush current and normalcy respectively.
The flash regulator shall be provided for regulating light flashing. The same shall
be completely solid state and provided with flash rate set points. The protection
against overload current shall also be provided.
Necessary sensor/ timer shall be provided in the system to “switch on” the light
automatically in the evening and poor visibility period and switch off the same
during day time and normal visibility period.
1.3.6.2.10 Cables, Cable Glands, Conduits and Accessories
The cable to be supplied and erected shall be of multi strands copper conductor,
weather proof, PVC insulated PVC sheathed, armoured 1.1 KV grade. The same
shall conform to IS 1554.
All the cable accessories such as thimble, glands etc. shall be in the scope of
supply and erection of the Contractor.
Supply and erection of all the PVC conduits and accessories shall be in the scope
of the contract. All the conduit and accessories shall be as per the relevant ISS or
ISI brand.
The inter-connection cable/ conduit will be clamped in a secured manner with the
tower members and any interconnection should be made only inside the
environmentally protected junction box.
1.3.6.2.11 Earthing
SECTION-IV C (VOLUME-II), Rev 9 (Jan’2025) Page 11 of 48
STANDARD SPECIFICATION OF TRANSMISSON LINE
(SECTION-TOWER: MATERIALS, FABRICATION, ERECTION
& STRINGING)
All the installations on the tower shall be securely and properly earthed with the
tower body by using flexible copper braided wire. Cost of earthing material shall
deem to be included in the total cost.
The dynamic solar powered LED type Bird Flight Diverter, consist of warning disc
(2-D or 3-D in design) and associated clamps & connectors, shall be preferred in
areas where foggy/dusty weather persists or intensity of light is low or the
sections of the lines lying in the route of migratory birds. BFD may be mixture of
LED and Non-LED BFD, where on a line LED type BFD should be at least 20%. For
solar powered LED type diverter, following additional requirement shall be
fulfilled:
(a) LED shall be of Orange colour with adequate light intensity so that it is
clearly visible from a distance (>300 m) even during foggy/dusty weather/
under low intensity of light.
(b) Battery shall be guaranteed for service life of 5 years and shall be suitable
for at least 100 hours of flashing operation by single charge.
(d) Position of solar cell shall be such that it gets sunlight irrespective of
direction of the diverter face and the dust & snow does not decrease its
efficiency.
Bird Flight Diverter (BFD) shall be designed for expected service life of at least 15
years. The Bird Flight Diverter shall be lightweight (total weight for each Non-
SECTION-IV C (VOLUME-II), Rev 9 (Jan’2025) Page 12 of 48
STANDARD SPECIFICATION OF TRANSMISSON LINE
(SECTION-TOWER: MATERIALS, FABRICATION, ERECTION
& STRINGING)
LED & LED type BFD shall not more than 500 gm and 800 gm respectively), and
should be easily installed by hand or by hot stick (under live line condition) or by
any other suitable method. Length of bird diverter, from connection point to
end, should not be more than 430 mm. The bird diverters should retain good
physical characteristics under all weather conditions, within a range of extreme
temperatures i.e. from -150 C to 850 C for conventional conductor and maximum
operating temperature under emergency loading conditions may be considered
to withstand temperature in case of HTLS conductor. Contractor/ subcontractor
shall submit valid test report/test certificate for mechanical test, ageing test i.e.
solar radiation test & sand and dust test as per MIL- STD 810 F etc. from
accredited third-party laboratory for the design which they intend to supply. The
grip on the earthwire/OPGW should ensure that the Bird-Flight Diverter remains
in the applied position and does not move along the span under Aeolian
vibration or other conditions.
Generally Suspended devices i.e. Dynamic Bird Flight Diverters shall be used in
the transmission line as bird diverters.
1.3.7.1 Suspended devices: Dynamic Bird Flight Diverters
Bird flight Diverters shall have one warning disc(2-D or 3-D in design) which shall
be attached to the wire through spring loaded clamp & connectors. Warning disc
shall be made through injection moulding of UV stabilized plastic while the
attachment clamp shall be made of UV stabilized engineered composite plastic.
All fasteners and spring shall be of stainless steel.
1.3.7.1.1 Warning Disc
Warning disk of Bird Flight Diverter must swing, sway, must not flip on the
powerline in high wind velocity, rotate and should have contrasting coloured
(combination of any two colours from Red,black, Yellow, Orange, White) retro-
reflective surface with Sun and Moon light reflectors on both faces. The colour
change, while revolving, shall provide significant forewarning. Warning disk must
glow in dark & glow in the dark shall remain activated for at least 12 hours after
exposure to sunlight and the warning disk in the BFD should have strong
luminescence properties that emit immense light to provide enhanced visibility
to the birds at night. If Glow in dark stickers are used, the same shall be
laminated and suitable for all weather conditions. The Warning disc should be
aerodynamically stable so that diverter faces minimum amount of drag force
which provide swing and rotation effect under medium/strong wind speed.
Diameter of circular warning disk shall not be less than 150 mm. If warning disk
is quadrilateral or trapezoid, then shortest arm length should not be less than 90
mm and total surface area of warning disc should not be less that 15,000 mm2
(including air vents). Thickness of the warning disc shall not be less than 3 mm.
Minimum reflective area on each face of warning disk shall not be less than 3500
mm2 . Glow in Dark area also should not be less than 3500 mm2 for LED type
BFD and not less than 7500 mm2 for the non LED type BFD. All suspension
hardware which are directly exposed (moving or static) must be corrosion free.
Bearing swivel shall be made of stainless steel and should allow free spinning in
minimum wind speed of 1 km/hour & be made of sealed bearing to avoid
deposition of sand and/or soil particles and helps in smooth rotation.
1.3.7.1.2 Clamp
The clamp of the Bird flight diverter shall be made of UV stabilized engineered
composite plastic (polymer) or metal or carbon fibre. Spring type clamp, suitable
for holding earth wire/ OPGW/conductor shall be used.
It shall be capable of supporting the Bird flight diverter during installation and
prevent damage or chaffing of the earth wire/ OPGW/conductor during erection
or continued operation. The clamp shall have smooth and permanent grip to
keep the Bird flight diverter in position on the earth wire/ OPGW/conductor
without damaging the strands or causing premature fatigue failure of the earth
wire/OPGW/conductor under the clamp. More than 50% of clamp gripping area
shall be in contact with earth wire/OPGW/conductor. The groove of the clamp
body and clamp cap shall be smooth, free from projections, sharp end/edges,
abrasions, grit or materials which could cause damage to the earth
wire/OPGW/conductor when the clamp is installed. In case of metallic bird
diverters, the parts of clamp, touching earth wire/OPGW/conductor must be
made of material, which is bad conductor of electricity.
The Clamp shall have strong grip on earth wire/ OPGW/conductor. The clamp
should not slip when pulled by a force of 250 N in the direction parallel to
earthwire/ OPGW/conductor. The details/ properties of Earthwire
/OPGW/conductor are mentioned in relevant section of Earth wire/OPGW of
Technical specification. All exposed metal parts of clamp shall be corrosion free.
The Clamp must be able to bear pulling load of minimum 500 N.
1.3.7.2 The supplier shall guarantee that there shall not be any failure/ breaking of bird
flight diverters under normal operating condition. In the event of any failure/
breaking of bird flight diverters during the first five (05) years of service, supplier
shall supply to the purchaser free of cost spare bird flight diverters equal to the
failed bird flight diverters quantity.
Report/ Certificate for following type tests conducted in any NABL or equivalent
accredited laboratory shall be submitted to the Purchaser. All of the following
tests shall be conducted on the same sample. However, No. of Samples for type
tests shall be as per relevant standard or procedure specified in Annexure-I to
this Section. Type test report shall be valid for 10 years from the date of
successful completion of test.
1.4.4 The diameter of the hole shall be equal to the diameter of bolt plus 1.5 mm.
1.4.5 The structure shall be such that all parts are accessible for inspection and cleaning.
Drain holes shall be provided at all points where pockets of depression are likely
to hold water.
1.4.6 All steel sections before any work is done on them, shall be carefully leveled,
straightened and made true to detailed drawings by methods which will not injure
the materials so that when assembled, the adjacent matching surfaces are in close
contact throughout. No rough edges shall be permitted in the entire structure.
1.4.7 Drilling and Punching
1.4.7.1 Before any cutting work is started, all steel sections shall be carefully straightened
and trued by pressure and not by hammering. They shall again be trued after
being punched and drilled.
1.4.7.2 Holes for bolts shall be drilled or punched with a jig but drilled holes shall be
preferred. The punching may be adopted for thickness up to 12 mm. Tolerances
regarding punch holes are as follows: -
a) Holes must be perfectly circular and no tolerances in this respect are
permissible.
b) The maximum allowable difference in diameter of the holes on the two
sides of plates or angle is 0.8mm. i.e. the allowable taper in a punched holes
should not exceed 0.8mm on diameter.
c) Holes must be square with the plates or angles and have their walls parallel.
1.4.7.3 All burns left by drills or punch shall be removed completely. When the tower
members are in position the holes shall be truly concentric/ matching to each
other. Drilling or reaming to enlarge holes shall not be permitted.
1.4.8 Erection mark
1.4.8.1 Each individual member shall have erection mark conforming to the component
number given to it in the fabrication drawings. The mark numbers shall be marked
with marking dies of 16mm size before galvanising and shall be legible after
galvanizing.
1.4.8.2 Erection Mark shall be A-BB-CC-DDD
A = Employer’s code assigned to the Contractors- Alphabet
BB = Contractor’s Mark-Numerical
CC = Tower Type Alphabet.
DDD = Number mark to be assigned by Contractor - Numerical.
Erection mark for high tensile steel members shall be prefixed by the letter “H”
1.5 Quantities and weights
1.5.1 The quantities of the following items have been envisaged in Metric Tonne (MT)
in case of Employer design towers and in ‘Nos.’ in case of Contractor design
towers, in the relevant price Schedules for various types of towers: -
i) Basic Body
ii) Body Extensions, wherever required
iii) Leg Extension
iv) Stubs & Cleats
v) Bolts & Nuts including spring washers and step bolts etc. for above items
During detailed engineering, proto corrected shop drawings shall be released by
POWERGRID for fabrication and manufacturing as per the Technical Specification
to the Contractor. The contractor shall carry out proto-assembly after fabrication
from the Employer’s shop drawing for his verification/ satisfaction prior to mass
production of the tower.
The manufacturing of the above items shall be taken up in such a manner that the
Equipment/ Material offered for inspection to POWERGRID are on completed
tower basis for each type of tower, completed Stubs & Cleats set basis so as to
facilitate availability of erectable tower of each type and erectable stubs & cleats
set for casting of foundation. After inspection of the offered Equipment/ Material
by POWERGRID representative(s), CIP shall be issued by POWERGRID for the
material meeting the Technical Specification. However, MICC shall be issued only
on Completed Tower Basis for each type of tower (comprising the required Basic
Body, body extensions wherever required, four (4) equal or defined unequal Leg
Extension, Bolts & Nuts along with D-shackles, Hangers, Packing and Spring
Washers) and on completed Stubs & Cleats set basis for each type of tower
foundations (comprising a set of stubs & Cleats, required Bolts and Nuts along
with Spring Washers).
Towers to be supplied by the Contractors/ Tower Manufacturers shall be
dispatched Panel wise as per mutually agreed procedure with Employer Quality
Assurance & Inspection Department.
Accordingly, the payment shall be released on completed Tower Basis for each
type of tower (comprising the Basic Body, body extensions, wherever applicable,
bolts & nuts along with spring washer and step bolts, four (4) equal or defined
unequal leg extensions wherever applicable for a completed tower) and on
completed Stubs and Cleats set basis for each type of foundation (comprising a
set of stubs & cleats, required Bolts and nuts along with Spring Washers) based
on the weight of the tower parts as calculated as per Clause 1.5.3 and fasteners
based on the unit rates incorporated in the contract.
1.5.2 The provisional quantities required (including provisional spare tower quantity)
are mentioned in the respective Schedules of BPS. Final quantities shall be
determined after completion and approval of the detailed route survey. The final
quantities of tower including spare towers shall be confirmed by the Employer/
Site -in-charge based on the requirement of quantities of various towers furnished
by the Contractor after completion of detailed survey. Hence it will be
responsibility of the Contractor to intimate the exact requirement of all towers
and various line materials required for line immediately after the survey.
The Employer reserves the right to order the final quantities including required
quantities of spares for which the rates quoted in the Bid shall be valid. Regarding
quantity variation the provisions of relevant clauses of SCC shall apply.
1.5.3 The estimated total weight of tower/ tower parts as well as bolts & nuts along
with spring washers and step bolts to be supplied by the Contractor under various
packages have been envisaged in the relevant Price Schedule. Though fully
galvanised tower parts are to be supplied, the weight of tower shall mean the
weight of tower calculated by using the black sectional (i.e. ungalvanised) weight
of steel members of the size indicated in the approved fabrication drawings and
bill of materials, without taking into consideration the reduction in weights due
to holes, notches and bevel cuts etc. but taking into consideration the weight of
the D shackles, hangers, strain plates, pack plates, gusset plates, extension
link/plates and pack washers etc. The weight of stub and cleats also shall be
calculated in similar manner. The weight of strain plates, pack plates, extension
link and gusset plates shall mean the weight of its circumscribing rectangle,
without taking into considerations the reductions in weight due to holes, notches
etc. The weight of D-shackles, hangers and pack washers shall be net actual
weight taking into consideration reduction due to holes. For bolts and nuts along
with spring washers and step bolts, the weight per tower shall be calculated from
the bolt schedule applicable to each type of towers and body extensions as
approved by the Employer. The rate quoted by the bidder for tower/tower parts
supply, is deemed to be inclusive of galvanising charges including the cost of zinc.
1.5.4 The contractor is permitted to get inspected and supply upto 2.5% extra fasteners
to take care of losses during erection. No payment shall be admissible for these
extra supplies.
1.6 Galvanising
1.6.1 Fabricated Tower Parts & Stubs
The tower parts, stubs and pack washers shall be hot dip galvanized. The
galvanization shall be done as per requirements of IS 4759 after all fabrication
work is completed. The contractor shall also take guidelines from the
recommended practices for hot dip galvanizing laid down in IS 2629 while
deciding and implementing galvanizing procedure. The mandatory requirements
however, are specified herein.
The fabricated tower parts and stubs shall have a minimum overall Zinc coating
of 610 gm per sq. m of surface area except for plates & sections below 5mm which
shall have Zinc coating of 460 gm per sq. m of surface area. The average zinc
coating for all sections and plates 5mm & above shall be maintained as 87 microns
and that for plates & sections below 5mm shall be maintained as 65 microns.
However, for coastal areas or creek regions or aggressive soil areas or under
marine environment, as specifically mentioned in BPS the fabricated tower parts
and stubs shall have a minimum overall zinc coating of 900 gm/ sqm of surface
area except for plates and sections below 5mm which shall have a minimum
overall zinc coating of 610 gm/sqm of surface area. The average zinc coating for
all sections and plates 5mm and above shall be maintained as 127 microns and
that for plates and sections below 5mm shall be maintained as 87 microns.
The zinc coating shall be adherent, reasonably uniform, smooth, continuous and
free from imperfections such as black/ bare spots, ash rust strains, bulky white
deposits/ wet storage strains and blisters.
The surface preparation for fabricated tower parts and stubs for hot dip
galvanizing shall be carried out as indicated herein below:
(ii) Pickling: Pickling shall be done using either hydrochloric or sulphuric acid
as recommended at clause 4.3 of IS 2629. The actual concentration of the
acids and the time duration of immersion shall be determined by the
Contractor depending on the nature of material to be pickled. Suitable
inhibitors also shall be used with the acids to avoid over pickling. The acid
concentration, inhibitors used, and maximum allowable iron content shall
form part of plant standard to be formulated and submitted to employer
along with Quality Assurance Program.
(iii) Rinsing: After pickling, the material shall be rinsed, preferably in running
water to remove acid traces, iron particles or any other impurities from the
surface. Two rinse tanks are preferable, with water cascading from the
second tank to the first to ensure thorough cleaning. Wherever single tank
SECTION-IV C (VOLUME-II), Rev 9 (Jan’2025) Page 19 of 48
STANDARD SPECIFICATION OF TRANSMISSON LINE
(SECTION-TOWER: MATERIALS, FABRICATION, ERECTION
& STRINGING)
(iv) Fluxing: The rinsed article shall be dipped in a solution of Zinc ammonium
chloride. The concentration and temperature of the flux solution shall be
standardized by the contractor depending on the article to be galvanized
and individual circumstances. These shall form part of plant standard to be
formulated and submitted to Employer along with Quality Assurance
Program. The specific gravity of the flux solution shall be periodically
monitored and controlled by adding required quantity of flux crystals to
compensate for drag-out losses. Free acid content of the flux solution also
shall be periodically checked and when it is more than two (2) grams of free
acid per litre of the solution, it shall be neutralized. Alternatively, Ph value
should be monitored periodically and maintained between 5.0 to 5.5.
(v) Drying: When dry galvanizing is adopted the article shall be thoroughly
dried after fluxing. For the purpose of drying, the contractor may use hot
plate, air oven or any other proven method ensuring complete drying of
the article after fluxing and prior to dipping in the molten zinc bath. The
drying process shall be such that the article shall not attain a temperature
at which the flux shall get decomposed. The article thus dried shall be
galvanized before the flux coating picks up moisture from the atmosphere
or the flux layer gets damaged or removed from the surface. The drying
procedure, time duration, temperature limits, time lag between fluxing,
drying, galvanizing etc. shall form part of plant standard to be formulated
and submitted to employer along with Quality Assurance Program.
(vi) Quality of Zinc: Any one or combination of the grades of zinc specified in IS
209 or IS 13229/ Prime Western (PW grade) (Zn 98.65%) or other
comparable international standard shall be used for galvanizing. The
contractor shall declare the grade(s) of zinc proposed to be used by them
for galvanizing. The molten metal in the zinc bath shall contain minimum
98.5 % zinc by mass. It shall be periodically measured and recorded. Zinc
aluminum alloy shall be added as per IS 2629.
(viii) Post Treatment: The article shall be quenched in water. The quench water
is to be changed/ drained periodically to prevent corrosive salts from
accumulating in it. If water quenching is not done then necessary cooling
arrangements should be made. The galvanized articles shall be dipped in
chromating solution containing sodium dichromate and sulphuric acid or
chromic acid base additive at a predetermined concentration and kept at
room temperature to retard white rust attack. The temperature of the
chromate solution shall not exceed 650 C. The articles shall not be stacked
immediately after quenching and dichromating. It shall be ensured that the
articles are dry before any further handling operation.
(ix) Storing, Packing and Handling: In order to prevent white rust formation
sufficient care should be exercised while storing handling and transporting
galvanized products. The articles shall be stored in an adequately
ventilated area. The articles shall be stored with spacers in between them
and kept at an inclination to facilitate easy drainage of any water collected
on the articles. Similar care is to be taken while transporting and storing
the articles at site.
The Contractor shall prepare a detailed galvanizing procedure including Flow Chart
with control parameters and all plant standards as required above and submit to
POWERGRID for approval as part of Quality Assurance Plan.
1.6.2 Fasteners
For fasteners, the galvanizing shall conform to IS 1367 (Part-13). The galvanizing
shall be done with centrifuging arrangement after all mechanical operations are
completed. The nuts, may however be tapped (threaded) or rerun after
galvanizing and the threads oiled. The threads of bolts & nuts shall have a neat fit
and shall be such that they can be turned with finger throughout the length of the
threads of bolts and they shall be capable of developing full strength of bolts.
Spring washers shall be electro galvanized as per Grade-IV of IS 1573.
1.7 Earthing
Each tower shall be earthed. The tower footing resistance shall not exceed 10
ohms. The Contractor shall measure the tower footing resistance (TFR) of each
tower during dry weather after it has been erected and before the stringing of the
earth wire. Pipe type earthing and counter poise type earthing shall be done as
required in accordance with the following standards:
IS 3043 Code of practice for Earthing
IS 5613 Code of practice for Design, Installation and maintenance
(Part-II/Section-2) of overhead power lines
1.7.1 The drawings for pipe & counterpoise type earthing are enclosed with these
specifications.
1.7.2 For pipe type earthing, length of flat indicated in the Section Drawing is indicative
only and actual length shall vary depending on site requirement (to avoid fouling
of pipe type earthing with foundation base slab). The payment for the pipe type
earthing shall be as per the unit rates in the BPS irrespective of the length of flat
1.7.3 For counterpoise type earthing, the earthing will vary depending on soil resistivity.
For soil resistivity less than 1500 ohms-meter, earthing shall be established by
providing 4 lengths of 30m counterpoise wire. Otherwise, for soil resistivity
greater than 1500 ohms meter earthing shall be established by providing 4 length
of 70m counterpoise wire. The contractor shall also measure tower footing
impedance using high frequency Tower footing impedance measurement kit, in
addition to Tower footing resistance (TFR). The value of Tower footing resistance
as well as tower footing impedance shall not exceed 10 Ohms.
1.7.4 The provisional quantities for pipe type earthing and counterpoise earthing are
indicated in the BPS. The bidders are required to quote unit rates for the same in
appropriate schedule of BPS. The quoted price shall include fabrication, supply
and installation of earthing material including supply of coke, salt etc. In case of
counterpoise type earthing, the unit rates shall correspond to 120/280 meters of
counterpoise wire per tower.
1.7.5 Chemical pipe/ counter poise type earthing shall be provided in some locations
as decided by Site In charge, where due to high resistivity tower footing
resistance/ impedance below 10 ohms is not achieved with normal pipe/ counter
poise type earthing. The provisional quantities for chemical pipe type earthing
and counterpoise earthing are indicated in the BPS. For chemical pipe/ counter
poise type earthing, ground enhancement material/ back fill/ grounding
compound shall be used. The material should generally conform to IEC 62561
(Part-7). The material should be permanent and maintenance free. It should not
dissolve or decompose or otherwise pollute the soil or local water table &
environment and should not depend on the continuous presence of water or
moisture in the surrounding to maintain its conductivity. The material of the
earthing enhancing compound in its set form should have a resistivity of less than
0.12 ohm-m (as per IEEE 80-2000, Clause No. 14.5(d)). It should have hygroscopic
properties and should not cause burns, irritation to eyes, skin etc. Test report for
the following test on earthing enhancement compound (conducted at accredited
SECTION-IV C (VOLUME-II), Rev 9 (Jan’2025) Page 22 of 48
STANDARD SPECIFICATION OF TRANSMISSON LINE
(SECTION-TOWER: MATERIALS, FABRICATION, ERECTION
& STRINGING)
laboratory as per IEC 62561 (Part-7) shall be submitted by the contractor to the
site in charge.
• Resistivity test using soil box
• Leaching test
• Sulfur determination
• Corrosion test
1.7.6 Earthing for River Crossing Towers /Pile foundation
Galvanised earthing strip of flat 50x6 mm is to be provided in two legs of tower
for each location with proper arrangement of connecting these strips by 16 mm
bolts shall be provided in the stubs. The Earthing strip from the tower leg may be
connected to the MS liner through the pile cap (an indicative drawing is enclosed
at drawing section). In case the length of the liner embedded in the ground/ river
bed is less than 3m or pile without liner the earthing strip shall be extended along
the pile & embedded in the soil upto min. 3m depth from the present minimum
RL. After execution of the earthing tower footing resistance/impedance is to be
measured and should be maintained below 10 Ohms by suitable measures. In case
due to specific soil conditions required tower footing resistance/ impedance
below 10 Ohms is not achieved, then additional separate earthing (pipe/
counterpoise type) may be provided. Only bolted connections are allowed for
connecting this strip to achieve desired length. Contractor shall submit the
detailed drawing for approval of Employer before installations.
Note: During O&M stage, in case it is observed that MS liner/ strip embedded in
the ground/ river bed is exposed due to scouring etc. and length of embedment
of liner/strip is less than 3m. Earthing strip may be extended in the ground/ river
bed upto 3m from the other end of the liner/ strip by POWERGRID.
1.7.7 In case of location where foundation is classified as hard rock and laying of
counter poise earthing at required depth of 1 m below the ground level is not
feasible, the earthing shall be provided at reduced depth as per enclosed drawing
of “counter poise earthing in hard rock strata. For the payment of hard rock
earthing, the unit rate under the contract for chemical counter poise earthing
shall be applicable.
1.7.9 Additional Rod type earthing shall be provided in one of the foundation pit
(diagonally opposite to pipe type earthing) of all the transmission line towers in
normal soil (i.e. Dry, Wet cultivated, Wet, PS, FS & Black Cotton soil) in addition
to pipe type earthing. This additional earthing MS Rod of 40 mm dia & 3.0 M
length shall be driven after excavation of foundation pit and connected to stub
cleat. The indicative drawing of Rod type earthing is enclosed in the section of
drawing.
1.8 Standards
1.8.1 The design, manufacturing, fabrication, galvanising, testing, erection procedure
and materials used for manufacture and erection of towers, design and
construction of foundations shall conform to the following Indian Standards (IS)/
International Standards which shall mean latest revisions, with amendments/
changes adopted and published, unless specifically stated otherwise in the
Specification. In the event of supply of material conforming to Standards other
than specified, the Bidder shall confirm in his bid that these Standards are
equivalent to those specified. In case of award, salient features of comparison
between the Standards proposed by the Bidder and those specified in this
document will be provided by the Contractor to establish their equivalence.
1.8.2 The material and services covered under the:se specifications shall be performed
as per requirements of the relevant latest standard code referred hereinafter
against each set of equipment and services
b) The acceptance of any part of items shall in no way relieve the Contractor
of any part of his responsibility for meeting all the requirements of the
Specification.
2.1.2 The Employer or his representative shall have free access at all reasonable times
to those parts of the Contractor’s works which are concerned with the
fabrication of the Employer’s material for satisfying himself that the fabrication
is being done in accordance with the provisions of the Specification.
2.1.3 Unless specified otherwise, inspection shall be made at the place of manufacture
prior to dispatch and shall be concluded so as not to interfere unnecessarily with
the operation of the work.
2.1.4 Should any member of the structure be found not to comply with the supplied
design, it shall be liable to rejection. No member once rejected shall be
resubmitted for inspection, except in cases where the Purchaser or his
authorized representative considers that the defects can be rectified.
2.1.5 Defect which may appear during fabrication shall be made good with the
consent of the Employer according to the procedure proposed by the Contractor
and its approval.
2.1.6 All gauges and templates necessary to satisfy the Employer shall be supplied by
the Contractor.
2.1.7 The specified grade and quality of steel shall be used by the Contractor. To
ascertain the quality of steel used, the inspector may at his discretion get the
material tested at an approved laboratory.
3.0 Tower Erection, Stringing and Installation of Line Materials
3.1 General
3.1.1 The scope of erection work shall include the cost of all labour, tools and plant such
as sagging bridges/ working platform, power operated winch machines, cranes of
suitable capacity and height (wherever feasible), tension stringing equipment,
mechanized rope way wherever required for hilly areas for transportation of
materials and all other incidental expenses in connection with erection and
stringing work. The stringing equipment shall be of sufficient capacity to string the
bundle conductors of specified size. Use of Tractor for tower erection & final
sagging shall not be permitted.
Use of helicopter for faster erection of transmission line, particularly in difficult
and inaccessible terrain, may be considered subject to the required clearance
from Director General of Civil Aviation (DGCA) / any other competent authority.
3.1.2 The Contractor shall be responsible for transportation to site of all the materials
to be supplied by the Contractor as well as proper storage and preservation of the
same at his own cost, till such time the erected line is taken over by the Employer.
Similarly, the Contractor shall be responsible for transportation, proper storage,
safe custody, and loss or damage of all Employer’s supplied items for
incorporation in the lines and shall maintain and render proper account of all such
materials at all times. The Contractor shall reimburse the cost of any of the
materials lost or damaged during storage and erection over and above specified
and permitted in Clause 3.13.2 of this section.
3.1.3 Contractor shall set up required number of stores along the line and the exact
location of such stores shall be discussed and agreed upon with the Employer.
Employer during the kick off meeting at site supplied items shall be dispatched to
the stores set up by the Contractor.
3.1.4 Payment for stringing shall be done on the basis of per kilometer and irrespective
of number of tension/ suspension towers. However, stringing for river crossing
spans with special towers (Anchor to Anchor) have been given separately in the
BPS. The units of measurement for tower erection and other line materials, like,
earth wire, Hardware fittings and Accessories for conductor & earth wire are
indicated in the BPS.
3.1.5 While handing over the Employer supplied OPGW drums, the testing (fibre loss
and length measurement using OTDR) of OPGW in each drum shall be carried out
by Contractor in presence of OPGW supplier and/or Employer representatives.
3.1.6 After installation of OPGW, the testing of each section shall be carried out by
Contractor in presence of Employer representatives. In case of any damage / high
loss in the fiber, the total length of that particular section/ portion of OPGW shall
be replaced by the contractor and in such case, the de-stringing & re-stringing
shall be carried out by the contractor without any extra cost to Employer and cost
of additional OPGW cable, hardware fittings and joint box, if any, for replacement
of damaged OPGW etc. shall be recovered from the contractor. However,
introduction of additional joints in the links due to replacement of OPGW in
damaged portion shall be allowed subject to meeting the optical link budget.
3.1.7 In case FO Cabling (OPGW, Approach cable etc.) installation is covered under the
scope of package, Site Acceptance Testing (SAT) for FO Cabling shall be carried
out by contractor as per Annexure-II.
3.1.8 For crossing of 33kV/11kV/LT lines during stringing, shut down shall be obtained
by Employer. However, contractor shall be required to arrange bypass
arrangement for such lines with suitable LT/HT power cables whenever shutdown
cannot be arranged during stringing.
The bypassing work shall be executed with suitable 33kV/11kV/LT cables,
following all electrical guidelines and proper safety measures in co-ordination
with concern DISCOM/agency/authority. However, the healthiness of cables shall
be ensured by the contractor before installation at each crossing. The
33kV/11kV/LT line shall be restored after the completion of stringing work, with
confirmation from Employer. The work shall be carried out as per the direction of
the Engineer-in-Charge.
The payment of bypass arrangement shall be inclusive of suitable cables and all
necessary items/arrangements/works required for successful bypassing of
existing 33kV/11kV/LT lines that includes de-stringing of existing 33kV/11kV/LT
conductors and their restoration after completion of stringing. The provisional
SECTION-IV C (VOLUME-II), Rev 9 (Jan’2025) Page 29 of 48
STANDARD SPECIFICATION OF TRANSMISSON LINE
(SECTION-TOWER: MATERIALS, FABRICATION, ERECTION
& STRINGING)
quantities for bypass arrangements are indicated in the BPS. The bidders are
required to quote unit rates for the same in appropriate schedule of BPS.
The Contractor shall be entirely responsible for repair/rectification/replacement
of any damage to the existing 33kV/11kV/LT line of DISCOM/agency/authority
during the execution of the work.
g) The towers shall not be out of vertical by more than 1 in 360 before stringing
is carried out.
3.7.1 The stringing of the conductor shall be done by the control tension method. The
equipment shall be capable of maintaining a continuous tension per bundle such
that the sag for each conductor is about twenty percent greater than the sags
specified in the stringing sag table.
3.7.2 The contractor shall give complete details of the stringing methods he proposes
to follow. Prior to stringing the Contractor shall submit the stringing charts for
the conductor and earth wire showing the initial and final sags and tension for
various temperatures and spans alongwith equivalent spans in the lines for the
approval of the Employer.
3.7.3 A controlled stringing method suitable for simultaneous stringing of the sub
conductors shall be used. The conductors making up one phase bundle shall be
pulled in and paid out simultaneously. The synchronous stringing of one phase
with six bundle conductors may be carried out by using one TSE of adequate
capacity. However, two pullers of adequate capacity, towing (4+2) or (3+3)
conductors combined with two sets of tensioners may also be used. These
conductors shall be of matched length. Conductors or earth wires shall not be
allowed to hang in the stringing blocks for more than 96 hours before being pulled
to the specified sag.
Conductor creep are to be compensated by over tensioning the conductor at a
temperature of 300C for ACSR or AACSR BERSIMIS, SNOWBIRD & LAPWING /260C
for AAAC/ AL59 conductors and ACSR or AACSR MOOSE, ZEBRA, PANTHER lower
than the ambient temperature or by using the initial sag and tensions indicated in
the sag and tension chart.
3.8 Jointing
3.8.1 When approaching the end of a drum length at least three coils shall be left in
place when the stringing operations are stopped. These coils are to be removed
carefully, and if another length is required to be run out, a joint shall be made as
per the specifications.
3.8.2 Conductor splices shall not crack or otherwise be susceptible to damage in the
stringing operation. The Contractor shall use only such equipment/ methods
during conductor stringing which ensures complete compliance in this regard.
3.8.3 All the joints on the conductor and earth wire shall be of the compression type, in
accordance with the recommendations of the manufacturer, for which all
necessary tools and equipment like compressors, dies etc., shall be obtained by
the Contractor. Each part of the joint shall be cleaned by wire brush till it is free
of dust or dirt etc., and be properly greased with anti-corrosive compound. If
required and as recommended by the manufacturer, before the final compression
is carried out with the compressors.
3.9.5 Tensioning and sagging operations shall be carried out in calm whether when
rapid changes in temperature are not likely to occur.
3.10 Clipping In
3.10.1 Clipping of the conductors into position shall be done in accordance with the
manufacturer’s recommendations.
3.10.2 Jumpers at section and angle towers shall be formed to parabolic shape to ensure
maximum clearance requirements. Pilot suspension insulator strings shall be
used, as per design requirement, to restrict jumper swing to design values.
Balancing weights shall be provided with pilot insulator strings in case of triple/
quad/ hexa bundle line and for all lines with composite insulators.
3.10.3 The Jumper drop shall be maintained as per design requirement. Jumper length
calculations for different line deviation angles shall be submitted by the
Contractor to Employer/ Site-In-Charge. The jumpers shall be prepared to the
required length & compressed with jumper pads at site stores. These shall be
assembled with due care taking into consideration conductor bundle
configuration and installed correctly.
3.10.4 Fasteners in all fittings and accessories shall be secured in position. The security
clip shall be properly opened and sprung into position.
3.11 Fixing of Conductors and Earth wire/OPGW Accessories and Bird Guard
Conductor and earth wire/ OPGW accessories including spacers, spacer dampers
(for bundle conductor) and vibration dampers shall be installed by the Contractor
as per the design requirements and manufacturer’s instruction within 24 hours of
the conductor/earth wire clamping. While installing the conductor and earth wire
accessories, proper care shall be taken to ensure that the surfaces are clean and
smooth and that no damage occurs to any part of the accessories or of the
conductors. Torque wrench shall be used for fixing the Dampers/ Spacer Dampers,
Suspension Clamps etc. and torque recommended by the manufacturer of the
same shall be applied. Bird guard shall be installed on all suspension towers.
Stringing shall not be considered completed without installation of Bird guard and
all Conductors and Earth wire/ OPGW Accessories.
3.11.1 Insulated Conductor sleeve
Insulating tape and insulating sleeve shall be suitable for conductor operating
temperature of 0 to 180 degree centigrade. The insulating sleeve and insulation
tape shall be Flame, Arc, UV & Ozone Resistant.
Supply & installation charges for insulated conductor sleeve shall be payable pro-
rata basis as per unit rate of respective BPS items under the contract.
ii) Tests have been conducted not prior to 5 (five) years from the date of NOA.
iii) In case the test have been conducted earlier than the above stipulated
period or in the event of any discrepancy in the test report (i.e., any test not
applicable due to any design/manufacturing change including substitution
of components or due to non-compliance with the requirement stipulated
in the Technical Specifications), the tests shall be conducted by the Supplier
at no extra cost to the Purchaser.
3.12 Replacement
If any replacement is to be affected after stringing and tensioning or during
maintenance, leg member and bracing shall not be removed without first
reducing the tension on the tower by proper guying techniques or releasing of the
conductor. For replacement of cross arms, the conductor shall be suitably tied to
the tower at tension points or transferred to suitable roller pulleys at suspension
points.
3.13 Permitted Extra Consumption of Line materials
3.13.1 The quantity of conductor and earth wire to be incorporated in the line shall be
worked as per the following norms.
SECTION-IV C (VOLUME-II), Rev 9 (Jan’2025) Page 39 of 48
STANDARD SPECIFICATION OF TRANSMISSON LINE
(SECTION-TOWER: MATERIALS, FABRICATION, ERECTION
& STRINGING)
Annexure-I
Bird diverter assemblies shall be visually examined for general finish and good
workmanship.
2 Verification of Dimensions
The dimensions of the bird diverter assembly, including area of warning disc, reflective
area and glow-in-dark area, shall be checked against approved drawings and
requirements given in the technical specification.
The clamp of the completely assembled Bird diverters shall be subjected to a load
equal to 50% of the specified load of 500 N (using Universal Testing machine) which
shall then be increased at a steady rate to 67% of the specified load. The load shall
be held for five minutes and then removed. After removal of the load, the assembly
and its components shall not show any visual deformation and it shall be possible
to disassemble them. The clamp shall then be re-assembled and loaded to 50% of
specified load. The load shall be further increased at a steady rate to the maximum
load of 500 N and shall be held for one minute. No damage /deformation should
occur during this period. The applied load shall then be gradually increased until the
failing load is reached and the value shall be recorded.
The test shall be carried out as per IEC 61854 (Fig. 1a). The tests shall be performed
separately using earthwire, and OPGW. The earthwire/ OPGW, free of any defects or
damage, shall be tensioned to 20% of its rated tensile strength. By means of a suitable
device (see fig. 1a of IEC 61854), load shall be applied to the clamp along the axis of the
earthwire/OPGW and shall be gradually increased (not faster than 100 N/s) until it
reaches the specified minimum slip load of 250 N. The load shall be kept constant for
one minute. The movement of the clamp relative to its original position on the
earthwire/ OPGW shall be observed. The clamp should not slip more than 10 mm and
there should not be any damage / deformation of the bird diverter and the earth
wire/OPGW. Thereafter, the load shall be increased gradually in steps of 25 N and shall
be kept constant for one minute at each step. The slippage at each step shall be
recorded. The process shall be continued till the slippage is observed to be more than
10 mm from its previous position and the corresponding load shall be recorded.
4 Vibration Test
The tests shall be conducted in a laboratory set up with a minimum effective span length
of 30 m for earthwire and OPGW separately. The earthwire/ OPGW shall be tensioned
at 25% of its Ultimate Tensile Strength (UTS). Constant tension shall be maintained
within the span by means of lever arm arrangement. The span shall be equipped with
vibration inducing equipment suitable for producing steady standing vibration. The
inducing equipment shall have facilities for stepless speed control as well as stepless
amplitude arrangement. Equipment shall be able to measure the frequency, cumulative
number of cycles and amplitude of vibration at any point along the span.
Four number of Bird Diverters shall be clamped to the earthwire/ OPGW in and around
the middle of the test span. These bird diverters shall be free to vibrate and shall not
be re-torqued or adjusted between the tests. The frequency of vibration is so chosen
as to get an odd number of loops. The shaker shall be positioned at least two loops
away from the test specimens to allow free movement of the earthwire/ OPGW close
to the test specimens. The earthwire/ OPGW shall be connected to the shaker and
vibrated to an amplitude such that
Where Ymax being the antinode displacement (mm) and f is the test frequency (Hz).
The test frequency shall be greater than 24 Hz and the total number of cycles shall be
more than 10 million. The bird diverter shall withstand the vibration test without
slipping on the earthwre/ OPGW, loosening, damage or failure of components parts.
After the completion of test, the same bird diverter shall be subjected to mechanical
strength test (direct pull test & clamp slip test) as per the procedure given above and
the sample shall be able to withstand the tests without damage/ deformation.
The complete bird diverter assembly shall be quickly and completely immersed,
without being placed in an intermediate container, in a water bath maintained at a
temperature of 85°C and left submerged at this temperature for 15 minutes. The
sample then shall be withdrawn and quickly & completely immersed, without being
placed in an intermediate container, in the cold water bath maintained at a
temperature of -15°C where it shall remain for 15 minutes. The sample shall be
subjected to 10 such cycles.
The time taken to transfer from either bath to the other shall be as short as possible
and never exceed 30 seconds. The quantity of water in the test tanks shall be
sufficiently large for the immersion of the samples so as not to cause a temperature
variation of more than ±5°C in the water.
After completion of 10 cycles, the sample shall be examined to verify that the samples
have not deformed/ damage.
After the completion of test, the same bird diverter shall be subjected to mechanical
strength test (direct pull test & clamp slip test) as per the procedure given above and
the sample shall be able to withstand the tests without damage/ deformation.
Salt fog (at 5% salt solution) and Humidity test (at 90% Rh) as per procedure in
accordance with MIL-STD 810F (method 509.4 and Method 507.4).
After the completion of test, the same bird diverter shall be subjected to mechanical
strength test (direct pull test & clamp slip test) as per the procedure given above and
the sample shall be able to withstand the tests without damage/ deformation.
7 Ageing Test
Solar radiation test & sand and dust test as per procedure in accordance with MIL-
STD 810F (Method 505.4 proc II and 510.4 proc I).
After the completion of test, the same bird diverter shall be subjected to mechanical
strength test (direct pull test & clamp slip test) as per the procedure given above and
the sample shall be able to withstand the tests without damage/ deformation.
Annexure-II
Prior to installation, every spooled fibre optic cable segment shall be tested for
compliance with the Pre-shipment data previously received from the manufacturer.
This requirement will preclude the installation of out of specification cable segments
that may have been damaged during shipment.
SAT shall be carried out link by link from FODP to FODP. SAT may be performed in
parts in case of long links.
Sag and tension of OPGW shall generally be as per approved sag-tension chart and
during installation, sag and tension of OPGW shall be documented. Upon completion
of a continuous cable path, all fibres within the cable path shall be demonstrated for
acceptance of the cable path. Fibre Optic cable site testing minimum requirements
are provided in Table 1(a) through 1 (c) below:
Table 1(a)
Fibre Optic Cable Pre-Installation Testing
Sl. No. Description
1 Physical Inspection of the cable assembly for damage
2 Optical fibre continuity and fibre attenuation with OTDR at 1550
nm
3 Fibre Optic Cable length measurement using OTDR
Table 1(b)
Fibre Optic Cable Splicing Testing
Sl. No. Description
1 Per splice bi-directional average attenuation with OTDR
2 Physical inspection of splice box/enclosure for proper fibre /
cable routing techniques
3 Physical inspection of sealing techniques, weather proofing, etc
Table 1(c)
Fibre Optic Cable Commissioning Testing
Sl. No. Description
1 End to End (FODP to FODP) bi-directional average attenuation of
each fibre at 1310 nm and 1550 nm by OTDR
2 End to End (FODP to FODP) bi-directional average attenuation of
each fibre at 1310 nm and 1550 nm by Power meter
3 Bi-directional average splice loss by OTDR of each splice as well as
for all splices in the link (including at FODP also)
4 Proper termination and labelling of fibres & fibre optic cables at
FODP as per approved labelling plan