Assignment 2

The document outlines an assignment for a software project management course, consisting of three questions related to project activities, including drawing diagrams, calculating project completion times, and determining critical paths. It requires students to create Activity on Node and Activity on Arrow diagrams, as well as a PERT network for a small project. Additionally, it asks for an analysis of project completion probabilities under a specified deadline.
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
0 views

Assignment 2

The document outlines an assignment for a software project management course, consisting of three questions related to project activities, including drawing diagrams, calculating project completion times, and determining critical paths. It requires students to create Activity on Node and Activity on Arrow diagrams, as well as a PERT network for a small project. Additionally, it asks for an analysis of project completion probabilities under a specified deadline.
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Software project management

CS Department
Assignment 2

Question 1:

Activity Completion time Immediate predecessor


(days) activities
A 5 -
B 7 -
C 6 -
D 3 A
E 4 B,C
F 2 C
G 6 A,D
H 5 E,F

 Draw the Activity on node diagram.


 Draw the Activity on arrow diagram for the same.
 Calculate the minimum overall project completion time and identify which
activities are critical in both the diagrams.

Question 2:

The following details are available regarding a project:

Determine the critical path, the critical activities and the project completion time.
Question 3:

A small project consisting of eight activities has the following characteristics:

(i) Draw the PERT network for the project.

(ii) Prepare the activity schedule for the project.

(iii) Determine the critical path.

(iv) If a 30- week deadline is imposed, what is the probability that the project will
be finished within the time limit?