PRESENTATION REPLANTING IN PEAT - THE PROCESS FLOW (21.07.2023)-1 (1)_compressed
PRESENTATION REPLANTING IN PEAT - THE PROCESS FLOW (21.07.2023)-1 (1)_compressed
3
2.0 PROCESS FLOW OF A REPLANTING WORK
4
PROCESS FLOW OF REPLANTING
3. Construction 5. New
1. Planning for of Field Drain 4. Construction Collection
2. Pre-Lining
replanting and New Coll of CECT Road
Drain Construction
5
3.0 SITE MEETING WITH CONTRACTOR, OPERATORS AND SUBORDINATES
Deliberate on:-
• Safety
• Work Specification
• Work Schedule
6
3.0 PERMIT TO WORK (PTW)
PTW
• Issue before starting work
• Should be issued weekly
• All operators report at AP post daily
7
3.0 HIRARC
HIRARC
• To update latest HIRARC for
replanting project
8
3.0 STANDARD OPERATING PROCEDURE (SOP)
SOP
• To update and display SOP at office
and workplace
9
3.0 MAINTAINING RECORDS
10
3.0 REPLANTING OWNERSHIP BOARD
11
4.0 REPLANTING DESIGN
12
4.0 REPLANTING DESIGN IN PEAT
13
4.0 REPLANTING DESIGN - BASIC REPLANTING DESIGN IN PEAT
The estate to maintain the current road system in the replanting design to save road
construction cost 14
4.0 REPLANTING DESIGN - SHORTENING CARRY DISTANCE IN PEAT
15
5.0 PRE-LINING
16
5.0 PRE-LINING
To ensure accurate lining for the CECT, drains and the planting rows. Pre-lining must be
carried out prior to felling by a proficient person such that the directions and the
distances are determined correctly as required by the management.
Pre-lined rows to be marked with pegs of at least 1.8 m @ 6 feet’s high at designated
CECT & New Field Drain intervals.
Pre-lining pegs it’s an option to use either bamboo/fronds/used pvc pipe and to paint
with different color or tide with color plastic bags (BLUE for CECT & RED for New Field
Drain)
The Pre-lining later will use as ‘Rajah Line’ for planting point.
17
5.0 PRE-LINING
Pre-lining pegs it’s an option to use 1.8m @ 6 feet's bamboo/used pvc pipe and to paint with different colour or
tide with colour plastic bags ( BLUE for CECT & RED for New Field Drain)
18
5.0 PRE-LINING
19
5.0 PRE-LINING
20
6.0 CONSTRUCTION OF CLOSE
ENDED CONSERVATION TRENCH
(CECT)
21
6.0 CONSTRUCTION OF CLOSE ENDED CONSERVATION TRENCH (CECT)
The CECT are to be constructed with excavator beginning 4.75 m from the collection
road in the front and ends 7.75 m before the collection drain. This will allow for future
mechanical path access.
The spoil from the CECT must be placed in between the old palm tree to be use later for
close the deboling pits.
The size of the close-ended conservation trenches (CECT) not less than 2.4 m wide at the
top, 1.8 m wide at the bottom and 2.4 m deep. The interval is at every 4th palm row or
2.4meter
22
6.0 CONSTRUCTION OF CLOSE ENDED CONSERVATION TRENCH (CECT)
Overflow
drain
2.4meter
23
6.0 CONSTRUCTION OF CLOSE ENDED CONSERVATION TRENCH (CECT)
CECT
(2.4m x 1.8m x 2.4m)
Stacks of chipped OP trunk
Field Drain 2.4meter
(1.0m x 0.75m x 0.30m)
0.3 m camber
3.7m 3.7m
14.8m
24
6.0 CONSTRUCTION OF CLOSE ENDED CONSERVATION TRENCH (CECT)
CECT
(2.4m x 2.4m x 2.4m)
2.4meter Stacks of chipped OP trunk
CECT
New Field Drain
(2.4m x 1.8m x 2.4m)
1.0m x 0.75m x 0.3m Stacks of chipped OP trunk
25
6.0 CONSTRUCTION OF CLOSE ENDED CONSERVATION TRENCH
(CECT)
26
6.0 CONSTRUCTION OF CLOSE ENDED CONSERVATION TRENCH
(CECT)
2.4 meter
2.4 meter
1.8 meter
27
6.0 CONSTRUCTION OF CLOSE ENDED CONSERVATION TRENCH
(CECT)
0.45 meter
0.6 meter
0.6 meter
End of CECT Path/Overflow drain with depth of The dimension of end of CECT/overflow drain
0.6 meter and width of 0.45 meter at the end of at the end of CECT.
CECT to drain out excess water to collection
drain and avoid water stagnant at the planting
point.
28
7.0 FELLING, SHREDDING, AND
STACKING
29
7.0 FELLING, SHREDDING, AND STACKING
Felling Shredding
Harvesting should continue prior to felling to Excavate the entire palm bole together with
minimize VOPs. all its roots. All trees either standing or
Prior to felling, all fully developed bunches collapsed shall be shredded and all stumps
with red color shall be recovered. must be uprooted.
30
7.0 FELLING, SHREDDING, AND STACKING
Chipped trunks, boles and root-masses All chipped trunks, boles and root-masses
should be stacked and must be placed into must be compressed using excavator.
the close-ended conservation trench (CECT).
31
7.0 FELLING, SHREDDING, AND STACKING
Thickness:
<10 cm @
4 inches
32
8.0 DEBOLING & CLOSING
DEBOLING
33
8.0 DEBOLES AND CLOSING DEBOLES
2 meter
2.4mer
1.2 meter
1.2meter
2 meter
To do 100% Ganoderma pits for standing palms and vacant old point.
To ensure that remains of bole tissue and the major part of root system are fully remove and
expose to sunlight
The debris (root mass/bole) should be shredded and spread out at the top of chips trunk in
the CECT.
The deboling pits needs to close minimum after 14 days using soil from CECT which kept near
to palm base during construction of CECT. 34
9.0 DESILTING EXISTING DRAIN
(COLLECTION DRAIN)
35
9.0 DESILTING EXISTING DRAIN (COLLECTION DRAIN)
2.0 meter
1.5 meter
0.9 meter
36
10.0 DRAIN CONSTRUCTION
(NEW FIELD DRAIN)
37
10.0 DRAIN CONSTRUCTION (NEW FIELD DRAIN)
The work should involve the construction of new drains determined by the management.
Construction of new drains shall be done after lining is completed.
All spoils excavated must be levelled to the surrounding ground at least 1 m away from the drain
edges.
The Estate Manager shall indicate the alignment and the type of drains to be constructed. General
cross sectioned dimensions of main, collection and field drains are as follows:
38
10.0 DRAIN CONSTRUCTION (NEW FIELD DRAIN)
Construction new field drain in progress After construction new field drain
0.9 meter
39
10.0 DRAIN CONSTRUCTION (NEW FIELD DRAIN)
1.0 meter
0.75 meter
0.3 meter
40
11.0 REALIGN OF ROAD
41
11.0 WIDENING & REALIGN OF ROAD
The standard widths of the roads both for flat/undulating areas to be constructed
are:
Existing roads to maintain and further improved to minimize the cost of replanting
and new roads construction. All roads must be in a grid system.
To realign and widen the existing road if required.
To strengthen the existing road with road resurfacing and stoning for all-weather
roads condition.
NO PLANTING POINT LOSS for the road to adhere.
The existing road is in the 4.25m inter-palm spacing row.
Lay-by
• Main Road: Based on estate requirement.
• Collection Road: Every 250 meters interval.
42
11.0 WIDENING & REALIGN OF ROAD
To realign planting
point 2.00 meters
from road edge to PLANTING
give access for DISTANCE
(8.5m)
road construction
and to avoid
planting point loss
Existing/ new
Collection Road
43
11.0 REALIGN OF ROAD
44
12.0 LAND FORMING
45
12.0 LAND FORMING AT STRAIGHT PLANTING AREAS
0.6 m
Land Forming
All spoils excavated must be levelled to the surrounding ground at least 1 meter away
from the drain edges.
The land forming must not be less than 0.60 m @ 2 feet above the original peat level.
46
13.0 PEAT COMPACTION
47
13.0 PEAT COMPACTION
2.4mer
0.45 m
8 runs compaction from field drain to CECT, it must be complied with the required depth.
Compacted planting rows shall not less than 0.45 m above original peat level.
48
13.0 PEAT COMPACTION
EX200 (
EXCAVATOR COMPACTION PASSES
TRACK SIZE )
3.0 m 1m 1m
X X X X
F C F
I E I
X X X X
E C E
1.4 m L 1.2 meter T L
D X X D
X X
D
D R D
R A R
A X X I X X A
I N I
N N
X X X X
8 runs compaction from field drain to CECT, it must be complied with the required depth to get 0.45 m
of cambering.
49
14.0 LINING FOR PLANTING
50
14.0 LINING FOR PLANTING
Proper lining and planting are essential to ensure efficient field operations throughout the
planting cycle.
Objective:
I. To provide uniform palm stands and spacing.
II. To provide palm equal access to nutrients, water and sunlight.
III. To achieve optimum stands per hectare (160 palms per hectare).
Install the first planting baseline(‘Rajah’ baseline following from the Pre-Lining point) right-
angle to the main block baseline. The former should be parallel to the collection road line.
Mark out 7.4 m inter-row spacing along the ‘Rajah’ baseline and 8.5 m along the planting
row.
Planting points are marked with colored bamboo sticks and checked by sighting along
the new palm row line to ensure the areas are properly aligned.
51
14.0 LINING FOR PLANTING
EQUILATERAL TRIANGLE
PLANTING (8.5m)
To realign
planting point
2.00 meters from
road edge to give
PLANTING
access for road DISTANCE
construction and (8.5m)
to avoid planting
point loss
Collection Road
52
14.0 LINING FOR PLANTING
53
14.0 LINING FOR PLANTING
Coloured
bamboo stick
54
14.0 LINING FOR PLANTING
Planting Inter-row:
distance: 7.4 meter
8.5 meter
55
15.0 ESTABLISHMENT OF MUCUNA
BRACTEATA
56
15.0 MUCUNA BRACTEATA ESTABLISHMENT
Importance of Cover Crop Establishment
57
15.0 MUCUNA BRACTEATA ESTABLISHMENT
• MB planted
immediately 15ft 15ft
palm at
cambered path.
58
15.0 MUCUNA BRACTEATA ESTABLISHMENT
61
16.0 HOLING (USING HAD PEAT PUNCHER)
62
16.0 HOLING (USING HAD PEAT PUNCHER)
63
16.0 HOLING
0.33 m
64
16.0 HOLING
65
17.0 PLANTING IN PEAT AREA
66
17.0 PLANTING IN PEAT AREA
Critical Area to Observe
• Loading at nursery.
– Unloading at field
– Distribution into field
– Unloading at planting point
• Wet the seedlings prior to dispatch.
• Suitable glove for handlers.
• Sign of poor handling - many pinnae
is broken.
• Open the polybag just before /
planting. Correct Handling Suitable Gloves
67
17.0 PLANTING IN PEAT AREA
Planting hole before planting the seedling Fertilizer application prior planting
Evenly broadcasted in the planting holes
1. RP – 250 gm
Stamping stick
Place the oil palm seedling into the planting Soil filling and consolidate firmly with a stamping
hole and make sure the seedling planted in stick to ensure no air pockets in the planting
upright position and firmly placed. holes. Empty polybags to be placed in
between of the lowest frond for inspection
purpose.
71
17.0 PLANTING ON PEAT AREA
72
18.0 MULCHING AND 1-YEAR 1-OFF
FERTILIZER APPLICATION
73
18.0 MULCHING AND 1-YEAR 1-OFF FERTILIZER APPLICATION
Applied for the whole 1st-year fertilizer program 1 month after planting.
The application is 0.30 m from the palm base with pre-pack and pre-
weighing fertilizer mixed in a plastic bag prior to the application.
The fertilizer per seedling as per recommendation is 3.90 Kg. The detail of
the fertilizer is as per below:
I. 3.20 kg of Compound Blue.
2.4mer
75
18.0 PLASTIC MULCHING AND 1-YEAR 1-OFF FERTILIZER APPLICATION
1. Using plastic mulching only with One off one-year fertilizer application (an alternative if plastic
mulch is available and non-existence of EFB).
76
18.0 EFB MULCHING
77
THANK YOU