010
010
10 m
L4 L2 L4
D
B
S4
S2
TOP REBARS
Span (L)
S4
BOTTOM REBARS
SEE SCHEDULE
L4 L2 L4
TYPICALSLAB DETAIL
SCHEDULE OF SLAB
SLAB NO. LOCATION THICKNESS (mm) TOP RBARS BOTTOM REBARS
SHORT SPAN 12 mm ø @ 300 mm ON CENTER 12 mm ø @ 300 mm ON CENTER
S1 GROUND FLOOR 100 LONG SPAN 12 mm ø @ 250 mm ON CENTER 12 mm ø @ 300 mm ON CENTER
SHORT SPAN 12 mm ø @ 300 mm ON CENTER 12 mm ø @ 300 mm ON CENTER
S2 SECOND FLOOR 150 LONG SPAN 12 mm ø @ 250 mm ON CENTER 12 mm ø @ 300 mm ON CENTER
SHORT SPAN 12 mm ø @ 300 mm ON CENTER 12 mm ø @ 300 mm ON CENTER
S3 GARAGE & CR 50 LONG SPAN 12 mm ø @ 250 mm ON CENTER 12 mm ø @ 300 mm ON CENTER
JRMSU-COE SUBMITTED BY: YEAR: III SEAL: PROJECT: SUBMITTED TO: SHEET CONTENT: SET NO.: SHEET NO.:
BLOCK: B
ID NO.:
22-A-01216
PROPOSED 2-STOREY RESIDENTIAL BUILDING 10
DATE: 04/25/25 BEAM & SLAB DETAILS A
ENGR. JOHN PAUL BATOCAEL
NIÑA MICHELE P. COQUILLA A
STUDENT PLATE NO: LOCATION: INSTRUCTOR