Assignment-3
Assignment-3
1. a. A radial distribution network is shown in figure Q1. Assume that all the failures in feeder
sections and the distributors are short circuits which will cause the main breaker at the
supply point to operate. The isolation and switching are 0.75 hours, and the failure
probability of fuses is 0.15
Determine the reliability parameters; Failure rate (⋋), Outage time (r), Unavailability (U)
at load points A and B for the following two cases.
• Case-1: An isolator is installed at R and distributors are solidly linked at point P&Q
• Case-2: An isolator is installed at R and distributors are connected through fuses at P&Q
• Discuss why the values obtained in case-1 is different from case-2
[16 Marks]
b. Evaluate the following customer and load oriented reliability indices for the Case-2
• System Average Interruption Index (SAIFI) [2 Marks]
• System Average Interruption Duration Index (SAIDI) [2 Marks]
• Customer Average Interruption Index (CAIDI) [2 Marks]
• Average Energy Not Supplied (AENS) [3 Marks]
SAIFI = (Total number of customer interruptions/Total number of customers served)
SAIDI = (Sum of customer interruption durations/Total number of customers)
CAIDI = (Sum of customer interruption durations/Total number of customer interruptions)
AENS = (Total energy not supplied/Total number of customers served)
Isolator (N/C)
2 km 3 km
Supply 0.1 f/km-yr r=4 s=0.75 0.1 f/km-yr r=4 s=0.75
Feeder section 1 R Feeder section 2
Main P Q
Breaker
Fuse
Lateral Distributor-2
r=2
Lateral Distributor-1
r=2
0.1 f/km-yr
3 km
0.1 f/km-yr
4 km
Load B
Figure Q1 Load A
Data pertaining to the above radial circuit are:
Feeder-1 failure rate = 0.1 f/km-yr Feeder-2 failure rate = 0.1 f/km-yr
Feeder-1 average repair time = 4 h Feeder-2 average repair time = 4 h
Feeder-1 section length = 2 km Feeder-2 section length = 3 km
Lateral distributor-1 failure rate = 0.1 f/km-yr Lateral distributor-2 failure rate = 0.1 f/km-yr
Average repair time = 2 h Average repair time = 2 h
2021/2022-Assignment-3 Page [1] of [6] Lalith A. Samaliarachchi
Lateral distributor-1 length = 4 km Lateral distributor-2 length = 3 km
Data for load point A and B
Load point Number of customers Average load/customer (W)
A 500 3000
B 700 4000
2. Consider the typical substation configurations Figure Q2.1 & Figure Q2.2 shown below, and
the reliability data given in table Q2 for each component:
2 2
T/F-1 3 L/T bus T/F-1 3 L/T bus
1 1
L1 L1
CB 7 CB 7
T/F-2 T/F-2
4 4
L2 L2
Case (1) L/T bus tie breaker #7 is normally closed [10 Marks]
Case (2) L/T bus tie breaker #7 is normally open [10 Marks]
b. If the average load connected at bus #3 and #6 are 50 MW each respectively, calculate the
total energy not served for each configuration. [5 Marks]
Area A Area B
Tie line
PA PB
Load at B
𝐶(𝑃𝐴 ) = 70 + 𝑃𝐴 + 0.001𝑃𝐴2 €/hr
a. Determine the optimal levels of generation in areas A and B for each of the peak and off-
peak period neglecting the constraints imposed by the transmission link. Calculate the
marginal cost of production in each period. [6 Marks]
Area A Area B
900 MW
PA PB
Load at B
b. Modify the levels of generation computed in (a), taking into the consideration of existing
transmission link capacity. What are the marginal cost prices in areas A and B in each
period? [6 Marks]
c. Assuming that the duration of peak load period is 2500 hr/year, calculate the generation
cost in each period for generation levels computes in (b). What are the total annual
generation costs? [6 Marks]
d. The transmission company is considering doubling the transmission capacity between the
two areas in order to reduce the generation cost. Assuming that the annuitized investment
cost of the reinforcement is 1,000,000 €/year, determine whether the proposed investment
can be justified. [7 Marks]
Hourly irradiance and temperature variation observed on a domestic roof top are graphically
shown in figure Q4a and Q4b, respectively.
e. What would be the hourly maximum possible power and total energy that can be harnessed
from a photovoltaic (PV) panel of which the specifications are given in table Q4a?
[7 Marks]
Assume that:
800 30
Irradiance (W/m2)
Temperature (0C)
600 25
400 20
200 15
10-11
10-11
13-14
13-14
7-8
7-8
8-9
8-9
9-10
9-10
11-12
12-13
14-15
15-16
16-17
11-12
12-13
14-15
15-16
16-17
Time Time
1000 35
800 30
Irradiance (W/m2)
Temperature
600 25
400 (0C) 20
200 15
7-8
7-8
10-11
10-11
8-9
8-9
13-14
13-14
9-10
9-10
11-12
12-13
14-15
15-16
16-17
11-12
12-13
14-15
15-16
16-17
Time Time
1000 35
32.5
Temperature (0C)
Irradiance (W/m2)
800 30
700
600 25
500
400 20
200 15
7-8
7-8
10-11
10-11
8-9
8-9
13-14
13-14
9-10
9-10
11-12
12-13
14-15
15-16
16-17
11-12
12-13
14-15
15-16
16-17
Time Time
compute the number of PV panels required to break-even his monthly energy consumption?
Assume that the invertor efficiency is 98%. [7 Marks]
g. Based on the following cost figures, calculate the simple payback period of the total PV net-
metering installation. You may use Table Q4b for domestic electricity tariff plan.
[7 Marks]