Lecture Notes

The lecture discusses transportation decisions in supply chain management, focusing on the shortest path model to minimize distance and cost when transporting goods from a factory to a destination. It outlines how to create a network diagram of routes and calculate distances between various check posts, emphasizing the importance of modeling to determine the optimal route. The objective is to minimize the total distance traveled while ensuring that all constraints related to material flow are satisfied.

Uploaded by

at.yh.ma1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

Lecture Notes

The lecture discusses transportation decisions in supply chain management, focusing on the shortest path model to minimize distance and cost when transporting goods from a factory to a destination. It outlines how to create a network diagram of routes and calculate distances between various check posts, emphasizing the importance of modeling to determine the optimal route. The objective is to minimize the total distance traveled while ensuring that all constraints related to material flow are satisfied.

Uploaded by

at.yh.ma1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

Modelling and Analytics for Supply Chain Management

Professor Kunal Kanti Ghosh


Vinod Gupta School of Management
Indian Institute of Technology Kharagpur
Lecture 15
Transportation Decisions: How to Take Decisions on Different Issues with Transportation?
(Contd.)

Hello, welcome to Modelling and Analytics for Supply Chain Management. We were in module
3 transportation decisions, right? And we have finished off with discussing on different types of
cost models. Some of these we have finished off. We have finished up with the total cost model;
we have finished up with having the min-max model that is we want certain quantities to be sent
to certain routes. And we then decided on the maximum flow model, for example, if you are
having a GIT system, what should we do? Now, today we will discuss on the shortest path
model.

(Refer Slide Time: 0:56)

Shortest path model means I have a factory here, I have a factory here and, sorry, I have a
supplier source here and my factory is here. Now, there is no direct road from S to F, there is no
direct route, rather there is a zigzag of different combinations of routes that are possible. So,
some routes will be like this, some routes will be like this. So, we have to find out the shortest
possible route from my supplier to my factory and definitely shortest possible route will mean
shortest time and shorter or lesser cost.
So, today's discussion is how to find out the shortest possible route or shortest path model. Now,
100 units, 100 units of materials are dispatched from factory and have to reach the destination
near check post 5 within the shortest possible time. So, how should we design this model? That
is what our job today is.

(Refer Slide Time: 2:08)

Now, see what is happening, here is my factory. From factory, I am drawing this the top, the top
box, this is my factory, from factory there are 2 roads that are going, 1 is check post 1 and the
other is check post 2, say factory to check post 1 or to check post 2. What is the distance from
the factory to check post 1? Distance is 20 kilometers. What is the distance from factory to check
post 2, distance is 25 kilometers.

Similarly, from check post 1 see the next, the next box from check post 1 the road takes you to
check post 2, there is another road that takes you to check post 3 and there is another road that
takes you to check post 5. So, if we can say from check Post 1, there is another road that checks
you to check post 2, another road that takes you to check post 2, there is another road that takes
you to check post 3 and there is another road that takes you to check post 5.

And then from check post 2 if you see there is another road that takes as we mentioned that there
is a road that takes you to check post 1. From check post 2 to check post 1 which I have already
drawn and there is another route that takes you to check post 4. So, in this way, you see what you
can do is you can start drawing a network diagram.

You can start drawing a diagram. And then what is the distance from factory to check post 1, 20
kilometers, you see distance from factory to check post 1 is 20, factory to check post 2 is 25. So,
these are the things that you can keep on writing down. And what is our job, from factory to
destination end point we have to find the shortest possible distance.

(Refer Slide Time: 4:14)

So, what we will do now is, this is if you map the drawing or the diagram from the previous
table, if you can draw the network diagram that we were drawing by hand here, we were drawing
by hand here, this drawing will lead you to this 1. This drawing will lead you to this 1. Factory to
check post 1, factory to check post 2, et cetera. Now, and so if you see, so what you can do, this
was my, this was my, this thing 20 units, factory to check post 2 was 25 units, check post 1 to
check post 2, check 1 to check post 2 see this arrow, this arrow 2 units check post 1 to check post
3, this arrow is 3 units and check post 1 to check post 5 this arrow is 10 units. Clear.

So, then you see check post 2 to check post 1, see check post 2 to check post 1, what are these
20, 10, 3 distances, road distance, say kilometer. From factory to check post 1 is 20 kilometers,
check post 1 to check post 5 is 10 kilometers. Now, from check post 2, if you keep on going back
to this problem from check post 2, from check post 2 to check post 1 distance is 3 kilometers,
now see check post 1 to check post 2, CP 1 to CP 2 is 2 kilometers, but CP 2 to CP 1 is 3
kilometers.

Why this discrepancy? Because there may be 1 way restrictions which will make me do a circuit.
So, that is why the distances are not same and from CP 1 to CP 5 we have done, that CP 1 and
from CP 2 there is a check post 4 it is again 6 kilometers. So, in this way you can keep on putting
the numbers. In this way you can keep on putting the numbers.

Then CP 3 to CP 1, let us see, CP 3 to CP 1 is 4 kilometers, CP 3 to CP 4 is 5, CP 3 to CP 5 is 4


kilometers and CP 4 to CP 2, this back arrow, this back arrow, 6, CP 4 to CP 3, this back arrow
is 5 and CP 4 to CP 5 is 8. So, you see all our arrows, all our road distances are now marked, all
our road distance is are now marked. So, this is the kilometers, road distances in kilometers from
1 point to other.

Remember the road distances in kilometers from 1 point from 1 point to the other. What is our
job? 100 units have to move from factory to the destination point check post 5, where my some
other unit is there, or where some manufacturing facility or wholesale go-downs or warehouses
are there. So, 100 units have to move. This is the kilometers.

So, what is my job? How to move so that my total distance traveled is the lowest. Total distance
travelled lowest means time taken is also lowest and cost is also the least. So, we do not know
which route it will take. So, x1 quantity is moving, x2 quantity is moving from here, x3, x4, x5,
x6, x7, x8, x9, x10, x11, x12, and x13. So, these are the possible quantities, these are the, this is
the quantity that can move through this route, agreed? So, this is the like the previous day this the
same type of a problem.
(Refer Slide Time: 9:09)

So, what is our objective? Our objective is to minimize the total distance traveled. Minimize the
total distance travelled, distance traveled is 20, say the first 1, take the first 1, this 20 kilometers
distance, 20 kilometers distance how much quantity is being taken, x1. 25 kilometers is the
distance from 1 check post to the other, how much quantity is being taken, x2.

So, in this way we model and the objective is to minimize this total distance that is traveled,
minimize the total distance that is traveled. What are the constraints? The constraints are x1 plus
x2 is equal 100, remember. This was my factory, right, and from factory, it was going to check
post 1 and another was going to check post 2. How much quantity and this was x1 and this was
x2.

Remember how much quantity is being dispatched from the factory? - 100 units. So, x1 plus x2
is the total movement from the factory; x1 plus x2. So, x1 plus x2 should equal to 100 units, x1
plus x2 should equal to 100 units. Now, if you remember this check post 1 from check post 1, 1
road was coming to check post 2 and another was going to check post 3 and another was going to
check post 5, from check post 1.

If you remember from check post 1, 1 road was coming to check post 2, another was going to
check post 3, another was going to check post 5. The 1 that was coming to check post 3 we have
mentioned is x3, x5, 1 that was coming to check post 2 is x3, x5 and this was x7. Now, the
products that are moving from the factory to check post 1 has to move out from check post 1, no
unit of the product will stay back at check post by 1.

Whatever is coming into check post 1 is moving out from check post 1, nothing is staying back.
So, at check post 1 what is happening, what is coming in, another 1, sorry I missed out, that is
there was another arrow that is from check post 2 there was a backend road that was there, and
we had called this as x4. So, what are the entry points to check post 1, x1 quantity from factory
or x4 quantity from check post 2, x1 quantity from factory, x4 quantity from check post 2?

So, at check post 1 how much can come in x1 plus x4. At check post 1, how much can come in?
“How much quantity can come in?” - x1 plus x4, so, x1 plus x4. “How much will have to go
out?”- x3 has to go out from check post 1 plus x5 plus x7. What is going out? - x3 quantity plus
x5 quantity plus x7 quantity, so, at check post 1 material in is equal to material out, nothing can
stay back in check post 1.

So, x1 plus x4, material in x1 plus x4 is equal to material out x3 x5 x7 is equal to x3 x5 x7. This
is your second equation, x3 x5 x7 clear, and x1 x5 and there is another 1 that is going out to
check post 3, yeah, sorry, another 1 is that is x6. So, we have taken all the moves out, moving out
on 1 side and we have made them equal to 0. So, basically it is material in is equal to material
out, material in is equal to material out. Nothing will stay back at this check post.
(Refer Slide Time: 14:01)

So, just a recap, let us go back to the previous diagram; whatever is coming in, whatever is
coming in, whatever is coming in, these are the arrows, the blue arrows are materials that are
coming in to check post 4, 3 arrows are coming in that is x1 x4 and x6 that should go out.

What is going out? - this one (x3), this one (x5) and this one (x7), so, x3 x5 and x7. So, what is
happening at check post 1, x1 plus x4 plus x6 the blue colored ones, x1 plus x4 plus x6 should
equal to rather let me place it in blue then you will not get going confused, Let me place it in
blue. So, what is coming in? x1 plus x4 plus x6. What is going out? What is going out? In red x3
x5 x7 and these should be equal because nothing can stay back at check post 1 and this applies to
all the check posts.

So, my objective is to minimize the total, my objective is to minimize the total distance moved,
subject to these conditions that nothing will stay back at the nodes. Nothing will stay back at the
notes. Agreed? This is what we wanted to say.
(Refer Slide Time: 16:01)

So, this is my, all these constraints are given here, all these constraints we have put equal to on
the right hand side just for modeling simplicity purpose, but otherwise it is x1 plus x2 plus x3 is
equal to x4 plus x5 plus x6 material in material out, material in is equal to the material out.
Remember this material in is equal to material out because we will require this in the subsequent
lecture sessions also.

(Refer Slide Time: 16:39)


So, once we solve this in LiPS, we get a value of 2700. We get a value of 2700. What is this
2700? 100 units multiplied by 27 kilometers is equal to 2700. So, what is the minimum distance
travelled? Minimum distance traveled or minimum distance possible is 27 kilometers, agreed?
So, 27 kilometers is the shortest distance from factory to my destination point.

(Refer Slide Time: 17:21)

What is the route, the route is x1 to x5 and then to x12. Remember x1 to x5 to x12, this is my
route.
(Refer Slide Time: 17:44)

Let us go back and see what this route was. What was x1, x1 was this, then x5 was this, and x12
was this, all the others are 0, we have seen 100 in these routes. So, x1 to x5 to x12. So, my route
is factory to check post 1 to check post 3 to check post 5, check post 5 this is my route. I will
write it in a fresh manner just give me this space. Factory to check post 1 to check post 3 to
check post 5, this is my shortest possible route.

So, when is this model and when is the earlier model, when this model is when you can move in
and we do not want to determine what is the maximum number of goods that can be travelled. It
is not a JIT system; this is a minimal cost or minimal time system. When there are network of
roads and the up-road may have a particular distance and the down-road may have another type
of a distance because of no entry restrictions. Now, this much is fine, there is no problem. Now,
we have another type of a question in our mind.
(Refer Slide Time: 19:35)

That is, let us say, that is, let us say we are having and we are having a situation when I have,
sorry, when I have, when I have 1 warehouse here, 1 warehouse here, 1 here, 1 here, and I have
to pick up and these warehouses have to be linked, these warehouses have to be linked.

They are linked by a, so I want to find out... So, you see, so all the roads are to be linked, all the
roads are to be linked. I want to find out, what is the minimal number of, minimal time required
to move across all these points. What is the minimal time, not the route, remember I am not
asking for, there is a basic difference between route planning and minimal time.

I am not asking that if a person starts moving from here, which route, which pattern he should
follow. What I am asking is, which route or which pattern he should he follow that I am not
asking, then we may say that he will start from here go there, go there, come there, come here
and come back here, that is which route, the sequence. What I am asking is that what is the
minimum distance that is to be traveled to cover all the routes, not the sequence? The routes have
to be covered.

We are not looking at that we are not asking that, what is the sequence we are not asking, how
should he cover, which city should come in first that we are not asking. We are asking he has to
cover all the places in 1 day, how much distance he has to travel. Because the distance travelled
among warehouses that will determine your overtime costs and that will increase your
warehousing cost.

So, what is the idea, minimize the travel distance. So, we want to know what is the travel
distance, what is the total travel distance. Have I been able to explain, what were we doing? We
are saying that the person has, it is not the sequence by which he has to go and cover all these,
we are saying what is the distance that he has to cover if he wants to cover all these places. This
is the problem.

(Refer Slide Time: 22:25)

So, let us see, this is, this is a, this thing, this is a diagram or schematic layout diagram we can
see that there is a workshop 1 or factory 1 (whatever) or warehouse 1, whatever you want to say.
This is a workshop 1, workshop 2, workshop 3, workshop 4, workshop 5, workshop 6. Within a
big factory there may be (simps) many workshops like machine shop, lathe shop, heat chamber,
cooling chamber, so many types of workshops are there.

So, the issue is that these are the locations of these workshops. If a product has to travel all these
workshops, then what is the minimal travel time taken or minimal distance taken? You can say
these are the travel time or the travel distance. Not the sequence, in which sequence the product
will go from 1 workshop to other that we are not asking, we are asking the minimal travel time.
Say for example, you have a vehicle in the morning that leaves your factory, transportation, your
vehicle in a, in the factory it leaves from the factory, factory is here and it has to go to all these
warehouses or all these distributors, it has to go to all these warehouses and all these distributors,
alright. It has to, there is one arrow there; there will be one arrow here. It has to let us say this is
4 and let us say this is 8. So, it has to travel to all these spaces. Let us say 10, 8.

(Refer Slide Time: 24:19)

Anyway, anyway let us forget this. Let us stick to this diagram only. So, what we, we are not
asking for the sequence, we are saying what is the distance that the work that the that the product
has to travel across. Similarly, one vehicle is moving from your factory at one here, one vehicle
is moving from your factory.

It has to cover all these wholesalers or distributors or warehouses or retailers whatever they are,
but it has to cover all of them. What is the minimal travel distance? Why is it necessary?
Because, if the minimal travel distance is such that it cannot be covered in one day then what
will I do? I will make this as one segment and this is another market segment, this as another
market segment.

This part is one segment which can be covered in one day, this part is another region which has
to be covered in another day, clear. So, that is why this is required. So, we want to know what
the travel distance is. This is helpful for market segmentation, vehicle planning also. If I know
that one vehicle can cover only this much and in one day because of the time, this may be
distance, this may be time same thing.

If I know that one vehicle can cover only this much of a distance in one day, so one center
remains pending. So, I will put them in another, another area or another location. So, how to do
this? Let us see how to do this. Idea is start from here. What are the 2 options - 25, 20? Go for
the lowest distance or lowest time. So, 1 is covered, then 3 is covered; I am not saying it should
go from 1 to 3, their sequence I am not saying, I am saying 1 and 3, this is 1 road, 1 distance.

Now, we will have to take these 2 roads which are circled means which have been covered,
which have been touched. From these 2 circles, you see what are the areas where you can go
which have not been circled, these 2 are circled means these 2 have been connected by a road,
connected by distance. So, now from here it is 25, from 3 it is 3, from 3 it is 6.

So, which one should we take, we should take the one with the lowest time or lowest distance.
So, you see now, wholesaler or distributor 2 is also connected. So, wholesale factory, wholesaler
3 is connected, wholesaler 3 to 2, 2 is also connected. Now, now remember we start, we have, we
were looking at 1 and 3 and we said this is 25 this is 3, this is 6, so we went for the lowest 1,
assume this was also 3.

So, 1 could we, could have been connected to 2 or 3 is all, here also it is 3 to 3 could have been
also connected. The choice is yours, you can take anyone. So, long as you go for the lowest cost
you can take any route. So, 2 is connected. Now, you see 1 has been connected, 2 has been
connected, 3 has been connected. So, forget the ones that are, forget the ones that are this side,
no need now, move forward, from 3 you can connect 5, 6 kilometers or 6 minutes.

From 2, 5 kilometers to unit 4, 14 kilometers to unit 6, so, 6 kilometers, 5 kilometers, and 14


kilometers, which is the lowest?: 5 kilometers; done. Now, next one, which one will you
consider the outer ones? So, 2, 4, 3, which ones left? 14 kilometers? 4 kilometers? 4 kilometers?
6 kilometers? 14 is ruled out, 6 is ruled out; so, you are left with 4 and 4.

Which one will you take? Let us take this one, let us take this one. Now what are left - 2, 4 and 5:
2, 4, 5, 14 kilometers, 14, 4, 7, which one is lowest?: 4. So, you see one circle it, so you see all
the wholesalers are covered and what is the total time taken or total distance that has to be
covered 20, 3, 5, 4, 4; 20, 3, 5, 4, 4. 28, 32, 36 kilometers, is the distance that had to be covered.

(Refer Slide Time: 30:01)

Now, take a situation here there was an arbitrary, take a situation when we were, we were here,
we were here. So, we had option 2, 5 and 3, sorry this 2, 4 and 3, how much is moving out 14, 4,
4, 6. So, 14 and 6 are ruled out, we have the option to take this route; we have the option to take
this route. What option did we take earlier? - this route.

It is arbitrary you take anyone. We took this route now let us take this one. So, this is my route.
This is my route, this is not covered. This is not covered. So, what will happen? I have to cover
either through this way or I have to cover to this way. Now, since this is the lowest or the
cheapest I will not take this route I will also have to take this route.

So, what is the distance now? 20 plus 3 – 23; 23 plus 5 – 28: 32, 36 - 20, 23, 28, 32, 36, same 23,
5, 4, 4. So, it asked me how much time or how much distance I have to cover if I am to cover all
the places. Now, you will ask me but this worker coming here has to go back. So, if you are
really taking the time you will have to double it.

Now, when is the single route model possible, say your laying a road or laying a cable you know
exactly how much of cable is required to cover all the places, how much a cable is required to
cover all the places. So, this is what we call as the minimal spanning tree problem. Now, with
this, we basically finish off with the transportation modeling and analytics part of „Modelling
and Analytics for Supply Chain Management‟.

In the next few lectures we will take you through the other dimensions of modeling. So, what
have we covered till now, we have gone into the basics then we looked into supplier selection.
Once the suppliers have been selected, the products are being transported. So, supplier selection
modeling, transportation modeling and analytics, in the next sessions onwards we will take you
through warehouse location decisions and warehouse location analytics.

So, once you have forecasted, how much is required, supply selection, transporting them to my
warehouse, and then after transporting them, it is where to locate are warehousing location
decisions. So, supplier selection, transportation, warehousing, so, next module in the next topic
will be warehousing and warehousing related modelling and analytics. Thank you!