SPM UNIT-5

The document outlines the course material for Software Project Management for B-Tech Computer Science students at SVCE Tirupati, detailing objectives, prerequisites, syllabus, and course outcomes. It covers project organization, responsibilities, future software project management trends, and includes a lesson plan, activity-based learning, and various assessments. The course aims to equip students with knowledge and skills in project planning, management, and quality assurance in software development.

Uploaded by

hanif38233
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views33 pages

SPM UNIT-5

The document outlines the course material for Software Project Management for B-Tech Computer Science students at SVCE Tirupati, detailing objectives, prerequisites, syllabus, and course outcomes. It covers project organization, responsibilities, future software project management trends, and includes a lesson plan, activity-based learning, and various assessments. The course aims to equip students with knowledge and skills in project planning, management, and quality assurance in software development.

Uploaded by

hanif38233
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 33

SVCE TIRUPATI

COURSE MATERIAL

Software Project Management


SUBJECT (20A05504a)

UNIT V

COURSE B-TECH

COMPUTER SCIENCE AND


DEPARTMENT ENGINEERING

SEMESTER 3-1

Mrs G T Prasanna Kumari


PREPARED BY
Senior Assistant Professor
(Faculty Name) Mrs N. Divya
Assistant Professor

Version 1

PREPARED / REVISED DATE 07-10-2022

BTECH_CSE_SEM 3-1
SVCE TIRUPATI

TABLE OF CONTENTS – UNIT V


S. NO CONTENTS PAGE NO.
1 COURSE OBJECTIVES 1
2 PREREQUISITES 1
3 SYLLABUS 1
4 COURSE OUTCOMES 1
5 CO - PO/PSO MAPPING 1
6 LESSON PLAN 2
7 ACTIVITY BASED LEARNING 2
8 LECTURE NOTES 2
5.1 PROJECT ORGANIZATION AND RESPONSIBILITIES 2

5.1.2 LINES-OF-BUSINESS ORGANIZATIONS 3

5.1.3 PROJECT ORGANIZATIONS 4

5.1.4 EVOLUTION OF ORGANIZATIONS 7

5.2 FUTURE SOFTWARE PROJECT MANAGEMENT 8

5.2.1 MODERN PROJECT PROFILES 8


5.2.2 NEXT GENERATION SOFTWARE ECONOMICS 16
5.2.3 MODERN PROCESS TRANSITIONS 21
5.3 CASE STUDY: THE COMMAND CENTER PROCESSING AND 24
DISPLAY SYSTEM-REPLACEMENT (CCPDS-R)

9 PRACTICE QUIZ 28
10 ASSIGNMENTS 29
11 QUESTIONS 30
12 SUPPORTIVE ONLINE CERTIFICATION COURSES 30
13 REAL TIME APPLICATIONS 30
14 CONTENTS BEYOND THE SYLLABUS 30
15 PRESCRIBED TEXT BOOKS & REFERENCE BOOKS 31
16 MINI PROJECT SUGGESTION 31

BTECH_CSE_SEM 3-1
SVCE TIRUPATI
1. COURSE OBJECTIVES
1. The objectives of this course are to
2. Understanding the specific roles within a software organization as related to
project and process management.
3. Describe the principles, techniques, methods & tools for model-based
management of software projects, assurance of product quality and process
adherence (quality assurance), as well as experience-based creation &
improvement of models (process management).
4. Understanding the basic infrastructure competences (e.g., process modelling
and measurement)
5. Understanding the basic steps of project planning, project management, quality
assurance and process management and their relationships.

2. PREREQUISITES
Students should have knowledge on
1. proper way of planning and leading software projects.
2. It is a part of project management in which software projects are planned,
implemented, monitored and controlled.
3. SYLLABUS
Project Organizations and Responsibilities: Line-of-Business Organizations, Project
Organizations, evolution of Organizations.

Future Software Project Management, Modern Project Profiles Next generation Software
economics, modern Process transitions.

Case Study: The Command Center Processing and Display System-Replacement(CCPDS-R)

4. COURSE OUTCOMES
1. Describe and determine the purpose and importance of project management
from the perspectives of planning, tracking and completion of project.
2. Compare and differentiate organization structures and project structures
3. Implement a project to manage project schedule, expenses and resources with
the application of suitable project management tools
5. Co-PO / PSO Mapping

SPM PO1 PO2 PO3 PO4 PO5 PO6 PO7 PO8 PO9 P10 PO11 PO12 PSO1 PSO2

CO1 3 2

CO2 3 2

CO3 3 2

CO4 3 2

1|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI

CO5 3 2

6. Lesson Plan

Lecture No. Weeks Topics to be covered References


Project Control and Process Instrumentation
1 T1

2 Seven core Metrics T1, R1


1
3 Indicators T1, R1

4 Quality and Management Indicators T1, R1

5 Life cycle Expectations T1, R2

6 Metrics Automation T1, R1


2
7 Software Project Control Panel (SPCP) T1, R1

8 fundamental metrics classes are trend, comparison and progress T1, R1


Case analysis regarding Metrics in project control with
9 T1, R1
instrumentation
3
10 Discussion of Previous year university questions in question papers T1, R1

7. Activity Based Learning


1. Providing project and resource schedules
2. Feasibility Assessment: is a project possible within required timescales?
3. Resource Allocation: what is the most effective way of allocating resources?
4. Detailed Costing: How much will the project cost and when is that expenditure
to take place?
5. Motivation: Providing targets is an effective way of motivating team members.

8. Lecture Notes
5.1 PROJECT ORGANIZATION AND RESPONSIBILITIES:

INTRODUCTION: Software lines of business and project teams have different motivations.
Software lines of business are motivated by return on investment, new business
discriminators, market diversification and profitability. Software professionals in both types
of organizations are motivated by career growth, job satisfaction and the opportunity to
make a difference.

2|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
5.1.2 LINES-OF-BUSINESS ORGANIZATIONS: Figure 11-1 maps roles and responsibilities to a
default line-of-business organization. This structure can be tailored to specific
circumstances.
• The main features of the default organization are as follows:
• Responsibility for process definition and maintenance is specific to a cohesive
line of business.
• Responsibility for process automation is an organizational role and is equal in
importance to the process definition role.
Organization roles may be fulfilled by a single individual or several different teams,
depending on the scale of the organization

The line of business organization consists of four component teams.


 SOFTWARE ENGINEERING PROCESS AUTHORITY
 The software engineering process authority (SEPA) is responsible for exchanging the
information and project guidance to or from the project practitioners.
 PROJECT REVIEW AUTHORITY
 The project review Authority (PRA) is responsible for reviewing the financial
performance, customer commitments, risks and accomplishments, adherence to
organizational policies by the customer etc.
 SOFTWARE ENGINEERING ENVIRONMENT AUTHORITY
3|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
The software Engineering Environment Authority (SEEA) deals with the maintenance or
organizations standard environment, training projects and process automation
INFRASTRUCTURE
 An organization’s infrastructure provides human resources support, project-
independent research and development other capital software engineering assets.
The typical components of the organizational infrastructure are as follows:
 Project Administration: time accounting system; contracts, pricing, terms and
conditions; corporate information systems integration.
 Engineering Skill Centers: custom tools repository and maintenance, bid and
proposal support, independent research and development.
Professional Development: Internal training boot camp, personnel recruiting, personnel skills
database maintenance, literature and assets library, technical publications

5.1.3 PROJECT ORGANIZATIONS


 shows a default project organization and maps project-level roles and responsibilities.
This structure can be tailored to the size and circumstance of the specific project
organization are as follows:
 The project management team is an active participant, responsible for
producing as well as managing. Project management is not a spectator sport.
 The architecture team is responsible for real artifacts and for the integration of
components, not just for staff functions.
 The development team owns the component construction and maintenance
activities. The assessment team is separate form development

4|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI

SOFTWARE MANAGEMENT TEAM


This is active participant in an organization and is incharge of producing as well as
managing. As the software attributes, such as Schedules, costs, functionality and quality
are interrelated to each other, negotiation among multiple stakeholders is required and
these are carried out by the software management team.
Responsibilities: Software management team is responsible for:
• Effort planning
• Conducting the plan
• Adapting the plan according to the changes in requirements and design
• Resource management
• Stakeholders satisfaction
• Risk management
• Assignment or personnel
• Project controls and scope definition
• Quality assurance
SOFTWARE ARCHITECTURE TEAM

• The software architecture team performs the tasks of integrating the components,
creating real artifacts etc. The skill possessed by the architecture team is of utmost
importance as it promotes team communications and implements the applications
5|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
with a system-wide quality. The success of the development team is depends on the
effectiveness of the architecture team along with the software management team
controls the inception and elaboration phases of a life-cycle.

• The architecture team must have:

• Domain experience to generate an acceptable design and use-case view.

• Software technology experience to generate an acceptable process view,


component and development views
• Responsibilities: Software architecture team is responsible for:
• System-level quality i.e., performance, reliability and maintainability.
• Requirements and design trade-offs.
• Component selection
• Technical risk solution
• Initial integration

SOFTWARE DEVELOPMENT TEAM


• The Development team is involved in the construction and maintenance
activities. It is most application specific team. It consists of several sub teams
assigned to the groups of components requiring a common skill set. The skill set
include the following:
• Commercial component: specialists with detailed knowledge of
commercial components central to a system's architecture.
• Database: specialists with experience in the organization, storage, and
retrieval of data.
• Graphical user interfaces: specialists with experience in the display
organization; data presentation, and user interaction.
• Operating systems and networking: specialists with experience in various
control issues arises due to synchronization, resource sharing,
reconfiguration, inter object communications, name space
management etc.
• Domain applications: Specialists with experience in the algorithms,
application processing, or business rules specific to the system.
• Responsibilities: Software development team is responsible for
• Component development, testing and maintenance.
• Component design and implementation
• Component documentation
SOFTWARE ASSESSMENT TEAM
• The team is involved in testing and product activities in parallel with the
ongoing development. This is an independent team for utilizing the
concurrency of activities. The use-case oriented and capability-based testing
of a process is done by using two artifacts:
• Release specification ( the plan and evaluation criteria for a release);
6|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
• Release description (the results of a release)
• Responsibilities: The assessment team is responsible for
• The exposure of the quality issues that affect the customer’s
expectations.
• Metric analysis.
• Verifying the requirements.
• Independent testing.
• Configuration control and user development.
• Building project infrastructure
5.1.4 EVOLUTION OF ORGANIZATIONS
 The project organization represents the architecture of the team and needs to
evolve consistent with the project plan captured in the work breakdown structure.
Figure 11-7 illustrates how the team's center of gravity shifts over the life cycle, with
about 50% of the staff assigned to one set of activities in each phase.
 A different set of activities is emphasized in each phase, as follows:
 Inception team: An organization focused on planning, with enough support
from the other teams to ensure that the plans represent a consensus of all
perspectives.
 Elaboration team: An architecture-focused organization in which the driving
forces of the project reside in the software architecture team and are
supported, by the software development and software assessment teams as
necessary to achieve a stable architecture baseline.
 Construction team: A fairly balanced organization in which most of the activity
resides in the software development and software assessment teams.
 Transition team: A customer-focused organization in which usage feedback
drives the deployment activities

7|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI

5.2 FUTURE SOFTWARE PROJECT MANAGEMENT:

5.2.1 MODERN PROJECT PROFILES

Continuous Integration

In the iterative development process, firstly, the overall architecture of the project is
created and then all the integration steps are evaluated to identify and eliminate the
design errors. This approach eliminates problems such as down stream integration, late
patches and shoe-horned software fixes by implementing sequential or continuous
integration rather than implementing large-scale integration during the project completion

 Moreover, it produces feasible and a manageable design by delaying the ‘design


breakage’ to the engineering phase, where they can be efficiently resolved. This can
be one by making use of project demonstrations which forces integration into the
design phase.
8|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
 With the help of this continuous integration incorporated in the iterative
development process, the quality tradeoffs are better understood and the system
features such as system performance, fault tolerance and maintainability are clearly
visible even before the completion of the project.

In the modern project profile, the distribution of cost among various workflows or project is
completely different from that of traditional project profile as shown below

Software Engineering Conventional Process Modern process


Workflows Expenditures Expenditures

Management 5% 10%

Environment 5% 10%

Requirements 5% 10%

Design 10% 15%

Implementation 30% 25%

Assessment 40% 25%

Deployment 5% 5%

Total 100% 100%

As shown in the table, the modern projects spend only 25% of their budget for integration
and Assessment activities whereas; traditional projects spend almost 40% of their total
budget for these activities. This is because, the traditional project involve inefficient large-
scale integration and late identification of design issues

Early Risk Resolution

 In the project development lifecycle, the engineering phase concentrates on


identification and elimination of the risks associated with the resource commitments
just before the production stage. The traditional projects involve, the solving of the
simpler steps first and then goes to the complicated steps, as a result the progress will
be visibly good, whereas, the modern projects focuses on 20% of the significant
requirements, use cases, components and risk and hence they occasionally have
simpler steps.

9|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
 To obtain a useful perspective of risk management, the project life cycle has to be
applied on the principles of software management. The following are the 80:20
principles.

 The 80% of Engineering is utilized by 20% of the requirements

 Before selecting any of the resources, try to completely understand all the
requirement because irrelevant resource selection (i.e., resources selected based on
prediction) may yield severe problems.

 80% of the software cost is utilized by 20% of the components

 Firstly, the cost-critical components must be elaborated which forces the project to
focus more on controlling the cost.

 80% of the bugs occur because of 20% of the components

 Firstly, the reliability-critical components must be elaborated which give sufficient


time for assessment activities like integration and testing, in order to achieve the
desired level of maturity.

 80% of the software scrap and rework is due to 20% if the changes.

 The change-critical components r elaborated first so that the changes that have
more impact occur when the project is matured.

 80% of the resource consumption is due to 20% of the components.

 Performance critical components are elaborated first so that, the trade-offs with
reliability; changeability and cost-consumption can be solved as early as possible.

 80% of the project progress is carried-out by 20% of the people

 It is important that planning and designing team should consist of best processionals
because the entire success of the project depends upon a good plan and
architecture.

 The following figure shows the risk management profile of a modern project.

10|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI

Evolutionary requirements

 The traditional methods divide the system requirements into subsystem requirements
which inturn gets divided into component requirements. These component
requirements are further divided into unit requirements. The reason for this systematic
division is to simplify the traceability of the requirements.

 In the project life cycle the requirements and design are given the first and the
second preference respectively. The third preference is given to the traceability
between the requirement and the design components these preferences are given
in order to make the design structure evolve into an organization so it parallels the
structure of the requirements organization.

 Modern architecture finds it difficult to trace the requirements because of the


following reasons.

 Usage of Commercial components

 Usage of legacy components

 Usage of distributed resources

 Usage of object oriented methods.

11|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
Moreover, the complex relationships such as one-one, many-one, one-many, conditional,
time-based and state based exists the requirements statement and the design elements

As shown in the above figure, the top category system requirements are kept as the vision
whereas, those with the lower category are evaluated. The motive behind theses artifacts
is to gain fidelity with respect to the progress in the project lifecycle. This serves as a
significant different from the traditional approach because, in traditional approach the
fidelity is predicted early in the project life cycle

Teamwork among stakeholders

 Most of the characteristics of the classic development process worsen the


stakeholder relationship s which in turn makes the balancing of requirement product
attributes and plans difficult. An iterative process which ahs a good relationship

12|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
between the stakeholders mainly focuses on objective understanding by each and
every individual stakeholder. This process needs highly skilled customers, users and
monitors which have experience in both the application as well as software.
Moreover, this process requires an organization whose focus is on producing a quality
product and achieves customer satisfaction.

The table below shows the tangible results of major milestones in a modern process

Obvious result Actual result

Demonstration at early stage reveals Demonstration firstly reveals the significant


the design issued and uncertainty in assets and risks associated with complicated
a tangible form. software systems such that they can be
worked out at the time of setting the life-
cycle goals.

Non-Complaint design Various perspective like requirements use


cases etc are observed in order to
completely understand the compliance.

Issues of influential requirements are Both the requirement changes and the
reveals but without traceability design trade-offs are considerably balanced.

The design is considered to be The engineering issues can be integrated into


“guilty until its innocence is proved. the succeeding iteration’s plans.

 From the above table, it can be observed that the progress of the project is not
possible unless all the demonstration objectives are satisfied. This statement does not
present the renegotiation of objectives, even when the demonstration results allow
the further processing of tradeoffs present in the requirement, design, plans and
technology.

 Modern iterative process that rely on the results of the demonstration need al its
stakeholders to be well-educated and with a g good analytical ability so as to
distinguish between the obviously negative results and the real progress visible. For
example, an early determined design error can be treated as a positive progress
instead to a major issue.

Principles of Software Management

 Software management basically relies on the following principles, they are,

1. Process must be based on architecture-first approach

13|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
If the architecture is focused at the initial stage, then there will be a good foundation for
almost 20% of the significant stuff that are responsible for the overall success of the project.
This stuff include the requirements, components use cases, risks and errors. In other words, if
the components that are being involved in the architecture are well known then the
expenditure causes by scrap and rework will be comparatively less.

2. Develop an iterative life-cycle process that identifies the risks at an early stage

An iterative process supports a dynamic planning framework that facilitates the risk
management predictable performance moreover, if the risks are resolved earlier, the
predictability will be more and the scrap and rework expenses will be reduced.

3.After the design methods in-order to highlight components-based development.

The quantity of the human generated source code and the customized development
can be reduced by concentrating on individual components rather than individual lines-of-
code. The complexity of software is directly proportional to the number of artifacts it
contains that is, if the solution is smaller then the complexity associated with its
management is less.

4. Create a change management Environment

Highly-controlled baselines are needed to compensate the changes caused by


various teams that concurrently work on the shared artifacts.

5. Improve change freedom with the help of automated tools that support round-trip
engineering.

The roundtrip-engineering is an environment that enables the automation and


synchronization of engineering information into various formats. The engineering
information usually consists requirement specification, source code, design models test
cases and executable code. The automation of this information allows the teams to focus
more on engineering rather than dealing with over head involved

Design artifacts must be captured in model based notation.

The design artifacts that are modeled using a model based notation like UML, are rich
in graphics and texture. These modeled artifacts facilitate the following tasks.

 Complexity control

 Objective fulfillment

 Performing automated analysis

7. Process must be implemented or obtaining objective quality control and estimation of


progress.

14|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
The progress in the lifecycle as well as the quality of intermediately products must be
estimated and incorporated into the process. This can be done with the help of well
defined estimation mechanism that are directly derived from the emerging artifacts. These
mechanisms provide detailed information about trends and correlation with requirements.

8. Implement a Demonstration-based Approach for Estimation of intermediately Artifacts

This approach involves giving demonstration on different scenarios. It facilitates earl


integration and better understanding of design trade-offs. Moreover, it eliminates
architectural defects earlier in the lifecycle. The intermediately results of this approach are
definitive

9.The Points Increments and generations must be made based on the evolving levels of
detail

Here, the ‘levels of detail’ refers to the level of understanding requirements and
architecture. The requirements, iteration content, implementations and acceptance
testing can be organized using cohesive usage scenarios.

10. Develop a configuration process that should be economically scalable

The process framework applied must be suitable for variety of applications. The process
must make use of processing spirit, automation, architectural patterns and components
such that it is economical and yield investment benefits.

Best Practices Associated with software Management

 According to airline software council, there are about nine best practices associated
with software management. These practices are implemented in order to reduce the
complexity of the larger projects and to improve software management discipline.

 The following are the best practices of software management:

1. Formal Risk Management: Earlier risk management can be done by making use of
iterative life cycle process that identifies the risks at early stage.

2. Interface Settlement: The interface settlement is one of the important aspects of


architecture first approach because; obtaining architecture involves the selection of
various internal and external interfaces that are incorporated into the architecture.

3. Formal Inspections: There are various defect removal strategies available. Formal
inspection is one of those strategies. However this is the least important strategy because
the cost associated with human recourses is more and is defect detection rate for the
critical architecture defects is less

15|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
Management and scheduling based on metrics: This principle is related to the model
based approach and objective quality control principles. It states to use common
notations fro the artifacts so that quality and progress can be easily measured.

5. Binary quality Gates at the inch-pebble level: The concept behind this practice is quite
confusing. Most of the organizations have misunderstood the concept and have
developed an expensive and a detailed plan during the initial phase of the lifecycle, but
later found the necessity to change most of their detailed plan due to the small changes in
requirements or architectural. This principle states that first start planning with an
understanding of requirements and the architecture. Milestones must be established during
engineering stage and inch-pebble must be followed in the production stage.

6. Plan versus visibility of progress throughout the progress: This practice involves a direct
communication between different team members of a project so that, they can discuss
the significant issues related to the project as well as notice the progress of the project in-
comparison to their estimated progress

7.Identifying defects associated with the desired quality: This practice is similar to the
architecture-first approach and objective quality control principles of software
management. It involves elimination of architectural defects early in the life-cycle, thereby
maintaining the architectural quality so as to successfully complete the project.

8. Configuration management: According to Airline software council, configuration


management serves as a crucial element for controlling the complexity of the artifacts and
for tracing the changes that occur in the artifacts. This practice is similar to the change
management principle of software management and prefers automation of components
so as to reduce the probability of errors that occur in the large-scale projects.

9.Disclose management accountability: The entire managerial process is disclosed to al the


people dealing with the project

5.2.2 Next generation software cost models

 In comparison to the current generation software cost modes, the next generation
software cost models should perform the architecture engineering and application
production separately. The cost associated with designing, building, testing and
maintaining the architecture is defined in terms of scale, quality, process, technology
and the team employed.

 After obtaining the stable architecture, the cost of the production is an exponential
function of size, quality and complexity involved.

 The architecture stage cost model should reflect certain diseconomy of scale
(exponent less than 1.0) because it is based on research and development-oriented
concerns. Whereas the production stage cost model should reflect economy of
scale (exponent less than 1.0) for production of commodities.
16|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
 The next generation software cost models should be designed in a way that, they
can assess larger architectures with economy of scale. Thus, the process exponent
will be less than 1.0 at the time of production because large systems have more
automated proves components and architectures which are easily reusable.

 The next generation cost model developed on the basis of architecture-first


approach is shown below.

 At architectural engineering Stage

 A Plan with less fidelity and risk resolution

 It is technology or schedule-based

 It has contracts with risk sharing

 Team size is small but with experienced professionals.

 The architecture team, consists of small number of software engineers

 The application team consists of small number of domain engineers.

 The output will be an executable architecture, production and requirements

 The focus of the architectural engineering will be on design and integration of


entities as well as host development environment.

 It contains two phases they are inspection and elaboration

• At Application production stage

17|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
• A plan with high fidelity and lower risk

• It is cost-based

• It has fixed-priced contracts

• Team size is large and diverse as needed.

• Architecture team consists of a small number of software engineers.

• The Application team may have nay number of domain engineers.

• The output will be a function which is deliverable and useful, tested

baseline and warranted quality.

• The focus of the application production will be on implementing testing

and maintaining target technology.

• It contains two phases they are construction and transition

Total Effort = Func(TechnologyArch, ScaleArch, Quality Arch, Process Arch) +


Func(TechnologyApp, ScaleApp, Quality App, Process App)

Total Time = Func(ProcessArch, EffortArch) + Func(ProcessApp, EffortApp,)

 The next generation infrastructure and environment automated various


management activities with low effort. It relieves many of the sources of diseconomy
of scale by reusing the common processes that are repetitive in a particular project.
It also reuses the common outcomes of the project. The prior experience and
matured processes utilized in these types of models eliminate the scrap rework
sources. Here, the economics of scale will be affected.

 The architecture and applications of next generation cost models have difference
scales and sized which represents the solution space. The size can be computed
18|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
inters of SLOC or megabytes of executable code while the scale can be computed
in 0-terms of components, classes, processes or nodes. The requirement or use cases
of solution space are different from that of a problem space. Moreover, there can
be more than one solution to a problem. Where cost serves as a key discriminator.
The cost estimates must be determined to find an optimal solution. If an optional
solution is not found then different solution s need to be selected or to change the
problem statement.

 A strict notation must be applied for design artifacts so, that the prediction of a
design scale can be improved. The Next-generation software cost model should
automate the process of measuring design scale directly from UML diagrams. There
should be two major improvements. There are,

 Separate architectural engineering stage from application production stage.


This will yield greater accuracy and more precision of lifecycle estimate.

 The use of rigorous design notations. This will enable the automation and
standardization of scale measure so that they can be easily traced which
helps to determine the total cost associated with production.

 The next generation software process has two potential breakthroughs, they are,

 Certain integrated tools would be available that automates the information


transition between the requirements, design, implementation and deployment
elements. These tools facilitate roundtrip engineering between various artifacts
of engineering.

It will reduce the four sets of fundamental technical artifacts into three sets. This is achieved
by automating the activities related to human-generated source code so as to eliminate
the need fro a separate implementation set

An organizational manager should strive for making the transition to a modern process’.

 The transition to a modern process should be made based on the following


quotations laid by Boehm.

Identifying and solving a software problem in the design phase is almost 100 times cost
effective than solving the same problem after delivery.

This quotation or metric serves as a base for most software processes. Modern processes,
component-based development techniques and architectural frameworks mainly focuses
on enhancing this relationship. The architectural errors are solved by implementing an
architecture-first approach. Modern process plays a crucial role in identification of risks

Software Development schedules can be compressed to a Maximum of 25 percent

19|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
If we want a reduction in the scheduled time, then we must increase the personnel
resources which inturn increases the management overhead. The management overhead,
concurrent activities scheduling, sequential activities conservation along some resource
constraints will have the flexibility limit of about 25 percent.

This metric must be acceptable by the engineering phase which consists of detailed
system content if we have successfully completed the engineering then compression in the
production stage will be automatically flexible. The concurrent development must be
possible irrespective of whether a business organization implements the engineering phase
over multiple projects or whether a project implements the engineering phase over
multiple incremental stages

The maintenance cost will be almost double the development cost

Most o the experts in the software industry find it difficult to maintain the software than
development. The ratio between development and maintenance can be measured by
computing productivity cost. One of the interesting fact of iterative development is that
the dividing line between the development and maintenance is vanishing. Moreover, a
good iterative process and an architecture will cause the reduction in the scrap and
rework levels so this ratio (i.e.,) 2:1 can be reduced to 1:1.

Both the software development cot and the maintenance cost are dependent on the
number of lines in the source code.

This metric was applicable to the conventional cost models which were lacking in-
terms of commercial components, reusing techniques, automated code generators etc.
The implementation of commercial components, reusing techniques and automated code
generators will make this metric inappropriate. However, the development cost is still
dependent on the commercial components, reuse technique and automatic code
generators and their integration.

The next-generation cost models should focus more on the number of components
and their integration efforts rather than on the number of lines of code.

Software productivity mainly relies on the type of people employed

The personal skills, team work ability and the motivation of employees are the crucial
factors responsible for the success and the failure of any project. The next-generation cost
models failure should concentrate more on employing a highly skilled team of professionals
at engineering stage

The ratio of software to hardware cost is increasing.

As the computers are becoming more and more popular, the need for software an
hardware applications is also increasing. The hardware components are becoming
cheaper whereas, the software applications are becoming more complicated as a result,
20|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
highly skilled professionals needed for development and controlling the software
applications, the in turn increases the cost. In 1955 the software to hardware cost ratio was
15:85 and in 1985 this ratio was 85:15. This ratio continuously increases with respect to the
need for variety of software applications. Certain software applications have already been
developed which provides automated configuration control and analysis of quality
assurance. The next-generation cost models must focus on automation of production and
testing.

Only 15% of the overall software development is dedicated process to programming.

 The automation and reusability of codes have lead to the reduction in programming
effort. Earlier in 1960s, the programming staff was producing about 200 machine
instructions per month and in 1970s and 1980s, the machine instruction count has
raised to about 1000 machine instructions. Now as days, programmers are able to
produce several thousand instructions without even writing few hundreds of them

Software system and products cost three times the cost associated with individual
software programs per SLOC software-system products cost 9 times more than the cost
of individual software program.

 In the software development, the cost of each instruction depends upon the
complexity of the software. Modern processes and technologies must reduce this
diseconomy of scale. The economy of the scale must be achievable under the
customer specific software systems with a common architecture, common
environment and common process.

60% of Errors are caught by walkthrough

 The walkthrough and other forms of human inspection catch only the surface
and style issues. However, the critical issues are not caught by the walkthroughs so,
this metric doesn’t prove to the reliable.

Only 20% of the contributors are responsible for the 80% of the contributions.

 This metric is applicable to most of the engineering concepts such as 80:20


principles of software project management. The next generation software process
must facilitate the software organizations in achieving economic scale.

5.2.3 MODERN PROCESS TRANSITIONS

Indications of a successful project transition to a modern culture

 Several indicators are available that can be observed in order to distinguish projects
that have made a genuine cultural transition from projects that only pretends.

 The following are some rough indicators available.

21|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
The lower-level managers and the middle level managers should participate in the project
development

Any organization which ha an employee count less than or equal to 25 does not need to
have pure managers. The responsibility of the managers in this type of organization will be
similar to that of a project manager. Pure managers are needed when personal resources
exceed 25. Firstly, these managers understand the status of the project them, develop the
plans and estimate the results. The manager should participate in developing the plans.
This transition affects the software project managers

Tangible design and requirements

The traditional processes utilize tons of paper in order to generate the documents
relevant to the desired project. Even the significant milestones of a project are expressed
via documents. Thus, the traditional process spends most of their crucial time on document
preparation instead of performing software development activities.

An iterative process involves the construction of systems that describe the architecture,
negotiates the significant requirements, identifies and resolves the risks etc. These
milestones will be focused by all the stakeholders because they show progressive deliveries
of important functionalities instead of documental descriptions about the project.
Engineering teams will accept this transition of environment from to less document-driven
while conventional monitors will refuse this transition.

Assertive Demonstrations are prioritized

The design errors are exposed by carrying-out demonstrations in the early stages of the
life cycle. The stake holders should not over-react to these design errors because
overemphasis of design errors will discourage the development organizations in producing
the ambitious future iterating. This does not mean that stakeholders should bare all these
errors. Infact, the stakeholders must follow all the significant steps needed for resolving
these issues because these errors will sometimes lead to serious down-fall in the project.

This transition will unmark all the engineering or process issues, so, it is mostly refused by
management team, and widely accepted by users, customers and the engineering team.

The performance of the project can be determined earlier in the life cycle.

The success and failure of any project depends on the planning and architectural
phases of life cycle so, these phases must employ high-skilled professionals. However, the
remaining phases may work well an average team.

Earlier increments will be adolescent

The development organizations must ensure that customers and users should not
expect to have good or reliable deliveries at the initial stages. This can be done by

22|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
demonstration of flexible benefits in successive increments. The demonstration is similar to
that of documentation but involves measuring of changes, fixes and upgrades based on
the objectives so as to highlight the process quality and future environments

Artifacts tend to be insignificant at the early stages but proves to be the most significant in
the later stages

The details of the artifacts should not be considered unless a stable and a useful baseline
is obtained. This transition is accepted by the development team while the conventional
contract monitors refuse this transition.

Identifying and Resolving of real issues is done in a systematic order

The requirements and designs of any successful project arguments along with the
continuous negotiations and trade-offs. The difference between real and apparent issued
of a successful project can easily be determined. This transition may affect any team of
stakeholders

Everyone should focus on quality assurance

The software project manager should ensure that quality assurance is integrated in
every aspect of project that is it should be integrated into every individuals role, every
artifact, and every activity performed etc. There are some organizations which maintains a
separate group of individuals know as quality assurance team, this team would perform
inspections, meeting and checklist inorder to measure quality assurance. However, this
transition involves replacing of separate quality assurance team into an organizational
teamwork with mature process, common objectives and common incentives. So, this
transition is supported by engineering teams and avoided by quality assurance team and
conventional managers.

Performance issues crop up earlier in the projects life cycle

Earlier performance issues are a mature design process but resembles as an immature
design. This transition is accepted by development engineers because it enables the
evaluation of performance tradeoffs in subsequent releases.

Automation must be done with appropriate investments

Automation is the key concept of iterative development projects and must be done
with sufficient funds. Moreover, the stakeholders must select an environment that supports
iterative development. This transition is mainly opposed by organizational managers.

Good software organizations should have good profit margins.

Most of the contractors for any software contracting firm focus only on obtaining their
profit margins beyond the acceptable range of 5% and 15%. They don’t look for the quality
of finished product as a result, the customers will be affected. For the success of any
23|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
software industry, the good quality and at a reasonable rate them, customer will not worry
about the profit the contractor has made. The bad contractors especially in a government
contracting firm will be against this transition

Characteristics of conventional and iterative software development Process

 The characteristics of the conventional software process are listed below:

1. It evolves in the sequential order (requirement design-code-test).

2. It gives the same preference to all the artifacts, components, requirements


etc.

3. It completes all the artifacts of a stage before moving to the other stage in the
project life cycle.

4. It achieves traceability with high-fidelity for al the artifacts present at each life
cycle stage.

 The characteristics of the modern iterative development process framework are


listed below:

1. It continuously performs round-trip engineering of requirements, design, coding


and testing at evolving levels of abstraction.

2. It evolves the artifacts depending on the priorities of the risk management.

3. It postpones the consistency analysis and completeness of the artifacts to the


later stages in the life cycle.

4. It achieves the significant drives (i.e. 20 percent) with high-fidelity during the
initial stages of the life cycle.

5.3. casestudy: The Command Center Processing and Display System-Replacement


(CCPDS-R)

• The Command Center Processing and Display Sys-tem-Replacement (CCPDS-R)


project was performed for the U.S. Air Force by TRW Space and Defense in Redondo
Beach, California. The entire project included systems engineering, hardware
procurement, and software development, with each of these three major activities
consuming about one-third of the total cost. The schedule spanned 1987 through
1994.

The metrics histories were all derived directly from the artifacts of the project's process.
These data were used to manage the project and were embraced by practitioners,
managers, and stakeholders.

24|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
There are very few well-documented projects with objective descriptions of what worked,
what didn't, and why. This was one of my primary motivations for providing the level of
detail contained in this appendix. It is heavy in project-specific details, approaches, and
results, for three reasons:

1. Generating the case study wasn't much work. CCPDS-R is unique in its detailed and
automated metrics approach. All the data were derived directly from the historical
artifacts of the project's process.

2. This sort of objective case study is a true indicator of a mature organization and a mature
project process. The absolute values of this historical perspective are only marginally useful.
However, the trends, lessons learned, and relative priorities are distinguishing characteristics
of successful software development.

3. Throughout previous chapters, many management and technical approaches are


discussed generically. This appendix provides in a real-world example at least one relevant
benchmark of performance

• The CCPDS-R project produced a large-scale, highly reliable command and control
system that provides missile warning information used by the National Command
Authority. The procurement agency was Air Force Systems Command Headquarters,
Electronic Systems Division, at Hanscom Air Force Base, Massachusetts. The primary
user was US Space Command, and the full-scale development contract was
awarded to TRWs Systems Integration Group in 1987. The CCPDS-R contract called
for the development of three subsystems:

1. The Common Subsystem was the primary missile warning system within the Cheyenne
Mountain Upgrade program. It required about 355,000 source lines of code, had a 48-
month software development schedule, and laid the foundations for the subsystems that
followed (reusable components, tools, environment, process, procedures). The Common
Subsystem included a primary installation in Cheyenne Mountain, with a backup system
deployed at Offutt Air Force Base, Nebraska.

2. The Processing and Display Subsystem (PDS) was a scaled-down missile warning display
system for all nuclear-capable commanders-in-chief. The PDS software (about 250,000
SLOC) was fielded on remote, read-only workstations that were distributed worldwide.

3. The STRATCOM Subsystem (about 450,000 SLOC) provided both missile warning and force
management capability for the backup missile warning center at the command center of
the Strategic Command

CCPDS-R life-cycle overview

• The CD phase was very similar in intent to the inception phase. The primary products
were a system specification (a vision document), an FSD phase proposal (a business
case, including the technical approach and a fixed-price-incentive and award-fee
25|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
cost proposal), and a software development plan. The CD phase also included a
system design review, technical interchange meetings with the government
stakeholders (customer and user), and several contract-deliverable documents.
These events and products enabled the FSD source selection to be based on
demonstrated performance of the contractor-proposed team as well as the FSD
proposal.

• From a software perspective, there was one additional source selection criterion
included in the FSD proposal activities: a software engineering exercise. This was a
unique but very effective approach for assessing the abilities of the two competing
contractors to perform software development. The Air Force was extremely
concerned with the overall software risk of this project: Recent projects had
demonstrated dismal software development performance. The Air Force acquisition
authorities had also been frustrated with previous situations in which a contractor's
crack proposal team was not the team committed to perform after contract award,
and contractor proposals exaggerated their approaches or capabilities beyond
what they could deliver.

CCPDS-R was also a very large software development activity and was one of the
first projects to use the Ada programming language. There was serious concern that
the Ada development environments, contractor processes, and contractor training
programs might not be mature enough to use on a full-scale development effort. The
purpose of the software engineering exercise was to demonstrate that the
contractor's proposed software process, Ada environment, and software team were
in place, were mature, and were demonstrable

• The software engineering exercise occurred immediately after the FSD proposals
were submitted. The customer provided both bidders with a simple two-page
specification of a "missile warning simulator." This simulator had some of the same
fundamental requirements as the CCPDS-R full-scale system, including a distributed
architecture, a flexible user interface, and the basic processing scenarios of a simple
CCPDS-R missile warning thread. The exercise requirements included the following:

• Use the proposed software team.

• Use the proposed software development techniques and tools.

• Use the FSD-proposed software development plan.

• Conduct a mock design review with the customer 23 days after receipt of the
specification.

• Four primary use cases were elaborated and demonstrated.

26|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
• A software architecture skeleton was designed, prototyped, and documented,
including two executable, distributed processes; five concurrent tasks (separate
threads of control); eight components; and 72 component-to-component interfaces.

• A total of 4,163 source lines of prototype components were developed and


executed. Several thousand lines of reusable components were also integrated into
the demonstration.

• Three milestones were conducted and more than 30 action items resolved.

• Production of 11 documents (corresponding to the proposed artifacts)


demonstrated the automation inherent in the documentation tools.

• The Digital Equipment Corporation VAX/VMS tools, Rational R1000 environment,


LaTeX documentation templates, and several custom-developed tools were used.

• Several needed improvements to the process and the tools were identified. The
concept of evolving the plan, requirements, process, design, and environment at
each major milestone was considered potentially risky but was implemented with
rigorous change management.

• In preparing for the CCPDS-R project, TRW placed a strong emphasis on evolving the
right team. The CD phase team represented the essence of the architecture team
which is responsible for an efficient engineering stage. This team had the following
primary responsibilities:

• Analyze and specify the project requirements

• Define and develop the top-level architecture

• Plan the FSD phase software development activities

• Configure the process and development environment

• Establish trust and win-win relationships among the stakeholders

1.Network Architecture Services (NAS). This foundation middleware provided


reusable components for network management, interprocess communications,
initialization, reconfiguration, anomaly management, and instrumentation of
software health, performance, and state. This CSCI was designed to be reused
across all three CCPDS-R subsystems.

2. System Services (SSV). This CSCI comprised the software architecture skeleton, real-
time data distribution, global data types, and the computer system operator
interface.

3. Display Coordination (DCO). This CSCI comprised user interface control, display
formats, and display population.
27|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
4. Test and Simulation (TAS). This CSCI comprised test scenario generation, test
message injection, data recording, and scenario playback.

5. Common Mission Processing (CMP). This CSCI comprised the missile warning
algorithms for radar, nuclear detonation, and satellite early warning messages.

6. Common Communications (CCO). This CSCI comprised external interfaces with


other systems and message input, output, and protocol management

9.Practice Quiz
1. The Primary themes of a modern software development process tackle the
central?
a) Management issues of complex software
b) planning
c) getting right
d) All of the above

2. The quality of software products and the progress made towards?


a) Management discipline
b) Un predictable practices
c) Project goals
d) None of the above

3. The goals of software metrics are to provide the development team and ?
a) Manage and control
b) Management team
c) Modern technologies
d) Fine practices

4. To maintain management control, measuring cost expenditures over _______ is


always necessary?
a) Modern technologies
b) Waterfall model
c) Analysis
d) Project life cycle

5. An iterative development should start with a small team until the risks in the
requirements and architecture have been suitably resolved in staffing and team
dynamics?
a) true
b) false
28|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI

6. Breakage is defined as ?
a) Requirement analysis
b) substantial design change
c) extent of change
d) none

7. Metrics collections agents are ________ from the environment tools?


a) Precise requirements
b) specifying requirements
c) Data Extraction
d) none

8. which is dominated by intellectual activities that are focused on solving problems of


immense complexity?
a) software engineering
b) software economics
c) required functionality
d) process values

9. The environment, which is made up of the tools and techniques available to support
efficient software development and to?
a) Project Performance
b) Automate the Process
c) Efforts
d) Predictions

10. Software Management efforts span a broad range of domains.


a) True
b) False

10.Assignments

S. No Question BL CO
1 Tailoring the Process 2 1
2 Process Discriminants 2 1
3 The Project Environment and responsibilities 2 1
4 Stakeholder Cohesion or Contention 2 1
5 Modern Project Profiles 3 1
6 Define conventional software management in detail 3 1
29|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI

11. Questions

S. No Question BL CO
1 What is meant by configuration baseline? (may/June -2016) 1 1

2 What are included in architecture baselines? (may/june-2017) 2 1

3 Define stakeholder environment. (may/june-2017) 2 1

4 Define breakage and modularity(may/june-2017) 3 1

5 Explain process maturity level. (may/june-2017) 3 1

12. Supportive Online Certification Courses


1. Software Project ManagementBy Prof. Rajib Mall & Prof. Durga Prasad Mohapatra,
conducted by IIT Kharagpur – 12 weeks.

13. Real Time Applications


S. No Application CO
1 1.1 Modern Project Profiles, Positive and Negative trends will 3
be more tangible early in the life cycle.

Most of the critical risks will be resolved by the end of the


elaboration phase. The construction and transition phases,
during which there is generally the most cost and risk,
should be free for surprises. Major milestones focus on
demonstrated results.
1.2 Early Risk Resolution
The engineering stage of the life cycle inception and
elaboration phases focuses on the risks and resolving
them before the big resource commitments of the
production stage.

14. Contents Beyond the Syllabus


DENOUEMENT
The Conventional software process was characterized by the sequentially
transitioning from requirements to design to code to test, Achieving 100%

30|S P M - U N I T - V

BTECH-CSE-SEM 3-1
SVCE TIRUPATI
completeness of each artifact at each life cycle stage and treating all
requirements, artifacts, components as equal.

15. Prescribed Text Books & Reference Books


Text Book
1. Software Project Management, Walker Royce, Pearson Education.
2. Software Project Management, Bob Hughes & Mike Cotterill, fourthedition, Tata
Mc-Graw Hill
Reference Books:
1. Applied Software Project Management, Andrew Stellman & Jennifer Greene,
2006
2. Head First PMP, Jennifer Greene & Andrew Stellman, O‟Reilly,2007
3. Software Engineering Project Management, Richard H. Thayer & Edward
Yourdon, second edition, Wiley India, 2004.
4. Agile Project Management, Jim Highsmith, Pearson education, 2004
5. The art of Project management, Scott Berkun, O‟Reilly, 2005.
6. Software Project Management in Practice, Pankaj Jalote, Pearson
Education,2002

16. Mini Project Suggestion


1. Modern Iterative development process framework
In today’s world almost all digital services like internet communication, medical
and military imaging systems, multimedia system needs a high-level security.
There is a need for security level in order to safely store and transmit digital
images containing critical information. This is because of the faster growth
multimedia technology, internet and cell phones. Therefore, there is a need for
image encryption techniques in order to hide images from such attacks.