Cross Examination
Cross Examination
Is it correct to state that you have been associated with the claimant com-
pany for several years?
Is it correct to state that you share both a professional and personal relation-
ship with the director of the claimant company?
Is it correct to state that the financial outcome of this arbitration directly im-
pacts the claimant company?
Is it correct to state that this document bears the signature of the claimant’s
authorized representative?
Is it correct to state that this letter acknowledges that the claimant has read
and understood all tender documents?
Is it correct to state that the letter confirms the claimant has conducted all
necessary surveys and investigations before bidding?
Is it correct to state that the claimant was fully aware of the project condi-
tions before submitting the bid?
Is it correct to state that despite this acknowledgment, the claimant now al-
leges that critical project details were not disclosed?
Is it correct to state that you were part of the team reviewing the tender doc-
uments before submission?
Is it correct to state that the DPR was not binding on the respondent? - can-
not comment since DPR was not there
Is it correct to state that the Request for Proposal (RFP) stated that the re-
spondent would not be liable for any project delays due to DPR inaccuracies?
- cannot comment since DPR was not there
Is it correct to state that the Technical Schedule in the DPR mentioned that
certain project permissions were pending? - needs to be checked (techni-
cal schedule)
Is it correct to state that the RFP required bidders to verify all project-related
permissions independently? - NO; it is the work of the respondent
Is it correct to state that the claimant did not raise any formal concerns re-
garding missing permissions before submitting the bid? - did not consider
it necessary in view of the assuring clauses of the Agreement
Is it correct to state that the RFP explicitly stated that the respondent would
not be liable for errors in the DPR? - cannot comment since DPR was not
there
Is it correct to state that the claimant was aware that the respondent was not
responsible for ensuring project permissions were in place before the bid? -
cannot comment since DPR was not there
Is it correct to state that the letter confirms that the claimant accepted all
tender documents, including disclaimers? - yes, including the reassuring
clauses
Is it correct to state that the letter affirms the claimant conducted an inde-
pendent survey? - yes to the extent of claimant work
Is it correct to state that the claimant has not produced a copy of this inde-
pendent survey? - no formal proof/record; procedural thing
Is it correct to state that the claimant was aware that the respondent was not
in possession of the project stretch at the time of bidding? - no; even Re-
spondent was not aware (refer PWD Goa and Karnataka forest clear-
ance letter)
Is it correct to state that this meant the claimant knew the right of way would
not be available from day one of the contract?- No; Respondent’s respon-
sibility to have all the permissions
Is it correct to state that after this date, any activity undertaken by the
claimant was at its own risk?
Is it correct to state that the claimant has not provided the requested bank
details to date? It was already with the Respondent
Is it correct to state that despite believing it was entitled to greater compen-
sation, the claimant refused to accept the 1% restitutionary payment? - yes;
since the contract was terminated at Respondent’s wish
Is it correct to state that this letter did not contain a definitive assurance re-
garding site availability? Assume since the copy has been shared with
Claimant
Is it correct to state that neither this letter nor the respondent provided a
binding assurance regarding site availability? - no contrary contention
was also shown; RO letter reference
Is it correct to state that the return of this guarantee in February 2024 con-
firms that the respondent fulfilled its obligations under the termination
clause?
Is it correct to state that the claimant had acknowledged in writing the risks
mentioned in the tender documents?
Is it correct to state that despite these disclaimers, the claimant did not con-
duct an independent survey?
Is it correct to state that given these facts, the losses claimed by the
claimant were self-inflicted?