1- MS for Block Work Onlyfor TSE Tank Support Purpose
1- MS for Block Work Onlyfor TSE Tank Support Purpose
DG-PIN-456-0000-AWJ-MTS-CE-000012_ R0
8 - August - 2024
2 Scope of Work
The scope of this method statement is for concrete work but is not limited to:
This method statement outlines a systematic approach to ensure that block masonry and
plastering work is carried out in accordance with the contract, project specification and
drawings.
The contractor must continuously monitor and supervise the work activities to verify they
are conducted in line with the method statement.
This method statement outlines the working procedures for block and plastering work
associated activities. This will cover the storage of materials, the layout of block work, the
laying of blocks, and the curing process.
2.1 References to be used
MS - Method Statement
ITP – Inspection and test plan.
HSE – Health Safety and Environment.
RA – Risk Assessment
COSHH - Control of Substances Hazardous to Health Regulations
MSDS – Material safety data sheet
PMC - Project Management Consultant (Saudi Arabian Parsons)
CSC - Construction Supervision Consultant (Dorsch Holding Gmbh)
DC - Diriyah Company
Contractor - ABCC & WETICO Joint Venture
IFC – Issued for Construction
MIR – Material Inspection Request
WIR – Work Inspection Request
MAR – Material Approval Request
CEMP - Construction Environmental Management Plans
CM - Construction manager
PM - Project manager
EPA - Environmental Protection Agency
CMU - Concrete Masonry Unit
2.3 Responsibility
2.3.1 Project Manager
The Project manager Shall be responsible for overall project execution, he will coordinate
with the client and head office, progress monitoring, attending review meetings, and
resource management, overall, he will be responsible for the timely completion of the
project by all contractual requirements.
He is responsible for ensuring the work is executed on time and by contract specifications
and production drawings. Ensures that the content of this method statement is
understood and implemented at all times.
Coordinate with the Construction Manager to ensure that the necessary resources to
implement the approved Method Statement have been allocated to the task.
Determine all the requirements needed to comply with quality and safety standards and
regulations as required.
2.3.2 Construction Manager
Oversee and direct construction activities from conception to completion. Review the
activities in-depth to schedule deliverables and estimate time. Oversee all onsite and
offsite constructions to monitor compliance with building and safety regulations.
The HSE Manager is responsible for establishing an effective HSE management plan.
Ensures the HSE management system requirements are established, implemented, and
maintained.
Coordinates with the Site HSE team and the Construction Management team to ensure
effective implementation of the Procedures. Assist the risk assessment team in formulating
Method Statements and Risk Assessments for specific construction activities
To lead the entire team, maintaining HSE awareness and creating a safe culture and
working environment through innovative ideas. Planning and coordinating the HSE
Training for the project.
Issue necessary directives to the Safety Officer / Supervisor and render advice to the
Project Manager, as required. Prepare and submit reports on HSE issues to, Safety
Executives whenever required.
Carry out HSE inspections at construction sites concerning all HSE issues. Liaise with
Client’s and Consultants’ HSE Departments. Take part in incident investigation and
reporting of all Incidents. Monitor and assess HSE measures on visits to sites.
2.3.4 HSE Engineer/Officer
Will ensure that all relevant notifications and signs have been posted before the
commencement of the work.
Will ensure that all the activities related to the specified task are being followed safely and
all workers are wearing PPE.
Identify and take control measures for the risks associated with the hazard. Will identify
and predict hazards in the surroundings or working conditions and take prompt corrective
measures to eliminate or correct them.
Has the authority to stop work immediately if an unacceptable impact on the environment
is occurring or is likely to occur. Responsible for ensuring the preparation of site-specific
environmental and regulatory documentation and for regular review and improvement of
such documentation, as appropriate.
Where a control measure used to limit environmental harm is found to be inadequate, or a
potential incident is likely, he may request remedial works to be carried out. Ensure that
the material and information for environmental induction, training, and toolbox talks are
timely prepared and delivered.
Revision 03 DD-SWD-SW-SWD-000-000-DGD-TEM-HS-000001 Date of Issue: March 24 Page No(s) 5 of 25
Ensure materials being used on the site are environmentally friendly and safe. Responsible
for ensuring that appropriate levels of environmental resources are available to conduct
environmental management functions.
2.3.5 QA/QC Manager
Will ensure that the concrete activities are conducted according to the approved Method
Statement and project contract documents. Will be responsible for the implementation of
this procedure.
Will ensure that the materials being delivered and used are to the project specifications.
Will be responsible for the inspection, preparation of all documents, and compiling them
for inclusion in the final documentation package.
2.3.6 QA-QC Engineer
To execute the tasks following the specified requirements and the corresponding quality
protocols. Reviewing the finished project and seeking approval from the Engineer.
Will be accountable for overseeing the progress and attending inspections at different
stages of the project as well as accurately documenting and reporting the findings.
Implementing a quality control plan to ensure precise and sufficient inspection compliance
with contract documents and promptly taking corrective action in case of any
noncompliance with contract documents.
Document all Quality Control activities, including inspections, and take necessary actions
to rectify any faulty work.
When tests are necessary, the engineer will choose samples at random and send them to
the approved laboratory for testing, as specified in the contract documents.
2.3.7 QC Inspector
QC personnel will ensure that all activities about the concrete works are conducted in strict
adherence to the project specification and approved drawings.
The necessary inspections and testing will be coordinated with the consultant as per the
ITP. The QC personnel is responsible for maintaining and keeping records of all quality
control documents.
The kickoff meeting should be scheduled on-site before or during the construction phase.
This meeting should include all personnel involved in the concrete work, including the
construction management staff.
Ensure the effective implementation of a Quality System and consistently monitor the
overall quality of the work. Perform inspections and oversee testing procedures. Identify
and document any instances of non-conformance, along with suggested corrective
measures.
It is important to inform all staff members about the quality standards that need to be met.
Perform surveillance and inspection tasks at different stages to verify adherence to the
It will be ensured at all times that the earthworks will be carried out under the control of a
competent works supervisor and the assigned supervisor will have extensive experience in
construction works undertaken.
Pre-task briefing to be provided by the relevant site Engineer/Supervisor before the start
of the work activity and to be recorded.
Will explain the Method Statement to his subordinates and be responsible for executing
the works by the method statement.
To ascertain that the work is being carried out as per the instructions of the site engineer
and in conformance with the approved drawings & specs.
Creating a report outlining daily activities or site status. Work necessitates the use of
various machinery and human labor. Ensure levels, and lines, are checked. Supervising
every individual activity.
2.3.9 Material engineer
Inspect arriving materials to ensure they meet the required requirements and perform on-
site testing if needed.
Supervise the storage and management of materials to prevent any harm or deterioration.
Conduct an investigation and resolve any material-related issues or nonconformance
raised during the construction process.
Provide technical assistance and guidance to other construction personnel, contractors,
and engineers in the selection and usage of materials. Ensure precise documentation of
material testing outcomes and inspections.
Engage in concluding inspections and verify that all materials adhere to contractual
specifications. Review of the concrete mix design calculation and participation in batch
plant trials.
Address concrete-related challenges. Review of the material and submission to the client.
Advice for the quality team if the material fails to satisfy the specifications. Choosing the
most suitable materials for specific applications by considering their properties.
2.3.10 Environmental Engineer
Has the authority to stop work immediately if an unacceptable impact on the environment
is occurring or is likely to occur.
Responsible for ensuring the preparation of site-specific environmental and regulatory
documentation and for regular review and improvement of such documentation, as
appropriate.
Where a control measure used to limit environmental harm is found to be inadequate, or a
potential incident is likely, he may request remedial works to be carried out. Ensure that
Directing the movement of vehicles on a work site. Recommending and laying out safe, on-
site traffic systems. Providing clear, correct, and safe directions to equipment operators.
Communicating with drivers and equipment operators verbally or by radio and/or industry-
standard hand signals.
Understanding risks (e.g. blind spots) and how to manage these effectively. Managing
traffic to avoid excessive queuing. Minimizing possible risks to personnel and equipment.
2.3.13 Safety Officer
Safety officer will ensure that all workers and workplaces are safe. All personnel must
adhere to the safety rules and regulations at the site.
A works permit has been issued before commencing the Excavation and Backfilling works.
A hazard identification and control measure has been implemented.
Safety officer will be available in the work area until the work is completed. PPE shall be
worn at all times.
Method statements for all activities shall be in place and discussed with workers. Suitable
access roads for equipment shall be provided by ABCC-Wetico JV.
Before the commencement of any activity, the workforce will receive a safety induction
and toolbox talk on the project site safety requirements.
Suitable access roads for equipment shall be defined and marked with caution boards and
warning signs.
Safety officer and direct supervisor will ensure that PPE (Safety Shoe, Hard Hat, Hand
Gloves, Reflective Waist, Safety Goggles, and Mask) are worn by site personnel at all times
during this activity.
For ready-mix applications (Factory-made products, follow the approved material and the
manufacturer's recommendations for detailed application instructions. The ready-mix
materials must be stored appropriately to safeguard them against moisture.
Mortar will be produced at the construction site using either a portable batch mixer with
weigh batching or a manual mix with volume batching. For greater amounts, it can be
blended in batch facilities.
Utilize mortars, excluding retarded mortars, within a time frame of 2 hours after mixing or
as indicated.
The mortar mix ratio for CMU solid blocks is 1:4 OPC to sand, while for thermal/hollow
blocks it is 1:3 OPC to sand, or as otherwise specified in spec.
Incorporate and mix the mortar in an amount of water that is sufficient to form a tightly
ball in the palm of a man and to allow it to lightly ooze through the fingertips as the hand is
closed demonstrate the consistency of mortar. The testing frequency shall be 1500m² for
block mortar.
3.2.1 Grout
For ready-mix applications, it is important to follow the approved material and the
manufacturer's recommendations for detailed application instructions. This will ensure
that the factory-made product is used correctly and effectively. It is important to store the
ready-mix materials properly to protect them from moisture.
Grout can be produced on-site using either a portable batch mixer with weigh batching or
a manual mix with volume batching. For larger quantities, it can be mixed in batch facilities.
Follow the ASTM C 404 guidelines for the grout aggregate, ensuring that the maximum size
is 5mm and that it passes through sieve #4 with 100%.
The testing frequency for block grout shall be 1500m². The recommended grout mix ratio
for CMU blocks is either 1 part OPC to 1 part sand or 2 parts OPC to sand.
3.3 Handling and storage of material
Material must be stored and utilized according to the manufacturer's instructions. Blocks
and accessories will be transported to the construction site in a stacked manner on a pallet
and unloaded as close as possible to the intended location.
The unloading area should be a clean and solid surface, without any mud or water. Cement
must be stored above ground level, in a dry place, and used in the order it was delivered.
Ensure that metal ties and straps are stored in a covered area to safeguard them from
harm and deformation.
The QA/QC Engineer will be responsible for supervising the receipt of CMU blocks and
conducting the sampling and testing of CMU blocks to ensure they meet project
specifications.
A mock-up of a typical block masonry (3m long and 2m high) will be constructed for each
type of external and internal location to demonstrate the proper fixing of accessories, the
quality of materials, and the execution of work.
Written approval will be obtained through the WIR before proceeding with any further
actual work at the site. The mock-up may become a permanent fixture at the site.
Construct block work within specified tolerances as per specification and approved
drawing.
The surveyor will mark out the arrangement for the block work based on the approved
layout drawings.
When working in a dry and hot climate, it is advisable to moisten masonry units before
laying them down. This helps to prevent the rapid drying and shrinking of cement-based
mortars.
Ensure that the first layer of the block is composed of solid blocks if using hollow blocks
and that it is completely laid out with perfect alignment.
The blocks should be positioned appropriately on a bed of mortar that is filled. Joints are
properly filled and the mortar's joint thickness will vary between 8 and 12 millimeters.
All necessary masonry cutting must be performed using power tools that will provide
precise edges without any chipping or damage to the surfaces.
Concrete slab surfaces must be clean and tidy before beginning block work activities. Make
sure to roughen the concrete surface that will be in direct contact with the block wall.
All block work (Hollow and solid) will be set out and constructed according to the
dimensions, thicknesses, and heights indicated in the approved drawings.
Ensure that the courses are kept level and that the perpendicular lines are aligned
vertically. Ensure that all faces are plumb and corners are properly aligned as the work
progresses.
It is recommended to vertically align every fifth or sixth perpendicular and ensure that the
size of intermediate joints is evenly distributed. It is important to maintain consistent
thickness for the horizontal joints.
Ensure that each course does not exceed the height specified in the contract specifications.
Make sure to carefully rake out the joints on all surfaces that will be plastered or rendered
as the work progresses. This will offer a reliable solution for the coating.
Maintain openings by the drawing and cut units to allow frames, conduit, fixtures, recesses,
and other pieces of mechanical, electrical, and plumbing work within the wall block work.
3.4.3 Blockwork cleaning
As the job progresses, it is advised to clean mortar droplets from masonry surfaces and
surfaces that are adjacent to them with great care. Following the completion of every
portion of the wall block work, surfaces should be cleaned and remedial measures should
be taken where necessary.
3.4.4 Curing
Curing shall be started 24 hours after finishing the blockwork. Ensure that the blockwork
remains adequately moist by regularly spraying water, at least twice a day for at least
three days
Potable Water
Curing compound
Burlap/ cotton mats, rugs
Concrete Masonry unit
Dry Mix Mortar for Masonry
Block Work Accessories like Masonry Reinforcement Ladder/Mesh, Steel lintel, and block
angle
Cement
Dry sand
4.2 Logistics
Nail Gun
Scaffolding Platforms
Line dory
Site Engineer
QC Engineers
Surveyor
Civil foreman
Carpenters
Steel fixers
Mason
Scaffolders
Safety officers
Flagmen
First Aider
Revision 03 DD-SWD-SW-SWD-000-000-DGD-TEM-HS-000001 Date of Issue: March 24 Page No(s) 14 of 25
Laborers
Block Work Mason
Equipment Operator
Familiarize yourself with the Site Emergency contact list, which is posted in various
locations throughout the site.
An Emergency Vehicle must be present on-site at all times during work activities.
There should be a designated First Aider available at the location of work to provide
immediate assistance in case of any medical emergencies.
Trained personnel should be present on-site to handle and manage emergencies
effectively.
Conduct task-oriented toolbox talks for each shift, covering various activities, to ensure
that workers are aware of potential hazards and safety measures.
Strictly enforce the policy of not allowing unauthorized individuals or visitors to enter the
work site without proper induction and personal protective equipment (PPE).
All personnel must receive training on working at heights, handling chemicals, using
respirators, and utilizing special PPE in addition to general safety training.
The work supervisor, area safety personnel, and permit receiver should continually
monitor the health condition of the workforce.
Ensure that access and exit points are never blocked, allowing for safe and efficient
movement throughout the site.
Encourage regular breaks and implement a heat stress program to prevent heat-related
illnesses.
Continuously monitor temperature and humidity levels to assess potential risks and take
appropriate measures to mitigate them.
By adhering to these protocols and guidelines, we can maintain a safe working
environment and effectively respond to any emergencies that may arise.
6 Emergency Preparedness
We have to ensure compliance with the following emergency protocols and guidelines.
Familiarize yourself with the Site Emergency contact list, which is posted in various
locations throughout the site.
An Emergency Vehicle must be present on-site at all times during work activities.
There should be a designated First Aider available at the location of work to provide
immediate assistance in case of any medical emergencies.
The disposal options for CMU block and inert debris are the following.
Propose the material to NCEC/MWAN for reuse in Riyadh regional environmental projects
Propose the material to the Royal Commission for Riyadh City (RCRC) for reuse in Riyadh
regional road projects
Sell the material to the excavation contractor for reuse in local projects (e.g. fill, road base,
aggregates)
Dispose in municipal dumping areas
Sites that will accept material from the Diriyah Gate project are the following
RCRC Projects
NCEC will confirm the preferred site disposal areas
The authorized disposal sites by Amana are the following.
Al Mahdi Dumping area; south Riyadh.
Wadi Laban Dumping area; South Riyadh
CDW – Dugham
Al Sulai Landfill
Al Nadhim Landfill
Wadi Laban Landfill
8 Security Arrangements
Gate permits will be obtained by the prequalified subcontractor for the necessary staff. The
people working on the STP project will be able to acquire vehicle registration and gate pass
services.
9 Document Records
9.1 Risk Assessment
Refer to Appendix A
11 Document Record
Project: DESIGN, BUILD, OPERATION & MAINTAINENCE OF SEWAGE Risk Assessment Ref:
TREATMENT PLANT
Company Name: ABCC-WETICO - JV Date: 06/08/2024
Activity Name: Block works Site Location DIRIYAH STP PROJECT- RIYADH
Risk Rating without
Residual Risk
Sr. No Task Hazards Identified Harm control measures Control Measures Controlled by whom
LXS L M H LXS L M H
Initial Planning Unauthorized work All Permit to Work shall be obtained Engineer/
and to be performed persons as a pre-requisite to perform Supervisor/
Arrangements 4x5 20 Safety Officer
1 within a defined work
location and in work 1x4 4
boundary Work shall not be started until
area. duly approved Permit to Work is
Uncontrolled available at site and that Safety
personnel entering Toolbox meeting was conducted
a restricted
location All workers attending the toolbox
meeting shall sign on the
Unidentified attendance sheet attached to the
hazards with specific Permit to Work
unplanned safety
mitigating A safe work practice shall be
measures implemented to reduce the
possibilities of accident / incident
Inadequate
coordination and Permit Receiver and Permit
area control Issuer shall visit together at the
protocol site to ensure that workplace
hazards are adequately identified
and mitigating measure shall be
established
3 Loading and Persons getting All 4x5 20 Conduct TBT Before Engineer/ 1x3 3
unloading of struck by persons commencing the work. Supervisor/
Concrete blocks suspended load. Safety Officer
in work Lifting equipments should not be
Fall hazard. old than 10 years of age as per
area. DC requirements.
Not complying
with safe lifting. All lifting equipments should be
third party certified along with
Crane collapse/ operators.
Equipment issues .
All lifting equipments should
Miscommunication have valid three months SASO
between the approved inspection record as
operator and the per DC procedures.
worker
Insure proper illumination
Falling of loads installed on the site area if work
in night shift.
Incompetent
operator/rigger Wear suitable PPE.
Fuel leaks and fire All 3x4 12 Engine to be turned off before Engineer/ 1x3 3
hazards persons refueling Supervisor/
Safety Officer
in work Keep suitable fire extinguisher on
machine and must be regularly
area. checked and provided with
inspection tagged and color code.
4 Work at height. Slip, trip & fall All 4x5 20 Only competent scaffolder can Engineer/ 1x3 3
persons erect the scaffolding. Supervisor/
Fall from height Safety Officer
5 Installation of Slip, trip and fall All 4x4 16 Provide approved rams & signed Engineer/ 1x3 3
concrete blocks persons PTW. Supervisor/
Falling from height Safety Officer
in work Insure proper illumination
Collapse of installed on the site if working in
scaffolding area. night shift.
6 Hand Inappropriate use All 4x5 20 Use quality tools in accordance Engineer/ 1x3 3
Tools/Power of the tools. person in with the type of work to carry Supervisor/
Tools the area out. Safety Officer
Use of faulty or
inappropriate tools. Approved MSRA communication
with workers and ensure the
Use of poor- implementations.
quality tools.
Do not use wet tools
Not using personal
protection Get a permit before starting the
equipment. work.
7 Manual Improper manual All 4x4 16 When handling heavy or oversize Engineer/ Supervisor/ Safety 1x3 3
handling person in loads, mechanical lifting Officer
Handling/ Lone
techniques the area equipment is to be used (trolleys,
8 Welfare Facility Poor Hygiene. All 4x4 16 An adequate number of toilets Supervising Engineer, 1x3 3
persons will be provided as required.
Environmental Foreman,
pollution in work Ensure mess hall at site with
sufficient space for utilize in Site Supervisor,
Poor and area. break time. The facilities will
HSE Supervisor
inadequate welfare provide shelter from the sun wind
facilities and rain. Site offices or huts can
make a suitable rest area.
Increased stress of
employees An ample Supply of drinking
water will be provided.
Heat stress
Whenever possible it will be
supplied direct from the mains
otherwise bottles or tanks of
9 Housekeeping, Manual handling All 3x4 12 Facilitate training for manual Engineer/ 1x3 3
clearing the area persons handling. Supervisor/
with all used Materials lying on Safety Officer
the ground in work Observe proper posture during Foremen
materials, tools
and equipment manual lifting, pushing, pulling,
Protruding object / area. etc.
and brought to
materials at the site
the designated
All materials and equipments
storage and
Uncollected / must be in the designated area
disposal area
scattered rubbish after finishing work.
10 Emergency Poor emergency All 4x4 16 Follow the emergency protocols Supervising Engineer, 1x3 3
response: response persons and Site Emergency contact list
posted on different location. Foreman,
Worsening the in work
incident if not Emergency Vehicle must be on- Site Supervisor,
dealt on time area. site all the time during the work
HSE Supervisor
activity.
Unforeseeable
situation First aider is available at the
location of work.
No unauthorized personal or
visitor permitted to enter work-
site without proper induction and
PPEs .
Likelihood (L)
Possible - 2 Minor - 2 High Risk 8 - 12 4 4 8 12 16 20
Likely - 3 Moderate - 3 Moderate Risk 4 - 6 3 3 6 9 12 15
Often - 4 Major - 4 Low Risk 1 - 3 2 2 4 6 8 10
Frequent/Almost certain - 5 Catastrophic - 5 1 1 2 3 4 5
1 2 3 4 5
Subcontractor Approval of
Project specification - Once prior to DG-PIN-000-0000-PRS-TEM-
1.5 prequalification Review of document R Subcontractor Site Engr. & QCI H H R P P N/A
R02 start QL-000010
prequalification
Approval of Third-
Third-party party
Project specification - Once prior to DG-PIN-000-0000-PRS-TEM-
1.6 inspecting/testing agency Review of document R inspecting/testing Site Engr. & QCI H H R P P N/A
R02 start QL-000010
prequalification agency
prequalification
Project specification R2
MAR - CMU Block and Once prior to MAR: SW-SWD-550-0000-
1.7 Review of document R - Section 042000 - Part2 Approved MAR Site Engr. & QCI H H R P P N/A
mortar start MAC-TEM-QL-000005
- Product(2.1)
Project specification R2
Once prior to MAR: SW-SWD-550-0000-
1.8 MAR - Block accessories Review of document R - Section 042000 - Part2 Approved MAR Site Engr. & QCI H H R P P N/A
start MAC-TEM-QL-000005
- 2.3, 2.4, 2.5 and 2.7
2.0 Construction
2.1 Block work ( Hollow, solid )
Approved Work inspection
Request: SW-SWD-550-0000-
Location and level
Survey Inspection and Approved shop drawing Once prior to MAC-TEM-QL-000002,
2.1.1 Survey setting out I as per approved Site surveyor & QCI H H H P P N/A
verification of level and project specification start Approved Survey Report: (DG-
drawing
ABCC-Wetico JV-QMS-FO-
0028)
Usage of mortar
should be the
approved mortar
mix. Prepared
mortar
shall be consumed
within initial setting
Method statement, and
time. All the blocks
approved shop drawing.
and substrates Every Approved Work inspection
Block work laying first Project specification R2
2.1.4 Visual Inspection I should be wetted Prepared Site Engr. & QCI H H W P P N/A Request: SW-SWD-550-0000-
layer with mortar mixing - Section 042000 - Part3
prior to installations, Area MAC-TEM-QL-000002,
- Execution(3.1, 3.2 and
walls should be
3.3)
constructed as true
planes and to the
lines and
dimensions as
indicated on the
approved drawings
and tolerances.
Horizontal
Method statement, and alignment: +/-
approved shop drawing. 3mm in 3.0m
Every Approved Work inspection
Block work laying Project specification R2 checked with a
2.1.5 Visual Inspection I Prepared Site Engr. & QCI H H W P P N/A Request: SW-SWD-550-0000-
succeeding rows - Section 042000 - Part3 straight edge
Area MAC-TEM-QL-000002.
- Execution(3.1, 3.2 and Vertical alignment
3.3) +/- 3mm checked
with plumb.
One Ladder/truss in
Method Statement and
Installation of horizontal every 900mm (Four Every Approved Work inspection
Project Spec R02 -
2.1.6 reinforcement, VerticaI Visual Inspection I layers of blockwork). Prepared Site Engr. & QCI H H W P P N/A Request: SW-SWD-550-0000-
Section 042000( 3.3, 3.4
Dowels One Dowel in every Area MAC-TEM-QL-000002,
and 3.5))
600mm
One Anchor on
Method Statement and every other Row on
Anchors (L-Shaped ) and Every Approved Work inspection
Project Spec R02 - each
2.1.7 Reinforcing Rod Visual Inspection I Prepared Site Engr. & QCI H H W P P N/A Request: SW-SWD-550-0000-
Section 042000( 3.3, 3.4 side.Reinforcing rod
Reinforcement Area MAC-TEM-QL-000002,
and 3.5)) on openings grater
than 300mm
When ambient
temperature
exceeds 38 deg C,
do not spread mortar
Method Statement and As per
Protection against beds more than Checklist - Form No: AWJ-ITP-
2.1.8 Visual Inspection I Project Spec R02 - inspection Site Engr. & QCI H H W P P N/A
Ambient Conditions 1200 mm ahead of CE-000012-F01
Section 042000(1.5) request
masonry. Set
masonry units within
one minute of
spreading mortar.
Minimum intensity is
to be 1.1 Kg/m2.
Metal lath shall be
prefabricated in coil
form. Width of lath
is to be 50 mm less
than nominal width
of wall with uniform
Method Statement and
25 mm recess from Every
Joint Width and Control Project Spec R02 - Checklist - Form No: AWJ-ITP-
2.1.9 Visual Inspection I wall face at both Prepared Site Engr. & QCI H H W P P N/A
Joints Section 042000( CE-000012-F01
sides. Form control Area
2.7,3.3,)
joints in concrete
masonry as follows:
1. Install
preformed control-
joint gaskets
designed to fit
standard sash block.
Every 5000-
Compliance to Block 10000 No. of
method statement and
compressive Blocks or
Project spec Section
strength, Weight one sample DG-PIN-000-0000-PRS-TEM-
2.1.11 QC tests: for CMU block Testing T 042000 and clause 3.2, Site Engr. & QCI H H H P P N/A
classification ,water per 10 of QL-000011
ASTMC90, 129 and
absorption and fire Block
ASTME-119
resisting as per MTC Delivery
trucks
General Comments:
Blockwork Checklist
ITP Reference No. : DG-PIN-456-0000-AWJ-ITP-CE-000012
Form No: AWJ-ITP-CE-000012-F01 Rev.00 Page: 1 of 1
BWJV QC - CSC -
Description of Work Inspector/Engineer Inspector/Engineer Remarks
YES / NO / NA YES / NO / NA
CSC - Inspector/Engineer
BWJV Construction team
Name
Signature
Date/Time