0% found this document useful (0 votes)
11 views158 pages

VO New file all

The document outlines the construction project for Prithvi Narayan Secondary School in Kathmandu, detailing the contract effective date, donor agency, and completion date. It includes financial information such as original and revised cost estimates, contract amounts, and variations in costs due to changes in project scope. The document also lists specific construction items and their respective costs, highlighting adjustments made throughout the project.

Uploaded by

kanchan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views158 pages

VO New file all

The document outlines the construction project for Prithvi Narayan Secondary School in Kathmandu, detailing the contract effective date, donor agency, and completion date. It includes financial information such as original and revised cost estimates, contract amounts, and variations in costs due to changes in project scope. The document also lists specific construction items and their respective costs, highlighting adjustments made throughout the project.

Uploaded by

kanchan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 158

Government of Nepal

Shree Prithvi Narayan Secondary School


Construction of Different Buildings of School
Tarakeshwar-5, Kathmandu
Name of the Project: Construction and Extension of Prithvi Narayan School Contract Effective Date: 2019
Donor Agency: Um Hong Gill Foundation, South Korea Completion Date:
Contract ID: 01-2075/076 PNSS New Completion date up to this variation: 30th Sep. 2023
Name of Contractor:- Religare construction Pvt. Ltd. [+/-] in estimate wrt original with VAT & PS cost in NRs: (13,833,295.44)
Original Cost estimate with VAT & PS Nrs: 192,890,060.49 percentage increase or decrease in estimate wrt original estimate: -7.17%
Original Contract Amount with VAT & PS Nrs: 162,644,356.67 Revised Contract amount after this variration with VAT & PS in NRs: 155,465,903.64
Revise cost estimate (till date)with VAT & PS Nrs: 179,056,765.05 [+/-] in amount after this variration wrt original contract with VAT & PS cost in NRs: (7,178,453.03)
Actual Expenditure till Date without discount Nrs: 155,465,903.64 Percentage increase or decrease in VO. 01 wrt original contract: -4.41%
Discount offered by Contractor 2.00%

TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity

GENERAL WORK, SITE


CLEARANCE: Clearing and
grubbing of site for construction
including uprooting of vegetation,
1 1.1 Estimated less in original
grass, brush wood, trees and Sq.M 2349.73 19.07 44,809.35 5382.47 19.07 102,643.70 57,834.35 1.29 100.00 234,973.00 100.00 538,247.00 3,032.74 1.29 303,274.00 1.29
estimate
sapplings of girth upto 300 mm &
removal upto a distance of 50 m as
per drawings, specifications and
instructions
EARTHWORK IN EXCAVATION:
Earthwork in excavation in
trenches, pits and foundations by
machine or appropriate technology
in soft soil including existing debris
and brick bats of old structure, if
any, upto specified depth including
shoring, dressing of sides, Due to sitte condition under
2 2.1 Cu.M 8330.15 119.39 994,536.61 10526.71 119.39 1,256,783.43 262,246.82 0.26 200.00 1,666,030.00 200.00 2,105,341.20 2,196.56 0.26 439,311.20 0.26
mechanical ramming of bottom, estimated
dewatering in foundation pits and
trenches, if required, lifting of soil
for minimum 3.5 m and stacking soil
to minimum height of 1m and lead
upto 30m, all complete as per
drawings, specifications and
nstructions
EARTWORK IN FILLING:
Providing and placing of random
filling of excavated earth from
cutting of slope and stacked at site
in 150mm thick layer in trenches,
plinth or under floor, sides of
3 2.2 foundation and below beam at Cu.M 6861.05 351.55 2,412,002.13 5179.42 351.55 1,820,823.87 (591,178.26) (0.25) 200.00 1,372,210.00 200.00 1,035,883.30 (1,681.63) (0.25) (336,326.70) (0.25) Due to site condition
footing covered area etc. including
watering, mechanical ramming and
compaction of each layer,
consolidation and dressing, all
complete as per drawings,
specifications and instructions.
SAND FILLING: Sand filling in
plinth under floors, including
watering, ramming, consolidating
4 2.3 Cu.M 130.42 4,630.34 603,888.94 0.00 4,630.34 - (603,888.94) (1.00) 2,500.00 326,050.00 2,500.00 - (130.42) (1.00) (326,050.00) (1.00) Not necessary in site
and dressing, all complete as per
drawings, specifications and
instructions.
STONE WORK : Dry stone soling
work in line and level, including
5 3.1 packing joints with sand dust, all Cu.M 475.74 9,806.28 4,665,239.65 241.03 9,806.28 2,363,607.67 (2,301,631.98) (0.49) 4,000.00 1,902,960.00 4,000.00 964,120.00 (234.71) (0.49) (938,840.00) (0.49)
complete as per drawings,
specifications and instructions
STONE MASONRY WALL: Stone
rubble masonry work in 1:4
cement and sand mortar with hard,
tough, sound and durable stone in
wall, made to required line, level,
6 3.2 Cu.M 1304.60 13,468.69 17,571,252.97 1193.39 13,468.69 16,073,413.43 (1,497,839.55) (0.09) 7,500.00 9,784,500.00 7,500.00 8,950,432.50 (111.21) (0.09) (834,067.50) (0.09)
shape, size and plumb including
setting out, drain outlet, curing of
the works and scaffolding etc.
complete as per drawings,
specifications and instructions
BRICK WORK,FLAT BRICK
SOLING: Flat brick soling of local
chimney bricks laid in line and level,
7 4.1 Sq.M 4183.83 1,096.50 4,587,569.60 3090.64 1,096.50 3,388,886.76 (1,198,682.83) (0.26) 800.00 3,347,064.00 800.00 2,472,512.00 (1,093.19) (0.26) (874,552.00) (0.26)
including packing joints with sand,
complete as per drawings,
specifications and instructions
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
FULL BRICK WORK: Brickwork
in substructure and super
structure cement and sand mortar
of mix 1:6 with first class chimney-
made bricks, in any size and shape
8 4.2 of wall, made to required line, level, Cu.M 262.93 15,132.90 3,978,893.40 426.21 15,132.90 6,449,793.31 2,470,899.91 15,000.00 3,943,950.00 15,000.00 6,393,150.00 163.28 0.62 2,449,200.00 0.62 Quantity under estimated
shape and plumb including setting
out, soaking of bricks, curing of the
works and scaffolding, etc.
complete as per drawings,
specifications and instructions.
AAC(Autoclaved Aerated
Concrete) BLOCK WORK:
Providing and laying of Autoclaved
Aerated Concrete Block
(600*200*200 ) work made with
cement mortar 1:4 (1 cement: 4
9 5.1 Sq.M 3152.07 2,936.76 9,256,873.09 2076.24 2,936.76 6,097,418.58 (3,159,454.51) (0.34) 1,800.00 5,673,726.00 1,800.00 3,737,232.00 (1,075.83) (0.34) (1,936,494.00) (0.34)
coarse sand) of any size and
shape, made to required line, level,
shape and plumb including setting
out, cutting of block and scaffolding,
etc. complete as per drawings,
specifications and instructions.
Providing and laying of Autoclaved
Aerated Concrete Block
(600*200*100 ) work made with
cement mortar 1:4 (1 cement: 4
coarse sand) of any size and
10 5.2 Sq.M 328.60 1,977.36 649,760.50 142.28 1,977.36 281,338.78 (368,421.72) (0.57) 2,000.00 657,200.00 2,000.00 284,560.00 (186.32) (0.57) (372,640.00) (0.57)
shape, made to required line, level,
shape and plumb including setting
out, cutting of block and scaffolding,
etc. complete as per drawings,
specifications and instructions.
Providing and laying of Autoclaved
Aerated Concrete Block
(600*200*150 ) work made with
cement mortar 1:4 (1 cement: 4
coarse sand) of any size and
11 5.3 Sq.M 104.90 2,445.36 256,518.26 31.17 2,445.36 76,221.87 (180,296.39) (0.70) 1,100.00 115,390.00 1,100.00 34,287.00 (73.73) (0.70) (81,103.00) (0.70)
shape, made to required line, level,
shape and plumb including setting
out, cutting of block and scaffolding,
etc. complete as per drawings,
specifications and instructions.
CONCRETE WORK,PCC OF
GRADE M10: Plain cement
concrete (PCC) of grade M10 (1:3:6
with 1 cement, 3 coarse sand and 6
aggregate of 19 mm and down
12 6.1 Cu.M 404.74 13,235.40 5,356,895.80 374.38 13,235.40 4,955,128.61 (401,767.18) (0.08) 10,000.00 4,047,400.00 10,000.00 3,743,845.00 (30.36) (0.08) (303,555.00) (0.08)
grade) in foundation base including
mixing, laying, compacting,
finishing, curing, laid to exact line,
level and dimensions, inclusive
ofside
PCC FOR RCC OF GRADE M25:
Structural concrete (PCC for RCC)
of Grade M25 (1:1:2)works with
approved quality of cement, sand
and well graded aggregate in any
form, size, shape and level Column and Shear wall of
13 6.2 Cu.M 183.26 20,696.16 3,792,778.28 301.15 20,696.16 6,232,648.58 2,439,870.30 - 20,000.00 3,665,200.00 20,000.00 6,023,000.00 117.89 0.64 2,357,800.00 0.64 secondary is calculated M20
including batching and mixing with but in Site M25 is done
machine, laying including
compaction with vibrating machine,
curing, testing and finishing, all
complete as per drawings,
specifications and instructions.
PCC FOR RCC OF GRADE M20:
Structural concrete (PCC for RCC)
of Grade M20 (1:1.5:3)works with
approved quality of cement, sand
and well graded aggregate in any
form, size, shape and level
14 6.3 Cu.M 1311.72 16,637.06 21,823,164.34 1141.77 16,637.06 18,995,696.00 (2,827,468.35) (0.13) 17,000.00 22,299,240.00 17,000.00 19,410,090.00 (169.95) (0.13) (2,889,150.00) (0.13)
including batching and mixing with
machine, laying including
compaction with vibrating machine,
curing, testing and finishing, all
complete as per drawings,
specifications and instructions.
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
FORMWORK: Placing Plyboard
form work with steel props,
shuttering, centering in
horizontal/Vertical surfaces like
15 7.1 Sq.M 10157.67 852.35 8,657,890.02 9904.13 852.35 8,441,785.21 (216,104.82) (0.02) 850.00 8,634,019.50 850.00 8,418,510.50 (253.54) (0.02) (215,509.00) (0.02)
slab, beams, column, wall, stair etc.
for all RCC works of any shape,
size and at any level and removal
after completion
REINFORCEMENT WORK:
Providing and placing steel
reinforcement bar tested grade Fe-
for different section same
500 equivalent NS, for RCC work detailing of rebar leads to
16 8.1 kg 167554.30 137.58 23,052,120.59 217600.27 137.58 29,937,445.50 6,885,324.91 0.30 110.00 18,430,973.00 110.00 23,936,029.99 50,045.97 0.30 5,505,056.99 0.30
including bending, binding with over-reinforced. Estimated
anneal wire and placing in position, as percentage
all complete as per drawings,
specifications and instruction
FLOORING WORK,PLASTIC
LAYING: Supplying and laying 500
17 9.1 gauge plastic sheet in floor as per Sq.M 1891.01 153.76 290,761.70 0.00 153.76 - (290,761.70) (1.00) 50.00 94,550.50 50.00 - (1,891.01) (1.00) (94,550.50) (1.00)
specificatio and instruction
SCREEDING: Providing and
placing 38 mm thick Plain cement
concrete of grade M15 (1:2:4 with 1
cement, 2 coarse sand and 4
aggregate chips) in the floor base
mixing, laying, compacting,
18 9.2 finishing, curing, laid to exact line Sq.M 4030.24 709.02 2,857,520.76 3661.87 709.02 2,596,342.61 (261,178.15) (0.09) 500.00 2,015,120.00 500.00 1,830,937.50 (368.37) (0.09) (184,182.50) (0.09)
level , surface chipping and
dimensions (floor concrete is laid in
alternate panels of 1 m x 1 m)
inclusive of shuttering complete as
per drawings, specifications and
instructions
CEMENT PUNNING: Providing
and laying 3 mm cement punning in
19 9.3 Sq.M 3900.06 281.47 1,097,749.89 2171.78 281.47 611,290.92 (486,458.97) (0.44) 200.00 780,012.00 200.00 434,356.00 (1,728.28) (0.44) (345,656.00) (0.44)
floor , laying in required pattern, line

CEMENT SKIRTING: Providing


and placing cement skirting 125mm
height of grade M15 (1:2:4 with
cement, 2 coarse sand and 4
aggregate
20 9.4 ) in wall ,mixing, laying, compactig, R.M 1646.42 90.09 148,325.98 1685.21 90.09 151,820.57 3,494.59 0.02 100.00 164,642.00 100.00 168,521.00 38.79 0.02 3,879.00 0.02
finishing, curing, laid to exact line
level and dimension all complete as
per drawing, specification and
instructions
TILE LAYING ON FLOOR:
Providing and laying approved
brand quality, pattern and color,
ceramic mat finish tile (Low range)
21 9.5 on floor over cement mortar of mix Sq.M quantity estimate is under
37.40 3,338.80 124,871.12 155.15 3,338.80 518,014.82 393,143.70 3.15 2,800.00 104,720.00 2,800.00 434,420.00 117.75 3.15 329,700.00 3.15
evaluated
1:3 backing and filling joints (epoxy
grout) complete as per drawings,
specifications and instructions.
(Base rate: NRs 100)
TILE LAYING ON TOILET:
Providing and laying approved
brand quality, pattern and color,
ceramic glazed tile in wall and
ceramic mat finish tile (Low range)
22 9.6 on floor of toilet over cement mortar Sq.M 643.01 3,338.80 2,146,881.79 383.75 3,338.80 1,281,264.50 (865,617.29) (0.40) 3,000.00 1,929,030.00 3,000.00 1,151,250.00 (259.26) (0.40) (777,780.00) (0.40)
of mix 1:3 backing and filling joints
(epoxy grout) complete as per
drawings, specifications and
instructions.(Base rate: NRs 100)
FINISHING WORK,
EXTERNAL PLASTER: Providing
and applying '10.5 mm thick cement
plastering with 1cement : 4 sand
mortar in outer surface any level
size and shape of wall, column,
ceiling, band, blocks, etc inclusive
23 10.1 of waterproofing compound, Sq.M 3951.29 469.50 1,855,130.66 3439.56 469.50 1,614,871.54 (240,259.11) (0.13) 400.00 1,580,516.00 400.00 1,375,822.40 (511.73) (0.13) (204,693.60) (0.13)
dusting, throating, etc as required
including racking, hacking,
watering, cleaning of base,
plastering to plumb, line, level,
smooth etc. and curing complete as
per drawings, specifications and
instructions.
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
INTERNAL PLASTER:
Providing and applying'10.5 mm
thick cement plastering with
1cement : 4 sand mortar in inner
surface except ceiling any level size
and shape of wall, column, band,
24 10.2 blocks, etc inclusive of dusting, Sq.M 5990.67 407.17 2,439,221.10 5071.26 407.17 2,064,864.93 (374,356.17) (0.15) 450.00 2,695,801.50 450.00 2,282,067.00 (919.41) (0.15) (413,734.50) (0.15)
throating, etc as required including
racking, watering, hacking, cleaning
of base, plastering to plumb, line,
level, smooth etc. and curing, all
complete as per drawings,
specifications and instructions.
CEILING PLASTER: Providing
and applying 12.5 mm thick cement
plastering with 1cement : 4 sand
25 10.3 mortar in Ceiling any level size and Sq.M 2423.84 469.50 1,137,992.88 3621.41 469.50 1,700,252.00 562,259.12 0.49 500.00 1,211,920.00 500.00 1,810,705.00 1,197.57 0.49 598,785.00 0.49
shape of ceiling inclusive of
dusting,
PLASTER ON RCC LINTEL
WITH CORNICE: 'Providing and
applying 12.5 mm thick cement
plastering with 1cement : 4 sand
mortar in RCC Lintel with cornice
inclusive of dusting, throating, etc
26 10.4 as required including racking, R.M 83.36 390.88 32,583.76 20.10 390.88 7,856.69 (24,727.07) (0.76) 3,000.00 250,080.00 3,000.00 60,300.00 (63.26) (0.76) (189,780.00) (0.76)
watering, cleaning of base,
plastering to plumb, line, level,
smooth etc. and curing, all
complete as per drawings,
specifications and instructions.
EMULSION PAINT: Providing
and applyibg two coat of emulsion
paint in mat finishing over two coat
27 10.5 of primer, finished including surface Sq.M 8316.81 316.15 2,629,359.48 8381.15 316.15 2,649,699.78 20,340.30 0.01 200.00 1,663,362.00 200.00 1,676,229.50 64.34 0.01 12,867.50 0.01
preparation all complete as per
drawings, specifications and
instruction
WEATHER COAT: Providing and
applying two coat of weather coat
(Apex or equivalent) over required
28 10.6 coat of primer, finished including Sq.M 3951.29 337.64 1,334,113.56 3124.38 337.64 1,054,916.84 (279,196.71) (0.21) 250.00 987,822.50 250.00 781,095.88 (826.91) (0.21) (206,726.62) (0.21)
surface preparation all complete as
per drawings, specifications and
instruction
DOOR,WINDOWS WORK/UPVC
SLIDING
WINDOWS: Providing and fixing
standard UPVC sliding window
without net (frame 50x80mm, sash
29 11.1 58x36mm white colour with 5mm Sq.M Change on site requirement
686.83 6,664.00 4,577,035.12 724.58 6,664.00 4,828,614.45 251,579.33 0.05 8,000.00 5,494,640.00 8,000.00 5,796,656.00 37.75 0.05 302,016.00 0.05
and under estimated
glass) along with patented standard
hardwares like roller, gaskets,
brush seal, moon locks etc all
complete as per drawings and
specifications.
UPVC TOP HUNG
WINDOWS: Providing and fixing
standard UPVC top hung window
(frame 60x60 mm, sash 60x104
mm, white colour with 5 mm glass)
30 11.2 along with patented standard Sq.M 84.22 7,493.00 631,060.46 60.60 7,493.00 454,075.80 (176,984.66) (0.28) 8,000.00 673,760.00 8,000.00 484,800.00 (23.62) (0.28) (188,960.00) (0.28)
hardwares like roller, gaskets,
brush seal, moon locks etc all
complete as per drawings and
specifications.
UPVC DOUBLE DOOR:
Providing and fixing standard UPVC
double door (frame 60x60mm, sash
60x104mm white colour with 5mm
31 11.3 glass) along with patented standard Sq.M Change on site requirement
203.34 8,884.00 1,806,472.56 255.30 8,884.00 2,268,085.20 461,612.64 0.26 10,000.00 2,033,400.00 10,000.00 2,553,000.00 51.96 0.26 519,600.00 0.26
and under estimated
hardwares like roller, gaskets,
brush seal, moon locks etc all
complete as per drawings and
specifications.
UPVC SINGLE DOOR:
Providing and fixing standard UPVC
single door with full panel
(frame60x60mm, sash 60x104mm
32 11.4 white colour with 5mm glass) along Sq.M 107.89 8,328.00 898,507.92 81.86 8,328.00 681,730.08 (216,777.84) (0.24) 7,000.00 755,230.00 7,000.00 573,020.00 (26.03) (0.24) (182,210.00) (0.24)
with patented standard hardwares
like roller, gaskets, brush seal,
moon locks etc all complete as per
drawings and specifications.
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
ROOFING WORK,CGI ROOFING
SHEET: Providing and fixing in
position 24 gauge (0 .50 mm thick)
corrugated CGI sheet over roof
truss with minimum 80 mm side
33 12.1 Sq.M 2610.00 1,333.57 3,480,617.70 0.00 1,333.57 - (3,480,617.70) (1.00) 800.00 2,088,000.00 800.00 - (2,610.00) (1.00) (2,088,000.00) (1.00)
laps and 200 mm end laps,
inclusive of nuts and bolts, 8 mm 'J'
hooks, washers, GI cup washers,
all complete as per drawings,
specifications and instruction
CGI ROOFING SHEET ON RIDGE:
Providing and fixing in position 24
gauge (0 .50 mm thick) CGI sheet
over roof truss in ridge with
34 12.2 minimum 80 mm side laps and 200 R.m 186.37 736.97 137,349.10 0.00 736.97 - (137,349.10) (1.00) 600.00 111,822.00 600.00 - (186.37) (1.00) (111,822.00) (1.00)
mm end laps, inclusive of nuts and
bolts, washers, GI cup washers, all
complete as per drawings,
specifications and instruction
GI GUTTER: providing and fixing in
position color plain GI sheet for
gutter 150mmX450mm, inclusive of
35 12.3 R.m 392.56 1,444.38 567,005.81 314.26 1,444.38 453,910.86 (113,094.95) (0.20) 1,000.00 392,560.00 1,000.00 314,260.00 (78.30) (0.20) (78,300.00) (0.20)
nuts and bolts, washers, all
complete as per drawings,
specifications and instruction.
FALSE CEILING WORK,PVC
BOARD: Providing and fixing
suspended PVC board false ceiling,
with necessary provisions for light
36 13.1 fittings, light boxes, where required Sq.M 1434.15 1,027.04 1,472,929.42 1012.62 1,027.04 1,040,001.24 (432,928.17) (0.29) 1,600.00 2,294,640.00 1,500.00 1,518,930.00 (421.53) (0.29) (775,710.00) (0.34)
finally finished with two coat acrylic
emulsion paint, all complete as per
drawings, specifications and
instructions.
MISCELLANEOUS WORK,
WATER PROOFING: Providing and
placing 20 mm thick cement sand
mortar (1:2) mixing with wate proof
compound in the floor base
37 14.1 mixing, laying, compacting, Sq.M 1336.51 538.68 719,951.21 260.88 538.68 140,528.15 (579,423.06) (0.80) 400.00 534,604.00 400.00 104,350.00 (1,075.64) (0.80) (430,254.00) (0.80)
finishing, curing, laid to exact line
level and dimensions complete as
per drawings, specifications and
instructions
INSULATION WORK:
Providing and installing Insulation
under CGI roofing sheet with
38 14.2 Insulation shield of 12mm thickness Sq.m 1624.71 631.35 1,025,760.66 1235.77 631.35 780,203.39 (245,557.27) (0.24) 200.00 324,942.00 200.00 247,154.00 (388.94) (0.24) (77,788.00) (0.24)
one sided and chicken wire mesh
all completeas per drawing and
specifications.
METAL WORKS,BLACK
TUBULAR PIPE: Supplying,
39 15.1 fabricating and fixing black pipe Kg 44989.57 166.52 7,491,663.20 31428.54 166.52 5,233,480.48 (2,258,182.72) (0.30) 150.00 6,748,435.50 150.00 4,714,281.00 (13,561.03) (0.30) (2,034,154.50) (0.30)
(Square or circular) work /Truss
with
MS PIPE: Supplying, fabricating
and fixing metal work of different
40 15.2 angles MS Pipe with one coat Kg 5936.66 168.22 998,664.95 6920.24 168.22 1,164,122.77 165,457.83 0.17 150.00 890,499.00 150.00 1,038,036.00 983.58 0.17 147,537.00 0.17
primer as shown in drawing all
complete
ROLLING SHUTTER:
Providing and fixing rolling shutterof
16-19 Gauge cold rolled MS lathe
interlocked throughout their entire
length and joined together at the
end by end locks and mounted on
41 15.3 specially designed pipe shaft with Sq.m 50.78 3,443.20 174,845.70 50.77 3,443.20 174,811.26 (34.43) (0.00) 4,000.00 203,120.00 4,000.00 203,080.00 (0.01) (0.00) (40.00) (0.00)
brackets, side guides and
arrangements for inside and outside
locking,with push and pull
operation, complete supplying,
fixing and painting with two coats of
approved plastic emulsion paint.
HOT ROLLED STEEL
SECTION: Supplying, fabricating
and fixing metal work of different
42 15.4 Hot Rolled Steel sections with one Kg 31317.53 168.22 5,268,234.90 0.00 168.22 - (5,268,234.90) (1.00) 150.00 4,697,629.50 150.00 - (31,317.53) (1.00) (4,697,629.50) (1.00)
coat primer as per drawings and
specifications all complete
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
METAL WORK,METAL
GATE: Supplying, fabricating and
fixing in position, metal gates of
standard sections consisting of
43 15.5 angles, pipes, flats,etc. including Sq.M 9.60 7,209.20 69,208.32 11.96 7,209.20 86,222.03 17,013.71 0.25 7,000.00 67,200.00 7,000.00 83,720.00 2.36 0.25 16,520.00 0.25
one coat primer and one coat
enamel paint as per drawings,
specifications and instructions all
complete
FENCING WORK: Providing and
fixing of ISA 50x50x5 mm along
with 25x25x5 flat and M8x40 bolts
44 12.3 at 300mm spacing to fix 10 R.M 446.40 2,123.77 948,050.93 190.00 2,123.77 403,516.30 (544,534.63) (0.57) 2,200.00 982,080.00 2,200.00 418,000.00 (256.40) (0.57) (564,080.00) (0.57)
S.W.G.G.I chain link with hole size
60x60 mm upto 3m height and 3
lines of barbed wire at top.
EXPANSION JOINT
WORKS/PLINTH LEVEL: Suuply
and fixing of expansion joint at level
of 100% non porous flexible
element allowing movement in all
45 16.1 directions, supported by aluminium R.M 28.05 18,040.00 506,022.00 10.68 18,040.00 192,577.00 (313,445.00) (0.62) 4,500.00 126,225.00 4,500.00 48,037.50 (17.38) (0.62) (78,187.50) (0.62)
framing and covering the top by
aluminium sheet and flused to
required floor level all complete as
per drawing, specification and
instruction.
EXPANSION JOINT
WORKS/SLAB: Supply and fixing
of expansion joint at floor level of
aluminium base supported by
alumunium framing,fixed on one
46 16.2 side by threaded screw and flushed R.M 8.55 10,490.00 89,689.50 29.70 10,490.00 311,553.00 221,863.50 2.47 4,500.00 38,475.00 4,500.00 133,650.00 21.15 2.47 95,175.00 2.47 Under estimated
to required floor level and
dimension all complete as per
drawing,specification and
instruction
EXPANSION JOINT
WORKS/ENDS OF WALL: Supply
and fixing of expansion joint atwall
of aluminium base supported by
alumunium framing,fixed on one under estimated on two face
47 16.3 R.M 59.40 7,540.00 447,876.00 114.05 7,540.00 859,937.00 412,061.00 0.92 4,500.00 267,300.00 4,500.00 513,225.00 54.65 0.92 245,925.00 0.92 only but required on four
side by threaded screw and flushed faces
to required wall level and dimension
all complete as per
drawing,specification and
instruction.
CHAIN LINK VENTILATION
WORK: Supplying, fabricating and
fixing in position of 10 S.W.G.I.
woven wire ventilation with hollow
square pipe framing of size
48 17.1 18x18x1.0 mm on all sides with Sq.M 67.29 484.72 32,616.81 0.00 484.72 - (32,616.81) (1.00) 4,000.00 269,160.00 4,000.00 - (67.29) (1.00) (269,160.00) (1.00)
proper welding on site, including
one coat primer and one coat
enamel paint on frames as per
drawings, specifications and
instructions all complete
LAND DEVELOPMENT WORKS,
INTERLOCKING
BLOCKS: Supplying and laying of
60 mm thick heavy duty interlocking
paving blocks of approved colour
49 18.1 and quality on the 50 mm thick Sq.M 293.94 2,035.40 598,285.48 280.84 2,035.40 571,621.74 (26,663.74) (0.04) 2,000.00 587,880.00 2,000.00 561,680.00 (13.10) (0.04) (26,200.00) (0.04)
stone dust with surface grading,
levelling and soil compaction base
in driveways and parking areas,
complete as per specifications and
drawings.
RAILING WORKS: Supply,
fabrication and fitting of Railing
works with MS square pipe framing
and 10 S.W.G.I. wire mesh of
50 18.2 height 1.05m including excavation, R.M 123.98 3,744.44 464,235.67 0.00 3,744.44 - (464,235.67) (1.00) 3,000.00 371,940.00 3,000.00 - (123.98) (1.00) (371,940.00) (1.00)
brickwork, plaster and two coats
enamel paint all complete as per
drawings and specifications
GUIDE RAMP: Supply,
fabrication and fitting of Guide
Ramp-Utility Guardrail for the
disabled with MS tubular pipes at
51 18.3
regular intervals of height 1.05m R.M 99.08 2,336.09 231,459.80 29.45 2,336.09 68,797.85 (162,661.95) (0.70) 6,500.00 644,020.00 6,500.00 191,425.00 (69.63) (0.70) (452,595.00) (0.70)
including two coats enamel paint
all complete as per drawings and
specifications
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
APRON DRAIN: Construction of
Apron drain along the perimeter of
buildings and retaining structures
52 18.4 including excavation, Brick soling, R.M 57.65 2,904.09 167,420.79 57.65 2,904.09 167,420.79 - - 20,000.00 1,153,000.00 20,000.00 1,153,000.00 - - - -
PCC and half brick thick apron
walls with plaster all complete as
per drawings and specifications
TACTILE PAVING: Providing
and laying approved brand quality,
pattern and colour of Tactile paving
tile on floor over constructed
cement mortar of mix 1:3 backing
53 18.5 and filling joints (epoxy grout) at R.M 96.41 1,067.25 102,893.57 0.00 1,067.25 - (102,893.57) (1.00) 3,500.00 337,435.00 3,500.00 - (96.41) (1.00) (337,435.00) (1.00)
straight path and turning points of
size 300x300x40mm, all complete
as per drawings, specifications and
instructions.
DEMOLITION WOKS: Demolition
54 19.1 PS 1.00 1,000,000.00 1,000,000.00 1.00 1,000,000.00 1,000,000.00 - 1,000,000.00 1,000,000.00 1,000,000.00 1,000,000.00 - - - -
of existing building and toilet blocks
RELOCATION WOKS: Relocation
of temple from existing site and to
be constructed at a new location
55 20.1 PS 1.00 400,000.00 400,000.00 0.00 400,000.00 - (400,000.00) (1.00) 400,000.00 400,000.00 400,000.00 - (1.00) (1.00) (400,000.00) (1.00)
outside of the school site as per
drawing,specification and
instructions.
56 21.1 INSURANCE PREMIUM PS 1.00 250,000.00 250,000.00 0.90 250,000.00 224,280.00 (25,720.00) (0.10) 250,000.00 250,000.00 250,000.00 224,280.00 (0.10) (0.10) (25,720.00) (0.10)
Extra Items - - -
ROOFING WORK,CGI ROOFING
SHEET: Providing and fixing in
position 24 gauge (0 .50 mm thick)
color corrugated CGI sheet over
roof truss with minimum 80 mm side Estimated as plain sheet but
22.1 Sq.M 0.00 - 1770.51 1,319.17 2,335,603.68 2,335,603.68 - 1,319.17 2,335,603.68 1,770.51 2,335,603.68
laps and 200 mm end laps, required color in site
inclusive of nuts and bolts, 8 mm 'J'
hooks, washers, GI cup washers,
all complete as per drawings,
specifications and instruction
CGI ROOFING SHEET ON RIDGE:
Providing and fixing in position 24
gauge (0 .50 mm thick) colour CGI
sheet over roof truss in ridge with
minimum 80 mm side laps and 200 Estimated as plain sheet but
23.1 Rm. 0.00 - 157.13 1,009.53 158,622.40 158,622.40 - - 1,009.53 158,622.40 157.13 158,622.40
mm end laps, inclusive of nuts and required color in site
bolts, washers, GI cup washers, all
complete as per drawings,
specifications and instruction by site
Incharge.
Floor Hardener: Providing,
sprinkling, laying & applying
Manually one layer in floor,applied
with 1.5 to 2.5kg/m2 in required
pattern,blended in, smoothed, over
57 24.1 Sq.M 0.00 1,480.00 - 1379.03 404.80 558,231.34 558,231.34 - - 400.00 551,612.00 1,379.03 551,612.00
by power trowelling,in line and level
including curing all complete as per
drawing, specification and
instruction. (Mapetop,N,AR6 or
equivalent)
Cement Board: Providing and
fixing in position 10mm water
proofed cement board in exterior
(one side)surface inclusive
58 25.1 minimum75mm GI metal framewith Sq.M 0.00 - 191.51 2,722.28 521,343.84 521,343.84 - 2,700.00 517,077.00 191.51 517,077.00
grooving and fixing of fastner,
washer, nuts,and bolts, all complete
as per drawings, specifications and
instructions.
Providing and laying approved
brand quality, pattern and colour,
ceramic or vetrified mat finish tile
(Medium range) on floor(600*600)
over cement mortar of mix 1:4
Cement Sand mortar backing and
59 26.1 filling joints (epoxy grout) complete Sq.M 0.00 - 318.59 3,126.23 995,985.62 995,985.62 - 2,500.00 796,475.00 318.59 796,475.00
as per drawings, specifications and
instructions.
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
Enamel Paint: Providing and
applying two coat of Enamel Paint
(Apex, Asian or equivalent) with
smooth finished including surface
preparation all complete as per
60 27.1 drawings, specifications and Sq.M 0.00 - 946.90 357.78 338,781.88 338,781.88 - 210.72 199,530.77 946.90 199,530.77
instruction

Slope Micropile with Geogrid netting


61 28.1 along slope surface between Middle m
Block Retaining wall and Library Block 0.00 - 288.00 3,152.64 907,959.67 907,959.67 - 2,653.58 764,229.65 288.00 764,229.65
Stone wall all complete

PILE WORK : Construction of pile


62 29 work including excavation, Rm. 0.00 - 135.50 15,482.54 2,097,883.97 2,097,883.97 - 13,005.33 1,762,222.54 135.50 1,762,222.54
reinforcement and concreting work.
63 30 DISMANTLING WORK - - -
30.1 CONCRETE DISMANTLING Cu.M 0.00 - 0.00 11,005.50 - - - 8,500.00 - - -
30.2 BRICKWALL DISMANTLING Cu.M 0.00 - 0.00 2,121.06 - - - 1,800.00 - - -
Total Civil Works 158,356,563.75 149,744,732.30 (8,611,831.45) 0.95 133,316,459.00 129,012,902.30 0.97 (4,303,556.70) (0.03)

Sanitary (Supply and Installation)


Providing and fixing in position of all
work items with all necessary
fittings complete with testing and
ready for operation as per
drawings, specifications,
manufacturer's recommendations
and instructions. The rate shall
include for position marking,
maintain line, level or grade
wherever required, sand
filling/compaction, earth cutting and
backfilling, cutting, chasing of walls,
plasters or tiles etc. and making
good and touching up to restore to
original conditions wherever
instructed and applicable for any of
the items below. Sanitaryware:
Hindware/ Parryware/ Somany
65 1 CP, Set 14.00 25,770.00 360,780.00 9.00 25,770.00 231,930.00 (128,850.00) (0.36) 8,000.00 112,000.00 8,000.00 72,000.00 (5.00) (0.36) (40,000.00) (0.36)
Fixtures: Hindware/ Parryware/
Jaquar, SWR Pipes:
Marvel/ Mangalam Ecodrain PVC,
Hot/Cold Water Supply Pipe and
fittings: Marvel/ Managlam/ Hilltake
CPVC,
Gun Metal Gate Valve:
LEADER/SANT,
Ball Valve: Marvel/ Managlam/
Hilltake CPVC, Plastic
Water Tank: Nepatop/ Hilltake/
Mangalam, A. SANITARY
INSTALLATION:1.1)White glazed
earthernware close coupled Water
Closet set with standard bakelite
seat cover, bracket, CP angular
cock, PVC connector pipe complete
with testing and ready for operation
1.2) White glazed earthernware
580x480mm Orissa Pan with 3/6
liters flushing cistern, trap pipe, pipe
66 2 Set 28.00 5,329.00 149,212.00 34.00 5,329.00 181,186.00 31,974.00 0.21 9,000.00 252,000.00 9,000.00 306,000.00 6.00 0.21 54,000.00 0.21
connector with complete
accessories including bracket,
flushing pipe, pipe
1.3) White glazed earthernware
Wall- hung Large Flat back Urinal
67 3 complete with CP Push cock, Set 6.00 12,359.00 74,154.00 1.00 12,359.00 12,359.00 (61,795.00) (0.83) 10,000.00 60,000.00 10,000.00 10,000.00 (5.00) (0.83) (50,000.00) (0.83)
Spreader, testing and ready for
operation
1.4) White glazed earthernware
under-counter Hand wash basin
with 15 mm CP/PVC connectors
with both ends couplings, 15mm
CP angular cock -1 no, 15mm CP
68 4 Set 4.00 7,729.00 30,916.00 0.00 7,729.00 - (30,916.00) (1.00) 8,000.00 32,000.00 8,000.00 - (4.00) (1.00) (32,000.00) (1.00)
Presmatic pillar cock, 32mm PVC
bottle trap, waste coupling with
testing and ready for operation as
per specifications and site engineer
instructions all complete
1.5) White glazed earthernware
wall- hung Hand wash basin with 15
mm CP/PVC connectors with both
ends couplings, 15mm CP angular
cock -1 no, 15mm CP Presmatic
69 5 Set 4.00 8,173.00 32,692.00 13.00 8,173.00 106,249.00 73,557.00 2.25 7,000.00 28,000.00 7,000.00 91,000.00 9.00 2.25 63,000.00 2.25
pillar cock, 32mm PVC bottle trap,
waste coupling with testing and
ready for operation as per
specifications and site engineer
instructions all complete
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
1.6) White glazed earthernware
70 6 Division Plate for Urinal with wall Set 4.00 3,095.00 12,380.00 0.00 3,095.00 - (12,380.00) (1.00) 5,000.00 20,000.00 5,000.00 - (4.00) (1.00) (20,000.00) (1.00)
brackets
1.7) Indian pattern bathroom
accessories as per specifications
71 7 and site engineer instructions all No. 14.00 1,135.00 15,890.00 9.00 1,135.00 10,215.00 (5,675.00) (0.36) 1,400.00 19,600.00 1,400.00 12,600.00 (5.00) (0.36) (7,000.00) (0.36)
complete set i)CP Toilet Paper
Holder heavy
72 8 ii)CP Soap Dish heavy No. 14.00 827.00 11,578.00 20.00 827.00 16,540.00 4,962.00 0.43 800.00 11,200.00 800.00 16,000.00 6.00 0.43 4,800.00 0.43
iii)CP Commode Spray with plastic
73 9 No. 14.00 2,481.00 34,734.00 9.00 2,481.00 22,329.00 (12,405.00) (0.36) 1,500.00 21,000.00 1,500.00 13,500.00 (5.00) (0.36) (7,500.00) (0.36)
head
74 10 iv)'CP Bib cock No. 28.00 3,137.00 87,836.00 55.00 3,137.00 172,535.00 84,699.00 0.96 15,000.00 420,000.00 15,000.00 825,000.00 27.00 0.96 405,000.00 0.96
75 11 v)CP Robe Hook No. 33.00 527.00 17,391.00 1.00 527.00 527.00 (16,864.00) (0.97) 1,500.00 49,500.00 1,500.00 1,500.00 (32.00) (0.97) (48,000.00) (0.97)
vi)CP Towel Rail Heavy (20 X
76 12 No. 7.00 2,034.00 14,238.00 1.00 2,034.00 2,034.00 (12,204.00) (0.86) 1,500.00 10,500.00 1,500.00 1,500.00 (6.00) (0.86) (9,000.00) (0.86)
600mm)
1.8) 5 mm thick looking mirror of
following size of Modi or approved
make with CP mirror screws and
77 13 No. 1.00 2,285.00 2,285.00 5.00 2,285.00 11,425.00 9,140.00 4.00 1,900.00 1,900.00 1,900.00 9,500.00 4.00 4.00 7,600.00 4.00
clips as per specifications and site
engineer instructions all complete
set.i)24"x18" Mirror
78 14 ii)48"x18" Mirror No. 2.00 4,283.00 8,566.00 0.00 4,283.00 - (8,566.00) (1.00) 1,500.00 3,000.00 1,500.00 - (2.00) (1.00) (3,000.00) (1.00)
1.9) PVC Multi-floor trap with cover
79 15 No. 60.00 554.00 33,240.00 33.00 554.00 18,282.00 (14,958.00) (0.45) 400.00 24,000.00 400.00 13,200.00 (27.00) (0.45) (10,800.00) (0.45)
80 16 1.10) 110 mm PVC cowl vent No. 16.00 380.00 6,080.00 4.00 380.00 1,520.00 (4,560.00) (0.75) 500.00 8,000.00 500.00 2,000.00 (12.00) (0.75) (6,000.00) (0.75)
1.11) CP Shower rose with divertor
81 17 No. 2.00 22,224.00 44,448.00 1.00 22,224.00 22,224.00 (22,224.00) (0.50) 1,300.00 2,600.00 1,300.00 1,300.00 (1.00) (0.50) (1,300.00) (0.50)
and arm
82 18 B. WATER SUPPLY - 0.00 - - -
INSTALLATION: 2.1) Chlorinated
Poly Vinyl Chloride (CPVC) pipes
SDR-11 including MS clamps and
brackets, nails and hooks,
fittings( Tees, Elbows,Unions etc)
and all necessary CPVC/Brass
specials required for complete
installation, cutting, jointing, sealing
of joints etc, installation of pipes
and specials including making holes
and cutting grooves on walls or
83 18 Rm 22.00 2,343.00 51,546.00 0.00 2,343.00 - (51,546.00) (1.00) 1,200.00 26,400.00 1,200.00 - (22.00) (1.00) (26,400.00) (1.00)
floor and repairing the same to its
original finish. Pipes to be installed
on trenches or walls or floor or duct
as per drawings, specifications and
instructions, cleaning of the system,
testing and ready for operation. The
rate shall include for all labour and
materials required. The
measurement shall be done for
running feet, fittings etc not payable
seperately. i) - 80 mm
84 19 ii) - 65mm Rm 76.00 1,499.00 113,924.00 0.00 1,499.00 - (113,924.00) (1.00) 1,000.00 76,000.00 1,000.00 - (76.00) (1.00) (76,000.00) (1.00)
85 20 ii) - 50 mm Rm 100.00 1,499.00 149,900.00 254.85 1,499.00 382,020.15 232,120.15 1.55 900.00 90,000.00 900.00 229,365.00 154.85 1.55 139,365.00 1.55
86 21 iv) - 40 mm Rm 22.00 937.00 20,614.00 0.00 937.00 - (20,614.00) (1.00) 600.00 13,200.00 600.00 - (22.00) (1.00) (13,200.00) (1.00)
87 22 v) - 32 mm Rm 65.00 680.00 44,200.00 0.00 680.00 - (44,200.00) (1.00) 500.00 32,500.00 500.00 - (65.00) (1.00) (32,500.00) (1.00)
23 vi) - 25 mm Items qty not included in
88 Rm 54.00 556.00 30,024.00 277.40 556.00 154,234.40 124,210.40 4.14 400.00 21,600.00 400.00 110,960.00 223.40 4.14 89,360.00 4.14
BOQ but required in site
24 vii) - 20 mm
89 Items qty not included in
Rm 130.00 406.00 52,780.00 133.80 406.00 54,322.80 1,542.80 0.03 350.00 45,500.00 350.00 46,830.00 3.80 0.03 1,330.00 0.03
BOQ but required in site
25 viii) - 15 mm Items qty not included in
90 Rm 38.00 315.00 11,970.00 27.21 315.00 8,571.15 (3,398.85) (0.28) 300.00 11,400.00 300.00 8,163.00 (10.79) (0.28) (3,237.00) (0.28)
BOQ but required in site
26 2.2) CPVC Ball Valve including
jointing materials all complete set
91 No. Items qty not included in
as per specifications and site 9.00 680.00 6,120.00 0.00 680.00 - (6,120.00) (1.00) 600.00 5,400.00 600.00 - (9.00) (1.00) (5,400.00) (1.00)
BOQ but required in site
engineer's instruciton. i) - 20 mm
dia.
92 27 ii) - 32 mm dia No. 10.00 1,820.00 18,200.00 0.00 1,820.00 - (18,200.00) (1.00) 1,600.00 16,000.00 1,600.00 - (10.00) (1.00) (16,000.00) (1.00)
28 ii) - 25 mm dia
93 No. Items qty not included in
1.00 919.00 919.00 17.00 919.00 15,623.00 14,704.00 16.00 700.00 700.00 700.00 11,900.00 16.00 16.00 11,200.00 16.00
BOQ but required in site
29 ii) - 50 mm dia Items qty not included in
94 No. 1.00 2,987.00 2,987.00 6.00 2,987.00 17,922.00 14,935.00 5.00 2,500.00 2,500.00 2,500.00 15,000.00 5.00 5.00 12,500.00 5.00
BOQ but required in site
95 30 ii) - 80 mm dia No. 1.00 4,554.00 4,554.00 0.00 4,554.00 - (4,554.00) (1.00) 5,000.00 5,000.00 5,000.00 - (1.00) (1.00) (5,000.00) (1.00)
31 2.3) Electric centrifugal water pump
with motor of capacity 40 liters per
minute at 28m head (approx. 1 HP
motor) complete with starter,
96 Set 10.00 28,615.00 286,150.00 10.00 28,615.00 286,150.00 - - 34,000.00 340,000.00 34,000.00 340,000.00 - - - -
electric cable, check valve,
automatic pump controller with high
and low level sensors and cable
etc. (one set stand- by)
32 2.4) 300 litres capacity solar water
heater with 3 solar collectors size
1000x2000mm complete with
97 No. 17.00 112,562.00 1,913,554.00 0.00 112,562.00 - (1,913,554.00) (1.00) 25,000.00 425,000.00 25,000.00 - (17.00) (1.00) (425,000.00) (1.00)
thermostat, stands, pipe
connections, valves, testing and
ready for operation
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
33 C. SEWER, VENT, RAIN AND
WASTE WATER INSTALLATION:
3.1) PVC SWR (Soil, Waste) eco-
drain pipes with all necessary ring
gaskets, PVC fittings, including MS
clamps, hangers, cutting, jointing,
sealing, installation of pipes and
specials including making holes and
cutting grooves on walls or floor
and repairing the same to its
original finish. Pipes to be installed Items qty not included in
98 Rm 68.00 2,268.00 154,224.00 141.60 2,268.00 321,148.80 166,924.80 1.08 1,200.00 81,600.00 1,200.00 169,920.00 73.60 1.08 88,320.00 1.08
on trenches or walls or floor or duct BOQ but required in site
or hung to ceilings as per drawings,
specifications, manufacturer's
recommendations, instructions,
cleaning of the system, testing and
ready for operation. The rate shall
include for all labour and materials
required. The measurement shall
be done for running feet, fittings etc
not payable seperately. i) - 160 mm
ED 6 kg/cm2
34 ii) - 110 mm ED 6 kg/cm2 Items qty not included in
99 Rm 240.00 1,252.00 300,480.00 554.70 1,252.00 694,484.40 394,004.40 1.31 1,000.00 240,000.00 1,000.00 554,700.00 314.70 1.31 314,700.00 1.31
BOQ but required in site
100 35 iii) - 75 mm ED 6 kg/cm3 Rm 142.00 657.00 93,294.00 44.31 657.00 29,111.67 (64,182.33) (0.69) 600.00 85,200.00 600.00 26,586.00 (97.69) (0.69) (58,614.00) (0.69)
36 iv) - 50 mm ED 6 kg/cm4
101 Rm items qty not included in
17.00 352.00 5,984.00 36.15 352.00 12,724.80 6,740.80 1.13 400.00 6,800.00 400.00 14,460.00 19.15 1.13 7,660.00 1.13
BOQ but required in site
37 3.2) Construction of brick masonry
Sewer manhole of internal diameter
600mm with 230mm thick brick
masonry in 1:4 cement mortar,
102 100mm thick RCC 1:2:4 slab cover, No. 26.00 31,436.00 817,336.00 12.00 31,436.00 377,232.00 (440,104.00) (0.54) 60,000.00 1,560,000.00 60,000.00 720,000.00 (14.00) (0.54) (840,000.00) (0.54)
600mm dia CI Manhole cover with
frame (medium duty), cement
plaster inside, height varies from
300mm to 1000mm
38 3.3) Construction of brick masonry
waste water collection chamber of
internal size 450x450mm (internal
height varies from 600 to 1500mm)
with 230mm thick brickwork in 1:4
cement mortar, 100mm thick PCC
M15 base, 150mm thick RCC M15
103 no. 16.00 19,980.00 319,680.00 7.00 19,980.00 139,860.00 (179,820.00) (0.56) 35,000.00 560,000.00 35,000.00 245,000.00 (9.00) (0.56) (315,000.00) (0.56)
slab cover, internal wall and floor
finish with 12mm thick cement
plaster 1:4, PCC M15 benching on
floor, 500x500mm dia CI manhole
cover with frame (Medium duty),
earthwork in excavation, backfilling
and site clearance
39 3.4) Construction of brick masonry
rain water inlet chamber of internal
size 450x450mm (internal height
varies from 600 to 1500mm) with
230mm thick brickwork in 1:4
cement mortar, 100mm thick PCC
104 M15 base, 150mm thick RCC M15 no. 24.00 22,448.00 538,752.00 7.00 22,448.00 157,136.00 (381,616.00) (0.71) 25,000.00 600,000.00 25,000.00 175,000.00 (17.00) (0.71) (425,000.00) (0.71)
slab cover, internal wall and floor
finish with 12mm thick cement
plaster 1:4, 450x450mm dia CI Rain
inlet cover with frame (Medium
duty), earthwork in excavation,
backfilling and site
3.5) Construction of RCC septic
tank of internal size 13'-0"x5'-0"x4'-
0" and 18" Free board as per
drawings including earthwork
excavation, flat brick soling, P.C.C.,
R.C.C. cover slab/baffles, walls and
base, cement plaster with punning
105 40 on internal walls, slab bottom & top, job 5.00 216,000.00 1,080,000.00 3.00 216,000.00 648,000.00 (432,000.00) (0.40) 70,000.00 350,000.00 70,000.00 210,000.00 (2.00) (0.40) (140,000.00) (0.40)
medium duty CI 600 mm x 600 mm
manhole cover pipe sleeves, etc.,
all complete as per drawing,
specifications and instructions.
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
3.6) Construction of soakpit of size
2000 mm clear diameter, 1500 mm
clear liquid height, 400 mm free
board; including earth work
excavation & filling, 230 mm thick
honey-comb/solid Brick wall in 1:6
cement mortar, 125mm thick R.C.C.
slab cover with plaster, filling pit
106 41 with graded washed stone gravel, job 5.00 81,672.00 408,360.00 3.00 81,672.00 245,016.00 (163,344.00) (0.40) 55,000.00 275,000.00 55,000.00 165,000.00 (2.00) (0.40) (110,000.00) (0.40)
filling 300mm wide gap between
wall and ground with coarse sand,
etc., all complete as per drawings,
specification and instructions.

3.7) Construction of Recharge Pit


made with RCC Rings 1200 mm dia
and 6 m high complete with
107 42 excavation, 150 thick RCC 1:2:4 Rm 12.00 8,878.00 106,536.00 0.00 8,878.00 - (106,536.00) (1.00) 40,000.00 480,000.00 40,000.00 - (12.00) (1.00) (480,000.00) (1.00)
slab cover, disposal of extra
excavated material

Total Sanitary Works 7,468,508.00 4,352,912.17 (3,115,595.83) (0.42) 6,425,100.00 4,417,984.00 - (2,007,116.00) (0.31)

ELECTRICALS (Supply and


108 1.3 instalation,testing and - -
commission)
1.3.1 Concealed wiring - -
Light and fan points wiring from
distribution boards to switch boxes
and switch boxes to light fixtures
and fans with 2x 2.5 +1x 1.5 sq mm
PVC insulated cu wire through
109 1 pts 206.00 1,331.95 274,381.29 534.00 1,331.95 711,260.23 436,878.94 1.59 3,000.00 618,000.00 3,000.00 1,602,000.00 328.00 1.59 984,000.00 1.59
20mm dia. HDPE conduit including
modular type switch/ electronic fan
control switch

15 amp Power points wiring from


distribution boards to 2 - 3 outlets
per circuit with 2x4+1x 2.5 sq mm
PVC insulated copper wires through
25mm dia. HDPE conduit including
110 2 pts 171.00 1,607.85 274,942.69 152.00 1,607.85 244,393.50 (30,549.19) (0.11) 4,000.00 684,000.00 4,000.00 608,000.00 (19.00) (0.11) (76,000.00) (0.11)
all necessary materials for point
wiring excluding power sockets.

13 amp Power points wiring from


distribution boards to 2 - 3 outlets
per circuit with 2x2.5+1x 1.5 sq mm
PVC insulated copper wires through
25mm dia. HDPE conduit including
111 3 pts 4.00 1,219.76 4,879.02 54.00 1,219.76 65,866.82 60,987.80 12.50 2,500.00 10,000.00 2,500.00 135,000.00 50.00 12.50 125,000.00 12.50
all necessary materials for point
wiring excluding power sockets.

- - - - - - -
Supply instalation
testing,commissioning of modular
1.3.2 type switch sockets,in metal box. - - - - - - - -

Supply instalation
testing,commissioning of light
1.3.2.1 fixture complete with lamps/tubes. - - - - - - - -

12 W LED down light surface


mounted 6" dia with inbuilt LED
113 1 Driver & lumen output not less than sets 83.00 851.58 70,680.73 62.00 851.58 52,797.65 (17,883.08) (0.25) 1,500.00 124,500.00 1,500.00 93,000.00 (21.00) (0.25) (31,500.00) (0.25)
90 lumen per watt.
22 watt LED Tube Light fixture
surface batten type with inbuilt LED
114 2 Driver lumen efficiency >110 sets 361.00 1,863.58 672,750.58 93.00 1,863.58 173,312.48 (499,438.10) (0.74) 1,500.00 541,500.00 1,500.00 139,500.00 (268.00) (0.74) (402,000.00) (0.74)
lumen/watt
12 watt LED Bulk head light fixture
with necessary fixing accessories
115 3 with inbuilt LED driver and lumen sets 23.00 1,872.20 43,060.60 0.00 1,872.20 - (43,060.60) (1.00) 2,500.00 57,500.00 2,500.00 - (23.00) (1.00) (57,500.00) (1.00)
efficiency not less than 90
lumen/watt
18 watt LED Tube Light fixture
suspendent batten type with inbuilt
116 4 LED Driver lumen efficiency > sets 12.00 2,200.00 26,400.00 0.00 2,200.00 - (26,400.00) (1.00) 3,500.00 42,000.00 3,500.00 - (12.00) (1.00) (42,000.00) (1.00)
110 lumen/watt
9 watt LED wall light fixture with
necessary fixing accessories with
117 5 inbuilt LED driver and lumen sets 2.00 1,469.70 2,939.40 0.00 1,469.70 - (2,939.40) (1.00) 5,000.00 10,000.00 5,000.00 - (2.00) (1.00) (10,000.00) (1.00)
efficiency not less than 90
lumen/watt
9 watt LED mirror light fixture with
necessary fixing accessories with
118 6 inbuilt LED driver and lumen sets 3.00 1,469.70 4,409.10 0.00 1,469.70 - (4,409.10) (1.00) 15,000.00 45,000.00 15,000.00 - (3.00) (1.00) (45,000.00) (1.00)
efficiency not less than 90
lumen/watt
30 watt LED hanging floor light
fixture with necessary fixing
119 7 accessories with inbuilt LED driver sets 9.00 8,000.00 72,000.00 0.00 8,000.00 - (72,000.00) (1.00) 25,000.00 225,000.00 25,000.00 - (9.00) (1.00) (225,000.00) (1.00)
and lumen efficiency not less than
110lumen/watt
120 - - - - - - - -
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
15 amp 3 Pin Power Socket with
safety shutter, modular switch and
121 1 required modular plate nos. 171.00 619.29 105,898.08 152.00 619.29 94,131.62 (11,766.45) (0.11) 1,500.00 256,500.00 1,500.00 228,000.00 (19.00) (0.11) (28,500.00) (0.11)

13 amp Universal Pin Power Socket


with safety shutter, modular switch
122 2 and required modular plate nos. 4.00 808.45 3,233.80 54.00 808.45 43,656.30 40,422.50 12.50 1,500.00 6,000.00 1,500.00 81,000.00 50.00 12.50 75,000.00 12.50

- - - - - - - -
4 core 35 sq.mm Al armoured PVC
cable from NEA Tapping point to
Main Electrical Panel via NEA
meter to be laid aerially on electrical
pole and partly on building structure
123 1 with switable cable clamp, shackle Rm 75.00 594.55 44,591.25 75.00 594.55 44,591.25 - - 500.00 37,500.00 500.00 37,500.00 - - - -
insulator with D-iron, Nut bolt as
per NEA rules and regulation .

4 core 25 sq.mm Al armoured PVC


cable+ 1x4 sq mmm copper cable
from Main controle Panel to
primary block, secondary block,
higher secondary block and
community block of main
124 2 distribution board through Rm 286.00 523.25 149,649.50 280.00 523.25 146,510.00 (3,139.50) (0.02) 400.00 114,400.00 400.00 112,000.00 (6.00) (0.02) (2,400.00) (0.02)
underground 32mm dia.
HDPE conduit all complete as per
specification, drawings and
instruction of the Consultant.

2core 16 sq.mm Al armoured PVC


cable + 1x4 sq mmm copper cable
from Main controle Panel to
multpurpose block board through
underground 32mm dia. HDPE
125 3 Rm 93.50 405.86 37,948.10 0.00 405.86 - (37,948.10) (1.00) 300.00 28,050.00 300.00 - (93.50) (1.00) (28,050.00) (1.00)
conduit all complete as per
specification, drawings and
instruction of the Consultant.

2core 10 sq.mm Al armoured PVC


cable + 1x4 sq mmm copper cable
Main controle Panel to toilet block
through underground 32mm dia.
126 4 HDPE conduit all complete as per Rm 45.00 382.86 17,228.79 50.00 382.86 19,143.10 1,914.31 0.11 250.00 11,250.00 250.00 12,500.00 5.00 0.11 1,250.00 0.11
specification, drawings and
instruction of the Consultant.

2core 10 sq.mm Al armoured PVC


cable 1x4 sq mmm copper cable
primary block to toilet block
through underground 32mm dia.
127 5 HDPE conduit all complete as per Rm 45.00 382.86 17,228.79 40.00 382.86 15,314.48 (1,914.31) (0.11) 200.00 9,000.00 200.00 8,000.00 (5.00) (0.11) (1,000.00) (0.11)
specification, drawings and
instruction of the Consultant.

2 x 6 sq.mm.+1 core 4 sq.mm.


copper armored PVC cable from
primary block Main distribution
board to GF, FF and SF distribution
board through underground 32mm
128 6 dia. HDPE conduit all complete as Rm 135.30 332.15 44,939.35 132.00 332.15 43,843.27 (1,096.08) (0.02) 1,000.00 135,300.00 1,000.00 132,000.00 (3.30) (0.02) (3,300.00) (0.02)
per specification, drawings and
instruction of the Consultant.

2 x 6 sq.mm.+1 core 4 sq.mm.


copper armored PVC cable from
secondary block Main distribution
board to GF, FF and SF distribution
board through underground 32mm
129 7 dia. HDPE conduit all complete as Rm 150.00 332.15 49,821.90 155.00 332.15 51,482.63 1,660.73 0.03 1,000.00 150,000.00 1,000.00 155,000.00 5.00 0.03 5,000.00 0.03
per specification, drawings and
instruction of the Consultant.

2 x 6 sq.mm.+1 core 4 sq.mm.


copper armored PVC cable from
higher secondary block Main
distribution board to GF,FF and SF
distribution board through
130 8 underground 32mm dia. HDPE Rm 145.00 332.15 48,161.17 140.00 332.15 46,500.44 (1,660.73) (0.03) 1,000.00 145,000.00 1,000.00 140,000.00 (5.00) (0.03) (5,000.00) (0.03)
conduit all complete as per
specification, drawings and
instruction of the Consultant.

2 x 6 sq.mm.+1 core 4 sq.mm.


copper armored PVC cable from
comunity block Main distribution
board to BF, GF,FF and SF
distribution board through
131 9 underground 32mm dia. Rm 130.00 332.15 43,178.98 125.00 332.15 41,518.25 (1,660.73) (0.04) 1,000.00 130,000.00 1,000.00 125,000.00 (5.00) (0.04) (5,000.00) (0.04)
HDPE conduit all complete as per
specification, drawings and
instruction of the Consultant.

- - - - - - - -
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
1200 mm 3 blade ceiling fan with 2
132 1 moudule fan speed step regulator sets 111.00 4,318.89 479,397.23 15.00 4,318.89 64,783.41 (414,613.82) (0.86) 4,000.00 444,000.00 4,000.00 60,000.00 (96.00) (0.86) (384,000.00) (0.86)

300mm dia heavy duty exhaust fan


133 2 sets 7.00 4,186.86 29,308.04 0.00 4,186.86 - (29,308.04) (1.00) 6,000.00 42,000.00 6,000.00 - (7.00) (1.00) (42,000.00) (1.00)
with metallic louvere
- - - - - - - -
Main Controle Panel comprising of
(Amp, TP, DP, MCCV, Fuse,
134 1 Meters, panel board, with fixing set 1.00 101,813.00 101,813.00 0.00 101,813.00 - (101,813.00) (1.00) 50,000.00 50,000.00 50,000.00 - (1.00) (1.00) (50,000.00) (1.00)
testing and commissioning)

- - - - - - - -
MDB-MH (Amp, TP, DP, MCCV,
Fuse, Meters, panel board, with
135 1 fixing testing and commissioning) set 1.00 81,520.69 81,520.69 1.00 81,520.69 81,520.69 - - 40,000.00 40,000.00 40,000.00 40,000.00 - - - -

DB-GF-SHOP-1,DB-GF-SHOP-2,
DB-GF-SHOP-3,DB-GF-SHOP-4
&DB-GF-SHOP-5 (Amp, TP, DP,
MCCV, Fuse, Meters, panel board,
136 2 with fixing testing and set 5.00 6,903.11 34,515.52 5.00 6,903.11 34,515.52 - - 25,000.00 125,000.00 25,000.00 125,000.00 - - - -
commissioning)

137 3 DB-FF/DB-SF (All complete) set 2.00 10,882.40 21,764.81 2.00 10,882.40 21,764.81 - - 20,000.00 40,000.00 20,000.00 40,000.00 - - - -
138 4 DB-MH (All complete) set 1.00 11,360.94 11,360.94 1.00 11,360.94 11,360.94 - - 20,000.00 20,000.00 20,000.00 20,000.00 - - - -
139 5 MDB-P (All complete) set 1.00 71,699.35 71,699.35 1.00 71,699.35 71,699.35 - - 10,000.00 10,000.00 10,000.00 10,000.00 - - - -
DB-GF-1/DB-FF-1/DB-FF-2/DB-SF-
140 6 2 (All complete) set 4.00 36,192.65 144,770.60 4.00 36,192.65 144,770.60 - - 10,000.00 40,000.00 10,000.00 40,000.00 - - - -

DB-GF-2/DB-SF-1 (All complete)


141 7 set 2.00 8,214.44 16,428.88 2.00 8,214.44 16,428.88 - - - - - - - - -
142 8 MDB-S (All complete) set 1.00 69,306.66 69,306.66 1.00 69,306.66 69,306.66 - - - - - - - - -
DB-GF-1/DB-FF-1/DB-FF-2/DB-SF-
143 9 2 (All complete) set 4.00 7,735.90 30,943.60 4.00 7,735.90 30,943.60 - - - - - - - - -

DB-GF-2/DB-SF-1 (All complete)


144 10 set 2.00 8,214.44 16,428.88 2.00 8,214.44 16,428.88 - - - - - - - - -
145 11 MDB-S (All complete) set 1.00 71,699.35 71,699.35 1.00 71,699.35 71,699.35 - - - - - - - - -
DB-GF-1,DB-GF-2,DB-FF-1,DB-FF-
2,DB-SF-1, & DB-SF-2 (All
146 12 complete) set 6.00 7,735.90 46,415.41 6.00 7,735.90 46,415.41 - - - - - - - - -

147 13 DB-T-2(GF) (All complete) set 1.00 5,736.96 5,736.96 1.00 5,736.96 5,736.96 - - - - - - - - -
DB-T-1(GF),DB-T-2(GF) & DB-T-2
148 14 (FF),( all complete) set 2.00 5,258.42 10,516.84 2.00 5,258.42 10,516.84 - - - - - - - - -

- - - - - - - -
Supply, installation and wiring for
Networking Terminals , with partly
surface installed in 25 mm HDPE
conduit and cable tray with CAT 6
E 4 pair cable including required
chiselling / chasing of wall , and
149 1 making good of the same, with 1 points 4.00 1,329.40 5,317.60 4.00 1,329.40 5,317.60 - - - - - - - - -
meter long spare CAT 6 Cable at
both ends as per specification,
drawings and instruction of the
Consultant.

Supply and installation of Computer


Outlets RJ 45 , CAT 6 , with
150 2 required facia plate and flush nos. 4.00 422.63 1,690.50 4.00 422.63 1,690.50 - - - - - - - - -
mounting GI boxes.
Supply , installation & testing of 8
Ports 10/10000 Base Unmanaged
computer switch with rack.(at
151 3 Principle room), all complete as per set 1.00 10,000.00 10,000.00 1.00 10,000.00 10,000.00 - - - - - - - - -
specification, drawings and
instruction of the Consultant.

Supply, installation and wiring for


Telephone Terminal RJ 11 2 pair
0.5 mm copper telephone wire in
20 mm dia HDPE Conduit laid
partly in the conduit and partly in
cable tray with total average length
of individual point at 25 meters from
152 1 Junction or the main distribution points 4.00 1,027.41 4,109.64 4.00 1,027.41 4,109.64 - - - - - - - - -
frame including chiselling / chasing
of wall / floor and making good of
the same.

Supply and installation of


Telephone Outlets , RJ11 with
153 2 required flush mounting GI boxes. nos. 4.00 338.20 1,352.82 4.00 338.20 1,352.82 - - - - - - - - -

Supply, delivery, installation, testing


and commissioning of 10 pair
Telephone Junction with lockable
154 3 cover and Krone Connector with nos. 1.00 6,066.25 6,066.25 1.00 6,066.25 6,066.25 - - - - - - - - -
tagging facilities
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
Supply and installation of 3 line
input and 8 line output PABX
telephone exchange system with 1
set of programmable master
155 4 telephone set with all necessary set 1.00 27,046.14 27,046.14 1.00 27,046.14 27,046.14 - - - - - - - - -
accessories as per specification,
drawings and instruction of the
Consultant.

Supply, installation, testing and


commissioning of copper plate
earthing stations making earth pits,
earthing with Copper earth plate
600 mm x 600 mm x 3 mm thick
including funnel, char-coal/coke,
salt, all earth work. Providing
masonry enclosure with 10 mm
156 1 thick C.I. cover plate having locking set 2.00 18,398.00 36,796.00 2.00 18,398.00 36,796.00 - - - - - - - - -
arrangement and 25 mm dia 2 m
long G.I. pipe perforated for
watering, disconnecting/ testing
links etc as per IS –3043 complete
as required.

Lightning Protection Air Terminal


Lightning Arrester ( 20 mm dia. 1.5
157 2 Mtr Height, solid copper rod ) set 2.00 4,343.00 8,686.00 2.00 4,343.00 8,686.00 - - - - - - - - -

50 sq. mm. stranded bare copper


conductor in 32mm dia HDPE pipe
158 3 from Air terminal to earthing point rm 50.00 583.00 29,150.00 50.00 583.00 29,150.00 - - - - - - - - -
including support clamps all
complete.
Galvanized 9 Meter Steel Tubular
Pole ( Bottom 134mm dia,3300mm
ht,155mm dia 2250mm ht,90mm
dia 2250 ht and 76mm dia 1650mm
159 1 ht with over lapping of set 13.00 22,764.00 295,932.00 13.00 22,764.00 295,932.00 - - - - - - - - -
200mm,150mm, 100mm
respectively Approx. 100 kg)

150Wp monocrystalline PV module


160 2 set 22.00 15,750.00 346,500.00 22.00 15,750.00 346,500.00 - - - - - - - - -
30 watt led solar street light builtin
161 3 charge controller with dust to down set 22.00 14,000.00 308,000.00 22.00 14,000.00 308,000.00 - - - - - - - - -
sensor
162 4 MS street light fixture arm set 22.00 4,500.00 99,000.00 22.00 4,500.00 99,000.00 - - - - - - - - -
Solar panel stand,G.I. Battery box ,
battery stand ,wiring material and
163 5 other minor materials for set 15.00 4,500.00 67,500.00 15.00 4,500.00 67,500.00 - - - - - - - - -
installation.
Solar Lithium Ion Batteries
164 6 set 15.00 25,000.00 375,000.00 15.00 25,000.00 375,000.00 - - - - - - - - -
(60AH@c10,12 Volt)

Extra Electrical Items


165 1 MDB
Supply, delivery, installation, and
commissioning of Main distribution
panel floor mountable made of 14
SWG MS metal sheet including neutral
bar, phase bar and earth bar with
adequate space for incomming and
outgoing cable with complete internal
wiring ( DB MAIN)

125A TP MCCB 36 KA ICS for main


incomer -1nos.
80A TP MCCB 25 KA ICS for spare -
1nos.
40A TP MCCB 25 KA ICS for Primary
Block MDB -1nos.
40A TP MCCB 25 KA ICS for
Secondary Block MDB -1nos.
40A TP MCCB 25 KA ICS for Middle
set 0.00 1.00 224,384.55 224,384.55 224,384.55 - - 188,483.00 188,483.00 1.00 188,483.00 Due to load capacity
Block MDB -1nos.
40A TP MCCB 25 KA ICS for Library
Block MDB -1nos.
32A TP MCCB 25 KA ICS for UPS -
1nos.
40A TP MCCB 25 KA ICS for Pump -
1nos.
40A TP MCCB 25 KA ICS for Spare -
1nos.
TPN copper bus bar with earth bar -
1Set
Voltmeter - 1Se
Ammeter - 1Se
Selector switch - 1Se
CT coil - 1Se
Indicator lamp with MCB - 1Se
167 3 Junction Box
TOTAL VARIATION ORDER

Original Cost Estimate Revised Cost Estimate Change w.r.t Original Estimate Original Contract Amount New Contract Amount after this variration in NRs Varition 1 (Change in Amount w.r.t. Original contract) Reasons For changes in
S.N. Item No. Description of Works Unit
Quantity Estimate Rate Amount Quantity Rate Amount Amount % Tender Rate Amount Rate Amount Quantity % Amount % Quantity
Supply, delivery, installation, and
commissioning of Distribution board
wall mountable made of 16 SWG MS
metal sheet with adequate space
(10"x10"x4") for incomming and
outgoing cable with complete internal set 0.00 10.00 2,092.43 20,924.30 20,924.30 - - 1,757.64 17,576.40 10.00 17,576.40 Due to load capacity
wiring as per drawing,specification and
instruction all complete.

Total Electrial Items 4,874,096.82 4,359,669.73 (514,427.09) (0.11) 4,191,500.00 4,149,559.40 (41,940.60) (0.01)

Total 170,699,168.58 158,457,314.20 (12,241,854.38) -0.07 143,933,059.00 137,580,445.70 (6,352,613.30)

VAT 13% 22,190,891.92 0.13 20,599,450.85 (1,591,441.07) -0.07 13% 18,711,297.67 13% 17,885,457.94 13% (825,839.73)
Grand Total 192,890,060.49 179,056,765.05 (13,833,295.44) -7% 162,644,356.67 155,465,903.64 (7,178,453.03) -4.41%

159,391,469.54 152,356,585.56 (4.414)

Prepared By Checked By Recommended By Approved By


Name : Name : Name : Name :

Designation: Designation: Designation: Designation:

…………………………………… ………………………………………. ………………………………………………………………… ………………………


Signature: Signature: Signature: Signature:
Date: Date: Date: Date:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

TOTAL CIVIL WORK ABSTRACT OF COST


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

GENERAL WORK, SITE CLEARANCE:Clearing and


grubbing of site for construction including uprooting of
1.1 vegetation, grass, brush wood, trees and sapplings of girth Sq.M 5,382.47 100.00 538,247.00
upto 300 mm & removal upto a distance of 50 m as per
drawings, specifications and instructions

EARTHWORK IN EXCAVATION: Earthwork in


2.1 excavation in trenches, pits and foundations by machine or Cu.M 10526.706 200.00 2,105,341.20
appropriate technology in soft soil including existing debris
and brick bats of old structure, if any, upto specified depth
EARTWORK IN FILLING: Providing and placing of
random filling of excavated earth from cutting of slope and
stacked at site in 150mm thick layer in trenches, plinth or
under floor, sides of foundation and below beam at footing
2.2 Cu.M 5,179.42 200.00 1,035,883.30
covered area etc. including watering, mechanical ramming
and compaction of each layer, consolidation and dressing,
all complete as per drawings, specifications and instructions.

SAND FILLING: Sand filling in plinth under floors,


including watering, ramming, consolidating and dressing, all
2.3 complete as per drawings, specifications and instructions. Cu.M 0 2,500.00 -

STONE WORK : Dry stone soling work in line and level,


including packing joints with sand dust, all complete as per
3.1 drawings, specifications and instructions Cu.M 241.03 4,000.00 964,120.00

STONE MASONRY WALL: Stone rubble masonry work in


1:4 cement and sand mortar with hard, tough, sound and
durable stone in wall, made to required line, level, shape,
3.2 size and plumb including setting out, drain outlet, curing of Cu.M 1193.391 7,500.00 8,950,432.50
the works and scaffolding etc. complete as per drawings,
specifications and instructions

BRICK WORK,FLAT BRICK SOLING: Flat brick soling


of local chimney bricks laid in line and level, including
4.1 packing joints with sand, complete as per drawings, Sq.M 3090.64 800.00 2,472,512.00
specifications and instructions
FULL BRICK WORK: Brickwork in substructure and super
4.2 structure cement and sand mortar of mix 1:6 with first class Cu.M 426.21 15,000.00 6,393,150.00
chimney-made bricks, in any size and shape of wall, made
to required line, level, shape and plumb including setting
AAC(Autoclaved Aerated Concrete) BLOCK WORK:
5.1 Providing and laying of Autoclaved Aerated Concrete Block Sq.M 2076.24 1,800.00 3,737,232.00
(600*200*200 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2)AAC(Autoclaved Aerated Concrete) BLOCK WORK:
Providing and laying of Autoclaved Aerated Concrete Block
(600*200*100 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2 required line, level, shape and plumb including setting out, Sq.M 142.28 2,000.00 284,560.00
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

5.3)AAC(Autoclaved Aerated Concrete) BLOCK WORK:


Providing and laying of Autoclaved Aerated Concrete Block
(600*200*150 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.3 required line, level, shape and plumb including setting out, Sq.M 31.17 1,100.00 34,287.00
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

CONCRETE WORK,PCC OF GRADE M10: Plain cement


concrete (PCC) of grade M10 (1:3:6 with 1 cement, 3 coarse
sand and 6 aggregate of 19 mm and down grade) in
6.1 foundation base including mixing, laying, compacting, Cu.M 374.3845 10,000.00 3,743,845.00
finishing, curing, laid to exact line, level and dimensions,
inclusive ofside

PCC FOR RCC OF GRADE M25: Structural concrete (PCC


for RCC) of Grade M25 (1:1:2)works with approved
quality of cement, sand and well graded aggregate in any
form, size, shape and level including batching and mixing
6.2 with machine, laying including compaction with vibrating Cu.M 301.15 20,000.00 6,023,000.00
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

Prepared By: Checked By: Approved By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

TOTAL CIVIL WORK ABSTRACT OF COST


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

PCC FOR RCC OF GRADE M20: Structural concrete (PCC


for RCC) of Grade M20 (1:1.5:3)works with approved
quality of cement, sand and well graded aggregate in any
6.3 form, size, shape and level including batching and mixing Cu.M 1141.77 17,000.00 19,410,090.00
with machine, laying including compaction with vibrating
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

FORMWORK: Placing plyboard form work with steel


props, shuttering, centering in horizontal/Vertical surfaces
like slab, beams, column, wall, stair etc. for all RCC works
7.1 of any shape, size and at any level and removal after Sq.M 9904.13 850.00 8,418,510.50
completion

REINFORCEMENT WORK: Providing and placing steel


reinforcement bar tested grade Fe-500 equivalent NS, for
8.1 RCC work including bending, binding with anneal wire and kg 217,600.27 110.00 23,936,029.98
placing in position, all complete as per drawings,
specifications and instruction
9.1)FLOORING WORK,PLASTIC
9.1 LAYING: Supplying and laying 500 gauge plastic sheet in Sq.M 0 50.00 -
floor as per specificatio and instruction
9.2)SCREEDING: Providing and placing 38 mm thick Plain
cement concrete of grade M15 (1:2:4 with 1 cement, 2
coarse sand and 4 aggregate chips) in the floor base mixing,
laying, compacting, finishing, curing, laid to exact line level
9.2 , surface chipping and dimensions (floor concrete is laid in Sq.M 3661.875 500.00 1,830,937.50
alternate panels of 1 m x 1 m) inclusive of shuttering
complete as per drawings, specifications and instructions

9.3)CEMENT PUNNING: Providing


and laying 3 mm cement punning in floor , laying in
9.3 Sq.M 2171.78 200.00 434,356.00
required pattern, line

9.4)CEMENT SKIRTING: Providing


and placing cement skirting 125mm height of grade M15
(1:2:4 with cement, 2 coarse sand and 4 aggregate
9.4 ) in wall ,mixing, laying, compactig, finishing, curing, laid R.M 1685.21 100.00 168,521.00
to exact line level and dimension all complete as per
drawing, specification and instructions

9.5)TILE LAYING ON FLOOR:


Providing and laying approved brand quality, pattern and
color, ceramic mat finish tile (Low range) on floor over
9.5 cement mortar of mix 1:3 backing and filling joints (epoxy Sq.M 155.15 2,800.00 434,420.00
grout) complete as per drawings, specifications and
instructions.(Base rate: NRs 100)

9.6)TILE LAYING ON TOILET:


Providing and laying approved brand quality, pattern and
color, ceramic glazed tile in wall and ceramic mat finish tile
9.6 (Low range) on floor of toilet over cement mortar of mix 1:3 Sq.M 383.75 3,000.00 1,151,250.00
backing and filling joints (epoxy grout) complete as per
drawings, specifications and instructions.(Base rate: NRs
100)

10.1)FINISHING WORK,
EXTERNAL PLASTER: Providing and applying '10.5 mm
thick cement plastering with 1cement : 4 sand mortar in
outer surface any level size and shape of wall, column,
10.1 ceiling, band, blocks, etc inclusive of waterproofing Sq.M 3439.556 400.00 1,375,822.40
compound, dusting, throating, etc as required including
racking, hacking, watering, cleaning of base, plastering to
plumb, line, level, smooth etc. and curing complete as per
drawings, specifications and instructions.
10.2)INTERNAL PLASTER:
Providing and applying'10.5 mm thick cement plastering
with 1cement : 4 sand mortar in inner surface except ceiling
any level size and shape of wall, column, band, blocks, etc
inclusive of dusting, throating, etc as required including
10.2 racking, watering, hacking, cleaning of base, plastering to Sq.M 5071.26 450.00 2,282,067.00
plumb, line, level, smooth etc. and curing, all complete as
per drawings, specifications and instructions.

Prepared By: Checked By: Approved By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

TOTAL CIVIL WORK ABSTRACT OF COST


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

10.3)CEILING PLASTER: Providing


and applying 12.5 mm thick cement plastering with 1cement
10.3 : 4 sand mortar in Ceiling any level size and shape of Sq.M 3621.41 500.00 1,810,705.00
ceiling inclusive of dusting,
10.4)PLASTER ON RCC LINTEL
WITH CORNICE: 'Providing and applying 12.5 mm thick
cement plastering with 1cement : 4 sand mortar in RCC
Lintel with cornice inclusive of dusting, throating, etc as
10.4 required including racking, watering, cleaning of base, R.M 20.1 3,000.00 60,300.00
plastering to plumb, line, level, smooth etc. and curing, all
complete as per drawings, specifications and instructions.

10.5)EMULSION PAINT: Providing


and applyibg two coat of emulsion paint in mat finishing
10.5 over two coat of primer, finished including surface Sq.M 8381.1475 200.00 1,676,229.50
preparation all complete as per drawings, specifications and
instruction
10.6)WEATHER COAT: Providing and applying two coat
of weather coat (Apex or equivalent) over required coat of
10.6 primer, finished including surface preparation all complete Sq.M 3124.3835 250.00 781,095.87
as per drawings, specifications and instruction

11.1)DOOR,WINDOWS WORK/UPVC SLIDING


WINDOWS: Providing and fixing standard UPVC sliding
window without net (frame 50x80mm, sash 58x36mm white
11.1 colour with 5mm glass) along with patented standard Sq.M 724.582 8,000.00 5,796,656.00
hardwares like roller, gaskets, brush seal, moon locks etc all
complete as per drawings and specifications.

11.2)UPVC TOP HUNG


WINDOWS: Providing and fixing standard UPVC top hung
window (frame 60x60 mm, sash 60x104 mm, white colour
11.2 with 5 mm glass) along with patented standard hardwares Sq.M 60.6 8,000.00 484,800.00
like roller, gaskets, brush seal, moon locks etc all complete
as per drawings and specifications.

11.3)UPVC DOUBLE DOOR:


Providing and fixing standard UPVC double door (frame
60x60mm, sash 60x104mm white colour with 5mm glass)
11.3 along with patented standard hardwares like roller, gaskets, Sq.M 255.3 10,000.00 2,553,000.00
brush seal, moon locks etc all complete as per drawings and
specifications.

11.4)UPVC SINGLE DOOR:


Providing and fixing standard UPVC single door with full
panel (frame60x60mm, sash 60x104mm white colour with
11.4 5mm glass) along with patented standard hardwares like Sq.M 81.86 7,000.00 573,020.00
roller, gaskets, brush seal, moon locks etc all complete as
per drawings and specifications.

12.1)ROOFING WORK,CGI
ROOFING SHEET: Providing and fixing in position 24
gauge medium (0 .5 mm thick) corrugated CGI sheet over
12.1 roof truss with minimum 80 mm side laps and 200 mm end Sq.M 1770.51 1,319.17 2,335,603.67
laps, inclusive of nuts and bolts, 8 mm 'J' hooks, washers,
GI cup washers, all complete as per drawings, specifications
and instruction

12.2)CGI ROOFING SHEET ON


RIDGE: Providing and fixing in position 24 gauge medium
(0 .5 mm thick) CGI sheet over roof truss in ridge with
12.2 minimum 80 mm side laps and 200 mm end laps, inclusive R.m 157.125 1,009.52 158,620.83
of nuts and bolts, washers, GI cup washers, all complete as
per drawings, specifications and instruction

12.3)GI GUTTER: providing and fixing in position color


plain GI sheet for gutter 150mmX450mm, inclusive of nuts
12.3 and bolts, washers, all complete as per drawings, R.m 314.26 1,000.00 314,260.00
specifications and instruction.
13.1)FALSE CEILING WORK,PVC
BOARD: Providing and fixing suspended PVC board false
ceiling, with necessary provisions for light fittings, light
13.1 boxes, where required finally finished with two coat acrylic Sq.M 1012.62 1,500.00 1,518,930.00
emulsion paint, all complete as per drawings, specifications
and instructions.

Prepared By: Checked By: Approved By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

TOTAL CIVIL WORK ABSTRACT OF COST


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

14.1)MISCELLANEOUS WORK,
WATER PROOFING: Providing and placing 20 mm thick
cement sand mortar (1:2) mixing with wate proof
14.1 compound in the floor base mixing, laying, compacting, Sq.M 260.875 400.00 104,350.00
finishing, curing, laid to exact line level and dimensions
complete as per drawings, specifications and instructions

14.2)INSULATION WORK:
Providing and installing Insulation under CGI roofing sheet
14.2 with Insulation shield of 12mm thickness one sided and Sq.m 1235.77 200.00 247,154.00
chicken wire mesh all completeas per drawing and
specifications.
15.1)METAL WORKS,BLACK
15.1 TUBULAR PIPE: Supplying, fabricating and fixing black Kg 31428.54 150.00 4,714,281.00
pipe (Square or circular) work /Truss with
15.2)MS PIPE: Supplying, fabricating and fixing metal
15.2 work of different angles MS Pipe with one coat primer as Kg 6920.24 150.00 1,038,036.00
shown in drawing all complete
15.3)ROLLING SHUTTER:
Providing and fixing rolling shutterof 16-19 Gauge cold
rolled MS lathe interlocked throughout their entire length
and joined together at the end by end locks and mounted on
specially designed pipe shaft with brackets, side guides and
15.3 arrangements for inside and outside locking,with push and Sq.m 50.77 4,000.00 203,080.00
pull operation, complete supplying, fixing and painting with
two coats of approved plastic emulsion paint.

15.4)HOT ROLLED STEEL


SECTION: Supplying, fabricating and fixing metal work of
15.4 different Hot Rolled Steel sections with one coat primer as Kg 0 150.00 -
per drawings and specifications all complete

15.5)METAL WORK,METAL
GATE: Supplying, fabricating and fixing in position, metal
gates of standard sections consisting of angles, pipes,
15.5 flats,etc. including one coat primer and one coat enamel Sq.M 11.96 7,000.00 83,720.00
paint as per drawings, specifications and instructions all
complete

15.6)FENCING WORK: Providing and fixing of ISA


50x50x5 mm along with 25x25x5 flat and M8x40 bolts at
12.3 300mm spacing to fix 10 S.W.G.G.I chain link with hole R.M 190 2,200.00 418,000.00
size 60x60 mm upto 3m height and 3 lines of barbed wire at
top.
16.1)EXPANSION JOINT WORKS/PLINTH LEVEL:
Suuply
and fixing of expansion joint at level of 100% non porous
flexible element allowing movement in all directions,
16.1 supported by aluminium framing and covering the top by R.M 10.675 4,500.00 48,037.50
aluminium sheet and flused to required floor level all
complete as per drawing, specification and instruction.

16.2)EXPANSION JOINT
WORKS/SLAB: Supply and fixing of expansion joint at
floor level of aluminium base supported by alumunium
16.2 framing,fixed on one side by threaded screw and flushed to R.M 29.7 4,500.00 133,650.00
required floor level and dimension all complete as per
drawing,specification and instruction

16.3)EXPANSION JOINT WORKS/ENDS OF WALL:


16.3 Supply R.M 114.05 4,500.00 513,225.00
17.1)CHAIN LINK VENTILATION
WORK: Supplying, fabricating and fixing in position of 10
S.W.G.I. woven wire ventilation with hollow square pipe
framing of size 18x18x1.0 mm on all sides with proper
17.1 welding on site, including one coat primer and one coat Sq.M 0 4,000.00 -
enamel paint on frames as per drawings, specifications and
instructions all complete

Prepared By: Checked By: Approved By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

TOTAL CIVIL WORK ABSTRACT OF COST


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

18.1)LAND DEVELOPMENT WORKS, INTERLOCKING


BLOCKS: Supplying and laying of 60 mm thick heavy duty
interlocking paving blocks of approved colour and quality
on the 50 mm thick stone dust with surface grading,
18.1 levelling and soil compaction base in driveways and parking Sq.M 280.84 2,000.00 561,680.00
areas, complete as per specifications and drawings.

18.2)RAILING WORKS: Supply,


fabrication and fitting of Railing works with MS square pipe
framing and 10 S.W.G.I. wire mesh of height 1.05m
18.2 including excavation, brickwork, plaster and two coats R.M 0 3,000.00 -
enamel paint all complete as per drawings and specifications

18.3)GUIDE RAMP: Supply,


fabrication and fitting of Guide Ramp-Utility Guardrail for
the disabled with MS tubular pipes at regular intervals of
18.3 height 1.05m including two coats enamel paint all complete R.M 29.45 6,500.00 191,425.00
as per drawings and specifications

18.4)APRON DRAIN: Construction of Apron drain along


the perimeter of buildings and retaining structures including
excavation, Brick soling, PCC and half brick thick apron 20.05 deducted due to
18.4 R.M 57.65 20,000.00 1,153,000.00
walls with plaster all complete as per drawings and over quantity
specifications
18.5)TACTILE PAVING: Providing
and laying approved brand quality, pattern and colour of
Tactile paving tile on floor over constructed cement mortar
18.5 of mix 1:3 backing and filling joints (epoxy grout) at R.M 0 3,500.00 -
straight path and turning points of size 300x300x40mm, all
complete as per drawings, specifications and instructions.

DEMOLITION WOKS: Demolition of existing building


19.1 and toilet blocks PS 1 1,000,000.00 1,000,000.00
RELOCATION WOKS: Relocation of temple from existing
site and to be constructed at a new location outside of the
20.1 school site as per drawing,specification and instructions. PS 0 300,000.00 -

INSURANCE PREMIUM
21.1 PS 1 224,281.00 224,281.00

Floor Hardener:providing,sprinkling,laying &applying


Manually two layer in floor,applied each layer with 1.5 to
2.5kg /m2 in required pattern,blended in,smoothed,over by
22.1 power trowelling,in line and level including curing all Sq.M 1379.03 400.00 551,612.00
complete as per drawing,specification and instruction.
(Mapetop,N,AR6 or equivalent)

Cement Board:providing and fixing in position 10mm


water proofed cement board in exterior (one side)surface
inclusive minimum75mm GI metal framewith grooving and
23.1 fixing of fastner ,washer,nuts,and bolts,all complete as per Sq.M 191.51 2,700.00 517,077.00
drawings,specifications and instructions.

FLOOR TILE (600*600)


24 Sq.M 318.59 2,500.00 796,475.00

ENAMEL PAINT
25 Sq.M 946.9 210.72 199,530.76

PILE WORK : Construction of pile work including


26 excavation, reinforcement and concreting work. Rm. 135.5 13,005.33 1,762,222.21

DISMANTLING WORK
27 0 -

CONCRETE DISMANTLING
27.1 Cu.M 21.8 8,500.00 -

BRICKWALL DISMANTLING
27.2 Cu.M 11.79 2,000.00 -

Micropiling work
28 R.m 288 2,653.58 764,231.04

TOTAL CIVIL WORKS

Prepared By: Checked By: Approved By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

TOTAL CIVIL WORK ABSTRACT OF COST


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

TOTAL AMOUNT
129,012,902.76

Total Item Price 129,012,902.76

Discount @2% 2,580,258.06

Sub Total 126,432,644.70

VAT @13% 16,436,243.81

Grand Total 142,868,888.52

Prepared By: Checked By: Approved By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks

Column
Column upto Plinth level
Column at F1 Sq.m. 9 2.15 1.2 23.22
Sq.m. 2 4.36 1.6 13.95 At grid A-A
Column at F2
Sq.m. 2 2.1 1.6 6.72
Column at F3
Sq.m. 7 4.26 1.6 47.71 At grid A-A
Column at F4
Sq.m. 6 2.05 1.6 19.68
Column at F5
Sq.m. 1 2 1.6 3.2
Sq.m. 2 4.21 1.6 13.47 At grid A-A
Column at F6 Sq.m. 2 1.85 1.6 5.92
Sq.m. 2 1.85 1.2 4.44
Deduction of beam face
Bottom tie beam Sq.m. -18 0.23 0.3 -1.25
Lower tie beam
Along grid A,B&C Sq.m. -54 0.23 0.3 -3.73
Along grid 1-11/A-C Sq.m. -44 0.23 0.3 -3.04
Plinth Beam
Along grid A,B&C Sq.m. -54 0.25 0.4 -5.4
Along grid 1-11/A-C Sq.m. -44 0.25 0.45 -4.95

Columns Above plinth level


400*400 column Sq.m. 22 9.525 1.6 335.28
Sq.m. 22 0.125 1.6 4.4 Truss lvl
300*300 column Sq.m. 11 9.525 1.2 125.73
Sq.m. 11 0.125 1.2 1.65 Truss Lvl
Deduction of beam faces
Along grid A,B&C Sq.m. -162 0.25 0.275 -11.14
Along grid 1-11/A-C Sq.m. -132 0.25 0.325 -10.73
Landing beam Sq.m. -4 0.25 0.4 -0.4

Slabs
First & Second floor slab Sq.m. 2 36.4 9.35 680.68
Sides Sq.m. 2 110.2 0.125 27.55
Deductions
Staircase void Sq.m. -2 4.15 4.95 -41.09
Columns area Sq.m. -44 0.4 0.4 -7.04
Sq.m. -22 0.3 0.3 -1.98

Staircase
Ground floor to first floor stair
First flight waist slab bottom Sq.m. 1 3.69 2 7.38
Sides of waist slab Sq.m. 2 3.69 0.325 2.39
Landing Sq.m. 1 4.15 1.65 6.84
Sq.m. 1 2 0.41 0.82
Sides of landing Sq.m. 1 4.27 0.175 0.74
Second flight waist slab bottom Sq.m. 1 3.27 2 6.54
Sides of waist slab Sq.m. 2 3.27 0.325 2.12
Step risers Sq.m. 22 2 0.15 6.6
Landing Beam bottom Sq.m. 1 4 0.25 1
Landing Beam Sides Sq.m. 1 4 0.625 2.5
First floor to Second floor stair
First flight waist slab bottom Sq.m. 1 3.69 2 7.38
Sides of waist slab Sq.m. 2 3.69 0.325 2.39
Landing Sq.m. 1 4.15 1.65 6.84

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
Sq.m. 1 2 0.41 0.82
Sides of landing Sq.m. 1 4.27 0.175 0.74
Second flight waist slab bottom Sq.m. 1 3.655 2 7.31
Sides of waist slab Sq.m. 2 3.655 0.325 2.37
Step risers Sq.m. 22 2 0.15 6.6
Landing Beam bottom Sq.m. 1 4 0.25 1
Landing Beam Sides Sq.m. 1 4 0.625 2.5

Bands
SILL BANDS
GROUND FLOOR
ALONG GRID 1/(A-B) Sq.m. 1 1.375 0.3 0.41
Sq.m. 1 3.525 0.15 0.52
ALONG GRID 3,5,6,7,9 &11/(A-B) Sq.m. 6 6.1 0.3 10.98
ALONG GRID A/1-11 Sq.m. 1 32 0.225 7.2
ALONG GRID B/1-11 Sq.m. 1 32 0.3 9.6
DEDUCTION Sq.m. 0
D Sq.m. -6 1.2 0.3 -2.16
D1 Sq.m. -1 1 0.3 -0.3
ALONG GRID B/1-2 Sq.m. -1 3.5 0.3 -1.05
ALONG GRID B/6-7 Sq.m. -1 4 0.3 -1.2
FIRST FLOOR 0
ALONG GRID1, 3,5,6,7,9 &11/(A-B) Sq.m. 7 6.1 0.3 12.81
ALONG GRID A/1-11 Sq.m. 1 32 0.225 7.2
ALONG GRID B/1-11 Sq.m. 1 32 0.3 9.6
DEDUCTION Sq.m. 0
D Sq.m. -8 1.2 0.3 -2.88
ALONG GRID B/6-7 Sq.m. -1 4 0.3 -1.2
SECOND FLOOR 0
ALONG GRID1, 3,5,6,7,8 &11/(A-B) Sq.m. 7 6.1 0.3 12.81
ALONG GRID A/1-11 Sq.m. 1 32 0.225 7.2
ALONG GRID B/1-11 Sq.m. 1 32 0.3 9.6
DEDUCTION 0
D Sq.m. -6 1.2 0.3 -2.16
D1 Sq.m. -1 1 0.3 -0.3
ALONG GRID B/6-7 Sq.m. -1 4 0.3 -1.2
AAC BLOCK(600*200*100) 0
Along x-Axis Sq.m. 1 7.125 0.3 2.13
Sq.m. 1 2.3 0.3 0.69
Along y-Axis Sq.m. 1 11 0.3 3.3
Store below staircase Sq.m. 1 3.4 0.3 0
AAC BLOCK(600*200*150) 0
Sleeping Room Wall Sq.m. 1 3.825 0.3 1.14
Sq.m. 1 3.6 0.3 1.08
LINTEL BANDS
GROUND FLOOR
ALONG GRID 1/(A-B) Sq.m. 1 1.375 0.15 0.41
ALONG GRID 3,5,6,7,9 &11/(A-B) Sq.m. 6 6.1 0.15 10.98
ALONG GRID A/1-3 Sq.m. 1 7 0.15 2.1
ALONG GRID B/1-11 Sq.m. 1 32 0.15 9.6

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
DEDUCTION
D Sq.m. -6 1.2 0.15 -2.16
D1 Sq.m. -1 1 0.15 -0.3
W1 Sq.m. -7 1.5 0.15 -3.15
ALONG GRID B/1-2 Sq.m. -1 3.5 0.15 -1.05
ALONG GRID B/6-7 Sq.m. -1 4 0.15 -1.2
FIRST FLOOR 0.15
ALONG GRID1, 3,5,6,7,9 &11/(A-B) Sq.m. 7 6.1 0.15 12.81
ALONG GRID B/1-11 Sq.m. 1 32 0.15 9.6
DEDUCTION Sq.m.
D Sq.m. -8 1.2 0.15 -2.88
ALONG GRID B/6-7 Sq.m. -1 4 0.15 -1.2
W1 Sq.m. -8 1.5 0.15 -3.6
SECOND FLOOR
ALONG GRID1, 3,5,6,7,8 &11/(A-B) Sq.m. 7 6.1 0.15 12.81
ALONG GRID B/1-11 Sq.m. 1 32 0.15 9.6
DEDUCTION
D Sq.m. -6 1.2 0.15 -2.16
D1 Sq.m. -1 1 0.15 -0.3
ALONG GRID B/6-7 Sq.m. -1 4 0.15 -1.2
W1 Sq.m. -6 1.5 0.15 -2.7
W2 Sq.m. -1 1.2 0.15 -0.36
W Sq.m. -1 3.5 0.15 -1.05
AAC BLOCK(600*200*100)
Along x-Axis Sq.m. 1 7.125 0.15 2.13
Sq.m. 1 2.3 0.15 0.69
Along y-Axis Sq.m. 1 11 0.15 3.3
AAC BLOCK(600*200*150)
Sleeping Room Wall Sq.m. 1 3.825 0.15 1.14
Sq.m. 1 3.6 0.15 1.08

Water Trough Slab Sq.m. 1 3.45 0.45 3.1


Water Trough Slab sides Sq.m. 1 3.9 0.1 0.78

Total Sq.m. 2283.33


8.1 REINFORCEMENT WORK
Foundations Kg 1 1952.25 1952.25
Columns Kg 1 18580.44 18580.44
Beams Kg 1 18097.83 18097.83
Slabs Kg 1 5892.52 5892.52
Staircase Kg 1 3472.32 3472.32
Bands Kg 1 1013.13 1013.13
Total Kg 49008.49
9 FLOORING WORK
9.1 PLASTIC LAYING
Rooms Sq.m. 8 3.65 6.25 182.5
Sq.m. 1 4.15 6.25 25.93
Passage Sq.m. 8 3.65 2.25 65.7
Sq.m. 1 4.15 2.25 9.33
Total Sq.m. 0
9.2 SCREEDING
Ground Floor
Class Room Nursery Sq.m. 1 7.7 6.425 49.47
Class Room L.K.G Sq.m. 1 7.7 6.425 49.47
Class Room U.K.G Sq.m. 1 7.7 6.425 49.47
Sleeping Room & Toilet Sq.m. 1 7.625 6.425 48.99

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
Passage Sq.m. 1 36.3 2.25 81.67
Steps Sq.m. 2 36.775 0.3 22.06
staircase
steps Sq.m. 22 2 0.3 13.2
Landing Sq.m. 1 4.15 2.075 8.61
Ground floor Lobby below staircase Sq.m. 1 7.1 4.15 29.46

First Floor
Class Room 1A Sq.m. 1 6.425 7.625 48.99
Class Room 1B Sq.m. 1 6.425 7.7 49.47
Class Room 2A Sq.m. 1 6.425 7.625 48.99
Class Room 2B Sq.m. 1 6.425 7.625 48.99
Passage Sq.m. 1 36.3 2.25 81.67
staircase
steps Sq.m. 22 2 0.3 13.2
Landing Sq.m. 1 4.15 2.075 8.61
Lobby Sq.m. 1 4.15 1.425 5.91
Second Floor
Class Room 3A Sq.m. 1 6.425 7.625 48.99
Class Room 3B Sq.m. 1 6.425 7.7 49.47
Multipurpose Hall Sq.m. 1 6.425 11.525 74.04
Teacher's Room Sq.m. 1 3.725 6.425 23.93
Passage Sq.m. 1 36.3 2.25 81.67
Lobby Sq.m. 1 4.15 1.425 5.91

TOTAL Sq.m. 942.24


9.3 CEMENT PUNNING
Ground Floor
Class Room Nursery Sq.m. 1 7.7 6.425 49.47
Class Room L.K.G Sq.m. 1 7.625 6.425 48.99
Class Room U.K.G Sq.m. 1 7.625 6.425 48.99
Sleeping Room Sq.m. 1 3.875 3.6 13.95
First Floor
Class Room 1A Sq.m. 1 6.425 7.625 48.99
Class Room 1B Sq.m. 1 6.425 7.7 49.47
Class Room 2A Sq.m. 1 6.425 7.625 48.99
Class Room 2B Sq.m. 1 6.425 7.625 48.99
Second Floor
Class Room 3A Sq.m. 1 6.425 7.625 48.99
Class Room 3B Sq.m. 1 6.425 7.7 49.47
Multipurpose Hall Sq.m. 1 6.425 11.525 74.04
Skirting Sq.m. 1 504.54 0.125 63.06

Front Steps Tread Sq.m. 1 36.775 0.6 22.06


Front Steps Riser Sq.m. 1 36.775 0.45 16.54
End sides of Wall Sq.m. 4 0.6 0.45 1.08

Total Sq.m. 633.08


9.4 CEMENT SKIRTING
Ground Floor
Class Room Nursery R.M. 1 27.45 27.45
Class Room L.K.G R.M. 1 27.3 27.3
Class Room U.K.G R.M. 1 27.3 27.3
Sleeping Room R.M. 1 14.15 14.15
Passage R.M. 1 22.9 22.9

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
Front column R.M. 1 8.7 8.7
Staircase area R.M. 1 17.35 17.35
Waist slab R.M. 1 16.42 16.42
First Floor
Class Room 1A R.M. 1 24.1 24.1
Class Room 1B R.M. 1 27.45 27.45
Class Room 2A R.M. 1 24.1 24.1
Class Room 2B R.M. 1 24.1 24.1
Passage R.M. 1 65.3 65.3
Staircase R.M. 1 20.57 20.57
Second Floor 0
Class Room 3A R.M. 1 27.3 27.3
Class Room 3B R.M. 1 27.45 27.45
Multipurpose Hall R.M. 1 35.9 35.9
Passage R.M. 1 66.7 66.7

Total R.M. 504.54


9.5 TILE LAYING ON FLOOR
Floor Tile
Total area of grid 1-3/A-B Sq.m. 1 7.6 6.6 50.16
Deduction
Pan area -8 0.58 0.43 -2
Sleeping room area Sq.m. -1 3.75 4.025 -15.1
100mm wall area Sq.m. -1 17.925 0.1 -1.8
Cement punning corridor Sq.m. -1 5.925 1 -5.93
Sq.m. -1 4.125 1.325 -5.47
Total Sq.m. 19.86
9.6 TILE LAYING ON TOILET
Wall Tile
Ground floor Toilet Sq.m. 4 4.15 1.3 21.58
Sq.m. 1 4.7 1.3 6.11
Sq.m. 1 7.25 1.3 9.42
Sq.m. 1 5.4 1.3 7.02
Sq.m. 1 3.9 1.3 5.07
Sq.m. 1 3.85 1.3 5
Sq.m. 1 8.2 1.3 10.66
Water Trough Sq.m. 1 3.4 0.4 1.36
Sq.m. 1 3.64 0.57 2.07
Sq.m.
Sq.m.

Total Sq.m. 68.29


10 FINISHING WORK
10.1 EXTERNAL PLASTER
Along grid A Sq.m. 1 37.75 11.75 443.56 Footing down
Along grid 11/A-B Sq.m. 1 7.05 10.35 72.96
Along grid 1/A-B Sq.m. 2 7.05 10.35 145.93
Along grid C Column Sq.m. 11 9.9 1.2 130.68 deduction of 4 columns due to failure
Deduction of beam coverage Sq.m. -54 0.25 0.4 -5.4
Sq.m. -33 0.25 0.45 -3.72
Deduction of column at grid 5-6 Sq.m. -2 9.9 0.3 -5.94
Beam along grid C/1-11 Sq.m. 3 32.9 0.275 27.14
Beam along grid B-C/1&11 Sq.m. 2 6.45 0.325 4.19
Perifery slab top Sq.m. 2 62.9 0.275 34.59
Wall along grid C /1-11 in FF & SF Sq.m. 2 32.9 1 65.8
Wall along grid 1&11 /B-C in FF & SF
Sq.m. 2 4.3 1 8.6

Deduction of openings 0
W1 Sq.m. -22 3.5 1.985 -152.85
V Sq.m. -2 3.5 0.65 -4.55
V3 Sq.m. -2 2 1.25 -5
Opening along grid 1/A-B Sq.m. -1 1.2 2.85 -3.42
Sq.m. -1 3.525 1.85 -6.53

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks

Front Steps Sq.m. 1 36.775 0.45 16.54


Steps sides support wall Sq.m. 4 0.6 0.45 1.08
Water Trough wall Sq.m. 2 1.13 0.75 1.69
Water Trough slab bottom Sq.m. 1 3.45 0.45 1.55
Water Trough slab Sides Sq.m. 1 4.35 0.41 1.78

Total Sq.m. 768.68


10.2 INTERNAL PLASTER
Ground Floor
Inside grid A-B/1-3
Along grid 1/A-B Sq.m. 1 3.725 1.2 4.47
Sq.m. 1 1.575 2.85 4.48
On wall 600*100*100
Along grid B/ 1-2 Sq.m. 1 2.4 2.9 6.96
internal wall 600*100*100 Sq.m. 1 37.05 2.1 77.8
Top bands Sq.m. 1 22.95 0.25 5.73
Top bands above door D3 &D4 Sq.m. 1 7.65 0.234 1.79
On wall 600*150*100 Sq.m. 1 7.5 2.85 21.37
Sq.m. 1 7.2 3.175 22.86
On 600*200*200 wall Sq.m. 1 14.95 2.85 42.6
Column copla Sq.m. 13 2.9 0.2 7.54

Along grid 3,5,6,7,9&11/A-B Sq.m. 8 6.1 2.85 139.08


Along grid A/3-11 Sq.m. 1 25 2.9 72.5
Along grid B/3-12 Sq.m. 1 21 2.9 60.9
Along grdi B/1-11 Sq.m. 1 31.2 2.9 90.48
Column copla Sq.m. 42 3.175 0.2 26.67
Sq.m. 2 3.175 0.4 2.54
Staircase riser Sq.m. 22 2 0.15 6.6
Perifery
W Sq.m. 6 10.97 0.2 13.16
W1 Sq.m. 7 6.97 0.2 9.75
D Sq.m. 6 5.8 0.2 6.96
D1 Sq.m. 1 5.8 0.2 1.16
Deductions
W Sq.m. -6 3.5 1.985 -41.69
W1 Sq.m. -7 1.5 1.985 -20.85
D Sq.m. -6 1.2 2.9 -20.88
D1 Sq.m. -1 1 2.9 -2.9

First Floor
Along grid 1,3,5,6,7,9&11/A-B Sq.m. 10 6.1 2.85 173.85
Along grid A/1-11 Sq.m. 1 32 2.9 92.8
Along grid B( Both sides) Sq.m. 2 28 2.9 162.4
Column copla Sq.m. 54 0.2 3.175 34.29
Sq.m. 21 0.4 3.175 26.67
Staircase riser Sq.m. 22 2 0.15 6.6
Perifery
W Sq.m. 8 10.97 0.2 17.55
W1 Sq.m. 8 6.97 0.2 11.15
D Sq.m. 8 5.8 0.2 9.28
V3 Sq.m. 1 6.5 0.2 1.3
Deduction
W Sq.m. -8 3.5 1.985 -55.58
W1 Sq.m. -8 1.5 1.985 -23.82
D Sq.m. -8 1.2 2.9 -27.84
V3 Sq.m. -1 2 1.25 -2.5

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
Second Floor
Along grid 1,3,5,6,8&11/A-B Sq.m. 10 6.1 2.85 173.85
Along grid A/1-11 Sq.m. 1 32 2.9 92.8
Along grid B( Both sides) Sq.m. 2 28 2.9 162.4
Column copla Sq.m. 54 0.2 3.175 34.29
Sq.m. 21 0.4 3.175 26.67
Perifery
W Sq.m. 9 10.97 0.2 19.74
W1 Sq.m. 6 6.97 0.2 8.36
W2 Sq.m. 1 6.37 0.2 1.27
D Sq.m. 6 5.8 0.2 6.96
D1 Sq.m. 1 5.8 0.2 1.16
V3 Sq.m. 1 6.5 0.2 1.3
Deduction
W Sq.m. -9 3.5 1.985 -62.53
W1 Sq.m. -6 1.5 1.985 -17.87
W2 Sq.m. -1 1.2 1.985 -2.39
D Sq.m. -6 1.2 2.9 -20.88
D1 Sq.m. -1 1 2.9 -2.9
V3 Sq.m. -1 2 1.25 -2.5
Total Sq.m. 1384.96
10.3 CEILING PLASTER
Ground floor
Along grid 1-11/A-C Sq.m. 1 36.4 9.35 340.34
Beam Sides
Main beam along grid A/ 1-11 Sq.m. 1 32 0.275 8.8
Main beam Along grid B/1-11 Sq.m. 2 32 0.275 17.6
Main beam Along grid C/1-11 Sq.m. 1 32.9 0.275 9.04
Main beam along grid 1-11/A-C Sq.m. 18 8.25 0.325 48.26
Secondary beam along gid X-X Sq.m. 2 29.2 0.175 10.22
Secondary beam on staircase section Sq.m. 2 4.15 0.175 1.45
Staircase
First flight waist slab Sq.m. 1 3.655 2 7.31
Sides of first flight Sq.m. 1 3.655 0.175 0.63
Sq.m. 11 0.3 0.075 0.24
Landing Sq.m. 1 4.15 1.65 6.84
Sq.m. 1 2 0.41 0.82
Second flight waist slab Sq.m. 1 3.27 2 6.54
Sides of second flight waist slab Sq.m. 1 3.27 0.175 0.57
Sq.m. 11 0.3 0.075 0.24
Top landing Sq.m. 1 4.15 1.3 5.39
Sq.m. 1 2 0.04 0.08
Deduction
Column area coverage Sq.m. -22 0.4 0.4 -3.52
Sq.m. -11 0.3 0.3 -0.99
Staircase void Sq.m. -1 4.15 6.5 -26.98
Internal wall
600*200*200 wall
ALONG GRID 1(A-B) Sq.m -1 1.375 0.2 -0.28
ALONG GRID 3,5,6,7,9 &11/(A-B) Sq.m -6 6.1 0.2 -7.32
ALONG GRID A/1-11 Sq.m -1 4 0.2 -0.8
ALONG GRID B/1-11 Sq.m -1 5.8 1.2 -6.96
600*200*150 wall
Sleeping Room Wall Sq.m. -11 3.825 0.15 -6.32
Sq.m. -1 3.6 0.15 -0.54

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
First floor
Along grid 1-11/A-C Sq.m. 1 36.4 9.35 340.34
Beam Sides
Main beam along grid A/ 1-11 Sq.m. 1 32 0.275 8.8
Main beam Along grid B/1-11 Sq.m. 2 32 0.275 17.6
Main beam Along grid C/1-11 Sq.m. 1 32.9 0.275 9.04
Main beam along grid 1-11/A-C Sq.m. 18 8.25 0.325 48.26
Secondary beam along gid X-X Sq.m. 2 29.2 0.175 10.22
Secondary beam on staircase section Sq.m. 2 4.15 0.175 1.45
Staircase
First flight waist slab Sq.m. 1 3.655 2 7.31
Sides of first flight Sq.m. 1 3.655 0.175 0.63
Sq.m. 11 0.3 0.075 0.24
Landing Sq.m. 1 4.15 1.65 6.84
Sq.m. 1 2 0.41 0.82
Second flight waist slab Sq.m. 1 3.27 2 6.54
Sides of second flight waist slab Sq.m. 1 3.27 0.175 0.57
Sq.m. 11 0.3 0.075 0.24
Top landing Sq.m. 1 4.15 1.3 5.39
Deduction
Column area coverage Sq.m. -22 0.4 0.4 -3.52
Sq.m. -11 0.3 0.3 -0.99
Staircase void Sq.m. -1 4.15 6.5 -26.98
Internal wall
600*200*200 wall
ALONG GRID 1,3,5,6,7,9 &11/(A-B) Sq.m -7 6.1 0.2 -8.54
ALONG GRID A/1-11 Sq.m -1 4 0.2 -0.8
ALONG GRID B/1-11 Sq.m -1 6.7 0.2 -1.34

Second Floor
Beam Sides & Bottom
Main beam along grid A/ 1-11 Sq.m. 1 32 0.525 16.8
Main beam Along grid B/1-11 Sq.m. 2 32 0.525 33.6
Main beam Along grid C/1-11 Sq.m. 1 32.9 0.525 17.27
Main beam along grid 1-11/A-C Sq.m. 18 8.25 0.575 85.38
Deductions
Wall area coverage along grid A/1-11 Sq.m. -1 4 0.2 -0.8
Wall area coverage along grid B/1-11 Sq.m. -1 5.87 0.2 -1.18
Wall area coverage along grid
1,3,5,6,7,8&11/A-B Sq.m. -6 6.1 0.2 -7.32
Total Sq.m. 976.53
10.4 PLASTER ON RCC LINTEL WITH
CORNICE
Ground Floor
Slab R.M. 1 81.9 0
W R.M. 6 3.5 21
V R.M. 2 3.5 7
First Floor
Slab R.M. 1 81.9 0
W R.M. 8 3.5 28
V3 R.M. 1 2 2
Second Floor R.M.
W R.M. 8 3.5 28
V3 R.M. 1 2 2
Total R.M. 0
10.5 EMULSION PAINT
Total internal plaster area Sq.m. 1384.96
Total ceiling plaster area Sq.m. 976.53
Deductions
Wall tile area Sq.m. -68.29
Total Sq.m. 2293.2
10.6 WEATHERCOAT PAINT
Total external plaster area Sq.m. 768.68
Total RCC lintel with cornices area Sq.m. 0
Cement Board area Sq.m. 39.84
Total Sq.m. 808.52

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
11 DOOR, WINDOWS WORK
11.1 UPVC SLIDING WINDOWS
Ground Floor
W Sq.m. 6 3.5 1.985 41.68
W1 Sq.m. 7 1.5 1.985 20.84
First Floor
W Sq.m. 8 3.5 1.985 55.58
W1 Sq.m. 7 1.5 1.985 20.84
W2 Sq.m. 1 1.2 1.985 2.38
Second Floor
W Sq.m. 9 3.5 1.985 62.52
W1 Sq.m. 6 1.5 1.985 17.86
W2 Sq.m. 1 1.2 1.985 2.38
Total Sq.m. 224.08
11.2 UPVC TOP HUNG WINDOWS
V Sq.m. 2 3.5 0.65 4.55
V3 Sq.m. 2 2 1.25 5
Total Sq.m. 9.55
11.3 UPVC DOUBLE DOOR
GROUND FLOOR
D Sq.m. 6 1.2 2.9 20.88
D4 Sq.m. 1 0.9 2.1 1.89
FIRST FLOOR
D Sq.m. 8 1.2 2.9 27.84
SECOND FLOOR
D Sq.m. 6 1.2 2.9 20.88
Total Sq.m. 71.49
11.4 UPVC SINGLE DOOR
GROUND FLOOR
D1 Sq.m. 1 1 2.9 2.9
D3 Sq.m. 9 0.75 2.1 14.17
SECOND FLOOR
D1 Sq.m. 1 1 2.9 2.9
Total Sq.m. 19.97
12 ROOFING WORK
12.1 CGI ROOFING SHEET
Sq.m. 2 38.275 5.89 450.87
Total Sq.m. 450.87
12.2 CGI ROOFING SHEET ON RIDGE
Rm. 1 38.275 38.275
TOTAL Sq.m. 38.275
12.3 GI GUTTER
Rm. 2 38.275 76.55
TOTAL Sq.m. 76.55
13.1 FLASE CEILING WORK PVC BOARD

Along grid A-B/1-11 Sq.m. 8 6.25 3.65 182.5


Sq.m. 1 6.25 4.15 25.93
Along grid B-C/1-11 Sq.m. 8 2.25 3.65 65.7
Sq.m. 1 2.25 4.15 9.33
Total Sq.m. 283.46
14 MISCELLANEOUS WORK
14.2 INSULATION WORK
Along grid 1-5/A-C Sq.m. 2 16 4.817 154.14
Along grid 6-11/A-C Sq.m. 2 20.4 4.817 196.53
Total Sq.m. 350.67
15 METAL WORK
15.1 BLACK TUBULAR PIPE
Description of Work Total l Unit wt.
Bottom Chord NB 50(M) Kg. 30 4.643 139.29 5.03 700.62
Vertical Bracing NB 40(M) Kg. 30 0.425 12.75 3.56 45.39
Kg. 30 0.851 25.53 3.56 90.88
Kg. 30 1.191 35.73 3.56 127.19
Kg. 30 1.487 44.61 3.56 158.81
Inclined Bracing NB 32(M) Kg. 30 1.221 36.63 3.09 113.18
Kg. 30 1.279 38.37 3.09 118.56
Kg. 30 1.46 43.8 3.09 135.34
Inclined Bracing NB 40(M) (wind clit) Kg. 16 2.15 34.4 3.56 122.46
Top Chord NB 50(M) Kg. 30 5.871 176.13 5.03 885.93
Purlin NB 65(M)
Grid 1-5 Kg. 72 2.57 185.04 6.44 1191.65
Grid 6-11 Kg. 84 2.827 237.46 6.44 1529.24
Beyond grid 1 & 11 Kg. 24 1.085 26.04 6.44 167.69
Between grid 5-6 Kg. 12 0.395 4.74 6.44 30.52
Runner NB 40(M) Kg.
Grid 1-5 Kg. 12 2.38 28.56 3.56 101.67
Grid 6-11 Kg. 14 2.637 36.91 3.56 131.39
Connections
Base Plate Volume
At column (300*300*10) Kg. 30 0.0009 7850 211.95
At beam(250*250*10) Kg. 60 0.000625 7850 294.37
Nut Kg. 180 0.00000826236 7850 11.67
16mm Dia anchord Bolt Kg. 180 0.45 81 1.58 127.98
ISA 50*50*10 Kg. 90 0.3 27 3.8 102.6
50*75mm plate stiffner Kg. 90 0.0000375 7850 26.49
Bottom Chord
Volume
10mm thick plate (175*175) Kg. 30 0.00030625 7850 72.12
10mm thick stiffner(63*63) Kg. 120 0.00003969 7850 37.38
4nos-16mm Boults Kg. 60 wt. per pcs 0.16 9.6
Runner Plate Connection
Runner Box (175*75mm outer size)
175*68.3*10mm runner box Kg. 4 2.47 9.88
Volume
175*68.3*10mm runner plate Kg. 4 0.000119525 7850 3.75
2nos-16mm dia bolts Kg. 8 wt. per pcs 0.16 1.28
At middle
175*68.3*10mm runner box Kg. 44 2.47 108.68
Volume
175*68.3*10mm runner plate Kg. 44 0.000119525 7850 41.28
2nos-16mm dia bolts Kg. 88 wt. per pcs 0.16 14.08
Purlin Cleat Connection

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
Volume
Top Chord Cleat 200*90*10 Kg. 540 0.00018 7850 763.02
2nos-16mm bolts Kg. 360 wt. per pcs 0.16 57.6
Top Ridge Connection
Volume
2 nos -10mm thick 175*175 mm plate Kg. 30 0.00030625 7850 72.12
10mm thick stiffners(57*59) Kg. 120 0.00003363 7850 31.67
16mm dia Nut bolts Kg. 60 wt. per pcs 0.16 9.6
Truss Cleat for wind Ties
Volume
Wind Tie Cleat(100*100*6) Kg. 32 0.00006 7850 15.07
MS Flat 165*80*6 Kg. 64 0.0000792 7850 39.79
MS Flat 380*80*6mm Kg. 16 0.0001824 7850 22.9
20mm dia Nut bolts Kg. 32 wt. per pcs 0.21 6.72
16mm dia Nut bolts Kg. 40 wt. per pcs 0.16 6.4
Total Kg. 7748.52
15.2 MS PIPE
Unit Lot No L Unit wt. Quantity
Windows Railing Work
First Floor
MS Base Plate (600*50*5mm) Kg. 8 2 0.00015 7850 18.84
Vol.
MS Base Plate (85*50*5mm) Kg. 8 3 0.00002125 7850 4
Vol.
25.4*25.4*2.6mm MS Post Kg. 8 3 0.58095 1.69 23.56
18*18*2mm MS pipe Kg. 8 3 3.42 1.0048 82.56
38.1*38.1*3.2mm MS pipe Kg. 8 1 3.5 3.29 92.12
Second Floor
MS Base Plate (600*50*5mm) Kg. 8 2 0.00015 7850 18.84
Vol.
MS Base Plate (85*50*5mm) Kg. 8 3 0.00002125 7850 4
Vol.
25.4*25.4*2.6mm MS Post Kg. 8 3 0.58095 1.69 23.56
18*18*2mm MS pipe Kg. 8 3 3.42 1.0048 82.56
38.1*38.1*3.2mm MS pipe Kg. 8 1 3.5 3.29 92.12

Staircase Railing
Ground Floor to First Floor
NB 40 MS Round Pipe Kg. 1 1 8.29 3.56 29.51
38.1*38.1*3.2mm MS Vertical pipe Kg. 1 8 0.92 3.29 24.21
18*18*2 mm MS Pipe Kg. 1 4 7.9852 1.0048 32.09
125*125*5 mm Base Plate Kg. 1 8 7.8125E-05 7850 4.9
Vol.
First Floor to Second Floor
NB 40 MS Round Pipe Kg. 1 1 10.06 3.56 35.81
38.1*38.1*3.2mm MS Vertical pipe Kg. 1 10 0.92 3.29 30.26
18*18*2 mm MS Pipe Kg. 1 4 9.679 1.0048 38.9
125*125*5 mm Base Plate Kg. 1 10 7.8125E-05 7850 6.13
Vol.
Balcony Railing
First Floor
Along Grid 1&11/B-C
38.1*38.1*3.2mm MS Pipe Kg. 2 1 2.15 3.29 14.14
25.4*25.4*2.6mm MS Pipe Kg. 2 2 1.95 1.69 13.18
25.4*25.4*2.6mm MS Post Kg. 2 3 0.822 1.69 8.33
18*18*2mm MS pipe Kg. 2 18 0.437 1.0048 15.8
125*125*5mm Plate Kg. 2 2 7.8125E-05 7800 2.43
Kg. Vol.
Along grid C/1-2,2-3,3-4,4-5,7-8,8-9,9-10,10-
11
38.1*38.1*3.2mm MS Pipe Kg. 8 1 3.6 3.29 94.75
25.4*25.4*2.6mm MS Pipe Kg. 8 2 3.4 1.69 91.93
25.4*25.4*2.6mm MS Post Kg. 8 4 0.822 1.69 44.45
18*18*2mm MS pipe Kg. 8 33 0.437 1.0048 115.92
125*125*5mm Plate Kg. 8 2 7.8125E-05 7800 9.75
Vol.
Along Grid C/6-7
38.1*38.1*3.2mm MS Pipe Kg. 1 1 4.1 3.29 13.48
25.4*25.4*2.6mm MS Pipe Kg. 1 2 3.9 1.69 13.18
25.4*25.4*2.6mm MS Post Kg. 1 4 0.822 1.69 5.55
18*18*2mm MS pipe Kg. 1 36 0.437 1.0048 15.8
125*125*5mm Plate Kg. 1 2 7.8125E-05 7800 1.21
Second Floor Vol.
Along Grid 1&11/B-C
38.1*38.1*3.2mm MS Pipe Kg. 2 1 2.15 3.29 14.14
25.4*25.4*2.6mm MS Pipe Kg. 2 2 1.95 1.69 13.18
25.4*25.4*2.6mm MS Post Kg. 2 3 0.822 1.69 8.33
18*18*2mm MS pipe Kg. 2 18 0.437 1.0048 15.8
125*125*5mm Plate Kg. 2 2 7.8125E-05 7800 2.43
Vol.
Along grid C/1-2,2-3,3-4,4-5,7-8,8-9,9-10,10-
11
38.1*38.1*3.2mm MS Pipe Kg. 8 1 3.6 3.29 94.75
25.4*25.4*2.6mm MS Pipe Kg. 8 2 3.4 1.69 91.93
25.4*25.4*2.6mm MS Post Kg. 8 4 0.822 1.69 44.45
18*18*2mm MS pipe Kg. 8 33 0.437 1.0048 115.92
125*125*5mm Plate Kg. 8 2 7.8125E-05 7800 9.75
Vol.
Along Grid C/6-7
38.1*38.1*3.2mm MS Pipe Kg. 1 1 4.1 3.29 13.48
25.4*25.4*2.6mm MS Pipe Kg. 1 2 3.9 1.69 13.18
25.4*25.4*2.6mm MS Post Kg. 1 4 0.822 1.69 5.55
18*18*2mm MS pipe Kg. 1 36 0.437 1.0048 15.8
125*125*5mm Plate Kg. 1 2 7.8125E-05 7800 1.21
Vol.
TOTAL MS PIPE Kg. 1563.77 poor finishing
16.1 Expansion joint
Plinth level
Ground floor Rm 1 2.15 2.15
Total Rm 2.15

16.2 Slab
Ground floor slab Rm 1 8.25 8.25

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
First floor slab Rm 1 8.25 8.25
Total Rm 16.5
16.3 Ends of Wall
Front face from Gl to Top level Rm 1 10.4 10.4
Backside column fron backside GL to top
level Rm 1 12.35 12.35
inside vertical column face (GF,1F,2F) Rm 1 17.1 17.1
Total Rm 39.85 poor finishing/seems gap

18.2 Guide Ramp Rm 1 6.6 6.6


Total 6.6
22 Floor Hardener
Ground Floor

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB PRIMARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
Passage Sq.m. 1 36.3 2.45 88.93
Toilet Passage Sq.m. 1 4.6 1 4.6
Sq.m. 1 5.225 1.325 6.92
staircase
steps Sq.m. 22 2 0.3 13.2
Riser Sq.m. 20 2 0.15 6
Landing Sq.m. 1 4.15 2.075 8.61
Lobby Sq.m. 1 7.1 4.15 29.46

First Floor
Passage Sq.m. 1 36.3 2.45 88.93
staircase
steps Sq.m. 22 2 0.3 13.2
Riser Sq.m. 20 2 0.15 6
Landing Sq.m. 1 4.15 2.075 8.61
Lobby Sq.m. 1 4.15 1.425 5.91
Second Floor
Passage Sq.m. 1 36.3 2.45 88.93
Lobby Sq.m. 1 4.15 1.425 5.91
TOTAL Sq.m. 375.21 poor finishing/Cracks

23 Cement Board
Gable Wall Sq.m. 2 9.325 1.76 16.41
Gap filling Sq.m. 2 36.475 0.6 21.88
Belowe ceiling beam gap in passage Sq.m. 2 2.15 0.725 1.55
TOTAL Sq.m. 39.84
24 FLOOR TILE (600*600)
Second Floor
Teacher's Room Sq.m. 1 3.725 6.425 23.93
Skirting Sq.m. 1 19.3 0.125 2.41
TOTAL TILE (600*600) Sq.m. 26.34
25 ENAMEL PAINT
Windows grill Sq.m. 16 7 0.62 69.44
Passage Grill Sq.m. 2 74.4 0.65 96.72
Staircase railing Sq.m. 1 36.7 0.95 34.86
Chain gate Sq.m. 1 7.9 2.9 22.91

Sq.m. 223.93

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST PRIMARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
GENERAL WORK, SITE CLEARANCE:Clearing and
grubbing of site for construction including uprooting of
1.10 vegetation, grass, brush wood, trees and sapplings of girth Sq.M 535.65 100.00 53,565.00
upto 300 mm & removal upto a distance of 50 m as per
drawings, specifications and instructions

EARTHWORK IN EXCAVATION: Earthwork in


2.10 excavation in trenches, pits and foundations by machine or Cu.M 528.17 200.00 105,634.00
appropriate technology in soft soil including existing debris
and brick bats of old structure, if any, upto specified depth
EARTWORK IN FILLING: Providing and placing of
random filling of excavated earth from cutting of slope and
stacked at site in 150mm thick layer in trenches, plinth or
under floor, sides of foundation and below beam at footing
2.20 Cu.M 426.45 200.00 85,290.00
covered area etc. including watering, mechanical ramming
and compaction of each layer, consolidation and dressing,
all complete as per drawings, specifications and instructions.

SAND FILLING: Sand filling in plinth under floors,


including watering, ramming, consolidating and dressing, all
2.30 complete as per drawings, specifications and instructions. Cu.M - 2,500.00 -

STONE WORK : Dry stone soling work in line and level,


including packing joints with sand dust, all complete as per
3.10 drawings, specifications and instructions Cu.M 10.88 4,000.00 43,520.00

STONE MASONRY WALL: Stone rubble masonry work in


1:4 cement and sand mortar with hard, tough, sound and
durable stone in wall, made to required line, level, shape,
3.20 size and plumb including setting out, drain outlet, curing of Cu.M - 7,500.00 -
the works and scaffolding etc. complete as per drawings,
specifications and instructions

BRICK WORK,FLAT BRICK SOLING: Flat brick soling


of local chimney bricks laid in line and level, including
4.10 packing joints with sand, complete as per drawings, Sq.M 429.20 800.00 343,360.00
specifications and instructions
FULL BRICK WORK: Brickwork in substructure and super
4.20 structure cement and sand mortar of mix 1:6 with first class Cu.M 69.02 15,000.00 1,035,300.00
chimney-made bricks, in any size and shape of wall, made
to required line, level, shape and plumb including setting
AAC(Autoclaved Aerated Concrete) BLOCK WORK:
5.10 Providing and laying of Autoclaved Aerated Concrete Block Sq.M 559.82 1,800.00 1,007,676.00
(600*200*200 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2)AAC(Autoclaved Aerated Concrete) BLOCK WORK:
Providing and laying of Autoclaved Aerated Concrete Block
(600*200*100 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.20 required line, level, shape and plumb including setting out, Sq.M 42.20 2,000.00 84,400.00
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

5.3)AAC(Autoclaved Aerated Concrete) BLOCK WORK:


Providing and laying of Autoclaved Aerated Concrete Block
(600*200*150 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.30 required line, level, shape and plumb including setting out, Sq.M 21.21 1,100.00 23,331.00
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

CONCRETE WORK,PCC OF GRADE M10: Plain cement


concrete (PCC) of grade M10 (1:3:6 with 1 cement, 3 coarse
sand and 6 aggregate of 19 mm and down grade) in
6.10 foundation base including mixing, laying, compacting, Cu.M 36.19 10,000.00 361,900.00
finishing, curing, laid to exact line, level and dimensions,
inclusive ofside

PCC FOR RCC OF GRADE M25: Structural concrete (PCC


for RCC) of Grade M25 (1:1:2)works with approved
quality of cement, sand and well graded aggregate in any
form, size, shape and level including batching and mixing
6.20 with machine, laying including compaction with vibrating Cu.M 57.75 20,000.00 1,155,000.00
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

PCC FOR RCC OF GRADE M20: Structural concrete (PCC


for RCC) of Grade M20 (1:1.5:3)works with approved
quality of cement, sand and well graded aggregate in any
6.30 form, size, shape and level including batching and mixing Cu.M 244.45 17,000.00 4,155,650.00
with machine, laying including compaction with vibrating
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

FORMWORK: Placing plyboard form work with steel


props, shuttering, centering in horizontal/Vertical surfaces
like slab, beams, column, wall, stair etc. for all RCC works
7.10 of any shape, size and at any level and removal after Sq.M 2,283.33 850.00 1,940,830.50
completion

REINFORCEMENT WORK: Providing and placing steel


reinforcement bar tested grade Fe-500 equivalent NS, for
8.10 RCC work including bending, binding with anneal wire and kg 49,008.49 110.00 5,390,933.90
placing in position, all complete as per drawings,
specifications and instruction

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST PRIMARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
9.1)FLOORING WORK,PLASTIC
9.10 LAYING: Supplying and laying 500 gauge plastic sheet in Sq.M - 50.00 -
floor as per specificatio and instruction
9.2)SCREEDING: Providing and placing 38 mm thick Plain
cement concrete of grade M15 (1:2:4 with 1 cement, 2
coarse sand and 4 aggregate chips) in the floor base mixing,
laying, compacting, finishing, curing, laid to exact line level
9.20 , surface chipping and dimensions (floor concrete is laid in Sq.M 942.24 500.00 471,120.00
alternate panels of 1 m x 1 m) inclusive of shuttering
complete as per drawings, specifications and instructions

9.3)CEMENT PUNNING: Providing


and laying 3 mm cement punning in floor , laying in
9.30 Sq.M 633.08 200.00 126,616.00
required pattern, line

9.4)CEMENT SKIRTING: Providing


and placing cement skirting 125mm height of grade M15
(1:2:4 with cement, 2 coarse sand and 4 aggregate
) in wall ,mixing, laying, compactig, finishing, curing, laid
9.40 to exact line level and dimension all complete as per R.M 504.54 100.00 50,454.00
drawing, specification and instructions

9.5)TILE LAYING ON FLOOR:


Providing and laying approved brand quality, pattern and
color, ceramic mat finish tile (Low range) on floor over
9.50 cement mortar of mix 1:3 backing and filling joints (epoxy Sq.M 19.86 2,800.00 55,608.00
grout) complete as per drawings, specifications and
instructions.(Base rate: NRs 100)

9.6)TILE LAYING ON TOILET:


Providing and laying approved brand quality, pattern and
color, ceramic glazed tile in wall and ceramic mat finish tile
9.60 (Low range) on floor of toilet over cement mortar of mix 1:3 Sq.M 68.29 3,000.00 204,870.00
backing and filling joints (epoxy grout) complete as per
drawings, specifications and instructions.(Base rate: NRs
100)

10.1)FINISHING WORK,
EXTERNAL PLASTER: Providing and applying '10.5 mm
thick cement plastering with 1cement : 4 sand mortar in
outer surface any level size and shape of wall, column,
10.10 ceiling, band, blocks, etc inclusive of waterproofing Sq.M 768.68 400.00 307,472.00
compound, dusting, throating, etc as required including
racking, hacking, watering, cleaning of base, plastering to
plumb, line, level, smooth etc. and curing complete as per
drawings, specifications and instructions.
10.2)INTERNAL PLASTER:
Providing and applying'10.5 mm thick cement plastering
with 1cement : 4 sand mortar in inner surface except ceiling
any level size and shape of wall, column, band, blocks, etc
inclusive of dusting, throating, etc as required including
10.20 racking, watering, hacking, cleaning of base, plastering to Sq.M 1,384.96 450.00 623,232.00
plumb, line, level, smooth etc. and curing, all complete as
per drawings, specifications and instructions.

10.3)CEILING PLASTER: Providing


and applying 12.5 mm thick cement plastering with 1cement
10.30 : 4 sand mortar in Ceiling any level size and shape of Sq.M 976.53 500.00 488,265.00
ceiling inclusive of dusting,
10.4)PLASTER ON RCC LINTEL
WITH CORNICE: 'Providing and applying 12.5 mm thick
cement plastering with 1cement : 4 sand mortar in RCC
Lintel with cornice inclusive of dusting, throating, etc as
required including racking, watering, cleaning of base,
10.40 plastering to plumb, line, level, smooth etc. and curing, all R.M - 3,000.00 -
complete as per drawings, specifications and instructions.

10.5)EMULSION PAINT: Providing


and applyibg two coat of emulsion paint in mat finishing
10.50 over two coat of primer, finished including surface Sq.M 2,293.20 200.00 458,640.00
preparation all complete as per drawings, specifications and
instruction
10.6)WEATHER COAT: Providing and applying two coat
of weather coat (Apex or equivalent) over required coat of
10.60 primer, finished including surface preparation all complete Sq.M 808.52 250.00 202,130.00
as per drawings, specifications and instruction

11.1)DOOR,WINDOWS WORK/UPVC SLIDING


WINDOWS: Providing and fixing standard UPVC sliding
window without net (frame 50x80mm, sash 58x36mm white
11.10 colour with 5mm glass) along with patented standard Sq.M 224.08 8,000.00 1,792,640.00
hardwares like roller, gaskets, brush seal, moon locks etc all
complete as per drawings and specifications.

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST PRIMARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
11.2)UPVC TOP HUNG
WINDOWS: Providing and fixing standard UPVC top hung
window (frame 60x60 mm, sash 60x104 mm, white colour
11.20 with 5 mm glass) along with patented standard hardwares Sq.M 9.55 8,000.00 76,400.00
like roller, gaskets, brush seal, moon locks etc all complete
as per drawings and specifications.

11.3)UPVC DOUBLE DOOR:


Providing and fixing standard UPVC double door (frame
60x60mm, sash 60x104mm white colour with 5mm glass)
11.30 along with patented standard hardwares like roller, gaskets, Sq.M 71.49 10,000.00 714,900.00
brush seal, moon locks etc all complete as per drawings and
specifications.

11.4)UPVC SINGLE DOOR:


Providing and fixing standard UPVC single door with full
panel (frame60x60mm, sash 60x104mm white colour with
11.40 5mm glass) along with patented standard hardwares like Sq.M 19.97 7,000.00 139,790.00
roller, gaskets, brush seal, moon locks etc all complete as
per drawings and specifications.

12.1)ROOFING WORK,CGI
ROOFING SHEET: Providing and fixing in position 24
gauge medium (0 .5 mm thick) corrugated CGI sheet over
12.10 roof truss with minimum 80 mm side laps and 200 mm end Sq.M 450.87 1,319.17 594,774.17
laps, inclusive of nuts and bolts, 8 mm 'J' hooks, washers,
GI cup washers, all complete as per drawings, specifications
and instruction

12.2)CGI ROOFING SHEET ON


RIDGE: Providing and fixing in position 24 gauge medium
(0 .5 mm thick) CGI sheet over roof truss in ridge with
12.20 minimum 80 mm side laps and 200 mm end laps, inclusive R.m 38.28 1,009.52 38,639.37
of nuts and bolts, washers, GI cup washers, all complete as
per drawings, specifications and instruction

12.3)GI GUTTER: providing and fixing in position color


plain GI sheet for gutter 150mmX450mm, inclusive of nuts
12.30 and bolts, washers, all complete as per drawings, R.m 76.55 1,000.00 76,550.00
specifications and instruction.
13.1)FALSE CEILING WORK,PVC
BOARD: Providing and fixing suspended PVC board false
ceiling, with necessary provisions for light fittings, light
13.10 boxes, where required finally finished with two coat acrylic Sq.M 283.46 1,500.00 425,190.00
emulsion paint, all complete as per drawings, specifications
and instructions.

14.1)MISCELLANEOUS WORK,
WATER PROOFING: Providing and placing 20 mm thick
cement sand mortar (1:2) mixing with wate proof
14.10 compound in the floor base mixing, laying, compacting, Sq.M - 400.00 -
finishing, curing, laid to exact line level and dimensions
complete as per drawings, specifications and instructions

14.2)INSULATION WORK:
Providing and installing Insulation under CGI roofing sheet
14.20 with Insulation shield of 12mm thickness one sided and Sq.m 350.67 200.00 70,134.00
chicken wire mesh all completeas per drawing and
specifications.
15.1)METAL WORKS,BLACK
15.10 TUBULAR PIPE: Supplying, fabricating and fixing black Kg 7,748.52 150.00 1,162,278.00
pipe (Square or circular) work /Truss with
15.2)MS PIPE: Supplying, fabricating and fixing metal
15.20 work of different angles MS Pipe with one coat primer as Kg 1,563.77 150.00 234,565.50
shown in drawing all complete
15.3)ROLLING SHUTTER:
Providing and fixing rolling shutterof 16-19 Gauge cold
rolled MS lathe interlocked throughout their entire length
and joined together at the end by end locks and mounted on
specially designed pipe shaft with brackets, side guides and
15.30 arrangements for inside and outside locking,with push and Sq.m - 4,000.00 -
pull operation, complete supplying, fixing and painting with
two coats of approved plastic emulsion paint.

15.4)HOT ROLLED STEEL


SECTION: Supplying, fabricating and fixing metal work of
15.40 different Hot Rolled Steel sections with one coat primer as Kg - 150.00 -
per drawings and specifications all complete

15.5)METAL WORK,METAL
GATE: Supplying, fabricating and fixing in position, metal
gates of standard sections consisting of angles, pipes,
15.50 flats,etc. including one coat primer and one coat enamel Sq.M - 7,000.00 -
paint as per drawings, specifications and instructions all
complete

15.6)FENCING WORK: Providing and fixing of ISA


50x50x5 mm along with 25x25x5 flat and M8x40 bolts at
12.30 300mm spacing to fix 10 S.W.G.G.I chain link with hole R.M - 2,200.00 -
size 60x60 mm upto 3m height and 3 lines of barbed wire at
top.

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST PRIMARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
16.1)EXPANSION JOINT WORKS/PLINTH LEVEL:
Suuply
and fixing of expansion joint at level of 100% non porous
flexible element allowing movement in all directions,
16.10 supported by aluminium framing and covering the top by R.M 2.15 4,500.00 9,675.00
aluminium sheet and flused to required floor level all
complete as per drawing, specification and instruction.

16.2)EXPANSION JOINT
WORKS/SLAB: Supply and fixing of expansion joint at
floor level of aluminium base supported by alumunium
16.20 framing,fixed on one side by threaded screw and flushed to R.M 16.50 4,500.00 74,250.00
required floor level and dimension all complete as per
drawing,specification and instruction

16.3)EXPANSION JOINT WORKS/ENDS OF WALL:


16.30 Supply R.M 39.85 4,500.00 179,325.00
17.1)CHAIN LINK VENTILATION
WORK: Supplying, fabricating and fixing in position of 10
S.W.G.I. woven wire ventilation with hollow square pipe
framing of size 18x18x1.0 mm on all sides with proper
17.10 welding on site, including one coat primer and one coat Sq.M 4,000.00 -
enamel paint on frames as per drawings, specifications and
instructions all complete

18.1)LAND DEVELOPMENT WORKS, INTERLOCKING


BLOCKS: Supplying and laying of 60 mm thick heavy duty
interlocking paving blocks of approved colour and quality
on the 50 mm thick stone dust with surface grading,
18.10 levelling and soil compaction base in driveways and parking Sq.M 2,000.00 -
areas, complete as per specifications and drawings.

18.2)RAILING WORKS: Supply,


fabrication and fitting of Railing works with MS square pipe
framing and 10 S.W.G.I. wire mesh of height 1.05m
18.20 including excavation, brickwork, plaster and two coats R.M 3,000.00 -
enamel paint all complete as per drawings and specifications

18.3)GUIDE RAMP: Supply,


fabrication and fitting of Guide Ramp-Utility Guardrail for
the disabled with MS tubular pipes at regular intervals of
18.30 height 1.05m including two coats enamel paint all complete R.M 6.60 6,500.00 42,900.00
as per drawings and specifications

18.4)APRON DRAIN: Construction of Apron drain along


the perimeter of buildings and retaining structures including
18.40 excavation, Brick soling, PCC and half brick thick apron R.M 49.70 20,000.00 994,000.00
walls with plaster all complete as per drawings and
specifications
18.5)TACTILE PAVING: Providing
and laying approved brand quality, pattern and colour of
Tactile paving tile on floor over constructed cement mortar
18.50 of mix 1:3 backing and filling joints (epoxy grout) at R.M 3,500.00 -
straight path and turning points of size 300x300x40mm, all
complete as per drawings, specifications and instructions.

DEMOLITION WOKS: Demolition of existing building


19.10 and toilet blocks PS - 1,000,000.00 -

RELOCATION WOKS: Relocation of temple from existing


site and to be constructed at a new location outside of the
20.10 school site as per drawing,specification and instructions. PS 300,000.00 -

INSURANCE PREMIUM
21.10 PS - 224,281.00 -

Floor Hardener:providing,sprinkling,laying &applying


Manually two layer in floor,applied each layer with 1.5 to
2.5kg /m2 in required pattern,blended in,smoothed,over by
22.10 power trowelling,in line and level including curing all Sq.M 375.21 400.00 150,084.00
complete as per drawing,specification and instruction.
(Mapetop,N,AR6 or equivalent)

Cement Board:providing and fixing in position 10mm


water proofed cement board in exterior (one side)surface
inclusive minimum75mm GI metal framewith grooving and
23.10 fixing of fastner ,washer,nuts,and bolts,all complete as per Sq.M 39.84 2,700.00 107,568.00
drawings,specifications and instructions.

FLOOR TILE (600*600)


24.00 Sq.M 26.34 2,500.00 65,850.00

ENAMEL PAINT
25.00 Sq.M 223.93 286.00 64,043.98

PILE WORK : Construction of pile work including


26.00 excavation, reinforcement and concreting work. Rm. 17,000.00 -

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST PRIMARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
DISMANTLING WORK
27.00 -

CONCRETE DISMANTLING
27.10 Cu.M 8,500.00 -

BRICKWALL DISMANTLING
27.20 Cu.M 2,000.00 -

TOTAL CIVIL WORKS -


TOTAL AMOUNT
25,788,354.42

Total Item Price 25,788,354.42

Discount @2% 515,767.09

Sub Total 25,272,587.33

VAT @13% 3,285,436.35

Grand Total 28,558,023.68

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


1.1 GENERAL WORK, SITE CLEARANCE Sq.M 1 40.425 13.2 533.61
2.1 EARTHWORK IN EXCAVATION
FOOTINGS
F1 Cu.m. 10 1.6 1.6 2.2 56.32
F2 Cu.m. 2 2.1 2.1 2.2 19.4
F3 Cu.m. 2 2.3 2.3 2.2 23.27
F4 Cu.m. 7 2.5 2.5 2.2 96.25
F5 Cu.m. 2 2.8 2.8 2.2 34.49
F6 Cu.m. 6 2.9 2.9 2.2 111.01
F7 Cu.m. 1 3.1 3.1 2.2 21.14
Bottom tie beam
Bottom tie beam along grid A /(5-7) Cu.m. 1 2.0125 0.375 1.55 1.16
Bottom tie beam along grid B/(5-7) Cu.m. 1 2.0125 0.375 1.55 1.16
Bottom tie beam Along grid 5,6&7/A-B Cu.m. 3 3.7 0.375 1.55 6.45
lower Tie Beam
Along grid A Cu.m. 1 11.7125 0.375 1.54 6.76
Along grid B Cu.m. 1 8.8125 0.375 1.54 5.08
Along grid 1& 11/ (A-B) Cu.m. 2 4.3 0.375 1.54 4.96
Along grid 2,3,4,8,9&10/A-B Cu.m. 6 3.8 0.375 1.54 13.16
Staircase footing Cum 1 2 0.3 1 0.6
Along grid C/1-11 Cum 1 21.725 0.375 1.54 12.54
Along grid B-C/1-11 Cum 2 0.55 0.375 1.54 0.63
Cum 6 0.25 0.375 1.54 0.86
Cum 1 0.3 0.375 1.54 0.17
1 0.15 0.375 1.54 0.08

Front Steps Cum 1 43.765 0.6 0.13 3.41


Backside Steps Cum 1 9.95 1.6 0.13 2.06
Side Steps from basement to GL Cum 2 2.645 2.45 1.03 13.34
Cum 1 2.05 2.45 1.18 5.92
Backside steps from lower basement to
basement Lvl Cum 2 3.3 3.2 1.78 37.59
Steps from road to ground floor apron level
Cum 1 3.9 2.46 1.05 10.07
Apron Drain Cum 1 47.5 0.76 0.625 22.56

TOTAL EARTHWORK IN
EXCAVATION Cu.m. 510.44
2.2 EARTHWORK IN FILLING
Total earthwork in excavation 510.44
Inside Room Cu.m. 8 6.25 3.65 0.45 82.12
Cu.m. 1 6.25 4.15 0.45 11.67
Passage Cu.m. 8 2.25 3.65 0.45 29.56
Cu.m. 1 2.25 4.15 0.45 4.2
Backside from lower basement to basement
Lvl. Cu.m. 2 11.25 2.5 1.65 92.81

Deduction
Sand Filling Cu.m. 0
Flat brick soling Cu.m. -45.14
Brickwork upto plinth beam Cu.m. -135.19
PCC M10 Cu.m. -61.85
RCC M25 (Colums upto plinth level) Cu.m. -28.47
RCC M20 (Footings , Bottom tie beam, Lower
tie beam) Cu.m. -78.41
Total Back Filling Cu.m. 381.74

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


2.3 SAND FILLING
CRUSHED STONE DUST
F1 Cu.m. 10 1.9 1.9 0.075 2.7
F2 Cu.m. 2 2.4 2.4 0.075 0.86
F3 Cu.m. 2 2.6 2.6 0.075 1.01
F4 Cu.m. 7 2.8 2.8 0.075 4.11
F5 Cu.m. 2 3.1 3.1 0.075 1.44
F6 Cu.m. 6 3.2 3.2 0.075 4.6
F7 Cu.m. 1 3.4 3.4 0.075 0.86

Inside Room Cu.m. 8 6.25 3.65 0.1 18.25


Cu.m. 1 6.25 4.15 0.1 2.59
Passage Cu.m. 8 2.25 3.65 0.1 6.57
Cu.m. 1 2.25 4.15 0.1 0.93
Total Sand Filling Cu.m. 0
4 BRICK WORK
4.1 FLAT BRICK SOLING
FOOTINGS
F1 Sq.m. 10 1.6 1.6 25.6
F2 Sq.m. 2 2.1 2.1 8.82
F3 Sq.m. 2 2.3 2.3 10.58
F4 Sq.m. 7 2.5 2.5 43.75
F5 Sq.m. 2 2.8 2.8 15.68
F6 Sq.m. 6 2.9 2.9 50.46
F7 Sq.m. 1 3.1 3.1 9.61
Bottom tie beam
Bottom tie beam along grid A /(5-7) Sq.m. 1 2.0125 0.375 0.75
Bottom tie beam along grid B/(5-7) Sq.m. 1 2.0125 0.375 0.75
Bottom tie beam Along grid 5,6&7/A-B Sq.m. 3 3.7 0.375 4.16
lower Tie Beam
Along grid A Sq.m. 1 11.7125 0.375 4.39
Along grid B Sq.m. 1 8.8125 0.375 3.3
Along grid 1& 11/ (A-B) Sq.m. 2 4.3 0.375 3.22
Along grid 2,3,4,8,9&10/A-B Sq.m. 6 3.8 0.375 8.55
Staircase footing Sq.m. 1 2 0.3 0.6
Along grid C/1-11 Sq.m. 1 21.725 0.375 8.14
Along grid B-C/1-11 Sq.m. 2 0.55 0.375 0.41
Sq.m. 6 0.25 0.375 0.56
Sq.m. 1 0.3 0.375 0.11
Sq.m. 1 0.15 0.375 0.05
Inside Room Sq.m. 8 6.25 3.65 182.5
Sq.m. 1 6.25 4.15 25.93
Passage Sq.m. 8 2.25 3.65 65.7
Sq.m. 1 2.25 4.15 9.33

Front apron area on ground floor sq m 1 5.7 2.1 11.97


sq m 1 40 2 80
sq m 1 3.35 1.75 5.86
Steps on ground floor level sq m 1 43.6 0.6 26.16
Steps on first floor level sq m 1 3.55 0.6 2.13
Steps from road to ground floor apron level
sq m 1 3.9 2.46 9.59
sq m 1 3.25 0.25 0.81

Backside Passage on basement & Lower


basement level sq m 1 42.55 2.5 106.37
Room Steps on basement level sq m 4 1.5 0.6 3.6
Updown Steps sq m 2 3.45 2.5 17.25
sq m
Stair down Steps 1 4.6 0.6 2.76
Stair down Landing sq m 1 6.95 2.5 17.37
Side Steps from basement to GL sq m 2 2.645 2.45 12.96
sq m 1 2.05 2.45 5.02
Apron Drain sq m 1 47.5 0.76 36.1

TOTAL FLAT BRICK SOLING Sq.m. 820.9

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


4.2 FULL BRICK WORK
In lower basement
From bottom tie beam to upper tie beam along
grid 5,6&7/A-B Cu.m. 3 6.05 0.23 1.24 5.17
From lower tie beam to upper tie beam along
grid A &B/6-7 Cu.m. 2 3.95 0.23 1.24 2.25
In basement
From lower tie beam to upper tie beam
Along grid A/1-11 Cu.m. 1 27.6 0.23 1.25 7.93
Along grid B/1-11 Cu.m. 1 27.6 0.23 1.25 7.93
Along grid C/1-11 Cu.m. 1 32.45 0.23 1.35 10.07
Along grid 1,2,3,4,5,8,9,10&11/A-B Cu.m. 9 6.05 0.23 1.25 15.65
Along grid 1,2,3,4,5,6,7,8,9,10&11/B-C Cu.m. 11 2.1 0.23 1.35 7.17
Footing of staircase at lower basement Cu.m. 1 2 0.23 0.87 0.4

Front step on ground floor level


First Steps cu.m 1 42.325 0.6 0.15 25.39
Second Steps cu.m 1 42.325 0.3 0.15 12.69
Side blocks cu.m 1 1.6 0.6 0.45 0.96
Backside Passage at basement level
first Steps cu.m 4 1.5 0.6 0.15 0.54
second Steps cu.m 4 1.5 0.3 0.15 0.27
lower basement to basement level steps (10 area cal from cad
steps ) cu.m 2 2.5 2.97 15
Lower basement level steps 4248000
first Steps cu.m 1 4.6 0.6 0.15 0.41
second Steps cu.m 1 4.6 0.3 0.15 0.2
Steps from baement to ground floor level near area cal from cad
stone masonry wall cu.m 3 2.4 1.588 11.43
west side near masonary wall cu.m 1 2.5 0.23 0.6 0.34
Masonary wall top brickwork cu.m 1 32.15 0.23 0.3 2.21

Steps from ground to first floor level cum 1 3.55 0.6 0.15 0.31
cum 1 3.55 0.3 0.15 0.15
Steps from entrance road to ground floor apron

Two sides wall cum 2 3.6 0.23 1.05 1.73


Side wall cum 1 3.25 0.23 1.05 0.78
7 Steps cum 7 2 0.3 0.15 0.63

Apron Drain cum 1 47.5 0.115 0.5 2.73


cum 1 47.5 0.12 0.5 2.85

TOTAL FULL BRICK WORK Cu.m. 135.19


5 AAC BLOCK
5.1 AAC BLOCK (600*200*200)
BASEMENT FLOOR
ALONG GRID 3&9/(A-B) Sq.m 2 4.85 2.7 26.19
ALONG GRID 5,6&7/(A-B) Sq.m 3 4.55 2.7 36.85
ALONG GRID A/1-11 Sq.m 1 27.6 2.825 77.97
ALONG GRID X/3-9 Sq.m 1 12.9 2.05 26.44
DEDUCTION
D Sq.m -4 1.2 2.9 -13.92
W1 Sq.m -4 1.5 1.985 -11.91
W3 Sq.m -4 3.45 1.985 -27.4
GROUND FLOOR
ALONG GRID1, 3,5,6,7,9 &11/(A-B) Sq.m 7 6.05 2.7 114.34
ALONG GRID A&B/1-11 Sq.m 2 31.55 2.825 178.25
DEDUCTION
D Sq.m -8 1.2 2.9 -27.84
W1 Sq.m -7 1.5 1.985 -20.85
W2 Sq.m -1 1.2 1.985 -2.39
W3 Sq.m -8 3.45 1.985 -54.79
V3 Sq.m -1 2 1.25 -2.5
LANDING BEAM Sq.m -1 3.95 0.4 -1.58
ALONG GRID B/6-7 Sq.m -1 3.95 2.825 -11.16
FIRST FLOOR
ALONG GRID1, 3,5,6,7,10&11/(A-B) Sq.m 7 6.05 2.7 114.34
ALONG GRID A&B/1-11 Sq.m 2 31.55 2.825 178.25
ALONG GRID C/1-11 Sq.m 1 32.45 0.4 12.98
ALONG GRID 1&11/B-C Sq.m 2 2.125 0.4 1.7
DEDUCTION
D Sq.m -8 1.2 2.9 -27.84
W3 Sq.m -8 3.45 1.985 -54.79
W1 Sq.m -7 1.5 1.985 -20.85
W2 Sq.m -1 1.2 1.985 -2.39
V3 Sq.m -1 2 1.25 -2.5
LANDING BEAM Sq.m -1 3.95 0.4 -1.58
ALONG GRID B/6-7 Sq.m -1 3.95 2.825 -11.16

Wall above connection slab Sq.m 2 2.35 1.05 4.93

TOTAL AAC BLOCK 600*200*200 Sq.m. 476.79

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


6 CONCRETE WORK
6.1 PCC of grade M10
FOOTINGS
F1 Cu.m. 10 1.6 1.6 0.075 1.92
F2 Cu.m. 2 2.1 2.1 0.075 0.66
F3 Cu.m. 2 2.3 2.3 0.075 0.79
F4 Cu.m. 7 2.5 2.5 0.075 3.28
F5 Cu.m. 2 2.8 2.8 0.075 1.17
F6 Cu.m. 6 2.9 2.9 0.075 3.78
F7 Cu.m. 1 3.1 3.1 0.075 0.72

Bottom tie beam


Bottom tie beam along grid A /(5-7) Cu.m. 1 2.0125 0.375 0.075 0.05
Bottom tie beam along grid B/(5-7) Cu.m. 1 2.0125 0.375 0.075 0.05
Bottom tie beam Along grid 5,6&7/A-B Cu.m. 3 3.7 0.375 0.075 0.31
lower Tie Beam
Along grid A Cu.m. 1 11.7125 0.23 0.075 0.2
Along grid B Cu.m. 1 8.8125 0.23 0.075 0.15
Along grid 1& 11/ (A-B) Cu.m. 2 4.3 0.23 0.075 0.14
Along grid 2,3,4,8,9&10/A-B Cu.m. 6 3.8 0.23 0.075 0.39
Staircase footing Cum 1 2 0.3 0.075 0.04
Along grid C/1-11 Cum 1 21.725 0.23 0.075 0.37
Along grid B-C/1-11 Cum 2 0.55 0.23 0.075 0.01
Cum 6 0.25 0.23 0.075 0.02
Cum 1 0.3 0.23 0.075 0
1 0.15 0.23 0.075 0
Inside Room Cu.m. 8 6.25 3.65 0.075 13.68
Cu.m. 1 6.25 4.15 0.075 1.94
Passage Cu.m. 8 2.25 3.65 0.075 4.92
Cu.m. 1 2.25 4.15 0.075 0.7

Front apron area on ground floor Cu.m. 1 5.7 2.1 0.075 0.89
Cu.m. 1 40 2 0.075 6
Cu.m. 1 3.35 1.75 0.075 0.43
Steps on ground floor level Cu.m. 1 43.6 0.6 0.075 1.96
Steps on first floor level Cu.m. 1 3.55 0.6 0.075 0.15
Steps from road to ground floor apron level
Cu.m. 1 3.9 2.46 0.075 0.71
Cu.m. 1 3.25 0.25 0.075 0.06

Backside Passage on basement & Lower


basement level Cu.m. 1 42.55 2.5 0.075 7.97
Room Steps on basement level Cu.m. 4 1.5 0.6 0.075 0.27
Updown Steps Cu.m. 2 3.45 2.5 0.075 1.29
Cu.m.
Stair down Steps 2 4.6 0.6 0.075 0.41
Stair down Landing Cu.m. 1 6.95 2.5 0.075 1.3
Side Steps from basement to GL Cu.m. 2 2.645 2.45 0.075 0.97
Cu.m. 1 2.05 2.45 0.075 0.37
Masonary wall top brickwork cu.m 1 32.15 0.45 0.075 1.08
Apron Drain cu.m 1 47.5 0.76 0.075 2.7

TOTAL PCC OF GRADE M10 Cu.m. 61.85


6.2 PCC for RCC of Grade M25
Lower Basement shear wall
along grid 6 & 7/(A-B) Sq.m. 2 6.05 0.2 1.35 3.26
along grid B /(6-7) Sq.m. 1 3.95 0.2 1.35 1.06
Basement shear wall
along grid 1& 11/A-B Sq.m. 2 6.05 0.2 2.85 6.89
along grid B /(1-11) Sq.m. 1 31.55 0.2 2.9 18.29
Column upto plinth lvl
C3 Cu.m. 11 0.35 0.35 2.1 2.82
C1 Cu.m. 2 0.45 0.45 6.95 2.81 F5 column from lower basement
Cu.m. 1 0.45 0.45 6.94 1.4 F6 column from lower basement
Cu.m. 6 0.45 0.45 5.3 6.43 F6 column from basement
Cu.m. 2 0.45 0.45 5.4 2.18 F3 column from basement
C2 Cu.m. 3 0.45 0.45 6.95 4.22
Cu.m. 2 0.45 0.45 5.4 2.18
Cu.m. 6 0.45 0.45 5.3 6.43

Columns from ground level to second floor


C1 Cu.m. 11 0.45 0.45 6.6 14.7
C2 Cu.m. 11 0.45 0.45 6.6 14.7
C3 Cu.m. 11 0.35 0.35 6.6 8.89

TOTAL PCC OF GRADE M25 Cu.m. 96.26

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


6.3 PCC for RCC of Grade M20
FOOTINGS
F1 Cu.m. 10 1.6 1.6 0.35 8.96
F2 Cu.m. 2 2.1 2.1 0.35 3.08
F3 Cu.m. 2 2.3 2.3 0.35 3.7
F4 Cu.m. 7 2.5 2.5 0.45 19.68
F5 Cu.m. 2 2.8 2.8 0.45 7.05
F6 Cu.m. 6 2.9 2.9 0.45 22.7
F7 Cu.m. 1 3.1 3.1 0.45 4.32
Foundation tie beam (At -7m lvl)
Bottom tie beam along grid A /(6-7) Cu.m. 1 3.95 0.23 0.3 0.27
Bottom tie beam along grid B/(6-7) Cu.m. 1 3.95 0.23 0.3 0.27
Bottom tie beam Along grid 5,6&7/A-B Cu.m. 3 6.05 0.23 0.3 1.25

Foundation tie beam (At -5.35m lvl)


Along grid A/1-11 Cu.m. 1 27.6 0.23 0.3 1.9
Along grid B/1-11 Cu.m. 1 27.6 0.23 0.3 1.9
Along grid 1,2,3,4,8,9,10 &11/A-B Cu.m. 8 6.05 0.23 0.3 3.33

Foundation tie beam (At -2.1 m lvl)


Along grid C/1-11 Cu.m. 1 32.45 0.23 0.3 2.23
Along grid 1,2,3,4,5,6,7,8,9,10 &11/A-B Cu.m. 11 2.1 0.23 0.3 1.59

Upper tie beam (At -4.95m lvl)


Bottom tie beam along grid A /(6-7) Cu.m. 1 3.95 0.23 0.3 0.27
Bottom tie beam along grid B/(6-7) Cu.m. 1 3.95 0.23 0.3 0.27
Bottom tie beam Along grid 6&7/A-B Cu.m. 2 6.05 0.23 0.3 0.83

Upper tie beam (At -3.3 m lvl)


Along grid A/1-11 Cu.m. 1 31.55 0.23 0.3 2.17
Along grid B/1-11 Cu.m. 1 31.55 0.23 0.3 2.17
Along grid 1,2,3,4,5,6,7,8,9,10 &11/A-B Cu.m. 11 6.05 0.23 0.3 4.59

Plinth Beam
Along grid A/1-11 Cu.m. 1 31.55 0.25 0.4 3.15
Along grid B/1-11 Cu.m. 1 31.55 0.25 0.4 3.15
Along grid C/1-11 Cu.m. 1 32.45 0.25 0.4 3.24
Along grid 1,2,3,4,5,6,7,8,9,10 &11/A-B Cu.m. 11 8.15 0.25 0.45 10.08
Secondary beam
Along X-X Cu.m. 2 14.6 0.23 0.175 1.17
Along grid 6-7 Cu.m. 1 4.15 0.23 0.175 0.16

Beam
Ground Floor Beam
Beam along grid A&B/1-11 Cu.m. 2 31.55 0.25 0.275 4.33
Beam along grid C/1-11 Cu.m. 1 32.45 0.25 0.275 2.23
Beam along grid1-11/A-C Cu.m. 11 8.15 0.25 0.325 7.28
Secondary beam
Along X-X Cu.m. 2 14.6 0.23 0.175 1.17
Along grid 6-7 Cu.m. 1 4.15 0.23 0.175 0.16
First Floor Beam
Beam along grid A&B/1-11 Cu.m. 2 31.55 0.25 0.4 6.31
Beam along grid C/1-11 Cu.m. 1 32.45 0.25 0.4 3.24
Beam along grid1-11/A-C Cu.m. 11 8.15 0.25 0.45 10.08

SLAB
Ground Floor Cu.m. 1 16.05 6.95 0.125 13.94
Cu.m. 1 20.45 6.95 0.125 17.76

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Deduction
Staircase void Cu.m. -1 4.15 4.85 0.125 -2.52
Column Cu.m. -22 0.45 0.45 0.125 -0.56

First FLoor Cu.m. 1 16.05 9.4 0.125 18.85


Cu.m. 1 20.45 9.4 0.125 24.02
Deduction 0.125
Staircase void Cu.m. -1 4.15 4.85 0.125 -2.52
Column Cu.m. -22 0.45 0.45 0.125 -0.56
Cu.m. -11 0.35 0.35 0.125 -0.17

STAIRCASE
Lower basement to basement
Bottom landing slab Cu.m. 1 2 1.991 0.175 0.69
Waist slab Cu.m. 1 3.69 2 0.175 1.29
Steps Cu.m. 11 2 0.15 0.15 0.49
Landing Cu.m. 1 4.15 1.65 0.175 1.19
Cu.m. 1 2 0.41 0.175 0.14
BASEMENT TO GROUND FLOOR Cu.m.
first flight Waist slab Cu.m. 1 3.655 2 0.175 1.27
Landing Cu.m. 1 4.15 0.92 0.175 0.66
Cu.m. 1 2 0.48 0.175 0.16
Landing beam Cu.m. 1 3.95 0.25 0.225 0.22
Second flight waist slab Cu.m. 1 3.27 2 0.175 1.14
Steps Cu.m. 22 2 0.15 0.15 0.99
GROUND FLOOR TO FIRST FLOOR Cu.m.
first flight Waist slab Cu.m. 1 3.655 2 0.175 1.27
Landing Cu.m. 1 4.15 0.92 0.175 0.66
Cu.m. 1 2 0.48 0.175 0.16
Landing beam Cu.m. 1 3.95 0.25 0.225 0.22
Second flight waist slab Cu.m. 1 3.27 2 0.175 1.14
Steps Cu.m. 22 2 0.15 0.15 0.99

BANDS
SILL BANDS
Basement Floor
ALONG GRID 3 &9/(A-B) Cu.m. 2 4.85 0.2 0.075 0.14
ALONG GRID 5,6&7/A-B Cu.m. 3 4.55 0.2 0.075 0.2
ALONG GRID A/1-11 Cu.m. 1 22.8 0.275 0.075 0.47
Infill wall along grid 3-5 Cu.m. 1 6.5 0.2 0.075 0.09
Infill wall along grid 7-9 Cu.m. 1 6.4 0.2 0.075 0.09
Ground Floor
ALONG GRID1, 3,5,6,7,9&11/(A-B) Cu.m. 7 6.05 0.2 0.075 0.63
ALONG GRID A/1-11 Cu.m. 1 31.55 0.275 0.075 0.65
ALONG GRID B/1-11 Cu.m. 1 27.6 0.2 0.075 0.41
DEDUCTION
D Cu.m. -8 1.2 0.2 0.075 -0.15

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


First Floor
ALONG GRID1, 3,5,6,7,10&11/(A-B) Cu.m. 7 6.05 0.2 0.075 0.63
ALONG GRID A/1-11 Cu.m. 1 31.55 0.275 0.075 0.65
ALONG GRID B/1-11 Cu.m. 1 27.6 0.2 0.075 0.41
DEDUCTION Cu.m.
D Cu.m. -8 1.2 0.2 0.075 -0.15

LINTEL BANDS
Basement Floor
ALONG GRID 3 &9/(A-B) Cu.m. 2 4.85 0.2 0.075 0.14
ALONG GRID 5,6&7/A-B Cu.m. 3 4.55 0.2 0.075 0.2
ALONG GRID A/1-11 Cu.m. 1 3 0.2 0.075 0.04
Infill wall along grid 3-5 Cu.m. 1 6.5 0.2 0.075 0.09
Infill wall along grid 7-9 Cu.m. 1 6.4 0.2 0.075 0.09
Ground Floor
ALONG GRID1, 3,5,6,7,9&11/(A-B) Cu.m. 7 6.05 0.2 0.075 0.63
ALONG GRID B/1-11 Cu.m. 1 27.6 0.2 0.075 0.41
DEDUCTION Cu.m.
D Cu.m. -8 1.2 0.2 0.075 -0.15
W1 Cu.m. -7 1.5 0.2 0.075 -0.16
W2 Cu.m. -1 1.2 0.2 0.075 -0.02
First Floor
ALONG GRID1, 3,5,6,7,10&11/(A-B) Cu.m. 7 6.05 0.2 0.075 0.63
ALONG GRID B/1-11 Cu.m. 1 27.6 0.2 0.075 0.41
DEDUCTION
D Cu.m. -8 1.2 0.2 0.075 -0.15
W1 Cu.m. -7 1.5 0.2 0.075 -0.16
W2 Cu.m. -1 1.2 0.2 0.075 -0.02

Connecting Slab to shearwall


Beam Cu.m. 1 4.6 0.25 0.3 0.34
Slab Cu.m. 1 2.1 4.65 0.125 1.22

TOTAL RCC M20 Cu.m. 236.81


7.1 FORM WORK
FOOTINGS
F1 Sq.m. 10 6.4 0.35 22.4
F2 Sq.m. 2 8.4 0.35 5.88
F3 Sq.m. 2 9.2 0.35 6.44
F4 Sq.m. 7 10 0.45 31.5
F5 Sq.m. 2 11.2 0.45 10.08
F6 Sq.m. 6 11.6 0.45 31.32
F7 Sq.m. 1 12.4 0.45 5.58
Foundation tie beam (At -7m lvl)
Bottom tie beam along grid A /(6-7) Sq.m. 1 7.9 0.3 2.37
Bottom tie beam along grid B/(6-7) Sq.m. 1 7.9 0.3 2.37
Bottom tie beam Along grid 5,6&7/A-B Sq.m. 3 12.1 0.3 10.89

Foundation tie beam (At -5.35m lvl)


Along grid A/1-11 Sq.m. 1 55.2 0.3 16.56
Along grid B/1-11 Sq.m. 1 55.2 0.3 16.56
Along grid 1,2,3,4,8,9,10 &11/A-B Sq.m. 8 12.1 0.3 29.04

Foundation tie beam (At -2.1 m lvl)


Along grid C/1-11 Sq.m. 1 64.9 0.3 19.47
Along grid 1,2,3,4,5,6,7,8,9,10 &11/A-B Sq.m. 11 4.2 0.3 13.86

Upper tie beam (At -4.95m lvl)


Bottom tie beam along grid A /(6-7) Sq.m. 1 7.9 0.3 2.37
Bottom tie beam along grid B/(6-7) Sq.m. 1 7.9 0.3 2.37
Bottom tie beam Along grid 6&7/A-B Sq.m. 2 12.1 0.3 7.26

Upper tie beam (At -3.3 m lvl)


Along grid A/1-11 Sq.m. 1 63.1 0.3 18.93
Along grid B/1-11 Sq.m. 1 63.1 0.3 18.93
Along grid 1,2,3,4,5,6,7,8,9,10 &11/A-B Sq.m. 11 12.1 0.3 39.93

Plinth Beam
Beam along grid A&B/1-11 Sq.m. 2 63.1 0.275 34.7
Beam along grid C/1-11 Sq.m. 1 64.9 0.4 25.96
Beam along grid1-11/A-B Sq.m. 11 12.1 0.325 43.25
Beam along grid1-11/B-C Sq.m. 11 4.2 0.45 20.79
Secondary beam
Along X-X Sq.m. 2 29.2 0.175 10.22
Along grid 6-7 Sq.m. 1 8.3 0.175 1.45
Deductions of secondary beam faces Sq.m. -18 0.23 0.175 -0.73

Ground Floor Beam


Beam along grid A&B/1-11 Sq.m. 2 63.1 0.275 34.7
Beam along grid C/1-11 Sq.m. 1 64.9 0.275 17.84
Beam along grid1-11/A-C Sq.m. 11 16.3 0.325 58.27
Secondary beam
Along X-X Sq.m. 2 29.2 0.175 10.22
Along grid 6-7 Sq.m. 1 8.3 0.175 1.45
Deductions of secondary beam faces Sq.m. -18 0.23 0.175 -0.73

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


First Floor Beam
Beam along grid A&B/1-11 Sq.m. 2 31.55 1.05 66.25
Beam along grid C/1-11 Sq.m. 1 32.45 1.05 34.07
Beam along grid1-11/A-C Sq.m. 11 16.3 1.15 206.19

Lower Basement shear wall


along grid 6 & 7/(A-B) Sq.m. 2 12.1 1.35 32.67
along grid B /(6-7) Sq.m. 1 7.9 1.35 10.66
Basement shear wall
along grid 1& 11/A-B Sq.m. 2 12.1 2.85 68.97
along grid B /(1-11) Sq.m. 1 63.1 2.9 182.99

Column upto basement level


C1 Sq.m. 2 1.8 3.65 13.14
Sq.m. 1 1.8 3.64 6.55
Sq.m. 6 1.8 2 21.6
Sq.m. 2 1.8 2.1 7.56
C2 Sq.m. 3 1.8 3.65 19.71
Sq.m. 2 1.8 2.1 7.56
Sq.m. 6 1.8 2 21.6
Deduction of beam faces Sq.m. -10 0.23 0.3 -0.69
Sq.m. -87 0.23 0.3 -6.01
Columns from basement to Plinth level
C1 Sq.m. 11 1.8 3.175 62.86
C2 Sq.m. 11 1.8 3.175 62.86
C3 Sq.m. 11 1.4 2.1 32.34
Deductions of beam faces Sq.m. -36 0.25 0.275 -2.48
Sq.m. -22 0.25 0.325 -1.79

Columns from plinth level to first floor lvl


C1 Sq.m. 11 1.8 6.475 128.2
C2 Sq.m. 11 1.8 6.475 128.2
C3 Sq.m. 11 1.4 6.475 99.71
Deductions of beam faces
First floor beamSq.m. -54 0.25 0.275 -3.72
Sq.m. -44 0.25 0.325 -3.58
Second floor beam Sq.m. -54 0.25 0.4 -5.4
Sq.m. -44 0.25 0.45 -4.95

SLAB 0
Ground Floor Sq.m. 1 16.05 6.95 111.54
Sq.m. 1 20.45 6.95 142.12
Perimeter of slab Sq.m. 1 100.8 0.125 12.6
Deduction
Staircase void Sq.m. -1 4.15 4.85 -20.13
Column Sq.m. -22 0.45 0.45 -4.46

First FLoor Sq.m. 1 16.05 9.4 150.87


Sq.m. 1 20.45 9.4 192.23
Perimeter of slab Sq.m. 1 110.6 0.125 13.82
Deduction Sq.m.
Staircase void Sq.m. -1 4.15 4.85 -20.13
Column Sq.m. -22 0.45 0.45 -4.46
Sq.m. -11 0.35 0.35 -1.35

STAIRCASE
Lower basement to ground floor
Bottom landing slab sides Sq.m. 1 6.132 0.175 1.07
Waist slab Sq.m. 1 3.69 2 7.38
Sides of waist slab Sq.m. 2 3.69 0.325 2.39
Steps riser Sq.m. 11 2 0.15 3.3
Landing Sq.m. 1 4.15 1.65 6.84
Sq.m. 1 2 0.41 0.82
Sides of landing Sq.m. 1 1.8 0.175 0.31

BASEMENT TO GROUND FLOOR


first flight Waist slab Sq.m. 1 3.655 2 7.31
Sides of waist slab Sq.m. 2 3.655 0.325 2.37
Landing Sq.m. 1 4.15 0.92 3.81
Sq.m. 1 2 0.48 0.96
Sides of landing Sq.m. 1 1.07 0.175 0.18
Landing beam bottom Sq.m. 1 3.95 0.25 0.98
Landing beam sides Sq.m. 1 3.95 0.625 2.46
Second flight waist slab Sq.m. 1 3.27 2 6.54
Sides of waist slab Sq.m. 2 3.27 0.325 2.12

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


GROUND FLOOR TO FIRST FLOOR Sq.m.
first flight Waist slab Sq.m. 1 3.655 2 7.31
Sides of waist slab Sq.m. 2 3.655 0.325 2.37
Landing Sq.m. 1 4.15 0.92 3.81
Sq.m. 1 2 0.48 0.96
Sides of landing Sq.m. 1 1.07 0.175 0.18
Landing beam bottom Sq.m. 1 3.95 0.25 0.98
Landing beam sides Sq.m. 1 3.95 0.625 2.46
Second flight waist slab Sq.m. 1 3.27 2 6.54
Sides of waist slab Sq.m. 2 3.27 0.325 2.12

BANDS
SILL BANDS
Basement Floor
ALONG GRID 3 &9/(A-B) Sq.m. 2 4.85 0.15 1.45
ALONG GRID 5,6&7/A-B Sq.m. 3 4.55 0.15 2.04
ALONG GRID A/1-11 Sq.m. 1 22.8 0.225 5.13
Infill wall along grid 3-5 Sq.m. 1 6.5 0.15 0.97
Infill wall along grid 7-9 Sq.m. 1 6.4 0.15 0.96
Ground Floor Sq.m.
ALONG GRID1, 3,5,6,7,9&11/(A-B) Sq.m. 7 6.05 0.15 6.35
ALONG GRID A/1-11 Sq.m. 1 31.55 0.225 7.09
ALONG GRID B/1-11 Sq.m. 1 27.6 0.15 4.14
DEDUCTION
D Sq.m. -8 1.2 0.15 -1.44
First Floor
ALONG GRID1, 3,5,6,7,10&11/(A-B) Sq.m. 7 6.05 0.15 6.35
ALONG GRID A/1-11 Sq.m. 1 31.55 0.225 7.09
ALONG GRID B/1-11 Sq.m. 1 27.6 0.15 4.14
DEDUCTION
D Sq.m. -8 1.2 0.15 -1.44

LINTEL BANDS
Basement Floor
ALONG GRID 3 &9/(A-B) Sq.m. 2 4.85 0.15 1.45
ALONG GRID 5,6&7/A-B Sq.m. 3 4.55 0.15 2.04
ALONG GRID A/1-11 Sq.m. 1 3 0.15 0.45
Infill wall along grid 3-5 Sq.m. 1 6.5 0.15 0.97
Infill wall along grid 7-9 Sq.m. 1 6.4 0.15 0.96
Ground Floor
ALONG GRID1, 3,5,6,7,9&11/(A-B) Sq.m. 7 6.05 0.15 6.35
ALONG GRID B/1-11 Sq.m. 1 27.6 0.15 4.14
DEDUCTION
D Sq.m. -8 1.2 0.15 -1.44
W1 Sq.m. -7 1.5 0.15 -1.58
W2 Sq.m. -1 1.2 0.15 -0.18
First Floor
ALONG GRID1, 3,5,6,7,10&11/(A-B) Sq.m. 7 6.05 0.15 6.35
ALONG GRID B/1-11 Sq.m. 1 27.6 0.15 4.14
DEDUCTION
D Sq.m. -8 1.2 0.15 -1.44
W1 Sq.m. -7 1.5 0.15 -1.58
W2 Sq.m. -1 1.2 0.15 -0.18

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks

Connecting slab to shearwall


Beam
Bottom Sq.m. 1 4.15 0.25 1.03
sides Sq.m. 1 0.175 4.4 0.77
Bottom Slab Sq.m. 1 1.9 4.4 8.36
Periferi of slab Sq.m. 1 9.1 0.15 1.36
Beam end face Sq.m. 2 0.25 0.3 0.15

Total form work Sq.m. 2479.74


8.1 REINFORCEMENT WORK
Foundations Kg 1 3219.55 3219.55
Columns Kg 1 18437.27 18437.27
Beams Kg 1 15568.23 15568.23
Slabs Kg 1 4982.41 4982.41
Staircase Kg 1 4341.92 4341.92
Bands Kg 1 812.79 812.79
Shear Walls Kg 1 3775.63 3775.63
Connecting Slab Kg 1 525.91 525.91

Total Kg 51663.71
9 FLOORING WORK
9.1 PLASTIC LAYING
Lower Basement level Sq.m. 1 4.15 6.45 26.76
Basement level
Rooms Sq.m. 8 3.65 6.25 182.5
Ground Floor level
Passage Sq.m. 8 3.65 2.25 65.7
Sq.m. 1 4.15 2.25 9.33

Total plastic laying Sq.m. 0 Can be deducted


9.2 SCREEDING
Lower Basement level
Lobby Sq.m. 1 6.75 4.1 27.67
Staircase Sq.m. 11 2 0.3 6.6

Basement level
ClassRoom -1 & 4 Sq.m. 2 7.65 6.45 98.68
ClassRoom -2 Sq.m. 1 7.7 4.5 34.65
ClassRoom -3 Sq.m. 1 7.6 4.5 34.2
Passage Sq.m. 1 20.45 1.725 35.27
Staircase Sq.m. 22 2 0.3 13.2
Landing Sq.m. 1 4.15 1.725 7.15

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Ground Floor level
Classroom 10A,11A,11B Sq.m. 3 7.625 6.45 147.54
Classroom 10B Sq.m. 1 7.725 6.45 49.82
Passage Sq.m. 1 36.4 2.4 87.36
steps Sq.m. 2 36.4 0.3 21.84
Lobby Sq.m. 1 4.15 1.4 5.81
Staircase Sq.m. 22 2 0.3 13.2
Landing Sq.m. 1 4.15 2 8.3

First Floor level


Classroom 12A Sq.m. 1 7.625 6.45 49.18
Classroom 12B Sq.m. 1 7.725 6.45 49.82
Principal Office Room Sq.m. 1 3.725 6.45 24.02
Office Room Sq.m. 1 11.525 6.45 74.33
Passage Sq.m. 1 36.4 2.4 87.36
Lobby Sq.m. 1 4.15 1.4 5.81

Steps
First steps Sq.m. 1 42.075 0.3 12.6225 In tread of steps
Second steps Sq.m. 1 42.075 0.3 12.6225
Block Sq.m. 1 1.6 0.6 0.96
Backside Passage
Room Steps sq m 4 1.5 0.6 3.6 In tread of steps
Updown Steps cu.m 2 3.3 2.5 16.5 Both side
Stair down Steps cu.m 2 4.6 0.6 5.52
Stair down Landing cu.m 1 6.95 2.5 0
West side Stair steps sq m 3 7.545 2 45.27

Steps from main entrance to ground floor level Sq.m. 1 2.4 1.8 0
Steps Sq.m. 7 2 0.3 0

First Floor step in connecting slab Sq.m. 2 3.1 0.3 1.86

TOTAL Sq.m. 980.765


9.3 CEMENT PUNNING
Basement level
ClassRoom -1 & 4 Sq.m. 2 7.65 6.45 98.68
ClassRoom -2 Sq.m. 1 7.7 4.5 34.65
ClassRoom -3 Sq.m. 1 7.6 4.5 34.2
Ground Floor level
Classroom 10A,11A,11B Sq.m. 3 7.625 6.45 147.54
Classroom 10B Sq.m. 1 7.725 6.45 49.82

First Floor level


Classroom 12A Sq.m. 1 7.625 6.45 49.18
Classroom 12B Sq.m. 1 7.725 6.45 49.82
Skirting Sq.m. 1 436.95 0.125 54.61

Front Steps
First steps Sq.m. 1 42.075 0.3 12.62 In tread of steps
Second steps Sq.m. 1 42.075 0.3 12.62
Block Sq.m. 1 1.6 0.6 0.96
Riser 1 Sq.m. 3 42.075 0.15 18.93
Sq.m. 1 5.2 0.45 2.34

Backside Passage
Room Steps sq m 4 1.4 0.6 3.36 In tread of steps
Riser 2 sq m 12 1.4 0.15 2.52
Updown Steps cu.m 2 3.3 2.5 16.5 Both side
Riser 3 sq m 26 2.5 0.15 9.75
Stair down Steps cu.m 1 4.6 0.6 2.76
Riser 4 sq m 3 4.6 0.15 2.07
Stair down Landing cu.m 1 6.95 2.5 17.37
West side Stair steps sq m 3 1.9 2 11.4 In tread of steps
Riser 5 sq m 20 2 0.15 6

First Floor step in connecting slab Sq.m. 2 3.1 0.3 1.86


Sq.m. 3 3.1 0.15 0

Total Cement Punning Sq.m. 639.56


9.4 CEMENT SKIRTING
Lower Basement
R.m. 2 6.975 13.95
R.m. 1 4.15 4.15
Staircase R.m. 1 5.765 5.76

Basement level
ClassRoom -1 & 4 R.m. 2 26.5 53
ClassRoom -2 R.m. 1 22.3 22.3
ClassRoom -3 R.m. 1 22.3 22.3
Passage R.m. 1 33.9 33.9
Staircase
First flight R.m. 1 7.065 7.06
Landing R.m. 1 4.15 4.15
Second flight R.m. 1 7.065 7.06
Ground Floor level
Classroom 10A,11A,11B R.m. 3 25.8 77.4

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Classroom 10B R.m. 1 22 22
Passage R.m. 1 22.85 22.85
Column along grid C R.m. 4 0.7 2.8
R.m. 7 0.7 4.9

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Staircase
First flight R.m. 1 7.065 7.06
Landing R.m. 1 4.15 4.15
Second flight R.m. 1 8.365 8.36

First Floor level


Classroom 12A R.m. 1 25.75 25.75
Classroom 12B R.m. 1 25.95 25.95
Passage along grid C R.m. 1 32.45 32.45
Passage along grid B R.m. 1 22.85 22.85 Addition
Passage along grid B-C/1 & 11 R.m. 1 2.1 2.1
Connecting slab R.m. 2 2.35 4.7

Total R.M. 436.95


10 FINISHING WORK
10.1 EXTERNAL PLASTER
Along grid 1& 11/A-B from basement to first
floor
Sq.m. 2 7.15 9.900 141.57

Along grid A/1-11 from basement to first floor Sq.m. 1 38.25 9.9 378.67
Basement shear wall along grid B /1-11 Sq.m. 1 31.55 3.3 0 No Plastering
Below basement level along grid B Sq.m. 2 12.075 0.45 10.86
Steps Side Sq.m. 2 2.275 2.1 9.55

Columns along grid C from ground floor to


Sq.m. 9 1.4 6.6 83.16
first floor
Sq.m. 2 1.05 6.6 13.86
Deduction of beam face Sq.m. -36 0.25 0.4 -3.6
Sq.m. -22 0.25 0.45 -2.48
Slab top of basement slab Sq.m. 1 43.65 0.2 8.73
Slab top of first floor slab Sq.m. 1 80.3 0.2 16.06
Beam face C/1-11 in first floor & Second floor Sq.m. 2 32.45 0.4 25.96
Beam face 1&11/B-C in first floor & Second
Sq.m. 2 4.2 0.45 3.78
floor
Wall along grid C/1-11 in first floor Sq.m. 1 32.45 0.4 12.98
Wall along grid 1&11/A-B in first floor Sq.m. 2 2.1 0.4 1.68

Wall above connecting slab Sq.m. 2 2.35 2.425 11.39

Deduction of doow & windows along grid A


D Sq.m. -4 1.2 2.9 -13.92
W1 Sq.m. -4 1.5 1.985 -11.91
W3 Sq.m. -20 3.45 1.985 -136.97
V3 Sq.m. -2 2 1.25 -5
Opening of staircase along grid A/6-7 from
basement to first flight Sq.m. -1 3.95 2.9 -11.46

West side Masonary wall plaster Sq.m. 1 6.95 2 13.9


West side Brickwall plaster Sq.m. 1 2.5 0.6 1.5
wall in ground floor level to support steps
from main entrance Sq.m. 1 10.45 1.23 12.85
Sq.m. -1 7.2 0.5 -3.6
steps
First floor level steps ( riser) at connecting slab
Sq.m. 2 3.1 0.15 0.93

Steps from main entrance to ground level

Tread Sq.m. 7 2 0.3 4.2


Riser Sq.m. 7 2 0.15 2.1
Top Landing Sq.m. 1 2.4 1.8 4.32

Ground floor level steps Sq.m. 3 42.075 0.15 18.93


Sq.m. 1 5.2 0.45 2.34

Basement level steps riser sq m 12 1.5 0.15 2.7

Steps from lower basement to basement sq m 24 2.5 0.15 9


Lower basement level step sq m 3 4.6 0.15 2.07
Steps from basement to ground floor ( west
side) sq m 20 2 0.15 6

Apron Drain both sides sq m 1 47.5 1.3 61.75

Total Sq.m. 671.9

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


10.2 INTERNAL PLASTER
Lower Basement
Along grid 6& 7 /A-B Sq.m. 2 7 1.2 16.8
Along grid 6-7/B Sq.m. 1 3.95 1.25 4.93

Basement
Along grid A/1-5 Sq.m. 1 11.4 2.9 33.06
Along grid A/7-11 Sq.m. 1 3.95 1.25 4.93
Along grid A/6-8 Sq.m. 1 11.4 2.9 33.06
Along grid 1&11/A-B Sq.m. 2 6.05 2.85 34.48
Along grid B/1-11 Sq.m. 1 31.55 2.9 91.49
Along grid 3&9 /A-B Sq.m. 2 9.7 2.85 55.29
Along grid 5&6/A-B Sq.m. 2 4.35 2.85 24.79
Along grid 7/A-B Sq.m. 1 9.1 2.85 25.93
Internal wall Sq.m. 1 27.2 2.2 59.84
Top of internal wall Sq.m. 1 12.9 0.2 2.58
Columns 0
Full columns Sq.m. 11 0.45 3.175 15.71
Kopla Sq.m. 56 0.125 3.175 22.22
Perifery of D&W 0
D Sq.m. 6 5.8 0.2 6.96
W1 Sq.m. 4 6.97 0.2 5.57
W3 Sq.m. 4 10.87 0.2 8.69
Deduction of D & W
D Sq.m. -4 1.2 2.9 -13.92
W1 Sq.m. -4 1.5 1.985 -11.91
W3 Sq.m. -4 3.45 1.985 -27.4
Ground Floor
Along grid A/1-11 Sq.m. 1 31.55 2.9 91.49
Along grid B/1-11 both sides Sq.m. 1 55.2 2.9 160.08
Along grid 1,5,6&11/A-B Sq.m. 4 6.05 2.85 68.97
Along grid 3,7&9/A-B Sq.m. 3 12.1 2.85 103.45
Columns 0
Full columns Sq.m. 21 0.4 3.175 26.67
Kopla Sq.m. 56 0.125 3.175 22.22
Door windows perifery
D Sq.m. 8 5.8 0.2 9.28
W1 Sq.m. 7 6.97 0.2 9.75
W2 Sq.m. 1 6.37 0.2 1.27
W3 Sq.m. 8 10.87 0.2 17.39
V3 Sq.m. 1 6.5 0.2 1.3
Deductions
D Sq.m. -16 1.2 2.9 -55.68
W1 Sq.m. -14 1.5 1.985 -41.69
W2 Sq.m. -2 1.2 1.985 -4.77
W3 Sq.m. -8 3.45 1.985 -54.79
V3 Sq.m. -1 2 1.25 -2.5

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


First Floor
Along grid A/1-11 Sq.m. 1 31.55 2.9 91.49
Along grid B/1-11 both sides Sq.m. 1 55.2 2.9 160.08
Along grid 1,5,6&11/A-B Sq.m. 4 6.05 2.85 68.97
Along grid 3,7&10/A-B Sq.m. 3 12.1 2.85 103.45
Walls along grid C/1-11 Sq.m. 1 32.45 0.6 19.47
Wall along grid 1&11 /B-C Sq.m. 2 2.1 0.6 2.52
Columns
Full columns Sq.m. 21 0.4 3.175 26.67
Kopla Sq.m. 56 0.125 3.175 22.22
Door windows perifery
D Sq.m. 8 5.8 0.2 9.28
W1 Sq.m. 7 6.97 0.2 9.75
W2 Sq.m. 1 6.37 0.2 1.27
W3 Sq.m. 8 10.87 0.2 17.39
V3 Sq.m. 1 6.5 0.2 1.3
Deductions
D Sq.m. -16 1.2 2.9 -55.68
W1 Sq.m. -14 1.5 1.985 -41.69
W2 Sq.m. -2 1.2 1.985 -4.77
W3 Sq.m. -8 3.45 1.985 -54.79
V3 Sq.m. -1 2 1.25 -2.5
Total Sq.m. 1119.97
10.3 CEILING PLASTER
Lower Basement
Waist slab of staircase Sq.m. 1 3.3 2 6.6
Landing Sq.m. 1 1.65 4.15 6.84
Sq.m. 1 2 0.41 0.82
Beam sides
Along grid 5&6/A-B Sq.m. 2 6.05 0.275 3.32
Along grid B/ 6-7 Sq.m. 1 3.95 0.275 1.08
Basement
Sq.m. 1 16.05 6.95 111.54
Sq.m. 1 20.45 6.95 142.12
Beam sides
Along grid 1,2,3,4,7,8,9,10&11/A-B Sq.m. 8 12.1 0.325 31.46
Along grid 5&6/A-B Sq.m. 2 6.05 0.325 3.93
Along grid X-X Sq.m. 1 58.4 0.175 10.22
Along grid A,B/1-11 Sq.m. 2 63.1 0.275 34.7
Staircase beam Sq.m. 1 8.4 0.125 1.05
Staircase
First flight Sq.m. 1 3.69 2 7.38
Landing Sq.m. 1 4.15 0.92 3.81
Sq.m. 1 2 0.48 0.96
Second Flight Sq.m. 1 3.27 2 6.54
Deductions
Staircase void Sq.m. -1 4.15 4.85 -20.13
Columns Sq.m. -22 0.45 0.45 -4.46
Wall (600*200*200) Sq.m. -1 63 0.2 -12.6
Shear Wall Sq.m. -2 6.05 0.2 -2.42
Sq.m. -1 31.55 0.2 -6.31

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Ground Floor
Sq.m. 1 36.5 9.375 342.18
Beam sides
Along grid 1,2,3,4,7,8,9,10&11/A-C Sq.m. 8 16.35 0.325 42.51
Along grid 5 & 6 /A-C Sq.m. 2 8.175 0.325 5.31
Along grid X-X Sq.m. 1 58.4 0.175 10.22
Along grid A,B/1-11 Sq.m. 2 63.1 0.275 34.7
Along grid C/1-11 Sq.m. 1 64.9 0.275 17.84
Staircase beam Sq.m. 1 8.4 0.125 1.05
Staircase
Sq.m.
First flight 1 3.69 2 7.38
Landing Sq.m. 1 4.15 0.92 3.81
Sq.m. 1 2 0.48 0.96
Second Flight Sq.m. 1 3.27 2 6.54
Deductions
Staircase void Sq.m. -1 4.15 4.85 -20.13
Columns Sq.m. -22 0.45 0.45 -4.46
Sq.m. -11 0.3 0.3 -0.99
Wall (600*200*200) 0
Along grid A Sq.m. -1 31.55 0.2 -6.31
Along grid B Sq.m. -1 21.95 0.2 -4.39
Along grid 1,3,5,6,7,9&11/A-B Sq.m. -7 6.05 0.2 -8.47

Connecting slab Sq.m. 1 2.05 4.85 9.94


Beam Sq.m. 1 4.85 0.175 0
Beam side face Sq.m. 2 0.25 0.3 0.15

First Floor
Beam sides & Bottom
Along grid A&B/1-11 Sq.m. 2 31.55 1.05 66.25
Along grid C/1-11 Sq.m. 1 32.45 1.05 34.07
Along grid 1,2,3,4,7,8,9,10&11/A-C Sq.m. 8 16.35 1.15 150.42
Along grid 5 & 6 /A-C Sq.m. 2 8.175 0.7 11.44

Total Ceiling Plaster Sq.m. 1026.47

10.4 PLASTER ON RCC LINTEL WITH


CORNICE
Basement Floor
W2 R.M. 4 3.45 13.8
DW R.M. 4 2.25 9
Ground Floor
Slab R.M. 1 80.8 0
W3 R.M. 8 3.45 27.6
V3 R.M. 1 2 2
First Floor
Slab R.M. 1 80.8 0
W3 R.M. 8 3.45 27.6
V3 R.M. 1 2 2

Total R.M. 0
10.5 EMULSION PAINT
Total internal plaster area Sq.m. 1119.97
Total ceiling plaster area Sq.m. 1026.47
Total Sq.m. 2146.44
10.6 WEATHER COAT
Total external plaster area Sq.m. 1 671.9 671.9
Total RCC Lintel with cornice area Sq.m. 1 0 0
Cement board area Sq.m. 1 64.28 64.28
Total Sq.m. 736.18
11 DOOR, WINDOWS WORK
11.1 UPVC SLIDING WINDOWS
Basement Floor
W2 Sq.m. 4 3.45 1.985 27.393
DW Sq.m. 4 1.2 1.985 9.528
Ground Floor
W1 Sq.m. 7 1.5 1.985 20.8425
W2 Sq.m. 1 1.2 1.985 2.382
W3 Sq.m. 8 3.45 1.985 54.786
First Floor
W1 Sq.m. 7 1.5 1.985 20.8425
W2 Sq.m. 1 1.2 1.985 2.382
W3 Sq.m. 8 3.45 1.985 54.786

Total Sq.m. 192.942

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


11.2 UPVC TOP HUNG WINDOWS
V3 Sq.m. 2 2 1.25 5
Ventilation(V1) in Basement Sq.m. 1 7.1 0.975 6.92
Sq.m. 1 0.25 0.65 0.16
Ventilation(V2) in Basement Sq.m. 1 7.2 0.975 7.02
Sq.m. 1 0.25 0.65 0.16
Total Sq.m. 19.26
11.3 UPVC DOUBLE DOOR
D Sq.m. 24 1.2 2.9 83.52

Total Sq.m. 83.52


11.4 UPVC SINGLE DOOR

Total Sq.m. 0
12 ROOFING WORK
12.1 CGI ROOFING SHEET
Sq.m. 2 38.2 5.914 451.82
Total Sq.m. 451.82
12.2 CGI ROOFING SHEET ON RIDGE
Rm 1 38.2 38.2
TOTAL Sq.m. 38.2
12.3 GI GUTTER:
Gutter fitting RM 2 38.2 76.4

TOTAL 76.4
13.1 FLASE CEILING WORK PVC BOARD
Along grid A-B/1-11 Sq.m. 8 6.25 3.65 182.5
Sq.m. 1 6.25 4.15 25.93
Along grid B-C/1-11 Sq.m. 8 2.25 3.65 65.7
Sq.m. 1 2.25 4.15 9.33
Total Sq.m. 283.46
14 MISCELLANEOUS WORK
14.1 WATER PROOFING
Shear wall Secondary block
Shear wall grid B/1-11 Sq.m. 1 36.45 3 109.35
Shear wall grid 1(A-B), 11 ( A-B ) Sq.m. 2 6.95 3 41.7
TOTAL 151.05
14.2 INSULATION WORK
Along grid 1-5/A-C Sq.m. 2 16.05 4.817 154.62
Along grid 6-11/A-C Sq.m. 2 20.45 4.817 197.01
Total Sq.m. 351.63
15 METAL WORK
15.1 BLACK TUBULAR PIPE
Description of Work Total l Unit wt.
Bottom Chord NB 50(M) Kg. 30 4.643 139.29 5.03 700.62
Vertical Bracing NB 40(M) Kg. 30 0.425 12.75 3.56 45.39
Kg. 30 0.851 25.53 3.56 90.88
Kg. 30 1.191 35.73 3.56 127.19
Kg. 30 1.487 44.61 3.56 158.81
Inclined Bracing NB 32(M) Kg. 30 1.221 36.63 3.09 113.18
Kg. 30 1.279 38.37 3.09 118.56
Kg. 30 1.46 43.8 3.09 135.34
Inclined Bracing NB 40(M) (wind clit) Kg. 16 2.83 45.28 3.56 161.19
Top Chord NB 50(M) Kg. 30 5.871 176.13 5.03 885.93
Purlin NB 65(M)
Grid 1-5 Kg. 72 2.57 185.04 6.44 1191.65
Grid 6-11 Kg. 84 2.827 237.46 6.44 1529.24
Beyond grid 1 & 11 Kg. 24 1.085 26.04 6.44 167.69
Between grid 5-6 Kg. 12 0.395 4.74 6.44 30.52
Runner NB 40(M) Kg.
Grid 1-5 Kg. 12 2.38 28.56 3.56 101.67
Grid 6-11 Kg. 14 2.637 36.91 3.56 131.39
Connections
Base Plate Volume
At column (300*300*10) Kg. 30 0.0009 7850 211.95
At beam(250*250*10) Kg. 60 0.000625 7850 294.37
Nut Kg. 180 0.00000826236 7850 11.67
16mm Dia anchord Bolt Kg. 180 0.45 81 1.58 127.98
ISA 50*50*10 Kg. 90 0.3 27 3.8 102.6
50*75mm plate stiffner Kg. 90 0.0000375 7850 26.49
Bottom Chord
Volume
10mm thick plate (175*175) Kg. 30 0.00030625 7850 72.12
10mm thick stiffner(63*63) Kg. 120 0.00003969 7850 37.38
4nos-16mm Boults Kg. 60 wt. per pcs 0.16 9.6
Runner Plate Connection
Runner Box (175*75mm outer size)
175*68.3*10mm runner box Kg. 4 2.47 9.88
Volume
175*68.3*10mm runner plate Kg. 4 0.000119525 7850 3.75
2nos-16mm dia bolts Kg. 8 wt. per pcs 0.16 1.28
At middle
175*68.3*10mm runner box Kg. 44 2.47 108.68

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Volume
175*68.3*10mm runner plate Kg. 44 0.000119525 7850 41.28
2nos-16mm dia bolts Kg. 88 wt. per pcs 0.16 14.08
Purlin Cleat Connection
Volume
Top Chord Cleat 200*90*10 Kg. 540 0.00018 7850 763.02
2nos-16mm bolts Kg. 360 wt. per pcs 0.16 57.6
Top Ridge Connection
Volume
2 nos -10mm thick 175*175 mm plate Kg. 30 0.00030625 7850 72.12
10mm thick stiffners(57*59) Kg. 120 0.00003363 7850 31.67
16mm dia Nut bolts Kg. 60 wt. per pcs 0.16 9.6
Truss Cleat for wind Ties
Volume
Wind Tie Cleat(100*100*6) Kg. 32 0.00006 7850 15.07
MS Flat 165*80*6 Kg. 64 0.0000792 7850 39.79
MS Flat 380*80*6mm Kg. 16 0.0001824 7850 22.9
20mm dia Nut bolts Kg. 32 wt. per pcs 0.21 6.72
16mm dia Nut bolts Kg. 40 wt. per pcs 0.16 6.4
Total Kg. 7787.25
15.2 MS PIPE
Unit Lot No L Unit wt. Quantity
Windows Railing Work
First Floor
MS Base Plate (600*50*5mm) Kg. 8 2 0.00015 7850 18.84
Vol.
MS Base Plate (85*50*5mm) Kg. 8 3 0.00002125 7850 4
Vol.
25.4*25.4*2.6mm MS Post Kg. 8 3 0.58095 1.69 23.56
18*18*2mm MS pipe Kg. 8 3 3.37 1.0048 81.35
38.1*38.1*3.2mm MS pipe Kg. 8 1 3.45 3.29 90.8
Second Floor
MS Base Plate (600*50*5mm) Kg. 8 2 0.00015 7850 18.84
Vol.
MS Base Plate (85*50*5mm) Kg. 8 3 0.00002125 7850 4
Vol.
25.4*25.4*2.6mm MS Post Kg. 8 3 0.58095 1.69 23.56
18*18*2mm MS pipe Kg. 8 3 3.37 1.0048 81.35
38.1*38.1*3.2mm MS pipe Kg. 8 1 3.45 3.29 90.8

Staircase Railing
Lower Basement to Basement Level
NB 40 MS Round Pipe Kg. 1 1 3.8 3.56 13.52
38.1*38.1*3.2mm MS Vertical pipe Kg. 1 4 0.92 3.29 12.1
18*18*2 mm MS Pipe Kg. 1 4 3.6476 1.0048 14.66
125*125*5 mm Base Plate Kg. 1 4 7.8125E-05 7850 2.45
Vol.
Basement to Ground Floor
NB 40 MS Round Pipe Kg. 1 1 8.12 3.56 28.9
38.1*38.1*3.2mm MS Vertical pipe Kg. 1 8 0.92 3.29 24.21
18*18*2 mm MS Pipe Kg. 1 4 7.8152 1.0048 31.41
125*125*5 mm Base Plate Kg. 1 8 7.8125E-05 7850 4.9
Vol.
Ground Floor to First Floor Kg.
NB 40 MS Round Pipe Kg. 1 1 10.32 3.56 36.73
38.1*38.1*3.2mm MS Vertical pipe Kg. 1 10 0.92 3.29 30.26
18*18*2 mm MS Pipe Kg. 1 4 9.939 1.0048 39.94
125*125*5 mm Base Plate Kg. 1 10 7.8125E-05 7850 6.13
Vol.
Balcony Railing
First Floor
Along Grid 1&11/B-C
38.1*38.1*3.2mm MS Pipe Kg. 2 1 2.1 3.29 13.81
25.4*25.4*2.6mm MS Pipe Kg. 2 2 1.9 1.69 12.84
25.4*25.4*2.6mm MS Post Kg. 2 3 0.822 1.69 8.33
18*18*2mm MS pipe Kg. 2 18 0.437 1.0048 15.8
125*125*5mm Plate Kg. 2 2 7.8125E-05 7800 2.43
Kg. Vol.
Along grid C/1-2,2-3,3-4,4-5,7-8,8-9,9-10,10-
11
38.1*38.1*3.2mm MS Pipe Kg. 8 1 3.55 3.29 93.43
25.4*25.4*2.6mm MS Pipe Kg. 8 2 3.3 1.69 89.23
25.4*25.4*2.6mm MS Post Kg. 8 4 0.822 1.69 44.45
18*18*2mm MS pipe Kg. 8 33 0.437 1.0048 115.92
125*125*5mm Plate Kg. 8 2 7.8125E-05 7800 9.75
Vol.
Total MS PIPE Kg. 1088.3 poor finishing
16.1 Expansion joint
Plinth level
Basement Rm 1 2.125 2.125
Ground Floor Rm 1 2.125 2.125
First Floor Rm 1 2.125 2.125

Total Rm 6.375

16.2 Slab
Ground floor slab Rm 1 6.05 6.05

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB SECONDARY
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Shear wall Back side face in basement Rm 1 2.85 2.85
Total Rm 8.9
16.3 Ends of Wall
Front face from Gl to Top level Rm 1 6.3 6.3
Backside column fron backside GL to top level Rm 1 11.55 11.55
inside vertical column face (GF,1F,2F) Rm 1 17.1 17.1

Total Rm 34.95 poor finishing/seems gap


22 Floor hardener
Lower Basement level
Lobby Sq.m. 1 6.6 4.1 27.06
Staircase tread Sq.m. 11 2 0.3 6.6
Riser Sq.m. 10 2 0.15 3
Basement level
Passage Sq.m. 1 20.45 1.725 35.27
Staircase tread Sq.m. 22 2 0.3 13.2
Riser Sq.m. 20 2 0.15 6
Landing Sq.m. 1 4.15 2.075 8.61
Ground Floor level
Passage Sq.m. 1 36.4 2.4 87.36
steps Sq.m. 2 36.4 0.3 21.84
Lobby Sq.m. 1 4.15 1.425 5.91
Staircase tread Sq.m. 22 2 0.3 13.2
riser Sq.m. 20 2 0.15 6
Landing Sq.m. 1 4.15 2.075 8.61

First Floor level


Passage Sq.m. 1 36.4 2.4 87.36
Lobby Sq.m. 1 4.15 1.425 5.91
Connecting slab Sq.m. 1 4.85 2.7 13.09

TOTAL Sq.m. 349.02 poor finishing/Cracks

23 Cement Board
Gap filling Sq.m. 2 36.475 0.6 44
Cement Board on Gable wall Sq.m. 2 9.325 1.76 16.41
Ceiling Beam bootom face in Passage Sq.m. 1 6.45 0.775 2.49
Gap filling in basement wall Sq.m. 1 0.975 2.85 1.38
TOTAL Sq.m. 64.28
24 FLOOR TILE (600*600)
First Floor Floor
Principal Office Room Sq.m. 1 3.725 6.45 24.02
Skirting Sq.m. 1 19.15 0.125 2.39
Office Room Sq.m. 1 11.525 6.45 74.33
Skirting Sq.m. 1 34.75 0.125 4.34
TOTAL TILE (600*600) Sq.m. 105.08
25 ENAMEL PAINT
Windows grill Sq.m. 16 7 0.62 69.44
Passage Grill Sq.m. 1 66.2 0.65 43.03
Staircase railing Sq.m. 1 44.48 0.95 42.25
Chain gate Sq.m. 2 7.9 2.9 45.82
Railing Above connecting slab Sq.m. 2 4.7 1.4 13.16

Sq.m. 213.7

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST SECONDARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

GENERAL WORK, SITE CLEARANCE:Clearing and


grubbing of site for construction including uprooting of
1.1 vegetation, grass, brush wood, trees and sapplings of girth Sq.M 533.61 100.00 53,361.00
upto 300 mm & removal upto a distance of 50 m as per
drawings, specifications and instructions

EARTHWORK IN EXCAVATION: Earthwork in


2.1 excavation in trenches, pits and foundations by machine or Cu.M 510.44 200.00 102,088.00
appropriate technology in soft soil including existing debris
and brick bats of old structure, if any, upto specified depth
EARTWORK IN FILLING: Providing and placing of
random filling of excavated earth from cutting of slope and
stacked at site in 150mm thick layer in trenches, plinth or
under floor, sides of foundation and below beam at footing
2.2 Cu.M 379.01 200.00 75,802.00
covered area etc. including watering, mechanical ramming
and compaction of each layer, consolidation and dressing,
all complete as per drawings, specifications and instructions.

SAND FILLING: Sand filling in plinth under floors,


including watering, ramming, consolidating and dressing, all
2.3 complete as per drawings, specifications and instructions. Cu.M 0 2,500.00 -

STONE WORK : Dry stone soling work in line and level,


including packing joints with sand dust, all complete as per
3.1 drawings, specifications and instructions Cu.M 4,000.00 -

STONE MASONRY WALL: Stone rubble masonry work in


1:4 cement and sand mortar with hard, tough, sound and
durable stone in wall, made to required line, level, shape,
3.2 size and plumb including setting out, drain outlet, curing of Cu.M 7,500.00 -
the works and scaffolding etc. complete as per drawings,
specifications and instructions

BRICK WORK,FLAT BRICK SOLING: Flat brick soling


of local chimney bricks laid in line and level, including
4.1 packing joints with sand, complete as per drawings, Sq.M 820.9 800.00 656,720.00
specifications and instructions
FULL BRICK WORK: Brickwork in substructure and super
4.2 structure cement and sand mortar of mix 1:6 with first class Cu.M 135.19 15,000.00 2,027,850.00
chimney-made bricks, in any size and shape of wall, made
to required line, level, shape and plumb including setting
AAC(Autoclaved Aerated Concrete) BLOCK WORK:
5.1 Providing and laying of Autoclaved Aerated Concrete Block Sq.M 476.79 1,800.00 858,222.00
(600*200*200 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2)AAC(Autoclaved Aerated Concrete) BLOCK WORK:
Providing and laying of Autoclaved Aerated Concrete Block
(600*200*100 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2 required line, level, shape and plumb including setting out, Sq.M 0 2,000.00 -
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

5.3)AAC(Autoclaved Aerated Concrete) BLOCK WORK:


Providing and laying of Autoclaved Aerated Concrete Block
(600*200*150 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.3 required line, level, shape and plumb including setting out, Sq.M 0 1,100.00 -
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

CONCRETE WORK,PCC OF GRADE M10: Plain cement


concrete (PCC) of grade M10 (1:3:6 with 1 cement, 3 coarse
sand and 6 aggregate of 19 mm and down grade) in
foundation base including mixing, laying, compacting,
6.1 finishing, curing, laid to exact line, level and dimensions, Cu.M 61.85 10,000.00 618,500.00
inclusive ofside

PCC FOR RCC OF GRADE M25: Structural concrete (PCC


for RCC) of Grade M25 (1:1:2)works with approved
quality of cement, sand and well graded aggregate in any
form, size, shape and level including batching and mixing
with machine, laying including compaction with vibrating
machine, curing, testing and finishing, all complete as per
6.2 Cu.M 96.26 20,000.00 1,925,200.00
drawings, specifications and instructions.

PCC FOR RCC OF GRADE M20: Structural concrete (PCC


for RCC) of Grade M20 (1:1.5:3)works with approved
quality of cement, sand and well graded aggregate in any
6.3 form, size, shape and level including batching and mixing Cu.M 236.81 17,000.00 4,025,770.00
with machine, laying including compaction with vibrating
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST SECONDARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

FORMWORK: Placing plyboard form work with steel


props, shuttering, centering in horizontal/Vertical surfaces
like slab, beams, column, wall, stair etc. for all RCC works
7.1 of any shape, size and at any level and removal after Sq.M 2479.74 850.00 2,107,779.00
completion

REINFORCEMENT WORK: Providing and placing steel


reinforcement bar tested grade Fe-500 equivalent NS, for
8.1 RCC work including bending, binding with anneal wire and kg 51663.71 110.00 5,683,008.10
placing in position, all complete as per drawings,
specifications and instruction
9.1)FLOORING WORK,PLASTIC
9.1 LAYING: Supplying and laying 500 gauge plastic sheet in Sq.M 0 50.00 -
floor as per specificatio and instruction
9.2)SCREEDING: Providing and placing 38 mm thick Plain
cement concrete of grade M15 (1:2:4 with 1 cement, 2
coarse sand and 4 aggregate chips) in the floor base mixing,
laying, compacting, finishing, curing, laid to exact line level
9.2 , surface chipping and dimensions (floor concrete is laid in Sq.M 980.765 500.00 490,382.50
alternate panels of 1 m x 1 m) inclusive of shuttering
complete as per drawings, specifications and instructions

9.3)CEMENT PUNNING: Providing


and laying 3 mm cement punning in floor , laying in
9.3 Sq.M 639.56 200.00 127,912.00
required pattern, line

9.4)CEMENT SKIRTING: Providing


and placing cement skirting 125mm height of grade M15
(1:2:4 with cement, 2 coarse sand and 4 aggregate
) in wall ,mixing, laying, compactig, finishing, curing, laid
9.4 to exact line level and dimension all complete as per R.M 436.95 100.00 43,695.00
drawing, specification and instructions

9.5)TILE LAYING ON FLOOR:


Providing and laying approved brand quality, pattern and
color, ceramic mat finish tile (Low range) on floor over
9.5 cement mortar of mix 1:3 backing and filling joints (epoxy Sq.M 0 2,800.00 -
grout) complete as per drawings, specifications and
instructions.(Base rate: NRs 100)

9.6)TILE LAYING ON TOILET:


Providing and laying approved brand quality, pattern and
color, ceramic glazed tile in wall and ceramic mat finish tile
9.6 (Low range) on floor of toilet over cement mortar of mix 1:3 Sq.M 0 3,000.00 -
backing and filling joints (epoxy grout) complete as per
drawings, specifications and instructions.(Base rate: NRs
100)

10.1)FINISHING WORK,
EXTERNAL PLASTER: Providing and applying '10.5 mm
thick cement plastering with 1cement : 4 sand mortar in
outer surface any level size and shape of wall, column,
10.1 ceiling, band, blocks, etc inclusive of waterproofing Sq.M 671.9 400.00 268,760.00
compound, dusting, throating, etc as required including
racking, hacking, watering, cleaning of base, plastering to
plumb, line, level, smooth etc. and curing complete as per
drawings, specifications and instructions.
10.2)INTERNAL PLASTER:
Providing and applying'10.5 mm thick cement plastering
with 1cement : 4 sand mortar in inner surface except ceiling
any level size and shape of wall, column, band, blocks, etc
inclusive of dusting, throating, etc as required including
10.2 racking, watering, hacking, cleaning of base, plastering to Sq.M 1119.97 450.00 503,986.50
plumb, line, level, smooth etc. and curing, all complete as
per drawings, specifications and instructions.

10.3)CEILING PLASTER: Providing


and applying 12.5 mm thick cement plastering with 1cement
10.3 : 4 sand mortar in Ceiling any level size and shape of Sq.M 1026.47 500.00 513,235.00
ceiling inclusive of dusting,
10.4)PLASTER ON RCC LINTEL
WITH CORNICE: 'Providing and applying 12.5 mm thick
cement plastering with 1cement : 4 sand mortar in RCC
Lintel with cornice inclusive of dusting, throating, etc as
required including racking, watering, cleaning of base,
10.4 plastering to plumb, line, level, smooth etc. and curing, all R.M 0 3,000.00 -
complete as per drawings, specifications and instructions.

10.5)EMULSION PAINT: Providing


and applyibg two coat of emulsion paint in mat finishing
10.5 over two coat of primer, finished including surface Sq.M 2146.44 200.00 429,288.00
preparation all complete as per drawings, specifications and
instruction

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST SECONDARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

10.6)WEATHER COAT: Providing and applying two coat


of weather coat (Apex or equivalent) over required coat of
10.6 primer, finished including surface preparation all complete Sq.M 736.18 250.00 184,045.00
as per drawings, specifications and instruction

11.1)DOOR,WINDOWS WORK/UPVC SLIDING


WINDOWS: Providing and fixing standard UPVC sliding
window without net (frame 50x80mm, sash 58x36mm white
11.1 colour with 5mm glass) along with patented standard Sq.M 192.942 8,000.00 1,543,536.00
hardwares like roller, gaskets, brush seal, moon locks etc all
complete as per drawings and specifications.

11.2)UPVC TOP HUNG


WINDOWS: Providing and fixing standard UPVC top hung
window (frame 60x60 mm, sash 60x104 mm, white colour
11.2 with 5 mm glass) along with patented standard hardwares Sq.M 19.26 8,000.00 154,080.00
like roller, gaskets, brush seal, moon locks etc all complete
as per drawings and specifications.

11.3)UPVC DOUBLE DOOR:


Providing and fixing standard UPVC double door (frame
60x60mm, sash 60x104mm white colour with 5mm glass)
11.3 along with patented standard hardwares like roller, gaskets, Sq.M 83.52 10,000.00 835,200.00
brush seal, moon locks etc all complete as per drawings and
specifications.

11.4)UPVC SINGLE DOOR:


Providing and fixing standard UPVC single door with full
panel (frame60x60mm, sash 60x104mm white colour with
11.4 5mm glass) along with patented standard hardwares like Sq.M 0 7,000.00 -
roller, gaskets, brush seal, moon locks etc all complete as
per drawings and specifications.

12.1)ROOFING WORK,CGI
ROOFING SHEET: Providing and fixing in position 24
gauge medium (0 .5 mm thick) corrugated CGI sheet over
12.1 roof truss with minimum 80 mm side laps and 200 mm end Sq.M 451.82 1,319.17 596,027.38
laps, inclusive of nuts and bolts, 8 mm 'J' hooks, washers,
GI cup washers, all complete as per drawings, specifications
and instruction

12.2)CGI ROOFING SHEET ON


RIDGE: Providing and fixing in position 24 gauge medium
(0 .5 mm thick) CGI sheet over roof truss in ridge with
12.2 minimum 80 mm side laps and 200 mm end laps, inclusive R.m 38.2 1,009.52 38,563.66
of nuts and bolts, washers, GI cup washers, all complete as
per drawings, specifications and instruction

12.3)GI GUTTER: providing and fixing in position color


plain GI sheet for gutter 150mmX450mm, inclusive of nuts
12.3 and bolts, washers, all complete as per drawings, R.m 76.4 1,000.00 76,400.00
specifications and instruction.
13.1)FALSE CEILING WORK,PVC
BOARD: Providing and fixing suspended PVC board false
ceiling, with necessary provisions for light fittings, light
13.1 boxes, where required finally finished with two coat acrylic Sq.M 283.46 1,500.00 425,190.00
emulsion paint, all complete as per drawings, specifications
and instructions.

14.1)MISCELLANEOUS WORK,
WATER PROOFING: Providing and placing 20 mm thick
cement sand mortar (1:2) mixing with wate proof
14.1 compound in the floor base mixing, laying, compacting, Sq.M 151.05 400.00 60,420.00
finishing, curing, laid to exact line level and dimensions
complete as per drawings, specifications and instructions

14.2)INSULATION WORK:
Providing and installing Insulation under CGI roofing sheet
14.2 with Insulation shield of 12mm thickness one sided and Sq.m 351.63 200.00 70,326.00
chicken wire mesh all completeas per drawing and
specifications.
15.1)METAL WORKS,BLACK
15.1 TUBULAR PIPE: Supplying, fabricating and fixing black Kg 7787.25 150.00 1,168,087.50
pipe (Square or circular) work /Truss with
15.2)MS PIPE: Supplying, fabricating and fixing metal
15.2 work of different angles MS Pipe with one coat primer as Kg 1088.3 150.00 163,245.00
shown in drawing all complete

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST SECONDARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

15.3)ROLLING SHUTTER:
Providing and fixing rolling shutterof 16-19 Gauge cold
rolled MS lathe interlocked throughout their entire length
and joined together at the end by end locks and mounted on
specially designed pipe shaft with brackets, side guides and
15.3 arrangements for inside and outside locking,with push and Sq.m 0 4,000.00 -
pull operation, complete supplying, fixing and painting with
two coats of approved plastic emulsion paint.

15.4)HOT ROLLED STEEL


SECTION: Supplying, fabricating and fixing metal work of
15.4 different Hot Rolled Steel sections with one coat primer as Kg 0 150.00 -
per drawings and specifications all complete

15.5)METAL WORK,METAL
GATE: Supplying, fabricating and fixing in position, metal
gates of standard sections consisting of angles, pipes,
15.5 flats,etc. including one coat primer and one coat enamel Sq.M 0 7,000.00 -
paint as per drawings, specifications and instructions all
complete

15.6)FENCING WORK: Providing and fixing of ISA


50x50x5 mm along with 25x25x5 flat and M8x40 bolts at
12.3 300mm spacing to fix 10 S.W.G.G.I chain link with hole R.M 0 2,200.00 -
size 60x60 mm upto 3m height and 3 lines of barbed wire at
top.
16.1)EXPANSION JOINT WORKS/PLINTH LEVEL:
Suuply
and fixing of expansion joint at level of 100% non porous
flexible element allowing movement in all directions,
16.1 supported by aluminium framing and covering the top by R.M 6.375 4,500.00 28,687.50
aluminium sheet and flused to required floor level all
complete as per drawing, specification and instruction.

16.2)EXPANSION JOINT
WORKS/SLAB: Supply and fixing of expansion joint at
floor level of aluminium base supported by alumunium
16.2 framing,fixed on one side by threaded screw and flushed to R.M 8.9 4,500.00 40,050.00
required floor level and dimension all complete as per
drawing,specification and instruction

16.3)EXPANSION JOINT WORKS/ENDS OF WALL:


16.3 Supply R.M 34.95 4,500.00 157,275.00
17.1)CHAIN LINK VENTILATION
WORK: Supplying, fabricating and fixing in position of 10
S.W.G.I. woven wire ventilation with hollow square pipe
framing of size 18x18x1.0 mm on all sides with proper
17.1 welding on site, including one coat primer and one coat Sq.M 0 4,000.00 -
enamel paint on frames as per drawings, specifications and
instructions all complete

18.1)LAND DEVELOPMENT WORKS, INTERLOCKING


BLOCKS: Supplying and laying of 60 mm thick heavy duty
interlocking paving blocks of approved colour and quality
on the 50 mm thick stone dust with surface grading,
18.1 levelling and soil compaction base in driveways and parking Sq.M 0 2,000.00 -
areas, complete as per specifications and drawings.

18.2)RAILING WORKS: Supply,


fabrication and fitting of Railing works with MS square pipe
framing and 10 S.W.G.I. wire mesh of height 1.05m
18.2 including excavation, brickwork, plaster and two coats R.M 0 3,000.00 -
enamel paint all complete as per drawings and specifications

18.3)GUIDE RAMP: Supply,


fabrication and fitting of Guide Ramp-Utility Guardrail for
the disabled with MS tubular pipes at regular intervals of
18.3 height 1.05m including two coats enamel paint all complete R.M 7 6,500.00 45,500.00
as per drawings and specifications

18.4)APRON DRAIN: Construction of Apron drain along


the perimeter of buildings and retaining structures including
18.4 excavation, Brick soling, PCC and half brick thick apron R.M 20,000.00 -
walls with plaster all complete as per drawings and
specifications
18.5)TACTILE PAVING: Providing
and laying approved brand quality, pattern and colour of
Tactile paving tile on floor over constructed cement mortar
18.5 of mix 1:3 backing and filling joints (epoxy grout) at R.M 0 3,500.00 -
straight path and turning points of size 300x300x40mm, all
complete as per drawings, specifications and instructions.

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST SECONDARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

DEMOLITION WOKS: Demolition of existing building


19.1 and toilet blocks PS 1,000,000.00 -

RELOCATION WOKS: Relocation of temple from existing


site and to be constructed at a new location outside of the
20.1 school site as per drawing,specification and instructions. PS 300,000.00 -

INSURANCE PREMIUM
21.1 PS 224,281.00 -

Floor Hardener:providing,sprinkling,laying &applying


Manually two layer in floor,applied each layer with 1.5 to
2.5kg /m2 in required pattern,blended in,smoothed,over by
22.1 power trowelling,in line and level including curing all Sq.M 349.02 400.00 139,608.00
complete as per drawing,specification and instruction.
(Mapetop,N,AR6 or equivalent)

Cement Board:providing and fixing in position 10mm


water proofed cement board in exterior (one side)surface
inclusive minimum75mm GI metal framewith grooving and
23.1 fixing of fastner ,washer,nuts,and bolts,all complete as per Sq.M 64.28 2,700.00 173,556.00
drawings,specifications and instructions.

FLOOR TILE (600*600)


24 Sq.M 105.08 2,500.00 262,700.00

ENAMEL PAINT
25 Sq.M 213.7 286.00 61,118.20

PILE WORK : Construction of pile work including


26 excavation, reinforcement and concreting work. Rm 0 17,000.00 -

DISMANTLING WORK
27 -

CONCRETE DISMANTLING
27.1 Cu.M 8,500.00 -

BRICKWALL DISMANTLING
27.2 Cu.M 2,000.00 -

TOTAL CIVIL WORKS -


TOTAL AMOUNT
26,735,174.34

Total Item Price 26,735,174.34

Discount @2% 534,703.49

Sub Total 26,200,470.85

VAT @13% 3,406,061.21

Grand Total 29,606,532.06

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


1.1 GENERAL WORK, SITE CLEARANCE Sq.M 1 26.97 13.05 351.95
2.1 EARTHWORK IN EXCAVATION
FOOTINGS
F1 Cu.m. 2 2.1 2.1 2.2 19.4
F2 Cu.m. 8 2.5 2.5 2.2 110
F3 Cu.m. 2 3.63 3.3 2.2 52.7
CF Cu.m. 1 22.53 2 2.2 99.13
Additional CF Cu.m. 1 5.2 1.8 2.2 20.59
Bottom tie beam along grid C Cu.m. 1 9.43 0.375 1.6 5.65
Bottom tie beam along grid A Cu.m. 2 8 0.375 1.6 9.6
Front steps Cu.m. 1 21.93 0.6 0.13 1.71

Left side protection wall Cu.m. 1 3.7 0.3 0.3 0.33


Right side protection wall Cu.m. 1 7.4 0.3 0.3 0.66
Front side protection wall Cu.m. 1 23.4 0.2 0.2 0.93
Left side protection wall at first floor Cu.m. 1 7.9 0.3 0.5 1.18

TOTAL EARTHWORK IN Cu.m.


EXCAVATION 321.88
2.2 EARTHWORK IN FILLING
Total earthwork in excavation 321.88
Inside Room Cu.m. 4 5.75 4.25 0.3 29.32
Cu.m. 1 5.75 3.28 0.3 5.65
Passage Cu.m. 4 2.25 4.25 0.3 11.47
Cu.m. 1 2.25 3.28 0.3 2.21
Deduction
Sand Filling Cu.m. 0
Dry stone soling Cu.m. 5.75 -9.01
Flat brick soling Cu.m. -26.58
Brickwork upto plinth beam Cu.m. -37.08
PCC M10 Cu.m. -36.18
RCC M25 (Colums upto plinth level, shear Cu.m.
wall) -19.23
RCC M20 (Footings , Lower tie beam) Cu.m. -52.42
Total Back Filling Cu.m. 190.03
2.3 SAND FILLING
CRUSHED STONE DUST
F1 Cu.m. 2 2.1 2.1 0.075 0.66
F2 Cu.m. 8 2.5 2.5 0.075 3.75
F3 Cu.m. 2 3.63 3 0.075 1.63
CF Cu.m. 1 22.53 2 0.075 3.37
Additional CF Cu.m. 1 5.2 1.5 0.075 0.58

Inside Room Cu.m. 4 5.75 4.25 0.1 9.77


Cu.m. 1 5.75 3.28 0.1 1.88
Passage Cu.m. 4 2.25 4.25 0.1 3.82
Cu.m. 1 2.25 3.28 0.1 0.73
Total Sand Filling Cu.m. 0

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


3.1 STONE WORK
DRY STONE SOLING
along grid B Combine footing Due to water
table
CF Cu.m. 1 22.53 2 0.2 9.01
Total Dry Stone Soling Cu.m. 9.01
4 BRICK WORK
4.1 FLAT BRICK SOLING
FOOTINGS
F1 Sq.m. 2 2.1 2.1 8.82
F2 Sq.m. 8 2.5 2.5 50
F3 Sq.m. 2 3.63 3 21.78
CF Sq.m. 1 22.53 2 45.06
Additional CF Sq.m. 1 5.2 1.5 0
BOTTOM TIE BEAM
Bottom tie beam along grid C Sq.m. 1 9.43 0.375 3.53
Bottom tie beam along grid A Sq.m. 2 8 0.375 6
Along grid 1 & 6/ B-C Sq.m. 2 2.95 0.375 2.21
Along grid 2,3,4,5/ B-C Sq.m. 4 2.75 0.375 4.12

Inside Room Sq.m. 4 5.75 4.25 97.75


Sq.m. 1 5.75 3.28 18.86
Passage Sq.m. 4 2.25 4.25 38.25
Sq.m. 1 2.25 3.28 7.38

Ground floor toilet Sq.m. 1 1.9 1.5 2.85


First floor Toilet Sq.m. 1 2.45 3.3 8.08
Second floor toilet Sq.m. 1 2.45 4.5 11.02

Front Steps Sq.m. 1 21.93 0.6 13.15

First floor Front Passage Sq.m. 1 23.25 1.2 27.9


Sq.m. 1 8.5 1.3 11.05
Second floor apron Sq.m. 1 28 3.4 95.2
Protection wall
Left side protection wall at ground floor Sq.m. 1 3.7 0.3 1.11
Right side protection wall at ground floor Sq.m. 1 7.4 0.3 2.22
Front side protection wall at ground floor Sq.m. 1 23.4 0.2 4.68
Left side protection wall at first floor Sq.m. 1 7.9 0.3 2.37

TOTAL FLAT BRICK SOLING Sq.m. 483.39


4.2 FULL BRICK WORK
From LTB to plinth beam Along grid C Cu.m. 1 19.53 0.23 1.325 5.95
Along grid A Cu.m. 1 19.53 0.23 1.325 5.95
Along grid 1,2,3,4,5&6/B-C Cu.m. 6 5.6 0.23 1.325 10.23
Along grid 1,2,3,4,5&6/A-B Cu.m. 6 2.1 0.23 1.45 4.2
Below projection slab Cu.m. 1 22.5 0.23 0.45 2.32
Second floor level steps
First steps Cu.m. 1 16.6 0.6 0.15 1.49
Second steps Cu.m. 1 16.6 0.3 0.15 0.74
Toe wall at first floor level Cu.m. 1 27.2 0.23 0.15 0.93
Cu.m. 1 22.1 0.23 0.15 0.76
Protection wall
Left side protection wall at ground floor Cu.m. 1 3.7 0.23 0.9 0.76
Right side protection wall at ground floor Cu.m. 1 7.4 0.23 0.65 1.1
Front side protection wall at ground floor Cu.m. 1 23.4 0.12 0.3 0.84
Left side protection wall at first floor Cu.m. 1 7.9 0.23 1 1.81

TOTAL FULL BRICK WORK Cu.m. 37.08


5 AAC BLOCK
5.1 AAC BLOCK (600*200*200)
GROUND FLOOR
ALONG GRID 2,3,4,5&6/A-B) Sq.m 5 5.6 2.4 67.2
toilet Sq.m 1 1.9 2.725 5.17

FIRST FLOOR
ALONG GRID1,4,5 &6/A-C Sq.m 4 7.7 2.4 73.92
ALONG GRID A&C/1-6 Sq.m 2 19.53 2.45 95.69

DEDUCTION
D Sq.m -3 1.2 2.55 -9.18
DW Sq.m -1 1 2.55 -2.55
Sq.m -1 2 1.635 -3.27
W Sq.m -9 2 1.635 -29.43
V1 Sq.m -2 1.5 0.6 -1.8
LANDING BEAM Sq.m -1 3.13 0.4 -1.26
Along grid 5/A-B Sq.m -1 2.1 2.55 -5.36

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


SECOND FLOOR
ALONG GRID1,4,5 &6/A-C Sq.m 4 7.7 2.4 73.92
ALONG GRID A&C/1-6 Sq.m 2 19.53 2.45 95.69
DEDUCTION
D Sq.m -4 1.2 2.55 -12.24
W Sq.m -10 2 1.635 -32.7
V1 Sq.m -2 1.5 0.6 -1.8
LANDING BEAM Sq.m -1 3.13 0.4 -1.26
Along grid 5/A-B Sq.m -1 0.8 2.55 -2.04
TOTAL Sq.m. 308.7
5.2 AAC BLOCK(600*200*100)
First Floor toilet wall Sq.m 1 6.055 2.45 14.83
Second Floor toilet wall Sq.m 1 7.36 2.45 18.03
Ground floor toilet Sq.m 1 1.5 2.725 4.08
DEDUCTION
D2 Sq.m -1 0.75 2.1 -1.58

TOTAL Sq.m. 35.36


5.3 AAC BLOCK(600*200*150)
First floor office area Sq.m. 1 2.45 2.4 5.88
First floor toilet Sq.m. 1 1.7 2.4 4.08
Total Sq.m. 9.96
6 CONCRETE WORK
6.1 PCC of grade M10
FOOTINGS
F1 Cu.m. 2 2.1 2.1 0.075 0.66
F2 Cu.m. 8 2.5 2.5 0.075 3.75
F3 Cu.m. 2 3.63 3 0.075 1.63
CF Cu.m. 1 22.53 2 0.075 3.37
Additional CF Cu.m. 1 5.2 1.5 0.075 0.58

BOTTOM TIE BEAM


Bottom tie beam along grid C Cu.m. 1 9.43 0.375 0.075 0.26
Bottom tie beam along grid A Cu.m. 2 8 0.375 0.075 0.45
Along grid 1 & 6/ B-C Cu.m. 2 2.95 0.375 0.075 0.16
Along grid 2,3,4,5/ B-C Cu.m. 4 2.75 0.375 0.075 0.3

Inside Room Cu.m. 4 5.75 4.25 0.075 7.33


Cu.m. 1 5.75 3.28 0.075 1.41
Passage Cu.m. 4 2.25 4.25 0.075 2.86
Cu.m. 1 2.25 3.28 0.075 0.55

Ground floor toilet Cu.m. 1 1.9 1.5 0.075 0.21


First floor Toilet Cu.m. 1 2.45 2.9 0.075 0.53
Second floor toilet Cu.m. 1 4.175 2.45 0.075 0.76
Cu.m.
Front Steps Cu.m. 1 21.93 0.6 0.075 0.98

First floor Front Passage Cu.m. 1 23.25 1.2 0.075 2.09


Cu.m. 1 8.5 1.3 0.075 0.82
Second floor apron Cu.m. 1 28 3.2 0.075 6.72
Protection wall
Left side protection wall at ground floor Cu.m. 1 3.7 0.3 0.075 0.08
Right side protection wall at ground floor Cu.m. 1 7.4 0.3 0.075 0.16
Front side protection wall at ground floor Cu.m. 1 23.4 0.2 0.075 0.35
Left side protection wall at first floor Cu.m. 1 7.9 0.3 0.075 0.17

Cu.m.
TOTAL Cu.m. 36.18
6.2 PCC for RCC of Grade M25
Column upto plinth lvl
C3 Cu.m. 2 0.4 0.4 1.975 0.63
Cu.m. 4 0.4 0.4 1.925 1.23
C1 Cu.m. 2 0.4 0.4 1.975 0.63
Cu.m. 4 0.4 0.4 1.925 1.23
C2 Cu.m. 6 0.4 0.4 2.025 1.94
Shearwall Cu.m. 1 26.805 0.25 2.025 13.57
Column above plinth lvl
C1 Cu.m. 6 0.4 0.4 6 5.76
C2 Cu.m. 6 0.4 0.4 9 8.64
C3 Cu.m. 6 0.4 0.4 9 8.64
Shearwall Cu.m. 1 26.805 0.25 2.55 17.08

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


TOTAL Cu.m. 59.35
6.3 PCC for RCC of Grade M20
FOOTINGS
F1 Cu.m. 2 2.1 2.1 0.35 3.08
F2 Cu.m. 8 2.5 2.5 0.4 20
F3 Cu.m. 2 3.63 3 0.35 7.62
CF Cu.m. 1 22.53 2 0.3 13.51
Additional CF Cu.m. 1 5.2 1.5 0.3 2.34
TIE BEAM
Bottom tie beam along grid A,C Cu.m. 2 19.53 0.23 0.3 2.69 B grid Shear Wall
Bottom tie beam along grid 1,2,3,4,5&6/A-C Cu.m.
6 7.7 0.23 0.3 3.18
Upper plinth BEAM
beam along grid B&C Cu.m. 2 19.53 0.25 0.4 3.9
beam along grid 1,2,3,4,5&6/B-C Cu.m. 6 5.6 0.25 0.45 3.78

Beam
Ground Floor Beam
beam along grid A,B&C Cu.m. 3 19.53 0.25 0.275 4.02
beam along grid 1,2,3,4,5&6/A-C Cu.m. 6 7.7 0.25 0.325 3.75
Secondary beam Cu.m.
Along X-X Cu.m. 1 17 0.23 0.175 0.68
Along grid 4-5 Cu.m. 1 3.28 0.23 0.225 0.16
First Floor Beam
beam along grid A,B&C Cu.m. 3 19.53 0.25 0.275 4.02
beam along grid 1,2,3,4,5&6/A-C Cu.m. 6 7.7 0.25 0.325 3.75
Secondary beam Cu.m.
Along X-X Cu.m. 1 17 0.23 0.175 0.68
Along grid 4-5 Cu.m. 1 3.28 0.23 0.225 0.16
Second Floor Beam
beam along grid A,B&C Cu.m. 3 19.53 0.25 0.4 5.85
beam along grid 1,2,3,4,5&6/A-C Cu.m. 6 7.7 0.25 0.45 5.19
SLAB
First FLoor Cu.m. 1 21.93 8.9 0.125 24.39
projection Cu.m. 1 1.675 2.15 0.125 0.45
Deduction
Column Cu.m. -18 0.4 0.4 0.125 -0.36
Second FLoor Cu.m. 1 21.93 10.7 0.125 29.33
Deduction
Staircase void Cu.m. -1 4.15 3.28 0.125 -1.71
Column Cu.m. -18 0.4 0.4 0.125 -0.36
Void at projection slab Cu.m. -5 1 1 0.125 -0.63
Cu.m. 5 4.4 0.1 0.1 0.22
STAIRCASE Cu.m.
FIRST FLOOR TO SECOND FLOOR Cu.m.
First flight waist slab Cu.m. 1 3.242 1.5 0.175 0.85
Landing slab Cu.m. 1 3.28 1.11 0.175 0.63
Cu.m. 1 1.5 0.44 0.175 0.11
Second flight waist slab Cu.m. 1 3 1.5 0.175 0.78
Landing Beam Cu.m. 1 3.13 0.25 0.225 0.17
Step Cu.m. 20 1.5 0.3 0.075 0.67

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


BANDS
SILL BANDS
GROUND FLOOR
ALONG GRID 2,3,4,5&6/A-B) Cu.m. 5 5.6 0.2 0.075 0.42
toilet Cu.m. 1 1.9 0.2 0.075 0.02
Cu.m. 1 1.5 0.2 0.075 0.02
DEDUCTION Cu.m.
D2 Cu.m. -1 0.75 0.2 0.075 -0.02
FIRST FLOOR Cu.m.
ALONG GRID1,4,5 &6/A-C Cu.m. 4 7.7 0.2 0.075 0.46
ALONG GRID A&C/1-6 Cu.m. 2 19.53 0.2 0.075 0.58
window sill projection Cu.m. 10 2.2 0.075 0.075 0.12
ventilation sill projection Cu.m. 2 1.7 0.075 0.075 0.01
DEDUCTION Cu.m.
D Cu.m. -3 1.2 0.2 0.075 -0.06
SECOND FLOOR Cu.m.
ALONG GRID1,4,5 &6/A-C Cu.m. 4 7.7 0.2 0.075 0.46
ALONG GRID A&C/1-6 Cu.m. 2 19.53 0.2 0.075 0.58
grid B Cu.m. 1 4.1 0.2 0.075 0.06
toilet Cu.m. 1 1.6 0.2 0.075 0.02
W Cu.m. 10 2 0.075 0.075 0.11
V1 Cu.m. 2 1.5 0.075 0.075 0.01
DEDUCTION
Wall gap along grid 5 Cu.m. -1 0.78 0.2 0.075 -0.02
D Cu.m. -4 1.2 0.2 0.075 -0.08

AAC BLOCK(600*200*100)
Along y-Axis Cu.m. 1 13.415 0.1 0.075 0.1
AAC BLOCK(600*200*150)
office area Cu.m. 1 4.15 0.15 0.075 0.04
LINTEL BANDS
GROUND FLOOR
ALONG GRID 2,3,4,5&6/A-B) Cu.m. 5 5.6 0.2 0.075 0.42
toilet Cu.m. 1 1.9 0.2 0.075 0.02
1 1.5 0.2 0.075 0.02
DEDUCTION Cu.m.
D2 Cu.m. -1 0.75 0.2 0.075 -0.02
FIRST FLOOR
ALONG GRID1,4,5 &6/A-C Cu.m. 4 7.7 0.2 0.075 0.46
ALONG GRID A&C/1-6 Cu.m. 2 19.53 0.2 0.075 0.58
DEDUCTION
D Cu.m. -3 1.2 0.2 0.075 -0.06
SECOND FLOOR
ALONG GRID1,/A-C Cu.m. 1 3.7 0.2 0.075 0.05
ALONG GRID6,/A-C Cu.m. 1 2.2 0.2 0.075 0.03
ALONG GRID4,5/A-C Cu.m. 2 7.7 0.2 0.075 0.23
ALONG GRID A/1-6 Cu.m. 1 13.13 0.2 0.075 0.19
ALONG GRID C/1-6 Cu.m. 1 10.03 0.2 0.075 0.15
ALONG GRID B/5-6 Cu.m. 1 4.1 0.2 0.075 0.06
toilet Cu.m. 1 1.6 0.2 0.075 0.02

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


AAC BLOCK(600*200*100) Cu.m.
Along y-Axis Cu.m. 1 13.415 0.1 0.075 0.1

AAC BLOCK(600*200*150)
office area Cu.m. 1 4.15 0.15 0.075 0.04
148.02
7.1 FORM WORK
Formwork for Footing
FOOTINGS
F1 Sq.m. 2 8.4 0.35 5.88
F2 Sq.m. 8 10 0.4 32
F3 Sq.m. 2 13.26 0.35 9.28
CF Sq.m. 1 49.06 0.3 14.71
Additional CF Sq.m. 1 13.4 0.3 0
TIE BEAM
beam along grid A&C Sq.m. 2 19.53 0.6 23.43 B grid shear wall
Bottom tie beam along grid 1,2,3,4,5&6/A-C Sq.m.
6 7.7 0.6 27.72

Upper plinth BEAM


beam along grid B&C Sq.m. 2 19.53 0.82 32.02
beam along grid 1,2,3,4,5&6/A-B Sq.m. 6 5.6 0.92 30.91
Shearwall along grid B/1-6 Sq.m. 2 21.205 1.75 74.21
Shearwall along grid 1/B-C Sq.m. 2 5.6 1.7 19.04

First Floor Beam


beam along gridA, B&C Sq.m. 3 19.53 0.55 32.22
beam along grid 1,2,3,4,5&6/A-C Sq.m. 6 7.7 0.65 30.03
Secondary beam
Along X-X Sq.m. 1 17 0.35 5.95
Along grid 4-5 Sq.m. 1 3.28 0.35 1.14
Shearwall along grid B/1-6 Sq.m. 1 42.41 2.55 108.14
Shearwall along grid 1/B-C Sq.m. 1 10.8 2.55 27.54
Second Floor Beam
beam along grid A,B&C Sq.m. 3 19.53 0.55 32.22
beam along grid 1,2,3,4,5&6/A-C Sq.m. 6 7.7 0.65 30.03
Secondary beam
Along X-X Sq.m. 1 17 0.35 5.95
Along grid 4-5 Sq.m. 1 3.28 0.35 1.14
Truss Beam
beam along grid A,B&C Sq.m. 3 19.53 1.05 61.51
beam along grid 1,2,3,4,5&6/A-C Sq.m. 6 7.7 1.15 53.13

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Column
Column upto Plinth level
Column upto plinth lvl
C3 Sq.m. 2 1.6 2.1 6.72
Sq.m. 4 1.6 2.05 13.12
C1 Sq.m. 2 1.6 2.1 6.72
Sq.m. 4 1.6 2.05 13.12
C2 Sq.m. 6 1.6 2.15 20.64
Deduction of beam faces
Foundation tie beam Sq.m. -42 0.23 0.3 -2.9
Plinth beam Sq.m. -12 0.25 0.4 -1.2
Sq.m. -20 0.25 0.45 -2.25

Columns from ground floor to first floor level


C1 Sq.m. 6 1.6 2.875 27.6
C2 Sq.m. 6 1.6 2.875 27.6
Deductions of beam faces Sq.m. -8 0.25 0.275 -0.55
Sq.m. -12 0.25 0.325 -0.98
Deduction of shear wall face Sq.m. -12 1.75 0.25 -5.25

Columns from first floor level to top floor


C1 Sq.m. 6 1.6 5.875 56.4
C2 Sq.m. 6 1.6 5.875 56.4
C3 Sq.m. 6 1.6 5.875 56.4
Deductions of beam faces
First floor beam Sq.m. -30 0.25 0.275 -2.07
Sq.m. -24 0.25 0.325 -1.95
Second floor beam Sq.m. -30 0.25 0.4 -3
Sq.m. -24 0.25 0.45 -2.7

SLAB
First floor slab Sq.m. 1 21.93 8.9 195.17
Sq.m. 1 2.115 1.625 3.43
Sides Sq.m. 1 69.14 0.125 8.64
Deduction Sq.m.
Column Sq.m. -18 0.4 0.4 -2.88

Second FLoor slab Sq.m. 1 21.93 10.7 234.65


Sides Sq.m. 1 65.26 0.125 8.15
Projection slab void Sq.m. 5 4 0.225 4.5
Sq.m. 5 4.8 0.1 2.4
Deduction
Staircase void Sq.m. -1 4.15 3.28 -13.62
Column Sq.m. -18 0.4 0.4 -2.88
Ventilation void Sq.m. -5 1 1 -5
Staircase
First floor to Second floor stair
First flight waist slab bottom Sq.m. 1 3.242 1.5 4.86
Sides of waist slab Sq.m. 2 3.242 0.325 2.1
Landing Sq.m. 1 3.28 1.11 3.64
Sq.m. 1 1.5 0.44 0.66
Sides of landing Sq.m. 1 3.25 0.175 0.56
Second flight waist slab bottom Sq.m. 1 3 1.5 4.5
Sides of waist slab Sq.m. 2 3 0.325 1.95
Step risers Sq.m. 20 1.5 0.15 4.5

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Landing Beam Sides Sq.m. 1 3.28 0.45 1.47

Bands
SILL BANDS
GROUND FLOOR
ALONG GRID 2,3,4,5&6/A-B) Sq.m 5 5.6 0.15 4.2
toilet Sq.m 1 1.9 0.15 0.28
Sq.m 1 1.5 0.15 0.22
DEDUCTION
D2 Sq.m -1 0.75 0.15 -0.12
FIRST FLOOR
ALONG GRID1,4,5 &6/A-C Sq.m 4 7.7 0.15 4.62
ALONG GRID A&C/1-6 Sq.m 2 19.53 0.15 5.85
window sill projection(W) Sq.m 10 2.2 0.075 1.65
ventilation sill projection(V1) Sq.m 2 1.7 0.075 0.25
DEDUCTION
D Sq.m -3 1.2 0.15 -0.54
SECOND FLOOR
ALONG GRID1,4,5 &6/A-C Sq.m 4 7.7 0.15 4.62
ALONG GRID A&C/1-6 Sq.m 2 19.53 0.15 5.85
grid B Sq.m 1 3.3 0.15 0.49
toilet Sq.m 1 1.6 0.15 0.24
window sill projection(W) Sq.m 10 2.2 0.075 1.65
ventilation sill projection(V1) Sq.m 2 1.7 0.075 0.25
DEDUCTION
D Sq.m -4 1.2 0.15 -0.72
D1 Sq.m -1 0.9 0.15 -0.14
AAC BLOCK(600*200*100) 0.15
First Floor toilet wall Sq.m 1 6.055 0.15 0.9
Second Floor toilet wall Sq.m 1 7.36 0.15 1.1

AAC BLOCK(600*200*150)
First floor office area Sq.m. 1 2.45 0.15 0.36
First floor toilet Sq.m. 1 1.7 0.15 0.25
LINTEL BANDS
GROUND FLOOR
ALONG GRID 2,3,4,5&6/A-B) Sq.m 5 5.6 0.15 4.2
toilet Sq.m 1 1.9 0.15 0.28
Sq.m 1 1.5 0.15 0
DEDUCTION
D2 Sq.m -1 0.75 0.15 -0.12
FIRST FLOOR
ALONG GRID1/A-C Sq.m 1 3.7 0.15 0.55
ALONG GRID2/A-C Sq.m 1 2.45 0.15 0.36
ALONG GRID4/A-C Sq.m 1 5.6 0.15 0.84
ALONG GRID5/A-C Sq.m 1 5.6 0.15 0.84
ALONG GRID6/A-C Sq.m 1 2.2 0.15 0.33
ALONG GRID A&C/1-6 Sq.m 1 10.03 0.15 1.5
ALONG GRID A&C/1-6 Sq.m 1 13.13 0.15 1.96
toilet portion Sq.m 1 6.8 0.15 1.02

SECOND FLOOR
ALONG GRID1/A-C Sq.m 1 3.7 0.15 0.55
ALONG GRID4/A-C Sq.m 1 6.5 0.15 0.97
ALONG GRID5/A-C Sq.m 1 5.725 0.15 0.85
ALONG GRID6/A-C Sq.m 1 2.2 0.15 0.33
ALONG GRID A&C/1-6 Sq.m 1 10.03 0.15 1.5
ALONG GRID A&C/1-6 Sq.m 1 13.13 0.15 1.96
ALONG GRID B/5-6 Sq.m 1 4.1 0.15 0.61
toilet portion Sq.m 1 1.6 0.15 0.24
AAC BLOCK(600*200*100) 0.15
First Floor toilet wall Sq.m 1 3.2 0.15 0.48
Second Floor toilet wall Sq.m 1 7.36 0.15 1.1

AAC BLOCK(600*200*150)
First floor office area Sq.m. 1 2.45 0.15 0.36
First floor toilet Sq.m. 1 1.7 0.15 0.25
Total Sq.m. 1429.09

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


8.1 REINFORCEMENT WORK
FOUNDATIONS Kg 1 2179.32 2179.32
COLUMNS Kg 1 9014.19 9014.19
BEAMS Kg 1 8610.33 8610.33
SLABS Kg 1 4044.2 4044.2
STAIRCASE Kg 1 1381.81 1381.81
BANDS Kg 1 734.3 734.3
SHEAR WALLS Kg 1 1911.14 1911.14

Total Kg 27875.29
9 FLOORING WORK
9.1 PLASTIC LAYING
Rooms Sq.m. 4 5.75 4.25 97.75
Sq.m. 1 3.28 4.25 13.94
Passage Sq.m. 4 5.75 2.25 51.75
Sq.m. 1 3.28 2.25 7.38
Total Sq.m. 0
9.2 SCREEDING
Ground Floor
Shop 1,3,4&,5 Sq.m. 4 6.075 4.3 104.49
Shop 2 Sq.m. 1 6.075 3.3 20.04
Toilet Sq.m. 1 1.8 1.5 2.7
First Floor
Community Hall Sq.m. 1 13.3 8.35 111.05
Dinning room & Toilet Sq.m. 1 8.1 4.3 34.83
Passage area Sq.m. 1 8.1 3.38 27.37

Second Floor
Library Hall Sq.m. 1 13.3 8.35 111.05
E- Library hall & Toilet Sq.m. 1 8.1 4.3 34.83
Staicase area passage Sq.m. 1 4.15 3.38 14.02

Top Projected Slab Sq.m. 1 21.93 1.8 39.47


Void Sq.m. -5 1 1 -5
Staircase
Tread Sq.m. 18 1.5 0.3 8.1
Landing Sq.m. 1 1.5 3.2 4.8

Front Steps on ground floor Sq.m. 2 21.93 0.3 13.15


Second floor front steps Sq.m. 2 16.6 0.3 9.96

TOTAL Sq.m. 530.86


9.3 CEMENT PUNNING

Ground Floor
Shop 1,3,4&,5 Sq.m. 4 6.075 4.3 104.49
Shop 2 Sq.m. 1 6.075 3.3 20.04
First Floor
Community Hall Sq.m. 1 8.35 13.3 111.05
Ground floor step
Front Steps tread Sq.m. 2 21.93 0.3 13.15
Front Steps riser Sq.m. 3 21.93 0.15 9.86
Second floor front steps tread Sq.m. 2 15.33 0.3 9.19
Second floor front steps riser Sq.m. 3 15.33 0.15 6.89

Skirting Sq.m. 1 191.38 0.125 23.92

Total Sq.m. 298.59


9.4 CEMENT SKIRTING
Ground Floor
Shop 1,3,4&,5 R.M. 4 15.65 62.6
Shop 2 R.M. 1 14.65 14.65
First Floor
Community Hall R.M. 1 58 58
Staircase lobby R.M. 1 23.31 23.31

Second Floor
Front top slab R.M. 1 19.53 19.53
Staircase
Waist Slab R.M. 2 3.466 6.93
Landing R.M. 1 6.36 6.36

Total R.M. 191.38

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


9.5 TILE LAYING ON TOILET
Ground floor
Toilet Sq.m. 1 1.8 1.5 2.7

First floor
Floor Tile
Gents toilet Sq.m. 1 2.45 2.8 6.86
Second floor
Gents toilet Sq.m. 1 2.45 1.88 4.6
Ladies Toilet & passage Sq.m. 1 2.31 2.45 5.65

Total Sq.m. 19.81


9.6 WALL TILE
Ground Floor toilet
Toilet Sq.m. 1 5.85 1.3 7.6
First floor toilet
Gents toilet Sq.m. 1 14.35 1.3 18.65
Second floor
Wall Tile
Gents toilet Sq.m. 1 7.55 1.3 9.81
Ladies Toilet Sq.m. 1 6.55 1.3 8.51
Passage Sq.m. 1 4.425 1.3 5.75
Total Sq.m. 50.32

10 FINISHING WORK
10.1 EXTERNAL PLASTER
Along grid C/1-6 from Ground floor to second
Sq.m. 1 23.93 9 215.37
floor
Along grid A/1-6 from First floor to second
Sq.m. 1 23.93 6 143.58
floor
along grid 1 & 6 from ground floor to First
Sq.m. 2 6.8 3 40.8
floor
along grid 1 & 6 from First floor to second
Sq.m. 2 9.7 6 116.4
floor
Slab top of ground floor to First floor Sq.m. 2 19.53 0.075 2.92
ground floor toilet Sq.m. 1 2.65 3 7.95
Deduction of doow & windows
shutter Sq.m. -4 4.1 2.6 -42.64
shutter Sq.m. -1 3.13 2.6 -8.14
W Sq.m. -20 2 1.65 -66
V3 Sq.m. -4 1.5 0.6 -3.6
D Sq.m. -4 1.2 2.55 -12.24
Dw Sq.m. -1 1 2.55 -2.55
Masonary wall plaster Sq.m. 1 23.555 3.3 77.73

Protection wall
Left side protection wall at ground floor Sq.m. 1 3.7 0.73 2.7
Right side protection wall at ground floor Sq.m. 1 7.4 0.73 5.4
Left side protection wall at first floor Sq.m. 1 7.9 0.83 6.55
0
Ground floor steps riser Sq.m. 3 21.93 0.15 9.86
Second floor steps Sq.m. 3 16.6 0.15 7.47

Total Sq.m. 501.56


10.2 INTERNAL PLASTER
Ground Floor
Along grid 1,2,3,4,5,6/A-B Sq.m. 10 6.15 2.55 156.82
Along grid B Sq.m. 4 4.3 2.6 44.72
Sq.m. 1 3.3 2.6 8.58
toilet Sq.m. 1 5.85 2.875 16.81

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


First Floor
Along grid 1/A-C Sq.m. 1 8.35 2.55 21.29
Along grid 2/A-C bothside Sq.m. 1 6.5 2.55 16.57
Along grid 4/A-C (bothside) Sq.m. 1 17.5 2.55 44.62
Along grid 5/A-C (bothside) Sq.m. 1 12.2 2.55 31.11
Along grid 6/A-C Sq.m. 1 8.65 2.55 22.05
ALONG GRID A/1-6 Sq.m. 1 21.23 2.6 55.19
ALONG GRID C/1-6 Sq.m. 1 20.33 2.6 52.85
ALONG GRID B/5-6 (BOTHSIDE) Sq.m. 1 6.2 2.875 17.82
TOILET(bothside) Sq.m. 1 8.5 2.1 17.85
Internal columns Sq.m. 4 1.6 2.875 18.4
Wall face Sq.m. -5 0.2 2.875 -2.88
Staircase riser Sq.m. 20 1.5 0.15 4.5
Perifery
W Sq.m. 10 7.3 0.2 14.6
D Sq.m. 3 5.1 0.2 3.06
DW Sq.m. 1 5.1 0.2 1.02
D1 Sq.m. 1 4.35
D2 Sq.m. 3 4.2 0.1 1.26
V3 Sq.m. 2 4.2 0.2 1.68
Deduction
W Sq.m. -10 2 1.65 -33
D Sq.m. -2 1.2 2.6 -6.24
DW Sq.m. -1 1 2.6 -2.6
V3 Sq.m. -2 1.5 0.6 -1.8
Second Floor
Along grid 1/A-C Sq.m. 1 8.35 2.55 21.29
Along grid 4/A-C (bothside) Sq.m. 1 17.5 2.55 44.62
Along grid 5/A-C (bothside) Sq.m. 1 15.9 2.55 40.54
Along grid 6/A-C Sq.m. 1 8.65 2.55 22.05
ALONG GRID A/1-6 Sq.m. 1 20.73 2.6 53.89
ALONG GRID C/1-6 Sq.m. 1 20.33 2.6 52.85
ALONG GRID B/5-6 (BOTHSIDE) Sq.m. 2 6.32 2.875 36.34
TOILET(bothside) Sq.m. 1 6.72 2.1 14.11
Internal columns Sq.m. 4 1.6 2.875 18.4
Wall face deduction Sq.m. -3 0.2 2.875 -1.73
Perifery
W Sq.m. 10 7.3 0.2 14.6
D Sq.m. 4 5.1 0.2 4.08
V3 Sq.m. 2 4.2 0.2 1.68
Deduction
W Sq.m. -10 2 1.65 -33
D Sq.m. -4 1.2 2.6 -12.48
V3 Sq.m. -2 1.5 0.6 -1.8

Total Sq.m. 779.72

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


10.3 CEILING PLASTER
First floor
Slab along grid 1-6/A-B Sq.m. 1 21.93 6.4 140.35
Beam Sides
Main beam along grid C/ 1-6 Sq.m. 1 19.53 0.275 5.37
Main beam Along grid B/1-6 Sq.m. 1 19.53 0.275 5.37
Main beam along grid 1-6//B-C Sq.m. 10 5.6 0.325 18.2
Secondary beam along gid X-X Sq.m. 2 17 0.175 5.95
Secondary beam on staircase section Sq.m. 2 3.28 0.175 1.14
Outside toilet slab Sq.m. 1 1.8 1.5 2.7

Deduction
Column area coverage Sq.m. -12 0.4 0.4 -1.92
Internal wall
600*200*200 wall Sq.m. -6 5.6 0.2 -6.72
SHEARWALL ALONG GRID B Sq.m. -1 19.53 0.25 -4.89
Second floor
SLAB PROJECTION Sq.m. 1 21.93 1.8 39.47
Slab along grid 1-6/A-B Sq.m. 1 21.93 8.9 195.17
Beam Sides
Main beam along grid C/ 1-6 Sq.m. 1 19.53 0.275 5.37
Main beam Along grid B/1-6 Sq.m. 1 19.53 0.275 5.37
Main beam Along grid A/1-6 Sq.m. 1 19.53 0.275 5.37
Main beam along grid 1-6/A-C Sq.m. 10 7.7 0.325 25.02
Secondary beam along gid X-X Sq.m. 2 17 0.175 5.95
Secondary beam on staircase section Sq.m. 2 3.28 0.175 1.14
Staircase void Sq.m. -1 4.15 3.28 -13.62

Staircase
First flight waist slab Sq.m. 1 3.242 1.5 4.86
Sides of first flight Sq.m. 1 3.242 0.175 0.56
Sq.m. 10 0.3 0.075 0.22
Landing Sq.m. 1 3.13 1.11 3.47
Sq.m. 1 1.5 0.44 0.66
Second flight waist slab Sq.m. 1 3 1.5 4.5
Sides of second flight waist slab Sq.m. 1 3 0.175 0.52
Sq.m. 10 0.3 0.075 0.22
Deduction
Column area coverage Sq.m. -18 0.4 0.4 -2.88
void on projection Sq.m. -5 1 1 -5

Wall area coverage


ALONG GRID A/1-6 Sq.m -1 13.13 0.2 -2.63
ALONG GRID B/1-6 Sq.m -1 4.1 0.1 -0.41
ALONG GRID C/1-6 Sq.m -1 10.03 0.2 -2.01
ALONG GRID 1/(A-C) Sq.m -1 3.7 0.2 -0.74
ALONG GRID 2/(A-C) Sq.m -1 2.45 0.15 -0.37
ALONG GRID 4/(A-C) Sq.m -1 6.5 0.2 -1.3
ALONG GRID 5/(A-C) Sq.m -1 5.73 0.2 -1.15
ALONG GRID 6/(A-C) Sq.m -1 2.165 0.2 -0.44

Top Floor
Beam Sides & Bottom
Main beam along grid A/ 1-6 Sq.m. 1 19.53 0.65 12.69
Main beam Along grid B/1-6 Sq.m. 2 19.53 0.65 25.38
Main beam Along grid C/1-6 Sq.m. 1 19.53 0.65 12.69

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Main beam along grid 1-6/A-C Sq.m. 10 7.7 0.7 53.9
Deductions
Wall area coverage
ALONG GRID A/1-6 Sq.m -1 13.13 0.2 -2.63
ALONG GRID B/1-6 Sq.m -1 4.1 0.2 -0.82
ALONG GRID C/1-6 Sq.m -1 10.03 0.2 -2.01
ALONG GRID 1/(A-C) Sq.m -1 3.7 0.2 -0.74
ALONG GRID 4/(A-C) Sq.m -1 6.5 0.2 -1.3
ALONG GRID 5/(A-C) Sq.m -1 5.725 0.2 -1.15
ALONG GRID 6/(A-C) Sq.m -1 2.165 0.2 -0.44
Total Sq.m. 528.44
10.4 PLASTER ON RCC LINTEL WITH
CORNICE
First Floor
W R.M. 10 2.2 22
V3 R.M. 2 1.7 3.4
Second Floor
W R.M. 10 2.2 22
V3 R.M. 2 1.7 3.4
Total R.M. 0
10.5 EMULSION PAINT
Total internal plaster area Sq.m. 779.72
Total ceiling plaster area Sq.m. 528.44
Deductions
Wall tile area Sq.m. -50.32
Total Sq.m. 1257.84
10.6 WEATHER COAT
Total external plaster area Sq.m. 1 501.56 501.56
Total RCC Lintel with cornice area Sq.m. 1 0 0
Sq.m. 1 39.98 39.98
Total Sq.m. 541.54
11 DOOR, WINDOWS WORK
11.1 UPVC SLIDING WINDOWS
First Floor
W Sq.m. 10 2 1.635 32.7
Second Floor
W Sq.m. 10 2 1.635 32.7
Total Sq.m. 65.4
11.2 UPVC TOP HUNG WINDOWS
V3 Sq.m. 2 2.1 0.6 2.52
V3 Sq.m. 2 1.5 0.6 1.8
Void Sq.m. 5 1 1 5
Total Sq.m. 9.32
11.3 UPVC DOUBLE DOOR
D Sq.m. 7 1.2 2.6 21.84
Total Sq.m. 21.84
11.4 UPVC SINGLE DOOR
D1 Sq.m. 2 1 2.175 4.35
D2 Sq.m. 6 0.75 2.1 9.45
Total Sq.m. 13.8
12 ROOFING WORK
12.1 CGI ROOFING SHEET
Sq.m. 2 23.78 5.725 272.28
Total Sq.m. 272.28
12.2 CGI ROOFING SHEET ON RIDGE
Rm 1 23.78 23.78
TOTAL Rm 23.78
12.3 GI GUTTER:
RM 2 23.78 47.56

TOTAL 47.56

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


13.1 FLASE CEILING WORK PVC BOARD
Along grid A-B/1-6 Sq.m. 4 2.25 4.25 38.25
Sq.m. 1 2.25 3.28 7.38
Along grid B-C/1-6 Sq.m. 4 5.75 4.25 97.75
Sq.m. 1 5.75 3.28 18.86
Total Sq.m. 162.24
14 MISCELLANEOUS WORK
14.1 WATER PROOFING
Shear wall Library Block Sq.m. 1 23.6 2.875 67.85
Sq.m. 1 6 2.875 17.25
TOTAL 85.1
14.2 INSULATION WORK
Along grid 1-6/A-C Sq.m. 1 19.53 9.36 182.8
Total Sq.m. 182.8
15 METAL WORK
15.1 BLACK TUBULAR PIPE
Description of Work Total l Unit wt.
Bottom Chord NB 50(M) Kg. 12 4.329 51.94 5.03 261.25
Vertical Bracing NB 40(M) Kg. 12 0.419 5.02 3.56 17.87
Kg. 12 0.825 9.9 3.56 35.24
Kg. 12 1.088 13.05 3.56 46.45
Kg. 12 1.351 16.21 3.56 57.7
Inclined Bracing NB 32(M) Kg. 12 1.272 15.26 3.1 47.3
Kg. 12 1.123 13.47 3.1 41.75
Kg. 12 1.312 15.74 3.1 48.79
Top Chord NB 50(M) Kg. 12 5.281 63.37 5.03 318.75
Purlin NB 65(M)
NB65 purlin rm 16 4.47 71.52 6.44 460.58
NB65 purlin rm 4 3.5 14 6.44 90.16
beyond 1 and 6 NB65 rm 24 1.11 26.64 6.44 171.56
Runner NB 40(M) Kg.
Runner NB40(M) kg 8 4.27 34.16 3.56 121.6
kg 2 3.3 6.6 3.56 23.49
Runner box kg 12 0.433705 5.20446 78.5 408.55
Nut-bolt rm 40 0.0006 0.024 78.5 1.88

Connections
Base Plate Volume

At column (300*300*10) Kg. 36 0.0009 7850 254.34


Nut Kg. 72 0.00000826236 7850 4.66
16mm Dia anchord Bolt Kg. 72 0.45 32.4 1.58 51.19

Bottom Chord & Top Chord


ISA 135*65*10 (300mm width) Kg. 36 4.38 157.68
ISA 50*65*10 (300mm width) Kg. 10 2.47 24.7
10mm thick stiffner (50*77) Volume
Kg. 36 0.0000385 7850 10.88
Purlin Cleat Connection
Volume
Top Chord Cleat 200*90*10 Kg. 72 0.00018 7850 101.73
Purlin Cleat 200*85*10mm Kg. 144 0.00017 7850 192.16
2nos-16mm bolts Kg. 144 0.00000826236 7850 9.33
Nut Kg. 144
Top Ridge Connection
Volume
plate at x-x(175*175*10) Kg. 12 0.00030625 7850 28.84
Nut-bolt Kg. 24 0.00000826236 7850 1.55
plate at y-y(175*175*10) Kg. 12 0.00030625 7850 28.84
Nut-bolt Kg. 24 0.00000826236 7850 1.55

Prepared By: Checked By: Verified By:


MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks

10mm thick stiffners(57*59) Kg. 24 0.00003363 7850 6.33


Nut Kg. 24 0.00000826236 7850 1.55
Bolts Kg. 60
Truss Cleat for wind Ties
Volume
Wind Tie Cleat(100*100*6) Kg. 12 0.00006 7850 5.65
MS Flat 165*80*6 Kg. 6 0.0000792 7850 3.73
MS Flat 380*80*6mm Kg. 16 0.0001824 7850 22.9
20mm dia Nut Kg. 32 0.00001259136 7850 3.16
16mm dia Nut Kg. 40 0.00000697536 7850 2.19
8 mm J Hook Kg. #REF!

Bracing NB40(M) Kg. 32 1.98 3.56 225.56


plate Kg. 32 0.16 0.08 47.1 19.29
MS flat plate Kg. 16 0.38 0.08 47.1 22.9
MS flat plate Kg. 32 0.165 0.08 47.1 19.89

Lib purlin truss


NB65 purlin Kg. 16 4.47 71.52 6.44 460.58
NB65 purlin Kg. 4 3.5 14 6.44 90.16
beyond 1 and 6 NB65 Kg. 24 1.11 26.64 6.44 171.56
UpperPurlin NB32 Kg. 32 4.47 143.04 3.1 443.42
Kg. 8 3.5 28 3.1 86.8
Lower Purlin NB32 Kg. 32 3.536 113.152 3.1 350.77
Kg. 8 2.566 20.528 3.1 63.63
vertical strut memberNB15 Kg. 288 0.3 86.4 1.21 104.54
Incline strut memberNB15 Kg. 320 0.521 166.72 1.21 201.73
vertical strut memberNB15 Kg. 56 0.3 16.8 1.21 20.32
Incline strut memberNB15 Kg. 64 0.521 33.344 1.21 40.34
Total Kg. 5387.37
15.2 MS PIPE
Unit Lot No L Unit wt. Quantity
Staircase Railing
First Floor to Second Floor
NB 40 MS Round Pipe Kg. 1 1 9.47 3.56 33.71
38.1*38.1*3.2mm MS Vertical pipe Kg. 1 12 0.92 3.29 36.32
18*18*2 mm MS Pipe Kg. 1 4 9.0128 1 36.05
125*125*5 mm Base Plate Kg. 1 13 7.8125E-05 7850 7.97
Vol.
Second floor projection slab
NB 40 MS Round Pipe Kg. 1 1 11.87 3.56 42.25
38.1*38.1*3.2mm MS Vertical pipe Kg. 1 10 0.92 3.29 30.26
18*18*2 mm MS Pipe Kg. 1 4 11.489 1 45.95
125*125*5 mm Base Plate Kg. 1 11 7.8125E-05 7850 6.74
Vol.

Total MS PIPE Kg. 239.25


15.3 ROLLING SHUTTER
SHOP 1 SQ.M 1 4.1 2.6 10.66
SHOP 2 SQ.M 1 3.13 2.6 8.13
SHOP 3 SQ.M 1 4.1 2.6 10.66
SHOP 4 SQ.M 1 4.1 2.6 10.66
SHOP 5 SQ.M 1 4.1 2.6 10.66
TOTAL 50.77

18.2 Guide Ramp Rm 1 7.85 7.85


Total 7.85
22 Floor Hardener
First Floor
Community Hall Sq.m. 1 13.3 8.35 111.05
Passage area Sq.m. 1 8.35 3.38 28.22

Second Floor
Top Projected Slab Sq.m. 1 21.93 1.8 39.47
Void Sq.m. -5 1 1 -5
Staircase
Tread Sq.m. 18 1.5 0.3 8.1
Riser Sq.m. 20 1.5 0.15 4.5
Landing Sq.m. 1 1.5 3.2 4.8

TOTAL Sq.m. 191.14


23 Cement Board
Gap filling Sq.m. 2 21.93 0.6 26
Gable Wall Sq.m. 2 8.425 1.66 13.98
TOTAL Sq.m. 39.98
24 FLOOR TILE (600*600)
First Floor
Dinning Room Sq.m. 1 5.8 4.3 24.94
Skirting Sq.m. 1 19.2 0.125 2.4
Second Floor
Library Hall Sq.m. 1 13.3 8.35 111.05
Skirting Sq.m. 1 44.1 0.125 5.51
E- Library Hall Sq.m. 1 5.8 4.36 25.28
Skirting Sq.m. 1 19.12 0.125 2.39
Passage Sq.m. 1 4.15 3.38 14.02
Skirting Sq.m. 1 12.66 0.125 1.58
Sq.m.
Prepared By: Checked By: Verified By:
MB LIBRARY BLOCK
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LIBRARY BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks

TOTAL TILE (600*600) Sq.m. 187.17


25 ENAMEL PAINT
Railing Sq.m. 1 42.68 0.95 40.54

Sq.m. 40.54

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST LIBRARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

GENERAL WORK, SITE CLEARANCE:Clearing and


grubbing of site for construction including uprooting of
1.1 vegetation, grass, brush wood, trees and sapplings of girth Sq.M 351.95 100.00 35,195.00
upto 300 mm & removal upto a distance of 50 m as per
drawings, specifications and instructions

EARTHWORK IN EXCAVATION: Earthwork in


2.1 excavation in trenches, pits and foundations by machine or Cu.M 321.88 200.00 64,376.00
appropriate technology in soft soil including existing debris
and brick bats of old structure, if any, upto specified depth
EARTWORK IN FILLING: Providing and placing of
random filling of excavated earth from cutting of slope and
stacked at site in 150mm thick layer in trenches, plinth or
under floor, sides of foundation and below beam at footing
2.2 Cu.M 190.03 200.00 38,006.00
covered area etc. including watering, mechanical ramming
and compaction of each layer, consolidation and dressing,
all complete as per drawings, specifications and instructions.

SAND FILLING: Sand filling in plinth under floors,


including watering, ramming, consolidating and dressing, all
2.3 complete as per drawings, specifications and instructions. Cu.M 0 2,500.00 -

STONE WORK : Dry stone soling work in line and level,


including packing joints with sand dust, all complete as per
3.1 drawings, specifications and instructions Cu.M 9.01 4,000.00 36,040.00

STONE MASONRY WALL: Stone rubble masonry work in


1:4 cement and sand mortar with hard, tough, sound and
durable stone in wall, made to required line, level, shape,
3.2 size and plumb including setting out, drain outlet, curing of Cu.M 0 7,500.00 -
the works and scaffolding etc. complete as per drawings,
specifications and instructions

BRICK WORK,FLAT BRICK SOLING: Flat brick soling


of local chimney bricks laid in line and level, including
4.1 packing joints with sand, complete as per drawings, Sq.M 483.39 800.00 386,712.00
specifications and instructions
FULL BRICK WORK: Brickwork in substructure and super
4.2 structure cement and sand mortar of mix 1:6 with first class Cu.M 37.08 15,000.00 556,200.00
chimney-made bricks, in any size and shape of wall, made
to required line, level, shape and plumb including setting
AAC(Autoclaved Aerated Concrete) BLOCK WORK:
5.1 Providing and laying of Autoclaved Aerated Concrete Block Sq.M 308.7 1,800.00 555,660.00
(600*200*200 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2)AAC(Autoclaved Aerated Concrete) BLOCK WORK:
Providing and laying of Autoclaved Aerated Concrete Block
(600*200*100 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2 required line, level, shape and plumb including setting out, Sq.M 35.36 2,000.00 70,720.00
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

5.3)AAC(Autoclaved Aerated Concrete) BLOCK WORK:


Providing and laying of Autoclaved Aerated Concrete Block
(600*200*150 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.3 required line, level, shape and plumb including setting out, Sq.M 9.96 1,100.00 10,956.00
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

CONCRETE WORK,PCC OF GRADE M10: Plain cement


concrete (PCC) of grade M10 (1:3:6 with 1 cement, 3 coarse
sand and 6 aggregate of 19 mm and down grade) in
6.1 foundation base including mixing, laying, compacting, Cu.M 36.18 10,000.00 361,800.00
finishing, curing, laid to exact line, level and dimensions,
inclusive ofside

PCC FOR RCC OF GRADE M25: Structural concrete (PCC


for RCC) of Grade M25 (1:1:2)works with approved
quality of cement, sand and well graded aggregate in any
form, size, shape and level including batching and mixing
6.2 with machine, laying including compaction with vibrating Cu.M 59.35 20,000.00 1,187,000.00
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

PCC FOR RCC OF GRADE M20: Structural concrete (PCC


for RCC) of Grade M20 (1:1.5:3)works with approved
quality of cement, sand and well graded aggregate in any
6.3 form, size, shape and level including batching and mixing Cu.M 148.02 17,000.00 2,516,340.00
with machine, laying including compaction with vibrating
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

FORMWORK: Placing plyboard form work with steel


props, shuttering, centering in horizontal/Vertical surfaces
like slab, beams, column, wall, stair etc. for all RCC works
7.1 of any shape, size and at any level and removal after Sq.M 1429.09 850.00 1,214,726.50
completion

REINFORCEMENT WORK: Providing and placing steel


reinforcement bar tested grade Fe-500 equivalent NS, for
8.1 RCC work including bending, binding with anneal wire and kg 27875.29 110.00 3,066,281.90
placing in position, all complete as per drawings,
specifications and instruction

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST LIBRARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

9.1)FLOORING WORK,PLASTIC
9.1 LAYING: Supplying and laying 500 gauge plastic sheet in Sq.M 0 50.00 -
floor as per specificatio and instruction
9.2)SCREEDING: Providing and placing 38 mm thick Plain
cement concrete of grade M15 (1:2:4 with 1 cement, 2
coarse sand and 4 aggregate chips) in the floor base mixing,
laying, compacting, finishing, curing, laid to exact line level
9.2 , surface chipping and dimensions (floor concrete is laid in Sq.M 530.86 500.00 265,430.00
alternate panels of 1 m x 1 m) inclusive of shuttering
complete as per drawings, specifications and instructions

9.3)CEMENT PUNNING: Providing


and laying 3 mm cement punning in floor , laying in
9.3 Sq.M 298.59 200.00 59,718.00
required pattern, line

9.4)CEMENT SKIRTING: Providing


and placing cement skirting 125mm height of grade M15
(1:2:4 with cement, 2 coarse sand and 4 aggregate
) in wall ,mixing, laying, compactig, finishing, curing, laid
9.4 to exact line level and dimension all complete as per R.M 191.38 100.00 19,138.00
drawing, specification and instructions

9.5)TILE LAYING ON FLOOR:


Providing and laying approved brand quality, pattern and
color, ceramic mat finish tile (Low range) on floor over
9.5 cement mortar of mix 1:3 backing and filling joints (epoxy Sq.M 19.81 2,800.00 55,468.00
grout) complete as per drawings, specifications and
instructions.(Base rate: NRs 100)

9.6)TILE LAYING ON TOILET:


Providing and laying approved brand quality, pattern and
color, ceramic glazed tile in wall and ceramic mat finish tile
9.6 (Low range) on floor of toilet over cement mortar of mix 1:3 Sq.M 50.32 3,000.00 150,960.00
backing and filling joints (epoxy grout) complete as per
drawings, specifications and instructions.(Base rate: NRs
100)

10.1)FINISHING WORK,
EXTERNAL PLASTER: Providing and applying '10.5 mm
thick cement plastering with 1cement : 4 sand mortar in
outer surface any level size and shape of wall, column,
10.1 ceiling, band, blocks, etc inclusive of waterproofing Sq.M 501.56 400.00 200,624.00
compound, dusting, throating, etc as required including
racking, hacking, watering, cleaning of base, plastering to
plumb, line, level, smooth etc. and curing complete as per
drawings, specifications and instructions.
10.2)INTERNAL PLASTER:
Providing and applying'10.5 mm thick cement plastering
with 1cement : 4 sand mortar in inner surface except ceiling
any level size and shape of wall, column, band, blocks, etc
inclusive of dusting, throating, etc as required including
10.2 racking, watering, hacking, cleaning of base, plastering to Sq.M 779.72 450.00 350,874.00
plumb, line, level, smooth etc. and curing, all complete as
per drawings, specifications and instructions.

10.3)CEILING PLASTER: Providing


and applying 12.5 mm thick cement plastering with 1cement
10.3 : 4 sand mortar in Ceiling any level size and shape of Sq.M 528.44 500.00 264,220.00
ceiling inclusive of dusting,
10.4)PLASTER ON RCC LINTEL
WITH CORNICE: 'Providing and applying 12.5 mm thick
cement plastering with 1cement : 4 sand mortar in RCC
Lintel with cornice inclusive of dusting, throating, etc as
required including racking, watering, cleaning of base,
10.4 plastering to plumb, line, level, smooth etc. and curing, all R.M 0 3,000.00 -
complete as per drawings, specifications and instructions.

10.5)EMULSION PAINT: Providing


and applyibg two coat of emulsion paint in mat finishing
10.5 over two coat of primer, finished including surface Sq.M 1257.84 200.00 251,568.00
preparation all complete as per drawings, specifications and
instruction
10.6)WEATHER COAT: Providing and applying two coat
of weather coat (Apex or equivalent) over required coat of
10.6 primer, finished including surface preparation all complete Sq.M 541.54 250.00 135,385.00
as per drawings, specifications and instruction

11.1)DOOR,WINDOWS WORK/UPVC SLIDING


WINDOWS: Providing and fixing standard UPVC sliding
window without net (frame 50x80mm, sash 58x36mm white
11.1 colour with 5mm glass) along with patented standard Sq.M 65.4 8,000.00 523,200.00
hardwares like roller, gaskets, brush seal, moon locks etc all
complete as per drawings and specifications.

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST LIBRARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

11.2)UPVC TOP HUNG


WINDOWS: Providing and fixing standard UPVC top hung
window (frame 60x60 mm, sash 60x104 mm, white colour
11.2 with 5 mm glass) along with patented standard hardwares Sq.M 9.32 8,000.00 74,560.00
like roller, gaskets, brush seal, moon locks etc all complete
as per drawings and specifications.

11.3)UPVC DOUBLE DOOR:


Providing and fixing standard UPVC double door (frame
60x60mm, sash 60x104mm white colour with 5mm glass)
11.3 along with patented standard hardwares like roller, gaskets, Sq.M 21.84 10,000.00 218,400.00
brush seal, moon locks etc all complete as per drawings and
specifications.

11.4)UPVC SINGLE DOOR:


Providing and fixing standard UPVC single door with full
panel (frame60x60mm, sash 60x104mm white colour with
11.4 5mm glass) along with patented standard hardwares like Sq.M 13.8 7,000.00 96,600.00
roller, gaskets, brush seal, moon locks etc all complete as
per drawings and specifications.

12.1)ROOFING WORK,CGI
ROOFING SHEET: Providing and fixing in position 24
gauge medium (0 .5 mm thick) corrugated CGI sheet over
12.1 roof truss with minimum 80 mm side laps and 200 mm end Sq.M 272.28 1,319.17 359,183.60
laps, inclusive of nuts and bolts, 8 mm 'J' hooks, washers,
GI cup washers, all complete as per drawings, specifications
and instruction

12.2)CGI ROOFING SHEET ON


RIDGE: Providing and fixing in position 24 gauge medium
(0 .5 mm thick) CGI sheet over roof truss in ridge with
12.2 minimum 80 mm side laps and 200 mm end laps, inclusive R.m 23.78 1,009.52 24,006.38
of nuts and bolts, washers, GI cup washers, all complete as
per drawings, specifications and instruction

12.3)GI GUTTER: providing and fixing in position color


plain GI sheet for gutter 150mmX450mm, inclusive of nuts
12.3 and bolts, washers, all complete as per drawings, R.m 47.56 1,000.00 47,560.00
specifications and instruction.
13.1)FALSE CEILING WORK,PVC
BOARD: Providing and fixing suspended PVC board false
ceiling, with necessary provisions for light fittings, light
13.1 boxes, where required finally finished with two coat acrylic Sq.M 162.24 1,500.00 243,360.00
emulsion paint, all complete as per drawings, specifications
and instructions.

14.1)MISCELLANEOUS WORK,
WATER PROOFING: Providing and placing 20 mm thick
cement sand mortar (1:2) mixing with wate proof
14.1 compound in the floor base mixing, laying, compacting, Sq.M 85.1 400.00 34,040.00
finishing, curing, laid to exact line level and dimensions
complete as per drawings, specifications and instructions

14.2)INSULATION WORK:
Providing and installing Insulation under CGI roofing sheet
14.2 with Insulation shield of 12mm thickness one sided and Sq.m 182.8 200.00 36,560.00
chicken wire mesh all completeas per drawing and
specifications.
15.1)METAL WORKS,BLACK
15.1 TUBULAR PIPE: Supplying, fabricating and fixing black Kg 5387.37 150.00 808,105.50
pipe (Square or circular) work /Truss with
15.2)MS PIPE: Supplying, fabricating and fixing metal
15.2 work of different angles MS Pipe with one coat primer as Kg 239.25 150.00 35,887.50
shown in drawing all complete
15.3)ROLLING SHUTTER:
Providing and fixing rolling shutterof 16-19 Gauge cold
rolled MS lathe interlocked throughout their entire length
and joined together at the end by end locks and mounted on
specially designed pipe shaft with brackets, side guides and
15.3 arrangements for inside and outside locking,with push and Sq.m 50.77 4,000.00 203,080.00
pull operation, complete supplying, fixing and painting with
two coats of approved plastic emulsion paint.

15.4)HOT ROLLED STEEL


SECTION: Supplying, fabricating and fixing metal work of
15.4 different Hot Rolled Steel sections with one coat primer as Kg 0 150.00 -
per drawings and specifications all complete

15.5)METAL WORK,METAL
GATE: Supplying, fabricating and fixing in position, metal
gates of standard sections consisting of angles, pipes,
15.5 flats,etc. including one coat primer and one coat enamel Sq.M 0 7,000.00 -
paint as per drawings, specifications and instructions all
complete

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST LIBRARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

15.6)FENCING WORK: Providing and fixing of ISA


50x50x5 mm along with 25x25x5 flat and M8x40 bolts at
12.3 300mm spacing to fix 10 S.W.G.G.I chain link with hole R.M 0 2,200.00 -
size 60x60 mm upto 3m height and 3 lines of barbed wire at
top.
16.1)EXPANSION JOINT WORKS/PLINTH LEVEL:
Suuply
and fixing of expansion joint at level of 100% non porous
flexible element allowing movement in all directions,
16.1 supported by aluminium framing and covering the top by R.M 0 4,500.00 -
aluminium sheet and flused to required floor level all
complete as per drawing, specification and instruction.

16.2)EXPANSION JOINT
WORKS/SLAB: Supply and fixing of expansion joint at
floor level of aluminium base supported by alumunium
16.2 framing,fixed on one side by threaded screw and flushed to R.M 0 4,500.00 -
required floor level and dimension all complete as per
drawing,specification and instruction

16.3)EXPANSION JOINT WORKS/ENDS OF WALL:


16.3 Supply R.M 0 4,500.00 -
17.1)CHAIN LINK VENTILATION
WORK: Supplying, fabricating and fixing in position of 10
S.W.G.I. woven wire ventilation with hollow square pipe
framing of size 18x18x1.0 mm on all sides with proper
17.1 welding on site, including one coat primer and one coat Sq.M 0 4,000.00 -
enamel paint on frames as per drawings, specifications and
instructions all complete

18.1)LAND DEVELOPMENT WORKS, INTERLOCKING


BLOCKS: Supplying and laying of 60 mm thick heavy duty
interlocking paving blocks of approved colour and quality
on the 50 mm thick stone dust with surface grading,
18.1 levelling and soil compaction base in driveways and parking Sq.M 0 2,000.00 -
areas, complete as per specifications and drawings.

18.2)RAILING WORKS: Supply,


fabrication and fitting of Railing works with MS square pipe
framing and 10 S.W.G.I. wire mesh of height 1.05m
18.2 including excavation, brickwork, plaster and two coats R.M 0 3,000.00 -
enamel paint all complete as per drawings and specifications

18.3)GUIDE RAMP: Supply,


fabrication and fitting of Guide Ramp-Utility Guardrail for
the disabled with MS tubular pipes at regular intervals of
18.3 height 1.05m including two coats enamel paint all complete R.M 7.85 6,500.00 51,025.00
as per drawings and specifications

18.4)APRON DRAIN: Construction of Apron drain along


the perimeter of buildings and retaining structures including
18.4 excavation, Brick soling, PCC and half brick thick apron R.M 28 20,000.00 560,000.00
walls with plaster all complete as per drawings and
specifications
18.5)TACTILE PAVING: Providing
and laying approved brand quality, pattern and colour of
Tactile paving tile on floor over constructed cement mortar
18.5 of mix 1:3 backing and filling joints (epoxy grout) at R.M 0 3,500.00 -
straight path and turning points of size 300x300x40mm, all
complete as per drawings, specifications and instructions.

DEMOLITION WOKS: Demolition of existing building


19.1 and toilet blocks PS 0 1,000,000.00 -

RELOCATION WOKS: Relocation of temple from existing


site and to be constructed at a new location outside of the
20.1 school site as per drawing,specification and instructions. PS 0 300,000.00 -

INSURANCE PREMIUM
21.1 PS 0 224,281.00 -

Floor Hardener:providing,sprinkling,laying &applying


Manually two layer in floor,applied each layer with 1.5 to
2.5kg /m2 in required pattern,blended in,smoothed,over by
22.1 power trowelling,in line and level including curing all Sq.M 191.14 400.00 76,456.00
complete as per drawing,specification and instruction.
(Mapetop,N,AR6 or equivalent)

Cement Board:providing and fixing in position 10mm


water proofed cement board in exterior (one side)surface
inclusive minimum75mm GI metal framewith grooving and
23.1 fixing of fastner ,washer,nuts,and bolts,all complete as per Sq.M 39.98 2,700.00 107,946.00
drawings,specifications and instructions.

FLOOR TILE (600*600)


24 Sq.M 187.17 2,500.00 467,925.00

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST LIBRARY


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

ENAMEL PAINT
25 Sq.M 40.54 286.00 11,594.44

PILE WORK : Construction of pile work including


26 excavation, reinforcement and concreting work. Rm 0 17,000.00 -

DISMANTLING WORK
27 -

CONCRETE DISMANTLING
27.1 Cu.M 8,500.00 -

BRICKWALL DISMANTLING
27.2 Cu.M 2,000.00 -

TOTAL CIVIL WORKS -


TOTAL AMOUNT
15,832,887.82

Total Item Price 15,832,887.82

Discount @2% 316,657.76

Sub Total 15,516,230.06

VAT @13% 2,017,109.91

Grand Total 17,533,339.97

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


GENERAL WORK, SITE CLEARANCE
1.1 Sq.M 1 40.275 13.3 535.65
2.1 EARTHWORK IN EXCAVATION
FOOTINGS
F1 Cu.m. 9 1.6 1.6 2.2 50.68
F2 Cu.m. 1 2.2 2.2 2.2 10.64
F3 Cu.m. 4 2.4 2.4 2.2 50.68
F4 Cu.m. 6 2.7 2.7 2.2 96.22
F5 Cu.m. 2 3 3 2.2 39.6
F6 Cu.m. 1 5 2.6 2.2 28.6
Pile cap Cu.m. 6 1.5 1.5 2.2 29.7
Cu.m. 5 1.5 1.5 2.2 12.37 Reconstruction
Cu.m. 1 2.1 2.1 2.2 4.85 Reconstruction
Ground cutting for pile foundation Cu.m. 1 60.75 5 2 607.5

Lower tie Beam


Along grid A/1-11 Cu.m. 1 20.25 0.375 1.4 10.63
Along grid B/1-11 Cu.m. 1 12.25 0.375 1.4 6.43
Along grid C/1-11 Cu.m. 1 16.95 0.375 1.4 8.89
Along grid C/6-11 Cu.m. 1 12.5 1.375 1.4 12.03 Reconstruction

Along grid 5,6/A-C Cu.m. 2 2.9 0.375 1.4 3.04


Along grid 7/A-C Cu.m. 1 4 0.375 1.4 2.1
Along grid 2,3,4/A-C Cu.m. 3 4.75 0.375 1.4 7.48
Along grid 8,9,10/A-C Cu.m. 3 4.3 0.375 1.4 6.77
Along grid 11/A-C Cu.m. 1 5.2 0.375 1.4 2.73
Along grid 1/A-C Cu.m. 1 6 0.375 1.4 3.15

Front Steps Cu.m. 1 24.05 0.9 0.13 2.81


Water Trough Cu.m. 1 6.3 0.45 0.13 0.36
Apron Drain Cu.m. 1 40.5 0.76 0.625 19.23

TOTAL EARTHWORK IN Cu.m.


EXCAVATION 1016.49
2.2 EARTHWORK IN FILLING
Total earthwork in excavation 1016.49
Inside Room Cu.m. 8 6.25 3.65 0.45 82.12
Cu.m. 1 6.25 4.15 0.45 11.67
Passage Cu.m. 8 2.25 3.65 0.45 29.56
Cu.m. 1 2.25 4.15 0.45 4.2
Deduction
Sand Filling Cu.m. 0
Flat brick soling Cu.m. -665.98
Brickwork upto plinth beam Cu.m. -73.2
PCC M10 Cu.m. -52.49
RCC M25 (Colums upto plinth level) Cu.m. -7
RCC M20 (Footings , Lower tie beam) Cu.m.
-50.73
Total Back Filling Cu.m. 294.64
2.3 SAND FILLING
CRUSHED STONE DUST
F1 Cu.m. 9 1.6 1.6 0.075 1.72
F2 Cu.m. 1 2.2 2.2 0.075 0.36
F3 Cu.m. 4 2.4 2.4 0.075 1.72
F4 Cu.m. 6 2.7 2.7 0.075 3.28
F5 Cu.m. 2 3 3 0.075 1.35
F6 Cu.m. 1 5 2.6 0.075 0.97
Pile cap P1 Cu.m. 11 1.5 1.5 0.075 1.85
Pile Cap P2 Cu.m. 1 2.1 2.1 0.075 0.33

Inside Room Cu.m. 8 6.25 3.65 0.1 18.25


Cu.m. 1 6.25 4.15 0.1 2.59
Passage Cu.m. 8 2.25 3.65 0.1 6.57
Cu.m. 1 2.25 4.15 0.1 0.93
Total Sand Filling Cu.m. 0
4 BRICK WORK
4.1 FLAT BRICK SOLING
FOOTINGS
F1 Sq.m. 9 1.6 1.6 23.04
F2 Sq.m. 1 2.2 2.2 4.84
F3 Sq.m. 4 2.4 2.4 23.04
F4 Sq.m. 6 2.7 2.7 43.74

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


F5 Sq.m. 2 3 3 18
F6 Sq.m. 1 5 2.6 13
Pile cap P1 Sq.m. 6 1.5 1.5 13.5
Sq.m. 5 1.5 1.5 5.62 Reconstruction
Pile Cap P2 Sq.m. 1 2.1 2.1 2.2 Reconstruction

Lower tie Beam


Along grid A/1-11 Sq.m. 1 20.25 0.375 7.59
Along grid B/1-11 Sq.m. 1 11.45 0.375 4.29
Along grid C/1-11 Sq.m. 1 14.55 0.375 5.45
Along grid C/6-11 Sq.m. 1 12.5 0.375 2.34 Reconstruction

Along grid 5,6/A-C Sq.m. 2 2.9 0.375 2.17


Along grid 7/A-C Sq.m. 1 4 0.375 1.5
Along grid 2,3,4/A-C Sq.m. 3 4.75 0.375 5.34
Along grid 8,9,10/A-C Sq.m. 3 4.3 0.375 4.83
Along grid 11/A-C Sq.m. 1 5.2 0.375 1.95
Along grid 1/A-C Sq.m. 1 6 0.375 2.25
Along grid 6-11/B-C Sq.m. 6 3 0.375 3.37 Reconstruction

Front Steps Sq.m. 1 23.725 0.9 21.35


Water Trough Sq.m. 1 6.3 0.45 2.83
Inside Room Sq.m. 8 6.25 3.65 182.5
Sq.m. 1 6.25 4.15 25.93
Passage Sq.m. 8 2.25 3.65 65.7
Sq.m. 1 2.25 4.15 9.33
Backside apron area Sq.m. 1 45 3.1 139.5
Apron Drain Sq.m. 1 40.5 0.76 30.78

TOTAL FLAT BRICK SOLING Sq.m. 665.98


4.2 FULL BRICK WORK
From lower tie beam to upper tie beam
Along grid A,B &C Cu.m. 3 32 0.23 1.4 30.91
Along grid C/6-11 Cu.m. 1 16.4 1.23 1.4 14.12 Reconstruction
Along grid 1-11/A-C Cu.m. 11 8.25 0.23 1.35 28.17
Along grid 6-11/A-C Cu.m. 6 3 0.23 1.35 2.79 Reconstruction
In truss beam Cu.m. 2 36.4 0.23 0.3 5.02

Water Trough wall Cu.m. 4 0.6 0.45 0.23 0.24


Cu.m. 1 6.3 0.23 0.15 0.21

Front Steps Cu.m. 1 24.05 0.6 0.15 2.16


Cu.m. 1 24.05 0.3 0.15 1.08
Apron drain Cu.m. 2 40.5 0.11 0.5 4.45

TOTAL FULL BRICK WORK Cu.m. 89.15


5 AAC BLOCK
5.1 AAC BLOCK (600*200*200)
GROUND FLOOR
ALONG GRID1, 3,5,6,7,9 &11/(A-B) 2.7
Sq.m 7 6.1 115.29
ALONG GRID A&B/1-11 Sq.m 2 32 2.825 180.8
DEDUCTION
D Sq.m -8 1.2 2.9 -27.84
W Sq.m -8 3.5 1.985 -55.58
W1 Sq.m -8 1.5 1.985 -23.82
LANDING BEAM Sq.m -1 4 0.4 -1.6
ALONG GRID B/6-7 Sq.m -1 4 2.825 -11.3
FIRST FLOOR
ALONG GRID1, 3,5,6,7,9 &11/(A-B) 2.7
Sq.m 7 6.1 115.29
ALONG GRID A&B/1-11 Sq.m 2 32 2.825 180.8
ALONG GRID C/1-11 Sq.m 1 32 0.4 12.8
ALONG GRID 1&11/B-C Sq.m 2 2.15 0.4 1.72
DEDUCTION
D Sq.m -8 1.2 2.9 -27.84
W Sq.m -8 3.5 1.985 -55.58
W1 Sq.m -8 1.5 1.985 -23.82
V1 Sq.m -1 2 1.25 -2.5
LANDING BEAM Sq.m -1 4 0.4 -1.6
ALONG GRID B/6-7 Sq.m -1 4 2.825 -11.3
SECOND FLOOR

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


ALONG GRID1, 3,5,6,7,8 &11/(A-B) 2.7
Sq.m 7 6.1 115.29
ALONG GRID A&B/1-11 Sq.m 2 32 2.825 180.8
ALONG GRID C/1-11 Sq.m 1 32 0.4 12.8
ALONG GRID 1&11/B-C Sq.m 2 2.15 0.4 1.72
DEDUCTION
D Sq.m -6 1.2 2.9 -20.88
D1 Sq.m -1 1 2.9 -2.9
W Sq.m -9 3.5 1.985 -62.53
W1 Sq.m -7 1.5 1.985 -20.85
V1 Sq.m -1 2 1.25 -2.5
LANDING BEAM Sq.m -1 4 0.4 -1.6
ALONG GRID B/6-7 Sq.m -1 4 2.825 -11.3

TOTAL Sq.m. 551.97


6 CONCRETE WORK
6.1 PCC of grade M10
FOOTINGS
F1 cum 9 1.6 1.6 0.075 1.72
F2 cum 1 2.2 2.2 0.075 0.36
F3 cum 4 2.4 2.4 0.075 1.72
F4 cum 6 2.7 2.7 0.075 3.28
F5 cum 2 3 3 0.075 1.35
F6 cum 1 5 2.6 0.075 0.97
Pile cap P1 cum 6 1.5 1.5 0.075 1.01
cum 5 1.5 1.5 0.075 0.42 Reconstruction
Pile Cap P2 cum 1 2.1 2.1 0.075 0.16 Reconstruction

Lower tie Beam


Along grid A/1-11 cum 1 20.25 0.375 0.075 0.56
Along grid B/1-11 cum 1 12.25 0.375 0.075 0.34
Along grid C/1-11 cum 1 16.95 0.375 0.075 0.47
Along grid C/6-11 cum 1 12.5 1.375 0.075 0.64 Reconstruction

Along grid 5,6/A-C cum 2 2.9 0.375 0.075 0.16


Along grid 7/A-C cum 1 4 0.375 0.075 0.11
Along grid 2,3,4/A-C cum 3 4.75 0.375 0.075 0.4
Along grid 8,9,10/A-C cum 3 4.3 0.375 0.075 0.36
Along grid 11/A-C cum 1 5.2 0.375 0.075 0.14
Along grid 1/A-C cum 1 6 0.375 0.075 0.16
Along grid 6-11/B-C cum 6 3 1.375 0.075 0.92 Reconstruction

Front Steps cum 1 24.05 0.9 0.075 1.62


Water Trough cum 1 6.3 0.45 0.075 0.21
Inside Room cum 8 6.25 3.65 0.075 13.68
cum 1 6.25 4.15 0.075 1.94
Passage cum 8 2.25 3.65 0.075 4.92
cum 1 2.25 4.15 0.075 0.7
Backside apron area cum 1 45 3.1 0.075 10.46
Left side apron area cum 1 9.45 2 0.075 1.41
Apron Drain cum 1 40.5 0.76 0.075 2.3

TOTAL Cu.m. 52.49


6.2 PCC for RCC of Grade M25
Column upto plinth lvl
C3 Cu.m. 8 0.3 0.3 2.15 1.54
Cu.m. 3 0.3 0.3 1.85 0.49
C1 Cu.m. 1 0.4 0.4 2.1 0.33
Cu.m. 6 0.4 0.4 2.05 1.96
Cu.m. 3 0.4 0.4 1.85 0.88
Cu.m. 1 0.4 0.4 2 0.32
C2 Cu.m. 5 0.4 0.4 1.85 1.48 On pile cap
Cu.m. 6 0.4 0.4 1.85 0.88 Reconstruction
Cu.m. 1 0.4 0.4 2.15 0.34
Cu.m. 2 0.4 0.4 2 0.64
Cu.m. 4 0.4 0.4 2.05 1.31

Column above plinth lvl


C1 Cu.m. 11 0.4 0.4 9.9 17.42
C2 Cu.m. 11 0.4 0.4 9.9 17.42
C3 Cu.m. 11 0.3 0.3 9.9 9.8

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks

Pile Cap
P1 Cu.m. 5 1.5 1.5 0.6 6.75
Cu.m. 6 1.5 1.5 0.6 4.05 Reconstruction
P2 Cu.m. 1 2.1 2.1 0.6 1.32 Reconstruction

TOTAL Cu.m. 66.93


6.3 PCC for RCC of Grade M20
FOOTINGS
F1 Cu.m. 8 1.6 1.6 0.3 6.14
F2 Cu.m. 1 2.2 2.2 0.35 1.69
F4 Cu.m. 6 2.7 2.7 0.4 17.49
F5 Cu.m. 1 3 3 0.45 4.05
F6 Cu.m. 1 5 2.6 0.6 7.8
TIE BEAM
Lower tie beam along grid A Cu.m. 1 32.9 0.23 0.3 2.27
Lower tie beam along grid B &C Cu.m. 2 32 0.23 0.3 4.41
Lower tie beam along grid C/6-11 Cu.m. 1 18 0.23 0.3 0.62 Reconstruction
Lower Tie beam along grid 1-11/A-C Cu.m. 11 8.25 0.23 0.3 6.26
Lower Tie beam along grid 6-11/A-C Cu.m. 6 3 0.23 0.3 0.62 Reconstruction

Plinthbeam along grid A Cu.m. 1 32.9 0.25 0.4 3.29


Plinth beam along grid B &C Cu.m. 2 32 0.25 0.4 6.4
Plinth beam along grid C/6-11 Cu.m. 1 18 0.25 0.4 0.9 Reconstruction
Plinth beam along grid 1-11/A-C Cu.m. 11 8.25 0.25 0.45 10.2
Plinthbeam along grid 6-11/A-C Cu.m. 6 3 0.25 0.45 1.01 Reconstruction

Beam
First Floor Beam
Beam along grid A, B Cu.m. 2 32 0.25 0.275 4.4
Beam along grid C Cu.m. 1 32.9 0.25 0.275 2.26
Beam along grid1-11/A-C Cu.m. 11 8.25 0.25 0.325 7.37
Secondary beam Cu.m.
Along X-X Cu.m. 2 14.6 0.23 0.175 1.17
Along grid 6-7 Cu.m. 1 4.15 0.23 0.175 0.16
Second Floor Beam
Beam along grid A, B Cu.m. 2 32 0.25 0.275 4.4
Beam along grid C Cu.m. 1 32.9 0.25 0.275 2.26
Beam along grid1-11/A-C Cu.m. 11 8.25 0.25 0.325 7.37
Secondary beam Cu.m.
Along X-X Cu.m. 2 14.6 0.23 0.175 1.17
Along grid 6-7 Cu.m. 1 4.15 0.23 0.175 0.16
Truss Beam
Beam along grid A, B Cu.m. 2 32 0.25 0.4 6.4
Beam along grid C Cu.m. 1 32.9 0.25 0.4 3.29
Beam along grid1-11/A-C Cu.m. 11 8.25 0.25 0.45 10.2
SLAB
First FLoor Cu.m. 1 16 9.35 0.125 18.7
Cu.m. 1 20.4 9.35 0.125 23.84
Deduction
Staircase void Cu.m. -1 4.15 5.435 0.125 -2.82
Column Cu.m. -22 0.4 0.4 0.125 -0.44
Cu.m. -11 0.3 0.3 0.125 -0.13
Second FLoor Cu.m. 1 16 9.35 0.125 18.7
Cu.m. 1 20.4 9.35 0.125 23.84
Deduction
Staircase void Cu.m. -1 4.15 5.435 0.125 -2.82
Column Cu.m. -22 0.4 0.4 0.125 -0.44
Cu.m. -11 0.3 0.3 0.125 -0.13

STAIRCASE
GROUND FLOOR TO FIRST FLOOR
Bottom landing slab Cu.m. 1 1.34 2 0.175 0.46
First flight waist slab Cu.m. 1 3.69 2 0.175 1.29
Landing slab Cu.m. 1 4.15 1.61 0.175 1.16
1 2 0.381 0.175 0.13
Second flight waist slab Cu.m. 1 3.69 2 0.175 1.29
Top Landing Cu.m. 1 0.959 4.15 0.175 0.69
1 2 0.381 0.175 0.13
Landing Beam Cu.m. 1 4 0.25 0.4 0.4
Step Cu.m. 22 2 0.3 0.075 0.99
FIRST FLOOR TO SECOND FLOOR Cu.m.
Bottom landing slab Cu.m. 1 1.34 2 0.175 0.46

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


First flight waist slab Cu.m. 1 3.69 2 0.175 1.29
Landing slab Cu.m. 1 4.15 1.61 0.175 1.16
1 2 0.381 0.175 0.13
Second flight waist slab Cu.m. 1 3.69 2 0.175 1.29
Top Landing Cu.m. 1 0.959 4.15 0.175 0.69
Landing Beam Cu.m. 1 4 0.25 0.4 0.4
Step Cu.m. 22 2 0.3 0.075 0.99

BANDS
SILL BANDS
GROUND FLOOR
ALONG GRID1, 3,5,6,7,9 &11/(A-B) 0.075
Cu.m. 7 6.1 0.2 0.64
ALONG GRID A/1-11 Cu.m. 1 32 0.275 0.075 0.66
ALONG GRID B/1-11 Cu.m. 1 32 0.2 0.075 0.48
ALONG GRID 1&11/B-C Cu.m. 2 2.15 0.2 0.075 0.06
DEDUCTION
D Cu.m. -6 1.2 0.2 0.075 -0.11
D1 Cu.m. -1 0.2 0.075 0
ALONG GRID B/6-7 Cu.m. -1 4 0.2 0.075 -0.06
FIRST FLOOR
ALONG GRID1, 3,5,6,7,9 &11/(A-B) 0.075
Cu.m. 7 6.1 0.2 0.64
ALONG GRID A/1-11 Cu.m. 1 32 0.275 0.075 0.66
ALONG GRID B/1-11 Cu.m. 1 32 0.2 0.075 0.48
ALONG GRID 1&11/B-C Cu.m. 2 2.15 0.2 0.075 0.06
DEDUCTION
D Cu.m. -6 1.2 0.2 0.075 -0.11
D1 Cu.m. -1 0.2 0.075 0
ALONG GRID B/6-7 Cu.m. -1 4 0.2 0.075 -0.06
SECOND FLOOR
ALONG GRID1, 3,5,6,7,8 &11/(A-B) 0.075
Cu.m. 7 6.1 0.2 0.64
ALONG GRID A/1-11 Cu.m. 1 32 0.275 0.075 0.66
ALONG GRID B/1-11 Cu.m. 1 32 0.2 0.075 0.48
ALONG GRID 1&11/B-C Cu.m. 2 2.15 0.2 0.075 0.06
DEDUCTION
D Cu.m. -6 1.2 0.2 0.075 -0.11
D1 Cu.m. -1 1 0.2 0.075 -0.02
ALONG GRID B/6-7 Cu.m. -1 4 0.2 0.075 -0.06
LINTEL BANDS
GROUND FLOOR
ALONG GRID1, 3,5,6,7,9 &11/(A-B) 0.075
Cu.m. 7 6.1 0.2 0.64
ALONG GRID B/1-11 Cu.m. 1 32 0.2 0.075 0.48
DEDUCTION
D Cu.m. -8 1.2 0.2 0.075 -0.15
ALONG GRID B/6-7 Cu.m. -1 4 0.2 0.075 -0.06
W1 Cu.m. -8 1.5 0.2 0.075 -0.18
FIRST FLOOR
ALONG GRID1, 3,5,6,7,9 &11/(A-B) 0.075
Cu.m. 7 6.1 0.2 0.64
ALONG GRID B/1-11 Cu.m. 1 32 0.2 0.075 0.48
DEDUCTION
D Cu.m. -8 1.2 0.2 0.075 -0.15
ALONG GRID B/6-7 Cu.m. -1 4 0.2 0.075 -0.06
W1 Cu.m. -8 1.5 0.2 0.075 -0.18
SECOND FLOOR
ALONG GRID1, 3,5,6,7,8 &11/(A-B) 0.075
Cu.m. 7 6.1 0.2 0.64
ALONG GRID B/1-11 Cu.m. 1 32 0.2 0.075 0.48
DEDUCTION
D Cu.m. -6 1.2 0.2 0.075 -0.11
D1 Cu.m. -1 1 0.2 0.075 -0.02
ALONG GRID B/6-7 Cu.m. -1 4 0.2 0.075 -0.06
W1 Cu.m. -6 1.5 0.2 0.075 -0.14
W2 Cu.m. -1 1.2 0.2 0.075 -0.02
W Cu.m. -1 3.5 0.2 0.075 -0.06

Water Trough Slab Cu.m. 1 6.3 0.45 0.1 0.28

TOTAL Cu.m. 222.45

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


7.1 FORM WORK

Formwork for Footing


F1 Sq.m. 9 6.4 0.3 17.28
F2 Sq.m. 1 8.8 0.35 3.08
F3 Sq.m. 4 9.6 0.4 15.36
F4 Sq.m. 6 10.8 0.4 25.92
F5 Sq.m. 2 12 0.45 10.8
F6 Sq.m. 1 15.2 0.6 9.12
Pile cap P1 Sq.m. 5 6 0.6 18
Sq.m. 6 6 0.6 10.8 Reconstruction
Pile Cap P2 Sq.m. 1 8.4 0.6 5.04 Reconstruction

BEAM
Lower tie beam
Lower tie beam along grid A Sq.m. 1 32.9 0.6 19.74
Lower tie beam along grid B &C Sq.m. 2 32 0.6 38.4
Lower tie beam along grid C/6-11 Sq.m. 1 18 0.6 5.4 Reconstruction
Lower Tie beam along grid 1-11/A-C Sq.m. 11 8.25 0.6 54.45
Lower Tie beam along grid 6-11/A-C Sq.m. 6 3 0.6 5.4 Reconstruction

Plinth Beam
Plinthbeam along grid A Sq.m. 1 32.9 0.82 26.97
Plinth beam along grid B &C Sq.m. 2 32 0.82 52.48
Plinth beam along grid C/6-11 Sq.m. 1 18 0.82 7.38 Reconstruction
Plinth beam along grid 1-11/A-C Sq.m. 11 8.25 0.92 83.49
Plinthbeam along grid 6-11/A-C Sq.m. 6 3 0.92 8.28 Reconstruction

Ground Floor Beam


Along grid A&B/1-11 Sq.m. 2 32 0.55 35.2
Along grid C/1-11 Sq.m. 1 32.9 0.55 18.09
Along grid 1,2,3,4,5,6,7,8,9,10&11/A-C Sq.m. 11 8.25 0.65 58.98
Along grid X/1-11 Sq.m. 1 29.2 0.35 10.22
Along grid 6-7 Sq.m. 1 4.15 0.35 1.45

First Floor Beam


Along grid A&B/1-11 Sq.m. 2 32 0.55 35.2
Along grid C/1-11 Sq.m. 1 32.9 0.55 18.09
Along grid 1,2,3,4,5,6,7,8,9,10&11/A-C Sq.m. 11 8.25 0.65 58.98
Along grid X/1-11 Sq.m. 1 29.2 0.35 10.22
Along grid 6-7 Sq.m. 1 4.15 0.35 1.45

Second Floor Beam


Along grid A&B/1-11 Sq.m. 2 32 0.8 51.2
Along grid C/1-11 Sq.m. 1 32.9 0.8 26.32
Along grid 1,2,3,4,5,6,7,8,9,10&11/A-C Sq.m. 11 8.25 0.9 81.67

Column
Column upto Plinth level
Column at F1 Sq.m. 9 2.15 1.2 23.22
Column at F2 Sq.m. 1 2.1 1.6 3.36
Column at F3 Sq.m. 4 2.05 1.6 13.12
Column at F4 Sq.m. 6 2.05 1.6 19.68
Column at F5 Sq.m. 3 2 1.6 9.6
Column at F6 Sq.m. 2 1.85 1.6 5.92
Sq.m. 2 1.85 1.2 4.44
Column at p1 Sq.m. 4 1.85 1.6 11.84
Sq.m. 1 1.85 1.2 2.22
Sq.m. 6 1.85 1.2 6.66 Reconstruction
Column at p2 Sq.m. 1 1.85 1.6 1.48 Reconstruction
Deduction of beam face
Bottom tie beam Sq.m. -20 0.23 0.3 -1.38
Lower tie beam
Along grid A,B&C Sq.m. -60 0.23 0.3 -4.14
Along grid 1-11/A-C Sq.m. -44 0.23 0.3 -3.04
Plinth Beam
Along grid A,B&C Sq.m. -60 0.25 0.4 -6
Along grid 1-11/A-C Sq.m. -44 0.25 0.45 -4.95

Columns Above plinth level


400*400 column Sq.m. 22 9.525 1.6 335.28
Sq.m. 22 0.125 1.6 4.4 Truss lvl

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


300*300 column Sq.m. 11 9.525 1.2 125.73
Sq.m. 11 0.125 1.2 1.65 Truss Lvl
Deduction of beam faces
Along grid A,B&C Sq.m. -180 0.25 0.275 -12.38
Along grid 1-11/A-C Sq.m. -132 0.25 0.325 -10.73
Landing beam Sq.m. -4 0.25 0.4 -0.4

Slabs
First & Second floor slab Sq.m. 2 36.4 9.35 680.68
Sides Sq.m. 2 110.2 0.125 27.55
Deductions
Staircase void Sq.m. -2 4.15 5.435 -45.12
Columns area Sq.m. -44 0.4 0.4 -7.04
Sq.m. -22 0.3 0.3 -1.98

Staircase
Ground floor to first floor stair
First flight waist slab bottom Sq.m. 1 3.69 2 7.38
Sides of waist slab Sq.m. 2 3.69 0.325 2.39
Landing Sq.m. 1 4.15 0.959 3.97
Sq.m. 1 2 0.381 0.76
Sides of landing Sq.m. 1 2.83 0.175 0.49
Second flight waist slab bottom Sq.m. 1 3.655 2 7.31
Sides of waist slab Sq.m. 2 3.655 0.325 2.37
Top Landing Sq.m. 1 4.15 1.61 6.68
Sq.m. 1 2 0.381 0.76
Step risers Sq.m. 22 2 0.15 6.6
Landing Beam bottom Sq.m. 1 4 0.25 1
Landing Beam Sides Sq.m. 1 4 0.625 2.5
First floor to Second floor stair
First flight waist slab bottom Sq.m. 1 3.69 2 7.38
Sides of waist slab Sq.m. 2 3.69 0.325 2.39
Landing Sq.m. 1 4.15 0.959 3.97
Sq.m. 1 2 0.381 0.76
Sides of landing Sq.m. 1 2.83 0.175 0.49
Second flight waist slab bottom Sq.m. 1 3.655 2 7.31
Sides of waist slab Sq.m. 2 3.655 0.325 2.37
Top Landing Sq.m. 1 4.15 1.61 6.68
Sides of top landing Sq.m. 1 2.15 0.175 0.37
Step risers Sq.m. 22 2 0.15 6.6
Landing Beam bottom Sq.m. 1 4 0.25 1
Landing Beam Sides Sq.m. 1 4 0.625 2.5

Bands
SILL BANDS
GROUND FLOOR
ALONG GRID1, 3,5,6,7,9 &11/(A-B) 0.075
Sq.m. 7 6.1 6.4
ALONG GRID A/1-11 Sq.m. 1 32 0.075 4.8
ALONG GRID B/1-11 Sq.m. 1 32 0.075 4.8
ALONG GRID 1&11/B-C Sq.m. 2 2.15 0.075 0.64
DEDUCTION Sq.m. 0.075
D Sq.m. -8 1.2 0.075 -1.44
ALONG GRID B/6-7 Sq.m. -1 4 0.075 -0.6
FIRST FLOOR
ALONG GRID1, 3,5,6,7,9 &11/(A-B) 0.075
Sq.m. 7 6.1 6.4
ALONG GRID A/1-11 Sq.m. 1 32 0.075 4.8
ALONG GRID B/1-11 Sq.m. 1 32 0.075 4.8
ALONG GRID 1&11/B-C Sq.m. 2 2.15 0.075 0.64
DEDUCTION Sq.m. 0.075
D Sq.m. -8 1.2 0.075 -1.44
ALONG GRID B/6-7 Sq.m. -1 4 0.075 -0.6
SECOND FLOOR
ALONG GRID1, 3,5,6,7,8 &11/(A-B) 0.075
7 6.1 6.4
Sq.m.
ALONG GRID A/1-11 Sq.m. 1 32 0.075 4.8
ALONG GRID B/1-11 Sq.m. 1 32 0.075 4.8
ALONG GRID 1&11/B-C Sq.m. 2 2.15 0.075 0.64
DEDUCTION Sq.m. 0.075
D Sq.m. -6 1.2 0.075 -1.08
D1 Sq.m. -1 1 0.075 -0.15
ALONG GRID B/6-7 Sq.m. -1 4 0.075 -0.6

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


LINTEL BANDS
GROUND FLOOR
ALONG GRID1, 3,5,6,7,9 &11/(A-B) 0.075
7 6.1 6.4
Sq.m.
ALONG GRID B/1-11 Sq.m. 1 32 0.075 4.8
DEDUCTION Sq.m.
D Sq.m. -8 1.2 0.075 -1.44
ALONG GRID B/6-7 Sq.m. -1 4 0.075 -0.6
W1 Sq.m. -8 1.5 0.075 -1.8
FIRST FLOOR
ALONG GRID1, 3,5,6,7,9 &11/(A-B) 0.075
7 6.1 6.4
Sq.m.
ALONG GRID B/1-11 Sq.m. 1 32 0.075 4.8
DEDUCTION Sq.m.
D Sq.m. -8 1.2 0.075 -1.44
ALONG GRID B/6-7 Sq.m. -1 4 0.075 -0.6
W1 Sq.m. -8 1.5 0.075 -1.8
SECOND FLOOR
ALONG GRID1, 3,5,6,7,8 &11/(A-B) 0.075
7 6.1 6.4
Sq.m.
ALONG GRID B/1-11 Sq.m. 1 32 0.075 4.8
DEDUCTION
D Sq.m. -6 1.2 0.075 -1.08
D1 Sq.m. -1 1 0.075 -0.15
ALONG GRID B/6-7 Sq.m. -1 4 0.075 -0.6
W1 Sq.m. -6 1.5 0.075 -1.35
W2 Sq.m. -1 1.2 0.075 -0.18
W Sq.m. -1 3.5 0.075 -0.53

Water Trough Sq.m. 1 5.4 0.45 4.86


Sq.m. 1 6.3 0.075 0.94

Total Sq.m. 2160


8.1 REINFORCEMENT WORK
FOUNDATIONS Kg. 1 2558.84 2558.84
COLUMNS Kg. 1 18842.17 18842.17
BEAMS Kg. 1 17782.08 17782.08
SLABS Kg. 1 5892.52 5892.52
STAIRCASE Kg. 1 3495.16 3495.16
BANDS Kg. 1 897.27 897.27
PILE CAP Kg. 1 902.52 902.52

Total Kg 50370.56
9 FLOORING WORK
9.1 PLASTIC LAYING
Rooms Sq.m. 8 3.65 6.25 182.5
Sq.m. 1 4.15 6.25 25.93
Passage Sq.m. 8 3.65 2.25 65.7
Sq.m. 1 4.15 2.25 9.33
Total Sq.m. 0
9.2 SCREEDING
Ground Floor
Class Room 4A Sq.m. 1 6.425 7.625 48.99
Class Room 4B Sq.m. 1 6.425 7.7 49.47
Class Room 5A Sq.m. 1 6.425 7.625 48.99
Class Room 5B Sq.m. 1 6.425 7.625 48.99
Staircasearea Sq.m. 1 4.15 6.5 26.97
Passage Sq.m. 1 36.3 2.45 88.93
Front Steps Sq.m. 2 24.05 0.3 14.43
staircase
steps Sq.m. 22 2 0.3 13.2
Landing Sq.m. 1 4.15 2.075 8.61
Lobby Sq.m. 1 7.1 4.15 29.46

First Floor
Class Room 6A Sq.m. 1 6.425 7.625 48.99
Class Room 6B Sq.m. 1 6.425 7.7 49.47
Class Room 7A Sq.m. 1 6.425 7.625 48.99
Class Room 7B Sq.m. 1 6.425 7.625 48.99
Passage Sq.m. 1 36.3 2.45 88.93
staircase
steps Sq.m. 22 2 0.3 13.2

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Landing Sq.m. 1 4.15 2.075 8.61
Lobby Sq.m. 1 4.15 1.425 5.91
Second Floor
Class Room 8A Sq.m. 1 6.425 7.625 48.99
Class Room 8B Sq.m. 1 6.425 7.7 49.47
Multipurpose Hall Sq.m. 1 6.425 11.525 74.04
teachers room Sq.m. 1 6.425 3.725 23.93
Passage Sq.m. 1 36.3 2.45 88.93
Lobby Sq.m. 1 4.15 1.425 5.91

Water Trough Sq.m. 1 5.4 0.45 2.43

TOTAL Sq.m. 984.83


9.3 CEMENT PUNNING
Ground Floor
Class Room 4A Sq.m. 1 6.425 7.625 48.99
Class Room 4B Sq.m. 1 6.425 7.7 49.47
Class Room 5A Sq.m. 1 6.425 7.625 48.99
Class Room 5B Sq.m. 1 6.425 7.625 48.99

First Floor
Class Room 6A Sq.m. 1 6.425 7.625 48.99
Class Room 6B Sq.m. 1 6.425 7.7 49.47
Class Room 7A Sq.m. 1 6.425 7.625 48.99
Class Room 7B Sq.m. 1 6.425 7.625 48.99
Second Floor
Class Room 8A Sq.m. 1 6.425 7.625 48.99
Class Room 8B Sq.m. 1 6.425 7.7 49.47

Skirting Sq.m. 1 537.04 0.125 67.13

Front Steps Tread Sq.m. 1 24.05 0.6 14.43


Front Steps Riser Sq.m. 1 24.05 0.45 10.82
End sides of Wall Sq.m. 4 0.6 0.45 1.08
Total Sq.m. 584.8
9.4 CEMENT SKIRTING
Ground Floor
Class Room 4A R.M. 1 27.45 27.45
Class Room 4B R.M. 1 27.3 27.3
Class Room 5A R.M. 1 27.3 27.3
Class Room 5B R.M. 1 27.45 27.45
Passage R.M. 1 23 23
Front column R.M. 1 8.7 8.7
Staircase area R.M. 1 17.35 17.35
Waist slab R.M. 1 16.42 16.42
First Floor
Class Room 6A R.M. 1 24.1 24.1
Class Room 6B R.M. 1 27.45 27.45
Class Room 7A R.M. 1 24.1 24.1
Class Room 7B R.M. 1 24.1 24.1
Passage R.M. 1 65.3 65.3
Staircase R.M. 1 20.57 20.57
Second Floor
Class Room 8A R.M. 1 27.3 27.3
Class Room 8B R.M. 1 27.45 27.45
Passage R.M. 1 66.7 66.7
Teacher's Room R.M. 1 19.1 19.1
Hall R.M. 1 35.9 35.9
Total R.M. 537.04
9.6 TILE ON WALL
Water Trough
Base sqm. 1 5.4 0.45 2.43
outer wall sqm. 1 6.3 0.27 1.7
Inner wall sqm. 1 6.3 0.55 3.46

Total Wall Tile Sqm. 7.59


10 FINISHING WORK
10.1 EXTERNAL PLASTER
Along grid C Sq.m. 1 37.75 11.75 443.56
Along grid 11/A-B Sq.m. 1 7.05 11.125 78.43
Along grid 1/A-B Sq.m. 1 7.05 10.2 71.91
Along grid A Column Sq.m. 11 9.9 1.2 130.68

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Below passage along grid A/1-3 Sq.m. 1 8.1 2 16.2
Deduction of beam coverage Sq.m. -54 0.25 0.4 -5.4
Sq.m. -33 0.25 0.45 -3.72
Deduction of column at grid 5-6 Sq.m. -2 9.9 0.3 -5.94
Beam along grid A/1-11 Sq.m. 3 32.9 0.275 27.14
Beam along grid A-B/1&11 Sq.m. 2 6.45 0.325 4.19
Perifery slab top Sq.m. 2 62.9 0.275 34.59
Wall along grid A /1-11 in FF & SF
Sq.m. 2 32.9 1 65.8
Wall along grid 1&11 /A-B in FF & SF
Sq.m. 2 4.3 1 8.6
Deduction of openings 0
W1 Sq.m. -22 3.5 1.985 -152.85
V Sq.m. -2 3.5 0.65 -4.55
V3 Sq.m. -2 2 1.25 -5
Opening along grid 1/A-B Sq.m. -1 1.2 2.85 -3.42
Sq.m. -1 3.525 1.85 -6.53

Front Steps Sq.m. 1 24.05 0.45 10.82


Steps sides support wall Sq.m. 4 0.6 0.45 1.08

Water Trough wall Sq.m. 3 1.13 0.6 2.03


Water Trough slab bottom Sq.m. 1 6.3 0.45 2.83
Water Trough slab Sides Sq.m. 1 7.2 0.495 3.56
Apron Drain Sq.m. 1 40.5 1.3 52.65

Total Sq.m. 766.66


10.2 INTERNAL PLASTER
Ground Floor
Along grid 1,3,5,6,7,9&11/A-B Sq.m. 10 6.1 2.85 173.85
Along grid A/1-11 Sq.m. 1 32 2.9 92.8
Along grid B( Both sides) Sq.m. 2 28 2.9 162.4
Column copla Sq.m. 54 0.2 3.175 34.29
Sq.m. 21 0.4 3.175 26.67
Staircase riser Sq.m. 22 2 0.15 6.6
Perifery
W Sq.m. 8 10.97 0.2 17.55
W1 Sq.m. 8 6.97 0.2 11.15
D Sq.m. 8 5.8 0.2 9.28
V3 Sq.m. 1 6.5 0.2 1.3
Deduction
W Sq.m. -8 3.5 1.985 -55.58
W1 Sq.m. -8 1.5 1.985 -23.82
D Sq.m. -8 1.2 2.9 -27.84
V3 Sq.m. -1 2 1.25 -2.5

First Floor
Along grid 1,3,5,6,7,9&11/A-B Sq.m. 10 6.1 2.85 173.85
Along grid A/1-11 Sq.m. 1 32 2.9 92.8
Along grid B( Both sides) Sq.m. 2 28 2.9 162.4
Column copla Sq.m. 54 0.2 3.175 34.29
Sq.m. 21 0.4 3.175 26.67
Staircase riser Sq.m. 22 2 0.15 6.6
Perifery
W Sq.m. 8 10.97 0.2 17.55
W1 Sq.m. 8 6.97 0.2 11.15
D Sq.m. 8 5.8 0.2 9.28
V3 Sq.m. 1 6.5 0.2 1.3
Deduction
W Sq.m. -8 3.5 1.985 -55.58
W1 Sq.m. -8 1.5 1.985 -23.82
D Sq.m. -8 1.2 2.9 -27.84
V3 Sq.m. -1 2 1.25 -2.5
Second Floor
Along grid 1,3,5,6,8&11/A-B Sq.m. 10 6.1 2.85 173.85
Along grid A/1-11 Sq.m. 1 32 2.9 92.8
Along grid B( Both sides) Sq.m. 2 28 2.9 162.4
Column copla Sq.m. 54 0.2 3.175 34.29
Sq.m. 21 0.4 3.175 26.67
Perifery
W Sq.m. 9 10.97 0.2 19.74

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


W1 Sq.m. 6 6.97 0.2 8.36
W2 Sq.m. 1 6.37 0.2 1.27
D Sq.m. 6 5.8 0.2 6.96
D1 Sq.m. 1 5.8 0.2 1.16
V3 Sq.m. 1 6.5 0.2 1.3
Deduction
W Sq.m. -9 3.5 1.985 -62.53
W1 Sq.m. -6 1.5 1.985 -17.87
W2 Sq.m. -1 1.2 1.985 -2.39
D Sq.m. -6 1.2 2.9 -20.88
D1 Sq.m. -1 1 2.9 -2.9
V3 Sq.m. -1 2 1.25 -2.5
Total Sq.m. 1272.03
10.3 CEILING PLASTER
Ground floor
Along grid 1-11/A-C Sq.m. 1 36.4 9.35 340.34
Beam Sides
Main beam along grid A/ 1-11 Sq.m. 1 32 0.275 8.8
Main beam Along grid B/1-11 Sq.m. 2 32 0.275 17.6
Main beam Along grid C/1-11 Sq.m. 1 32.9 0.275 9.04
Main beam along grid 1-11/A-C Sq.m. 18 8.25 0.325 48.26
Secondary beam along gid X-X Sq.m. 2 29.2 0.175 10.22
Secondary beam on staircase section Sq.m. 2 4.15 0.175 1.45
Staircase
First flight waist slab Sq.m. 1 3.655 2 7.31
Sides of first flight Sq.m. 1 3.655 0.175 0.63
Sq.m. 11 0.3 0.075 0.24
Landing Sq.m. 1 4.15 1.61 6.68
Sq.m. 1 2 0.381 0.76
Second flight waist slab Sq.m. 1 3.69 2 7.38
Sides of second flight waist slab Sq.m. 1 3.69 0.175 0.64
Sq.m. 11 0.3 0.075 0.24
Top landing Sq.m. 1 4.15 0.959 3.97
Deduction
Column area coverage Sq.m. -22 0.4 0.4 -3.52
Sq.m. -11 0.3 0.3 -0.99
Staircase void Sq.m. -1 4.15 6.5 -26.98
Internal wall
600*200*200 wall
ALONG GRID 1,3,5,6,7,9 &11/(A-B)
Sq.m -7 6.1 0.2 -8.54
ALONG GRID A/1-11 Sq.m -1 4 0.2 -0.8
ALONG GRID B/1-11 Sq.m -1 6.7 0.2 -1.34

First floor
Along grid 1-11/A-C Sq.m. 1 36.4 9.35 340.34
Beam Sides
Main beam along grid A/ 1-11 Sq.m. 1 32 0.275 8.8
Main beam Along grid B/1-11 Sq.m. 2 32 0.275 17.6
Main beam Along grid C/1-11 Sq.m. 1 32.9 0.275 9.04
Main beam along grid 1-11/A-C Sq.m. 18 8.25 0.325 48.26
Secondary beam along gid X-X Sq.m. 2 29.2 0.175 10.22
Secondary beam on staircase section Sq.m. 2 4.15 0.175 1.45
Staircase
First flight waist slab Sq.m. 1 3.655 2 7.31
Sides of first flight Sq.m. 1 3.655 0.175 0.63
Sq.m. 11 0.3 0.075 0.24
Landing Sq.m. 1 4.15 1.61 6.68
Sq.m. 1 2 0.381 0.76
Second flight waist slab Sq.m. 1 3.69 2 7.38
Sides of second flight waist slab Sq.m. 1 3.69 0.175 0.64
Sq.m. 11 0.3 0.075 0.24
Top landing Sq.m. 1 4.15 0.959 3.97
Deduction
Column area coverage Sq.m. -22 0.4 0.4 -3.52
Sq.m. -11 0.3 0.3 -0.99
Staircase void Sq.m. -1 4.15 6.5 -26.98
Internal wall
600*200*200 wall
ALONG GRID 1,3,5,6,7,9 &11/(A-B)
Sq.m -7 6.1 0.2 -8.54
ALONG GRID A/1-11 Sq.m -1 4 0.2 -0.8

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


ALONG GRID B/1-11 Sq.m -1 6.7 0.2 -1.34

Second Floor
Beam Sides & Bottom
Main beam along grid A/ 1-11 Sq.m. 1 32 0.65 20.8
Main beam Along grid B/1-11 Sq.m. 2 32 0.65 41.6
Main beam Along grid C/1-11 Sq.m. 1 32.9 0.65 21.38
Main beam along grid 1-11/A-C Sq.m. 18 8.25 0.45 66.82
11 8.25 0.25 22.68
Deductions
Wall area coverage along grid C/1-11
Sq.m. -1 4 0.2 -0.8
Wall area coverage along grid B/1-11
Sq.m. -1 5.87 0.2 -1.18
Wall area coverage along grid
1,3,5,6,7,8&11/A-B Sq.m. -7 6.1 0.2 -8.54

Total Sq.m. 1005.54


10.4 PLASTER ON RCC LINTEL WITH
CORNICE
Ground Floor
Slab R.M. 1 81.9 81.9
W R.M. 8 3.5 28
First Floor
Slab R.M. 1 81.9 81.9
W R.M. 8 3.5 28
V3 R.M. 1 2 2
Second Floor R.M.
W R.M. 8 3.5 28
V3 R.M. 1 2 2
Total R.M. 0
10.5 EMULSION PAINT
Total internal plaster area Sq.m. 1272.03
Total ceiling plaster area Sq.m. 1005.54
Second floor Passage Ceiling Sq.m. 8 3.65 2.25 65.7
Sq.m. 1 4.15 2.25 9.3375
Total Sq.m. 2352.6075
10.6 WEATHERCOAT PAINT
Total external plaster area Sq.m. 766.66
Total RCC lintel with cornices area
Sq.m. 0
Cement board Sq.m. 17.96
Total Sq.m. 784.62
11 DOOR, WINDOWS WORK
11.1 UPVC SLIDING WINDOWS
Ground Floor
W Sq.m. 8 3.5 1.985 55.58
W1 Sq.m. 8 1.5 1.985 23.82
First Floor
W Sq.m. 8 3.5 1.985 55.58
W1 Sq.m. 8 1.5 1.985 23.82
Second Floor
W Sq.m. 9 3.5 1.985 62.52
W1 Sq.m. 7 1.5 1.985 20.84
Total Sq.m. 242.16
11.2 UPVC TOP HUNG WINDOWS
V3 Sq.m. 2 2 1.25 5
Total Sq.m. 5
11.3 UPVC DOUBLE DOOR
GROUND FLOOR
D Sq.m. 8 1.2 2.9 27.84
FIRST FLOOR
D Sq.m. 8 1.2 2.9 27.84
SECOND FLOOR
D Sq.m. 6 1.2 2.9 20.88
Total Sq.m. 76.56
11.4 UPVC SINGLE DOOR
SECOND FLOOR
D1 Sq.m. 1 1 2.9 2.9
Total Sq.m. 2.9
12 ROOFING WORK
12.1 CGI ROOFING SHEET

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Sq.m. 2 38.275 5.89 450.87
Total Sq.m. 450.87
12.2 CGI ROOFING SHEET ON RIDGE

Rm. 1 38.275 38.27


TOTAL Rm. 38.27
12.3 GI GUTTER
Rm. 2 38.275 76.55
TOTAL Rm. 76.55
13.1 FLASE CEILING WORK PVC BOARD

Along grid A-B/1-11 Sq.m. 8 6.25 3.65 182.5


Sq.m. 1 6.25 4.15 25.93
Along grid B-C/1-11 Sq.m. 8 2.25 3.65 65.7
Sq.m. 1 2.25 4.15 9.33
Total Sq.m. 283.46
14 MISCELLANEOUS WORK
14.2 INSULATION WORK
Along grid 1-5/A-C Sq.m. 2 16 4.817 154.14
Along grid 6-11/A-C Sq.m. 2 20.4 4.817 196.53
Total Sq.m. 350.67
15 METAL WORK
15.1 BLACK TUBULAR PIPE
Description of Work Total l Unit wt.
Bottom Chord NB 50(M) Kg. 30 4.643 139.29 5.03 700.62
Vertical Bracing NB 40(M) Kg. 30 0.425 12.75 3.56 45.39
Kg. 30 0.851 25.53 3.56 90.88
Kg. 30 1.191 35.73 3.56 127.19
Kg. 30 1.487 44.61 3.56 158.81
Inclined Bracing NB 32(M) Kg. 30 1.221 36.63 3.09 113.18
Kg. 30 1.279 38.37 3.09 118.56
Kg. 30 1.46 43.8 3.09 135.34
Inclined Bracing NB 40(M) (wind clit) Kg. 16 2.55 40.8 3.56 145.24
Top Chord NB 50(M) Kg. 30 5.871 176.13 5.03 885.93
Purlin NB 65(M)
Grid 1-5 Kg. 72 2.57 185.04 6.44 1191.65
Grid 6-11 Kg. 84 2.827 237.46 6.44 1529.24
Beyond grid 1 & 11 Kg. 24 1.085 26.04 6.44 167.69
Between grid 5-6 Kg. 12 0.395 4.74 6.44 30.52
Runner NB 40(M) Kg.
Grid 1-5 Kg. 12 2.38 28.56 3.56 101.67
Grid 6-11 Kg. 14 2.637 36.91 3.56 131.39
Connections
Base Plate Volume
At column (300*300*10) Kg. 30 0.0009 7850 211.95
At beam(250*250*10) Kg. 60 0.000625 7850 294.37
Nut Kg. 180 0.00000826236 7850 11.67
16mm Dia anchord Bolt Kg. 180 0.45 81 1.58 127.98
ISA 50*50*10 Kg. 90 0.3 27 3.8 102.6
50*75mm plate stiffner Kg. 90 0.0000375 7850 26.49
Bottom Chord
Volume
10mm thick plate (175*175) Kg. 30 0.00030625 7850 72.12
10mm thick stiffner(63*63) Kg. 120 0.00003969 7850 37.38
4nos-16mm Boults Kg. 60 wt. per pcs 0.16 9.6
Runner Plate Connection
Runner Box (175*75mm outer size)
175*68.3*10mm runner box Kg. 4 2.47 9.88
Volume
175*68.3*10mm runner plate Kg. 4 0.000119525 7850 3.75
2nos-16mm dia bolts Kg. 8 wt. per pcs 0.16 1.28
At middle
175*68.3*10mm runner box Kg. 44 2.47 108.68
Volume
175*68.3*10mm runner plate Kg. 44 0.000119525 7850 41.28
2nos-16mm dia bolts Kg. 88 wt. per pcs 0.16 14.08
Purlin Cleat Connection
Volume
Top Chord Cleat 200*90*10 Kg. 540 0.00018 7850 763.02
2nos-16mm bolts Kg. 360 wt. per pcs 0.16 57.6
Top Ridge Connection
Volume

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


2 nos -10mm thick 175*175 mm plate Kg. 30 0.00030625 7850 72.12
10mm thick stiffners(57*59) Kg. 120 0.00003363 7850 31.67
16mm dia Nut bolts Kg. 60 wt. per pcs 0.16 9.6
Truss Cleat for wind Ties
Volume
Wind Tie Cleat(100*100*6) Kg. 32 0.00006 7850 15.07
MS Flat 165*80*6 Kg. 64 0.0000792 7850 39.79
MS Flat 380*80*6mm Kg. 16 0.0001824 7850 22.9
20mm dia Nut bolts Kg. 32 wt. per pcs 0.21 6.72
16mm dia Nut bolts Kg. 40 wt. per pcs 0.16 6.4
Total Kg. 7771.3
15.2 MS PIPE
Unit Lot No L Unit wt. Quantity
Windows Railing Work
First Floor
MS Base Plate (600*50*5mm) Kg. 8 2 0.00015 7850 18.84
Vol.
25.4*25.4*2.6mm MS Post Kg. 8 3 0.695 1.69 28.18
18*18*2mm MS pipe Kg. 8 3 3.42 1 82.17
38.1*38.1*3.2mm MS pipe Kg. 8 1 3.5 3.29 92.12
Second Floor
MS Base Plate (600*50*5mm) Kg. 8 2 0.00015 7850 18.84
Vol.
25.4*25.4*2.6mm MS Post Kg. 8 3 0.695 1.69 28.18
18*18*2mm MS pipe Kg. 8 3 3.42 1 82.17
38.1*38.1*3.2mm MS pipe Kg. 8 1 3.5 3.29 92.12

Staircase Railing
Ground Floor to First Floor
NB 40 MS Round Pipe Kg. 1 1 8.29 3.56 29.51
38.1*38.1*3.2mm MS Vertical pipe Kg. 1 10 0.92 3.29 30.26
18*18*2 mm MS Pipe Kg. 1 4 7.9852 1 31.94
125*125*5 mm Base Plate Kg. 1 10 7.8125E-05 7850 6.13
Vol.
First Floor to Second Floor
NB 40 MS Round Pipe Kg. 1 1 10.06 3.56 35.81
38.1*38.1*3.2mm MS Vertical pipe Kg. 1 12 0.92 3.29 36.32
18*18*2 mm MS Pipe Kg. 1 4 9.679 1 38.71
125*125*5 mm Base Plate Kg. 1 12 7.8125E-05 7850 7.35
Vol.
Balcony Railing
First Floor
Along Grid 1&11/B-C
38.1*38.1*3.2mm MS Pipe Kg. 2 1 2.15 3.29 14.14
25.4*25.4*2.6mm MS Pipe Kg. 2 2 1.95 1.69 13.18
25.4*25.4*2.6mm MS Post Kg. 2 3 0.822 1.69 8.33
18*18*2mm MS pipe Kg. 2 18 0.437 1 15.73
Along grid C/1-2,2-3,3-4,4-5,7-8,8-9,9-10,10-
11
38.1*38.1*3.2mm MS Pipe Kg. 8 1 3.6 3.29 94.75
25.4*25.4*2.6mm MS Pipe Kg. 8 2 3.4 1.69 91.93
25.4*25.4*2.6mm MS Post Kg. 8 4 0.822 1.69 44.45
18*18*2mm MS pipe Kg. 8 33 0.437 1 115.36
Along Grid C/6-7
38.1*38.1*3.2mm MS Pipe Kg. 1 1 4.1 3.29 13.48
25.4*25.4*2.6mm MS Pipe Kg. 1 2 3.9 1.69 13.18
25.4*25.4*2.6mm MS Post Kg. 1 4 0.822 1.69 5.55
18*18*2mm MS pipe Kg. 1 36 0.437 1 15.73
Second Floor
Along Grid 1&11/B-C
38.1*38.1*3.2mm MS Pipe Kg. 2 1 2.15 3.29 14.14
25.4*25.4*2.6mm MS Pipe Kg. 2 2 1.95 1.69 13.18
25.4*25.4*2.6mm MS Post Kg. 2 3 0.822 1.69 8.33
18*18*2mm MS pipe Kg. 2 18 0.437 1 15.73
Along grid C/1-2,2-3,3-4,4-5,7-8,8-9,9-10,10-
11
38.1*38.1*3.2mm MS Pipe Kg. 8 1 3.6 3.29 94.75
25.4*25.4*2.6mm MS Pipe Kg. 8 2 3.4 1.69 91.93
25.4*25.4*2.6mm MS Post Kg. 8 4 0.822 1.69 44.45
18*18*2mm MS pipe Kg. 8 33 0.437 1 115.36
Along Grid C/6-7
38.1*38.1*3.2mm MS Pipe Kg. 1 1 4.1 3.29 13.48
25.4*25.4*2.6mm MS Pipe Kg. 1 2 3.9 1.69 13.18

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


25.4*25.4*2.6mm MS Post Kg. 1 4 0.822 1.69 5.55
18*18*2mm MS pipe Kg. 1 36 0.437 0.95 14.94

Ground floor along grid A/1-3


NB 40 MS Round Pipe Kg. 2 1 3.6 3.56 25.63
38.1*38.1*3.2mm MS Vertical pipe Kg. 2 3 1.025 3.29 20.23
18*18*2 mm MS Pipe Kg. 2 4 3.49 1 27.88

TOTAL MS PIPE Kg. 1623.22


16.1 Expansion joint
Plinth level
Ground floor Rm 1 2.15 2.15
Total Rm 2.15

16.2 Slab
Ground floor slab Rm 1 2.15 2.15
First floor slab Rm 1 2.15 2.15
Total Rm 4.3
16.3 Ends of Wall
Front face from Gl to Top level Rm 1 10.4 10.4
Backside column fron backside GL to top 1 11.75 11.75
level Rm
inside vertical column face (GF,1F,2F) Rm 1 17.1 17.1
Total Rm 39.25

18.2 Guide Ramp Rm 1 8 8


Total 8
22 Floor Hardener
Ground Floor
Passage Sq.m. 1 36.3 2.25 81.67
staircase
steps Sq.m. 22 2 0.3 13.2
Riser Sq.m. 20 2 0.15 6
Landing Sq.m. 1 4.1 2 8.2
Lobby Sq.m. 1 7.1 4.1 29.11

First Floor
Passage Sq.m. 1 36.3 2.45 88.93
staircase
steps Sq.m. 22 2 0.3 13.2
Riser Sq.m. 20 2 0.15 6
Landing Sq.m. 1 4.1 2 8.2
Lobby Sq.m. 1 4.1 1.25 5.12
Second Floor
Passage Sq.m. 1 36.3 2.45 88.93
Lobby Sq.m. 1 4.1 1.25 5.12
Teacher's Room Sq.m. 1 3.725 6.425 23.93
Skirting Sq.m. 1 19.3 0.125 2.41
Multipurpose hall Sq.m. 1 11.525 6.425 74.04
Skirting Sq.m. 1 35.9 0.125 4.48
Lobby Sq.m. 1 4.1 1.25 5.12
TOTAL Sq.m. 463.66

23 Cement Board
Gable Wall Sq.m. 2 9.325 1.76 16.41
Belowe ceiling beam gap in passage
Sq.m. 2 2.15 0.725 1.55
TOTAL Sq.m. 17.96
24 FLOOR TILE (600*600)

TOTAL TILE (600*600) Sq.m. 0


25 ENAMEL PAINT
Windows railing Sq.m. 16 7 0.62 69.44
Staircase Railing Sq.m. 1 36.7 0.9 33.03
Passage Railing Sq.m. 2 74.4 0.65 96.72
Ground Floor Passage Railing Sq.m. 1 14.4 0.9 12.96
Chain Gate Sq.m. 1 8.2 2.85 23.37

Prepared By: Checked By: Verified By:


MB MIDDLE BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB MIDDLE BLOCK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks

Total Sqm. 235.52


26 PILE Work
Piles
P1 Rm 5 10 50
Rm 6 10 30 Reconstruction
P2 Rm 1 12 6 Reconstruction

Total Rm. 86
27 DISMANTLING WORK
27.1 Concrete dismantling
Plinth Beam
Grid 6-11 cum 6 3 0.25 0.45 2.02
Grid C cum 1 18 0.25 0.4 1.8
Lower Tie beam
Grid 6-11 cum 6 3 0.23 0.23 0.95
Grid C cum 1 18 0.23 0.23 0.95
Column
Grid C cum 6 0.4 0.4 2.15 2.06
Footing 0
F1 cum 1 1.6 1.6 0.3 0.76
F3 cum 4 2.4 2.4 0.4 9.21
F5 cum 1 3 3 0.45 4.05

Total cum 21.8


27.2 Brickwork Dismantling
Along grid 6-11 cum 6 3 0.23 1.4 5.79
Along grid C cum 1 18 0.23 1.45 6

Total cum 11.79

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST MIDDLE BLOCK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

GENERAL WORK, SITE CLEARANCE:Clearing and


grubbing of site for construction including uprooting of
1.1 vegetation, grass, brush wood, trees and sapplings of girth Sq.M 535.65 100.00 53,565.00
upto 300 mm & removal upto a distance of 50 m as per
drawings, specifications and instructions

EARTHWORK IN EXCAVATION: Earthwork in


2.1 excavation in trenches, pits and foundations by machine or Cu.M 1016.49 200.00 203,298.00
appropriate technology in soft soil including existing debris
and brick bats of old structure, if any, upto specified depth
EARTWORK IN FILLING: Providing and placing of
random filling of excavated earth from cutting of slope and
stacked at site in 150mm thick layer in trenches, plinth or
under floor, sides of foundation and below beam at footing
2.2 Cu.M 294.64 200.00 58,928.00
covered area etc. including watering, mechanical ramming
and compaction of each layer, consolidation and dressing,
all complete as per drawings, specifications and instructions.

SAND FILLING: Sand filling in plinth under floors,


including watering, ramming, consolidating and dressing, all
2.3 complete as per drawings, specifications and instructions. Cu.M 0 2,500.00 -

STONE WORK : Dry stone soling work in line and level,


including packing joints with sand dust, all complete as per
3.1 drawings, specifications and instructions Cu.M 0 4,000.00 -

STONE MASONRY WALL: Stone rubble masonry work in


1:4 cement and sand mortar with hard, tough, sound and
durable stone in wall, made to required line, level, shape,
3.2 size and plumb including setting out, drain outlet, curing of Cu.M 0 7,500.00 -
the works and scaffolding etc. complete as per drawings,
specifications and instructions

BRICK WORK,FLAT BRICK SOLING: Flat brick soling


of local chimney bricks laid in line and level, including
4.1 packing joints with sand, complete as per drawings, Sq.M 665.98 800.00 532,784.00
specifications and instructions
FULL BRICK WORK: Brickwork in substructure and super
4.2 structure cement and sand mortar of mix 1:6 with first class Cu.M 89.15 15,000.00 1,337,250.00
chimney-made bricks, in any size and shape of wall, made
to required line, level, shape and plumb including setting
AAC(Autoclaved Aerated Concrete) BLOCK WORK:
5.1 Providing and laying of Autoclaved Aerated Concrete Block Sq.M 551.97 1,800.00 993,546.00
(600*200*200 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2)AAC(Autoclaved Aerated Concrete) BLOCK WORK:
Providing and laying of Autoclaved Aerated Concrete Block
(600*200*100 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2 required line, level, shape and plumb including setting out, Sq.M 0 2,000.00 -
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

5.3)AAC(Autoclaved Aerated Concrete) BLOCK WORK:


Providing and laying of Autoclaved Aerated Concrete Block
(600*200*150 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.3 required line, level, shape and plumb including setting out, Sq.M 0 1,100.00 -
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

CONCRETE WORK,PCC OF GRADE M10: Plain cement


concrete (PCC) of grade M10 (1:3:6 with 1 cement, 3 coarse
sand and 6 aggregate of 19 mm and down grade) in
6.1 foundation base including mixing, laying, compacting, Cu.M 52.49 10,000.00 524,900.00
finishing, curing, laid to exact line, level and dimensions,
inclusive ofside

PCC FOR RCC OF GRADE M25: Structural concrete (PCC


for RCC) of Grade M25 (1:1:2)works with approved
quality of cement, sand and well graded aggregate in any
form, size, shape and level including batching and mixing
6.2 with machine, laying including compaction with vibrating Cu.M 66.93 20,000.00 1,338,600.00
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

PCC FOR RCC OF GRADE M20: Structural concrete (PCC


for RCC) of Grade M20 (1:1.5:3)works with approved
quality of cement, sand and well graded aggregate in any
6.3 form, size, shape and level including batching and mixing Cu.M 222.45 17,000.00 3,781,650.00
with machine, laying including compaction with vibrating
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

FORMWORK: Placing plyboard form work with steel


props, shuttering, centering in horizontal/Vertical surfaces
like slab, beams, column, wall, stair etc. for all RCC works
7.1 of any shape, size and at any level and removal after Sq.M 2160 850.00 1,836,000.00
completion

REINFORCEMENT WORK: Providing and placing steel


reinforcement bar tested grade Fe-500 equivalent NS, for
8.1 RCC work including bending, binding with anneal wire and kg 50370.56 110.00 5,540,761.60
placing in position, all complete as per drawings,
specifications and instruction

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST MIDDLE BLOCK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

9.1)FLOORING WORK,PLASTIC
9.1 LAYING: Supplying and laying 500 gauge plastic sheet in Sq.M 0 50.00 -
floor as per specificatio and instruction
9.2)SCREEDING: Providing and placing 38 mm thick Plain
cement concrete of grade M15 (1:2:4 with 1 cement, 2
coarse sand and 4 aggregate chips) in the floor base mixing,
laying, compacting, finishing, curing, laid to exact line level
9.2 , surface chipping and dimensions (floor concrete is laid in Sq.M 984.83 500.00 492,415.00
alternate panels of 1 m x 1 m) inclusive of shuttering
complete as per drawings, specifications and instructions

9.3)CEMENT PUNNING: Providing


and laying 3 mm cement punning in floor , laying in
9.3 Sq.M 584.8 200.00 116,960.00
required pattern, line

9.4)CEMENT SKIRTING: Providing


and placing cement skirting 125mm height of grade M15
(1:2:4 with cement, 2 coarse sand and 4 aggregate
) in wall ,mixing, laying, compactig, finishing, curing, laid
9.4 to exact line level and dimension all complete as per R.M 537.04 100.00 53,704.00
drawing, specification and instructions

9.5)TILE LAYING ON FLOOR:


Providing and laying approved brand quality, pattern and
color, ceramic mat finish tile (Low range) on floor over
9.5 cement mortar of mix 1:3 backing and filling joints (epoxy Sq.M 0 2,800.00 -
grout) complete as per drawings, specifications and
instructions.(Base rate: NRs 100)

9.6)TILE LAYING ON TOILET:


Providing and laying approved brand quality, pattern and
color, ceramic glazed tile in wall and ceramic mat finish tile
9.6 (Low range) on floor of toilet over cement mortar of mix 1:3 Sq.M 7.59 3,000.00 22,770.00
backing and filling joints (epoxy grout) complete as per
drawings, specifications and instructions.(Base rate: NRs
100)

10.1)FINISHING WORK,
EXTERNAL PLASTER: Providing and applying '10.5 mm
thick cement plastering with 1cement : 4 sand mortar in
outer surface any level size and shape of wall, column,
10.1 ceiling, band, blocks, etc inclusive of waterproofing Sq.M 766.66 400.00 306,664.00
compound, dusting, throating, etc as required including
racking, hacking, watering, cleaning of base, plastering to
plumb, line, level, smooth etc. and curing complete as per
drawings, specifications and instructions.
10.2)INTERNAL PLASTER:
Providing and applying'10.5 mm thick cement plastering
with 1cement : 4 sand mortar in inner surface except ceiling
any level size and shape of wall, column, band, blocks, etc
inclusive of dusting, throating, etc as required including
10.2 racking, watering, hacking, cleaning of base, plastering to Sq.M 1272.03 450.00 572,413.50
plumb, line, level, smooth etc. and curing, all complete as
per drawings, specifications and instructions.

10.3)CEILING PLASTER: Providing


and applying 12.5 mm thick cement plastering with 1cement
10.3 : 4 sand mortar in Ceiling any level size and shape of Sq.M 1005.54 500.00 502,770.00
ceiling inclusive of dusting,
10.4)PLASTER ON RCC LINTEL
WITH CORNICE: 'Providing and applying 12.5 mm thick
cement plastering with 1cement : 4 sand mortar in RCC
Lintel with cornice inclusive of dusting, throating, etc as
required including racking, watering, cleaning of base,
10.4 plastering to plumb, line, level, smooth etc. and curing, all R.M 0 3,000.00 -
complete as per drawings, specifications and instructions.

10.5)EMULSION PAINT: Providing


and applyibg two coat of emulsion paint in mat finishing
10.5 over two coat of primer, finished including surface Sq.M 2352.6075 200.00 470,521.50
preparation all complete as per drawings, specifications and
instruction
10.6)WEATHER COAT: Providing and applying two coat
of weather coat (Apex or equivalent) over required coat of
10.6 primer, finished including surface preparation all complete Sq.M 784.62 250.00 196,155.00
as per drawings, specifications and instruction

11.1)DOOR,WINDOWS WORK/UPVC SLIDING


WINDOWS: Providing and fixing standard UPVC sliding
window without net (frame 50x80mm, sash 58x36mm white
11.1 colour with 5mm glass) along with patented standard Sq.M 242.16 8,000.00 1,937,280.00
hardwares like roller, gaskets, brush seal, moon locks etc all
complete as per drawings and specifications.

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST MIDDLE BLOCK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

11.2)UPVC TOP HUNG


WINDOWS: Providing and fixing standard UPVC top hung
window (frame 60x60 mm, sash 60x104 mm, white colour
11.2 with 5 mm glass) along with patented standard hardwares Sq.M 5 8,000.00 40,000.00
like roller, gaskets, brush seal, moon locks etc all complete
as per drawings and specifications.

11.3)UPVC DOUBLE DOOR:


Providing and fixing standard UPVC double door (frame
60x60mm, sash 60x104mm white colour with 5mm glass)
11.3 along with patented standard hardwares like roller, gaskets, Sq.M 76.56 10,000.00 765,600.00
brush seal, moon locks etc all complete as per drawings and
specifications.

11.4)UPVC SINGLE DOOR:


Providing and fixing standard UPVC single door with full
panel (frame60x60mm, sash 60x104mm white colour with
11.4 5mm glass) along with patented standard hardwares like Sq.M 2.9 7,000.00 20,300.00
roller, gaskets, brush seal, moon locks etc all complete as
per drawings and specifications.

12.1)ROOFING WORK,CGI
ROOFING SHEET: Providing and fixing in position 24
gauge medium (0 .5 mm thick) corrugated CGI sheet over
12.1 roof truss with minimum 80 mm side laps and 200 mm end Sq.M 450.87 1,319.17 594,774.17
laps, inclusive of nuts and bolts, 8 mm 'J' hooks, washers,
GI cup washers, all complete as per drawings, specifications
and instruction

12.2)CGI ROOFING SHEET ON


RIDGE: Providing and fixing in position 24 gauge medium
(0 .5 mm thick) CGI sheet over roof truss in ridge with
12.2 minimum 80 mm side laps and 200 mm end laps, inclusive R.m 38.27 1,009.52 38,634.33
of nuts and bolts, washers, GI cup washers, all complete as
per drawings, specifications and instruction

12.3)GI GUTTER: providing and fixing in position color


plain GI sheet for gutter 150mmX450mm, inclusive of nuts
12.3 and bolts, washers, all complete as per drawings, R.m 76.55 1,000.00 76,550.00
specifications and instruction.
13.1)FALSE CEILING WORK,PVC
BOARD: Providing and fixing suspended PVC board false
ceiling, with necessary provisions for light fittings, light
13.1 boxes, where required finally finished with two coat acrylic Sq.M 283.46 1,500.00 425,190.00
emulsion paint, all complete as per drawings, specifications
and instructions.

14.1)MISCELLANEOUS WORK,
WATER PROOFING: Providing and placing 20 mm thick
cement sand mortar (1:2) mixing with wate proof
14.1 compound in the floor base mixing, laying, compacting, Sq.M 0 400.00 -
finishing, curing, laid to exact line level and dimensions
complete as per drawings, specifications and instructions

14.2)INSULATION WORK:
Providing and installing Insulation under CGI roofing sheet
14.2 with Insulation shield of 12mm thickness one sided and Sq.m 350.67 200.00 70,134.00
chicken wire mesh all completeas per drawing and
specifications.
15.1)METAL WORKS,BLACK
15.1 TUBULAR PIPE: Supplying, fabricating and fixing black Kg 7771.3 150.00 1,165,695.00
pipe (Square or circular) work /Truss with
15.2)MS PIPE: Supplying, fabricating and fixing metal
15.2 work of different angles MS Pipe with one coat primer as Kg 1623.22 150.00 243,483.00
shown in drawing all complete
15.3)ROLLING SHUTTER:
Providing and fixing rolling shutterof 16-19 Gauge cold
rolled MS lathe interlocked throughout their entire length
and joined together at the end by end locks and mounted on
specially designed pipe shaft with brackets, side guides and
15.3 arrangements for inside and outside locking,with push and Sq.m 0 4,000.00 -
pull operation, complete supplying, fixing and painting with
two coats of approved plastic emulsion paint.

15.4)HOT ROLLED STEEL


SECTION: Supplying, fabricating and fixing metal work of
15.4 different Hot Rolled Steel sections with one coat primer as Kg 0 150.00 -
per drawings and specifications all complete

15.5)METAL WORK,METAL
GATE: Supplying, fabricating and fixing in position, metal
gates of standard sections consisting of angles, pipes,
15.5 flats,etc. including one coat primer and one coat enamel Sq.M 0 7,000.00 -
paint as per drawings, specifications and instructions all
complete

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST MIDDLE BLOCK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

15.6)FENCING WORK: Providing and fixing of ISA


50x50x5 mm along with 25x25x5 flat and M8x40 bolts at
12.3 300mm spacing to fix 10 S.W.G.G.I chain link with hole R.M 0 2,200.00 -
size 60x60 mm upto 3m height and 3 lines of barbed wire at
top.
16.1)EXPANSION JOINT WORKS/PLINTH LEVEL:
Suuply
and fixing of expansion joint at level of 100% non porous
flexible element allowing movement in all directions,
16.1 supported by aluminium framing and covering the top by R.M 2.15 4,500.00 9,675.00
aluminium sheet and flused to required floor level all
complete as per drawing, specification and instruction.

16.2)EXPANSION JOINT
WORKS/SLAB: Supply and fixing of expansion joint at
floor level of aluminium base supported by alumunium
16.2 framing,fixed on one side by threaded screw and flushed to R.M 4.3 4,500.00 19,350.00
required floor level and dimension all complete as per
drawing,specification and instruction

16.3)EXPANSION JOINT WORKS/ENDS OF WALL:


16.3 Supply R.M 39.25 4,500.00 176,625.00
17.1)CHAIN LINK VENTILATION
WORK: Supplying, fabricating and fixing in position of 10
S.W.G.I. woven wire ventilation with hollow square pipe
framing of size 18x18x1.0 mm on all sides with proper
17.1 welding on site, including one coat primer and one coat Sq.M 0 4,000.00 -
enamel paint on frames as per drawings, specifications and
instructions all complete

18.1)LAND DEVELOPMENT WORKS, INTERLOCKING


BLOCKS: Supplying and laying of 60 mm thick heavy duty
interlocking paving blocks of approved colour and quality
on the 50 mm thick stone dust with surface grading,
18.1 levelling and soil compaction base in driveways and parking Sq.M 0 2,000.00 -
areas, complete as per specifications and drawings.

18.2)RAILING WORKS: Supply,


fabrication and fitting of Railing works with MS square pipe
framing and 10 S.W.G.I. wire mesh of height 1.05m
18.2 including excavation, brickwork, plaster and two coats R.M 0 3,000.00 -
enamel paint all complete as per drawings and specifications

18.3)GUIDE RAMP: Supply,


fabrication and fitting of Guide Ramp-Utility Guardrail for
the disabled with MS tubular pipes at regular intervals of
18.3 height 1.05m including two coats enamel paint all complete R.M 8 6,500.00 52,000.00
as per drawings and specifications

18.4)APRON DRAIN: Construction of Apron drain along


the perimeter of buildings and retaining structures including
18.4 excavation, Brick soling, PCC and half brick thick apron R.M 20,000.00 -
walls with plaster all complete as per drawings and
specifications
18.5)TACTILE PAVING: Providing
and laying approved brand quality, pattern and colour of
Tactile paving tile on floor over constructed cement mortar
18.5 of mix 1:3 backing and filling joints (epoxy grout) at R.M 0 3,500.00 -
straight path and turning points of size 300x300x40mm, all
complete as per drawings, specifications and instructions.

DEMOLITION WOKS: Demolition of existing building


19.1 and toilet blocks PS 0 1,000,000.00 -

RELOCATION WOKS: Relocation of temple from existing


site and to be constructed at a new location outside of the
20.1 school site as per drawing,specification and instructions. PS 0 300,000.00 -

INSURANCE PREMIUM
21.1 PS 0 224,281.00 -

Floor Hardener:providing,sprinkling,laying &applying


Manually two layer in floor,applied each layer with 1.5 to
2.5kg /m2 in required pattern,blended in,smoothed,over by
22.1 power trowelling,in line and level including curing all Sq.M 463.66 400.00 185,464.00
complete as per drawing,specification and instruction.
(Mapetop,N,AR6 or equivalent)

Cement Board:providing and fixing in position 10mm


water proofed cement board in exterior (one side)surface
inclusive minimum75mm GI metal framewith grooving and
23.1 fixing of fastner ,washer,nuts,and bolts,all complete as per Sq.M 17.96 2,700.00 48,492.00
drawings,specifications and instructions.

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST MIDDLE BLOCK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ item
Item Description Unit Quantity Rate Amount Remarks
no

FLOOR TILE (600*600)


24 Sq.m. 0 2,500.00 -

ENAMEL PAINT
25 Sq.M 235.52 286.00 67,358.72

PILE WORK : Construction of pile work including


26 excavation, reinforcement and concreting work. Rm 86 17,000.00 1,462,000.00

DISMANTLING WORK
27 -

CONCRETE DISMANTLING
27.1 Cu.M 21.8 8,500.00 -

BRICKWALL DISMANTLING
27.2 Cu.M 11.79 2,000.00 -

TOTAL CIVIL WORKS -


TOTAL AMOUNT
26,334,260.82

Total Item Price 26,334,260.82

Discount @2% 526,685.22

Sub Total 25,807,575.60

VAT @13% 3,354,984.83

Grand Total 29,162,560.43

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB TOILET-1
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


1.1 GENERAL WORK, SITE CLEARANCE Sq.M 1 11.6 10.4 120.64
2.1 EARTHWORK IN EXCAVATION
FOOTINGS
F1 Cu.m. 6 1.6 1.6 2.2 33.79
Lower tie beam along grid A &B Cu.m. 2 4.8 0.375 1.83 6.58
Lower tie beam along grid 1,2,3 Cu.m. 3 5.2 0.375 1.83 10.7

Steps Cu.m. 4 3.75 0.3 0.13 0.58


Water Trough Cu.m. 1 5.2 0.45 0.13 0.3

TOTAL EARTHWORK IN Cu.m.


EXCAVATION 51.95
2.2 EARTHWORK IN FILLING
Total earthwork in excavation 51.95
Inside Room Cu.m. 1 6.74 3.255 0.45 9.87
Cu.m. 1 6.74 4.455 0.45 13.51
Deduction
Sand Filling Cu.m. 0
Flat brick soling Cu.m. -4.84
Brickwork upto plinth beam Cu.m. -15.67
PCC M10 Cu.m. -6.73
RCC M25 (Colums upto plinth level) Cu.m. -2.88
RCC M20 (Footings , Bottom tie beam, Lower Cu.m.
tie beam) -12.87
Total Back Filling Cu.m. 32.34
2.3 SAND FILLING
CRUSHED STONE DUST
For Isolated Footing F1 Cu.m. 6 1.6 1.6 0.075 1.15
Inside Room Cu.m. 1 6.74 3.255 0.1 2.19
Cu.m. 1 6.74 4.455 0.1 3
Total Sand Filling Cu.m. 0
4 BRICK WORK
4.1 FLAT BRICK SOLING
FOOTINGS
F1 Sq.m. 6 1.6 1.6 15.36
LOWER TIE BEAM
Along gridA, B/1-3 Sq.m. 2 4.8 0.375 3.6
along grid 1,2,3/A-B Sq.m. 3 5.2 0.375 5.85
Inside Room Sq.m. 1 6.74 3.255 21.93
Sq.m. 1 6.74 4.455 30.02
Steps Sq.m. 4 3.75 0.6 9
Water Trough Sq.m. 1 5.2 0.45 2.34

TOTAL FLAT BRICK SOLING Sq.m. 88.1


4.2 FULL BRICK WORK
From lower tie beam to upper tie beam
Along grid A&B Cu.m. 2 7.2 0.23 1.55 5.13
along grid 1,2,3/A-B Cu.m. 3 6.4 0.23 1.55 6.84
For male urinal Cu.m. 1 4.5 0.25 0.1 0.11
For female urinal Cu.m. 1 4.5 0.4 0.1 0.18
First Steps cu.m 4 3.75 0.6 0.15 1.35
Second Steps cu.m 4 3.75 0.3 0.15 0.67
Deduction of ladies urinal Cu.m. -6 0.43 0.35 0.1 -0.1
Outside Water Trough
Base wall cu.m 4 0.45 0.23 0.3 0.12
Top Wall cu.m 1 6.1 0.11 0.15 0.1
Outside Water Trough ( Two)
Base wall cu.m 6 0.6 0.23 0.6 0.49
Top Wall cu.m 2 3.3 0.11 0.15 0.1
Inceneration cu.m 1 2.7 0.23 1.1 0.68

TOTAL FULL BRICK WORK Cu.m. 15.67


5 AAC BLOCK
5.1 AAC BLOCK (600*200*200)
ALONG GRID A&B Sq.m 2 5.75 2.45 28.17
ALONG GRID 1 Sq.m 1 4.3 2.4 10.32
ALONG GRID 2 Sq.m 1 6.4 2.4 15.36
ALONG GRID 3 Sq.m 1 4.3 2.4 10.32
Middle partition wall Sq.m 1 7.8 2.85 22.23
Teacher's Toilet male Sq.m 1 1.45 1.95 2.82

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB TOILET-1
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Teacher's Toilet Female Sq.m 1 1.45 1.95 2.82
Male Toilet Sq.m 1 1.45 1.95 2.82
Female Toilet Sq.m 1 1.45 1.95 2.82
DEDUCTION
V3 Sq.m -4 2.1 0.425 -3.57
V4 Sq.m -4 1.85 0.375 -2.78
TOTAL Sq.m. 91.33
5.2 AAC BLOCK(600*200*100)
Teacher's Toilet male Sq.m 1 1.75 1.95 3.41
Teacher's Toilet Female Sq.m 1 2.05 1.95 3.99
Male Toilet Sq.m 1 3.8 1.95 7.41
Female Toilet Sq.m 1 3.8 1.95 7.41
TOTAL Sq.m. 22.22
6 CONCRETE WORK
6.1 PCC of grade M10
FOOTINGS
F1 Cu.m. 6 1.6 1.6 0.075 1.15
LOWER TIE BEAM
Along gridA, B/1-3 Cu.m. 2 6.4 0.375 0.075 0.36
along grid 1,2,3/A-B Cu.m. 3 5.2 0.375 0.075 0.43
Inside Room Cu.m. 1 6.74 3.255 0.075 1.64
Cu.m. 1 6.74 4.455 0.075 2.25
Cu.m.
Steps Cu.m. 4 3.75 0.6 0.075 0.67
Water Trough Cu.m. 1 5.2 0.45 0.075 0.17
Inceneration Cu.m. 1 1.05 0.825 0.075 0.06

TOTAL Cu.m. 6.73


6.2 PCC for RCC of Grade M25
Column upto plinth lvl Cu.m. 6 0.4 0.4 2.15 2.06
Columns above plinth level Cu.m. 6 0.4 0.4 3 2.88
TOTAL Cu.m. 4.94
6.3 PCC for RCC of Grade M20
FOOTINGS
F1 Cu.m. 6 1.6 1.6 0.3 4.6
LOWER TIE BEAM
Along gridA, B/1-3 Cu.m. 2 7.2 0.23 0.3 0.99
along grid 1,2,3/A-B Cu.m. 3 6.4 0.23 0.3 1.32
PLINTH BEAM
Along gridA, B/1-3 Cu.m. 2 7.2 0.23 0.3 0.99
along grid 1,2,3/A-B Cu.m. 3 6.4 0.23 0.3 1.32
GROUND FLOOR BEAM
Along gridA, B/1-3 Cu.m. 2 7.2 0.23 0.4 1.32
along grid 1,2,3/A-B Cu.m. 3 6.4 0.23 0.45 1.98

Incineration slab Cum. 1 1.2 0.975 0.075 0.08


Inceneration Band Cum. 1 2.7 0.23 0.075 0.04
BANDS
SILL BANDS
AAC BLOCK (600*200*200)
ALONG GRID A&B Cu.m. 2 5.8 0.2 0.075 0.17
ALONG GRID 1 Cu.m. 1 4.3 0.2 0.075 0.06
ALONG GRID 2 Cu.m. 1 6.4 0.2 0.075 0.09
ALONG GRID 3 Cu.m. 1 4.3 0.2 0.075 0.06
Middle partition wall Cu.m. 1 7.8 0.2 0.075 0.11
Teacher's Toilet male Cu.m. 1 1.45 0.2 0.075 0.02
Teacher's Toilet Female Cu.m. 1 1.45 0.2 0.075 0.02
Male Toilet Cu.m. 1 1.45 0.2 0.075 0.02
Female Toilet Cu.m. 1 1.45 0.2 0.075 0.02
AAC BLOCK(600*200*100)
Teacher's Toilet male Cu.m. 1 1.75 0.1 0.075 0.01
Teacher's Toilet Female Cu.m. 1 2.05 0.1 0.075 0.01
Male Toilet Cu.m. 1 3.8 0.1 0.075 0.02
Female Toilet Cu.m. 1 3.8 0.1 0.075 0.02

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB TOILET-1
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


LINTEL BANDS
AAC BLOCK (600*200*200)
ALONG GRID A&B Cu.m. 2 5.8 0.275 0.075 0.23
ALONG GRID 1 Cu.m. 1 4.3 0.275 0.075 0.08
ALONG GRID 2 Cu.m. 1 6.4 0.2 0.075 0.09
ALONG GRID 3 Cu.m. 1 4.3 0.275 0.075 0.08
Middle partition wall Cu.m. 1 7.8 0.2 0.075 0.11
Teacher's Toilet male Cu.m. 1 1.45 0.2 0.075 0.02
Teacher's Toilet Female Cu.m. 1 1.45 0.2 0.075 0.02
Male Toilet Cu.m. 1 1.45 0.2 0.075 0.02
Female Toilet Cu.m. 1 1.45 0.2 0.075 0.02
AAC BLOCK(600*200*100)
Teacher's Toilet male Cu.m. 1 1.75 0.1 0.075 0.01
Teacher's Toilet Female Cu.m. 1 2.05 0.1 0.075 0.01
Male Toilet Cu.m. 1 3.8 0.1 0.075 0.02
Female Toilet Cu.m. 1 3.8 0.1 0.075 0.02
Cu.m.
Water Trough Base Slab Cu.m. 1 5.2 0.45 0.1 0.23
Inside water trough Cu.m. 2 3.3 0.6 0.1 0.39

TOTAL RCC M20 Cu.m. 14.62


7.1 FORM WORK
For PCC
Formwork for Footing
F1 Sq.m. 6 6.4 0.075 2.88
BEAM
LOWER TIE BEAM
Along gridA, B/1-3 Sq.m. 2 7.2 0.075 1.08
along grid 1,2,3/A-B Sq.m. 3 6.4 0.075 1.44

For Steps PCC Sq.m. 4 4.95 0.075 1.48


For Water Trough PCC Sq.m. 1 11.3 0.075 0.84
Formwork for Footing
F1 Sq.m. 6 6.4 0.3 11.52
BEAM
LOWER TIE BEAM
Along gridA, B/1-3 Sq.m. 2 7.2 0.6 8.64
along grid 1,2,3/A-B Sq.m. 3 6.4 0.6 11.52
PLINTH BEAM
Along gridA, B/1-3 Sq.m. 2 7.2 0.6 8.64
along grid 1,2,3/A-B Sq.m. 3 6.4 0.6 11.52
GROUND FLOOR BEAM
Along gridA, B/1-3 Sq.m. 2 7.2 1.03 14.83
along grid 1,2,3/A-B Sq.m. 3 6.4 1.13 21.69
COLUMNS
Upto plinth level Sq.m. 6 1.6 2.15 20.64
Above plinth level Sq.m. 6 1.6 3 28.8
DEDUCTIONS
Lower tie beam face Sq.m. -14 0.23 0.3 -0.97
Plinth Beam face Sq.m. -14 0.23 1.3 -4.19
Ground floor beam face Sq.m. -8 0.23 0.4 -0.74
Sq.m. -6 0.23 0.45 -0.63
BANDS
SILL BANDS
AAC BLOCK (600*200*200)
ALONG GRID A&B Sq.m 2 5.8 0.15 1.74
ALONG GRID 1 Sq.m 1 4.3 0.15 0.64
ALONG GRID 2 Sq.m 1 6.4 0.15 0.96
ALONG GRID 3 Sq.m 1 4.3 0.15 0.64
Middle partition wall Sq.m 1 7.8 0.15 1.17
Teacher's Toilet male Sq.m 1 1.45 0.15 0.21
Teacher's Toilet Female Sq.m 1 1.45 0.15 0.21
Male Toilet Sq.m 1 1.45 0.15 0.21
Female Toilet Sq.m 1 1.45 0.15 0.21
AAC BLOCK(600*200*100)
Teacher's Toilet male Sq.m 1 1.75 0.15 0.26
Teacher's Toilet Female Sq.m 1 2.05 0.15 0.3
Male Toilet Sq.m 1 3.8 0.15 0.57
Female Toilet Sq.m 1 3.8 0.15 0.57
LINTEL BANDS
AAC BLOCK (600*200*200)
ALONG GRID A&B Sq.m 2 5.8 0.225 2.61
ALONG GRID 1 Sq.m 1 4.3 0.225 0.96

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB TOILET-1
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


ALONG GRID 2 Sq.m 1 6.4 0.15 0.96
ALONG GRID 3 Sq.m 1 4.3 0.225 0.96
Middle partition wall Sq.m 1 7.8 0.15 1.17
Teacher's Toilet male Sq.m 1 1.45 0.15 0.21
Teacher's Toilet Female Sq.m 1 1.45 0.15 0.21
Male Toilet Sq.m 1 1.45 0.15 0.21
Female Toilet Sq.m 1 1.45 0.15 0.21
AAC BLOCK(600*200*100)
Teacher's Toilet male Sq.m 1 1.75 0.15 0.26
Teacher's Toilet Female Sq.m 1 2.05 0.15 0.3
Male Toilet Sq.m 1 3.8 0.15 0.57
Female Toilet Sq.m 1 3.8 0.15 0.57

Water Trough Slab


Outside of building Sq.m 1 5.2 0.45 2.34
Sq.m 1 6.1 0.1 0.61
Inside building Sq.m 2 3.3 0.6 3.96
Sq.m 2 3.3 0.1 0.66

Total Formworks Sq.m. 163.45


8.1 REINFORCEMENT WORK
FOUNDATIONS Kg 1 200.64 200.64
COLUMNS Kg 1 1542.85 1542.85
BEAMS Kg 1 1284.48 1284.48
BANDS Kg 1 303.54 303.54
Water trogh Kg 1 69.68 69.68

Total Kg 3401.19
9 FLOORING WORK
9.1 PLASTIC LAYING
Inside Room Sq.m. 1 6.74 3.255 0.075 21.93
Sq.m. 1 6.74 4.455 0.075 30.02
Total Sq.m. 0
9.2 SCREEDING
Ground Floor
first steps Sq.m. 4 3.75 0.3 4.5 In tread of steps
Second steps Sq.m. 4 3.75 0.6 9
Floor tile area Sq.m. 1 49.52
Water Trough
Outer Sq.m. 1 5.09 0.395 2.01
Inner Sq.m. 2 1.95 0.6 2.34

TOTAL Sq.m. 67.37


9.3 CEMENT PUNNING
Steps
Riser Sq.m. 12 3.75 0.15 6.75
Tread Sq.m. 8 3.75 0.3 9
Sq.m. 15.75
9.5 TILE LAYING ON FLOOR
Floor Tile
Teacher's Toilet Male Sq.m. 1 3.5 3.5 12.25
Deductions
Wall area 600*200*200 Sq.m. -1 5.8 0.2 -1.16
Wall area 600*200*100 Sq.m. -1 1.75 0.1 -0.18
Column Sq.m. -1 0.4 0.4 -0.16

Teacher's Toilet Female Sq.m. 1 3.5 3.5 12.25


Deductions
Wall area 600*200*200 Sq.m. -1 5.8 0.2 -1.16
Wall area 600*200*100 Sq.m. -1 2.05 0.1 -0.21
Column Sq.m. -1 0.4 0.4 -0.16
Pan area Sq.m. -1 0.58 0.48 -0.28

Male Toilet Sq.m. 1 4.7 3.7 17.39


Deductions
Wall area 600*200*200 Sq.m. -1 6.95 0.2 -1.39
Wall area 600*200*100 Sq.m. -1 3.8 0.1 -0.38

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB TOILET-1
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Column Sq.m. -1 0.4 0.4 -0.16
Pan area Sq.m. -3 0.58 0.48 -0.84

Female Toilet Sq.m. 1 4.7 3.7 17.39


Deductions
Wall area 600*200*200 Sq.m. -1 6.95 0.2 -1.39
Wall area 600*200*100 Sq.m. -1 3.8 0.1 -0.38
Column Sq.m. -1 0.4 0.4 -0.16
Pan area Sq.m. -3 0.58 0.48 -0.84
Ladies urinal Sq.m. -6 0.43 0.35 -0.91

Total floor Tile Sq.m. 49.52


9.6 TILE LAYING ON TOILET
Wall Tile
Teacher's Toilet Male
Wall 600*200*200 Sq.m. 1 14.25 1.3 18.52
Wall 600*200*100 Sq.m. 1 3.7 1.3 4.81
Column Sq.m. 1 0.8 1.3 1.04

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB TOILET-1
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Teacher's Toilet Female
Wall 600*200*200 Sq.m. 1 14.35 1.3 18.65
Wall 600*200*100 Sq.m. 1 4.3 1.3 5.59
Column Sq.m. 1 0.8 1.3 1.04
Male Toilet
Wall 600*200*200 Sq.m. 1 16.6 1.3 21.58
Wall 600*200*100 Sq.m. 1 7.9 1.3 10.27
Column Sq.m. 1 0.8 1.3 1.04
Female Toilet
Wall 600*200*200 Sq.m. 1 16.6 1.3 21.58
Wall 600*200*100 Sq.m. 1 7.9 1.3 10.27
Column Sq.m. 1 0.8 1.3 1.04

Outer Water Trough


Slab Base Sq.m. 1 5.2 0.45 2.34
Outer Wall Sq.m. 1 6.1 0.25 1.52
Inner wall ( towards tap) Sq.m. 1 5.2 0.6 3.12
Inner Water Trough
Slab Base Sq.m. 2 3.3 0.6 3.96
Outer Wall Sq.m. 2 3.3 0.5 3.3
Base Support wall Sq.m. 4 0.85 0.6 2.04

Total Wall Tile Sq.m. 131.71


10 FINISHING WORK
10.1 EXTERNAL PLASTER
Walls Along grid A&B/1-3 Sq.m. 2 5.75 2.45 28.17
Walls Along grid 1&3/A-B Sq.m. 2 4.3 2.45 21.07
Columns Sq.m. 18 0.4 3 21.6

Steps riser Sq.m. 12 3.75 0.15 6.75


External Water Trough
Slab Wall perimeter Sq.m. 1 6.1 0.6 3.66
Support Brick Wall Sq.m. 4 1.13 0.3 1.356

Total Sq.m. 82.606


10.2 INTERNAL PLASTER
Walls along grid -1&3/A-B Sq.m. 2 4.5 2.175 19.57
Walls along grid 2/A-B both sides Sq.m. 1 12.4 2.55 31.62
Wallas along grid A&B/1-3 Sq.m. 2 5.45 2.175 23.7
Wall Between grid A&B/1-3 Sq.m. 2 15.6 3 93.6
Sq.m. 1 7.8 0.2 1.56
Internal walls in Teacher's Toilet Male
Wall 600*200*200 Sq.m. 1 3.1 2.1 6.51
Sq.m. 1 1.45 0.2 0.29
Wall 600*200*100 Sq.m. 1 3.7 2.1 7.77
Sq.m. 1 1.75 0.1 0.17
Column kopla Sq.m. 1 0.3 3 0.9
Internal Walls in Teacher's Toilet Female

Wall 600*200*200 Sq.m. 1 3.1 2.1 6.51


Sq.m. 1 1.45 0.2 0.29
Wall 600*200*100 Sq.m. 1 4.3 2.1 9.03
Sq.m. 1 2.05 0.1 0.2
Column kopla Sq.m. 1 0.3 3 0.9
Inside walls in Male Toilet
Wall 600*200*200 Sq.m. 1 3.1 2.1 6.51
Sq.m. 1 1.45 0.2 0.29
Wall 600*200*100 Sq.m. 1 7.9 2.1 16.59
Sq.m. 1 3.8 0.1 0.38
Column kopla Sq.m. 1 0.3 3 0.9
Inside walls in Female Toilet
Wall 600*200*200 Sq.m. 1 3.1 2.1 6.51
Sq.m. 1 1.45 0.2 0.29
Wall 600*200*100 Sq.m. 1 7.9 2.1 16.59
Sq.m. 1 3.8 0.1 0.38
Column kopla Sq.m. 1 0.3 3 0.9

Water trough (Two)


Perimeter wall Sq.m. 2 3.3 0.5 3.3
Slab bottom Sq.m. 2 3.3 0.6 3.96
Support wall Sq.m. 6 1.43 0.6 5.14

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB TOILET-1
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks

Total Internal Plaster Sq.m. 264.36


10.3 CEILING PLASTER
Ground Floor Beam
Along grid A&B/1-3 sides Sq.m. 2 14.4 0.4 11.52
Along grid A&B/1-3 bottom Sq.m. 2 7.2 0.23 3.31
Along grid 1,2,3/A-B Sides Sq.m. 3 12.8 0.45 17.28
Along grid 1&3/A-B bottom Sq.m. 2 6.4 0.23 2.94
Total Sq.m. 35.05

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB TOILET-1
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


10.4 PLASTER ON RCC LINTEL WITH
CORNICE
Along grid A& B/1-3 R.M. 2 5.75 11.5
Along grid 1&3/A-B R.M. 2 4.3 8.6
Total R.M. 20.1
10.5 EMULSION PAINT
Total internal plaster area Sq.m. 264.36
Total ceiling plaster area Sq.m. 35.05
Deductions
Wall tile area Sq.m. -131.71
Total Sq.m. 167.7
10.6 WEATHER COAT PAINT
Total External Plaster Sq.m. 1 82.606 82.606
Total RCC lintel with cornice Sq.m. 1 1.5075 1.5075
Cement Board Sq.m. 1 24 24

Total coating 108.1135


11.2 UPVC TOP HUNG WINDOWS
V2 Sq.m. 2 3.25 0.425 2.76
V3 Sq.m. 2 2.1 0.425 1.78
V4 Sq.m. 4 1.8 0.375 2.7
Total Sq.m. 7.24
11.4 UPVC SINGLE DOOR
D2 Sq.m. 4 0.9 2.1 7.56
D3 Sq.m. 9 0.75 2.1 14.17
Total Sq.m. 21.73
12 GROOFING WORK
12.1 CGI ROOFING SHEET
Sq.m. 2 9.6 4.404 84.55
Total Sq.m. 84.55
12.2 CGI ROOFING SHEET ON RIDGE
Rm 1 9.6 9.6
TOTAL Sq.m. 9.6
12.3 GI GUTTER:
RM 2 9.6 19.2

TOTAL RM. 19.2


15 METAL WORK
15.1 BLACK TUBULAR PIPE
Description of Work Total l Unit wt.
Bottom Chord NB 50(M) Kg. 4 6.8 27.2 5.03 136.81
Vertical Bracing NB 40(M) Kg. 8 0.385 3.08 3.56 10.96
Kg. 8 0.771 6.16 3.56 21.92
Kg. 4 1.156 4.62 3.56 16.44
Inclined Bracing NB 32(M) Kg. 8 1.09 8.72 3.09 26.94
Kg. 8 1.32 10.56 3.09 32.63
Inclined Bracing NB 40(M) in wind clit Kg. 32 1.088 34.81 3.56 123.92
Top Chord NB 50(M) Kg. 8 4.413 35.3 5.03 177.55
Purlin NB 50(M) Kg. 10 9.6 96 5.03 482.88
Runner NB 40(M) Kg. 3 8 24 3.56 85.44
Connections
Base Plate Volume
At column (300*300*10) Kg. 8 0.0009 7850 56.52
At beam(250*250*10) Kg. 8 0.000625 7850 39.25
Nut Kg. 32 0.00000826236 7850 2.07
16mm Dia anchord Bolt Kg. 32 0.45 14.4 1.58 22.75
Bottom Chord & Top Chord
ISA 135*40*5 (300mm width) Kg. 8 2 16
ISA 50*65*10 (300mm width) Kg. 16 2.47 39.52
10mm thick stiffner (50*77) Volume
Kg. 16 0.0000385 7850 4.83
Runner Plate Connection
At ends
175*68.3*10mm runner box Kg. 6 2.47 14.82
Volume
175*68.3*10mm runner plate Kg. 6 0.000119525 7850 5.62
2nos-16mm dia nut bolts Kg. 12 wt per pcs 0.16 1.92
At middle
175*68.3*10mm runner box Kg. 12 2.47 29.64
Volume

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB TOILET-1
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


175*68.3*10mm runner plate Kg. 12 0.000119525 7850 11.25
2nos-16mm dia nuts bolts Kg. 24 wt per pcs 0.16 3.84
Purlin Cleat Connection
Volume
Top Chord Cleat 200*90*10 Kg. 40 0.00018 7850 56.52
Purlin Cleat 200*85*10mm Kg. 80 0.00017 7850 106.76
2nos-16mm nuts bolts Kg. 80 wt per pcs 0.16 12.8
Truss Cleat for wind Ties
Volume
Wind Tie Cleat(100*100*6) Kg. 32 0.00006 7850 15.07
MS Flat 165*80*6 Kg. 64 0.0000792 7850 39.79
MS Flat 380*80*6mm Kg. 16 0.0001824 7850 22.9
20mm dia Nut bolts Kg. 32 wt. per pcs 0.21 6.72
16mm dia Nut nut bolts Kg. 32 wt. per pcs 0.16 5.12
Total Kg. 1629.2
23 Cement Board
Gap filling Sq.m. 2 8.4 0.6 10
Gable Wall Sq.m. 2 6.8 1.06 14
TOTAL Sq.m. 24

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST TOILET-1


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
GENERAL WORK, SITE CLEARANCE:Clearing and
grubbing of site for construction including uprooting of
1.1 vegetation, grass, brush wood, trees and sapplings of girth Sq.M 120.64 100.00 12,064.00
upto 300 mm & removal upto a distance of 50 m as per
drawings, specifications and instructions

EARTHWORK IN EXCAVATION: Earthwork in


2.1 excavation in trenches, pits and foundations by machine or Cu.M 51.95 200.00 10,390.00
appropriate technology in soft soil including existing debris
and brick bats of old structure, if any, upto specified depth
EARTWORK IN FILLING: Providing and placing of
random filling of excavated earth from cutting of slope and
stacked at site in 150mm thick layer in trenches, plinth or
under floor, sides of foundation and below beam at footing
2.2 Cu.M 32.34 200.00 6,468.00
covered area etc. including watering, mechanical ramming
and compaction of each layer, consolidation and dressing,
all complete as per drawings, specifications and instructions.

SAND FILLING: Sand filling in plinth under floors,


including watering, ramming, consolidating and dressing, all
2.3 complete as per drawings, specifications and instructions. Cu.M 0 2,500.00 -

STONE WORK : Dry stone soling work in line and level,


including packing joints with sand dust, all complete as per
3.1 drawings, specifications and instructions Cu.M 0 4,000.00 -

STONE MASONRY WALL: Stone rubble masonry work in


1:4 cement and sand mortar with hard, tough, sound and
durable stone in wall, made to required line, level, shape,
3.2 size and plumb including setting out, drain outlet, curing of Cu.M 0 7,500.00 -
the works and scaffolding etc. complete as per drawings,
specifications and instructions

BRICK WORK,FLAT BRICK SOLING: Flat brick soling


of local chimney bricks laid in line and level, including
4.1 packing joints with sand, complete as per drawings, Sq.M 88.1 800.00 70,480.00
specifications and instructions
FULL BRICK WORK: Brickwork in substructure and super
4.2 structure cement and sand mortar of mix 1:6 with first class Cu.M 15.67 15,000.00 235,050.00
chimney-made bricks, in any size and shape of wall, made
to required line, level, shape and plumb including setting
AAC(Autoclaved Aerated Concrete) BLOCK WORK:
5.1 Providing and laying of Autoclaved Aerated Concrete Block Sq.M 91.33 1,800.00 164,394.00
(600*200*200 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2)AAC(Autoclaved Aerated Concrete) BLOCK WORK:
Providing and laying of Autoclaved Aerated Concrete Block
(600*200*100 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2 required line, level, shape and plumb including setting out, Sq.M 22.22 2,000.00 44,440.00
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

5.3)AAC(Autoclaved Aerated Concrete) BLOCK WORK:


Providing and laying of Autoclaved Aerated Concrete Block
(600*200*150 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.3 required line, level, shape and plumb including setting out, Sq.M 0 1,100.00 -
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

CONCRETE WORK,PCC OF GRADE M10: Plain cement


concrete (PCC) of grade M10 (1:3:6 with 1 cement, 3 coarse
sand and 6 aggregate of 19 mm and down grade) in
6.1 foundation base including mixing, laying, compacting, Cu.M 6.73 10,000.00 67,300.00
finishing, curing, laid to exact line, level and dimensions,
inclusive ofside

PCC FOR RCC OF GRADE M25: Structural concrete (PCC


for RCC) of Grade M25 (1:1:2)works with approved
quality of cement, sand and well graded aggregate in any
form, size, shape and level including batching and mixing
6.2 with machine, laying including compaction with vibrating Cu.M 4.94 20,000.00 98,800.00
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

PCC FOR RCC OF GRADE M20: Structural concrete (PCC


for RCC) of Grade M20 (1:1.5:3)works with approved
quality of cement, sand and well graded aggregate in any
6.3 form, size, shape and level including batching and mixing Cu.M 14.62 17,000.00 248,540.00
with machine, laying including compaction with vibrating
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

FORMWORK: Placing plyboard form work with steel


props, shuttering, centering in horizontal/Vertical surfaces
like slab, beams, column, wall, stair etc. for all RCC works
7.1 of any shape, size and at any level and removal after Sq.M 163.45 850.00 138,932.50
completion

REINFORCEMENT WORK: Providing and placing steel


reinforcement bar tested grade Fe-500 equivalent NS, for
8.1 RCC work including bending, binding with anneal wire and kg 3401.19 110.00 374,130.90
placing in position, all complete as per drawings,
specifications and instruction

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST TOILET-1


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
9.1)FLOORING WORK,PLASTIC
9.1 LAYING: Supplying and laying 500 gauge plastic sheet in Sq.M 0 50.00 -
floor as per specificatio and instruction
9.2)SCREEDING: Providing and placing 38 mm thick Plain
cement concrete of grade M15 (1:2:4 with 1 cement, 2
coarse sand and 4 aggregate chips) in the floor base mixing,
laying, compacting, finishing, curing, laid to exact line level
9.2 , surface chipping and dimensions (floor concrete is laid in Sq.M 67.37 500.00 33,685.00
alternate panels of 1 m x 1 m) inclusive of shuttering
complete as per drawings, specifications and instructions

9.3)CEMENT PUNNING: Providing


and laying 3 mm cement punning in floor , laying in
9.3 Sq.M 15.75 200.00 3,150.00
required pattern, line

9.4)CEMENT SKIRTING: Providing


and placing cement skirting 125mm height of grade M15
(1:2:4 with cement, 2 coarse sand and 4 aggregate
) in wall ,mixing, laying, compactig, finishing, curing, laid
9.4 to exact line level and dimension all complete as per R.M 0 100.00 -
drawing, specification and instructions

9.5)TILE LAYING ON FLOOR:


Providing and laying approved brand quality, pattern and
color, ceramic mat finish tile (Low range) on floor over
9.5 cement mortar of mix 1:3 backing and filling joints (epoxy Sq.M 49.52 2,800.00 138,656.00
grout) complete as per drawings, specifications and
instructions.(Base rate: NRs 100)

9.6)TILE LAYING ON TOILET:


Providing and laying approved brand quality, pattern and
color, ceramic glazed tile in wall and ceramic mat finish tile
9.6 (Low range) on floor of toilet over cement mortar of mix 1:3 Sq.M 131.71 3,000.00 395,130.00
backing and filling joints (epoxy grout) complete as per
drawings, specifications and instructions.(Base rate: NRs
100)

10.1)FINISHING WORK,
EXTERNAL PLASTER: Providing and applying '10.5 mm
thick cement plastering with 1cement : 4 sand mortar in
outer surface any level size and shape of wall, column,
10.1 ceiling, band, blocks, etc inclusive of waterproofing Sq.M 82.606 400.00 33,042.40
compound, dusting, throating, etc as required including
racking, hacking, watering, cleaning of base, plastering to
plumb, line, level, smooth etc. and curing complete as per
drawings, specifications and instructions.
10.2)INTERNAL PLASTER:
Providing and applying'10.5 mm thick cement plastering
with 1cement : 4 sand mortar in inner surface except ceiling
any level size and shape of wall, column, band, blocks, etc
inclusive of dusting, throating, etc as required including
10.2 racking, watering, hacking, cleaning of base, plastering to Sq.M 264.36 450.00 118,962.00
plumb, line, level, smooth etc. and curing, all complete as
per drawings, specifications and instructions.

10.3)CEILING PLASTER: Providing


and applying 12.5 mm thick cement plastering with 1cement
10.3 : 4 sand mortar in Ceiling any level size and shape of Sq.M 35.05 500.00 17,525.00
ceiling inclusive of dusting,
10.4)PLASTER ON RCC LINTEL
WITH CORNICE: 'Providing and applying 12.5 mm thick
cement plastering with 1cement : 4 sand mortar in RCC
Lintel with cornice inclusive of dusting, throating, etc as
required including racking, watering, cleaning of base,
10.4 plastering to plumb, line, level, smooth etc. and curing, all R.M 20.1 3,000.00 60,300.00
complete as per drawings, specifications and instructions.

10.5)EMULSION PAINT: Providing


and applyibg two coat of emulsion paint in mat finishing
10.5 over two coat of primer, finished including surface Sq.M 167.7 200.00 33,540.00
preparation all complete as per drawings, specifications and
instruction
10.6)WEATHER COAT: Providing and applying two coat
of weather coat (Apex or equivalent) over required coat of
10.6 primer, finished including surface preparation all complete Sq.M 108.1135 250.00 27,028.37
as per drawings, specifications and instruction

11.1)DOOR,WINDOWS WORK/UPVC SLIDING


WINDOWS: Providing and fixing standard UPVC sliding
window without net (frame 50x80mm, sash 58x36mm white
11.1 colour with 5mm glass) along with patented standard Sq.M 0 8,000.00 -
hardwares like roller, gaskets, brush seal, moon locks etc all
complete as per drawings and specifications.

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST TOILET-1


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
11.2)UPVC TOP HUNG
WINDOWS: Providing and fixing standard UPVC top hung
window (frame 60x60 mm, sash 60x104 mm, white colour
11.2 with 5 mm glass) along with patented standard hardwares Sq.M 7.24 8,000.00 57,920.00
like roller, gaskets, brush seal, moon locks etc all complete
as per drawings and specifications.

11.3)UPVC DOUBLE DOOR:


Providing and fixing standard UPVC double door (frame
60x60mm, sash 60x104mm white colour with 5mm glass)
11.3 along with patented standard hardwares like roller, gaskets, Sq.M 0 10,000.00 -
brush seal, moon locks etc all complete as per drawings and
specifications.

11.4)UPVC SINGLE DOOR:


Providing and fixing standard UPVC single door with full
panel (frame60x60mm, sash 60x104mm white colour with
11.4 5mm glass) along with patented standard hardwares like Sq.M 21.73 7,000.00 152,110.00
roller, gaskets, brush seal, moon locks etc all complete as
per drawings and specifications.

12.1)ROOFING WORK,CGI
ROOFING SHEET: Providing and fixing in position 24
gauge medium (0 .5 mm thick) corrugated CGI sheet over
12.1 roof truss with minimum 80 mm side laps and 200 mm end Sq.M 84.55 1,319.17 111,535.82
laps, inclusive of nuts and bolts, 8 mm 'J' hooks, washers,
GI cup washers, all complete as per drawings, specifications
and instruction

12.2)CGI ROOFING SHEET ON


RIDGE: Providing and fixing in position 24 gauge medium
(0 .5 mm thick) CGI sheet over roof truss in ridge with
12.2 minimum 80 mm side laps and 200 mm end laps, inclusive R.m 9.6 1,009.52 9,691.39
of nuts and bolts, washers, GI cup washers, all complete as
per drawings, specifications and instruction

12.3)GI GUTTER: providing and fixing in position color


plain GI sheet for gutter 150mmX450mm, inclusive of nuts
12.3 and bolts, washers, all complete as per drawings, R.m 19.2 1,000.00 19,200.00
specifications and instruction.
13.1)FALSE CEILING WORK,PVC
BOARD: Providing and fixing suspended PVC board false
ceiling, with necessary provisions for light fittings, light
13.1 boxes, where required finally finished with two coat acrylic Sq.M 0 1,500.00 -
emulsion paint, all complete as per drawings, specifications
and instructions.

14.1)MISCELLANEOUS WORK,
WATER PROOFING: Providing and placing 20 mm thick
cement sand mortar (1:2) mixing with wate proof
14.1 compound in the floor base mixing, laying, compacting, Sq.M 0 400.00 -
finishing, curing, laid to exact line level and dimensions
complete as per drawings, specifications and instructions

14.2)INSULATION WORK:
Providing and installing Insulation under CGI roofing sheet
14.2 with Insulation shield of 12mm thickness one sided and Sq.m 0 200.00 -
chicken wire mesh all completeas per drawing and
specifications.
15.1)METAL WORKS,BLACK
15.1 TUBULAR PIPE: Supplying, fabricating and fixing black Kg 1629.2 150.00 244,380.00
pipe (Square or circular) work /Truss with
15.2)MS PIPE: Supplying, fabricating and fixing metal
15.2 work of different angles MS Pipe with one coat primer as Kg 0 150.00 -
shown in drawing all complete
15.3)ROLLING SHUTTER:
Providing and fixing rolling shutterof 16-19 Gauge cold
rolled MS lathe interlocked throughout their entire length
and joined together at the end by end locks and mounted on
specially designed pipe shaft with brackets, side guides and
15.3 arrangements for inside and outside locking,with push and Sq.m 0 4,000.00 -
pull operation, complete supplying, fixing and painting with
two coats of approved plastic emulsion paint.

15.4)HOT ROLLED STEEL


SECTION: Supplying, fabricating and fixing metal work of
15.4 different Hot Rolled Steel sections with one coat primer as Kg 0 150.00 -
per drawings and specifications all complete

15.5)METAL WORK,METAL
GATE: Supplying, fabricating and fixing in position, metal
gates of standard sections consisting of angles, pipes,
15.5 flats,etc. including one coat primer and one coat enamel Sq.M 0 7,000.00 -
paint as per drawings, specifications and instructions all
complete

15.6)FENCING WORK: Providing and fixing of ISA


50x50x5 mm along with 25x25x5 flat and M8x40 bolts at
12.3 300mm spacing to fix 10 S.W.G.G.I chain link with hole R.M 0 2,200.00 -
size 60x60 mm upto 3m height and 3 lines of barbed wire at
top.

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST TOILET-1


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
16.1)EXPANSION JOINT WORKS/PLINTH LEVEL:
Suuply
and fixing of expansion joint at level of 100% non porous
flexible element allowing movement in all directions,
16.1 supported by aluminium framing and covering the top by R.M 0 4,500.00 -
aluminium sheet and flused to required floor level all
complete as per drawing, specification and instruction.

16.2)EXPANSION JOINT
WORKS/SLAB: Supply and fixing of expansion joint at
floor level of aluminium base supported by alumunium
16.2 framing,fixed on one side by threaded screw and flushed to R.M 0 4,500.00 -
required floor level and dimension all complete as per
drawing,specification and instruction

16.3)EXPANSION JOINT WORKS/ENDS OF WALL:


16.3 Supply R.M 0 4,500.00 -
17.1)CHAIN LINK VENTILATION
WORK: Supplying, fabricating and fixing in position of 10
S.W.G.I. woven wire ventilation with hollow square pipe
framing of size 18x18x1.0 mm on all sides with proper
17.1 welding on site, including one coat primer and one coat Sq.M 0 4,000.00 -
enamel paint on frames as per drawings, specifications and
instructions all complete

18.1)LAND DEVELOPMENT WORKS, INTERLOCKING


BLOCKS: Supplying and laying of 60 mm thick heavy duty
interlocking paving blocks of approved colour and quality
on the 50 mm thick stone dust with surface grading,
18.1 levelling and soil compaction base in driveways and parking Sq.M 0 2,000.00 -
areas, complete as per specifications and drawings.

18.2)RAILING WORKS: Supply,


fabrication and fitting of Railing works with MS square pipe
framing and 10 S.W.G.I. wire mesh of height 1.05m
18.2 including excavation, brickwork, plaster and two coats R.M 0 3,000.00 -
enamel paint all complete as per drawings and specifications

18.3)GUIDE RAMP: Supply,


fabrication and fitting of Guide Ramp-Utility Guardrail for
the disabled with MS tubular pipes at regular intervals of
18.3 height 1.05m including two coats enamel paint all complete R.M 0 6,500.00 -
as per drawings and specifications

18.4)APRON DRAIN: Construction of Apron drain along


the perimeter of buildings and retaining structures including
18.4 excavation, Brick soling, PCC and half brick thick apron R.M 0 20,000.00 -
walls with plaster all complete as per drawings and
specifications
18.5)TACTILE PAVING: Providing
and laying approved brand quality, pattern and colour of
Tactile paving tile on floor over constructed cement mortar
18.5 of mix 1:3 backing and filling joints (epoxy grout) at R.M 0 3,500.00 -
straight path and turning points of size 300x300x40mm, all
complete as per drawings, specifications and instructions.

DEMOLITION WOKS: Demolition of existing building


19.1 and toilet blocks PS 1,000,000.00 -

RELOCATION WOKS: Relocation of temple from existing


site and to be constructed at a new location outside of the
20.1 school site as per drawing,specification and instructions. PS 300,000.00 -

INSURANCE PREMIUM
21.1 PS 224,281.00 -

Floor Hardener:providing,sprinkling,laying &applying


Manually two layer in floor,applied each layer with 1.5 to
2.5kg /m2 in required pattern,blended in,smoothed,over by
22.1 power trowelling,in line and level including curing all Sq.M 400.00 -
complete as per drawing,specification and instruction.
(Mapetop,N,AR6 or equivalent)

Cement Board:providing and fixing in position 10mm


water proofed cement board in exterior (one side)surface
inclusive minimum75mm GI metal framewith grooving and
23.1 fixing of fastner ,washer,nuts,and bolts,all complete as per Sq.M 24 2,700.00 64,800.00
drawings,specifications and instructions.

FLOOR TILE (600*600)


24 Sq.M 2,500.00 -

ENAMEL PAINT
25 Sq.M 0 286.00 -

PILE WORK : Construction of pile work including


26 excavation, reinforcement and concreting work. Rm. 17,000.00 -

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST TOILET-1


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
DISMANTLING WORK
27 -

CONCRETE DISMANTLING
27.1 Cu.M 8,500.00 -

BRICKWALL DISMANTLING
27.2 Cu.M 2,000.00 -

TOTAL CIVIL WORKS -

TOTAL AMOUNT
2,991,645.38

Total Item Price 2,991,645.38

Discount @2% 59,832.91

Sub Total 2,931,812.47

VAT @13% 381,135.62

Grand Total 3,312,948.09

Prepared By: Checked By: Verified By:


MB PRIMARY BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB TOILET-2
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


1.1 GENERAL WORK, SITE CLEARANCE Sq.M 1 15.8 13.1 206.98
2.1 EARTHWORK IN EXCAVATION
Ground Cutting Cu.m. 1 13.8 11.1 3.9 597.4

TOTAL EARTHWORK IN Cu.m.


EXCAVATION 597.4
2.2 EARTHWORK IN FILLING

Inside Room Cu.m. 2 3.585 4.7 1.875 63.18


Between Toilet-2 & middle block Cu.m. 1 8 2.6 5.45 113.36
Total Back Filling Cu.m. 176.54
2.3 SAND FILLING
CRUSHED STONE DUST
For Isolated Footing F1 Cu.m. 6 1.5 1.5 0.075 1.01
Inside Room Cu.m. 1 6.94 4.47 0.1 3.1

Total Sand Filling Cu.m. 0

Prepared By: Checked By: Verified By:


MB PRIMARY BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB TOILET-2
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


3.1 STONE WORK
DRY STONE SOLING
Left Side Wall cum 1 2.75 1.3 0.2 0.71
Right side wall cum 1 2.5 1.3 0.2 0.65
In front of septic tank cum 1 3.1 1.3 0.2 0.8

Total Dry Stone Soling Cu.m. 2.16


3.2 STONE WORK
STONE MASONRY WALL c/s
Left Side Wall cum 1 2.75 2.175 5.98
Right side wall cum 1 2.5 2.175 5.43
In front of septic tank cum 1 3.1 1.8125 5.61

Total Dry Stone Soling Cu.m. 17.02


4 BRICK WORK
4.1 FLAT BRICK SOLING
FOOTINGS
F1 Sq.m. 6 1.5 1.5 13.5
LOWER TIE BEAM
Bottom tie beam along grid A,B,C Sq.m. 3 4.3 0.23 2.96
Along grid 1,2 Sq.m. 2 6.6 0.23 3.03
Inside Room Sq.m. 1 6.94 4.47 31.02
Inceneration Sq.m. 1 1.2 1.05 1.26
To raise pan level height
Ground floor Sq.m. 4 1 1.45 5.8 Inside toilet
2 1.2 1.45 3.48
First Floor Sq.m. 1 4.7 7.8 36.66 Inside toilet
Sq.m. -1 2.5 2.4 -6
Between Toilet & Middle Block Sq.m. 1 9 2.6 23.4

TOTAL FLAT BRICK SOLING Sq.m. 115.11


4.2 FULL BRICK WORK
From lower tie beam to upper tie beam
Along gridA, B &C Cu.m. 3 4.3 0.23 1.5 4.45
Along grid 1,2 Cu.m. 2 6.6 0.23 1.5 4.55
Inceneration Cu.m. 1 2.4 0.23 1.1 0.6

Truss Beam level Cu.m. 2 7.8 0.23 0.3 1.07


For Urinal Flow 0
Ground floor Cu.m. 1 11.525 0.15 0.15 0.25
At Door level Cu.m.
Ground floor Cu.m. 6 0.75 0.15 0.15 0.1
Cu.m. 1 0.9 0.15 0.15 0.02
First floor Cu.m. 7 0.75 0.15 0.4 0.31
Cu.m. 2 0.9 0.15 0.15 0.04
Above Stone masonry wall Cu.m. 1 2.5 0.23 0.9 0.51

TOTAL FULL BRICK WORK Cu.m. 11.9


5 AAC BLOCK
5.1 AAC BLOCK (600*200*200)
GROUND FLOOR
ALONG GRID A Sq.m 1 4.3 2.4 10.32
ALONG GRID C Sq.m 1 4.3 2.4 10.32
Internal grid Sq.m 1 2.4 2.025 4.86
Along grid 2 Sq.m 1 6.6 2.4 15.84
Deduction Sq.m
D2 Sq.m -1 0.9 2.025 -1.83
V9 Sq.m -2 3.3 0.425 -2.81
V10 Sq.m -1 4.3 0.375 -1.62
FIRST FLOOR Sq.m 0
Along grid A Sq.m 1 4.3 2.62 11.26
Along grid C Sq.m 1 2.1 2.62 5.5
Sq.m 1 2.2 0.975 2.14
Along grid 1 Sq.m 1 4.3 2.62 11.26
Along grid 2 Sq.m 1 6.6 2.62 17.29
Internal wall Sq.m 1 1.6 2.025 3.24
Sq.m 1 3.8 2.025 7.69
Deduction 0
V9 Sq.m -3 3.3 0.425 -4.21
V10 Sq.m -1 4.3 0.375 -1.62

TOTAL Sq.m. 87.63


5.2 AAC BLOCK(600*200*100)

Prepared By: Checked By: Verified By:


MB PRIMARY BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB TOILET-2
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Ground Floor
Along X Axis Sq.m 1 7.25 2.025 14.68
Along Y axis Sq.m 1 2.7 2.025 5.46
First Floor
Along X Axis Sq.m 1 8.7 2.025 17.61
Along Y axis Sq.m 1 2.35 2.025 4.75
Sq.m 0
TOTAL Sq.m. 42.5
5.3 AAC BLOCK(600*200*150)

Total Sq.m. 0
6 CONCRETE WORK
6.1 PCC of grade M10
FOOTINGS
F1 Cu.m. 6 1.5 1.5 0.075 1.01
LOWER TIE BEAM
Bottom tie beam along grid A,B,C Cu.m. 3 4.3 0.23 0.075 0.22
Along grid 1,2 Cu.m. 2 6.6 0.23 0.075 0.22
Inside Room
Ground floor Cu.m. 1 6.94 4.47 0.075 2.32
Inceneration Cu.m. 1 1.2 1.05 0.075 0.09
To raise pan level height Cu.m.
Ground floor Cu.m. 4 1 1.45 0.075 0.43 Inside toilet
Cu.m. 2 1.2 1.45 0.075 0.26
First Floor Cu.m. 1 4.7 7.8 0.075 2.74 Inside toilet
Cu.m. -1 2.5 2.4 0.075 -0.45
Between Toilet & Middle Block Cu.m. 1 9 2.6 0.075 1.75

Stone Masonry wall


Lest Side Wall cum 1 2.75 1.3 0.075 0.26
cum 1 2.75 0.45 0.075 0.09
Right side wall cum 1 2.5 1.3 0.075 0.24
cum 1 2.5 0.45 0.075 0.08
In front of septic tank cum 1 3.1 1.3 0.075 0.3
cum 1 3.1 0.45 0.075 0.1

TOTAL Cu.m. 9.66


6.2 PCC for RCC of Grade M25
Pile Cap Cu.m. 6 1.5 1.5 0.35 4.72
Column upto plinth level Cu.m. 6 0.4 0.4 2.1 2.01
Column above plinth lvl Cu.m. 6 0.4 0.4 6 5.76
Shear Wall Cu.m. 2 3.3 0.2 2.6 3.43

TOTAL Cu.m. 15.92


6.3 PCC for RCC of Grade M20
Foundation Tie Beam
Along grid 1,2 Cu.m. 2 6.6 0.23 0.3 0.91
Along grid A,B,C Cu.m. 3 4.3 0.23 0.3 0.89
Plinth Beam
Along grid 1,2 Cu.m. 2 6.6 0.23 0.4 1.21
Along grid A,B,C Cu.m. 3 4.3 0.23 0.45 1.33
Ground Floor Beam
Along grid 1,2 Cu.m. 2 6.6 0.23 0.275 0.83
Along grid A,B,C Cu.m. 3 4.3 0.23 0.325 0.96
First Floor Beam
Along grid 1,2 Cu.m. 2 6.6 0.23 0.23 0.69
Along grid A,B,C Cu.m. 3 4.3 0.23 0.23 0.68
First Floor Slab
Cu.m. 1 8.8 5.1 0.125 5.61
Deduction of column Cu.m. -6 0.4 0.4 0.125 -0.12
Sill Band
600*200*200 wall
Ground Floor
ALONG GRID A Cu.m. 1 3.4 0.2 0.075 0.05
ALONG GRID C Cu.m. 1 4.3 0.2 0.075 0.06
Internal grid Cu.m. 1 2.4 0.2 0.075 0.03
Along grid 2 Cu.m. 1 6.6 0.2 0.075 0.09
FIRST FLOOR
Along grid A Cu.m. 1 4.3 0.2 0.075 0.06
Along grid C Cu.m. 1 2.1 0.2 0.075 0.03
Cu.m. 1 2.2 0.2 0.075 0.03
Along grid 1 Cu.m. 1 4.3 0.2 0.075 0.06
Along grid 2 Cu.m. 1 6.6 0.2 0.075 0.09

Prepared By: Checked By: Verified By:


MB PRIMARY BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB TOILET-2
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Internal wall Cu.m. 1 1.6 0.2 0.075 0.02
600*200*100 wall
Ground Floor
Along X Axis Cu.m. 1 7.25 0.1 0.075 0.05
Along Y axis Cu.m. 1 2.7 0.1 0.075 0.02
First Floor
Along X Axis Cu.m. 1 8.7 0.1 0.075 0.06
Along Y axis Cu.m. 1 2.35 0.1 0.075 0.01
Lintel Band
600*200*200 wall
Ground Floor
ALONG GRID A Cu.m. 1 4.3 0.275 0.075 0.08
ALONG GRID C Cu.m. 1 4.3 0.275 0.075 0.08
Internal grid Cu.m. 1 2.4 0.2 0.075 0.03
Along grid 2 Cu.m. 1 6.6 0.275 0.075 0.13
FIRST FLOOR
Along grid A Cu.m. 1 4.3 0.275 0.075 0.08
Along grid C Cu.m. 1 2.1 0.275 0.075 0.04
Cu.m. 1 2.2 0.2 0.075 0.03
Along grid 1 Cu.m. 1 4.3 0.2 0.075 0.06
Along grid 2 Cu.m. 1 6.6 0.275 0.075 0.13
Internal wall Cu.m. 1 1.6 0.2 0.075 0.02
Cu.m.
Inceneration Cu.m. 1 0.9 0.75 0.075 0.05 Top Slab
Cu.m. 1 2.4 0.23 0.075 0.04 Band

TOTAL Cu.m. 14.42


7.1 FORM WORK
Formwork for Footing
F1 Sq.m. 6 6 0.35 12.6
Foundation Tie Beam
Along grid 1,2 Sq.m. 2 6.6 0.6 7.92
Along grid A,B,C Sq.m. 3 4.3 0.6 7.74
Plinth Beam
Along grid 1,2 Sq.m. 2 6.6 0.8 10.56
Along grid A,B,C Sq.m. 3 4.3 0.9 11.61
Ground Floor Beam
Along grid 1,2 Sq.m. 2 6.6 0.55 7.26
Along grid A,B,C Sq.m. 3 4.3 0.65 8.38
First Floor Beam
Along grid 1,2 Sq.m. 2 6.6 0.69 9.1
Along grid A,B,C Sq.m. 3 4.3 0.69 8.9
First Floor Slab
Sq.m. 1 8.8 5.1 44.88
Deduction of column Sq.m. -6 0.4 0.4 -0.96
Slab Perimeter Sq.m. 1 27.8 0.125 3.47

Shear Wall Sq.m. 1 13.2 2.6 34.32


Sq.m.
Column upto plinth level Sq.m. 6 1.6 2.1 20.16
Column above plinth lvl Sq.m. 6 1.6 6 57.6
Deductions of beam faces 0
Foundation tie beam Sq.m. -14 0.23 0.3 -0.97
Plinth Beam Sq.m. -8 0.23 0.4 -0.74
Sq.m. -6 0.23 0.45 -0.63
Ground floor beam Sq.m. -8 0.23 0.4 -0.74
Sq.m. -6 0.23 0.45 -0.63
First floor beam Sq.m. -14 0.23 0.23 -0.75

Sill Band
600*200*200 wall
Ground Floor

Prepared By: Checked By: Verified By:


MB PRIMARY BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB TOILET-2
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


ALONG GRID A Sq.m. 1 3.4 0.15 0.51
ALONG GRID C Sq.m. 1 4.3 0.15 0.64
Internal grid Sq.m. 1 2.4 0.15 0.36
Along grid 2 Sq.m. 1 6.6 0.15 0.99
FIRST FLOOR
Along grid A Sq.m. 1 4.3 0.15 0.64
Along grid C Sq.m. 1 2.1 0.15 0.31
Sq.m. 1 2.2 0.15 0.33
Along grid 1 Sq.m. 1 4.3 0.15 0.64
Along grid 2 Sq.m. 1 6.6 0.15 0.99
Internal wall Sq.m. 1 1.6 0.15 0.24
600*200*100 wall
Ground Floor
Along X Axis Sq.m. 1 7.25 0.15 1.08
Along Y axis Sq.m. 1 2.7 0.15 0.4
First Floor
Along X Axis Sq.m. 1 8.7 0.15 1.3
Along Y axis Sq.m. 1 2.35 0.15 0.35
Lintel Band
600*200*200 wall
Ground Floor
ALONG GRID A Sq.m. 1 4.3 0.15 0.64
ALONG GRID C Sq.m. 1 4.3 0.15 0.64
Internal grid Sq.m. 1 2.4 0.15 0.36
Along grid 2 Sq.m. 1 6.6 0.15 0.99
FIRST FLOOR
Along grid A Sq.m. 1 4.3 0.15 0.64
Along grid C Sq.m. 1 2.1 0.15 0.31
Sq.m. 1 2.2 0.15 0.33
Along grid 1 Sq.m. 1 4.3 0.15 0.64
Along grid 2 Sq.m. 1 6.6 0.15 0.99
Internal wall Sq.m. 1 1.6 0.15 0.24

TOTAL Sq.m. 253.64


8.1 Reinforcement Work
From BBS kg 1 6428.15

Total kg 6428.15
9.1 PLASTIC LAYING
Ground Floor Sq.m. 1 6.94 4.47 31.02

Total Sq.m. 0
9.2 SCREEDING
Ground Floor Sq.m. 1 7.4 4.7 34.78
First Floor Sq.m. 1 7.4 4.7 34.78

Total Sqm. 69.56


9.3 CEMENT PUNNING

Total Sqm. 0
9.4 CEMENT SKIRTING
Ground floor entry rm 1 5.1 5.1
First Floor Slab top rm 1 5.1 5.1
First floor north side rm 1 5.1 5.1
rm
Total rm 15.3
9.5 TILE LAYING ON FLOOR
Floor Tile
Ground floor Sq.m. 1 7.4 4.7 34.78
Deduction of internal wall Sq.m. -1 2.4 0.2 -0.48
Sq.m. -1 9.5 0.1 -0.95
0
First Floor Sq.m. 1 7.4 4.7 34.78
Deduction of internal wall Sq.m. -1 5.4 0.2 -1.08
Sq.m. -1 10.85 0.1 -1.09

Total Sq.m. 65.96


9.6 TILE LAYING ON TOILET WALL
Ground Floor
Along grid 1 & 2 Sq.m. 2 7.4 1.3 19.24
Along grid A & C Sq.m. 2 4.7 1.3 12.22
Internal Wall

Prepared By: Checked By: Verified By:


MB PRIMARY BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB TOILET-2
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


600*200*200 wall Sq.m. 1 4.8 1.3 6.24
600*200*100 wall
X Axis Sq.m. 1 14.5 1.3 18.85
Y Axis Sq.m. 1 5.4 1.3 7.02
First Floor
Along grid 1 Sq.m. 1 5.5 1.3 7.15
Along grid 2 Sq.m. 1 7.6 1.3 9.88
Along grid A Sq.m. 1 4.7 1.3 6.11
Along grid C Sq.m. 1 2.3 1.3 2.99
Sq.m. 1 2.6 1.25 3.25
Internal Wall
600*200*200 wall Sq.m. 1 11.2 1.3 14.56
600*200*100 wall
Along X Axis Sq.m. 1 17.4 1.3 22.62
Along Y axis Sq.m. 1 4.7 1.3 6.11

Total Sq.m. 136.24


10 FINISHING WORK
10.1 EXTERNAL PLASTER
Along grid A & C Sq.m. 2 5.1 6.45 65.79
Along grid 2 Sq.m. 1 7.8 6.65 51.87
Along grid 1 Sq.m. 1 7.8 3.65 28.47
Deductions Sq.m. -1 2.3 2.77 -6.38
Sq.m. -1 2.2 1.72 -3.79
D2 Sq.m. -1 0.9 2.1 -0.95
V9 Sq.m. -5 3.3 0.425 -3.51
V10 Sq.m. -2 4.3 0.375 -1.62

Projection Slab Sq.m. 1 5.1 1 2.55


Between Toilet-2 & middle block Sq.m. 1 9 2.6 11.7
Inceneration Sq.m. 2 0.75 1.175 1.76
Sq.m. 1 0.9 1.175 1.05
Total Sq.m. 146.94
10.2 INTERNAL PLASTER
Ground Floor
Along grid 1 & 2 Sq.m. 2 7.4 2.875 42.55
Along grid A & C Sq.m. 2 4.7 2.875 27.02
Internal Walls
600*200*200 wall Sq.m. 1 4.8 2.2 10.56
600*200*100 wall
X Axis Sq.m. 1 14.5 2.15 31.17
Y Axis Sq.m. 1 5.4 2.15 11.61
Deductions
D2 Sq.m. -1 0.9 2.1 -0.95
V9 Sq.m. -2 3.3 0.425 -1.41
V10 Sq.m. -1 4.3 0.375 -0.81
First Floor
Along grid 1 Sq.m. 1 5.1 3 15.3
Along grid 2 Sq.m. 1 7.4 3 22.2
Along grid A Sq.m. 1 4.7 3 14.1
Along grid B Sq.m. 1 2.3 3 6.9
Sq.m. 1 2.2 1.25 2.75
Internal Wall 0
600*200*200 wall Sq.m. 1 11.2 2.2 24.64
600*200*100 wall
Along X Axis Sq.m. 1 17.4 2.15 37.41
Along Y axis Sq.m. 1 4.7 2.15 10.1
Deductions Sq.m. 0
V9 Sq.m. -3 3.3 0.425 -2.11
V10 Sq.m. -1 4.3 0.375 -0.81

Total Sq.m. 250.22


10.3 CEILING PLASTER

Ground floor Sq.m. 1 8.8 5.1 44.88


First Floor beam
Along grid 1 Sq.m. 1 2.3 0.23 0.52
Along grid 2 Sq.m. 1 6.6 0.23 1.51
Along grid A & B Sq.m. 2 4.3 0.23 1.97
Along grid C Sq.m. 1 2.2 0.23 0.5

Total Sq.m. 49.38


10.4 PLASTER ON RCC LINTEL WITH
CORNICE

Prepared By: Checked By: Verified By:


MB PRIMARY BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB TOILET-2
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Total R.M.
10.5 EMULSION PAINT
Total internal plaster area Sq.m. 250.22
Total ceiling plaster area Sq.m. 49.38
Deductions
Wall tile area Sq.m. -136.24
Total Sq.m. 163.36
10.6 WEATHERCOAT PAINT
Total external plaster area Sq.m. 146.94
Gable Wall Sq.m. 2 5.1 1.07 5.45

Total Sq.m. 152.39

Prepared By: Checked By: Verified By:


MB PRIMARY BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB TOILET-2
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


11 DOOR, WINDOWS WORK
11.1 UPVC SLIDING WINDOWS

Total Sq.m. 0
11.2 UPVC TOP HUNG WINDOWS
V9 Sq.m. 5 3.3 0.425 7.01
V10 Sq.m. 2 4.3 0.375 3.22
Total Sq.m. 10.23
11.3 UPVC DOUBLE DOOR
D4 Sq.m. 1 0.9 2.1 1.89

Total Sq.m. 1.89


11.4 UPVC SINGLE DOOR
GROUND FLOOR
D2 Sq.m. 1 0.9 2.1 1.89
D3 Sq.m. 6 0.75 2.1 9.45
SECOND FLOOR
D2 Sq.m. 1 0.9 2.1 1.89
D6 Sq.m. 7 0.75 1.95 10.23
Total Sq.m. 23.46
12 ROOFING WORK
12.1 CGI ROOFING SHEET
Sq.m. 2 9 3.34 60.12
Total Sq.m. 60.12
12.2 CGI ROOFING SHEET ON RIDGE
Rm. 1 9 9
TOTAL Rm. 9
12.3 GI GUTTER
Rm. 2 9 18
TOTAL Sq.m. 18
13.1 FLASE CEILING WORK PVC BOARD

Total Sq.m. 0
14 MISCELLANEOUS WORK
14.1 WATER PROOFING WORK
Shear Wall Sq.m. 1 8.6 2.875 24.725

Total Sq.m. 24.725


14.2 INSULATION WORK

Total Sq.m. 0
15 METAL WORK
15.1 BLACK TUBULAR PIPE
Description of Work Total l Unit wt.
Bottom Chord NB 50(M) Kg. 3 5.1 15.3 5.03 76.95
Vertical Bracing NB 40(M) Kg. 6 0.505 3.03 3.56 10.78
Kg. 3 0.873 2.61 3.56 9.29
Inclined Bracing NB 32(M) Kg. 6 1.138 6.82 3.09 21.07
Inclined Bracing NB 40(M) (wind clit) Kg. 6 3.336 20.01 3.56 71.23
Top Chord NB 50(M) Kg. 6 3.337 20.02 5.03 100.7
Purlin NB 50(M)
Grid 1-2 Kg. 8 9 72 5.03 362.16
Runner NB 40(M)
Grid 1-2 Kg. 2 7.8 15.6 3.56 55.53
Connections
Base Plate Volume
At column (300*300*10) Kg. 12 0.0009 7850 84.78
Nut Kg. 24 0.00000826236 7850 1.55
16mm Dia anchord Bolt Kg. 24 0.45 10.8 1.58 17.06
ISA 50*50*10 Kg. 12 0.3 3.6 3.8 13.68
50*75mm plate stiffner Kg. 12 0.0000375 7850 3.53
Bottom Chord
Volume
10mm thick plate (175*175) Kg. 6 0.00030625 7850 14.42
10mm thick stiffner(63*63) Kg. 24 0.00003969 7850 7.47
4nos-16mm Boults Kg. 12 wt. per pcs 0.16 1.92
Runner Plate Connection
Runner Box (175*75mm outer size)
175*68.3*10mm runner box Kg. 8 2.47 19.76

Prepared By: Checked By: Verified By:


MB PRIMARY BLOCK

PRITHVI NARAYAN SECONDARY SCHOOL


Tarakeswor-5, Kathmandu
MB TOILET-2
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

S.N. Item Description Unit No Length Breadth Height Quantity Remarks


Volume
175*68.3*10mm runner plate Kg. 8 0.000119525 7850 7.5
2nos-16mm dia bolts Kg. 16 wt. per pcs 0.16 2.56
Purlin Cleat Connection
Volume
Top Chord Cleat 200*90*10 Kg. 72 0.00018 7850 101.73
2nos-16mm bolts Kg. 48 wt. per pcs 0.16 7.68
Top Ridge Connection
Volume
2 nos -10mm thick 175*175 mm plate Kg. 6 0.00030625 7850 14.42
10mm thick stiffners(57*59) Kg. 24 0.00003363 7850 6.33
16mm dia Nut bolts Kg. 12 wt. per pcs 0.16 1.92
Truss Cleat for wind Ties
Volume
Wind Tie Cleat(100*100*6) Kg. 32 0.00006 7850 15.07
MS Flat 165*80*6 Kg. 64 0.0000792 7850 39.79
MS Flat 380*80*6mm Kg. 16 0.0001824 7850 22.9
20mm dia Nut bolts Kg. 32 wt. per pcs 0.21 6.72
16mm dia Nut bolts Kg. 40 wt. per pcs 0.16 6.4
Total Kg. 1104.9
15.2 MS PIPE
Unit Lot No L Unit wt. Quantity
Between Toilet-2 & Middle block
NB 40 MS Round Pipe Kg. 1 1 5.25 3.56 18.69 both sides
38.1*38.1*3.2mm MS Vertical pipe Kg. 1 6 1.2 3.29 23.68
18*18*2 mm MS Pipe Kg. 1 4 5.0214 1 20.08
Incineration smoke pipe Kg. 1 1 9.7 18.98 184.1
TOTAL MS PIPE Kg. 197.24

18.2 Guide Ramp


Total 0

23 Cement Board
Gable Wall Sq.m. 2 5.1 1.07 5.45

TOTAL Sq.m. 5.45


24 FLOOR TILE (600*600)

TOTAL TILE (600*600) Sq.m. 0


25 ENAMEL PAINT
Railing Sqm. 1 5.25 0.9 2.36

Sq.m. 2.36
26 PILE WORK
P1 Rm 6 8.25 49.5

Rm 49.5

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST TOILET-2


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
GENERAL WORK, SITE CLEARANCE:Clearing and
grubbing of site for construction including uprooting of
1.1 vegetation, grass, brush wood, trees and sapplings of girth Sq.M 206.98 100.00 20,698.00
upto 300 mm & removal upto a distance of 50 m as per
drawings, specifications and instructions

EARTHWORK IN EXCAVATION: Earthwork in


2.1 excavation in trenches, pits and foundations by machine or Cu.M 597.4 200.00 119,480.00
appropriate technology in soft soil including existing debris
and brick bats of old structure, if any, upto specified depth
EARTWORK IN FILLING: Providing and placing of
random filling of excavated earth from cutting of slope and
stacked at site in 150mm thick layer in trenches, plinth or
under floor, sides of foundation and below beam at footing
2.2 Cu.M 176.54 200.00 35,308.00
covered area etc. including watering, mechanical ramming
and compaction of each layer, consolidation and dressing,
all complete as per drawings, specifications and instructions.

SAND FILLING: Sand filling in plinth under floors,


including watering, ramming, consolidating and dressing, all
2.3 complete as per drawings, specifications and instructions. Cu.M 0 2,500.00 -

STONE WORK : Dry stone soling work in line and level,


including packing joints with sand dust, all complete as per
3.1 drawings, specifications and instructions Cu.M 2.16 4,000.00 8,640.00

STONE MASONRY WALL: Stone rubble masonry work in


1:4 cement and sand mortar with hard, tough, sound and
durable stone in wall, made to required line, level, shape,
3.2 size and plumb including setting out, drain outlet, curing of Cu.M 17.02 7,500.00 127,650.00
the works and scaffolding etc. complete as per drawings,
specifications and instructions

BRICK WORK,FLAT BRICK SOLING: Flat brick soling


of local chimney bricks laid in line and level, including
4.1 packing joints with sand, complete as per drawings, Sq.M 99.87 800.00 79,896.00
specifications and instructions
FULL BRICK WORK: Brickwork in substructure and super
4.2 structure cement and sand mortar of mix 1:6 with first class Cu.M 11.9 15,000.00 178,500.00
chimney-made bricks, in any size and shape of wall, made
to required line, level, shape and plumb including setting
AAC(Autoclaved Aerated Concrete) BLOCK WORK:
5.1 Providing and laying of Autoclaved Aerated Concrete Block Sq.M 87.63 1,800.00 157,734.00
(600*200*200 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2)AAC(Autoclaved Aerated Concrete) BLOCK WORK:
Providing and laying of Autoclaved Aerated Concrete Block
(600*200*100 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2 required line, level, shape and plumb including setting out, Sq.M 42.5 2,000.00 85,000.00
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

5.3)AAC(Autoclaved Aerated Concrete) BLOCK WORK:


Providing and laying of Autoclaved Aerated Concrete Block
(600*200*150 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.3 required line, level, shape and plumb including setting out, Sq.M 0 1,100.00 -
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

CONCRETE WORK,PCC OF GRADE M10: Plain cement


concrete (PCC) of grade M10 (1:3:6 with 1 cement, 3 coarse
sand and 6 aggregate of 19 mm and down grade) in
6.1 foundation base including mixing, laying, compacting, Cu.M 9.44 10,000.00 94,400.00
finishing, curing, laid to exact line, level and dimensions,
inclusive ofside

PCC FOR RCC OF GRADE M25: Structural concrete (PCC


for RCC) of Grade M25 (1:1:2)works with approved
quality of cement, sand and well graded aggregate in any
form, size, shape and level including batching and mixing
6.2 with machine, laying including compaction with vibrating Cu.M 15.92 20,000.00 318,400.00
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

PCC FOR RCC OF GRADE M20: Structural concrete (PCC


for RCC) of Grade M20 (1:1.5:3)works with approved
quality of cement, sand and well graded aggregate in any
6.3 form, size, shape and level including batching and mixing Cu.M 14.42 17,000.00 245,140.00
with machine, laying including compaction with vibrating
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

FORMWORK: Placing plyboard form work with steel


props, shuttering, centering in horizontal/Vertical surfaces
like slab, beams, column, wall, stair etc. for all RCC works
7.1 of any shape, size and at any level and removal after Sq.M 253.64 850.00 215,594.00
completion

REINFORCEMENT WORK: Providing and placing steel


reinforcement bar tested grade Fe-500 equivalent NS, for
8.1 RCC work including bending, binding with anneal wire and kg 6428.15 110.00 707,096.50
placing in position, all complete as per drawings,
specifications and instruction

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST TOILET-2


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
9.1)FLOORING WORK,PLASTIC
9.1 LAYING: Supplying and laying 500 gauge plastic sheet in Sq.M 0 50.00 -
floor as per specificatio and instruction
9.2)SCREEDING: Providing and placing 38 mm thick Plain
cement concrete of grade M15 (1:2:4 with 1 cement, 2
coarse sand and 4 aggregate chips) in the floor base mixing,
laying, compacting, finishing, curing, laid to exact line level
9.2 , surface chipping and dimensions (floor concrete is laid in Sq.M 69.56 500.00 34,780.00
alternate panels of 1 m x 1 m) inclusive of shuttering
complete as per drawings, specifications and instructions

9.3)CEMENT PUNNING: Providing


and laying 3 mm cement punning in floor , laying in
9.3 Sq.M 0 200.00 -
required pattern, line

9.4)CEMENT SKIRTING: Providing


and placing cement skirting 125mm height of grade M15
(1:2:4 with cement, 2 coarse sand and 4 aggregate
) in wall ,mixing, laying, compactig, finishing, curing, laid
9.4 to exact line level and dimension all complete as per R.M 15.3 100.00 1,530.00
drawing, specification and instructions

9.5)TILE LAYING ON FLOOR:


Providing and laying approved brand quality, pattern and
color, ceramic mat finish tile (Low range) on floor over
9.5 cement mortar of mix 1:3 backing and filling joints (epoxy Sq.M 65.96 2,800.00 184,688.00
grout) complete as per drawings, specifications and
instructions.(Base rate: NRs 100)

9.6)TILE LAYING ON TOILET:


Providing and laying approved brand quality, pattern and
color, ceramic glazed tile in wall and ceramic mat finish tile
9.6 (Low range) on floor of toilet over cement mortar of mix 1:3 Sq.M 125.84 3,000.00 377,520.00
backing and filling joints (epoxy grout) complete as per
drawings, specifications and instructions.(Base rate: NRs
100)

10.1)FINISHING WORK,
EXTERNAL PLASTER: Providing and applying '10.5 mm
thick cement plastering with 1cement : 4 sand mortar in
outer surface any level size and shape of wall, column,
10.1 ceiling, band, blocks, etc inclusive of waterproofing Sq.M 129.88 400.00 51,952.00
compound, dusting, throating, etc as required including
racking, hacking, watering, cleaning of base, plastering to
plumb, line, level, smooth etc. and curing complete as per
drawings, specifications and instructions.
10.2)INTERNAL PLASTER:
Providing and applying'10.5 mm thick cement plastering
with 1cement : 4 sand mortar in inner surface except ceiling
any level size and shape of wall, column, band, blocks, etc
inclusive of dusting, throating, etc as required including
10.2 racking, watering, hacking, cleaning of base, plastering to Sq.M 250.22 450.00 112,599.00
plumb, line, level, smooth etc. and curing, all complete as
per drawings, specifications and instructions.

10.3)CEILING PLASTER: Providing


and applying 12.5 mm thick cement plastering with 1cement
10.3 : 4 sand mortar in Ceiling any level size and shape of Sq.M 49.38 500.00 24,690.00
ceiling inclusive of dusting,
10.4)PLASTER ON RCC LINTEL
WITH CORNICE: 'Providing and applying 12.5 mm thick
cement plastering with 1cement : 4 sand mortar in RCC
Lintel with cornice inclusive of dusting, throating, etc as
required including racking, watering, cleaning of base,
10.4 plastering to plumb, line, level, smooth etc. and curing, all R.M 0 3,000.00 -
complete as per drawings, specifications and instructions.

10.5)EMULSION PAINT: Providing


and applyibg two coat of emulsion paint in mat finishing
10.5 over two coat of primer, finished including surface Sq.M 163.36 200.00 32,672.00
preparation all complete as per drawings, specifications and
instruction
10.6)WEATHER COAT: Providing and applying two coat
of weather coat (Apex or equivalent) over required coat of
10.6 primer, finished including surface preparation all complete Sq.M 135.33 250.00 33,832.50
as per drawings, specifications and instruction

11.1)DOOR,WINDOWS WORK/UPVC SLIDING


WINDOWS: Providing and fixing standard UPVC sliding
window without net (frame 50x80mm, sash 58x36mm white
11.1 colour with 5mm glass) along with patented standard Sq.M 0 8,000.00 -
hardwares like roller, gaskets, brush seal, moon locks etc all
complete as per drawings and specifications.

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST TOILET-2


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
11.2)UPVC TOP HUNG
WINDOWS: Providing and fixing standard UPVC top hung
window (frame 60x60 mm, sash 60x104 mm, white colour
11.2 with 5 mm glass) along with patented standard hardwares Sq.M 10.23 8,000.00 81,840.00
like roller, gaskets, brush seal, moon locks etc all complete
as per drawings and specifications.

11.3)UPVC DOUBLE DOOR:


Providing and fixing standard UPVC double door (frame
60x60mm, sash 60x104mm white colour with 5mm glass)
11.3 along with patented standard hardwares like roller, gaskets, Sq.M 1.89 10,000.00 18,900.00
brush seal, moon locks etc all complete as per drawings and
specifications.

11.4)UPVC SINGLE DOOR:


Providing and fixing standard UPVC single door with full
panel (frame60x60mm, sash 60x104mm white colour with
11.4 5mm glass) along with patented standard hardwares like Sq.M 23.46 7,000.00 164,220.00
roller, gaskets, brush seal, moon locks etc all complete as
per drawings and specifications.

12.1)ROOFING WORK,CGI
ROOFING SHEET: Providing and fixing in position 24
gauge medium (0 .5 mm thick) corrugated CGI sheet over
12.1 roof truss with minimum 80 mm side laps and 200 mm end Sq.M 60.12 1,319.17 79,308.50
laps, inclusive of nuts and bolts, 8 mm 'J' hooks, washers,
GI cup washers, all complete as per drawings, specifications
and instruction

12.2)CGI ROOFING SHEET ON


RIDGE: Providing and fixing in position 24 gauge medium
(0 .5 mm thick) CGI sheet over roof truss in ridge with
12.2 minimum 80 mm side laps and 200 mm end laps, inclusive R.m 9 1,009.52 9,085.68
of nuts and bolts, washers, GI cup washers, all complete as
per drawings, specifications and instruction

12.3)GI GUTTER: providing and fixing in position color


plain GI sheet for gutter 150mmX450mm, inclusive of nuts
12.3 and bolts, washers, all complete as per drawings, R.m 18 1,000.00 18,000.00
specifications and instruction.
13.1)FALSE CEILING WORK,PVC
BOARD: Providing and fixing suspended PVC board false
ceiling, with necessary provisions for light fittings, light
13.1 boxes, where required finally finished with two coat acrylic Sq.M 0 1,500.00 -
emulsion paint, all complete as per drawings, specifications
and instructions.

14.1)MISCELLANEOUS WORK,
WATER PROOFING: Providing and placing 20 mm thick
cement sand mortar (1:2) mixing with wate proof
14.1 compound in the floor base mixing, laying, compacting, Sq.M 24.725 400.00 9,890.00
finishing, curing, laid to exact line level and dimensions
complete as per drawings, specifications and instructions

14.2)INSULATION WORK:
Providing and installing Insulation under CGI roofing sheet
14.2 with Insulation shield of 12mm thickness one sided and Sq.m 0 200.00 -
chicken wire mesh all completeas per drawing and
specifications.
15.1)METAL WORKS,BLACK
15.1 TUBULAR PIPE: Supplying, fabricating and fixing black Kg 1104.9 150.00 165,735.00
pipe (Square or circular) work /Truss with
15.2)MS PIPE: Supplying, fabricating and fixing metal
15.2 work of different angles MS Pipe with one coat primer as Kg 0 150.00 -
shown in drawing all complete
15.3)ROLLING SHUTTER:
Providing and fixing rolling shutterof 16-19 Gauge cold
rolled MS lathe interlocked throughout their entire length
and joined together at the end by end locks and mounted on
specially designed pipe shaft with brackets, side guides and
15.3 arrangements for inside and outside locking,with push and Sq.m 0 4,000.00 -
pull operation, complete supplying, fixing and painting with
two coats of approved plastic emulsion paint.

15.4)HOT ROLLED STEEL


SECTION: Supplying, fabricating and fixing metal work of
15.4 different Hot Rolled Steel sections with one coat primer as Kg 0 150.00 -
per drawings and specifications all complete

15.5)METAL WORK,METAL
GATE: Supplying, fabricating and fixing in position, metal
gates of standard sections consisting of angles, pipes,
15.5 flats,etc. including one coat primer and one coat enamel Sq.M 0 7,000.00 -
paint as per drawings, specifications and instructions all
complete

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST TOILET-2


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
15.6)FENCING WORK: Providing and fixing of ISA
50x50x5 mm along with 25x25x5 flat and M8x40 bolts at
12.3 300mm spacing to fix 10 S.W.G.G.I chain link with hole R.M 0 2,200.00 -
size 60x60 mm upto 3m height and 3 lines of barbed wire at
top.
16.1)EXPANSION JOINT WORKS/PLINTH LEVEL:
Suuply
and fixing of expansion joint at level of 100% non porous
flexible element allowing movement in all directions,
16.1 supported by aluminium framing and covering the top by R.M 0 4,500.00 -
aluminium sheet and flused to required floor level all
complete as per drawing, specification and instruction.

16.2)EXPANSION JOINT
WORKS/SLAB: Supply and fixing of expansion joint at
floor level of aluminium base supported by alumunium
16.2 framing,fixed on one side by threaded screw and flushed to R.M 0 4,500.00 -
required floor level and dimension all complete as per
drawing,specification and instruction

16.3)EXPANSION JOINT WORKS/ENDS OF WALL:


16.3 Supply R.M 0 4,500.00 -
17.1)CHAIN LINK VENTILATION
WORK: Supplying, fabricating and fixing in position of 10
S.W.G.I. woven wire ventilation with hollow square pipe
framing of size 18x18x1.0 mm on all sides with proper
17.1 welding on site, including one coat primer and one coat Sq.M 0 4,000.00 -
enamel paint on frames as per drawings, specifications and
instructions all complete

18.1)LAND DEVELOPMENT WORKS, INTERLOCKING


BLOCKS: Supplying and laying of 60 mm thick heavy duty
interlocking paving blocks of approved colour and quality
on the 50 mm thick stone dust with surface grading,
18.1 levelling and soil compaction base in driveways and parking Sq.M 0 2,000.00 -
areas, complete as per specifications and drawings.

18.2)RAILING WORKS: Supply,


fabrication and fitting of Railing works with MS square pipe
framing and 10 S.W.G.I. wire mesh of height 1.05m
18.2 including excavation, brickwork, plaster and two coats R.M 0 3,000.00 -
enamel paint all complete as per drawings and specifications

18.3)GUIDE RAMP: Supply,


fabrication and fitting of Guide Ramp-Utility Guardrail for
the disabled with MS tubular pipes at regular intervals of
18.3 height 1.05m including two coats enamel paint all complete R.M 0 6,500.00 -
as per drawings and specifications

18.4)APRON DRAIN: Construction of Apron drain along


the perimeter of buildings and retaining structures including
18.4 excavation, Brick soling, PCC and half brick thick apron R.M 0 20,000.00 -
walls with plaster all complete as per drawings and
specifications
18.5)TACTILE PAVING: Providing
and laying approved brand quality, pattern and colour of
Tactile paving tile on floor over constructed cement mortar
18.5 of mix 1:3 backing and filling joints (epoxy grout) at R.M 0 3,500.00 -
straight path and turning points of size 300x300x40mm, all
complete as per drawings, specifications and instructions.

DEMOLITION WOKS: Demolition of existing building


19.1 and toilet blocks PS 0 1,000,000.00 -
RELOCATION WOKS: Relocation of temple from existing
site and to be constructed at a new location outside of the
20.1 school site as per drawing,specification and instructions. PS 0 300,000.00 -

INSURANCE PREMIUM
21.1 PS 0 224,281.00 -

Floor Hardener:providing,sprinkling,laying &applying


Manually two layer in floor,applied each layer with 1.5 to
2.5kg /m2 in required pattern,blended in,smoothed,over by
22.1 power trowelling,in line and level including curing all Sq.M 0 400.00 -
complete as per drawing,specification and instruction.
(Mapetop,N,AR6 or equivalent)

Cement Board:providing and fixing in position 10mm


water proofed cement board in exterior (one side)surface
inclusive minimum75mm GI metal framewith grooving and
23.1 fixing of fastner ,washer,nuts,and bolts,all complete as per Sq.M 5.45 2,700.00 14,715.00
drawings,specifications and instructions.

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST TOILET-2


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
FLOOR TILE (600*600)
24 Sq.M 0 2,500.00 -

ENAMEL PAINT
25 Sq.M 0 286.00 -

PILE WORK : Construction of pile work including


26 excavation, reinforcement and concreting work. Rm. 49.5 17,000.00 841,500.00

DISMANTLING WORK
27 -

CONCRETE DISMANTLING
27.1 Cu.M 8,500.00 -

BRICKWALL DISMANTLING
27.2 Cu.M 2,000.00 -

TOTAL CIVIL WORKS -


TOTAL AMOUNT
4,650,994.18

Total Item Price 4,650,994.18

Discount @2% 93,019.88

Sub Total 4,557,974.30

VAT @13% 592,536.66

Grand Total 5,150,510.95

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LANDSCAPE WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks

GENERAL WORK, SITE CLEARANCE


1
PRIMARY BLOCK
RCC SHEARWALL Sq.M 1 38.2 3.6 137.52
Masonary wall
BOUNDARY WALL
For 1m Sq.M 1 122.7 1.7 208.59
For 2m Sq.M 1 56.2 2.6 146.12
BOUNDARY DRAIN WALL Sq.M 1 91.5 1.06 96.99

SECONDARY BLOCK
RCC SHEARWALL Sq.M 1 40.6 3.3 133.98
Masonary wall
For 2m Wall backside of building Sq.M 1 38.3 2.6 99.58
For 3m wall attahed to shear wall Sq.M 1 6.3 3.3 20.79
Infront of Secondary block
passage Sq.M 1 42 3
MIDDLE BLOCK
For 3m Wall Sq.M 1 42.9 3.3 141.57
Beside Middle block
Middle Block passage Cum 1 43.98 3 131.94

LIBRARY BLOCK
For 3m Wall Sq.M 1 28.5 3.3 94.05
For 3m wall on both side from ground floor Sq.M 1 5.85 3.3 19.3
For 2m Wall between library and middle block Sq.M 1 43.85 2.1 0 Repair wall
Beside library block
Passage on second floor level Sq.M 1 28 3.3 92.4
Ramp from Library block to Middle Block Sq.M 1 34.4 3.3 113.52

TOILET BLOCK 1
For 3m Wall Sq.M 1 12 3.3 39.6
TOILET BLOCK 2
BesideToilet block-2 as per previous plan
For 3m Wall Sq.M 1 24.5 3.3 0

NEW WALL SECTION


Wall near Secondary block ( Along road )
1.5m ht wall Sq.M 1 16 2.765 44.24
2m ht wall Sq.M 1 10 3.07 30.7
3m ht wall Sq.M 1 13.4 3.781 50.66
Wall near primary block (New wall )
3m ht wall Sq.M 1 41 3.781 155.02
Wall Infront of Canteen block Sq.M 1 10.8 1.6 17.28
Secondary block supporting wall(2 M & 3 Mnew wall
section) Sq.M 1 4.5 4.07 18.31
Sq.M 1 4 3.781 15.12

Drain Wall along 40 m new wall section Sq.M 1 40 0.95


Pathway from primary to secondary block
Spiral Steps Sq.M 1 9 2.63 23.67
9" Brick masonry wall Sq.M 1 19 0.53 10.07
14" brick masonry wall Sq.M 1 21 0.7 14.7
Horizontal pathway above 40m wall Sq.M 1 42.3 2.2 93.06
Stone wall both sides Sq.M 1 12.14 3.2 38.84

Ground from main gate to middle block Sq.M 1 1110.37 area measured from cad 1110.37

TOTAL SITE CLEARANCE Sqm. 3097.99


2.1 EARTHWORK IN EXCAVATION
PRIMARY BLOCK
PRIMARY BLOCK
RCC SHEARWALL cum 1 37.9 3.60 2.45 334.27 only for footing excavation
Masonary wall
BOUNDARY WALL
For 1m cum 1 122.4 1.463 1.005 179.96
For 2m cum 1 55.9 1.92 1.005 107.86
BOUNDARY DRAIN WALL cum 1 91.5 1.06 0.625 60.61

SECONDARY BLOCK
RCC SHEARWALL cum 1 40.3 3.3 5.6 744.74
Masonary wall
For 2m Wall backside of building cum 1 38 1.92 0.93 67.85 Only for depth+soling
For 3m wall attahed to shear wall cum 1 6 2.63 1.38 21.77

MIDDLE BLOCK
For 3m Wall cum 1 42.6 2.63 3 336.11

LIBRARY BLOCK
For 3m Wall below connecting slab cum 1 27.8 2.63 3 219.34 only for base depth
For 3m wall on both side from ground floor cum 1 3.85 2.63 3 30.37
For 2m Wall between library and middle block cum 1 43.55 1.92 2 0 14.4m wall repaired?/tilted

Ramp from Library block to Middle Block cum 1 34.4 3.3 1 113.52
9 " Brickwork from library to first landing cum 1 26.4 0.38 0.7 7.02
9" Brickwork from landing to middle block
on outer edge cum 1 8 0.38 1.7 5.16
on inner edge cum 1 19 0.38 0.9 6.49

TOILET BLOCK 1
For 3m Wall cum 1 11.7 2.6 1.33 40.45
TOILET BLOCK 2
BesideToilet block-2 as per previous plan
For 3m Wall cum 1 24.5 2.6 3 0 Repaired?

NEW WALL SECTION


Wall near Secondary block ( Along road )
1.5m ht wall cum 1 15 1.6 2.43 58.32
2m ht wall cum 1 9 2.37 2.93 62.49
3m ht wall cum 1 12.4 3.081 4.38 167.33
Wall near primary block (New wall )
3m ht wall cum 1 40 3.081 4.38 539.79

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LANDSCAPE WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks

Wall Infront of Canteen block cum 1 9.8 1.5 2.43 35.72


Secondary block supporting wall(2 M & 3M new wall
section) cum 1 3.5 2.37 3.3
27.37
1 3 3.081 4.38 40.48
Drain Wall along 40 m new wall section cum 1 40 0.76 0.375 11.4
Pathway from primary to secondary block
Spiral Steps cum 1 9 2.63 0.8 18.93
9" Brick masonry wall cum 1 19 0.53 1.125 11.32
14" brick masonry wall cum 1 23.3 0.7 1.625 26.5
Horizontal pathway above 40m wall cum 1 42.3 2.2 0.125 11.63
Stone wall both sides cum 2 12.14 0.9 1 21.85 ?
cum 1 2 1.95 1 3.9
Pathway from secondary to toilet-2 and middle block cum 1 36.86 0.6 22.116
area from cad
Brickwork attached to main gate cum 1 9.65 0.53 0.3 1.53
Main gate column cum 2 1.2 1.2 1.2 3.45

EARTH SLOPE CUTTING


Proposed Academic Block-Primary (1324.5) Cu.m. 1 1132.27
Infront of Proposed Primary Block (1324.05) Cu.m. 1 1380.67
Proposed Toilet Block (1328.1) Cu.m. 1 228.92
Proposed Sports Complex (1326.15) Cu.m. 1 0
Proposed Academic Block-Secondary (1336.85) Cu.m. 1 1418.87
Behind Library Block (1327) Cu.m. 1 0
Proposed Library Block (1333.45) Cu.m. 1 0

TOTAL EARTHWORK IN EXCAVATION Cu.m. 7500.376


2.2 EARTHWORK IN FILLING
Total earthwork in excavation 3339.646
For earth slope filing
Proposed Academic Block-Primary (1324.5) 0.86
Infront of Proposed Primary Block (1324.05) 0
Proposed Toilet Block (1328.1) 24.31
Proposed Sports Complex (1326.15) 0
Proposed Academic Block-Secondary (1336.85) 0.15
Behind Library Block (1327) 256.06
Proposed Library Block (1333.45) 1518.93

Deduction cu.m.
Shearwall cu.m. -119.7
stone masonary wall cu.m. -1176.371
Boundary wall above cutting line L C/S
1m wall cu.m. 1 126.5 0.569 71.978
2m wall cu.m. 1 55.9 1.297 72.502
Masonry wall in front of toilet-1 abouve cutting line cu.m. 1 12 2.77 33.24
Masonry wall backside of secondary block abouve cutting line cu.m.
1 38 1.297 49.286

soling cu.m. -218.98


pcc cu.m. -171.5045

Total Back Filling Cu.m. 3680.4065


3 STONE WORK
3.1 DRY STONE SOLING AREA
PRIMARY BLOCK
SHEARWALL Cu.m. 1 37.9 0.63 23.87
BOUNDARY WALL
For 1m Wall Cu.m. 1 122.4 0.299 36.59
For 2m Wall Cu.m. 1 55.9 0.368 20.57
SECONDARY BLOCK
SHEARWALL Cu.m. 1 40.3 0.585 23.57
Masonary wall
3m Wall attached to shear wall Cu.m. 1 6 0.529 3.17
For 2m Wall Cu.m. 1 38 0.368 13.98
MIDDLE BLOCK
For 3m Wall Cu.m. 1 42.60 0.529 22.53
LIBRARY BLOCK
For 3m Wall Cu.m. 1 27.5 0.529 14.54
For 3m Wall Cu.m. 1 3.85 0.529 2.03
For 2m Wall Cu.m. 1 43.55 0.368 0 14.4m repaired?/tilted
TOILET BLOCK 1
For 3m Wall Cu.m. 1 11.7 0.529 6.18
TOILET BLOCK 2
BesideToilet block-2
For 3m Wall Cu.m. 1 24.5 0.529 0 repair

NEW WALL SECTION


Wall near Secondary block ( Along road )
1.5m ht wall cum 1 15 0.4 6
2m ht wall cum 1 9 0.47 4.23 12.4
3m ht wall cum 1 14.4 0.63 9.07

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LANDSCAPE WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks

Wall near primary block (New wall )


3m ht wall cum 1 40 0.63 25.2 38.4
Wall Infront of Canteen block cum 1 9.8 0.4 3.92 40
Secondary block supporting wall(2 M & 3M new wall
section) cum 1 3 0.63 1.89
cum 1 3.5 0.47 1.64

TOTAL DRY STONE SOLING Cu.m. 218.98

5 STONE MASONARY WALL C/S AREA


BOUNDARY WALL
For 1m Wall Cu.m. 1 122.4 1.147 140.39
For 2m Wall Cu.m. 1 55.9 2.232 124.76
SECONDARY BLOCK
For 2m Wall Cu.m. 1 38 2.232 84.81
Addition of 750mm wall Cu.m. 1 25.9 0.3375 8.74 backside of sec. block
3m wall Cu.m. 1 6 4.95 29.7
MIDDLE BLOCK
For 3m Wall Cu.m. 1 42.60 4.95 210.87
LIBRARY BLOCK
For 3m Wall Cu.m. 1 27.5 4.95 136.12
For 3m Wall Cu.m. 1 3.85 4.95 19.05
For 2m Wall Cu.m. 1 43.55 1.75 0 reconstructed?/tilted 14.4m
TOILET BLOCK 1
For 3m Wall Cu.m. 1 11.7 4.95 57.91
TOILET BLOCK 2
For 3m Wall Cu.m. 1 24.5 4.95 0

NEW WALL SECTION


Wall near Secondary block ( Along road )
1.5m ht wall cum 1 15 1.73 25.95
2m ht wall cum 1 9 2.232 20.08
3m ht wall cum 1 12.4 4.95 61.38
Secondary block supporting wall cum 1 3.5 2.23 7.8
1 3 4.95 14.85
Wall near primary block (New wall )
3m ht wall cum 1 40 4.95 198

Wall Infront of Canteen block Cu.m. 1 9.8 1.785 17.493

Wall for pathway from primary to secondary Cu.m. 2 12.14 0.6 1.675 14.568
Cu.m. 1 2 1.95 1.45 3.9

TOTAL Cum 1176.371


4 BRICK WORK
4.1 FLAT BRICK SOLING
PRIMARY BLOCK
BOUNDARY DRAIN WALL Sqm. 1 91.5 0.76 69.54

Ramp from Library block to Middle Block Sqm. 1 34.4 3.3 113.52
9 " Brickwork from library to first landing Sqm. 1 26.4 0.5 13.2
9" Brickwork from landing to middle block
on outer edge Sqm. 1 8 0.5 4
on inner edge Sqm. 1 19 0.5 9.5

Drain Wall along 40 m new wall section Sqm. 1 40 0.7 28


Pathway from primary to secondary block
Spiral Steps Sqm. 1 9 2.63 23.67
9" Brick masonry wall Sqm. 1 19 0.53 10.07
14" brick masonry wall Sqm. 1 23.3 0.7 16.31
Horizontal pathway above 40m wall Sqm. 1 42.3 2.2 93.06
Vertical steps from landing to secondary Sqm. 1 14.61 3.5 51.13
Soling for stone wall both ways Sqm. 2 12.14 0.9 21.85
Sqm. 1 2 2.25 4.5

Pathway from secondary to toilet-2 and middle block Sqm. 1 36.86 36.86
area from cad
Brickwork attached to main gate Sqm. 1 9.65 0.53 5.11
Main gate column Sqm. 2 1.2 1.2 2.88
TOTAL BRICK SOLING Sqm. 503.2
4.2 Full Brick work
PRIMARY BLOCK
BOUNDARY DRAIN WALL cum 2 91.5 0.11 0.6 12.07 both side

Ramp from Library block to Middle Block


9 " Brickwork from library to first landing cum 1 26.4 0.23 1.2 7.28
9" Brickwork from landing to middle block 0
on outer edge cum 1 8 0.23 2 3.68
on inner edge cum 1 19 0.23 0.9 3.93
Drain wall cum 2 20.2 0.23 0.6 5.57 Both sides

Drain Wall along 40 m new wall section cum 1 40 0.11 0.25 1.1
cum 1 40 0.125 0.25 1.25
Pathway from primary to secondary block
Spiral Steps
Outer 9" wall cum 1 9.01 0.23 1.2 2.48
Steps cum 3 2.1 0.3 0.15 0.28
cum 12 2.1 0.35 0.15 1.32
cum
9" Brick masonry wall cum 1 19 0.23 1 4.37
14" brick masonry wall cum 1 23.3 0.4 1.5 13.98
Vertical steps from landing to secondary cum 28 3.2 0.3 0.2 5.37

Pathway from secondary to toilet-2 and middle block


Steps From secondary to landing cum 5 2 0.3 0.15 0.45
Steps From Toilet -2 to landing cum 2 2.2 0.3 0.2 0.26
Steps from landing to ground in front of middle block 1.95 0.3
cum 6
0.2 0.7
cum 2 2.5 0.3 0.2 0.3
cum 2 1.65 0.6 0.15 0.29
cum 2 1.8 0.6 0.15 0.32

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LANDSCAPE WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks

Outer wall at edge cum 1 3.1 0.23 0.5 0.35


Wall at landing to middle block step cum 1 1.87 0.23 0.6 0.25

9" Wall to cover pile cap cum 1 4.3 0.23 1.4 1.38

Brickwork attached to main gate cum 1 9.65 0.23 0.55 1.22

TOTAL BRICK WORK Cum. 68.2

6 CONCRETE WORK
6.1 PCC of grade M10
PRIMARY BLOCK Area
SHEARWALL Cu.m. 1 38.025 0.315 11.97

BOUNDARY WALL Cu.m.


For 1m Wall Cu.m. 1 122.4 0.13 15.91
For 2m Wall Cu.m. 1 55.9 0.162 9.05
BOUNDARY DRAIN Cu.m. 1 91.5 0.0795 7.27

SECONDARY BLOCK
SHEARWALL Cu.m. 1 40.3 0.281 11.32
Masonary wall
For 2m Wall Cu.m. 1 38 0.16 6.08
For 3m Wall Cu.m. 1 6 0.345 2.07

MIDDLE BLOCK
For 3m Wall Cu.m. 1 42.60 0.345 14.69
LIBRARY BLOCK
For 3m Wall Cu.m. 1 27.5 0.345 9.48

For 3m Wall Cu.m. 1 3.85 0.345 1.32

For 2m Wall Cu.m.


1 43.55 0.16 0 14.4m needs reconstruction

Ramp from Library block to Middle Block Cu.m. 1 34.4 0.2475 8.51
9 " Brickwork from library to first landing Cu.m. 1 26.40 0.0225 0.59
9" Brickwork from landing to middle block Cu.m.
on outer edge Cu.m. 1 8 0.0225 0.18
on inner edge Cu.m. 1 19 0.0225 0.42
TOILET BLOCK 1
For 3m Wall Cu.m. 1 11.7 0.345 4.03
TOILET BLOCK 2
BesideToilet block-2
For 3m Wall Cu.m. 1 24.5 0.345 0 needs to repair

NEW WALL SECTION


Wall near Secondary block ( Along road )
1.5m ht wall cum 1 15 0.17 2.55
cum 1 15 0.07 1.05 At middle
2m ht wall cum 1 9 0.2 1.8
cum 1 9 0.09 0.81 At middle
3m ht wall cum 1 12.4 0.41 5.08
cum 1 12.4 0.12 1.48 At middle
Wall near primary block (New wall )
3m ht wall cum 1 40 0.63 25.2
cum 1 40 0.12 4.8 At middle
Wall Infront of Canteen block cum 1 9.8 0.16 1.56
Secondary block supporting wall(2 M & 3M new wall
section) cum 1 3.5 0.2 0.7
cum 1 3.5 0.09 0.31 At middle
cum 1 3 0.41 1.23
cum 1 3 0.12 0.36 At middle

Drain Wall along 40 m new wall section cum 1 40 0.04875 1.95


Pathway from primary to secondary block
Spiral Steps cum 1 9 0.19725 1.77
9" Brick masonry wall cum 1 19 0.03975 0.75
14" brick masonry wall cum 1 23.3 0.0525 1.22
Horizontal pathway above 40m wall cum 1 42.3 0.165 6.97
Vertical steps from landing to secondary cum 1 14.61 0.2625 3.83
PCC for stone wall both sides cum 2 12.14 0.0675 1.63
cum 1 2 0.16875 0.33

Pathway from secondary to toilet-2 and middle block


cum 1 36.86 0.075
2.7645
area from cad
Brickwork attached to main gate cum 1 9.65 0.03975 0.38
Main gate column cum 1 1.2 0.075 0.09

TOTAL M10 grade Cu.m. 171.5045

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LANDSCAPE WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
6.3 PCC for RCC of Grade M20
PRIMARY BLOCK area
Shear wall footing Cu.m. 1 37.9 1.687 63.93
Shear Wall Cu.m. 1 37.9 1.73 65.56 5.325
Deduction of shear wall top Cu.m. -1 2.91 0.2486 -0.73
SECONDARY BLOCK
Shear wall footing Cu.m. 1 40.3 1.402 56.5
Shear Wall Cu.m. 1 40.3 1.462 58.91

BOUNDARY WALL
For 1m Wall Cu.m. 1 122.4 0.03375 4.13
For 2m Wall Cu.m. 1 55.9 0.03375 1.88
SECONDARY BLOCK
Masonary wall
For 2m Wall Cu.m. 1 38 0.03375 1.28
For 3m Wall Cu.m. 1 6 0.03375 0.2
MIDDLE BLOCK
For 3m Wall Cu.m. 1 42.6 0.03375 1.43
LIBRARY BLOCK
For 3m Wall Cu.m. 1 27.5 0.03375 0.92

For 3m Wall Cu.m. 1 3.85 0.03375 0.12

For 2m Wall Cu.m. 14.4m needs


1 43.55 0.03375 0
reconstruction/tilted
TOILET BLOCK 1
For 3m Wall Cu.m. 1 11.7 0.03375 0.39
TOILET BLOCK 2
BesideToilet block-2
For 3m Wall Cu.m. 1 24.5 0.03375 0

NEW WALL SECTION


Wall near Secondary block ( Along road )
1.5m ht wall cum 1 15 0.03375 0.5
2m ht wall cum 1 9 0.03375 0.3
3m ht wall cum 1 12.4 0.03375 0.41
Wall near primary block (New wall )
3m ht wall cum 1 40 0.03375 1.35
Wall Infront of Canteen block cum 1 9.8 0.03375 0.33
Secondary block supporting wall(2 M new wall section)
cum 1 3.5 0.03375 0.11
cum 1 3 0.03375 0.1
9" Wall attached to main gate cum 1 9.65 0.01725 0.16
Main Gate
Footing cum 2 1.6 0.48 1.53
Column cum 2 3.5 0.2025 1.41
Beam cum 1 4.6 0.0625 0.28

TOTAL M20 Grade Cu.m. 261


10 FORM WORK
PRIMARY BLOCK
SHEARWALL FOOTINGS sq.m 2 37.9 0.45 34.11
SHEARWALL FOOTINGS sq.m 2 3.3 0.45 2.97
TRENCH FOOTINGS sq.m 2 37.9 0.45 34.11
SHEARWALL sq.m 2 37.9 5.325 403.63
Deduction of shear wall top sq.m -2 2.91 1.1 -6.41

BOUNDARY WALL sq.m


For 1m Wall bottom Pcc sq.m 1 247.4 0.1 24.74
For 1m Wall Top Rcc sq.m 1 245.7 0.075 18.42
For 2m Wall bottom Pcc sq.m 1 115 0.1 11.5
For 2m Wall Top Rcc sq.m 1 112.7 0.075 8.45
SECONDARY BLOCK
Shear Wall FOOTINGS sq.m 2 40.3 0.4 32.24
sq.m 2 3 0.4 2.4
Shear wall TRENCH FOOTINGS sq.m 2 40.3 0.45 36.27
SHEARWALL sq.m 2 40.3 4.875 392.92
MASONARY WALL
For 2m Wall bottom Pcc sq.m 1 79.2 0.1 7.92
For 2m Wall Top Rcc sq.m 1 76.9 0.075 5.76
For 3m Wall bottom Pcc sq.m 1 10.6 0.15 1.59
For 3m Wall Top Rcc sq.m 1 6.9 0.075 0.51
MIDDLE BLOCK
For 3m Wall bottom Pcc sq.m 1 89.8 0.15 13.47
For 3m Wall Top Rcc sq.m 1 86.1 0.075 6.45
LIBRARY BLOCK
For 3m Wall bottom Pcc sq.m 1 59.6 0.15 8.94
For 3m Wall Top Rcc sq.m 1 55.9 0.075 4.19
For 3m Wall bottom Pcc sq.m 1 12.3 0.15 1.84
For 3m Wall Top Rcc sq.m 1 8.6 0.075 0.64
For 2m Wall bottom Pcc sq.m 1 90.3 0.1 0 repaired?
For 2m Wall Top Rcc sq.m 1 88 0.075 0 repaired?
TOILET BLOCK 1
For 3m Wall bottom Pcc sq.m 1 28 0.15 4.2
For 3m Wall Top Rcc sq.m 1 24.3 0.075 1.82
TOILET BLOCK 2
BesideToilet block-2
For 3m Wall bottom Pcc sq.m 1 53.6 0.15 0 repaired?
For 3m Wall Top Rcc sq.m 1 49.9 0.075 0 repaired?

TOTAL
NEW WALL SECTION
Wall near Secondary block ( Along road )
1.5m ht wall sq.m 1 33.53 0.1 3.35 Base PCC
sq.m 1 31.95 0.1 3.19 Middle PCC
sq.m 1 30.9 0.075 2.31 Top RCC
2m ht wall sq.m 1 22.14 0.1 2.21
sq.m 1 20.53 0.1 2.05
sq.m 1 18.9 0.075 1.41
3m ht wall sq.m 1 30.362 0.15 4.55
sq.m 1 28.16 0.1 2.81
sq.m 1 25.7 0.075 1.92
Wall near primary block (New wall )

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LANDSCAPE WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks

3m ht wall sq.m 1 84.6 0.15 12.69


sq.m 1 83.36 0.1 8.33
sq.m 1 80.9 0.075 6.06

Wall Infront of Canteen block sq.m 1 22.8 0.1 2.28


sq.m 1 20.5 0.075 1.53

Secondary block supporting wall(2 M & 3M new wall sq.m


section) 1 12.4 0.1 1.24
sq.m 1 9.53 0.1 0.95
sq.m 1 7.9 0.075 0.59
sq.m 1 10.6 0.15 1.59
sq.m 1 9.36 0.1 0.93
sq.m 1 6.9 0.075 0.51

9" Wall attached to main gate sq.m 2 19.76 0.075 2.96

Main Gate
Footing sq.m 2 6.4 0.3 3.84
Column sq.m 2 1.8 3.5 12.6
Beam sq.m 1 4.6 0.5 2.3

TOTAL Sq.m. 1134.88

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LANDSCAPE WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks

11 REINFORCEMENT WORK
PRIMARY BLOCK
Shearwall chair and space bar included/this
Kg 1 13786.40593 13786.4059259 can be excluded

SECONDARY BLOCK
Shearwall Kg 1 13937.06667 13937.0666667

BOUNDARY WALL 3nos. 8mm bar Throughout


& 8mm strriups @ 230mm c/c
Kg No. L Unit wt.

1m ht wall
Main Bar kg. 3 122.4 0.39 143.2
Stirrups kg. 532.1 0.56 0.39 116.21
2m ht wall
Main Bar kg. 3 55.9 0.39 65.4
Stirrups kg. 243 0.56 0.39 53.07
SECONDARY BLOCK
MASONARY WALL
2m ht wall
Main Bar kg. 3 38 0.39 44.46
Stirrups kg. 165.2 0.56 0.39 36.07
3m ht wall
Main Bar kg. 3 6 0.39 7.02
Stirrups kg. 26 0.56 0.39 5.67
Wall in front of canteen block
Main Bar kg. 3 9.8 0.39 11.46
Stirrups kg. 42.6 0.56 0.39 9.3
MIDDLE BLOCK
3m ht wall
Main Bar kg. 3 42.6 0.39 49.84
Stirrups kg. 185.2 0.56 0.39 40.44
LIBRARY BLOCK
3m ht wall
Main Bar kg. 3 27.5 0.39 32.17
Stirrups kg. 119.5 0.56 0.39 26.09
3m ht wall
Main Bar kg. 3 3.85 0.39 4.5
Stirrups kg. 16.7 0.56 0.39 3.64
2m ht wall
Main Bar kg. 3 43.55 0.39 0 repaired?/tilted
Stirrups kg. 189.3 0.56 0.39 0
TOILET BLOCK 1
3m ht wall
Main Bar kg. 3 11.7 0.39 13.68
Stirrups kg. 50.8 0.56 0.39 11.09
TOILET BLOCK 2
BesideToilet block-2
For 3m Wall
Main Bar kg. 3 24.5 0.39 0 repaired?
Stirrups kg. 106.5 0.56 0.39 0 repaired?

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LANDSCAPE WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks

Wall near Secondary block ( Along road ) 3nos. 8mm bar Throughout
& 8mm strriups @ 230mm c/c
No. L Unit wt.

1.5m ht wall
Main Bar kg. 3 15 0.39 17.55
Stirrups kg. 65.2 0.56 0.39 14.23
2m ht wall
Main Bar kg. 3 9 0.39 10.53
Stirrups kg. 39.1 0.56 0.39 8.53
2m ht wall ( sec. block supporting wall)
Main Bar kg. 3 14.4 0.39 16.84 ?
Stirrups kg. 62.6 0.56 0.39 13.67 ?
3m ht wall
Main Bar kg. 3 12.4 0.39 14.5
Stirrups kg. 53.9 0.56 0.39 11.77
wall along step of sec. block section 1
Main Bar kg. 3 3.5 0.39 4.09
Stirrups kg. 15.2 0.56 0.39 3.31
wall along step of sec. block section 2
Main Bar kg. 3 3 0.39 3.51
Stirrups kg. 13 0.56 0.39 2.83
Wall near primary block (New wall )
3m ht wall
Main Bar kg. 3 40 0.39 46.8
Stirrups kg. 173.9 0.56 0.39 37.97

Main Gate
Footing kg. 44 1.7 0.61 45.62 10mm rod
Tie Beam
Main Bar kg. 4 4.9 1.58 30.96 16mm rod, 4nos.
Stirrups kg. 25.5 0.96 0.39 9.54 8mm @ 200mm c/c
Column
Main Bar kg. 16 4.35 1.58 109.96 16mm rod, 8nos.
Stirrups kg. 48.66667 1.64 0.39 31.12 8mm @ 150mm c/c
kg. 48.66667 1.2 0.39 22.77

TOTAL kg. 28852.8825926

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LANDSCAPE WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks

9.2 SCREEDING
PATHWAY FROM PRIMARY TO SECONDARY

SPIRAL STEPS
Steps Sqm. 3 2.1 0.3 1.89
Sqm. 12 2.1 0.35 8.82
Vertical Steps from landing to secondary
First 2 steps ( Both sides) Sqm. 4 2.1 0.3 2.52
Remaining steps Sqm. 1 11.3 3.2 36.16

Pathway from secondary to toilet-2 and middle block Sqm.


1 36.86
36.86
area from cad

TOTAL SCREEDING Sqm. 86.25


10.1 ETERNAL PLASTERING WORK
Primary Block
Boundary Drain Sqm. 1 91.5 1.8 164.7
Drain along 40m wall Sqm. 1 40 1.17 46.8
Library Block to middle block pathway 0
Drain along pathway to middle block Sqm. 1 20.2 2 40.4
First flight support wall Sqm. 1 26.4 1.03 27.19
Second flight wall on inner end Sqm. 1 19 0.91 17.29
Second flight wall on outer end Sqm. 1 8 1.75 14

Pathway from secondary to toilet-2 and middle block Sqm.


1 36.86 36.86
area from cad
Steps riser Sqm. 5 2 0.15 1.5
Sqm. 2 2.2 0.2 0.88
Sqm. 6 1.95 0.2 2.34
Sqm. 2 2.5 0.2 1
Sqm. 2 1.65 0.15 0.49
Sqm. 2 1.8 0.15 0.54

Wall to cover pile cap Sqm. 1 4.3 1.4 6.02

Main gate column Sqm. 2 1.8 2.8 10.08


9" wall attached to main gate Sqm. 1 9.65 1.33 12.83

Pathway from primary to secondary


Spiral Steps
Outer Wall Sqm. 1 9.01 1.28 11.53
Steps Sqm. 3 2.1 0.45 2.83
Sqm. 12 2.1 0.5 12.6
9" Wall Sqm. 1 19 1.15 21.85
14" wall Sqm. 1 23.3 1.15 26.79

First three steps both ways Sqm. 6 2.1 0.45 5.67


Vertical Steps from landing to secondary Sqm. 0
Tread Sqm. 1 11.3 3.2 36.16
Riser Sqm. 28 3.2 0.2 17.92

Total eternal plaster Sqm. 518.27


10.6 WEATHER COAT PAINT
Main gate column Sqm. 2 1.8 2.8 10.08

Total Sqm. 10.08


15.2 MS PIPE
Landscape Railing
Unit. No. L Total L Un. Wt. Quantity
Library Block to Middle block footpath railing
38.1*38.1*3.2mm MS Vertical pipe kg. 21 1.25 26.25 3.29 86.36
kg. 12 0.95 11.4 3.29 37.5
kg. 1 1.5 1.5 3.29 4.93
NB 40 MS Round Pipe kg. 1 47.66 47.66 3.56 169.66
18*18*2 mm MS Pipe kg. 4 46.2 184.8 1 184.8
125*125*5mm plate kg. 6 0.125 0.75 4.9 3.67

In front of canteen block


NB 40 MS Round Pipe kg. 1 9.8 9.8 3.56 34.88
38.1*38.1*3.2mm MS Vertical pipe kg. 6 1.025 6.15 3.29 20.23
18*18*2 mm MS Pipe kg. 4 9.472 37.888 1 37.88

Entry road wall


NB 40 MS Round Pipe kg. 1 41.3 41.3 3.56 147.02
38.1*38.1*3.2mm MS Vertical pipe kg. 24 1.025 24.6 3.29 80.93
18*18*2 mm MS Pipe kg. 4 40.288 161.152 1 161.15

NB 40 MS Round Pipe kg. 1 10.4 10.4 3.56 37.02 near main gate
38.1*38.1*3.2mm MS Vertical pipe kg. 8 1.025 8.2 3.29 26.97
18*18*2 mm MS Pipe kg. 4 9.996 39.984 1 39.98

NB 40 MS Round Pipe kg. 1 6.5 6.5 3.56 23.14 Additional in


38.1*38.1*3.2mm MS Vertical pipe kg. 6 1.025 6.15 3.29 20.23 secondary block steps
18*18*2 mm MS Pipe kg. 4 6.172 24.688 1 24.68

Road backside of secondary block


NB 40 MS Round Pipe kg. 1 24.8 24.8 3.56 88.28
38.1*38.1*3.2mm MS Vertical pipe kg. 19 1.025 19.475 3.29 64.07
18*18*2 mm MS Pipe kg. 4 23.978 95.912 1 95.91

NB 40 MS Round Pipe kg. 1 40 40 3.56 142.4


38.1*38.1*3.2mm MS Vertical pipe kg. 23 1.025 23.575 3.29 77.56
18*18*2 mm MS Pipe kg. 4 39.026 156.104 1 156.1
18*18*2 mm MS vertical Pipe kg. 1 1.025 1.025 1 1.02

Above Stone masonry wall in front of sec. Block


NB 40 MS Round Pipe kg. 1 5.8 5.8 3.56 20.64
38.1*38.1*3.2mm MS Vertical pipe kg. 4 1.025 4.1 3.29 13.48
18*18*2 mm MS Pipe kg. 4 5.548 22.192 1 22.19

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu
MB LANDSCAPE WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
S.N. Item Description Unit No Length Breadth Height Quantity Remarks
Above Shear wall in front of secondary block
25.4*25.4*2.6mm MS Post kg. 25 0.9 22.5 1.69 38.02
25.4*25.4*2.6mm MS Top Rail kg. 1 35.3 35.3 1.69 59.65
18*18*2mm MS pipe kg. 5 35.3 176.5 1.0048 177.34

Above masonry wall behind secondary block


25.4*25.4*2.6mm MS Post kg. 30 1.1 33 1.69 55.77
25.4*25.4*2.6mm MS Top Rail kg. 1 37.57 37.57 1.69 63.49
18*18*2mm MS pipe kg. 5 37.57 187.85 1.0048 188.75

Total Ms pipe kg. 2405.7 Not proper welding and finishing


15.5 METAL WORK GATE
Sqm. 1 4.6 2.6 11.96

Total gate Sqm. 11.96


15.6 FENCING WORK
Boundary wall beside primary block Rm 1 190 190

TOTAL FENCING WORK Rm 190 to unsufficient work/barbed wire


18.1 INTERLOCKING BLOCK
In front of primary block Sqm. 1 7.9 2 15.8
-1 2.9 0.6 -1.74
Sqm. 1 37 3.3 122.1
Between Primar & Toilet-1 Sqm. 1 12.5 4.4 55
Around Toilet-1 Sqm. 1 11 2.1 23.1
In front of Library Block Sqm. 1 21.75 2.5 54.37
Sqm. 1 7.4 1.65 12.21

Total Sqm. 280.84


25 ENAMEL PAINT
Library Block to Middle block footpath railing Sqm. 1 47.66 0.9 42.89
In Front of canteen block Sqm. 1 9.8 0.9 8.82
Above wall from gate to secondary Sqm. 1 58.2 0.9 52.38
Pathway from primary to secondary Sqm. 1 64.8 0.9 58.32
5.8
Above Stone masonry wall in front of sec. Block Sqm. 1
0.9 5.22
Above shear wall of secondary block Sqm. 1 35.3 0.9 31.77
Above masonry wall behind secondary Sqm. 1 37.57 0.9 33.81

TOTAL ENAMEL PAINT Sqm. 233.21

26 Micropiling work behind middle block R.m 48 6 288

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST LANDSCAPE WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
GENERAL WORK, SITE CLEARANCE:Clearing and
grubbing of site for construction including uprooting of
vegetation, grass, brush wood, trees and sapplings of girth
1.1 upto 300 mm & removal upto a distance of 50 m as per Sq.M 3097.99 100.00 309,799.00
drawings, specifications and instructions

EARTHWORK IN EXCAVATION: Earthwork in


excavation in trenches, pits and foundations by machine or
appropriate technology in soft soil including existing debris
and brick bats of old structure, if any, upto specified depth
including shoring, dressing of sides, mechanical ramming of
bottom, dewatering in foundation pits and trenches, if
2.1 required, lifting of soil for minimum 3.5 m and stacking soil Cu.M 7500.376 200.00 1,500,075.20
to minimum height of 1m and lead upto 30m, all complete
as per drawings, specifications and nstructions

EARTWORK IN FILLING: Providing and placing of


random filling of excavated earth from cutting of slope and
stacked at site in 150mm thick layer in trenches, plinth or
under floor, sides of foundation and below beam at footing
covered area etc. including watering, mechanical ramming
2.2 and compaction of each layer, consolidation and dressing, Cu.M 3680.4065 200.00 736,081.30
all complete as per drawings, specifications and instructions.

SAND FILLING: Sand filling in plinth under floors,


including watering, ramming, consolidating and dressing, all
2.3 complete as per drawings, specifications and instructions. Cu.M 0 2,500.00 -

STONE WORK : Dry stone soling work in line and level,


including packing joints with sand dust, all complete as per
3.1 drawings, specifications and instructions Cu.M 218.98 4,000.00 875,920.00

STONE MASONRY WALL: Stone rubble masonry work in


1:4 cement and sand mortar with hard, tough, sound and
durable stone in wall, made to required line, level, shape,
3.2 size and plumb including setting out, drain outlet, curing of Cu.M 1176.371 7,500.00 8,822,782.50
the works and scaffolding etc. complete as per drawings,
specifications and instructions

BRICK WORK,FLAT BRICK SOLING: Flat brick soling


of local chimney bricks laid in line and level, including
4.1 packing joints with sand, complete as per drawings, Sq.M 503.2 800.00 402,560.00
specifications and instructions
FULL BRICK WORK: Brickwork in substructure and super
structure cement and sand mortar of mix 1:6 with first class
chimney-made bricks, in any size and shape of wall, made
4.2 to required line, level, shape and plumb including setting Cu.M 68.2 15,000.00 1,023,000.00
out, soaking of bricks, curing of the works and scaffolding,
etc. complete as per drawings, specifications and
instructions.

AAC(Autoclaved Aerated Concrete) BLOCK WORK:


Providing and laying of Autoclaved Aerated Concrete Block
(600*200*200 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.1 required line, level, shape and plumb including setting out, Sq.M 0 1,800.00 -
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

5.2)AAC(Autoclaved Aerated Concrete) BLOCK WORK:


Providing and laying of Autoclaved Aerated Concrete Block
(600*200*100 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.2 required line, level, shape and plumb including setting out, Sq.M 0 2,000.00 -
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

5.3)AAC(Autoclaved Aerated Concrete) BLOCK WORK:


Providing and laying of Autoclaved Aerated Concrete Block
(600*200*150 ) work made with cement mortar 1:4 (1
cement: 4 coarse sand) of any size and shape, made to
5.3 required line, level, shape and plumb including setting out, Sq.M 0 1,100.00 -
cutting of block and scaffolding, etc. complete as per
drawings, specifications and instructions.

CONCRETE WORK,PCC OF GRADE M10: Plain cement


concrete (PCC) of grade M10 (1:3:6 with 1 cement, 3 coarse
sand and 6 aggregate of 19 mm and down grade) in
6.1 foundation base including mixing, laying, compacting, Cu.M 171.5045 10,000.00 1,715,045.00
finishing, curing, laid to exact line, level and dimensions,
inclusive ofside

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST LANDSCAPE WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
PCC FOR RCC OF GRADE M25: Structural concrete (PCC
for RCC) of Grade M25 (1:1:2)works with approved
quality of cement, sand and well graded aggregate in any
form, size, shape and level including batching and mixing
6.2 with machine, laying including compaction with vibrating Cu.M 0 20,000.00 -
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

PCC FOR RCC OF GRADE M20: Structural concrete (PCC


for RCC) of Grade M20 (1:1.5:3)works with approved
quality of cement, sand and well graded aggregate in any
form, size, shape and level including batching and mixing
6.3 with machine, laying including compaction with vibrating Cu.M 261 17,000.00 4,437,000.00
machine, curing, testing and finishing, all complete as per
drawings, specifications and instructions.

FORMWORK: Placing plyboard form work with steel


props, shuttering, centering in horizontal/Vertical surfaces
like slab, beams, column, wall, stair etc. for all RCC works
7.1 of any shape, size and at any level and removal after Sq.M 1134.88 850.00 964,648.00
completion

REINFORCEMENT WORK: Providing and placing steel


reinforcement bar tested grade Fe-500 equivalent NS, for
RCC work including bending, binding with anneal wire and
8.1 placing in position, all complete as per drawings, kg 28852.8825925926 110.00 3,173,817.08
specifications and instruction

9.1)FLOORING WORK,PLASTIC
9.1 LAYING: Supplying and laying 500 gauge plastic sheet in Sq.M 0 50.00 -
floor as per specificatio and instruction
9.2)SCREEDING: Providing and placing 38 mm thick Plain
cement concrete of grade M15 (1:2:4 with 1 cement, 2
coarse sand and 4 aggregate chips) in the floor base mixing,
laying, compacting, finishing, curing, laid to exact line level
9.2 , surface chipping and dimensions (floor concrete is laid in Sq.M 86.25 500.00 43,125.00
alternate panels of 1 m x 1 m) inclusive of shuttering
complete as per drawings, specifications and instructions

9.3)CEMENT PUNNING: Providing


and laying 3 mm cement punning in floor , laying in
9.3 Sq.M 0 200.00 -
required pattern, line

9.4)CEMENT SKIRTING: Providing


and placing cement skirting 125mm height of grade M15
(1:2:4 with cement, 2 coarse sand and 4 aggregate
9.4 ) in wall ,mixing, laying, compactig, finishing, curing, laid R.M 0 100.00 -
to exact line level and dimension all complete as per
drawing, specification and instructions

9.5)TILE LAYING ON FLOOR:


Providing and laying approved brand quality, pattern and
color, ceramic mat finish tile (Low range) on floor over
9.5 cement mortar of mix 1:3 backing and filling joints (epoxy Sq.M 0 2,800.00 -
grout) complete as per drawings, specifications and
instructions.(Base rate: NRs 100)

9.6)TILE LAYING ON TOILET:


Providing and laying approved brand quality, pattern and
color, ceramic glazed tile in wall and ceramic mat finish tile
9.6 (Low range) on floor of toilet over cement mortar of mix 1:3 Sq.M 0 3,000.00 -
backing and filling joints (epoxy grout) complete as per
drawings, specifications and instructions.(Base rate: NRs
100)

10.1)FINISHING WORK,
EXTERNAL PLASTER: Providing and applying '10.5 mm
thick cement plastering with 1cement : 4 sand mortar in
outer surface any level size and shape of wall, column,
ceiling, band, blocks, etc inclusive of waterproofing
10.1 compound, dusting, throating, etc as required including Sq.M 518.27 400.00 207,308.00
racking, hacking, watering, cleaning of base, plastering to
plumb, line, level, smooth etc. and curing complete as per
drawings, specifications and instructions.

10.2)INTERNAL PLASTER:
Providing and applying'10.5 mm thick cement plastering
with 1cement : 4 sand mortar in inner surface except ceiling
any level size and shape of wall, column, band, blocks, etc
inclusive of dusting, throating, etc as required including
10.2 racking, watering, hacking, cleaning of base, plastering to Sq.M 0 450.00 -
plumb, line, level, smooth etc. and curing, all complete as
per drawings, specifications and instructions.

10.3)CEILING PLASTER: Providing


and applying 12.5 mm thick cement plastering with 1cement
10.3 : 4 sand mortar in Ceiling any level size and shape of Sq.M 0 500.00 -
ceiling inclusive of dusting,

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST LANDSCAPE WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
10.4)PLASTER ON RCC LINTEL
WITH CORNICE: 'Providing and applying 12.5 mm thick
cement plastering with 1cement : 4 sand mortar in RCC
Lintel with cornice inclusive of dusting, throating, etc as
10.4 required including racking, watering, cleaning of base, R.M 0 3,000.00 -
plastering to plumb, line, level, smooth etc. and curing, all
complete as per drawings, specifications and instructions.

10.5)EMULSION PAINT: Providing


and applyibg two coat of emulsion paint in mat finishing
10.5 over two coat of primer, finished including surface Sq.M 0 200.00 -
preparation all complete as per drawings, specifications and
instruction
10.6)WEATHER COAT: Providing and applying two coat
of weather coat (Apex or equivalent) over required coat of
10.6 primer, finished including surface preparation all complete Sq.M 10.08 250.00 2,520.00
as per drawings, specifications and instruction

11.1)DOOR,WINDOWS WORK/UPVC SLIDING


WINDOWS: Providing and fixing standard UPVC sliding
window without net (frame 50x80mm, sash 58x36mm white
11.1 colour with 5mm glass) along with patented standard Sq.M 0 8,000.00 -
hardwares like roller, gaskets, brush seal, moon locks etc all
complete as per drawings and specifications.

11.2)UPVC TOP HUNG


WINDOWS: Providing and fixing standard UPVC top hung
window (frame 60x60 mm, sash 60x104 mm, white colour
11.2 with 5 mm glass) along with patented standard hardwares Sq.M 0 8,000.00 -
like roller, gaskets, brush seal, moon locks etc all complete
as per drawings and specifications.

11.3)UPVC DOUBLE DOOR:


Providing and fixing standard UPVC double door (frame
60x60mm, sash 60x104mm white colour with 5mm glass)
11.3 along with patented standard hardwares like roller, gaskets, Sq.M 0 10,000.00 -
brush seal, moon locks etc all complete as per drawings and
specifications.

11.4)UPVC SINGLE DOOR:


Providing and fixing standard UPVC single door with full
panel (frame60x60mm, sash 60x104mm white colour with
11.4 5mm glass) along with patented standard hardwares like Sq.M 0 7,000.00 -
roller, gaskets, brush seal, moon locks etc all complete as
per drawings and specifications.

12.1)ROOFING WORK,CGI
ROOFING SHEET: Providing and fixing in position 24
gauge medium (0 .5 mm thick) corrugated CGI sheet over
12.1 roof truss with minimum 80 mm side laps and 200 mm end Sq.M 0 1,319.17 -
laps, inclusive of nuts and bolts, 8 mm 'J' hooks, washers,
GI cup washers, all complete as per drawings, specifications
and instruction

12.2)CGI ROOFING SHEET ON


RIDGE: Providing and fixing in position 24 gauge medium
(0 .5 mm thick) CGI sheet over roof truss in ridge with
12.2 minimum 80 mm side laps and 200 mm end laps, inclusive R.m 0 1,009.52 -
of nuts and bolts, washers, GI cup washers, all complete as
per drawings, specifications and instruction

12.3)GI GUTTER: providing and fixing in position color


plain GI sheet for gutter 150mmX450mm, inclusive of nuts
12.3 and bolts, washers, all complete as per drawings, R.m 0 1,000.00 -
specifications and instruction.
13.1)FALSE CEILING WORK,PVC
BOARD: Providing and fixing suspended PVC board false
ceiling, with necessary provisions for light fittings, light
13.1 boxes, where required finally finished with two coat acrylic Sq.M 0 1,500.00 -
emulsion paint, all complete as per drawings, specifications
and instructions.

14.1)MISCELLANEOUS WORK,
WATER PROOFING: Providing and placing 20 mm thick
cement sand mortar (1:2) mixing with wate proof
14.1 compound in the floor base mixing, laying, compacting, Sq.M 0 400.00 -
finishing, curing, laid to exact line level and dimensions
complete as per drawings, specifications and instructions

14.2)INSULATION WORK:
Providing and installing Insulation under CGI roofing sheet
14.2 with Insulation shield of 12mm thickness one sided and Sq.m 0 200.00 -
chicken wire mesh all completeas per drawing and
specifications.
15.1)METAL WORKS,BLACK
15.1 TUBULAR PIPE: Supplying, fabricating and fixing black Kg 0 150.00 -
pipe (Square or circular) work /Truss with
15.2)MS PIPE: Supplying, fabricating and fixing metal
15.2 work of different angles MS Pipe with one coat primer as Kg 2405.7 150.00 360,855.00
shown in drawing all complete

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST LANDSCAPE WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
15.3)ROLLING SHUTTER:
Providing and fixing rolling shutterof 16-19 Gauge cold
rolled MS lathe interlocked throughout their entire length
and joined together at the end by end locks and mounted on
specially designed pipe shaft with brackets, side guides and
15.3 arrangements for inside and outside locking,with push and Sq.m 0 4,000.00 -
pull operation, complete supplying, fixing and painting with
two coats of approved plastic emulsion paint.

15.4)HOT ROLLED STEEL


SECTION: Supplying, fabricating and fixing metal work of
15.4 different Hot Rolled Steel sections with one coat primer as Kg 0 150.00 -
per drawings and specifications all complete

15.5)METAL WORK,METAL
GATE: Supplying, fabricating and fixing in position, metal
gates of standard sections consisting of angles, pipes,
15.5 flats,etc. including one coat primer and one coat enamel Sq.M 11.96 7,000.00 83,720.00
paint as per drawings, specifications and instructions all
complete

15.6)FENCING WORK: Providing and fixing of ISA


50x50x5 mm along with 25x25x5 flat and M8x40 bolts at
15.6 300mm spacing to fix 10 S.W.G.G.I chain link with hole R.M 190 2,200.00 418,000.00
size 60x60 mm upto 3m height and 3 lines of barbed wire at
top.
16.1)EXPANSION JOINT WORKS/PLINTH LEVEL:
Suuply
and fixing of expansion joint at level of 100% non porous
flexible element allowing movement in all directions,
16.1 supported by aluminium framing and covering the top by R.M 0 4,500.00 -
aluminium sheet and flused to required floor level all
complete as per drawing, specification and instruction.

16.2)EXPANSION JOINT
WORKS/SLAB: Supply and fixing of expansion joint at
floor level of aluminium base supported by alumunium
16.2 framing,fixed on one side by threaded screw and flushed to R.M 0 4,500.00 -
required floor level and dimension all complete as per
drawing,specification and instruction

16.3)EXPANSION JOINT WORKS/ENDS OF WALL:


16.3 Supply R.M 0 4,500.00 -
17.1)CHAIN LINK VENTILATION
WORK: Supplying, fabricating and fixing in position of 10
S.W.G.I. woven wire ventilation with hollow square pipe
framing of size 18x18x1.0 mm on all sides with proper
17.1 welding on site, including one coat primer and one coat Sq.M 0 4,000.00 -
enamel paint on frames as per drawings, specifications and
instructions all complete

18.1)LAND DEVELOPMENT WORKS, INTERLOCKING


BLOCKS: Supplying and laying of 60 mm thick heavy duty
interlocking paving blocks of approved colour and quality
on the 50 mm thick stone dust with surface grading,
18.1 levelling and soil compaction base in driveways and parking Sq.M 280.84 2,000.00 561,680.00
areas, complete as per specifications and drawings.

18.2)RAILING WORKS: Supply,


fabrication and fitting of Railing works with MS square pipe
framing and 10 S.W.G.I. wire mesh of height 1.05m
18.2 including excavation, brickwork, plaster and two coats R.M 0 3,000.00 -
enamel paint all complete as per drawings and specifications

18.3)GUIDE RAMP: Supply,


fabrication and fitting of Guide Ramp-Utility Guardrail for
the disabled with MS tubular pipes at regular intervals of
18.3 height 1.05m including two coats enamel paint all complete R.M 0 6,500.00 -
as per drawings and specifications

18.4)APRON DRAIN: Construction of Apron drain along


the perimeter of buildings and retaining structures including
18.4 excavation, Brick soling, PCC and half brick thick apron R.M 0 20,000.00 -
walls with plaster all complete as per drawings and
specifications
18.5)TACTILE PAVING: Providing
and laying approved brand quality, pattern and colour of
Tactile paving tile on floor over constructed cement mortar
18.5 of mix 1:3 backing and filling joints (epoxy grout) at R.M 0 3,500.00 -
straight path and turning points of size 300x300x40mm, all
complete as per drawings, specifications and instructions.

DEMOLITION WOKS: Demolition of existing building


19.1 and toilet blocks PS 1 1,000,000.00 1,000,000.00

RELOCATION WOKS: Relocation of temple from existing


site and to be constructed at a new location outside of the
20.1 school site as per drawing,specification and instructions. PS 0 300,000.00 -

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST LANDSCAPE WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Quantity Rate Amount Remarks
no
INSURANCE PREMIUM
21.1 PS 1 224,281.00 224,281.00

Floor Hardener:providing,sprinkling,laying &applying


Manually two layer in floor,applied each layer with 1.5 to
2.5kg /m2 in required pattern,blended in,smoothed,over by
22.1 power trowelling,in line and level including curing all Sq.M 0 400.00 -
complete as per drawing,specification and instruction.
(Mapetop,N,AR6 or equivalent)

Cement Board:providing and fixing in position 10mm


water proofed cement board in exterior (one side)surface
inclusive minimum75mm GI metal framewith grooving and
23.1 fixing of fastner ,washer,nuts,and bolts,all complete as per Sq.M 0 2,700.00 -
drawings,specifications and instructions.

FLOOR TILE (600*600)


24 Sq.m. 0 2,500.00 -

ENAMEL PAINT
25 Sq.M 233.21 286.00 66,698.06

PILE WORK : Construction of pile work including


26 excavation, reinforcement and concreting work. Rm 0 17,000.00 -

DISMANTLING WORK
27 0 -

CONCRETE DISMANTLING
27.1 Cu.M 0 8,500.00 -

BRICKWALL DISMANTLING
27.2 Cu.M 0 2,000.00 -

Micropiling work
28 R.m 288 2,653.58 764,231.04

TOTAL AMOUNT
27,693,146.18

Total Item Price 27,693,146.18

Discount @2% 553,862.92

Sub Total 27,139,283.26

VAT @13% 3,528,106.82

Grand Total 30,667,390.08

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

MB ELECTRICAL WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

22W LED
LIGHT FAN 15 amp 13 amp network telephone CC AC Junction 12W LED
BLOCK ROOM DETAILS Tube Fan Remarks
POINT POINT PP PP point point Camera Point Box Downlight
Light

GROUND FLOOR 1
UKG 8 2 2 1 1 1 2
LKG 8 2 3 1 1 1 2
NURSARY 8 2 3 1 1 1 2
SLEEPING ROOM 3 1 1 0 1 1
TOILET 11 0 1 0 4
PASSAGE 10 0 1 1 1 4

FIRST FLOOR 1
1A 8 2 4 1 1 1 2
PRIMARY
1B 8 2 3 1 1 1 2
BLOCK
2A 6 4 3 1 1 1 2
2B 8 4 3 1 1 1 2
PASSAGE 11 0 3 0 0 0 4

SECOND FLOOR 1
3A 8 3 2 1 1 1 2
3B 8 3 2 1 1 1 2
TEACHER'S ROOM 3 1 2 1 3 3 2 1
HALL 12 6 8 0 1 1 4 2
PASSAGE 11 0 2 0 6
Total 131 32 43 11 13 13 1 0 3 18 25 4
LOWER BASEMENT 1 0 0 0

BASEMENT 1
OPT-1 2 2 3 1 1 1 2
OPT-2 4 2 3 1 1 1 2
OPT-3 2 2 3 1 1 1 2
OPT-4 4 2 3 1 1 1 2
PASSAGE 5 0 0 0 0 0 2

GROUND FLOOR 1
9A 8 2 3 1 1 1 2
SECONDARY 9B 8 2 3 1 1 1 2
BLOCK
10A 8 2 3 1 1 1 2
10B 8 2 3 1 1 1 2
PASSAGE 11 0 0 0 0 0 4

FIRST FLOOR
11A 8 3 3 1 1 1 2
11B 8 3 3 1 1 1 2

4 1 3 1 1 1 1 2 1 Additional 1 nos power point


HEAD SIR ROOM PIPING ON FLOOR
6 3 3 2 7 7 2 4 3 Additional 10 nos. power point
TEACHER'S ROOM PIPING ON FLOOR
PASSAGE 11 0 2 0 7
Total 98 26 38 13 18 18 0 3 2 13 26 4
GROUND FLOOR
S-1 4 1 2 1 1
S-2 4 1 2 1 1
S3 4 1 2 1 1
S-4 4 1 2 1 1
S-5 4 1 1 0 1
Toilet 1 0 0 0 1

FIRST FLOOR 1

9 3 6 5 10 10 4 5 2
LIBRARY OFFICE ROOM Additional 20 poer socket piping
BLOCK DINING ROOM 2 1 3 2 1
TOILET 4 0 0 0 2
INSIDE PASSAGE 3 0 1 0 1
OUTER PASSAGE 5 0 0 0

SECOND FLOOR 1
LIBRARY 9 3 5 4 1 1 4 2
E-LIBRARY 2 1 2 1 1 1 1
TOILET 3 0 0 0 2
INSIDE PASSAGE 3 0 1 0 1
OUTER PASSAGE 4 0 0 0
TOTAL 65 13 27 16 12 12 0 4 2 7 16 4
GROUND FLOOR 1
4A 8 2 3 1 1 1 2
4B 8 2 3 1 1 1 2
5A 8 2 3 1 1 1 2
5B 8 2 3 1 1 1 2
PASSAGE 11 0 2 0 0 0 5 4

FIRST FLOOR 1
6A 8 2 3 1 1 1 2
MIDDLE 6B 8 2 3 1 1 1 2
BLOCK 7A 8 2 3 1 1 1 2
7B 8 2 3 1 1 1 2
PASSAGE 11 0 2 0 0 0 4

SECOND FLOOR 1
8A 8 2 3 1 1 1 2
8B 8 2 3 1 1 1 2
TEACHER'S ROOM 3 1 2 1 0 0 2 1
HALL 12 6 7 4 3 3 4 2
PASSAGE 11 0 2 0 0 0 6

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

MB ELECTRICAL WORK
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

22W LED
LIGHT FAN 15 amp 13 amp network telephone CC AC Junction 12W LED
BLOCK ROOM DETAILS Tube Fan Remarks
POINT POINT PP PP point point Camera Point Box Downlight
Light

TOTAL 120 25 42 14 12 12 5 0 3 14 26 3
MALE TOILET 3 0 0 0 1
TEACHER'S MALE TOILET 2 0 1 0 1
TOILET-1 FEMALE TOILET 3 0 1 0 1
TEACHER'S FEMALE TOILET 2 0 0 0 1
OUTSIDE BUILDING 4 0 0 0
TOTAL 14 0 2 0 0 0 0 0 0 4 0 0
TOILET-2 MALE TOILET 6 0 0 0 3
FEMALE TOILET 4 0 0 0 3
TOTAL 10 0 0 0 0 0 0 0 0 6 0 0

GRAND TOTAL 438 96 152 54 55 55 6 7 10 62 93 15

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST ELECTRICAL WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ No. Description of work Total Qty. Rate Amount Remarks

ELECTRICALS (Supply and instalation,testing and


1.3 commission)
Concealed wiring
1.3.1

Light and fan points wiring from distribution boards to


switch boxes and switch boxes to light fixtures and fans
with 2x 2.5 +1x 1.5 sq mm PVC insulated cu wire through
1 20mm dia. HDPE conduit including modular type switch/ pts 534 3,000.00 1,602,000.00
electronic fan control switch

15 amp Power points wiring from distribution boards to 2 -


3 outlets per circuit with 2x4+1x 2.5 sq mm PVC insulated
2 copper wires through 25mm dia. HDPE conduit including pts 152 4,000.00 608,000.00
all necessary materials for point wiring excluding power
sockets.
13 amp Power points wiring from distribution boards to 2 -
3 outlets per circuit with 2x2.5+1x 1.5 sq mm
3 PVC insulated copper wires through 25mm dia. HDPE pts 54 2,500.00 135,000.00
conduit including all necessary materials for point wiring
excluding power sockets.
Supply and installation of 20mm HDPE pipe for electrical
4 works as future extension. pts 154 2,198.80 -

Supply instalation testing,commissioning of modular


1.3.2 type switch sockets,in metal box.
Supply instalation testing,commissioning of light fixture
1.3.2.1 complete with lamps/tubes.
12 W LED down light surface mounted 6" dia with inbuilt
1 LED Driver & lumen output not less than 90 lumen per sets 62 1,500.00 93,000.00
watt.
22 watt LED Tube Light fixture surface batten type with
2 inbuilt LED Driver lumen efficiency >110 lumen/watt sets 93 1,500.00 139,500.00

12 watt LED Bulk head light fixture with necessary fixing


3 accessories with inbuilt LED driver and lumen efficiency sets 0 2,500.00 -
not less than 90 lumen/watt
18 watt LED Tube Light fixture suspendent batten type with
4 inbuilt LED Driver lumen efficiency > 110 lumen/watt sets 0 3,500.00 -

9 watt LED wall light fixture with necessary fixing


5 accessories with inbuilt LED driver and lumen efficiency sets 0 5,000.00 -
not less than 90 lumen/watt
9 watt LED mirror light fixture with necessary fixing
6 accessories with inbuilt LED driver and lumen efficiency sets 0 15,000.00 -
not less than 90 lumen/watt
30 watt LED hanging floor light fixture with necessary
7 fixing accessories with inbuilt LED driver and lumen sets 0 25,000.00 -
efficiency not less than 110lumen/watt

15 amp 3 Pin Power Socket with safety shutter, modular


1 switch and required modular plate nos. 152 1,500.00 228,000.00
13 amp Universal Pin Power Socket with safety shutter,
2 modular switch and required modular plate nos. 54 1,500.00 81,000.00

Supply Installation testing commissioning of fans with


1.3.3 necessary epansion bolts down rods electoni

Supplying laying testing and commissioning of following


1.3.3.1 main/ sub mains 1100V/ 65V Armoured
4 core 35 sq.mm Al armoured PVC cable from NEA
Tapping point to Main Electrical Panel via NEA meter to
be laid aerially on electrical pole and partly on building
1 structure with switable cable clamp, shackle insulator with Rm 75 500.00 37,500.00
D-iron, Nut bolt as per NEA rules and regulation .

4 core 25 sq.mm Al armoured PVC cable+ 1x4 sq mmm


copper cable from Main controle Panel to primary block,
secondary block, higher secondary block and community
2 block of main distribution board through underground Rm 280 400.00 112,000.00
32mm dia.
HDPE conduit all complete as per specification, drawings
and instruction of the Consultant.

2core 16 sq.mm Al armoured PVC cable + 1x4 sq mmm


copper cable from Main controle Panel to multpurpose
block board through underground 32mm dia. HDPE
3 conduit all complete as per specification, drawings and Rm 0 300.00 -
instruction of the Consultant.

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST ELECTRICAL WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ No. Description of work Total Qty. Rate Amount Remarks

2core 10 sq.mm Al armoured PVC cable + 1x4 sq mmm


copper cable Main controle Panel to toilet block through
4 underground 32mm dia. Rm 50 250.00 12,500.00
HDPE conduit all complete as per specification, drawings
and instruction of the Consultant.
2core 10 sq.mm Al armoured PVC cable 1x4 sq mmm
copper cable primary block to toilet block through
5 underground 32mm dia. HDPE conduit all complete as per Rm 40 200.00 8,000.00
specification, drawings and instruction of the Consultant.

2 x 6 sq.mm.+1 core 4 sq.mm. copper armored PVC cable


from primary block Main distribution board to GF, FF and
SF distribution board through underground 32mm dia.
6 HDPE conduit all complete as per specification, drawings Rm 132 1,000.00 132,000.00
and instruction of the Consultant.

2 x 6 sq.mm.+1 core 4 sq.mm. copper armored PVC cable


from secondary block Main distribution board to GF, FF
and SF distribution board through underground 32mm dia.
7 HDPE conduit all complete as per specification, drawings Rm 155 1,000.00 155,000.00
and instruction of the Consultant.

2 x 6 sq.mm.+1 core 4 sq.mm. copper armored PVC cable


from higher secondary block Main distribution board to
GF,FF and SF distribution board through underground
8 32mm dia. HDPE conduit all complete as per specification, Rm 140 1,000.00 140,000.00
drawings and instruction of the Consultant.

2 x 6 sq.mm.+1 core 4 sq.mm. copper armored PVC cable


from comunity block Main distribution board to BF, GF,FF
and SF distribution board through underground 32mm dia.
9 HDPE conduit all complete as per specification, drawings Rm 125 1,000.00 125,000.00
and instruction of the Consultant.

1200 mm 3 blade ceiling fan with 2 moudule fan speed step


1 regulator sets 15 4,000.00 60,000.00
300mm dia heavy duty exhaust fan with metallic louvere
2 sets 0 6,000.00 -
Supply, delivery and installation of 16mm heavy metal grip
having round threaded hook at bottom for Ceiling Fan with
3 all necessary drilling, hammering and making good sets 58 750.00 -
apperence etc.

Mains control Panel ( Supply Installation testing


1.3.4 commissioning of cubical floor mounting type main)

Main control panel comprising of (Amp, TP, DP,MCCV,


1 Fuse, Meters,panel board with fixing testing and set 0 40,000.00
commissioning)

2 MDB
Supply, delivery, installation, and
commissioning of Main distribution panel floor mountable
made of 14
SWG MS metal sheet including neutral bar, phase bar and
earth bar with adequate space for incomming and outgoing
cable with complete internal wiring ( DB MAIN)

125A TP MCCB 36 KA ICS for main incomer -1nos.


80A TP MCCB 25 KA ICS for spare -1nos.
40A TP MCCB 25 KA ICS for Primary Block MDB -1nos.

40A TP MCCB 25 KA ICS for Secondary Block MDB -


1nos.
set 1 188,483.00 188,483.00
40A TP MCCB 25 KA ICS for Middle Block MDB -1nos.

40A TP MCCB 25 KA ICS for Library Block MDB -1nos.

32A TP MCCB 25 KA ICS for UPS -1nos.


40A TP MCCB 25 KA ICS for Pump -1nos.
40A TP MCCB 25 KA ICS for Spare -1nos.
TPN copper bus bar with earth bar - 1Set
Voltmeter - 1Se
Ammeter - 1Se
Selector switch - 1Se
CT coil - 1Se
Indicator lamp with MCB - 1Se
3 Junction Box

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST ELECTRICAL WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ No. Description of work Total Qty. Rate Amount Remarks

Supply, delivery, installation, and


commissioning of Distribution board wall mountable made
of 16 SWG MS metal sheet with adequate space
(10"x10"x4") for incomming and outgoing cable with set 10 1,757.64 17,576.40
complete internal wiring as per drawing,specification and
instruction all complete.

Distribution Board ( Supply installation testing


1.3.5 commissioning of flush mounting type of sub Distr)
MDB-MH (Amp, TP, DP, MCCV,
1 Fuse, Meters, panel board, with fixing testing and set 1 40,000.00 40,000.00
commissioning)
DB-GF-SHOP-1,DB-GF-SHOP-2, DB-GF-SHOP-3,DB-
GF-SHOP-4
2 &DB-GF-SHOP-5 (Amp, TP, DP, set 5 25,000.00 125,000.00
MCCV, Fuse, Meters, panel board, with fixing testing and
commissioning)
3 DB-FF/DB-SF (All complete) set 2 20,000.00 40,000.00
4 DB-MH (All complete) set 1 20,000.00 20,000.00
5 MDB-P (All complete) set 1 10,000.00 10,000.00
DB-GF-1/DB-FF-1/DB-FF-2/DB-SF-
6 2 (All complete) set 4 10,000.00 40,000.00
7 DB-GF-2/DB-SF-1 (All complete) set 2 - -
8 MDB-S (All complete) set 1 - -
DB-GF-1/DB-FF-1/DB-FF-2/DB-SF-
9 2 (All complete) set 4 - -
10 DB-GF-2/DB-SF-1 (All complete) set 2 - -
11 MDB-S (All complete) set 1 - -
DB-GF-1,DB-GF-2,DB-FF-1,DB-FF- 2,DB-SF-1, & DB-
12 SF-2 (All set 6 - -
complete)
13 DB-T-2(GF) (All complete) set 1 - -
DB-T-1(GF),DB-T-2(GF) & DB-T-2
14 (FF),( all complete) set 2 - -

1.3.6 Communication System Works and Networking

Supply, installation and wiring for Networking Terminals ,


with partly surface installed in 25 mm HDPE conduit and
cable tray with CAT 6 E 4 pair cable including required
chiselling / chasing of wall , and making good of the same,
1 with 1 meter long spare CAT 6 Cable at both ends as per points 4 - -
specification, drawings and instruction of the Consultant.

Supply and installation of Computer Outlets RJ 45 , CAT 6 ,


2 with required facia plate and flush mounting GI boxes. nos. 4 - -

Supply , installation & testing of 8 Ports 10/10000 Base


Unmanaged computer switch with rack.(at Principle room),
3 all complete as per specification, drawings and instruction set 1 - -
of the Consultant.

1.3.7 Telephone System / Communication


Supply, installation and wiring for Telephone Terminal RJ
11 2 pair 0.5 mm copper telephone wire in 20 mm dia
HDPE Conduit laid partly in the conduit and partly in cable
1 tray with total average length of individual point at 25 points 4 - -
meters from Junction or the main distribution frame
including chiselling / chasing of wall / floor and making
good of the same.

Supply and installation of Telephone Outlets , RJ11 with


2 required flush mounting GI boxes. nos. 4 - -
Supply, delivery, installation, testing and commissioning of
10 pair Telephone Junction with lockable cover and Krone
3 Connector with tagging facilities nos. 1 - -

Supply and installation of 3 line input and 8 line output


PABX telephone exchange system with 1 set of
4 programmable master telephone set with all necessary set 1 - -
accessories as per specification, drawings and instruction of
the Consultant.

Earthing And Lightening System ( Supply Installation


1.3.8 Testing of Earthing System All Complete)

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST ELECTRICAL WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5

BOQ No. Description of work Total Qty. Rate Amount Remarks

Supply, installation, testing and commissioning of copper


plate earthing stations making earth pits, earthing with
Copper earth plate 600 mm x 600 mm x 3 mm thick
including funnel, char-coal/coke, salt, all earth work.
Providing masonry enclosure with 10 mm thick C.I. cover
1 plate having locking arrangement and 25 mm dia 2 m long set 2 - -
G.I. pipe perforated for watering, disconnecting/ testing
links etc as per IS –3043 complete as required.

Lightning Protection Air Terminal Lightning Arrester ( 20


2 mm dia. 1.5 Mtr Height, solid copper rod ) set 2 - -

50 sq. mm. stranded bare copper conductor in 32mm dia


3 HDPE pipe from Air terminal to earthing point including rm 50 - -
support clamps all complete.

Supply Installation of 9M Steel Tubulor Pole Including


1.3.9 ecavation backfilling and compaction
Galvanized 9 Meter Steel Tubular Pole ( Bottom 134mm
dia,3300mm ht,155mm dia 2250mm ht,90mm dia 2250 ht
1 and 76mm dia 1650mm ht with over lapping of set 13 - -
200mm,150mm, 100mm respectively Approx. 100 kg)

2 150Wp monocrystalline PV module set 22 - -


30 watt led solar street light builtin charge controller with
3 dust to down sensor set 22 - -
4 MS street light fixture arm set 22 - -
Solar panel stand,G.I. Battery box , battery stand ,wiring
5 material and other minor materials for installation. set 15 - -

Solar Lithium Ion Batteries (60AH@c10,12 Volt)


6 set 15 - -

TOTAL AMOUNT
4,149,559.40

Total Item Price 4,149,559.40

Discount @2% 82,991.19

Sub Total 4,066,568.21

VAT @13% 528,653.87

Grand Total 4,595,222.08

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

MB SANITARY FITTING
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
Wall
Toilet Multi Rain Water
Water hung Soap Commode Bib Robe Towel Mirror(24 Cowel Sewer WWC Septic
BLOCK ROOM DETAILS Pan Urinal Paper Floor Shower Inlet Soak Pit Remarks
Closet Wash Disc spray Cock Hook Rail "*18") Vent manhole Chamber Tank
Holder Trap Chamber
Basin
PRIMARY Toilet 1 8 0 1 1 2 1 8 1 1 1 5 0 1 3 3 0 1 1
BLOCK Water Trough 0 0 4
Total 1 8 0 1 1 2 1 12 1 1 1 5 0 1 3 3 0 1 1
GROUND FLOOR
Toilet 1 1 1 1 1 1 2 2 1 1
FIRST FLOOR
LIBRARY
Toilet 2 1 2 1 2 1 3
BLOCK
SECOND FLOOR
Toilet 2 2 2 2 2 1 2 2

TOTAL 5 0 0 4 5 4 5 0 0 0 2 6 2 0 2 2 0 1 1
GROUND FLOOR
MIDDLE BLOCK Water Trough 2 7 2

TOTAL 0 0 0 0 0 2 0 7 0 0 0 2 0 0 0 0 0 0 0
MALE TOILET 3 4 1
TEACHER'S MALE TOILET 1 1 1 2 1 3 5
FEMALE TOILET 9 4 1
TOILET-1
TEACHER'S FEMALE TOILET 1 1 1 2 1 4 5
Water Trough 5 6 1 3
Outside Building 3 5 1
TOTAL 2 13 1 3 2 9 2 21 0 0 1 15 0 0 5 1 0 0 0
MALE TOILET 6 8 3
FEMALE TOILET 1 7 1 1 1 1 7 1 2 2
TOILET-2
Outside Building 4 2 2 1 1 1

TOTAL 1 13 0 5 1 3 1 15 0 0 1 5 2 0 2 1 0 1 1
LANDSCAPE 7

GRAND TOTAL 9 34 1 13 9 20 9 55 1 1 5 33 4 1 12 7 7 3 3

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

MB SANITARY FITTING
Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
CPVC Pipe CPVC Ball Valve PVC Pipe
BLOCK/ DESCRIPTION Remarks
50mm 25mm 20mm 15mm 50mm dia 25mm dia 160mm 110mm 75mm 50mm
24.6 24 32.7 15 2 6 34.5 119.4 8.4 11.7
PRIMARY BLOCK

Total 24.6 24 32.7 15 2 6 34.5 119.4 8.4 11.7


21.9 3 18 75.9 6 5.55
LIBRARY BLOCK

0 0 21.9 0 0 3 18 75.9 6 5.55


75
MIDDLE BLOCK

Total 0 0 0 0 0 0 0 75 0 0
18 23.1 9.9 2 57.6 9.12 9
TOILET-1

Total 0 18 23.1 9.9 0 2 0 57.6 9.12 9


36.3 44.1 2.31 2 23.1 121.5 20.79 9.9
TOILET-2

Total 0 36.3 44.1 2.31 0 2 23.1 121.5 20.79 9.9


105.3
SECONDARY BLOCK

Total 0 0 0 0 0 0 0 105.3 0 0
LANDSCAPE
Pipe from Tank to Library 56.55 5.4 12
Pipe from Tank to Toilet-2 88.2 88.2 4 4
Pipe from Tank to Primary &Toilet-1 85.5 85.5
For Water supply 20
Pipe for drain from sec. to primary drain 66 8" pipe used

Total 230.25 199.1 12 0 4 4 66 0 0 0

GRAND TOTAL 254.85 277.4 133.8 27.21 6 17 141.6 554.7 44.31 36.15

Prepared By: Checked By: Verified By:


PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST SANITARY WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Total Qty. Rate Amount Remarks
no
1.2 Sanitary (Supply and Installation)

Providing and fixing in position of all work items with all


necessary fittings complete with testing and ready for
operation as per drawings, specifications, manufacturer's
recommendations and instructions.
The rate shall include for position marking, maintain line,
level or grade wherever required, sand filling/compaction,
earth cutting and backfilling, cutting, chasing of walls,
plasters or tiles etc. and making good and touching up to
restore to original conditions wherever instructed and
applicable for any of the items below. Sanitaryware:
Hindware/ Parryware/ Somany CP,
Fixtures: Hindware/ Parryware/ Jaquar, SWR Pipes:
Marvel/ Mangalam Ecodrain PVC,
Hot/Cold Water Supply Pipe and fittings: Marvel/
1 Managlam/ Hilltake CPVC, Set 9 8,000.00 72,000.00
Gun Metal Gate Valve: LEADER/SANT,
Ball Valve: Marvel/ Managlam/ Hilltake CPVC,
Plastic Water Tank: Nepatop/ Hilltake/ Mangalam,
A. SANITARY INSTALLATION:1.1)White glazed
earthernware close coupled Water Closet set with standard
bakelite seat cover, bracket, CP angular cock, PVC
connector pipe complete with testing and ready for
operation as per specifications and site engineer instructions
all complete

1.2) White glazed earthernware 580x480mm Orissa Pan


with 3/6 liters flushing cistern, trap pipe, pipe connector
2 with complete accessories including bracket, flushing pipe, Set 34 9,000.00 306,000.00
pipe
1.3) White glazed earthernware Wall- hung Large Flat back
Urinal complete with CP Push cock, Spreader, testing and
3 ready for operation Set 1 10,000.00 10,000.00

1.4) White glazed earthernware under-counter Hand wash


basin with
15 mm CP/PVC connectors with both ends couplings,
15mm CP angular cock -1 no, 15mm CP Presmatic pillar
4 cock, 32mm PVC bottle trap, waste coupling with testing Set 0 8,000.00 -
and ready for operation as per specifications and site
engineer instructions all complete

1.5) White glazed earthernware wall- hung Hand wash basin


with 15 mm CP/PVC connectors with both ends couplings,
15mm CP angular cock -1 no, 15mm CP Presmatic pillar
5 cock, 32mm PVC bottle trap, waste coupling with testing Set 13 7,000.00 91,000.00
and ready for operation as per specifications and site
engineer instructions all complete

1.6) White glazed earthernware Division Plate for Urinal


6 with wall brackets Set 0 5,000.00 -
1.7) Indian pattern bathroom accessories as per
7 specifications and site engineer instructions all complete set No. 9 1,400.00 12,600.00
i)CP Toilet Paper Holder heavy
8 ii)CP Soap Dish heavy No. 20 800.00 16,000.00
9 iii)CP Commode Spray with plastic head No. 9 1,500.00 13,500.00
10 iv)'CP Bib cock No. 55 15,000.00 825,000.00
11 v)CP Robe Hook No. 1 1,500.00 1,500.00
12 vi)CP Towel Rail Heavy (20 X 600mm) No. 1 1,500.00 1,500.00
1.8) 5 mm thick looking mirror of following size of Modi or
approved make with CP mirror screws and clips as per
13 specifications and site engineer instructions all complete No. 5 1,900.00 9,500.00
set.i)24"x18" Mirror
14 ii)48"x18" Mirror No. 0 1,500.00 -
15 1.9) PVC Multi-floor trap with cover No. 33 400.00 13,200.00
16 1.10) 110 mm PVC cowl vent No. 4 500.00 2,000.00
17 1.11) CP Shower rose with divertor and arm No. 1 1,300.00 1,300.00
B. WATER SUPPLY

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST SANITARY WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Total Qty. Rate Amount Remarks
no
INSTALLATION: 2.1) Chlorinated Poly Vinyl Chloride
(CPVC) pipes SDR-11 including MS clamps and brackets,
nails and hooks, fittings( Tees, Elbows,Unions etc) and all
necessary CPVC/Brass specials required for complete
installation, cutting, jointing, sealing of joints etc,
installation of pipes and specials including making holes
and cutting grooves on walls or floor and repairing the same
to its original finish. Pipes to be installed on trenches or
walls or floor or duct as per drawings, specifications and
instructions, cleaning of the system, testing and ready for
operation. The rate shall include for all labour and materials
18 required. The measurement shall be done for running feet, Rm 0 1,200.00 -
fittings etc not payable seperately. i) - 80 mm

19 ii) - 65mm Rm 0 1,000.00 -


20 ii) - 50 mm Rm 254.85 900.00 229,365.00
21 iv) - 40 mm Rm 0 600.00 -
22 v) - 32 mm Rm 0 500.00 -
23 vi) - 25 mm Rm 277.4 400.00 110,960.00
24 vii) - 20 mm Rm 133.8 350.00 46,830.00
25 viii) - 15 mm Rm 27.21 300.00 8,163.00
2.2) CPVC Ball Valve including jointing materials all
26 complete set as per specifications and site engineer's No. 0 600.00 -
instruciton. i) - 20 mm dia.
27 ii) - 32 mm dia No. 0 1,600.00 -
28 ii) - 25 mm dia No. 17 700.00 11,900.00
29 ii) - 50 mm dia No. 6 2,500.00 15,000.00
30 ii) - 80 mm dia No. 0 5,000.00 -
2.3) Electric centrifugal water pump with motor of capacity
40 liters per minute at 28m head (approx. 1 HP motor)
31 complete with starter, electric cable, check valve, automatic Set 10 34,000.00 340,000.00
pump controller with high and low level sensors and cable
etc. (one set stand- by)
2.4) 300 litres capacity solar water heater with 3 solar
collectors size 1000x2000mm complete with thermostat,
32 stands, pipe connections, valves, testing and ready for No. 0 25,000.00 -
operation
C. SEWER, VENT, RAIN AND WASTE WATER
INSTALLATION: 3.1) PVC SWR (Soil, Waste) eco- drain
pipes with all necessary ring gaskets, PVC fittings,
including MS clamps, hangers, cutting, jointing, sealing,
installation of pipes and specials including making holes
and cutting grooves on walls or floor and repairing the same
to its original finish. Pipes to be installed on trenches or
walls or floor or duct or hung to ceilings as per drawings,
33 specifications, manufacturer's recommendations, Rm 141.6 1,200.00 169,920.00
instructions, cleaning of the system, testing and ready for
operation. The rate shall include for all labour and materials
required. The measurement shall be done for running feet,
fittings etc not payable seperately. i) - 160 mm ED 6
kg/cm2

34 ii) - 110 mm ED 6 kg/cm2 Rm 554.7 1,000.00 554,700.00


35 iii) - 75 mm ED 6 kg/cm3 Rm 44.31 600.00 26,586.00
36 iv) - 50 mm ED 6 kg/cm4 Rm 36.15 400.00 14,460.00
3.2) Construction of brick masonry Sewer manhole of
internal diameter 600mm with 230mm thick brick masonry
in 1:4 cement mortar, 100mm thick RCC 1:2:4 slab cover,
37 600mm dia CI Manhole cover with frame (medium duty), No. 12 60,000.00 720,000.00
cement plaster inside, height varies from 300mm to
1000mm

3.3) Construction of brick masonry waste water collection


chamber of internal size 450x450mm (internal height varies
from 600 to 1500mm) with 230mm thick brickwork in 1:4
cement mortar, 100mm thick PCC M15 base, 150mm thick
RCC M15 slab cover, internal wall and floor finish with
38 12mm thick cement plaster 1:4, PCC M15 benching on no. 7 35,000.00 245,000.00
floor, 500x500mm dia CI manhole cover with frame
(Medium duty), earthwork in excavation, backfilling and
site clearance

Prepared by:
Checked by: Approved by:
PRITHVI NARAYAN SECONDARY SCHOOL
Tarakeswor-5, Kathmandu

ABSTRACT OF COST SANITARY WORK


Project: Construction and extension of School Building
Contract ID: 01-2075/076 PNSS
Location: Tarkeswor-5
BOQ item
Item Description Unit Total Qty. Rate Amount Remarks
no
3.4) Construction of brick masonry rain water inlet chamber
of internal size 450x450mm (internal height varies from 600
to 1500mm) with 230mm thick brickwork in 1:4 cement
mortar, 100mm thick PCC M15 base, 150mm thick RCC
M15 slab cover, internal wall and floor finish with 12mm
39 thick cement plaster 1:4, 450x450mm dia CI Rain inlet no. 7 25,000.00 175,000.00
cover with frame (Medium duty), earthwork in excavation,
backfilling and site

3.5) Construction of RCC septic tank of internal size 13'-


0"x5'-0"x4'-0" and 18" Free board as per drawings including
earthwork excavation, flat brick soling, P.C.C., R.C.C.
cover slab/baffles, walls and base, cement plaster with
40 punning on internal walls, slab bottom & top, medium duty job 3 70,000.00 210,000.00
CI 600 mm x 600 mm manhole cover pipe sleeves, etc., all
complete as per drawing, specifications and instructions.

3.6) Construction of soakpit of size 2000 mm clear


diameter, 1500 mm clear liquid height, 400 mm free board;
including earth work excavation & filling, 230 mm thick
honey-comb/solid Brick wall in 1:6 cement mortar, 125mm
thick R.C.C. slab cover with plaster, filling pit with graded
41 washed stone gravel, filling 300mm wide gap between wall job 3 55,000.00 165,000.00
and ground with coarse sand, etc., all complete as per
drawings, specification and instructions.

3.7) Construction of Recharge Pit made with RCC Rings


1200 mm dia and 6 m high complete with excavation, 150
42 thick RCC 1:2:4 slab cover, disposal of extra excavated Rm 0 40,000.00 -
material

TOTAL AMOUNT
4,417,984.00

Total Item Price 4,417,984.00

Discount @2% 88,359.68

Sub Total 4,329,624.32

VAT @13% 562,851.16

Grand Total 4,892,475.48

Prepared by:
Checked by: Approved by:

You might also like