Estimate of Electricity

The document outlines the cost estimate for the construction of an 11 KV HT line and associated infrastructure in various areas of Rolpa, Nepal. The total estimated material and labor cost, including VAT, is approximately 26,547,931.86 NRs. Detailed breakdowns of material and labor costs are provided for both HT and LT line constructions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views2 pages

Estimate of Electricity

The document outlines the cost estimate for the construction of an 11 KV HT line and associated infrastructure in various areas of Rolpa, Nepal. The total estimated material and labor cost, including VAT, is approximately 26,547,931.86 NRs. Detailed breakdowns of material and labor costs are provided for both HT and LT line constructions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

NEPAL ELECTRICITY AUTHORITY

DISTRIBUTION & CONSUMER SERVICE DIRECTORATE


NEPALGUNJ REGIONAL OFFICE
ROLPA DISTRIBUTION CENTRE

Scheme Title : Cost Estimate of 11 KV HT Line Construction at Jinabang Jhayam - Kukurgade- Mungrakhola- Nauli -Bade
Mela- Ramai and Nauli to Ghareli danda- Burti-Ooat Meldaari -Vittabang and Ghar veer and Kalo veer area of Rolpa.

(A) Material Cost


S.No. Description Unit Quantity Rate(NRs) Amount(NRs) Remarks
(1) 11 KV HT Line Construction
1 11m. long Steel Tubular F/T Pole Single Pole Set. 221.00 18,802.41 4,155,332.61
11m. long Steel Tubular F/T Pole Double Pole Dead End Set.
2 45.00 37,604.82 1,692,216.90
Type
3 0.05 sq.inch ACSR "Rabbit" Conductor Km. 48.00 55,118.99 2,645,711.52
4 Disc Insulator Nos. 270.00 1,450.00 391,500.00
5 Dead End (Tension) Clamp Set Set. 270.00 884.96 238,939.20
6 11 KV Pin Insulator with Spindle Set Set. 798.00 1,731.00 1,381,338.00
7 Stay Set HT(plate, laltern bow, eye bolt etc.) Complete Set. 163.00 2,640.37 430,380.31
8 Stay Wire (7/12 SWG) Kg. 652.00 217.00 141,484.00
9 HT Stay Insulator Nos. 163.00 238.00 38,794.00
10 Channel(6*50*50*100*3300 mm) Nos. 45.00 4,458.40 200,628.00
11 T - Channel(100x50x50x6.4x1900mm) Nos. 221.00 3,670.58 811,197.12
Double Pole Cross Arm(Bracing Angle set)
12 Nos. 45.00 12,000.00 540,000.00
(40x40x5x2416)mm, (40x40x5x2872)mm
13 PG Clamp 3 Nut Heavy(R-R) Nos. 135.00 2,000.00 270,000.00
14 Pole Clamps sizes as required Nos. 311.00 221.24 68,805.64
15 Nut Bolts (4" 5" 7" & 8" Half & Full Thread) sizes as Kg. 222.00 49,115.28
required 221.24
Sub Total 13,055,442.58
Contingency@5% 737,632.51
Vat @13% 1,697,207.54
Total 15,490,282.63
(2) 0.4/0.23 KV LT Line Construction 2 KM for all Transformer Station.
1 8m. long Steel Tubular F/T Pole Set. 280 11,214.06 3,139,937.35
2 0.03 sq.inch ACSR "Weasel" Conductor Km. 42 30,811.35 1,294,076.50
3 D Iron with Shackle Insulator Set Set. 1344 250.00 336,000.00
4 Stay Set LT(plate, laltern bow, eye bolt etc.) Complete Set. 93 1,670.00 155,866.67
5 Stay Wire (7/12 SWG) Kg. 280 217.00 60,760.00
6 NutBolts (4" 5" 7" & 8" Half & Full Thread) sizes as requir Kg. 269 221.24 59,469.31
Sub Total 5,046,109.82
Contingency@5% 285,105.20
Vat @13% 655,994.28
Total 5,987,209.30
Total Material Cost with VAT 21,477,491.93
(B) Labour Cost & Transportation Cost
Erection of 11 m. long Steel Tubular F/T Pole for HT Line
1 Set. 311 3,831.97 1,191,742.67

Stringing of 0.05 sq.inch ACSR conductor 3wire for HT


2 Km. 15.24 56,190.73 856,239.63
Line
Erection of 8 m. long Steel Tubular F/T Pole for LT Line
3 Set. 280 3,664.60 1,026,088.50

Stringing of 0.03 sq.inch ACSR conductor 2 wire for LT


4 Km. 40 17,917.06 716,682.40
Line
5 Stay Set (HT/LT) Installation Complete Work Set. 256 1,943.27 497,477.12
6 Installation of Distribution Transformer(25-250kVA) Set. 7 19,962.16 139,735.12
7 Transportation cost/km/quintal Km. 50 3.28 59,149.55
Sub Total 4,487,114.98
Vat @ 13% 583,324.95
Total Labour Cost with VAT 5,070,439.93
Grand Total Cost A & B with VAT 26,547,931.86

Estimated By: Checked By: Approved By:


#f]/fxL pk-dxfgu/kflnsf
gu/ sfo{kflnsfsf] sfof{no
#f]/fxL, bfª, n"lDjgL k|b]z, g]kfn

लागत अनुमान
of]hgfsf] gfdM ljß't lj:tf/
of]hgf :ynM j*f g+= 1
(1) 0.4/0.23 KV LT Line Construction
1 8m. long Steel Tubular F/T Pole Set. 34 -
2 0.03 sq.inch ACSR "Weasel" Conductor wire Km. 3.4 -
3 D Iron with Shackle Insulator Set Set. 74 -
4 Stay Set LT(plate, laltern bow, eye bolt etc.) Complete Set. 20 -
5 Stay Wire (7/12 SWG) Kg. 100 -
6 NutBolts (4" 5" 7" & 8" Half & Full Thread) sizes as requi Kg. 68 -
Sub Total -
Contingency@5% -
Vat @13% -
Total -
(3) Transformer Stations
Distribution Transformers (11/0.4 KV,25 KVA) @
1 Nos. 1 -
Jinabang and Oat
2 Transformer Mounting Set Set. 1 -
3 Channel(6*50*50*100*2250 mm) Nos. 2 -
4 11 KV DO Fuse Set (3nos. 1Set) Set. 1 -
5 11 KV Lightning Arreter Set(3nos. 1Set) Set. 1 -
6 MCCB 200A Nos. 1 -
7 MCCB Box Metal Nos. 1 -
8 Earthing Chemical Kg. 25 -
9 Earthing Rod Nos. 3 -
10 Copper wire 8 SWG(5 kg for each tfr.) Kg. 5 -
11 ABC Cable 95 mm2 Mtr. 15 -
12 Pole Clamps sizes as required Nos. 2 -
13 Cable Shoes Copper 95 mm Nos. 3 -
14 Cable Shoes Copper 70 mm Nos. 3 -
15 NutBolts (4" 5" 7" & 8" Half & Full Thread) sizes as requi Kg. 1 -
Sub Total -
Contingency@5% -
Vat @ 13% -
Total -
Total Material Cost with VAT -
(B) Labour Cost & Transportation Cost
1 Erection of 8 m. long Steel Tubular F/T Pole for LT Line Set. 34 -
Stringing of 0.03 sq.inch ACSR conductor 2 wire for LT
3 Km. 3.40
Line -
4 Stay Set (LT) Installation Complete Work Set. 20 -
5 Installation of Distribution Transformer(25 to 250kVA) Nos. 10 -
6 Transportation cost/km/quintal Km. 15 -
Sub Total -
Vat @ 13% -
Total Labour & Transportaton Cost with VAT -
Grand Total Cost A & B with VAT -

Estimated By: Checked By: Approved By: