The project proposal outlines the construction of a G+2 commercial building in Limu Shaye Town, Oromia Regional State, aimed at addressing the demand for modern commercial facilities. Promoted by Mr. Nasir Aba Bulgu, the project is expected to create employment opportunities and generate income while serving various market needs. The total project cost is approximately 11 million ETB, with funding sourced from owner equity and a bank loan, and it is projected to be financially viable with a payback period of 10 years.

Uploaded by

kamilreshad89
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views

Na

The project proposal outlines the construction of a G+2 commercial building in Limu Shaye Town, Oromia Regional State, aimed at addressing the demand for modern commercial facilities. Promoted by Mr. Nasir Aba Bulgu, the project is expected to create employment opportunities and generate income while serving various market needs. The total project cost is approximately 11 million ETB, with funding sourced from owner equity and a bank loan, and it is projected to be financially viable with a payback period of 10 years.

Uploaded by

kamilreshad89
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 40

Project Proposal for the construction

of Commercial use Building

Project is to be implemented in Oromia Regional


State, Jimma Zone,Goma Wereda District ,Limu
Shaye Town

Promoter: - Mr. Nasir ABA BULGU

May, 2025
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

Contents pages
1. Executive Summary.........................................................................................................4
2. Introduction......................................................................................................................5
2.1. General Background.....................................................................................................5
2.2. Objective of the project................................................................................................7
2.3. Project description........................................................................................................8
2.4. Project Rationale...........................................................................................................9
2.5. The significance of the project.....................................................................................9
2.6. Project Location..........................................................................................................11
3. The market Study...........................................................................................................11
3.1. Market Analysis..........................................................................................................11
3.2. The Demand-Supply Gap...........................................................................................12
3.3. Current supply of mixed use building........................................................................13
3.4. Future market or Demand of commercial Building rental..........................................14
3.5. Target customers.........................................................................................................15
3.6. Marketing promotion and strategy..............................................................................15
3.7. Competition................................................................................................................16
3.8. The project facilities and Services plan......................................................................17
4. Technical Study.............................................................................................................18
4.1. Description of the project Service/ Product mix.........................................................18
4.2. Construction work and Technology............................................................................19
4.3. Utilities.......................................................................................................................23
5. Engineering and civil works..........................................................................................24
5.1. Land, Building and Civil Works.................................................................................24
5.2.Man Power...................................................................................................................25
5.3. Project implementation...............................................................................................27
5.4.Organizational Structure..............................................................................................27
5.4.1. Organization and management................................................................................27

[Author Name] 2
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

5.5. Financial Requirement and Analysis..........................................................................31


6. Financial analysis and Statements.................................................................................36
6.2. Financial Statement....................................................................................................39
6.2.1. Income loss/statement..............................................................................................39
6.3. Financial analysis........................................................................................................41
7. Environmental impact of the project.............................................................................41

List of table

Table 1.Office Space Demand Forecast............................................................................15


Table 2.The plan is that the ground will be partitioned in to different rooms:..................17
Table 3. Land utilization Plan............................................................................................19
Table 4.List of Building and Civil Works and Their Costs...............................................24
Table 5.Manpower Requirement and Annual Labor Cost.................................................25
Table 6. project Implementation schedule.........................................................................27
Table 7. Land, Building & Construction...........................................................................31
Table 8. Building Machineries and Equipments................................................................32
Table 9.office equipment...................................................................................................33
Table 10.Operating Expenses............................................................................................34
Table 11 Pre-service Expenses..........................................................................................35
Table 12.Summary of Total initial investment cost...........................................................35
Table 13.Loan repayment schedule...................................................................................37
Table 14.Depreciation schedule.........................................................................................38
Table 15.Mixed use Building profit/Loss Statement.........................................................39
Table 16.Cash Flow statement...........................................................................................40
List of Figures

1.Executive Summary

[Author Name] 3
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

Key information highlights

Project owner Mr.Nasir Aba Bulgu


Project title Commercial use building

Land requirement 400 m2

Project area Limu Shaye town

Production capacity G +2

Products to be manufactured
Rental rooms

Market Domestic and international

Cost of the project 11,000,083.05 etb

Source of fund 30% or 3300024.915 etb from owner equity and the
rest 70% from bank loan.

Number of working days 365 days

Employment opportunity: 24 individuals on permanent 86 on casual basis

Social and economic benefit: Provide better building service, employment opportunities,
generation of income and benefits for the local people

Pbp ( payback period) 10 yrs

Analysis result

The project is technically feasible, financially and commercially viable as well as


socially and economically acceptable. Hence, the project is worth implementing.

[Author Name] 4
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

2. Introduction
2.1. General Background
The growth of investment in the property market over the last five years in consistent
with the global experience suggesting that investment in the residential and commercial
property (real estate) is greatly influenced by the performance of the macroeconomic
conditions. In general, a stable macroeconomic condition leads to economic and business
growth and develops investors’ confidence. This certainly spurs large demand in the
property market for office space, shopping malls, catering services, apartment and
residential houses. Following growing demand trends, and with the expectation of high
return on their investment capital, large number of land developers pooled their financial
resources and invested in the property market.

Limu shay town is one of more economically stable town in Jimma zone popular in
Chat,Cereal Crop,Fruits and Vegetatn Coffee and livestock market. Mixed use building
will be owned and operated by Mr Nasir Aba Bulgu, whom are resident for long time in
the district planned to construct mixed use building in Limu shay town Thus, This project
feasibility study is undertaken to check the market, technical and financial feasibility of
this project. The business will be operated as a Private ownership and will offer
supermarkets, Beauty salon, shops, offices Computer and mobile Center, Cafeterias,
boutiques, textile fashion, baby clothe, assembly hall and other activities, pharmaceutical,
as well as novelty items. Recently Limu shay town is becoming convenience for such
investment and the growing demand of better economic service. To realize this mixed use
building plays a crucial role to promote the growth of the town in one hand and to reduce
the growing demand of commercial house. The socio-economic environment of the town

The promoter is very ambitious and committed to realize the project. Hence, they expects
to get the necessary support from the city administration to make the project to be
operational.
[Author Name] 5
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

Looking at the past trends and permits issues by the Government to the
construction of real estate properties including the mixed use building in the
major urban areas of the country especially in Addis Ababa one can easily conclude that
the momentum is more likely to continue.

Besides, the government policies and incentives for the private sector investment are very
promising that motivates the promoter to engaged in mixed use building business.

2.2. Objective of the project


The major goal of this project is to contribute towards the growth of the trade sector in
Limu shay town.

Its specific objectives include the following.

 The primary objective of this project is to gives quality and convenient services to the
customer on their demand and to facilitate Urbanization of towns, targeting in
government policies.
 Provide restaurant and hotels service to serve growing market demand and to address
the needs of the community;
 create an economically viable development that will contributes to the national
economy through creating job opportunities to unemployment, generating tax
revenue to bodies of the government and facilitating supply and service availability
in the market.

 To construct and develop modern shops, offices, and restaurant, bedroom & cafeteria
facilities that enable to provide standard services to visitors.

 To undertake trading and other refuted business activities that enable to generate a
reasonable to the invested capital.

[Author Name] 6
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

 To develop modern business center that would provide product and services to meet
the market demand with efficient and quality to attract foreign visitors and thereby
contribute towards the generation of hard currency for the country.

 To create employment opportunities for the population in the town and

 Contribute towards the development of the town through the construction of modern
building infrastructure and facilities.

2.3. Project description


The popularity of convenience building and mixed market center continues as people
become more economically grow and demand for better product and service by creating
less time for household purchases. Chat and Crop is the major cash crop in Goma woreda
and surrounding woreda. In Limu shay town this is shortage of mixed use building that
promote efficient marketing. The closest activity is only in Agaro which is far away by
20 km from Limu shay town. Mixed use building will carry a wide range of goods and
services in its shop, allowing customers to satisfy more needs quickly in one location
without having to drive to other market center. In Ethiopia there are some convenience
mixed building and market center, more established each year in the suburbs and
concentrated city areas. However, there is a shortage of such activity in Limu shay town
beside its being a center of market for nearby kebeles like Limu sapa, Meti Koticha \ and
surrounding Goma woreda rural kebele areas traveler from those kebeles will shop
commodities from the town, the population demand for product and service increase and
the merchant have no favorable shop to satisfy their customer demand and offers a
significant secondary target market for Commercial use building. The limited number of
mixed use building along the town, giving them a large potential share of the market.
Growth potential of the community for product and service is promising. The rapid
increasing of population has increased consistently over the past ten years and the
number of businesses in the city has risen during this time period. The owner plans the
project to render banking and insurance, shopping facility, and cafeteria services to create

[Author Name] 7
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

high quality class to satisfy the interest of customers in the town. Based on environmental
and other considerations, the entrepreneur has determined the type and size of the
building which is already determined by the site; conceptual planning and preliminary
analysis have been carried out by analysts.

2.4. Project Rationale


One of the biggest problems which are often occurring in the current urbanization
development in least developed countries is in convenience of market and lack of modern
market center. Therefore it is important to offer economic integration of demand and
supply. Mr Nasir Aba Bulgu mixed commercial building is reliable business center
renovating G+2 story building for mixed use in Limu shay town. Therefore, The
Promoter will complete the building as per requirements and specification provided by
the client.

The Economic growth and rapid urbanization in the country is promising investment
opportunities, the demands of product and service needs along with relatively sound
investment support made by the government in such kinds of feasible projects, compelled
the project promoter to initiate the multipurpose oriented business project to be
established. Despite the promising business opportunities of the town, the trend on such
kinds of investment found to not enough. The mismatch between the demand for and
supply of such kind of services in easily observed in the town.

Therefore, the existing shortage or absence in the supply of these services, along with its
commercial and administrative access, better location and infrastructure access,
escalating trend of urbanization and business activities, thus it is with such reason that
this project is identified and proposed and assumed to be more profitable.

In general, the country’s privatized and free market economy; good governance creates a
favorable environment for the development of investment for private investors.

[Author Name] 8
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

2.5. The significance of the project


The envisaged project deemed to add to the economic development of the nation in
general and zone and town in specific with following ways:

A. Source of Revenue

As public policy of any nation, the government collects different forms of taxes from
different business organizations and individuals. Among the different forms of taxes,
business income taxes, payroll income tax and VAT are collected from undertaking
business activities. Therefore, the building will serve as sources of revenue for the town
as well as for the region.

B. Employment opportunity

One of the problems that our country faced is unemployment. Therefore, the current
objective of the government is working on tackling the problem of unemployment and
fostering the development process either through creating self-employment or
employment in other organization. Hence, this project will hire 25 individuals and more
than eighty individual during construction.

C. Sources of social service

In addition to serving as a source of employment and income for the region, the project
renders social services for different group of people. Hence, it is also provide the
following services;

 Serve as a source of mental satisfaction for the different users,

 Since, the center encompasses different recreational areas; it will divert the attention
of the users from different evil deeds.

 It deemed to minimize the demand for shops and other bundles of services in the area.

[Author Name] 9
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

Furthermore, it serves as the pilot experience and ground for other investor to enter in to
such kinds of urban development. It also contributes on the efforts made on as a character
given building for physical development pattern of the townscape.

2.6. Project Location


The area is located in Oromia Regional State, Jimma Zone, Gomma district Limu Shaye.
The total land the farmer have is 50 hactares. Gomma district extends between 70 40-80
04 north latitudes and 360 17’-360 46’ east longitudes. It is bordered with Gumay district
north, Limmu kossa distrct in east, Manna district in southeast, with Seka chokersa in
south and Gera district in west. It is situated in the central of the zone. Because of
geographical location (i.e. near to the largest market centers like Jimma and Agaro
towns) the district has a great advantage for accessing the local products to the market
and creates ideal condition for provision of the demanded commodities to the local
communities. It has a total surface area of 936.58 Km 2 993657.72 hectare that accounted
4.8 % of the total area of jimma Zone.

Limu Shaye town is a have its own administrative unit (municipal) under Gomma woreda
in Jimma zone of the Oromia regional state. Limu Shaye town is a center of socio-
economic activity the town is surrounded by rural kebele of Gomma woreda.

The envisioned project is intended to be located in Limu Shaye 26 km from Agaro city
and about 70 km from jimma city and at about 420 km from Addis Ababa to the south
west. The town is selected because of strategic economic hub for different cash crop like
chat, coffee, and also Fruits and vegetation and livestock. The town’s economic
catchment extends beyond the Gomma woreda.

3. The market Study


3.1. Market Analysis

1
[Author Name]
0
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

The rapid growth of population along with urbanization, Increasing income and
modernity of town dweller and surrounding population residents are currently purchasing
“specialty” items in Agaro town that will be replaced provided by this project in Limu
shay town. Recently the increase in the price of Chat,Fruit and vegetable,Livestock and
coffee has increased the power of population for market. Town residents and surrounding
area population presently purchase everyday “necessity” items from small scale shop
‘Kiosk’ kebele house which does not allow satisfactory commercial activity and poor in
construction. On the other hand it’s not convenient to get goods and service in one
location which will waste time and price as well. People who purchase goods from such
small shop express dissatisfaction with availability and price. People travel to Jimma
town to fulfill their market demand, and the same is true for businessman to get
convenient rental shop they leave the town.

There are three major customer groups: (1) Local entrepreneurs (2) Diaspora looking for
essential business shop (2) surrounding town businessmen and entrepreneur (3) Whole
sale and distributer of good and service from big city, who look for convenience yet are
relatively price sensitive.

3.2. The Demand-Supply Gap


Limu Shaye town is situated in very centre of Chat, Coffee Arabica, Crops, fruit and
Vegetablex and fat livestock producing area. The town is a cash crop hub which is highly
known for its Fruit and vegetable, Cereal crop, Chat and Livestock. Local business man,
town resident and surrounding population reside on income generated from the above
product. Recently the growing demand of Chat, Cereal crop, Fruits and vegetation is
increasing from local market to international market. So the income level of the society is
increasing due to the incrassating price of those products. On the other hand Limu Shaye
town is also a major business center and commercial route that attracts thousands of
business travelers. These are also the most important groups of potential customers that
include both the local and foreign tourists, commuters and the modern business
1
[Author Name]
1
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

community who choose services that range from economic to high class standards. These
groups would also choose a healthy comfortable climate that combines a more traditional
type with that of modern shops, offices, bedrooms restaurants and cafeterias. Even
though the town is older town in the Limu Shaye town seems to have no developed
mixed use building, the existing supply is far behind the growing demand for standard
service. Hence, the project will solve the serous demand problem in the town .

Over the last decade, there has been a significant growth in the number of local and
international trades across the country. Merchant from Jimma town from central market
and foreign trader starts to come to the town. This increase is mainly associated with the
stimulation of economic activist and partly due to an increase in the flow of international
and local traders in to the town. Since Limu Shaye town is an important commercial
center in addition there is a significant increase in business activates and hence increasing
the number of traders to the town. Even though there is a lack of quantitative estimates
that number of traders to the town. Even though there is a lack of quantitative estimates
that depict the actual demand and also the annual growth rate Hotel facilities and urban
commercial facilities are scarce in the city. So far in the town there is no development of
such kind standard building and it is the first of its kind in the town and will promote
other investors from the town and the surrounding areas. They are mostly villa type
premises modified as show rooms and sailing posits. As a result there is a large gap
between the developed and that of the supply for modern bed rooms; Bank and cafeteria
accommodation hence this project would not face any problem of demand scarcity for it
business center and it would provide good service to customers.

3.3. Current supply of mixed use building


Commercial building/office sector has shown a dynamic change in the past few years.
The reason for this could be rapid economic growth and a supporting public
infrastructural development. Other factors relevant in the specific case of commercial

1
[Author Name]
2
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

buildings are the large increases in national and international businesses, particularly
firms in the services sector.

The business of multipurpose buildings in Limu Shaye Town in booming highly due to
the recent rapid growth experienced in Ethiopia. As a result, a good number of local and
international organizational are coming in place. Government offices which used to
operate in limited spaces all over the city are also concentrating on leasing new and
modern buildings. Increasing numbers of international organization and NGOs which in
the past had typically converted residences into office space are now moving towards
renting whole floors or even multiple floors in modern city-center commercial buildings.

3.4. Future market or Demand of commercial


Building rental
The demand for office space is a derived demand because firms rent space as an input to
the production of services or goods they provide to businesses and households in the local
regional or national economy.

Following our survey of office space users in Limu shay town are mainly firms providing
banking, cafeteria and restaurants, bed room, supermarkets service, computer Center
Crevice. The different customers for commercial buildings also include shops and offices
that are currently renting out to provide their goods and services.

Future demand for office space is actually driven from growth in number of offices in the
city which in turn is influenced by the macro-economic growth in the country. Following
the government five year growth and transformation plan (GTP), the Ethiopian economy
is expected to increase by 11% for base case scenario and 14% under the optimistic case
scenario. Assuming that demand for office space is directly related to the growth in the
economy, the forecast for office space demand is shown in the following table;

Table 1.Office Space Demand Forecast

1
[Author Name]
3
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

Office space demand Office space demand


under base case under high case economic
economic

Years Growth Growth

2010/2011 9,916,543 11,304,859

2011/2012 11,007,363 12,057,416

2012/2013 12,218,173 12,953,878

2013/2014 13,562,173 13,963,577

2014/2015 15,054,011 14,554,534

2015/2016 16,709,952 14,987,431

Source: estimation based on GTP’s forecasted Ethiopian Economic Growth

3.5. Target customers


The target customers of this envisaged project include:-

1. business Community

2. Nearby business organization

3. Bank and financial institution

4. the government bureau

5. small accounts(SOHO) SME

6. Nongovernmental organizations

3.6. Marketing promotion and strategy


1
[Author Name]
4
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

In order to penetrate and gain considerable market share, one of the major marketing
strategies for the project is consistently rendering quality service to its tenants. Due
emphasis must be placed on improving quality of service and facilities. The major
marketing strategies to promote the project and gain considerable market share include:

 Advertising through different means focusing on the existing service and


facilities using FM radio, Social Media and newspaper.

 Promote in association to the key location and nearby business

 Using advertising means like Banner, Business card, internet channel and pages.

 Working on public relations to reach and influence key personas and


organization with a capacity of making decision.

 Keeping the quality of its service/ facilities and consistently improving with
changing situations.

 Seasonal discount pricing different others customer centric marketing strategies


will be used by the company.

3.7. Competition
There are different forms of competition that may face the envisaged mixed use building.
These are price and non-price based competition. Moreover, there are different
competitors that will compete with the project either directly or indirectly. Mixed Use
commercial building desires to set a precedent in Limu shay town as a full service
convenience shop, store and service rendering with an economical image, offering a wide
range of competitively priced products and services in one location. Need of residents

1
[Author Name]
5
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

and surrounding population combined with the consistent popularity of convenience


market predict a favorable business climate for Mr Abdurahim Abdo Commercial use
building

3.8. The project facilities and Services plan


In order to provide mixed use business center building services of a high standard, it has
been planned to construct and develop the infrastructure and facilities that would viable
to meet the requirements of an international standard business center. Accordingly,
various buildings and facilities will be constructed phase by phase starting with the most
needed ones that are essential to commence the operation of its business activities. With
the completion of construction, the building will provide a combined service such as
shops, bedroom, restaurant and café service as well as modern business center that
primarily serve its guests and major clients.

Table 2.The plan is that the ground will be partitioned in to different rooms:

Buildin Description UOM Unit price


g in Birr

Ground Supermarket, Pharmacy, Banking & Insurance M2 200

1st floor Beauty salon, shop, Computer Center, Cafeteria M2 200

2nd floor Different governmental, NGO & other offices M2 200

Parking Service Car 5/per hour

Total

Since the project will be engaged in mixed building the main sources of its annual
revenue would be from the rental of building spaces such as shops, offices, and banking,
café & restaurant bedrooms. Therefore, the sources of revenue have been classified in to
one category namely the rental of banking & supermarket, offices, shops, bedrooms

1
[Author Name]
6
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

restaurant and café based on these classifications. Based on the market price of similar
mixed use building in the area, the envisioned buildings set the following fair price
(Before VAT) for its service, hence when the building construction fully get operational
it is assumed to generate a yearly income of ETB 971,662.12.

4. Technical Study
4.1. Description of the project Service/ Product
mix
The envisioned mixed purpose building will provide different rental services to the
different customer groups for different purpose. The building will have basement, ground
and eight floors. The purpose of the building explained as follows;

 the ground floor, first floor and second floor designed for different business
centers like banks, supermarket, beauty salon(man and women), Computer
center, pharmacy, internet café, boutiques, different shops and other business
activities,

 The third floor designed for bed room services.

Besides, the buildings will have enough parking facility for its customers and green area
in its compound.

4.1.1. Land Use Plan

The total land required for the envisioned project is estimated to be 400 m 2 the total area
for the construction of the building will be 200 m2, as revealed below.

Table 3. Land utilization Plan

SN Description Land M2

Ground 1st 2nd 3rd

1
[Author Name]
7
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

floor floor Floor

1 Building (G+2)

1.2 Ground 200

1.3 First floor 200

1.4 Second Floor 200

Parking & Green area 200

Total 400

4.2. Construction work and Technology


4.2.1. Construction schedule

The construction project is proposed to be started on June to September 2025, and is


expected to be finished on January 2026. as seen in the abbreviated construction
schedule above, a majority of the schedule’s time is made up of five major activities;
Concrete, building Enclosure, masonry, mechanical & HVAC and Electrical installation.
Concrete activities include processes such as placing foundations and slab on deck.

The Building Enclosure Phase includes erecting the scaffolding that will allow for
exterior sheathing installation and bricklaying.

Mechanical and Electrical install coincide with each other due to the need for
coordination between the two divisions. There are several periods of construction during
the schedule in which there are multiple construction activities occurring at the same
time.

1
[Author Name]
8
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

The construction site must be organized accordingly as these processes take place. As
with any construction project, the goal of the schedule was to complete all construction
activities before the required Date of completion.

This date of completion is practical based on the time of year in which the building will
be completed. The team allowed a two week contingency for any setbacks. Typically,
winter construction tends to cause unforeseen delays that negatively impact a
construction project. These conditions can and will almost undoubtedly impact the
project schedule by causing unforeseen delays and project inefficiency.

4.2.2. Architectural Design & Layout

Although functional spaces for the project were laid out in significant detail, the rest of
the building had designated spaces but n set layouts. It was at the discretion of the project
promoter to devise typical layouts for the non-detailed commercial and office spaces.

To make sure that the building’s layouts were practical, the project owner researched
typical architectural layouts for laboratory and executive office spaces. The walls and
partitions throughout the floor were congruent with the structural frame and column
locations.

4.2.3. Structural design

One of principle deliverables of our project is the structural design of the building. The
structural bays were coordinated with the layout of the building adjustments were made
to the bays if specific layouts are necessary. The frame was made up of a grid with
repeating standard structural bays. Included in the structural system are bay sizes, shape
and size of structural members, floor compositions and curtain walls. These elements
were established to resist gravity ad lateral loads as appropriate.

1
[Author Name]
9
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

The gravity load design was completed for two frames; one of structural steel and one of
reinforced concrete. The structural steel frame was chosen for further design based on
cost per square foot, local availability of material and constructability considerations,
such as erection and fabrication. The steel system was then designed for lateral loading
with necessary adjustment being made to framing.

4.2.4. Reinforced concrete

The project group prepared hand structural design calculations for a typical bay of a
reinforced concrete frame. In all reinforced concrete bay designs, a superimposed dead
load of 7.5 pounds per square foot was assumed for mechanical equipment, floor
coverings and ceilings.

Similarly, the design of the typical bay accounted for the use of different commercial
space, in which a live load of 125 pounds per square was assumed. Loads were calculated
based on the requirements of the minimum Design loads for Buildings and other
Structures.

4.2.5. Foundation Design

The design of a superstructure may be accurate, have considered all possibilities and still
fail because the substructure is incapable of distributing the applied loads to the
supporting soil.

Foundation design takes more into consideration than merely the loading from the
columns. While the main part of the project focused on the structural frame and its
alternate designs, a preliminary foundation plan was designed based upon maximum load
carried from the superstructure through the columns. The foundation design conducted by
the project team consisted of the selection of foundation type, determination of the
bearing capacity and the design for typical interior and exterior spread footings.

2
[Author Name]
0
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

4.2.6. Construction Plan and process

The project team developed a coordinated project schedule and construction plans that
would reflect the expectations for an actual construction project. The project schedule
was developed using the preliminary designs given to the project team.

Additionally, the group considered typical construction activities and durations taken
from similar construction projects as well as realistic constraints on building
development. For instance, it is necessary for the structural frame to be completed before
concrete can be placed for the slab on deck. Hand drawn construction plans detailing site
entrances and storage areas were coordinated with the project schedule to give the reader
visualizations of the construction site set up through various periods of the construction
process.

The construction process for this project is normally a disjointed three mages
development by which the conceptualized need of the promoter of this project is
translated into a functional facility that will meet their needs in terms of time, cost and
quality.

Based on a general program of the project owners the consultant who is going to be hired
makes site studies, develops structural designs, prepares drawings and specifications,
determines quantities involved and estimated the resultants costs. All these activities will
be done in the first phase of the project which is the design stage after the document are
produced by the designers have been received, and the works secured the project is
supposed to enter the tendering stage. At this stage contractors study the project
document analyze and subsequently determine the construction methods, built up their
unit rates and submit their bids for the works. The promoter of this project intends to
compare the bids and award the contract for the lowest responsible bidder. This, is of
course, presupposes that the favorable proposal does not exceed the allocated budget.

2
[Author Name]
1
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

After the award is made and the contract signed between this project owner and the
contractor, the project constructor is expected to prepare and submits a detailed
construction program which includes material schedule, manpower requirement and cash
flow forecast.

After the award is made and the contract signed between this project owner and the
contractor, the project constructor is expected to prepare and submits a detailed
construction program which includes material schedule, manpower requirement and cash
flow forecast.

4.3. Utilities
A number of utilities world be put in place in order to ensure smooth functioning of the
project. These utilities include:

 Water Supply,

 Supplementary Electricity supply.

 Telephone line Internet Broadband

 Fuel, Oil and lubricant

 Drainage Facility

5. Engineering and civil works


5.1. Land, Building and Civil Works
The Mixed use building has a total site area of 400 m2. The building floor area has
covered 200 m2 and the remaining 200 m2 is left for greenery and parking. The type of
buildings and its corresponding civil construction cost is given on Table 4.

Table 4.List of Building and Civil Works and Their Costs

2
[Author Name]
2
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

No Description Total price

A. SUB-
STRACTURE
1 excavation and earth
works 110,324.12

2 concrete work 1,346,000

Sub total 1456324.12

B. SUPER
STRACTURE
1 Concrete work 1,100,358.45

2 Block work 252,534.40

3 Roofing 110,193.00

4 Carpentry and joinery 98,760.00

5 Metal works 600,665.00

6 Finishing 1,051,379.44

7 Painting 108,398.88

8 Electrical installation 400,532.00

9 Sanitary installation 750,057.00

Subtotal 4,411,868.17

A+B 5,868,192.29

Vat (15%) 88,231.05

Grand total 6,850,000

As shown on Table 5, the total cost of building and civil work is estimated at Birr
6,850,000 and out of which the proponent has worked more than birr 5.86 million.

5.2. Man Power

2
[Author Name]
3
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

The total manpower required for the building will be 23 persons. The manpower list and
the corresponding labor cost are shown in part five of this document.

5.2.1. Man Power Requirement

The list of manpower and the annual cost of labor is indicated in Table 5.

Table 5.Manpower Requirement and Annual Labor Cost

S Position N Qualification Monthly Annual


N o salary in salary
Birr in Birr

1 General manager 1 BA in management 3000 36,000

2 Building admin 1 BA in Acct/Mgt 2500 30,000

2 Secretary 1 10+2 in secretariat 2000 24,000


science

3 HRM Officer 1 10+2 in 2000 24,000


HRM/Management

6 Finance head 1 BA in Accounting 4500 30,000

4 Technical and 1 Diploma in building 1500 18,000


maintenance manager maintenance

5 Marketer 1 Diploma in marketing 2000 24,000

6 Accountant 1 Diploma in accounting 2000 24,000

7 Guards/Security 4 Basic 1000 12,000

8 General Service head 1 Diploma in 1500 18,000


Management

9 Electrician 1 10+2 in general 1500 18,000


electricity

10 Casher 2 10+1 in bookkeeping 1000 12,000


2
[Author Name]
4
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

11 Cleaner 5 Unskilled 750 9,000

12 Maintenance officer 1 10+2 in General 1000 12,000


mechanic

13 Driver 1 10 completed 2000 24,000

Total 23 315,000

Benefit (20%) 63,000

Grand Total 378,000

5.2.1. Labor Availability

Workers for this type of plant are available throughout the year. No foreseeable problems
are expected as most of the work requires no previous skills.

5.3. Project implementation


The project’s implementation is expected to take 24 months. The major activities include
Bank loan processing construction of the building, cleaning the area around the building,
Procurement of equipment’s and start rendering services. The time schedule for the above
matured major activities is presented below:

Table 6. Project Implementation schedule

SN Activities Date

1 Land request processing September 2021

2 Land approval October 2021

3 Bank loan processing Nov-Dec 2021

2
[Author Name]
5
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

4 Site Development January 2022

5 Building and construction work February-March 2022

6 Preparation for service April, -2022

7 Service execution May-June 2022

5.4. Organizational Structure


5.4.1. Organization and management
The organizational structure should be in a way that the company able to achieve its
objectives as well as the satisfaction of standard requirement. In addition to this, the
structure should fit the dynamics of all customers in the building ranging from small
business to large tenants.

Organizational Structure

The organizational structure of the project is designed by including all the necessary
personnel under the right division. At the top of the organizational structure, there will be
manager with the responsibility of supervising the overall activity of the building.
Depending up on the nature of the center and the amount of work to be performs; there
exist auxiliary units under the general manager.

Employees under each unit will be supervised by the department head that is accountable
for the general manager. General Manager is appointed by owner.

Owner

2
[Author Name] General 6
Manager

Building Admin Marketing Technical and


maintenance
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

Figure 1.organization structure of the Building


As clearly shown in the organizational structure, the center organization has one general
manager and three main sections. Under the general manager there are the, marketing
Department, maintenance and building administration department.

Under building admin dept there exist two sections i.e., HRM & finance and general
service. Further sub sections are also organized under technical and maintenance
manager. The following section deals with the duties and responsibilities of each
department.

A. The General Manager’s Duties and Responsibilities

 He/she will plan, organize, direct and control the overall activities of the building.

2
[Author Name]
7
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

 He/she will devise policies and strategies that will enable the center to be profitable.

 He/she will incorporate modern technological innovation that will facilitate the
service delivery of the building to increase customer’s satisfaction.

 He/she will plan, organize, direct and control the human and non-human resources of
the building so as to achieve the short and long run objectives of the organization.

B. Building Administration Department

The building Administration Department of the multipurpose building has two main
sections (HRM and Finance and General Service section). It has responsible for
undertaking the following activities;

 Manage the human resources and control employee’s activity

 Well non-human resources of the project, which include; effective handling of the
different resources of the building, and devise strategies of controlling against
fraud and damage.

 Will provide the right material or inventory to the center with right price at the
right time.

 Will plan, organize direct and control the financial transaction of the building by
using all the necessary documents.

 Accountant and casher that will collect money from the customers.

 Will develop sound financial control system by developing modern financial


control systems.

 Will prepare the annual financial statements and prepare condensed reports for
both the General Manager and other concerned government body.

2
[Author Name]
8
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

 Follow the overall status of the business and provide maintenance and repair
services

C. The marketing Department

 Will handle the overall marketing activities of the organization which include
planning, organizing, directing, and controlling.

 Will develop the marketing strategies for future multipurpose building


development

 Will develop effective customer handling strategies.

 Execute the promotion methods.

D. Technical and maintenance manager

 Will handle the overall physical maintenance and related issues

 Will make sure electricity and back up is organized.

 Follow up security issues and educate tenants

 Works in collaboration with general service to make sure tenants are well served

5.5. Financial Requirement and Analysis


The financial resource is a prime resource for undertaking any activities. Hence for
implementing this mixed use building a total of 11,000,083.05 ETB is required. From this
30% (3,300,024.915) birr will be covered by the promoter of the project while the rest
70% (7,700,058.135) will be covered through loan from bank at the prevailing interest
rate. Therefore the said amount of finance is needed for undertaking the following.

5.5.1. Fixed Investment

2
[Author Name]
9
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

A. Land, Building & Construction

Table 7. Land, Building & Construction

S.N Description of works Total Cost in birr

1 Building construction 6,850,000.00

2 Site Development 50,000.00

3 Design and supervision 120,000.00

4 1st Year land lease & (10%) 40,396.50


down payment

Total 7,060,396.50

B. Building Machineries and Equipment’s

Table 8. Building Machineries and Equipment’s

S Description Measure Qt Unit cost Total cost


N ment y in Birr in Birr.

1 Generator Unit 1 200,000.00 200,000.00

2 Carpentry tool box Set 1 30,000.00 30,000.00

3 Electrician tools box Set 1 18,500.00 25,500.00

4 Plumber tools kit Set 1 12,300.00 19,300.00

5 Fire extinguisher Unit 10 6,000.00 80,000.00

(Security Unit 1 40,000.00 40,000.00


Equipment)

6 Total 394,800.00

3
[Author Name]
0
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

C. Vehicle

S Description UO Qt Unit Cost Total cost Remar


N M y in Fr. in Birr k

1 medium Unit 1 1,500,000.00 1,500,000.00 Duty


Truck(FSR) Free

Total 1,500,000.00

D. Office Equipment’s

Table 9.office equipment

S Description Measureme Qt Unit cost Total cost


N nt y in birr in Birr

1 Managerial tables Unit 5 3,600.00 18,000.00

2 Managerial chairs Unit 5 2,000.00 10,000.00

3 Office table with Unit 7 3,000.00 21,000.00


chair

4 Secretarial table Unit 1 2,500.00 2,500.00


with chairs

5 Computer with Unit 3 28,000.00 84,000.00


chairs

6 Shelf Unit 4,500.00 0.00

7 Filing cabinets Unit 1 3,500.00 3,500.00

8 Guest chairs Unit 1 2000 2,000.00

9 Fax & Telephone Unit 5 2,500.00 12,500.00


machine

10 Carpet and Curtain LS 1 33000 33,000.00


3
[Author Name]
1
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

Total 186,500.00

5.5.2..Working Capital

Operating Expense at full Capacity2

Table 10.Operating Expenses


S List of Items Annual List of Items Annual Assumptions
N cost in cost in birr Used
birr

1 Audit and legal SN Audit and legal 24,000.00 2000 br/per ,month
fee fee

2 Stationery 1 Stationery 6,000.00 500 br/month


supplies supplies

3 Promotional Cost 2 Promotional Cost 40,000.00 Lump sum annual


cost

4 Property 3 Property 84,009.00 1% of the building


Insurance Insurance

5 Cleaning Supplies 4 Cleaning Supplies 10,800.00 900 br. Per month

6 Uniforms 5 Uniforms 1,670.00 180 per pes for 16


people

7 Water 6 Water 12,600.00 4000m3 by 3.15 br


consumption consumption

8 Electric 7 Electric 12,000.00 20000KWH By


consumption consumption Br.0.4736

9 Fuel 8 Fuel 63,000.00 3000 lit per year by


Br. 21

10 Oil & Iubricants 9 Oil & Iubricants 6,300.00 10% of fuel cost

11 Telephone & fax 10 Telephone & fax 18,000.00 1500 per month

3
[Author Name]
2
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

12 Repair expense 11 Repair expense 132,000.00 2% of building cost

13 Miscellaneous 12 Miscellaneous 20,000.00 3000 per month


costs costs

Total 13 Total 430,379.00

Table 11 Pre-service Expenses


SN Description Cost in birr

1 Project proposal & EIA 50,000.00

2 Licensing fee and others

Total 50,000.00

Table 12.Summary of Total initial investment cost


SN Description Cost in Birr

1 Land, building & construction 7,060,396.50

2 machines & Equipments 394,800.00

3 Vehicle 1,500,000.00

4 Office Equipment 186,500.00

Total fixed investment cost 9,141,696.50

6 Salary expense 378,000.00

7 Operation Expense 430,379.00

8 Pre service Expense 50,000.00

Total Working capital 858,379.00

Sub total 10,000,075.50

3
[Author Name]
3
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

11 Contingency (10%) 1,000,007.55

Total initial invest. capital 11,000,083.05

6. Financial analysis and Statements


Underlying Assumption

The financial analysis of the mixed use building is based on the data provided in the
preceding sections and the following assumptions.

A. construction and finance

Construction period 2 Years

Source of finance 30% equity and 70 loan

Bank interest rate 10%

B. depreciation

Building 10%

Building machinery and equipment 10%

Office Equipment’s 10%

6.3.2. Sources of Fund

The source of fund to finance the project is planned to be from two sources. These are
promoter’s equity and bank loan. The loan is expected to be obtained from one of the
local lending institutions. Since the project is expected to take some times to repay all its
debts, the bank loan is assumed to obtain on long term credit basis. Taking the financial
position of the promoters into account, equity contribution and bank loan to finance the

3
[Author Name]
4
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

total investment outlays of the project are assumed to be 30% and 70% respectively.
Accordingly, the total financial requirement from the two sources will be;

Table 13.Source of fund.

Owners’ 3,000,24.91
equity 30% 5

Bank loan 70% 7,700,058.135

Total 100% 11,000,083.05

6.3.3. Bank loan Repayment Schedule

Table 14.Loan repayment schedule

Total
ye Principal Interest rate annual year ending
ar payment (8.5%) Payment in balance
ETB

0 7700058.135

1 770005.8135 654504.9415 1424510.755 6930052.322

2 773085.8135 589054.4473 1362140.261 6156966.508

3 773085.8135 523342.1532 1296427.967 5383880.695

4 773085.8135 457629.859 1230715.673 4610794.881

5 773085.8135 391917.5649 1165003.378 3837709.068

6 773085.8135 326205.2707 1099291.084 3064623.254

7 773085.8135 260492.9766 1033578.79 2291537.441

8 773085.8135 194780.6824 967866.4959 1518451.627

9 773085.8135 129068.3883 902154.2018 745365.8135


3
[Author Name]
5
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

10 63356.09415 0

Assumption

Total loan= 7700058.135

Repayment rate 10year

Annual interest rate 8.50%

6.3.4. Depreciation Schedule

Table 15.Depreciation schedule

S Description Original Depreciatio Depreciation


N Value in n rate in % per year in
Birr Birr

1 Construction and 10 706,039.65


Building 7,060,396.50

2 Bldg. machines & 394,800.00 10 39,480.00


Equipment’s

3 Vehicle 1,500,000.00 5 75,000.00

4 Office Equipment 186,500.00 10 18,650.00

Total 9,141,696.50 839,169.65

6.2. Financial Statement


6.2.1. Income loss/statement

3
[Author Name]
6
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

Project revenue and production costs are listed and compared to see whether the project
generate profits or not. Starting from first year of the project operation, the project will
generate a reasonable amount of net profit for the owners throughout its life period. Profit
and loss statement shows that the project will generate net profit of ETB 133,849.56 in
the first year and increase to ETB 971,662.12 starting from the third year of the project
life and hence it is found to be profitable.

Table 16.Mixed use Building profit/Loss Statement


Revenue Year 1 Year 2 Year 3 year 4
and after

Rental Income 2,500,000.00 2,600,000.00 3,000,000.00 3,500,000.00

Expenses

Salary Expense 378,000.00 378,000.00 378,000.00 378,000.00

Operating Expenses 430,379.00 430,379.00 430,379.00 430,379.00

Deprecation Bld. 839,169.65 839,169.65 839,169.65 839,169.65


Machineries ,Equip & vehicle

Interest Expense3 654,504.94 589,054.45 523,342.15 457,629.86

Lease payment4 6,732.75 6,732.75 6,732.75 6,732.75

Total Expense 2,308,786.34 2,243,335.85 2,177,623.55 2,111,911.26

Profit before Tax 191,213.66 356,664.15 822,376.45 1,388,088.74

Tax (30%) 57,364.10 106,999.25 246,712.93 416426.6223

Net profit 133,849.56 249,664.91 575,663.51 971,662.12

6.4.2. Cash flow Statement

Table 17.Cash Flow statement

3
[Author Name]
7
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

Year Year 0 Year 1 Year 2 Year 3 year 4

Equity Capital 3300024.915

Loan principal 7700058.135

Net sale 0 2,500,000.00 2,600,000.00 3,000,000.00 3,500,000.00

Total Cash in 11,000,083 2,500,000.00 2,600,000.00 3,000,000.00 4,338,400.00


flow

Cash payment

Salary Expense 0 378,000.00 378,000.00 378,000.00 378,000.00

Investment 9,141,697 0 0 0 0

Pre operating 50,000 0 0 0 0


Expense

Operating Cost 0 430,379.00 430,379.00 430,379.00 430,379.00

Loan repayment 0 1,424,510.75 1,362,140.26 1,296,427.97 1,230,715.67

Lease payment 0 6,732.75 6,732.75 6,732.75 6,732.75

Tax payment 0 57,364.10 106,999.25 246,712.93 416,426.62

Total payment 9,191,696.50 1,918,986.60 1,906,251.26 1,980,252.65 2,084,254.04

Cash surplus/ 1,808,386.55 581,013.40 693,748.74 1,019,747.35 2,254,145.96


deficit

Cumulative 1,491,638.37 581,013.40 693,748.74 1,019,747.35 2,254,145.96


cash flow

6.3. Financial analysis


i. Profitability

3
[Author Name]
8
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

According to the projected income statement, the building will start generating profit in
the 2nd year of operation. Important ration such as profit to total sales, net profit to equity
(Return on equity) and net profit plus interest on total investment (return on total
investment) show as increasing trend during the lifetime of the project. The income
statement and the other indicators of profitability show that the project is viable.

7. Environmental impact of the project


The EIA of the project activities was determined by identifying the environmental aspects
and then undertaking an environmental risk assessment to determine the significant
environmental aspects. The environmental impact assessment has included all phases of
the project namely construction phase and operational phase.

The building has both positive and negative impact

Positive impact of the project

The positive impact of the project is:-

 Generation of employment opportunity

 Source income for the government through business income tax

 Income generation for the promoter

 Being exemplary for other investors who want to engage in the same business
line.

Negative impact of the project

The project has the following negative impacts:

1. noise and Dust emission during Construction

3
[Author Name]
9
Project Proposal for Mr. Nasir Aba Bulgu G+2 Commercial use Building construction

There are some noises during the construction due to the construction operation
and the company will use construct the construction during the day time. Again
there is the emission of dust which will be mitigated by sprinkling water on the
service.

2. problem on workers on construction

During construction there are some problems that will materialize on workers. These are:
damage on operation by using machines, construction materials and others. To mitigate
such impact the company will provide safety insurance and safety equipment’s.

3. sewages during operation

During operation there are some wastes emitting from the mixed use building. These are
wastes from the latrine and will be mitigated by using modern waste treatment
technology.