CTM Unit-5 notes
CTM Unit-5 notes
An agreement comes into existence whenever one or more persons promise to one or
others, to do or not to do something, ―Every promise and every set of promises,
forming the consideration for each other, is an agreement. Some agreements cannot
be enforced through the courts of law, e.g., an agreement to play cards or go to a
cinema. An agreement, which can be enforced through the courts of law, is called
contract.
The Contract Act is the law of those agreements which create obligations, and in case
of a breach of a promise by one party to the agreement, the other has a legal remedy.
Parts of a contract
• Offer/Proposal
• Acceptance
• Agreed terms
Offer / proposal
When one person signifies to another his willingness to do a work, he is said to make a
proposal. Communication of an Offer: By words or by actions
Acceptance: When the person to whom the proposal is made signifies his assent
2. It must be communicated.
Essentials of a contract
1. Agreement.
2. Intention to create legal relationship.
3. Free and genuine consent.
4. Parties competent to contract.
5. Lawful consideration.
6. Lawful object.
7. Agreements not declared void or illegal.
8. Certainty of meaning.
9. Possibility of performance.
10. Necessary Legal Formalities.
―lawful‖.
4. Capacity of Parties: The parties to an agreement must be legally capable of
entering into an agreement; otherwise it cannot be enforced by a court of law.
Want of capacity arises from minority, lunacy, idiocy, drunkenness, and similar
other factors. If any of the parties to the agreement suffers from any such
disability, the agreement is not enforceable by law, except in some special cases.
5. Free Consent: In order to be enforceable, an agreement must be based on the
free consent of all the parties. There is absence of genuine consent if the
agreement is induced by coercion, undue influence, mistake, misrepresentation,
and fraud. A person guilty of coercion, undue influence etc. cannot enforce the
agreement. The other party (the aggrieved party) can enforce it, subject to rules
laid down in the Act.
6. Legality of the Object: The object for which the agreement has been entered
into must not be illegal or immortal or opposed to public policy.
7. Certainty: The agreement must not be vague. It must be possible to ascertain
the meaning of the agreement, for otherwise it cannot be enforced.
8. Possibility of Performance: The agreement must be capable of being
performed. A promise to do an impossible thing cannot be enforced.
9. Void Agreements: An agreement so made must not have been expressly
declared to be void. Under Indian Contract Act there are five categories of
agreements which are expressly declared to be void. They are:
1. Agreement in restraint to marriage.
2. Agreement in restraint of trade.
3. Agreement in restraint of proceedings.
4. Agreements having uncertain meaning.
5. Wagering agreement.
10. Writing Registration and Legal Formalities: An oral contract is a perfectly
good contract, except in those cases where writing and/or registration is
required by some statute. In India writing and/or registration is required by some
statute.
TYPES OF CONTRACT
Contracts for the execution of civil engineering works are of following types:
a) Lumpsum Contract
In this type of contract, the contractor offers to do the whole work as shown in
drawings and described by specifications, for a total stipulated sum of money.
There are no individual rates quoted, thus it becomes difficult to make
adjustments in the contract value if any changes are to be made in the work later
on. The schedule of different items of work is not provided and the contractor
has to complete the work as per drawings and specifications for the agreed lump
sum amount.
Deposit of 10% security money and other conditions of the contract are included
in the contract agreement. Upon the completion of work, a fixed lump sum
amount is paid to the contractor. Detailed measurements of different items are
required but the whole work is compared and checked with drawings and
specifications before releasing the payment. In large projects, part payments are
made to the contractor at different stages of work on mutually agreed terms. In
case the contractor stops the work in between he is not entitled for any further
payment.
Suitability
A lump sum contract is more suitable for works for which contractors have prior
construction experience. This experience enables the contractors to submit a
more realistic bid. This type of contract is not suitable for difficult foundations,
excavations of uncertain character, and projects susceptible to unpredictable
hazards and variations.
Merits
• The owner can decide whether to start or shelve the project knowing the
total lump sum price quoted by different contractors.
• The contractor can earn more profit by in-depth planning and effective
management at site.
Demerits
• Before the contract is awarded, the project has to be studied thoroughly
and the complete contract document has lo be prepared in advance.
• In this type of contract, unforeseen details of work are not specified in the
contract document. Many additional items may have to be undertaken as
the work progresses, giving opportunity to the contractor for claiming
higher rates for the extra items not included in the contract agreement.
Also called a schedule contract, in this contract, the contractor undertakes the
execution of work on an item rate basis. The amount to be received by the
contractor, depends upon the quantities of various items of work actually
executed. The payment to the contractor is made on the basis of detailed
measurements of different items of work actually donc by him.
Suitability
The item rate contract is most commonly used for all types of engineering works
financed by public or government bodies. This type of contract is suitable for
works which can be split into various items and quantities under each item can
be estimated with accuracy.
Merits
• In this type of contract, there is no need for detailed drawings at the time
of allotting contract as ¡n the case of lump sum contract. The detailed
drawings can be prepared after the contract is awarded.
• Changes in drawings and quantities of individual items can be made as
per requirement within agreed limits.
• The payment to the contractor is made on the actual work done by him at
the agreed rates.
Demerits
• The total cost of work can only be known upon completion. As such, the
owner may incur financial difficulty if the final cost increases substantially.
• Additional staff is required w take detailed measurements of work done
for releasing payments to the contractor.
• The scope for additional saving with the use of inferior quality materials
may prompt the contractor to use such materials in the work.
This is similar to the lump sum contract except the schedule of rates is also
included in the contract agreement. In this type of contract the contractor offers
to do a particular work at a fixed sum within a specified lime as per plans and
detailed specifications. The schedule of rates for various items is provided which
regulates the extra amount to bc paid or deducted for any additions or deletions
made during the progress of work. Measurements of different items of original
work are not required but extra items are required to be measured for payment.
The original work shall however be checked and compared with the drawings
and specifications.
Suitability
This type of contract is more suitable for construction works for which
contractors have prior work experience and can consequently estimate the
project cost more realistically.
Merits
• In this type of contract, additional staff for recording detailed
measurement of original item of work is not required for making payment
to the contractor.
• The owner can know from tenders as to what the project will cost him.
Knowing the financial implications, the owner can decide to start or defer
the project.
Demerits
• Before the contract is awarded the project has to be studied thoroughly
and all the contract documents are required to be completed in every
respect.
• The non-scheduled extra items arising out of changes made in the
drawings and specifications are often a source of dispute because the
contractor presses for rates higher than the prevailing market rates.
Cost plus fixed fee contract is desirable when the scope and nature of the work
can atleast be broadly defined. The amount of fee is determined as a lump sum
from a consideration of the scope of work, its approximate cost, nature of work,
estimated time of construction, manpower and equipment requirements etc. In
order to negotiate such a type of contract, it is essential that the scope and some
general details of the work are defined. The contractor in this type of contract is
selected on the basis of merit rather than the fee alone. In case of cost plus
percentage contract, the contractor has a tendency to increase his profit by
increasing the cost of work. But this drawback is overcome in cost plus fixed fee
contract because here the contractor‘s fee is fixed and does not fluctuate with
actual cost of work. Once this fee is fixed, the contractor cannot increase the cost
of work.
Suitability
• This type of contract is suitable for works required to be completed
expeditiously and where it is difficult to foretell what difficulties are likely
to be encountered.
• This contract is also suitable for important structures where the cost of
construction is immaterial.
Merits
• In this type of contract, actual cost is to be borne by the owner. Therefore,
the contractor performs the work in the best interest of the owner
resulting in good quality work.
• The work can be taken in band even before the detailed drawings and
specifications are finalized.
• Changes in design and method of construction if needed can be easily
carried out without disputes.
• The work can be executed speedily.
Demerits
• This form of contract cannot bc adopted normally in case of public bodies
and Government departments.
• The final cost of the work is no known in advance and this may subject the
owner to financial difficulties.
e) Cost Plus Percentage of Cost Contract
In this type of contract, instead of awarding the work on lumsum or item rate basis, it is
given on certain percentage over the actual cost of construction. The actual cost of
construction is reported by the contractor and paid to him by the owner together with
a certain percentage as agreed earlier.
The contractor agrees to do the work in accordance with the drawings, specifications,
other conditions of contract. In this type of contract proper control has been exercised
by the owner in purchase of materials and in arranging labour.
The suitability, merits and demerits of these type of contract are similar to cost plus
fixed fee contarct. An addition to demerit, the tendency of the contractor to increase
the cost of work to earn more profit by way of percentage of enhanced actual cost.
Special contract
There are certain special contract used at different occasions. Some of these contracts
are:
1. Turnkey contract
2. Package contract
3. Negotiated contract
4. Continuing contract
5. Running contract
6. Joint venture contract
7. BOT contract
8. BOOT contract
1. Turnkey contract
A turnkey contract is an integrated contract in which all works pertaining to various
disciplines such as civil, electrical, mechanical etc. are in a single contract called the
main contract. The main contractor can sublet the contract to sub-contractors who
are specialist in their respective fields.
In this contract, the main advantage of the owner is that he need not to coordinate
the work of different contractors. The main contractor is responsible for all kinds of
jobs, starting from planning to commissioning stage. The owner takes over the
entire work which is fully operational and of proven performance from the main
contractor.
2. Package contract
In a package contract, two or more related jobs, each of which could form a
separate contract are combined in a single contract. In the field of civil engineering
generally design and development are combined with construction and supplying
or maintenance.
In this type of contract, plan of work and standards are established and the work is
carried out accordingly by the contractor. The main contractor is responsible for
safe guarding the owner‘s interest , clear approval of design and technical aspect
have to be taken from the owner. The responsibility for the correctness of design
lays with the main contractor.
3. Negotiated contract
In this type of contract negotiation across the table takes place between the
representatives of the owner and the main contractor for the project cost and other
conditions of contract. In this type of contract, detailed project specifications, are
arrived at by discussions between the owner and the main contractor.
A negotiated contract involves extended discussions for finalization as a
competitive contract. Most of the consultancy works of World Bank are negotiated
contract
4. Continuing contract
In this type of contract new or additional work is awarded to the contractor on the
basis of the agreed terms and conditions of an existing contract. Such contract do
not require retendering and hence can save time and money.
5. Running contract
Such contracts provide goods and services at specified intervals or as on when
required by the owner. The contract price is not fixed and the payment is based on
actual goods supplied and services rendered as specified in the contract document.
7. BOT contract
Build - Operate – Transfer , a third party contract to to build, then operate an assest(
for
e.g dam , bridge, road) for a specific amount of time for a fee and then transfer the
asset back to contracting company or entity ( usually a government entity). This is
commonly used by public sector for large capital projects. The system of
contracting is useful when client does not want to invest directly in the project and
wants to encourage development projects through external funding and
investment. It is also a method of attracting and involving the private sector which
typically involve very heavy capital investment
For e.g: a power corporation may ask bidders to setup power plant on BOT basis,
where in the bidder agrees to design and construct the plant for in return for the
right to operate. The plant, say for 10 years, during which the contractor can
generate and sell the power. Design and construction of certain highways or
airways can also be similar done on BOT basis.
8. BOOT contract
BOOT- Build – Own –Operate –Transfer is similar to BOT except that rather than
receiving a fee for operating it. It receives the net income from the asset as if it
owned it. This asset is a revenue generating asset ( e.g: toll bridges, powerstations)
1. Time of completion
2. Delay and extension of time
3. Penalty
4. Compensation of delay in completion of work
5. Liquidated damages
6. Debitable agency
7. Valuation of variations
8. Settlement of disputes
9. Force majeure and natural disaster
10. Price excalation
11. Termination of contract
1. Time of completion
The contract is required to complete the work within the agreed time of completion
which is specified in a suitable unit of time ( year, month, week, days ) depending
on the nature and scope of work. The contractor is also required to maintain the
proportionate progress of work.
2. Delay and extension of time
The delay in completion of work not attributed to the contractor, should be brought
to the notice of the owner by the contractor in writing, within the time specified in
the contract for seeking extension of time. The owner will satisfy himself that the
delay is not on account of a lapse on the part of a contractor before granting
suitable extension of time.
3. Penalty
It is a fine imposed on the contractor for non-fulfillment of contractual obligations
such as failure to maintain required progress of work, delay in completion, poor
quality of work, bad workmanship etc.
4. Compensation for delay in completion of work
The contractor is liable to pay compensation to the owner for delay attributed to
him in completion of work. The amount of compensation may be stated as a
percentage of the estimated cost of work for each unit of time delay. The maximum
limit of compensation may be 10% of the contract price.
5. Liquidated damages
It is a fixed stipulated sum payable by the contractor on account of penalty for
delays and does not bear any relationship to the real damage to the owner. It is
generally high and fixed per day for the excess period over that specified in the
contract for completing the work.
6. Debitable agency
Whenever the contractor fails to fulfill his contractual obligation in respect of
progress or quality of work even after giving due notice by the owner, it becomes
necessary to appoint a debitable agency which works at the cost and risk of the
contractor. This agency is in the form of labour or other contractor to fulfill the
contractual obligations of the main contractor. The expenses incurred are charged
from the bill or security of the original contractor.
7. Valuation of variations
The valuation of variations is based on change in orders issued in writing by the
owner. Generally, the variation in individual items of work should not be more than
25% and variation in total cost should not exceed 10%.
8. Settlement of disputes
Efforts should be made to resolve disputes amicably between the owner and the
contractor through mutual discussions and negotiations. Arbitration clause may be
incorporated in the contract to settle disputes not resolved through mutual
discussions and negotiations.
9. Force majeure and natural disasters
Natural disasters are acts of nature, such as unprecedented floods or rainfall,
earthquake, hurricanes, typhoons, fire etc. These disasters along with occurrence of
riots, revolt etc. are beyond the control of the contractor and may lead to financial
and time loss. The contractor should obtain an insurance policy for such risks as can
be covered by insurance. In the event of financial or time loss, the contractor can
claim financial compensation from the owner for risks which are not insurable and
an extension of time for all such risks.
10. Price escalation
During execution of the work, labour wages and material prices may increase as a
result of inflation. The contract conditions should, therefore, include on appropriate
clause for payment of escalation to the contractor. Generally, escalation payment is
made for increase in the cost of labour, materials and petrol, oil and lubricants (POL)
and the percentages of three components are taken as under:
Labour 30% of contract price
Materials 65% of contract price
POL 5% of contract price
11. Termination of Contract
The owner can terminate the contract in the event of default or bankruptcy of the
contractor and may impose penalty as per the contract agreement. Default on the
part of the contractor includes abandoning the work, failure to maintain required
progress, nonobservance of rules/instructions etc. for which the owner may resend
the contract and impose penalty upto 10% of the estimated cost of the work. Due
notice must be served on the contractor before termination of the contract.
CONTRACT DOCUMENT
Construction works intended to be awarded to be awarded to contractors are given
by publicity so that a sufficient number of interested parties may bid for the work.
Usually the lowest bid is accepted unless there are valid reasons for not following
these practices. Every written contract which clearly describes the work should also
define the right and obligations of the parties. If the right and obligations of the
owner and the contractor are defined in a document , then it is called the contract
document. This document generally follows a standard format for construction
contracts entered into by govt. and public bodies. The contract document consist
of contract agreement on non-judicial stamp paper of prescribed value and the
following sets of document each page of it is signed both by the owner and the
contractor. 1. Cover or Title Page
It contains the name of the work, name of the owner, name of the contractor,
contract agreement number, contents etc.
2. Contents page
It contains the contents of the agreement with page references
3. Notice Inviting Tender(NIT)
It contains a brief description of work estimated cost of work date and time for
receiving the tender, amount of earnest money (EMD), security deposit(SD), time
of completion etc.
4. Tender form
It comprises of bill of quantities, contractor‘s rate, total cost of work, time for
completion, security money to be deposited and penalty process etc.
5. Schedule of issue of materials
It contains the list of materials to be issued by the department or owner to the
contractor with rates or place of issue.
6. Drawings
These comprise a complete set of fully dimensioned drawings including plans,
elevations, sections, detailed drawings and site plan.
7. Specifications
It is not practicable to include the detailed information of each item of work in
the limited space of description in the bill of quantities. As such detailed
agreement forms a part of the contract agreement.
Specification should be clear and precise covering all items of bill of quantities
(BOQ). Following specifications are normally included in the contract document
a. General specification- These specify the class and type of work, quality of
materials etc, in general for the work as a whole.
b. In detailed specification – These views detailed description of each item of
work including material and method to be used along with quality of
workmanship required
8. Conditions Of Contract
The terms and conditions of the contract specify the following.
a. Rates of each item of work inclusive of materials, labour , transport, plant and
equipment and other arrangements required for the completion of work.
b. Amount and form of earnest and security money to be deposited
c. Manner of payment to contractor including running payments, final
payments, refund of security money
d. Time of completion of work
e. Proportionate progress to be achieved
f. Penalty for poor quality and unsatisfactory work, back to proportionate
progress and for delay in completion
g. Extension of time for completion of work
h. Engaging other agency at contractors cost and risk
i. Termination of contract
j. Changes in design and drawings etc and valuation of variations
k. Measurement of the work
l. Arbitration for settlement of disputes
In addition to the above performance and payments bonds are also sometimes
considered as part of the contract document.
All the above stated documents collectively constitute a contract document. The
documents are considered together for the purpose of contract interpretations,
giving rise to meaning and effect to each part of the contract. In general, the
intention of contracting parties is determined from the contract executed by
them. The contractor should generally read and understand the contract before
executing the work.
TENDER
Tender is an offer in writing for executing certain specified work or for supplying
specified materials subject to certain terms and conditions like rates, time limit etc.
TYPES OF TENDERS:
1. Open Tenders
2. Limited tenders
3. Single tender
4. Rate contract
1. Open Tenders
Open tender is a tender in which bids are invited from all contractors. An open
advertisement in the important news papers and Indian trade journal will be
published.
2. Limited Tenders
In this kind of tender, only selected contractors are invited to bid or quote the
rates for the supply of articles or to execute the work
3. Single Tender
Only a single firm or contractor is invited for the tender. If the quoted rates are
high, negotiations prior to agreement are done with the contractor.
4. Rate Contract
This type of contract is used mainly for the supply of stores of items. The
quantities are not mentioned. According to this contract, items are supplied at
fixed rate during the period of contract.
TENDER DOCUMENTS
a) Notice Inviting Tenders.
b) Tender form with standard conditions of contract.
c) Schedule of quantities.
d) Special terms and conditions.
e) Complete specification of work.
f) Special specification and additional condition of contract.
g) Approved drawings where necessary.
PRE-QUALIFICATION PROCESS
There are other terminologies and processes that closely serve the function of the
prequalification process. These are,
• licensing,
• registration of contractors,
• enlistment of contractors, and
• rating or grading of contractors.
Some organizations, instead of resorting to the pre-qualification process again and
again, enlist or register sonic contractors for doing a particular type of work, and they
also specify the limit of contract value (say, up to 5 crore, 5 crore -25 crore, more than
25 crore, and so on) for which the contractors are eligible. As and when any project of
certain value is undertaken by these organizations, the tender document is issued to
the Contractors enlisted for the said contract value. Indeed, this process saves time and
effort for the owner as well as the contracting organization. The enlistment or
registration is done for a particular period. Upon the expiry of the registration period,
fresh application may have to be submitted in order to be registered.
In some countries, there is a system of providing license to the contractors. Under this
system, a project beyond a certain value can he executed by a licensed contractor only.
Under the licensing system, the contractors are awarded license in different categories,
such as common contractors, and special contractors for different types of works such
as civil works, plumbing and sanitary works, and electrical works. These classifications
arc done based on the amount of work executed by the applicant and a number of
other factors including experience of the contractor in relevant construction work;
available stall strength; sales volume of completed projects; financial parameters such
as ratio of current assets to current liabilities, ratio of fixed assets to capital, ratio of net
profit to total liabilities and net worth; construction machinery owned by the contractor;
and safety and labour relations record. As explained earlier, the enlistment or
registration system helps in saving time as every time the pre-qualilication process
need not he repeated. However, for any unusual or specialized kind of work, pre-
qualification process is carried out afresh. Pre-qualification of contractors is done by
government as well as private organizations.
The announcement of pre-qualilication process is advertised in leading dailies, trade
journals, etc., and sometimes also intimated individually to reputed contractors. Typical
document required for prequalifier
• Letter of transmittal
• Power of attorney
• Financial information
• Details of similar work
• Concurrent commitment
• Certificates for completed job
• Structure and organization
• Details of technical and administrative personnel
• Details of plant and equipment
INVITATION OF TENDER
Tender notice
Whenever an agency or a firm wants to float tenders, they are to follow certain
procedures The tenders are to be given publicity in leading dailies by way of
advertisement. A time duration of about a month may be given for the
submission of tenders. However, the tender notice should carry the following
information:
On the date of opening of tender, the sealed tenders are opened in the
presence of contractors or their representatives. Officers have to read out the
rates/amounts offered. The comparative statement showing the quoted rates all
participated contractors must be published. Tenders that are not received in
proper form duly filled can be rejected.
Acceptance of tender
Work Order
A work order is issued after the intimation of the acceptance. Formal agreement
has to be made within the specified days. Letter issued after formal agreement.
Date of completion is treated from the date of issue of work order. Execution of
civil engineering works. The execution of any proposed civil engineering work
can be divided into two stages.
a) Preliminaries
b) Execution of works Execution of works:
Before a work is taken in hand for execution, the following condition should be
followed systematically.
It is the assurance or guarantee in the form of cash on the part of the contractor
to keep open the offer for consideration and to confirm his intention to take up
the work accepted in his favor for execution. In case if tender fails, this money is
forfeited to government.
• Rs. 50/- for works up to 2000/- Rs.100/- for works of 2000/- to 5000/- Rs
200/- for works from 5000/- to 10000/- and Rs 100/- for every additional
5000/- or part there of above Rs. 10000/-
• The earnest money may be cash or encashable at any time. It may be in
form of deposit in treasury or State Bank or other approved Bank or
government security or saving certificate or post office savings pass book
or cash certificate pledges to the Executive Engineer.
SECURITY DEPOSIT
Amount deposited by the contractor whose tender has been accepted in order
to render himself liable to dept. to pay compensation if the work is not carried
out according to specification, time limit, conditions of contract.
• -0.5% on rest
• -0.5% on second lakh , 5% on rest.
Deposit is refundable after prescribed maintenance period.
For workers costing up to Rs. 100000/- as security money is 10% of the estimated
cost. For costing more than one lakh and up to two lakh rupees the security
money is 10% on first one lakh and 7.5% on the balance. In case of works costing
more than two lakh the amount of security deposit will be 10% on the first, one
lakh 7.5% on the next one lakh and 5% on the balance subjected to the
maximum of Rs.one lakh only.
MEASUREMENTS
Measurement of a building occupies a very important place in the planning and
execution of any civil engineering works from the time of first estimate to the
final completion and settlement of payment for the project. The work is divided
into sub heads for keeping accounts of money and materials accurately.
Accuracy is a must in measurement and should be kept as under.
c) Cubic contents shall be worked out to the nearest 0.01 cubic metre.
Loss of MB:
On checking:
SMB is mainly used for periodical repairs and maintenance works which are to
be carried out at fixed intervals of time. For small works it may be single MB but
in case of large works it consists of a set of MBs. Single MB or a set of MBs where
the detailed measurements of certain items of works of a building is recorded
correctly in ink after the completion of construction and whose accuracy is
certified by an officer of the rank not less than AE is known as SMB. Any alteration
in structure is entered in SMB. SMB is checked every 5 years and this checking is
termed as Quennial Checking.
QUALITY
Quality is perceived differently by different people. Yet, everyone understands
what is meant by ―quality.‖ In a manufactured product, the customer as a user
recognizes the quality of fit, finish, appearance, function, and performance. The
quality of service may be rated based on the degree of satisfaction by the
customer receiving the service. The relevant dictionary meaning of quality is
―the degree of excellence.‖ However, this definition is relative in nature. The
ultimate test in this evaluation process lies with the consumer. The customer‘s
needs must be translated into measurable characteristics in a product or service.
Once the specifications are developed, ways to measure and monitor the
characteristics need to be found. This provides the basis for continuous
improvement in the product or service. The ultimate aim is to ensure that the
customer will be satisfied to pay for the product or service. This should result in
a reasonable profit for the producer or the service provider. The relationship with
a customer is a lasting one. The reliability of a product plays an important role in
developing this relationship
QUALITY CONCEPTS
1. Quality
2. Grade
3. Inspection
4. Quality control
5. Quality assurance
6. Quality management
7. Total quality management
8. ISO standards
1. Quality
A subjective term for which each person has his or her own definition.
• Characteristics of a product that bears on it‘s ability to satisfy
the stated or implied needs
• A product or service free of deficiencies.
2. Grade
According to ISO 9001:2000 Category or rank given to different quality
requirements for products, processes, or systems having the same functional
use.
3. Inspection
▪ It is the sorting / segregation of Non conforming items from the
conforming items
▪ Means separation of Defective items from the right items
4. Quality Control
Is the operational techniques and activities that are used to fulfill the
requirements for quality .
5. Quality Assurance
Is all systematic and planned actions which are necessary to provide adequate
confidence that a product or service will satisfy the given requirement for quality.
6. Quality Management
Is a systematic set of operating procedures which is companywide, documented,
implemented and maintained while ensuring the growth of business in a
consistent manner. So QMS is meant to establish a framework of reference to
ensure that every time process is performed, the same information, method,
skills, and controls are used and applied in a consistent manner.
7. Total Quality Management
The comprehensive approach towards quality management system. The process
of individual & organizational development the purpose of which is to increase
the level of satisfaction of all the stakeholders.
INSPECTION
Objectives of Inspection
ii To protect the consumer from receiving a product that is below the quality
level and limits specified, by sorting the good units or lots from those which are
below standard, permits only good quality to pass inspection.
i Sampling Inspection
This kind of inspection is performed over a random number of units which are
drawn from a lot of product. This random number is considered as
representative of the entire lot. The lot is accepted or rejected as the result of
examination. This procedure may be employed in either of the two conditions.
b. When the test procedure destroys the unit, there is a need to change
necessary procedure.
The advantages of this type of inspection are that in this procedure the inspector
is not fatigued and sometimes it may be more effective than 100% inspection.
ii Centralized Inspection
Comparatively light and small parts and assemblies are transported to the
inspection department for examination. Usually this department is located in a
place that is separated from manufacturing areas so that a proper care can be
imparted to tools and inspection can be carrid over without interference.
Heavy parts and assemblies are examined at the production center itself, since
they cannot be transported to inspection department.
v Working Inspection
After a machine or machines have been released for production, the work be
inspected periodically in the production time itself by inspection going to the
machine itself.
And if any defect occurs then machine may be corrected by shutting down it.
Machines may be taken from assembly lines and seen for specified time or until
failure occurs. Then the components of the machine are inspected to discover
the effect of use. This type of inspection is common with automobiles.
QUALITY CONTROL
Quality control is the control over process. It consists of two major processes.
Total Quality Control defined as an effective system for integrating the quality
development, quality maintenance and quality improvement efforts of the
various groups in an organization so as to enable production and service at the
most economical level which allow for full customer satisfaction.
Total quality control is an aid for good engineering designs, good manufacturing
methods and conscious inspection activity that have always been required for
the production of high quality articles.
Quality of any product is effected at many stages of the industrial cycle :
• Marketing : Evaluates the level of Quality which customers want for which
they are willing to pay.
• Purchasing : Chooses, contracts with and retains vendors for parts and
materials.
service. In other words, the determination of both quality and quality costs
actually takes
place throughout the entire industrial cycle. Quality control is responsible for
quality assurance at optimum quality costs.
Benefits:
CONCEPTS OF TQM
1. Ethics
2. Integrity
3. Trust
4. Training
5. Teamwork
6. Leadership
7. Recognition
8. Communication
Key Elements
TQM has been coined to describe a philosophy that makes quality the driving
force behind leadership, design, planning, and improvement initiatives. For this,
TQM requires the help of those eight key elements. These elements can be
divided into four groups according to their function. The groups are:
1. Ethics – Ethics is the discipline concerned with good and bad in any
situation. It is a two-faceted subject represented by organizational and individual
ethics. Organizational ethics establish a business code of ethics that outlines
guidelines that all employees are to adhere to in the performance of their work.
Individual ethics include personal rights or wrongs.
II. Bricks
Basing on the strong foundation of trust, ethics and integrity, bricks are placed
to reach the roof of recognition. It includes:
4. Training – Training is very important for employees to be highly
productive. Supervisors are solely responsible for implementing TQM within
their departments, and teaching their employees the philosophies of TQM.
Training that employees require are interpersonal skills, the ability to function
within teams, problem solving, decision making, job management performance
analysis and improvement, business economics and technical skills. During the
creation and formation of TQM, employees are trained so that they can become
effective employees for the company.
IV. Roof
8. Recognition – Recognition is the last and final element in the entire system. It
should be provided for both suggestions and achievements for teams as well as
individuals. Employees strive to receive recognition for themselves and their
teams. Detecting and recognizing contributors is the most important job of a
supervisor. As people are recognized, there can be huge changes in self-esteem,
productivity, quality and the amount of effort exhorted to the task at hand.
Recognition comes in its best form when it is immediately following an action
that an employee has performed.
Recognition comes in different ways, places and time such as,
• Time – Recognition can given at any time like in staff meeting, annual
award banquets, etc.
PRINCIPLES OF TQM
Every action by every employee should add value to the process or product in
every way all the time. Enhance your work by your actions.
Develop a pattern of delivering perfect products & services on time. Rate your
sources by their ability to do this.
Teach Problem -Solving Tools / Techniques & Teaming as the means to solve
quality, safety, productivity, and deliverability problems.
5. Empower employees
-who have proven their capability. Reward and reinforce empowerment with
Incentives, Job Security and Equity Sharing. Make employees owners of the
process, not attendants.
- before Making Decisions. "It never hurts to turn the light on." (J. DeSimone).
Make
Decisions based on evidence. "If you can't measure it, you can't evaluate it."
9. Apply the '80/20' principle:
Use this Problem-Solving Tool to put problems into 'Trivial Many' and 'Vital Few'
categories. Record the causes and frequencies of problems on a Tally Sheet.
Develop this into a Pareto Chart which plots the frequencies (most- to least-
important) of the problems. 20% of the causes create at least 80% of the
problems. Importance of resolving vital problems first.
Create solutions that will benefit all parties. Cooperation that develops
synergism is the best solution.
Use the tools of TQM, SPC, and Problem-Solving to achieve these goals by
detecting and eliminating the causes.
15. Deliverability:
The Right Product at the Right Place at the Right Time. In world-class Just-in-Time
(JIT) delivery systems, source parts are used without delay and inspection
in the process.
IMPLEMENTATION OF TQM:
7. Zero defect planning : When the performance of the organisation and its
employees has reached a reasonably good level the quality improvement team
moves ahead and plans for a foolproof system of the zero defect or the DO IT
RIGHT THE FIRST TIME culture. The suitable quality improvement tools are
implemented for elimination of the organisational problems.
8. Employee education : now the quality improvement team with the help
of the consultants imparts training and education on the ‗quality improvement
tools‘ for systematically and scientifically undertaking the quality improvement
projects and reducing the cost of non-conformnace.
9. Zero defect days: the quality improvement team plans for occasional zero
defect days as the practical implementation of the zero defect planning.The
team closely monitors the processes and the activities on a zero defect day and
ensures that the employees actually believes that zero defect is possible by
seeing the actual zero defect day happening.
10. Goal setting : The quality improvement team should help individual
functions and activities set up their on individual objectives and goals and
suitable quality improvement project for the same.The team should set up for
itself the attainment of the organisational objective and a strategic action plan
for the same.
11. Error cause removal : the quality improvement team should not settle
down for the corrective action alone after finding out the root cause of the
problem as it will give only temporary relief from the cost of non-
conformance.there is a good likelihood that the problem may repeat
again.hence the quality improvement team should find out the root cause of
each problemand try to take preventive action for the removal of the root cause.
13. Quality council : The quality improvement team should submit a periodic
report of the activity of the quality improvement projects to the quality
council.concil discusses all the quality improvement activities and takes a
decision on their implementation along with the resource allocation and revises
their implementation periodically.
14. Do it over again : The quality improvement team take stock of the
successful quality improvement projects and measure the gain from such
projects . The quality council and the quality improvement team now examine
critically all the functions and try to identify the area where the similar spin-off
projects can be taken up straight way for implementation.
ADVANTAGES OF TQM