EC Unit 001 new
EC Unit 001 new
1. Estimating and costing Cost accounting: various methods, classification of cost, direct and indirect charges,
BECVE 702 T Evaluation Scheme 80/20 distribution of overheads, MAS account, issue rates, and store account
L(3)+T(1) =4 hrs/week total credits: 4 Exam duration: 4hrs
UnitV
Course outcomes: Rate analysis: Introduction, purpose aand principles of cSR, Factors affecting
1. Prepare the preliminary estimate for administrative approval & technical sanction for analysis of rates, labour guidelines form national building organization, market rates
civil engineering project of materials and labour, Rate analysis of major items of work
2. Write the specification of the works to be undertaken, prepare the tender documents, fill
the contracts and make use of knowledge of different contract submission & opening in Unit VI
awarding the work to the contractor.
Valuation: purpose of valuation, Factors affecting property price and cost. Types of
3. Use concepts of SD, HMD, MAS, Running bill, final bill during the entire project
4. Schedule the project for its timely completion
value, real estate, tenure of land, free hod and lease hold, sinking fund, depreciation,
5. Use the technique of rate analysis in estimating the exact cost of material & manpower and its methods, Capitalised value, method of valuation, net and gross income, rent
and hence the entire project fixation.
6. Estimate the bill of quantities using different techniques of preliminary and detailed
estimation of buildings and roads Reference books:
7. Arrive the exact value of the asset (movable & immovable) using different valuation 1. Estimating and Costing BN Dutta (S Dutta & Co)
techniques 2. Estimating, Costing and .. : M Chakraborti (By author)
(Teacher: Peruse various government documents, know Market rates, terms used in 3. Contracts and Estimates: BS Patil (Universities press)
local practice, constructional aspects ..... ] 4. Engineer's Duties and accounts: S K Hussain (Satya prakashan)
Syllabus: 5. Professional Practice: Roshan Namavati (Lakahni book depot)
Unit I
Introduction: Importance and purpose of the subject, units of measurements as per IS Practical:
1 200. Items of work and description of items of work, administrative approval, BECVE 702 P Evaluation scheme 50 + 50
technical sanction, preliminary estimates, objectives, and its methods P-2 hrs/ week Total credits: 2
"
Unit II , Minimum of 8 practical assignments based on
Detailed estimates: objectives, importance, accuracy, methods of detailed estimates. 1. Preliminary estimate using plinth area method
Detailed estimate of load bearing and framed structures, calculating reinforcing steel 2. Detailed estimate of load bearing structure
with Bar bending schedule. 3. Detailed estimate of framed structure
4. Calculation of steel with BBS
Unit III 5. Detailed estimate of earthwork of road for approximate 1 km length
Tenders and contracts: Method of carrying out works, tender notice, acceptance of 6. Draft detailed specifications of 8 major works
tender, essentials of contract, types of contracts, contract documents, , land 7. Analysis of unit rate of 8 major items of work
acquisition act, legal aspects of various contract provisions, arbitration. 8. Draft a short tender notice for proposed work
9. Calculation of annual, total depreciation and book value of the end of each ear
10. Fixation of standard rent of the property
Unit IV 11. Market survey for material and labour rates for various items
Specifications: IS 1200 introduction, purpose and principles of specification writing, 12. Detailed planning and estimate of plumbing work
types of specifications, writing and developing detailed specifications and important 13. Detailed estimate of building using estimate software.
items of building and road work (Proper bound submission]
1|Page Estimating & Costing VII BE (Civil) Prof. R.V.R.K.Prasad KDKCE, Nagpur
IS:1200(Part x):_ Methods of measurement of Building and Civil Engineering Approximate building estimates
Works The common methods used to estimate the costs of buildings approximately are
Part Year Title Pa
ges 1. Plinth area (or square meter) method
1 IS:1200 ( Part I ) 1992 Earth work 4 2. Cubic contents (cubic rate or cubic meter) method
2 IS: 1200 (Part II) 1974 Concrete Works 11 3. Service unit method
->
IS: 1200 (Part III) 1976 Brick work 9 4. Bay method
4 IS:1200 (Part IV) 1976 Stone Masonry 9 5. Cost comparison method
5 IS: 1200 (PartV) 1982 Form work 6 6. Approximate quantities and bill method
6 IS:1200 (Part VI) 1974 Refractory work 4 7. Cost from materials method
7 IS:1200 (Part VII) 1972 Hard ware 4
8 IS: 1200 (Part VIII) 1993 Steel work and Iron work 4 1. Plinth area (or square meter) method
9 IS: 1200 (Part IX) 1973 Roof covering 7 In this method the plinth area of the building is multiplied by the rate per square
10 15:1200 (Part X) -i meter of the plinth area. To arrive at a suitable rate per square meter of plinth area,
1973 Ceiling and lining
cost of similar constructions in that locality at that time should be known. The plinth
11 IS:1200 (Part XI) 1977 Paving, floor, dado skirting 7
area rate depends on the location, type of building, quality of materials, shape of
12 IS: 1200 (Part XII) 1976 Plastering and pointing 7
building, arrangement of internal rooms etc.
13 IS:1200 (Part XIII) 1994 White wash, distemper 2
14 1S:1200 (Part XIV) 1984 Glazing 3 2. Cubic contents (cubic rate or cubic meter) method
15 IS: 1200 (Part XV) 1987 Paint varnish 4 As the cost of construction depends upon the volume of materials required for it, it is,
16 IS:1200 (Part XVI) 1979 Water and sewer lines 5 more reliable to estimate the approximate cost based on the volume of a building.
17 IS:1200 (Part XVII) 1985 Road and pavements 7 In this method the approximate cost is arrived by multiplying the volume of the
18 IS: 1200 (Part XVIII) 1974 Demolition and dismantling 7 proposed building by its rate. The per cubic meter of construction can be known from
19 IS:1200 (Part XIX) 1981 Water supply, plumbing 6 that locality from similar construction at that date. The height of the building may be
20 IS: 1200 (Part XX) 1981 Gas pipe line 4 measured from the mid way between the GL and foundation level. In case of pitched
21 IS: 1200 (Part XXI) 1973 Wood work 7 roofs it should be upto midway between the ridge and point of intersection of roof
22 IS: 1200 (Part XXII) 1982 Materials 5 with outer walls. In case of buildings with parapet walls it should be up to the mid-
23 IS: 1200 (Part XXIII) 1986 Piling 5 height.
24 IS:1200 (Part XXIV) 1983 Well foundations 4
25 IS:1200 (Part XXV) 1971 Tunneling 5 These are better suitable for estimating the cost of ware houses, etc where height is a
26 IS: 1200 (Part XXVI) 1987 Acid resistant lining 4 predominant factor.
27 IS: 1200 (Part XXVI 1) 1992 Earthwork by mechanical appliances 2
28 IS: 1200 (PartXXVIIl) 1992 Sound insulation work 1 3. Service unit method
In this cost per unit service quantity is to be known. Suitable units for roads and
bridges is length, schools and colleges is student, water tank is liter, hospitals is bed
etc. In this method first the estimated cost per service unit is prepared first and later
this is multiplied by corresponding units.
V> '
Ex.3 Prepare an approximate estimate for a hospital with 100 beds for the following
data:
1. Carpet are required per bed =30 sqm
2. Corridors, lavatories and other ammonites =20% of carpet area
3. Walls occupy 10% of the carpet area
4. Cost of construction - Rs.9,300/- per square meter of plinth.,
5. Cost of water supply = 7% of the construction cost
6. Cost of sanitation = 8% of the construction cost
7. Cost of electrification = 12% of the construction cost
8. Cost of boundary walls and internal roads = 3% of the construction cost
9. Contingencies = 3 % of the total building cost
10. Work charged establishment = 4% of the total building cost.
Solution:
Appropriations and re-appropriations The term 'contingencies' indicate the incidental expenses of miscellaneous character
which cannot be classified under any distinct item or sub-head, yet pertain to the
Appropriation means assignment to meet specified expenditure of funds included in a work as a whole.
primary unit of appropriation. Re-appropriation means the transfer of funds from one
unit of appropriation to another under such unit. It is a fundamental principle that no In an estimate a certain amount in the form of contingencies, of 3 to 5 percent of
outlay on a work shall be incurred without funds having been allotted for it by estimated cost, is provided to allow for the expenses for miscellaneous petty items
appropriation or re-appropriation. In exceptional cases, where expenditure is which do not fall under any sub-head of item of work. Miscellaneous incidental
|Page Estimating & Costing V I I B E ( C i v 1) P r o f . R . V . R . K . P r a s ad , KDKCE, Nagpur
expenses cannot be classified under any sub-head or item, are met from the amount preliminary works like soil testing, site survey/contour etc., are to be done before
provided under contingencies. hand, a small estimate may be sent to the client and deposits received.
If there is any saving against the amount provided under contingencies, this amount Realization of deposits
may be utilized with the sanction of the competent authority, to meet the expenses of
extra items of work, if any unforeseen expenditure, expenses to minor changes in Whenever a deposit work is to be undertaken, the deposit should be realised before
design etc. any liability is incurred on the work. 1% of the anticipated project cost should be
realised before preparation of preliminary estimates. In addition to the outlay on the
Work-charged establishment: work in the preliminary estimate, departmental charges shall also be realized in
advance. No interest will be allowed on sums deposited from any source, including
Work-charged establishment is the establishment which is charged to the works private contributions.
directly. During the construction of a building or a project, a certain number of
work-supervisors, chaukidars, mates munshis etc. are required to be employed, and
their salaries are paid from the amount of work-charged establishment provided in Centage charges (Departmental charges/ Supervison charges):
the estimate. When an engineering department takes up the work of other department a percentage
For work-charged establishment a percentage of 1 Vi to 2 % of the estimated cost is amount of 10 to 15 % of the estimated cost is charged to meet the expenses of
included in the estimate. The work-charged employees are temporary staff and their establishment, designing, planning, supervision etc. and the this percentage charge is
appointment shall have to be sanctioned by the competent authority for a specific known as centage charge. The centage charge is also made on contributory and
period. The services are terminated at the expiry of the sanction period, if their deposit works of local bodies, private persons and others. The centage charge is
services are required a fresh sanction shall have to be taken. The services can, provided in the estimate of the work. State PWD charges 10 to 15% when the work
however, be terminated any time but a prior (usually one month) notice is given. of Central Government is under taken for execution. These charges are also known as
supervision charges.
DEPOSIT WORKS
Traditional brick size = 9" x 4 !/2 " x3" (Varied traditional sizes in our country)
The term 'Deposit Works' is applied to works of construction or repairs and
maintenance, the cost of which is met out of Government grants to autonomous or Deductions for plastering and pointing: (IS 1200)
semi-autonomous bodies or institutions through their Administrative Ministries, or is Deductions for openings are made as follows:
financed from non-Government sources wholly or partly from: i) Funds of public Area of opening Deductions
nature, but not included in the financial estimates and accounts of the Union of India, < 0.5 m2 No deduction for opening is made and no addition for
ii) Contributions from the public. (small openings jamb, soffits, sills is allowed.
The funds may either be deposited in cash or otherwise placed at the disposal of the 0.5 m2-3m2 Deduction is made for one face only, the other face is allowed
Divisional Officer. Where a work is to be carried out partly from funds provided in for jamb, soffits, sills
the financial estimates of the Department and partly from funds of the foregoing >3m2 Deductions are made for both faces of the opening, area for
nature, the contribution should be considered as a lump sum in addition to the (large openings) jamb, soffits, sills is added separately
Government grant.
Measurement for Painting of Doors and windows: (follow IS 1200)
Before acceptance of any deposit by the EE, it is essential that an estimate should be The measurements for painting or varnishing of doors and windows should be as per
sent to the client Department after fully ascertaining all necessary site details, their outer dimensions.
technical feasibility, topographical details, ownership of land etc. In case any*
|Page Estimating & Costing VII BE (Civi I) Prof. R.V.R.K.Prasad. KDKCE, Nagpur
Type of Door/Window Area for both the faces* tender with or P
Paneled, framed, ledged, 2'/2 times that of one surface area without negotiations
battened and braced 4 Acceptance of single 0.75 4.5 62.5 125 500 800 1000 FP
Fully glazed 1 times that of one surface area tender with or
Partly paneled and partly 2 times that of one surface area without negotiations
glazed 5 Award of work 0.60 4 6 12 30 150 300 FP
Flush door 2 times that of one surface area without call of
Venetian 3 times that of one surface area tenders
Iron bars, grills 1 times of one opening area(between chowkats) 6 Splitting up projects/ 30 125 250 1000 1300 1600 FP
works/ sub-heads
Unit conversion ( FPS - MKS(SI) ) {Where sanctioned
cost of Work/Distinct
Sub Head to be split
1 Inch = 25.4mm 1 mile = 8x220 yds =1.609 km up is)
1 foot - ; 04.8 mm 1 acre = 1 Ox222 yd2 =4046.8 m2 7 Accord of sanction to 10% 15% 15% 30% FP
1 m2 =1 0.764 ft2 deviation in quantities con con con con
1 m3 - 3; .315ft 3 of agreement items 50% (TS)
Unit wei; 2/162.196 kg -^where ty in mm
Measurernent Box (Furma) size = 12"xl2"14.7r-»0.305 x 0.305 x 0.374 8 Accord of sanction to 30% 30% 30% 30% FP
extra /substituted con con con con
P-1440 items 30% (TS) 100%(TS)
Format Abstract of estimate form For 7 & 8 Deviations up to + 10% of agreement quant ty will not '
Item Description or Quantity unit Rate Amount require any sanction.
No particulars 9 Invitation of tenders Up to 10%ofTS FP
for components parts power
FP: Full Powers SE/PSE promoted on in situ basis
Delegation of Financial Powers Rules, 1Q78. (DFPR1 INDhX
S Centage (Departmental/ supervision) Report
. -a
CU O fc Charges Supervision charges -> centage charges
m u u3 UJ UJ Q 0 > £™ 0
< w 09 V) rj < Q C u CQ Contingencies Traditional brick size
Deductions for plastering and pointing Unit conversion
Extent of power in Rs. (lacs)
150 Departmental charges -> centage charges Work-charged establishment
I To accord 5 12.5 25 250 500
Formats The Schedule of Rates for Delhi
Administrative
Measurements for painting of doors and
Approval and
expenditure sanction windows
T
2 Accord of technical J 45 125 250 FP
sanction to detailed
estimates (Civ&Ele) •
*>
^ Acceptance of lowest 45 125 250 1000 1300 1600 Full
Page Estimating & Costing VI! BE ( C i v i l ) Prof. R .V . R . K . P r a s a d . KDKCE, Nagpur
Awd I
Earth-work calculations Solution:
The usual cross section of a road or canal is trapezoidal. Chainage 0 30 60 90 120 150 180
RLofFL 100 100.3 100.6 100. .9 101.2 101.5 101.8
RLofGL 98.2 98.1 98 97.7 98.8 99.4 100.2
h, emban 1.8 2.2 2.6 3.2 2.4 2.1 1.6
Area 28.08 36.08 44.72 58.88 40.32 34.02 24.32
-B-
Road in Embankment Road in cutting
The side slopes are 1 in s and the level of formation above GL is 'h' Volume by Average area method / Trapezoidal rule:
Area of trapezium, A = h(b+sh) 30
— [28.08 + 24.32 + 2(36.08 + 44.72 + 58.88 + 40.32 + 34.02)] = 7206.6m3
Z*
The quantity /volume of earthwork is determined by: Volume by prismoidal rule / Simpson's rule:
1. Average area method (trapezoidal rule) 30
2. Mid ordinate method — [28.08 + 24.32 + 4(36.08 + 58.88 + 34.02) + 2(44.72 + 40.32)] = 7384m3
3. Simpson's rule (Prismoidal formula) Volume b
ch 0 30 60 90 120 150 180
1 . Trapezoidal rule:V = c +c +- +c +c h 1.8 2.2 2.6 3.2 2.4 2.1 1.6
mid 2.0 2.4 2.9 2.8 2.25 1.85
— — (Ao + 2Ai + 2A2 + 2An_! + A n ) A 32 40.32^ 51.62 49.28, 37.125 29.045
v -in*/T>-i-,in v>jxi zij-AQ o»j-n IO^J-OQ n/i<a--7iei -r m3
.2. Simpson's rule: It is applicable for even number of segments:- 02)
^ ./ Calculate the quantity
_i it of earthwork for a hill road with the following
- g data
_ c ^ _ j c ^ _ j _ c ^ _
Q1) Determine quantity of earthwork in a road project for which levels taken along
the longitudinal section are as below. Width of formation is 12m. and the side
slopes are 1 in 2. All the values are in meters. Use i)Average area method ii)
prismoidal formula and iii) average ordinate rule. Chainage 180 210 240 270 300 330 360
RLofFL 100 100.5 101.0 101.5 102.0 102.5 103.0
Chainage 0 30 60 90 120 150 180 RLofGL 102 101.9 101.8 101.8 101.4 101 100.6
RLofFL 100 h, emban -2 -1.4 -0.8 -0.3 0.6 1.5 2.4
Gradient + 1 in 100
GL 98.2 98.1 98 97.7 98.8 99.4 100.2 0.3
; x = 10m-» Chainge at GL eFl, is 270+10 = 280m
30 0.3+0.6
FromA2,
T-
—- , -r."
_ A 1. "Z — i.llii — ± - •
1
For partial cutting / Filling — depending upon 'h' A&0 = 12*0.5 + - (—) (. 74)2 + - (— ] (0.26)2 = 6 + 0.595 + 0.0626 = 6.658
L \ C) r & \£i I /
-b/2i
2 \r-
l/15xl.5\ 1/15x1.5
.lso = 12^.4 + -(^-r)(0.8^+-(^r = 4.8 + 0.533 + 0 = 5.33
i,\
Or WHY?
Summary:
chainage A V Cum volume
0 32.222 0 rs \ 1 rs b_2
— 1 + bh + -(
30 3.92 542.13 542.13 2 Vr - 2r/ 2 \r ^r1
60 6.658 158.67 700.8
90 2.782 141.6 842.4 Or
105 0.052 21.255 863.655
120 2.654 (-)19.515 844.14 (6/1 + sh 2 ) +
-2 _ Lr2 - s2- (l-s 2 /r 2 )
150 5.33 (-)l 19.76 724.38
180 15.156 (-)307.29 417.09 For partial cutting / Filling -- depending upon 'h
f O V
2\r-s
Or
A=- h- —
2\r-s
vA L*