Solved Problems Pro.Planning Control
Solved Problems Pro.Planning Control
PRODUCTION
PLANNING & CONTROL
August 2012
Solved Problems in Production Planning & Control 2012
I. Forecasting
WMAn = W iDi
i=1
where
Exponential Smoothing
Ft+1 = Dt + (1 – ) Ft
where
where
where
y = a + bx
where
2|P a g e
Solved Problems in Production Planning & Control 2012
xy – nxy
b = -------------------------
x2 – nx2
a = y – bx
where
n = number of periods
x
x = ----------------- = the mean of the x values
n
y
y = ----------------- = the mean of the y values
n
Seasonal Factor
Di
Si = --------------
D
where
Di = demand in period i
Forecast Accuracy
Dt – Ft /
MAD = -------------------------
n
where
3|P a g e
Solved Problems in Production Planning & Control 2012
Dt – Ft /
MAPD = -------------------------
Dt
Cumulative Error
E= et
Average Error
et
E = ------------------
n
Forecast Control
(Dt – Ft ) E
Tracking Signal = ---------------------------------- = ----------------
MAD MAD
(Dt – Ft )2
Mean Squared Error = ---------------------------------
n–1
Linear Regression
y = a + bx
where
a = the intercept
b = the slope of the line
x = the independent variable
y = the dependent variable
xy – nxy
b = -------------------------
2 2
x – nx
a = y – bx
4|P a g e
Solved Problems in Production Planning & Control 2012
where
n = number of variables
x
x = ----------------- = the mean of the x data
n
y
y = ----------------- = the mean of the y data
n
Correlation
n xy – x y
r = --------------------------------------------------------
[n x2 – ( x)2] [n y2 – ( y)2]
Coefficient of Determination = r2
CoD
Annual Ordering Cost = ------------
Q
where
CcQ
Annual Carrying Cots = ------------
2
where
5|P a g e
Solved Problems in Production Planning & Control 2012
CoD CcQ
TC = -------------- + ---------------
Q 2
Optimal Value of Q
2CoD
Qopt = -----------------
Cc
CoD CcQopt
TCmin = -------------- + ----------------
Qopt 2
Let:
p = daily rate at which the order is received over time, also known as the production rate.
CoD CcQ
Total Annual Inventory Cost = ------------- + ------------- (1 – d/p)
Q 2
Optimal Value Q
2CoD
Qopt = ---------------------
Cc(1 – d/p)
6|P a g e
Solved Problems in Production Planning & Control 2012
Quantity Discounts
CoD CcQ
TC = -------------- + --------------- + PD
Q 2
where
R = dL
where
R = dL + z d L
where
Q = d(tb + L) + (z d tb + L ) – I
where
7|P a g e
Solved Problems in Production Planning & Control 2012
Capacity
Utilization
Time Working
Utilization = --------------------------------------
Total Time Available
Load Percent
Load
Load Percent = -------------------- x 100%
Capacity
IV. Scheduling
Minimum Slack
Critical Ratio
1. Perform row reductions by subtracting the minimum value in each row from all other row values.
2. Perform column reductions by subtracting the minimum value in each column from all other
column values.
3. The resulting table is an opportunity cost matrix. Cross out all zeroes in the matrix using the
minimum number of horizontal or vertical lines.
4. If the number of lines equals the number of rows in the matrix, an optimum solution has been
reached and assignments can be made where the zeros appear. Otherwise, modify the matrix by
subtracting the minimum uncrossed value from all other uncrossed values and adding this same
amount to all cells where two lines intersect. All other values in the matrix remain unchanged.
5. Repeat steps 3 and 4 until an optimum solution is reached.
8|P a g e
Solved Problems in Production Planning & Control 2012
1. List the time required to complete each job at each process. Set up a one dimensional matrix to
represent the desired sequence with the number of slots equal to the number of jobs.
2. Select the smallest processing time at either process. If that time occurs at process 1, put the
associated job as near to the beginning of the sequence as possible.
3. If the smallest time occurs at process 2, put the associated job as near to the end of the
sequence as possible.
4. Remove the job from the list.
5. Repeat steps 2 – 4 until all slots in the matrix have been filled or all jobs have been sequenced.
V. Just-In-Time Systems
Number of Kanbans
dL +S
N = --------------------
C
where
9|P a g e
Solved Problems in Production Planning & Control 2012
1. The facilities, functions, and activities involved in producing and delivering a product or service, from
suppliers to customers.
2. He introduced the interchangeable parts that allowed the manufacture of firearms, clocks, watches,
sewing machines, and other goods to shift from customized one-at-a-time production to volume
production of standardized parts.
3. When higher levels of output cost more per unit to produce is called –
4. As the number of units produced increases, the cost of producing each individual unit decreases, which
is known as --
5. A mathematical technique that solves a set of four quadratic equations to determine the optimal
workforce size and production rate.
24 | P a g e
Solved Problems in Production Planning & Control 2012
7. It is the setting of broad policies and plans for using the resources of a firm to best support the firm’s
long term competitive strategy
8. An average demand for a fixed sequence of periods including the most recent period.
9. These are the basic criteria that permit the firm’s products to be considered as candidates for purchase
by customers.
11. An aggregate planning strategy that varies two or more capacity factors to determine a feasible
production plan.
12. These are the criteria that differentiate the products and services of one firm from another.
13. A pricing schedule in which lower prices are provided for specific higher order quantities is called –
25 | P a g e
Solved Problems in Production Planning & Control 2012
14. Typically component parts or materials used in the process to produce a final product is called –
15. A measure computed by dividing the cumulative error by MAD and it is used for monitoring bias in a
forecast.
16. A computerized system that plans all the resources necessary for manufacturing, including financial
and marketing analysis, feedback loops, and overall business plan.
17. A method for classifying inventory items according to their dollar value to the firm based on the
principle that only a few items account for the greatest dollar value of total inventory.
18. The production of a very high-volume commodity product with highly automated equipment is called --
19. The process of determining the quantity and timing of production over an intermediate time frame is
called --
26 | P a g e
Solved Problems in Production Planning & Control 2012
20. The limiting of suppliers or transportation carriers for a company to a relative few is called –
a. Group-Sourcing b. Double-Sourcing
c. Single-Sourcing d. Demand-Sourcing
Answer: c. Single-Sourcing
22. It measures the portion of the variation in the dependent variable that can be attributed to the
independent variable.
23. The process of breaking down the aggregate plan into more detailed plans.
Answer: b. Disaggregation
24. A list of all the materials, parts, and assemblies that make up a product, including quantities, parent-
component relationships, and order of assemblies.
25. A procedure for acquiring informed judgments and opinions from knowledgeable individuals to use as
a subjective forecast.
26. The cost of replenishing the stock of inventory including requisition cost, transportation and shipping,
receiving, inspection, handling, and so forth is called –
27 | P a g e
Solved Problems in Production Planning & Control 2012
27. The probability that the amount of inventory on hand during the lead time is sufficient to meet
expected demand.
28. A forecast using the linear regression equation to relate demand to time.
29. The total length of time required to manufacture a product and it is also the longest path through a
product structure.
31. A computerized system with relational data base management, client/ server architecture, and
expanded scope to cover enterprise-wide activities.
32. A mathematical relationship that relates a dependent variable to two or more independent variables.
28 | P a g e
Solved Problems in Production Planning & Control 2012
33. It is a function or system that transforms inputs into outputs of greater value.
Answer: a. Operations
34. The time that it takes for a group of jobs to be completed – that is, the completion time of the last job
in a group.
Answer: a. Makespan
35. A class of mathematical techniques that relate demand to factors that cause demand behavior.
36. A stock of items kept by an organization to meet internal or external customer demand.
Answer: b. Inventory
37. The process of subtracting an item’s lead time from its due date to determine when an order should
be released is called --
a. Netting b. Loading
c. Lead Time Offsetting d. Time Fence
38. An oscillating movement in demand that occurs periodically in the short run and is repetitive.
39. The processing of a single order in separate batches at multiple machines simultaneously is called –
29 | P a g e
Solved Problems in Production Planning & Control 2012
40. It is a philosophy based on observation, measurement, and analysis that identifies the best method
for performing each job. Once determined, the methods were standardized for all workers, and
economic incentives were established to encourage workers to follow the standards.
41. Also known as the production lot-size model; an inventory system in which an order is received
gradually and the inventory level is depleted at the same time it is being replenished.
42. A class of statistical methods that uses historical demand data over a period of time to predict future
demand.
43. The process of speeding up orders so that they are completed in less than their normal lead time.
a. Explosion b. Expediting
c. Netting d. Time Fence
Answer: b. Expediting
44. The percent of capacity utilization at which unit costs are lowest.
45. An inventory shortage occurring when demand exceeds the inventory in stock is called –
Answer: d. Stockout
30 | P a g e
Solved Problems in Production Planning & Control 2012
46. A computerized inventory control and production planning system for generating purchase orders and
work orders of materials, components, and assemblies.
47. A shop paper that specifies the sequence in which jobs should be processed; it is often derived from
specific sequencing rules.
48. An aggregate planning strategy that schedules production to match demand and absorbs variations in
demand by adjusting the size of the workforce.
49. The process of assigning priorities to jobs so that they are processed in particular order is called –
a. Scheduling b. Sequencing
c. Loading d. Load Leveling
Answer: b. Sequencing
50. It contains inventory status and descriptive information on every item in inventory.
51. When higher levels of output cost less per unit to produce is called –
31 | P a g e
Solved Problems in Production Planning & Control 2012
52. A scheduling approach that differentiates between bottleneck and non-bottleneck resources and
between transfer batches and process batches.
54. An aggregate planning technique that uses regression analysis to improve the consistency of
production planning decisions.
55. The difference between a job’s due date and its completion time for those jobs completed after their
due date is called –
Answer: b. Tardiness
56. The degree to which a nation can produce goods and services that meet the test of international
markets while simultaneously maintaining or expanding the real incomes of its citizens.
a. Competitiveness b. Globalization
c. Trading d. Commerce
Answer: a. Competitiveness
57. The cost of holding an item in inventory including lost opportunity costs, storage, rent, cooling,
lighting, interest on loans, and so on is called –
32 | P a g e
Solved Problems in Production Planning & Control 2012
58. He proposed the division of labor in which the production process was broken down into a series of
small tasks, each performed by a different worker. The specialization of the worker on limited,
repetitive tasks allowed him or her to become very proficient at those tasks and further encouraged the
development of specialized machinery.
59. An approach to scheduling that initially assumes infinite capacity and then manually “levels the load”
of resources that have exceeded capacity.
61. A moving average with more recent demand values adjusted with weights.
62. A measure of strength of the causal relationship between the independent and dependent variables in
a linear regression equation.
Answer: d. Correlation
63. An algorithm for sequencing any number of jobs through two serial operations to minimize makespan.
33 | P a g e
Solved Problems in Production Planning & Control 2012
64. Final or finished products that are not a function of, or dependent upon, internal production activity.
65. It is the temporary or permanent loss of sales that will result when customer demand cannot be met.
66. A file that contains computerized bills of material for all products.
67. The time between the receipt of orders in an inventory system is called –
68. Movements in demand that are not predictable and follow no pattern.
70. Which of the following is the first phase of the typical phases of product development?
34 | P a g e
Solved Problems in Production Planning & Control 2012
71. Which of the following is the first step in building a house of quality in product development?
72. The per-period average of the absolute difference between actual and forecasted demand is called –
73. A manufacturing environment in which major subassemblies are produced in advance of a customer’s
order and are then configured to order.
Answer: c. Assemble-To-Order
74. An averaging method that weighs the most recent data more strongly than more distant data.
75. The productive capability of a worker, machine, work center, or system is called –
Answer: b. Capacity
76. A date specified by management beyond which no changes in the master schedule are allowed.
35 | P a g e
Solved Problems in Production Planning & Control 2012
78. A method for auditing inventory accuracy that counts inventory and reconciles errors on a cyclical
schedule rather than once a year.
79. A system in which the inventory level is continually monitored; when it decreases to a certain level, a
fixed amount is ordered.
80. The weighting factor given to the most recent data in exponential smoothing forecasts.
81. An aggregate planning strategy that produces units at a constant rate and uses inventory to absorb
variations in demand.
82. The process of determining requirements for lower-level items by multiplying the planned orders of
parent items by the quantity per assembly of component items is called --
a. Explosion b. Expediting
c. Netting d. Time Fence
Answer: a. Explosion
83. Which of the following is an example of a continuous type of process flow structure?
36 | P a g e
Solved Problems in Production Planning & Control 2012
Answer: d. Load
86. An aggregate planning strategy that varies only one capacity factor in determining a feasible
production plan.
87. A schedule for the production of end items or final products. It drives the MRP process that schedules
the production of component parts.
88. A numerical value that is multiplied by the normal forecast to get a seasonal adjusted forecast.
89. A system in which the inventory level is checked after a specific time period and a variable amount is
ordered, depending on the inventory in stock.
37 | P a g e
Solved Problems in Production Planning & Control 2012
90. The process of subtracting on-hand quantities from gross requirements to produce net requirements
is called –
Answer: a. Netting
91. A long term strategic decision that establishes the overall level of productive resources for a firm.
92. An approach to scheduling that loads jobs in priority order and delays to those jobs for which current
capacity is exceeded.
93. Stocks of partially completed items kept between stages of a production process are called –
94. It is also known as a continuous system; an inventory system in which a fixed, predetermined amount
is ordered whenever inventory in stock falls to a certain level called the reorder point.
95. The process of smoothing out the work assigned across time and the available resources.
38 | P a g e
Solved Problems in Production Planning & Control 2012
97. An inventory system in which a variable amount is ordered after a predetermined, constant passage
of time.
98. Scheduling and monitoring day-to-day production in a job shop. It is also known as production control
or production activity control.
99. A mathematical technique that relates a dependent to an independent variable in the form of a linear
equation.
100. A computerized system that projects the load from a given material plan onto the capacity of a
system and identifies under loads and over loads.
39 | P a g e
Solved Problems in Production Planning & Control 2012
1. The Razon Office Supply Company sells and delivers office supplies to companies, schools, and
agencies within 50-kilometer radius of its warehouse. The office supply business is competitive, and
the ability to deliver orders promptly is a factor in getting new customers and keeping old ones. The
manager of the company wants to be certain enough drivers and vehicles are available to deliver
orders promptly and they have adequate inventory in stock. Therefore, the manager wants to be able
to forecast the number of orders that will occur the next month. From the records of delivery orders,
management has accumulated the following data for the past 10 months, from which it wants to
compute 3-month moving average.
Month Orders
January 1200
February 900
March 1000
April 750
May 1100
June 500
July 750
August 1300
September 1100
October 900
a. 900 b. 1100
c. 1300 d. 3300
Answer: b. 1100
Solution:
a. 910 b. 1110
c. 1310 d. 4550
Answer: a. 910
Solution:
64 | P a g e
Solved Problems in Production Planning & Control 2012
3. In reference to problem no. 1, the company wants to compute a 3-month weighted moving average
with a weight of 50 percent for the October data, a weight of 33 percent for the September data, and
a weight of 17 percent for the August data. These weights reflect the company’s desire to have the
most data influence the forecast most strongly.
a. 345 b. 450
c. 1034 d. 1045
Answer: c. 1034
Solution:
4. Marquez Computer Services assembles customized personal computers from generic parts. The
company has had steady growth since it started. The company assembles computers mostly at night,
using part time students. The company purchase generic computer parts in volume at a discount from
a variety of sources whenever they see a good deal. Thus, they need a good forecast of demand for
their computers so that they will know how many computer component parts to purchase and stock.
The company has accumulated the demand data in the table below for its computers for the past
twelve months, from which it wants to consider exponential smoothing forecasts using smoothing
constant equal to 0.30.
a. 50 b. 52
c. 54 d. 56
Answer: b. 52
Solution:
F2 = (0.30)(37) + (0.70)(37)
F2 = 37 units
F3 = (0.30)(40) + (0.70)(37)
F3 = 37.9 units
65 | P a g e
Solved Problems in Production Planning & Control 2012
5. In reference to problem no. 4, compute for the accuracy of its forecast using MAD?
a. 3.58 b. 3.85
c. 4.58 d. 4.85
Answer: d. 4.85
Solution:
53.39
MAD = ------------- = 4.85
11
6. In reference to problem no. 5, what is its Mean Absolute Percent Deviation (MAPD)?
a. 9.1% b. 9.6%
c. 44.1% d. 44.6%
66 | P a g e
Solved Problems in Production Planning & Control 2012
Answer: b. 9.6%
Solution:
53.39
MAPD = -------------- x 100 = 9.6%
557
7. In reference to problem no. 4, the company wants to develop an adjusted exponentially smoothed
forecast using the same twelve months of demand. It will use the exponentially smoothed forecast
with constant = 0.5 and with a smoothing constant for trend of 0.30. What is the forecast in January
next year?
a. 51 b. 53
c. 55 d. 57
Answer: c. 55
Solution:
The adjusted forecast for February, AF2, is the same as the exponentially smoothed forecast, since the
trend computing factor will be zero i.e. F1 and F2 are the same and T2 = 0. Thus, we compute the adjusted
forecast for March, AF3, as follows:
AF3 = F3 + T3
AF3 = 38.5 +0.45
AF3 = 38.95 units
67 | P a g e
Solved Problems in Production Planning & Control 2012
8. In reference to problem no. 4, the demand data for computers appears to follow an increasing linear
trend. The company wants to compute a linear trend line to see if it is more accurate than exponential
smoothing and adjusted exponential smoothing forecast. What is the forecast on period 13?
a. 52 b. 54
c. 56 d. 58
Answer: d. 58
Solution:
x (period) y (demand) xy x2
1 37 37 1
2 40 80 4
3 41 123 9
4 37 148 16
5 45 225 25
6 50 300 36
7 43 301 49
8 47 376 64
9 56 504 81
10 52 520 100
11 55 605 121
12 54 648 144
78
x = --------------- = 6.5
12
557
y = --------------- = 46.42
12
3867 – [(12)(6.5)(46.42)]
b= -----------------------------------------------
650 – [12(6.5)2]
b = 1.72
a = 46.42 – (1.72)(6.5)
a = 35.2
y = 35.2 + 1.72x
y = 35.2 + 1.72(13) = 57.56 = 58 units for period 13
68 | P a g e
Solved Problems in Production Planning & Control 2012
9. Delima Farms grows chickens to sell to a meat processing company throughout the year. However, its
peak season is obviously during the fourth quarter of the year, from October to December. Delima
Farms has experienced the demand for chickens for the past three years shown in the following table:
Solution:
42.0
S1 = ---------------- = 0.28
148.7
29.5
S2 = ---------------- = 0.20
148.7
21.9
S3 = ---------------- = 0.15
148.7
55.3
S4 = ---------------- = 0.37
148.7
y = 40.97 + 4.30x
y = 40.97 + 4.30(4)
y = 58.17
69 | P a g e
Solved Problems in Production Planning & Control 2012
10. The Tomas University athletic department wants to develop its budget for the coming year using a
forecast for football attendance. Football attendance accounts for the largest portion of its revenues,
and the athletic director believes attendance is directly related to the number of wins by the team. The
business manger has accumulated total annual attendance for the past eight years.
Given the number of returning starters and the strength of the schedule, the athletic director believes the
team will win at least seven games next year. Develop a simple regression equation for this data to
forecast attendance next year.
a. 45,880 b. 46,880
c. 47,850 d. 48,850
Answer: b. 46,880
Solution:
x y
No. of Wins Attendance xy x2
(1,000s)
4 36.3 145.2 16
6 40.1 240.6 36
6 41.2 247.2 36
8 53.0 424.0 64
6 44.0 264.0 36
7 45.6 319.2 49
5 39.0 195.0 25
7 47.5 332.5 49
49
x = --------------- = 6.125
8
346.9
y = --------------- = 43.36
8
(2,167.7) – [(8)(6.125)(43.36)]
b= -----------------------------------------------------
(311) – [(8)(6.125)2]
b = 4.06
a = 43.36 – (4.06)(6.125)
70 | P a g e
Solved Problems in Production Planning & Control 2012
a = 18.46
y = 18.46 + 4.06x
y = 18.46 + 4.06(7) = 46.88 = 46,880 attendance for 7 wins
11. In reference to problem no. 10, compute the correlation for the linear regression equation.
a. 0.647 b. 0.747
c. 0.847 d. 0.947
Answer: d. 0.947
Solution:
[(8)(2,167.7)] – [(49)(346.9)]
r = ------------------------------------------------------------------------ = 0.947
12. A manufacturing company has monthly demand for one its products as follows:
Month Demand
February 520
March 490
April 550
May 580
June 600
July 420
August 510
September 610
a. 45,880 b. 46,880
c. 47,850 d. 48,850
Answer: b. 46,880
Solution:
MA3 = 1100
71 | P a g e
Solved Problems in Production Planning & Control 2012
13. The Zaki Motorcycle Dealer in Kamuning area wants to be able to forecast accurately the demand for
the Zaki Super VIII motorcycle during the next month. Because the manufacturer is in Japan, it is
difficult to send motorcycles back or reorder if the proper number is not ordered a month ahead. From
sales records, the dealer has accumulated the following data for the past year.
Compute a 3-month moving average forecast of demand for April through January (of the next
year) and a 5-month moving average forecast for June through January. Compare the two
forecasts computed in parts using MAD. Which one should the dealer use for January of the next
year?
a. 3-month moving ave with MAD = 1.89 b. 3-month moving ave with MAD = 2.89
c. 5-month moving ave with MAD = 2.43 d. 5-month moving ave with MAD = 1.43
Solution:
The dealer should use the Three-month Moving Average w/a MAD of 1.89. The smaller the MAD,
the more accurate the forecast is.
72 | P a g e
Solved Problems in Production Planning & Control 2012
14. The manager of the Secreto Carpet outlet needs to be able to forecast accurately the demand for soft
carpet, its biggest seller. If the manager does not order enough carpet from the carpet mill, customers
will buy their carpets from one of Secreto’s many competitors. The manager has collected the
following demand data for the past eight months.
Compute a 3-month moving average forecast for months 4 through 9 and a weighted 3-month moving
average forecast for months 4 through 9. Assign weights 0.55, 0.33, and 0.12 to the months in sequence
starting with the most recent month. Compare the two forecasts using MAD. Which forecast appears to be
more accurate?
Solution:
MA3 = Di/3
= (8+12+7)/3
=9
WMA3 = W iDi
= 7(0.55) + 12(.33) + 8(0.12)
= 8.77
73 | P a g e
Solved Problems in Production Planning & Control 2012
Tabular Representation:
Because MAD and the cumulative error are less for the weighted 3-month moving average
forecast, it would appear to be the most accurate.
15. The Glorioso Fertilizer Company distributes fertilizer to various lawn and garden shops. The company
must base its quarterly production schedule on a forecast of how many tons of fertilizer will be
demanded from it. The company has gathered the following data for the past three years from its
sales records.
Compute a 3-quarter moving average forecast for quarters 4 through 13 and compute the forecast error
for each quarter and a weighted 3-quarter moving average forecast using weights of 0.50, 0.33, and 0.17
for the most recent, next recent, and most distant data, respectively, and compute the forecast error for
each quarter. Compare the forecasts developed using cumulative error. Which forecasts appears to be
more accurate?
74 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
Comparison using Cumulative Error: 3-Quarter Moving Average with E = 32.00 and Weighted 3-Quarter
Moving Average with E = 28.05
Weighted 3-Quarter Moving Average is more accurate than the moving average because it has lower
error.
75 | P a g e
Solved Problems in Production Planning & Control 2012
16. Determine the seasonally adjusted forecast for the demand data for fertilizer in Problem No. 15 with
the use a linear trend line model to compute a forecast estimate for demand in year 4.
Solution:
S1 = Di / ∑D
y = 1850 + 180(4)
y = 622.35
Using the annual forecast of demand, the seasonally adjusted forecast for year 4 is:
76 | P a g e
Solved Problems in Production Planning & Control 2012
17. The chairperson of the department of management at Razon University wants to forecast the number
of students who will enroll in production and operations management next semester in order to
determine how many sections to schedule. The chair has accumulated the following enrollment data
for the past eight semesters:
Compute a 3-semester moving average forecast for semesters 4 through 9 and the exponentially
smoothed forecast (α= 0.20) for the enrollment data. Compare the two forecasts using MAD and
choose the most accurate.
Solution:
The 3-Semester Moving Average is more accurate because it has lower value of MAD.
18. The Dy Café in Espana, Manila, is well known for its popular homemade ice cream, which it makes in
a small plant in back of the café. People drive all the way from Alabang and Mandaluyong to buy the
ice cream. The two ladies who own the café want to develop a forecasting model so they can plan
their ice cream production operation and determine the number of employees they need to sell ice
cream in the café. They have accumulated the following sales records for their ice cream for the past
twelve quarters.
77 | P a g e
Solved Problems in Production Planning & Control 2012
Determine the seasonally adjusted forecast for 1998 with the use of a linear trend line model.
Solution:
S1 = Di / ∑D
Using the annual forecast of demand, the seasonally adjusted forecast for 1998 is:
78 | P a g e
Solved Problems in Production Planning & Control 2012
19. The purchasing manager for the Ormilon Steel Company must determine a policy for ordering coal to
operate 12 converters. Each converter requires exactly 5 tons of coal per day to operate, and the
firm operates 360 days per year. The purchasing manager has determined that the ordering cost is
P80 per order, and the cost of holding coal is 20 percent of the average peso value of inventory held.
The purchasing manager has negotiated a contract to obtain the coal for P1200 per ton for the
coming year. Determine the optimal quantity of coal to receive in each other.
a. 100 b. 110
c. 120 d. 130
Answer: c. 120
Given:
Co = P80/ order
Cc = 20% of the ave. peso value of inventory held
P = P1200/ton
Solution:
20. In reference to problem no. 19, determine the total inventory related costs associated with the optimal
ordering policy with cost of coal not included.
a. 29,100 b. 31,600
c. 30,200 d. 28,800
Answer: d. 28,800
Solution:
Tc = CoD + Cc Qopt
Qopt 2
= P 28,800
79 | P a g e
Solved Problems in Production Planning & Control 2012
21. In reference to problem no. 19 and if 5 days’ lead-time is required to receive an order of coal, how
much coal should be on hand when an order is placed?
a. 300 b. 350
c. 400 d. 450
Answer: a. 300
Solution:
22. The Capulong Lumber Company and Mill processes 10,000 logs annually, operating 250 days per
year. Immediately upon receiving an order, the logging company’s supplier begins delivery to the
lumber mill at the rate of 60 logs per day. The lumber mill has determined that the ordering cost
is$1,600 per order, and the cost of carrying logs in inventory before they are processed is $15 per log
on an annual basis. Determine the optimal order size.
a. 3,540 b. 2,530
c. 4,250 d. 5,500
Answer: b. 2,530
Given:
D = 10,000 250 days/yr p = 60 logs/day
Co = $1600/order d = 10,000_
Cc = $15/log annually 250 days
= 40 logs / day
Solution:
23. In reference to problem no. 22, determine the total inventory cost associated with the optimal order
quantity.
a. 12,759 b. 11,531
c. 11,621 d. 12,649
Answer: d. 12,649
Solution:
80 | P a g e
Solved Problems in Production Planning & Control 2012
Tc =$12,649.11 = $12,649
24. In reference to problem no. 22, determine the number of operating days between orders.
a. 59 b. 61
c. 63 d. 65
Answer: c. 63
Solution:
25. In reference to problem no. 22, determine the number of operating days required to receive an order.
a. 42 b. 44
c. 46 d. 48
Answer: a. 42
Solution:
Production run = Q
p
= 2,529.8
60
26. The Sanga Tire Company produces a brand of tire called the Roadrunner. The annual demand at its
distribution center is 17,400 tires per year. The transport and handling cost are $2,600 each time a
shipment of tires is ordered at the distribution center. The annual carrying cost is $3.75 per tire.
Determine the optimal order quantity and the minimum total annual cost.
Given:
D = 17,400/yr Co = $ 3.75
Co = $ 2,600
Solution:
Qopt = 2CoD
Cc
81 | P a g e
Solved Problems in Production Planning & Control 2012
= 2 (2,600) (17,400)
3.75
Tc = CoD + Qopt Cc
Qopt 2
= $18,420.098 = 18,420
27. In reference to problem no. 26, the company is thinking about relocating its distribution center, which
would reduce transport and handling costs to $1,900 per order but increase carrying costs to $4.50
per tire per year. Determine the savings if the relocation pushes through.
a. $1,255 b. $1,850
c. $1,171 d. $1,625
Answer: c. $1,171
Solution:
Co = $1,900; Cc = $ 4.5
Qopt = 2CoD
Cc
= 2 (1,900) (17,400)
4.5
Qopt = 3,833.19
Tc = CoD + Qopt Cc
Qopt 2
= $17,249
☺ The Company should relocate with the savings of $18,420 - $17,249 = $1,171
82 | P a g e
Solved Problems in Production Planning & Control 2012
28. The Ngo Farms produces its own natural organic fertilizer, which it sells mostly to the gardeners and
homeowners. The annual demand for fertilizer is 270,000 pounds. The company is able to produce
305,000 pounds annually. The cost to transport the fertilizer from the plan to the nursery is $620 per
load. The annual carrying load cost is $0.12 per pound. Compute the optimal order size.
a. 135,871 b. 143,753
c. 155,926 d. 163,125
Answer: c. 155,926
Given:
D = 270,000/yr p = 305,000/yr
Co = $620 Cc = $0.12
Solution:
29. In reference to Problem No. 28, compute the total minimum cost.
a. $2,253 b. $2,147
c. $2,534 d. $2,622
Answer: b. $2,147
Solution:
Tc = $2,147.18 = $2,147
30. In reference to Problem No. 28, compute the maximum inventory level.
a. 17,893 b. 18,953
c. 19,261 d. 20,530
Answer: a. 17,893
Solution:
Max. Inv. Level = Q 1 - d
P
= 155,925.8 1 - 270,000
305,000
= 17,893.12 = 17,893
83 | P a g e
Solved Problems in Production Planning & Control 2012
31. If Ngo Farms in Problem No. 28 can increase production capacity to 360,000 pounds per year, what
will be the total inventory cost?
a. $1,934 b. $2,747
c. $3,169 d. $4,282
Answer: b. $3,169
Solution:
Tc = $3,169.23 = $3,169
32. The Baldrige Kiln is an importer of ceramics from overseas. It has arranged to purchase a particular
type of ceramic pottery from a Chinese artisan. The artisan makes the pottery in 120-unit batches
and will ship only that exact amount. The transportation and the handling cost of a shipment is
$7,600 (not including the unit cost). The Baldrige Kiln estimates its annual demand to be 900 units.
What storage and handling cost per unit does it need to achieve in order to minimize its inventory
cost?
a. $6,120 b. $5,380
c. $4,760 d. $3,450
Answer: d. $3,450
Given:
Qopt = 120 Co = 7600
D = 900 Cc = ?
Solution:
Qopt = 2CoD
Cc
2
(120)2 = 2(7,600)(900)
Cc
14,400 = 49,680,000
Cc
Cc = 49,680,000
14,400
Cc = $3,450 / unit is needed to achieve in order to minimize its inventory cost.
84 | P a g e
Solved Problems in Production Planning & Control 2012
33. The Ligan Carpet Discount Store has annual demand of 10,000 yards of Super Shag carpet. The
annual carrying cost for a yard of this carpet is $0.75 and the ordering cost is $150. The carpet
manufacturer normally charges the store $8 per yard for the carpet. However, the manufacturer has
offered a discount price of $6.50 per yard if the store will order 5,000 yards. How much should the
store order and the total annual inventory cost for that order quantity?
Given:
Solution:
Tc = CoD + Cc Qopt + PD
Qopt 2
= $81,500
☺The store should order 5,000 to avail discount and only have a total cost of $67,175
34. The Sta. Maria Bar buys draft beer by the barrel from a local distributor. The bar has an annual
demand of 900 barrels, which it purchases at a price of $205 per barrel. The annual carrying cost is
$24.60, and the cost per order is $160. The distributor has offered the bar a reduced price of $190
per barrel if it will order a minimum of 300 barrels. What is the cost difference if the bar takes the
discount?
a. $14,128 b. $13,374
c. $12,873 d. $11,992
Answer: d. $11,992
Given:
D = 900 P = $205/barrel
Cc = 424.60 Co = $160
Discounted price of $ 190/barrel with min order of 300
85 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
At regular price: At discounted price:
= 108.2 ≈ 108
= $187,161.73
☺The bar should take the discount with a difference of $ 11,992 to the regular price
35. The bookstore at Aviba University purchases sweatshirts emblazoned with the school name and logo
from the vendor. The vendor sells the sweatshirt to the store for $38 apiece. The cost to the
bookstore for placing an order is $120, and the annual carrying cost is 25 percent of the cost of a
sweatshirt will be sold during the year. The vendor has offered the bookstore the following volume
discount schedule:
The bookstore manager wants to determine the bookstore’s optimal order quantity given this quantity
discount information.
Given:
P = $38 D = 1,700
Co = 120 Cc = 25% price of the sweatshirt
Solution:
86 | P a g e
Solved Problems in Production Planning & Control 2012
☺The bookstore manager should choose the 500-799 brackets having the lowest total cost.
36. Determine the optimal order quantity of sweatshirt and total annual cost in Problem No. 49 if the
carrying cost is a constant $8 per shift per year.
Given:
P = $38 D = 1700
Co = $120 Cc = $ 8
Solution:
At (0%)
Qopt = 2 (120) (1,700) Tc = 120 (1,700) + 8 (226) + 38 (1,700)
8 226 2
At (2%)
Qopt = 300 Tc = 120 (1,700) + 8 (300) + 37.24 (1,700)
P = [38-(38*.02)] 300 2
= 37.24 = $65,188
At ( 4%)
Qopt = 500
P = [38-(38*.04)] Tc = 120 (1,700) + 8 (500) + 36.48 (1,700)
= 36.48 500 2
= $64,424
At (5%)
Qop = 800 Tc = 120 (1,700) + 8 (800) + 36.1 (1,700)
P = [38-(38*.05)] 800 2
=36.1 = $64,825
☺ 500 - 799 is the optimal order quantity with the total annual cost of $64,424
87 | P a g e
Solved Problems in Production Planning & Control 2012
37. The office manager for the Breganza Life Insurance Company orders letterhead stationery from an
office products firm in boxes of 500 sheets. The company uses 6,500 boxes per year. Annual
carrying cost are $3 per box, and ordering costs are $28. The following supply company provides the
following discount price:
Determine the optimal order quantity at the least total annual inventory cost.
Answer: d. 6,000+
Given:
D = 6,000 Co = $28
Cc = $ 3/box
Solution:
At P = 16
Tc = 28 (6500) + 3 (348.33) + 16 (6,500)
348.33 2
Tc = $105,044.988
At P = 14
Tc = 28 (6,500) + 3 (1,000) + 14 (6,500)
1,000 2
Tc = $92,682
At P = 13
Tc = 28 (6,500) + 3 (3,000) + 13 (6,500)
3,000 2
Tc = $89,060.66
At P = 12
Tc = 28 (6,500) + 3 (6,000) + 12 (6,500)
6,000 2
Tc = $87,030.33
☺ The manager should order 6,000 with the lowest total annual inventory cost $ 87,030.33
88 | P a g e
Solved Problems in Production Planning & Control 2012
38. Determine the optimal quantity and total annual inventory cost for boxes of stationery in Problem No.
37 if the carrying cost is 20 percent of the price of a box of stationery.
Answer: d. 6,000+
Given:
D = 6,500 Cc = 20% of the price
Co = $28
Solution:
At P = 16
Qopt = 2 (28) (6,500) Tc = 28 (6,500) + 3.2 ( 337) + 16 (6,500)
3.2 337 2
At P =14
Qopt = 1,000 Tc = 28 (6,500) + 2.8 (1,000) + 14 (6,500)
Cc = (.20*14) 1,000 2
= 2.8 = $92,563.5
At P = 13
Qopt = 3,000 Tc = 28 (6,500) + 2.6 (3,000) + 13 (6,500)
Cc = (.20*13) 3,000 2
= 2.6 = $88,454.17
At P = 12
Qopt = 6,000 Tc = 28 (6,500) + 2.4 (6,000) + 12 (6,500)
Cc = (.20*12) 6,000 2
Cc = 2.4 = $85,227.08
☺ The optimal order quantity is 6,000 with the lowest total annual inventory of $ 85,227.08
39. Padilla Electronics stocks and sells a particular brand of microcomputer. It costs the firm $450 each
time it places an order with the manufacturer for the microcomputers. The cost of carrying one
microcomputer in inventory for a year is $170. The store manager estimates that total annual demand
for the computers will be 1,200 units, with a constant demand rate throughout the year. Orders are
received within the minutes after placement from a local warehouse maintained by the manufacturer.
The store policy is never to have stock outs of the microcomputers. The store is open for business
everyday of the rear except Christmas day. Determine the optimal order quantity per order.
a. 75 b. 80
c. 85 d. 90
Answer: b. 80
Given: Co = $450
Cc = $170
D = 1,200 units
89 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
Qopt = 2 Co D
Cc
= 2(450)(1200)
170
= 79.71 = 80 units
40. In reference to Problem No. 39, determine the minimum total annual inventory cost.
a. $14,150 b. $13,550
c. $12,350 d. $11,950
Answer: b. $13,550
Solution:
TC = Co D + Cc Q
Q 2
= (450)(1200) + (170)(79.71)
79.71 2
= $13,549.91 = $13,550
41. In reference to Problem No. 39, determine the number of orders per year.
a. 15 b. 20
c. 25 d. 30
Answer: a. 15
Solution:
D = Number of orders per year
Qopt
42. In reference to Problem No. 39, determine the time between orders in working days.
a. 20 b. 17
c. 14 d. 11
Answer: c. 14
90 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
43. A firm is faced with the attractive situation in which it can obtain immediate delivery of an item it stocks
for retail sale. The firm has therefore not bothered to order the item in any systematic way. However,
recently profits have been squeezed due to increasing competitive pressures, and the firm has
retained a management consultant to study its inventory management. The consultant has
determined that the various cost associated with making an order for the item stocked are
approximately $30 per order. She has also determined that the costs of carrying the item in inventory
amount to approximately $20 per unit per year (primarily storage costs and forgone profit on
investment in inventory). Demand for the item is reasonably constant over time, and the forecast is for
19,200 units per year. When an order is placed for the item, the supplier immediately delivers the
entire order to the firm. The firm operates 6 days a week plus a few Sundays, or approximately 320
days per year. Determine the optimal order per year.
a. 240 b. 270
c. 250 d. 260
Answer: a. 240
Given: Co = $30
Cc = $20
D = 19,000 units
320 days per year
Solution:
Qopt = 2 Co D
Cc
= 2(30)(19,200)
20
= 240 units
44. In reference to Problem No. 43, determine the total annual inventory cost.
a. $2,900 b. $3,700
c. $4,800 d. $5,200
Answer: c. $4,800
Solution:
TC = Co D + Cc Q
Q 2
= (80)(19,200) + (20)(240)
240 2
= $4,800
91 | P a g e
Solved Problems in Production Planning & Control 2012
45. In reference to Problem No. 43, determine the optimal number of orders to place per year.
a. 50 b. 60
c. 70 d. 80
Answer: d. 80
Solution:
46. In reference to Problem No. 43, determine the number of operating days between orders, based on
the optimal ordering.
a. 3 b. 4
c. 5 d. 6
Answer: b. 4
Solution:
320 = 4 days
80
47. The Gonzales Jeans Company purchases denim from Hipolito Textile Mills. The Gonzales uses
35,000 yards of denim per year to make jeans. The cost of ordering denim from the textile company is
$500 per order. It costs Western $0.35 per yard annually to hold a yard from denim in inventory.
Determine the optimal number of yards of denim the company should order.
a. 10,000 b. 12,000
c. 14,000 d. 16,000
Answer: a. 10,000
Given: Co = $500
Cc = $0.35
D = 35,000 yards
Solution:
Qopt = 2 Co D
Cc
= 2(500)(35,000)
0.35
= 10,000 yards
92 | P a g e
Solved Problems in Production Planning & Control 2012
48. In reference to Problem No. 47, determine the minimum total inventory cost.
a. $2,500 b. $3,500
c. $4,500 d. $5,500
Answer: b. $3,500
TC = Co D + Cc Q
Q 2
= (500)(35,000) + (0.35)(10,000)
10,000 2
= $3,500
49. In reference to Problem No. 47, determine the optimal number of orders per year and the optimal time
between orders.
Solution:
50. The Osila Book Company purchases paper from the Biscocho Paper Company. Osila produces
magazines and paperbacks that require 1,215,000 yards of paper per year. The cost per order for the
company is $1,200 while the cost of holding 1 yard of paper in inventory is $0.08 per year. Determine
the Economic Order Quantity.
a. 180,714 b. 185,917
c. 190,919 d. 200,302
Answer: c. 190,919
Given: Co = $1,200
Cc = $0.08
D = 1,215,000 units
320 days per year
93 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
Qopt = 2 Co D
Cc
= 2(1,200)(1,215,000)
0.08
51. In reference to Problem No. 50, determine the minimum total annual cost.
a. $12,972 b. $13,587
c. $14,741 d. $15,274
Answer: d. $15,274
Solution:
TC = Co D + Cc Q
Q 2
= (1,200)(1,215,000) + (0.08)(190,918.83)
190,918.83 2
= $15,273.51 = $15,274
52. In reference to Problem No. 50, determine the optimal number of orders per year and time between
orders.
Solution:
94 | P a g e
Solved Problems in Production Planning & Control 2012
53. The Ligon Bakery produces fruit pies for freezing and subsequent sale. The bakery, which operates 5
days a week, 52 weeks a year, can produce pies at the rate of 64 pies per day. The bakery sets up
the pie-production operation and produces until a predetermined number (Q) have been produced.
When not producing pies, the bakery uses its personnel and facilities for producing other bakery
items. The setup cost for a production run of fruit pies is $500. The cost of holding frozen pies in
storage is $5 per pie per year. The annual demand for frozen fruit pies, which is constant over time, is
5,000 pies. Determine the optimum production quantity (Q).
a. 1,196 b. 1,352
c. 2,239 d. 2,474
Answer: a. 1,196
Given: Co = $500
Cc = $5
D = 5,000 pies
d = (5,000 260) = 19.23 pies per day
P = 64 pies per day
Solution:
a.) Qopt = 2 Co D .
Cc 1 - d
p
= 2(500)(5,000)
5 1-19.23
64
= 1,195.63 = 1,196
54. In reference to Problem No. 53, determine the total annual inventory cost.
a. $3,071 b. $4,182
c. $5,243 d. $5,284
Answer: b. $4,182
Solution:
TC = Co D + Cc Q 1 - d
Q 2 p
= $4,181.90 = $4,182
95 | P a g e
Solved Problems in Production Planning & Control 2012
55. In reference to Problem No. 53, determine the optimum number of production runs per year.
a. 2 b. 4
c. 6 d. 8
Answer: b. 4
Solution:
56. In reference to Problem No. 53, determine the optimum cycle time (time between run starts)
a. 39 b. 48
c. 65 d. 74
Answer: d. 74
Solution:
57. In reference to Problem No. 53, determine the run length in working days.
a. 19 b. 21
c. 23 d. 25
Answer: a. 19
Solution:
58. The Quitain Bicycle Shop operates 364 days a year, closing only on Christmas Day. The shop pays
$300 for a particular bicycle purchased from the manufacturer. The annual holding cost per bicycle is
estimated to be 25 percent of the dollar value of inventory. The shop sells an average of 25 bikes per
week. The ordering cost for each order is $100. Determine the optimal order quantity and the total
minimum cost.
a. 48 at $5,623 b. 53 at $4,972
c. 59 at $4,416 d. 62 at $5,183
Answer: c. 59 at $4,416
96 | P a g e
Solved Problems in Production Planning & Control 2012
Given: Co = $100
Cc = 300 x 0.25 =75
D = 1,300
Solution:
Qopt = 2 Co D
Cc
= 2(100)(1300)
75
= 58.8 = 59
TC = Co D + Cc Q
Q 2
= (100)(1300) + (75)(58.8)
58.8 2
= $4,415.88 = $4,416
59. The Lanuza Petroleum Company uses a highly toxic chemical in one of its manufacturing processes.
It must have the product delivered by special cargo trucks designed for safe shipment of chemicals.
As such, ordering (and delivery) costs are relatively high, at $2,600 per order. The chemical product
is packaged in 1-gallon plastic containers. The cost of holding the chemical in storage is $50 per
gallon per year. The annual demand for the chemical, which is constant overtime, is 2,000 gallons per
year. The lead-time from time of order placement until receipt is 10 days. The company operates 310
working days per year. Compute the optimal order quantity and the total minimum cost.
Given: Co = $2,600
Cc = $ 50
D = 2,000
L = 10 days
310 days per year
Solution:
Qopt = 2 Co D
Cc
= 2(2,600)(2,000)
50
= 456.07 = 456
97 | P a g e
Solved Problems in Production Planning & Control 2012
TC = Co D + Cc Q
Q 2
= (2,600)(2,000) + (50)(456.07)
456.07 2
= $22,803.51 = $22,804
a. 35 b. 47
c. 52 d. 64
Answer: d. 64
Solution:
R = dL
61. The Sandico Supermarket stocks Munchies Cereal. Demand for munchies is 4,000 boxes per year
(365 days). It costs the store $60 per order of munchies, and it costs $0.80 per box per year to keep
the cereal in stock. Once an order for munchies is placed, it takes 4 days to receive the order from a
food distributor. Determine the optimal order size and the minimum total annual inventory cost.
a. 57 at $805 b. 62 at $780
c. 75 at $620 d. 84 at $560
Answer: c. 75 at $620
Given: Co = $60
Cc = $0.80
D = 4,000
L = 4 days
Solutions:
Qopt = 2 Co D
Cc
= 2(60)(4,000)
0.80
= 774.60 = 775
TC = Co D + Cc Q
Q 2
= (60)(4,000) + (0.80)(774.60)
774.60 2
= $619.68 = $620
98 | P a g e
Solved Problems in Production Planning & Control 2012
a. 38 b. 44
c. 56 d. 62
Answer: b. 44
Solution:
R = d(L)
63. The Tenorio Dairy makes cheese to supply to stores in its area. The dairy can make 250 pounds of
cheese per day, and the demand at area stores is 180 pounds per day. Each time the dairy makes
cheese, it costs $125 to set up the production process. The annual cost of carrying a pound of
cheese in a refrigerated storage area is $12. Determine the optimal size and the total annual
inventory cost.
Given: Co = $125
Cc = $12
D = 65,700 units
d = 180 lbs/day
p = 250 lbs/day
Solution:
Qopt = 2 Co D .
Cc 1 - d
p
= 2(125)(65,700)
12 1-180
250
= 2,210.97 = 2,211
TC = Co D + Cc Q 1 - d
Q 2 p
= $7,428.86 = $7,429
99 | P a g e
Solved Problems in Production Planning & Control 2012
64. The Rebueno Water Ski Company is the world’s largest producer of water skis. As you might suspect,
water skis exhibit a highly seasonal demand pattern, with peaks during the summer months and
valleys during the winter months. Given the following costs and quarterly sales forecasts, use the
transportation method to design a production plan that will economically meet demand. What is the
cost of the plan?
a. $20,520,000 b. $25,850,000
c. $28,430,000 d. $30,290,000
Answer: d. $30,290,000
Solution:
PERIOD OF USE
PERIOD OF unused
1 2 3 4 capacity
PRODUCTION capacity
0 3 6 9
beginning inventory - - - - - -
50 53 56 59
regular 50,000 - - - 0 50,000
75 78 8 84
1 overtime - 50,000 - - 0 50,000
85 88 1
91 94
subcontract - - 20,000 - 20,000 40,000
50 53 56
regular 50,000 - - 0 50,000
75 78 81
2 overtime 50,000 - - 0 50,000
85 88 91
subcontract - 40,000 - 0 40,000
50 53
regular 50,000 - 0 50,000
75 78
3 overtime 50,000 - 0 50,000
85 88
subcontract 40,000 - 0 40,000
50
regular 50,000 0 50,000
75
4 overtime 2,000 48,000 50,000
85
subcontract - 40,000 40,000
DEMAND 50,000 150,000 200,000 52,000
100 | P a g e
Solved Problems in Production Planning & Control 2012
PRODUCTION PLAN
ENDING
PERIOD DEMAND REGULAR OVERTIME SUBCONTRACT
INVENTORY
1 50,000 50,000 50,000 20,000 70,000
2 150,000 50,000 50,000 40,000 60,000
3 200,000 50,000 50,000 40,000 0
4 52,000 50,000 2,000 0 0
TOTAL 452,000 200,000 152,000 100,000 130,000
Total cost = 200,000 ($ 50) + 152,000 ($ 75) + 100,000 ($ 85) + 130,000 ($ 3) = $30,290,000
65. The CEO of Rebueno Water Ski from Problem No. 64 has decided to forgo the company’s policy of
guaranteed employment. Assume the cost of hiring and firing workers is $100 per worker hired and
$400 per worker fired. Try level production strategy. If necessary, allow backordering at $10 per pair
of skis per quarter. What is the cost of the plan?
a. $21,421,000 b. $23,483,300
c. $26,716,000 d. $28,835,000
Answer: b. $23,483,300
Solution:
SALES
QUARTER REGULAR BACKORDER INVENTORY WORKERS HIRED FIRED
FORECAST
1 50,000 113,000 0 63,000 113 63 0
2 150,000 113,000 0 26,000 113 0 0
3 200,000 113,000 61,000 0 113 0 0
4 52,000 113,000 0 0 113 0 0
TOTAL 452,000 452,000 61,000 89,000 63 0
Total Cost = 452,000 ($50) + 61,000 ($10) + 89,000 ($3) + 63 ($100) = $ 23,483,300
66. In reference to Problem No. 65, use the chase demand production strategy and determine the cost of
plan.
a. $20,928,000 b. $22,674,200
c. $24,542,000 d. $26,356,000
Answer: b. $22,674,200
101 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
Chase Demand
SALES
QUARTER REGULAR WORKERS HIRED FIRED
FORECAST
1 50,000 50,000 50 0 0
2 150,000 150,000 150 100 0
3 200,000 200,000 200 50 0
4 52,000 52,000 52 0 148
TOTAL 452,000 452,000 150 148
67. Hong Apparel, manufacturer of a famous swimwear line, needs help planning production for the next
year. Demand for swimwear follows a seasonal pattern, as shown here. Given the following costs and
demand forecasts, use as a strategy the level production with overtime and subcontracting and
determine the cost of the plan.
a. $725,000 b. $613,000
c. $529,000 d. $448,000
Answer: d. $448,000
102 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
68. In reference Problem No. 67, use as a strategy the level production with backorders as needed and
determine the cost of this plan.
a. $403,250 b. $524,620
c. $611,460 d. $718,500
Answer: a. $403,250
103 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
69. In reference to Problem No. 67, use as a strategy the chase demand and determine the cost of plan.
a. $532,700 b. $424,200
c. $367,600 d. $288,300
Answer: c. $367,600
104 | P a g e
Solved Problems in Production Planning & Control 2012
70. Candelaria Press publishes textbooks for the college market. The demand for college textbooks is
high during the beginning of each semester and then tapers off during the semester. The
unavailability of books can cause a professor to switch adoptions, but the cost of storing books and
their rapid obsolescence must also be considered. Given the demand and cost factors shown here,
use the transportation method to design an aggregate production plan for Candelaria Press that will
economically meet demand. What is the cost of the production plan?
a. $1,650,000 b. $1,800,000
c. $1,750,000 d. $1,900,000
Answer: c. $1,800,000
Solution:
105 | P a g e
Solved Problems in Production Planning & Control 2012
PRODUCTION PLAN
ENDING
MONTHS DEMAND REGUALR OVERTIME SUBCONTRACT
INVENTORY
February-
5,000 10,000 5,000 0 10,000
April
May-July 10,000 10,000 5,000 0 15,000
August-
30,000 10,000 5,000 0 0
October
November-
25,000 10,000 5,000 10,000 0
January
TOTAL 70,000 40,000 20,000 10,000 25,000
Total cost = 40,000 ($ 20) + 20,000 ($ 30) + 10,000 ($ 35) + 25,000 ($ 2) = $ 1,800,000
71. Bautista’s Empanada is a popular food item during the cold months, but it is marginal in other months.
Use the following demand forecasts to determine the cost of plan if production planning strategy on
level production over the twelve months is used.
No backordering
Overtime capacity per month regular production
Subcontracting capacity per month unlimited
Regular production cost $ 30 per pallet
Overtime production cost $ 40 per pallet
Subcontracting production cost $ 50 per pallet
Holding cost $ 2 per pallet
No beginning inventory
Beginning workforce 10 workers
Production rate 200 pallet per worker per month
Hiring cost $ 5,000 per worker
Firing cost $ 8,000 per worker
a. $1,197,000 b. $1,232,000
c. $1,341,000 d. $1,475,000
Answer: b. $1,232,000
106 | P a g e
Solved Problems in Production Planning & Control 2012
72. In reference to Problem No. 71, use a strategy to produce and meet the demand each month and
absorb variations in demand by changing the size of the workforce to determine the cost of plan.
a. $1,560,000 b. $1,602,000
c. $1,722,000 d. $1,850,000
Answer: a. $1,560,000
Solution: Produce to meet demand each month. Absorb variations in demand by changing the size of the
workforce.
107 | P a g e
Solved Problems in Production Planning & Control 2012
73. In reference to Problem No. 71, use a strategy to keep the workforce at its current level and
supplement with overtime and subcontracting as necessary to determine the cost of plan.
a. $1,571,000 b. $1,453,000
c. $1,391,000 d. $1,293,000
Answer: d. $1,293,000
Solution: Keep the workforce at its current level. Supplement with overtime and subcontracting as
necessary.
Total cost = 24,000($ 30) + 7,000 ($ 40) + 5,000 ($ 50) + 21,500 ($ 2) = $1,293,000
74. The Palanca Company produces two products, A and B, that are made from components C and D.
Given the following product structures, master scheduling requirements, and inventory information,
determine when order should be released for product A and the size of the order.
A B
LT = 3 LT = 2 Level 0
108 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
Item: A Period
LCC: 0
Lot Size: 1 PD 1 2 3 4 5 6 7 8
LT:3
Gross 100
Requirements
Scheduled
Receipts
Projected On 10 10 10 10 10 10 10 10 0
Hand
Net 90
Requirements
Planned 90
Order
Receipts
Planned 90
Order
Releases
75. In reference to Problem No. 74, determine when order should be released for product B and the size
of the order.
Solution:
Item: B Period
LCC: 0
Lot Size: 1 PD 1 2 3 4 5 6 7 8
LT:2
Gross 200
Requirements
Scheduled
Receipts
Projected On 5 5 5 5 5 5 0
Hand
Net 195
Requirements
Planned 195
Order
Receipts
Planned 195
Order
Releases
109 | P a g e
Solved Problems in Production Planning & Control 2012
76. In reference to Problem No. 74, determine when order should be released for product C and the size
of the order.
Solution:
Item: C Period
LCC: 1
Lot Size: 150 PD 1 2 3 4 5 6 7 8
LT:4
Gross 270
Requirements (90 x 3)
Scheduled
Receipts
Projected On 140 140 140 140 140 20 20 20 20
Hand
Net 130
Requirements
Planned 150
Order
Receipts
Planned 150
Order
Releases
77. In reference to Problem No. 74, determine when order should be released for product D and the size
of the order.
a. 250, period 2 & 250, period 3 b. 500, period 1 & 250, period 2
c. 250, period 3 & 500, period 4 d. 500, period 5 & 250, period 6
Solution:
Item: D Period
LCC: 1
Lot Size: 250 PD 1 2 3 4 5 6 7 8
LT:4
Gross 585 180
Requirements (195 x 3) (90 x 2)
Scheduled 250
Receipts
Projected On 200 200 450 450 115 185 20 20 20
Hand
Net 135 65
Requirements
Planned 250 250
Order
Receipts
Planned 250 250
Order
Releases
110 | P a g e
Solved Problems in Production Planning & Control 2012
78. Given the following MRP matrix, what is the entry value for X?
Item: E Period
LCC: 1
Lot Size: 50 PD 1 2 3 4 5 6 7 8
LT:2
Gross 20 30 50 50 60 90 40 60
Requirements
Scheduled 50
Receipts
Projected On 40 X
Hand
Net Y
Requirements
Planned
Order
Receipts
Planned Z
Order
Releases
a. 20 b. 40
c. 50 d. 70
Answer: b. 40
Solution:
Item: E Period
LCC: 1
Lot Size: 50 PD 1 2 3 4 5 6 7 8
LT:2
Gross 20 30 50 50 60 90 40 60
Requirements
Scheduled 50
Receipts
Projected On 40 20 40 X = 40
Hand
Net 10 Y
Requirements
Planned 50
Order
Receipts
Planned 50 Z
Order
Releases
79. In reference to Problem No. 78, what is the entry value for Y?
a. 20 b. 40
c. 50 d. 70
Answer: a. 20
111 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
Item: E Period
LCC: 1
Lot Size: 50 PD 1 2 3 4 5 6 7 8
LT:2
Gross 20 30 50 50 60 90 40 60
Requirements
Scheduled 50
Receipts
Projected On 40 20 40 40 40 30
Hand
Net 10 10 Y = 20
Requirements
Planned 50 50 50
Order
Receipts
Planned 50 50 50 Z
Order
Releases
80. In reference to Problem No. 79, what is the entry value for Z?
a. 50 b. 70
c. 100 d. 150
Answer: a. 50
Solution:
Item: E Period
LCC: 1
Lot Size: 50 PD 1 2 3 4 5 6 7 8
LT:2
Gross 20 30 50 50 60 90 40 60
Requirements
Scheduled 50
Receipts
Projected On 40 20 40 40 40 30 0 10 0
Hand
Net 10 10 20 60 40 50
Requirements
Planned 50 50 50 60 50 50
Order
Receipts
Planned 50 50 50 60 50 Z = 50
Order
Releases
112 | P a g e
Solved Problems in Production Planning & Control 2012
81. Referring to the following product structure diagram, how many E’s are needed for each A.
a. 85 b. 110
c. 125 d. 130
Answer: c. 125
Solution:
E = (3 X 5 X 3) + (4 X 5 X 4) = 45 + 80 = 125
82. In reference to problem no. 81, how many Js are needed for two As?
a. 80 b. 100
c. 120 d. 140
Answer: c. 120
Solution:
E = (3 X 5 X 4) (2) = 120
113 | P a g e
Solved Problems in Production Planning & Control 2012
83. Capistrano Cans packages processed food into cans for a variety of customers. The factory has four
multipurpose cookers and canning lines that can pressure-cook, vacuum-pack, and applies labels to
just about any type of food or size of can. The processing equipment was purchased some years
apart, and some of the cookers are faster and more efficient than others. Capistrano Cans has four
orders that need to be run today for a particular customer: canned beans, canned peaches, canned
tomatoes, and canned corn. The customer is operating under a just-in-time production system and
needs the mixed order of canned food tomorrow. Capistrano Cans has estimated the number of
hours required to pressure-cook, process, and can each type of food by type of cooker as follows:
Cooker 1 2 3 4
Food
Beans 10 5 6 10
Peaches 6 2 4 6
Tomatoes 7 6 5 6
Corn 9 5 4 10
Due to time constraints imposed by lengthy changeover procedures, only one job can be assigned to
each cooker. How should the jobs be assigned to the cookers in order to process the food most
efficiently?
Solution:
Row Reduction:
Cooker 1 2 3 4
Food
Beans 5 0 1 5
Peaches 4 0 2 4
Tomatoes 2 1 0 1
Corn 5 1 0 6
Column Reduction:
Cooker 1 2 3 4
Food
Beans 3 0 1 4
Peaches 2 0 2 3
Tomatoes 0 1 0 0
Corn 3 1 0 5
Cooker 1 2 3 4
Food
Beans 3 0 1 4
Peaches 2 0 2 3
Tomatoes 0 1 0 0
Corn 3 1 0 5
114 | P a g e
Solved Problems in Production Planning & Control 2012
Since the number of lines does not equal the number of rows, continue.
Modify the matrix:
Cooker 1 2 3 4
Food
Beans 1 0 1 2
Peaches 0 0 2 1
Tomatoes 0 3 2 0
Corn 1 1 0 3
Cooker 1 2 3 4
Food
Beans 1 0 1 2
Peaches 0 0 2 1
Tomatoes 0 3 2 0
Corn 1 1 0 3
Cooker 1 2 3 4
Food
Beans 1 0 1 2
Peaches 0 0 2 1
Tomatoes 0 3 2 0
Corn 1 1 0 3
84. In reference to Problem No. 83, when can they complete the customer’s order?
a. 4 b. 5
c. 6 d. 7
Answer: c. 6
Cooker 1 2 3 4
Food
Beans 10 5 6 10
Peaches 6 2 4 6
Tomatoes 7 6 5 6
Corn 9 5 4 10
Beans will take 5 hours to cook, peaches will take 6 hours, tomatoes 6 hours, and corn 4 hours. Given
that the four cooker/ canning lines can operate simultaneously, we can complete the customer’s order in
6 hours.
115 | P a g e
Solved Problems in Production Planning & Control 2012
85. Liquido Printing Shop has four jobs waiting to be run this morning. Fortunately, they have four printing
presses available. However, the presses are of different vintage and operate at different speeds. The
approximate times (in minutes) required to process each job on each press are given next. Assign jobs to
presses so that the batch can be completed as soon as possible.
Press
Job 1 2 3 4
A 20 90 40 10
B 40 45 50 35
C 30 70 35 25
D 60 45 70 40
Solution:
Row reduction:
Job 1 2 3 4
A 10 80 30 0
B 5 10 15 0
C 5 45 10 0
D 20 5 30 0
Column reduction:
Job 1 2 3 4
A 5 75 20 0
B 0 5 5 0
C 0 40 0 0
D 15 0 20 0
Job 1 2 3 4
A 5 75 20 0
B 0 5 5 0
C 0 40 0 0
D 15 0 20 0
The number of lines equals the number of rows, so this is the final solution. Make assignments:
Job 1 2 3 4
A 5 75 20 0
B 0 5 5 0
C 0 40 0 0
D 15 0 20 0
Assign job A to press 4, job B to press 1, job C to press 3, and job D to press 2.
116 | P a g e
Solved Problems in Production Planning & Control 2012
86. In reference to Problem No. 85, when can the entire batch be completed?
a. 35 b.45
c. 70 d. 90
Answer: b. 45
Solution:
Job 1 2 3 4
A 20 90 40 10
B 40 45 50 35
C 30 70 35 25
D 60 45 70 40
Since the jobs can be run concurrently, the entire batch will be completed by the maximum completion
time of the individual jobs, or job D’s time of 45 minutes.
87. Today is the morning of September 1. Because of the approaching holiday season, Mr. Cuenco is
scheduled to work 7 days a week for the next 2 months. September’s work for Mr. Cuenco consists
of five jobs, A, B, C, D, E. Job A takes 5 days to complete and is due September 10, job B takes 10
days to complete and is due September 15, job C takes 2 days to process and is due September 5,
job D takes 8 days to process and is due September 12, and job E, which takes 6 days to process, is
due September 8.
What is the average completion time if you sequence the jobs by First-Come, First-Serve (FCFS)?
a. 15.00 b. 16.40
c. 17.80 d. 18.60
Answer: d. 18.60
Solution:
88. In reference to Problem No. 87, what is the average tardiness if you sequence the jobs by earliest
due date (DDATE)?
a. 5.6 b. 6.0
c. 6.8 d. 9.6
Answer: a. 5.6
117 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
89. In reference to Problem No. 87, what is the number of jobs tardy if you sequence the jobs by
minimum slack (SLACK)?
a. 2 b. 3
c. 4 d. 5
Answer: c. 4
Job A = (10 – 1) – 5 = 4
Job B = (15 – 1) – 10 = 4
Job C = (5 – 1) – 2 = 2
Job D = (12 – 1) – 8 = 3
Job E = (8 – 1) – 6 = 1
90. In reference to Problem No. 87, what is the maximum tardiness if you sequence the jobs by shortest
processing time (SPT)?
a. 26 b. 23
c. 17 d. 16
Answer: d. 16
118 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
91. In reference to Problem No. 87, what is the sequence of jobs if you use the smallest critical ratio (CR)
rule?
a. A-B-C-D-E b. C-E-A-D-B
c. E-C-D-A-B d. E-D-B-A-C
Answer: d. E-D-B-A-C
92. Today is day 4 of the planning cycle. Sequence the following jobs by FCFS and determine the
average completion time.
a. 19.91 b. 21.61
c. 23.81 d. 24.71
Answer: d. 24.71
119 | P a g e
Solved Problems in Production Planning & Control 2012
Solution:
93. In reference to Problem No. 92, what is the average tardiness if you sequence the jobs by earliest
due date (DDATE)?
a. 6.66 b. 7.86
c. 8.86 d. 9.66
Answer: c. 8.86
Solution:
94. In reference to Problem No. 92, what is the number of jobs tardy if you sequence the jobs by
minimum slack (SLACK)?
a. 4 b. 5
c. 6 d. 7
Answer: d. 7
Job A = (10 – 4) – 3 = 3
Job B = (12 – 4) – 10 = -2
Job C = (25 – 4) – 2 = 19
Job D = (8 – 4) – 4 = 0
Job E = (15 – 4) – 5 = 6
Job F = (18 – 4) – 8 = 6
120 | P a g e
Solved Problems in Production Planning & Control 2012
Job G = (20 – 4) – 7 = 9
95. In reference to Problem No. 92, what is the maximum tardiness if you sequence the jobs by shortest
processing time (SPT)?
a. 31 b. 21
c. 17 d. 11
Answer: a. 31
Solution:
96. In reference to Problem No. 92, what is the sequence of jobs if you use the smallest critical ratio (CR)
rule?
a. A-B-C-D-E-F-G b. C-E-A-D-B-G-F
c. F-B-D-A-E-G-C d. G-F-E-D-B-A-C
Answer: c. F-B-D-A-E-G-C
121 | P a g e
Solved Problems in Production Planning & Control 2012
97. Zerrudo Fine Restoration has received a rush order to refinish five carousel animals – an alligator, a
bear, a cat, a deer, and an elephant. The restoration involves two major processes: sanding and
painting. Mr. Zerrudo takes care of the sanding; his son does the painting. The time required for
each refinishing job differs by the state of disrepair and degree of detail of each animal. Given the
following processing times (in hours), determine the order in which the jobs should be processed so
that the rush order can be completed as soon as possible.
a. B-A-C-D-E b. D-E-A-C-B
c. E-A-D-B-C d. A-D-E-B-C
Answer: c. E-A-D-B-C
Solution:
The smallest processing time is 3 hours, occurs at process 2 for job C, so we place job C to the end of
the sequence.
The next smallest is 5 hours. It occurs at process 1 for job E, so we place it to the beginning of the
sequence.
E C
The next smallest time is 6 hours. It occurs at process 1 for job A and at process 2 for job B. Thus, we
place job A as near to the beginning of the sequence and job B as near to the end.
E A B C
The only remaining is job D. It is placed in the only available slot, in the middle of the sequence.
E A D B C
122 | P a g e
Solved Problems in Production Planning & Control 2012
98. Satumira Car Service has five cars waiting to be washed and waxed. The time required (in minutes)
for each activity is given below. In what order should the cars be processed through the facility using the
Johnson’s rule?
a. 2-1-5-4-3 b. 5-1-4-3-2
c. 3-2-4-5-1 d. 4-3-1-2-5
Answer: b. 5-1-4-3-2
Solution:
The lowest processing time is 2 minutes for waxing car 2. Since waxing is the second operation,
we place car 2 as near to the end of the sequence as possible, in last place.
The next-lowest time is 3 minutes for washing car 5. Since washing is the first operation, we
place car 5 as near to the front of the sequence as possible, in first place.
The next-lowest time is 5 minutes for washing car 1 and waxing car 3. Car 1 is scheduled in
second place, and car 3 is put in the next-to-last place (i.e. fourth). That leaves car 4 for third
place.
Sequence: 5-1-4-3-2
99. Au Princena works in a cosmetic factory filling, capping, and labeling bottles. She is asked to process
an average of 150 bottles per hour through her work cell. If one kanban is attached to every
container, a container holds 25 bottles, it takes 30 minutes to receive new bottles from the previous
workstation, and the factory uses a safety stock factor of 10 percent, how many kanbans are
needed for the bottling process?
a. 3 b. 5
c. 7 d. 9
Answer: a. 3
Given:
Solution:
123 | P a g e
Solved Problems in Production Planning & Control 2012
100. An assembly station is asked to process 100 circuit boards per hour. It takes 20 minutes to receive
the necessary components from the previous workstation. Completed circuit boards are placed in a
rack that will hold 10 boards. The rack must be full before it is sent on to the next workstation. If the
factory uses a safety factor of 10 percent, how many kanbans are needed for the circuit board
assembly process?
a. 2 b. 4
c. 6 d. 8
Answer: b. 4
Given:
Solution:
124 | P a g e