CERC Connectivity Regulations
CERC Connectivity Regulations
Page 1 of 14
State transmission system is not required to be done and the requirement is
to be accommodated within the available spare transmission capacity
due to redundancy or part utilization of the transmission capacity.
5. In view of the above provision, the CTU has been flooded with large
number of applications for connectivity. The CTU vide its letter dated 3.1.
2011 has intimated to the Commission that it has received 82 numbers of
connectivity applications corresponding to about 100000 MW of installed
capacity (Tharmal-71Nos of 95,300 MW & Hydro- 11 nos. of 4,700 MW). The
CTU has further informed that the timeframes for coming up of the
Page 2 of 14
generating stations for which dedicated lines are to be constructed is less
than the timeframe of nine months plus minimum timeline prescribed by
CERC. The CTU has submitted that being a public sector undertaking, it is
required to follow stringent procurement procedures and it is difficult for
CTU to develop dedicated lines in less than the prescribed timeframe. On
the other hand, private developers are in a much better position to
develop these lines in much shorter timeframe.
6. In view of the above, the CTU in its letter dated 3.1.2011 has sought
for directions of the Commission on the following:
Page 3 of 14
dedicated transmission system up to the grid. However, the generating
company/licensee may be able to firm up its delivery/injection points at a
later date, and be able to apply for open access at that stage only. Thus,
connectivity may be seen as a pre-cursor to the open access. The
requirement of connectivity of this nature was not envisaged previously
and, therefore, the Commission’s regulations on open access did not cater
for these situations. The requests for connectivity from all such persons who
are eligible to buy/sell as per the Electricity Act, 2003 should normally be
disposed of within one month of receipt of such requests. While granting
permission to connect to the system, reasonable broad design requirements
may be intimated to the person seeking connection. It is needless to say
that the person seeking connectivity must agree to:
9. The Electricity Act, 2003 (the Act) has de-licensed generation and it
is, therefore, expected that there should not be any barriers for setting up
of generating stations by the investors/promoters. But in actual practice,
there are a number of requirements/activities which need to be
Page 4 of 14
completed before even starting the construction of projects. These
activities are:
Page 5 of 14
11. In the prevailing scenario of the power sector in India, it is even
difficult to find a buyer beforehand. The Tariff Policy mandates that
procuring agencies i.e. distribution companies should procure power only
through competitive bidding route. As such, the investors/promoters have
to depend on the action of procuring distribution companies to invite bids
for competitive procurement of power and wait for their response. Further,
it is not necessary that the investor/promoter would emerge as successful
bidder through the process of competitive bidding. Therefore, it is not
necessary that a generating station would be able to tie-up power for its
full capacity on long term basis and may be forced to sell power in short-
term or medium term open access through bilateral arrangements with
the traders or on power exchanges. The question therefore arises whether
generation activities which require much higher investment as compared
to the transmission, should be allowed to be frustrated for want of
connectivity and transmission system in the absence of long-term open
access. It would not be appropriate in the overall interest of the power
sector in the long run. In case LTA applications are not being received,
CTU and CEA would have to plan for transmission corridors taking into
account the generation potential and demand scenario in the various
regions and anticipating the power flows in the short term, medium term
and long term scenarios. Viewed in this perspective, it should not be
necessary to make an application of LTA along with the application for
“connectivity”.
12. The CTU has submitted that two categories of Long-term Access
may be created; one with firmed-up beneficiaries and another without
firmed-up beneficiaries and that this would do away with the requirement
of firming up the beneficiaries for the 50% of the capacity before or after
the submission of connectivity/LTA applications. According to CTU, there is
no clarity as to what should be done in case after grant of LTA, the
Page 6 of 14
generator is unable to tie up at least 50% of LTA capacity in long-term
PPAs.
13. CTU has submitted that the long-term purchase of power through
competitive bidding route is going rather slow. Further, merchant power
gaining wider acceptance amongst developers as well as utilities, it is
quite likely that firming up of beneficiaries may not actually happen in
near future.
14. In our view this may not be required at this stage. As per the
information available till date around 42605 MW of capacity has already
been tied up through competitive bidding under case 1 and case 2 as per
the details given below:
(In MW)
Case-1 Case-2 UMPP (Case-2) Total
15. The bifurcation of capacity under State Sector under Case-1 &
Case-2 is as follows:
CH 1320
GJ 6800
HY 1724 1320
MH 4900
MP 1841
PU 3300
RJ 1000
UP 4400
Page 7 of 14
16. It is apparent from the above that the States are gradually shifting
their focus on generation capacity augmentation with a view to meeting
future demand.
“The MTOA and STOA shall be offset against the long-term access granted
without identified beneficiaries to the same region only and not against
LTA granted to any other region. The traders who have a portfolio of
generators in a state, for which LTA was obtained to a target region, shall
not be allowed to use this facility to prevent corridor blocking through
LTA.”
Page 8 of 14
commissioned in a given time frame after ensuring that the generating
company has released the advance for the main plant packages i.e.
Turbine island and steam generator island or the EPC contract in case of
thermal generating station and major civil work packages or the EPC
contract in case of hydro generating stations for the corresponding
capacity of the phase or the phases subject to a minimum of 10% of the
sum of the such contract values:
Provided also that if the long-term customer has not identified the
buyer for the capacity in full or in part under long-term access and sells
such power under short-term or medium term open access, then the short
term or medium term transmission charges paid or payable for the period
of such short-term or medium-term open access for the given capacity
shall be offset against the transmission charges for the Long Term access
granted without identified beneficiaries, only if such short-term or medium-
term open access is taken to the same region:
21. But with regard to construction of dedicated lines for the generator
by CTU as per Regulation 8, CTU’s main concern is regarding recovery of
cost of investment on the dedicated line in case generation gets unduly
delayed or does not come up. It appears to be genuine concern and it
Page 9 of 14
may be difficult for the Regulatory Commissions also to burden the other
constituents with such stranded cost. At the same time, the generation
should not be frustrated unduly as discussed above for want of
connectivity or for want of dedicated line. The concerns of the CTU would
get addressed adequately once they take construction of dedicated lines
after the generator has released the advance to the main plant
packages and construction contracts as the CTU should draw sufficient
comfort that generator would not release the advance unless it is sure of
completing the project. However, the CTU and the transmission licensees
are expected to complete the ground work of coordinated planning, the
substation in which dedicated line is to be terminated, designing of
substation or the additional bay etc and be ready with the construction in
the shortest possible timeline.
Provided also that the transmission charges for such dedicated transmission
line shall be payable by the generator even if the project gets delayed or is
abandoned.”
Page 10 of 14
do the lines much earlier than the CTU. With the expertise available with
the CTU, it is in a much better position to do the transmission project as
compared to the IPPs. If it is not possible for the CTU to do the line to meet
the COD of the station then it should try to make arrangement for
evacuation of power through alternate mode till such time the proposed
dedicated line is constructed by CTU. Further it is not clear as to how many
stations are having such problem and in the absence of relevant data,
there is no need to make provision in the regulations for construction of
transmission lines by IPPS.
25. Clause (7) of the Regulation 8 carves out an exception to clause (6)
by providing for injection of power by the generator as infirm power
before commercial operation of the generating station even without
having any access . The said clause reads as under:
Page 11 of 14
or a unit thereof, other than those based on non-conventional energy
sources, the tariff of which is determined by the Commission, will be
governed by the Central Electricity Regulatory Commission (Terms and
Conditions of Tariff) Regulations, 2009. The power injected into the grid
from other generating stations as a result of this testing shall also be
charged at UI rates.”
26. It has come to the notice of the Commission that a certain private
generator is injecting power into the grid without declaring the
commercial operation even though the generating station has been
synchronized to the grid for a considerable period of time. This has
happened apparently due to two reasons; firstly there is no provision in the
Connectivity Regulations about the period during which injection of infirm
power by the generator as UI can be allowed. Secondly, there is no built-in
disincentive which would prevent the generator to stop injecting infirm
power into the grid as UI and identify buyers for sale of such infirm power.
Therefore, the generator also is required to be allowed to inject infirm
power during testing before COD of units of a generating station after
finding buyers for the same as far as possible. However, if the generators
are unable to do so, the infirm power generated during testing before
COD of units of the generating station may be allowed to be injected as
UI but charged at UI rates subject to the ceiling rates which should be
near to their variable cost which would encourage the generators to
declare their COD at an early date. As a number of merchant power
plants getting connected to the grid is likely to rise in future, there is a
requirement for clarity on the issue. Accordingly, it has been proposed to
substitute clause (7) of Regulation 8 of Connectivity Regulations as under:
Page 12 of 14
exceeding three months after obtaining prior permission of the concerned
Regional Load Despatch Centre:
Provided that the concerned Regional Load Despatch Centre while granting
such permission shall keep the grid security in view and ensure that injection
of such infirm power is only for the purpose of testing, prior to COD of the
generating station or a unit thereof;
(ii) Infirm power from a generating station or a unit thereof, other than those
based on non-conventional energy sources, the tariff of which is determined
by the Commission, shall be governed by the provisions of Central Electricity
Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2009 as
amended from time to time or subsequent amendment thereof;
Provided that where infirm power is injected into the grid during the testing
prior to COD of a generating station or unit thereof for which no buyer has
been identified, the generator shall be paid at UI rates for such infirm power
subject to the ceiling of the following rates corresponding to the fuel used for
the generation:
Domestic coal
(Rs. / kWh sent out) : 1.65
Imported Coal/RLNG
(Rs. / kWh sent out) : 3.30
Liquid Fuel
(Rs. / kWh sent out) : 9.00
Page 13 of 14
Provided further that in case imported coal is being blended with domestic
coal, then the ceiling rate of infirm power shall be arrived at in proportion to the
ratio of blending based on the above rates of domestic and imported coal
Provided also that in case the generating station uses natural gas
supplied under Administrative Price Mechanism (APM), Re-gassified Liquid
Natural Gas (RLNG) and Liquid fuel in combination for power generation, then
the rate of infirm power shall be arrived at in proportion to the ratio of fuel
consumption based on the rates specified above.”
27. Any short fall in recovery of fuel cost could be factored in the tariff
by the merchant power generator for the firm power supply as and when
starts.
Page 14 of 14