Utility_Contribution_to_Arc_Flash_Studies
Utility_Contribution_to_Arc_Flash_Studies
Abstract – The utility contribution input to an arc flash study has accidentally or intentionally, between two or more points of
a significant effect on the output incident energy. Accurate input different potential).” [2]
data can be difficult to obtain from serving utilities or is not Short circuit current is calculated based on the fault current
consistently available. Defaulting to infinite bus can provide non- input to the electrical system and the system impedances
conservative results. This focus session poster will discuss the between the sources and equipment location. Common fault
challenges with utility contribution with examples and suggest current sources include utility, motors, and generators.
approaches to calculate conservative incident energy when the Available fault current is “the largest amount of current capable
utility contribution data is not made available. of being delivered at a point on the system during a short-circuit
condition.” [2]
Index Terms — Arc flash study, utility contribution data, Short circuit current is calculated using the following
incident energy, short-circuit current, infinite bus. equations:
𝑘𝑉𝐴 × 1000
𝐼!.#.$. =
I. INTRODUCTION 𝐸## × 1.732
Where:
𝑉=) = open-circuit voltage (kV)
𝐼9: = bolted fault short circuit current 𝐼%.&. (kA)
𝐼'()_+,, = average RMS arcing current at 𝑉=) = 600𝑉 (kA)
𝐼'() = final rms arcing current at 𝑉=) (kA)
Where:
𝐸+,, = incident energy at 𝑉=) = 600𝑉 (J/cm2)
𝑇 = arc duration (ms)
𝐺 = gap distance between electrodes (mm)
𝐼'()_+,, = average RMS arcing current at 𝑉=) = 600𝑉 (kA)
𝐼'() = final rms arcing current for 𝑉=) ≤ 600𝑉 (kA)
𝐼9: = bolted fault short circuit current 𝐼%.&. (kA)
𝐷 = working distance (mm)
𝐶𝐹 = correction factor for enclosure size (𝐶𝐹 = 1 for VOA)
𝑘1 to 𝑘10 = coefficients provided in IEEE 1584-2018 Table 1
Fig. 1 Sample System Formats
Final incident energy:
𝐸 = 𝐸>+,, IV. RESULTS
Where: Calculations are currently in progress. Results from the
𝐸>+,, = incident energy for 𝑉=) ≤ 600𝑉 (J/cm2) calculations for the systems to be provided. The following tables
𝐸 = final incident energy at specified 𝑉=) (J/cm2) (or similar) and results summaries will be provided:
• Maximum AFIE and associated % Bolted Fault
C. Requirements
Current for each sample system.
Short circuit current and incident energy are calculated to
• AFIE at % Bolted Fault Current for each sample
ensure equipment is properly rated for the electrical system, and
system.
to allow workers to choose appropriate PPE to protect against
arc flash hazards.
The following figures will be provided:
NFPA 70 article 408.6 requires switchboards, switchgear, and
panelboards to be rated for the available fault current, and for the • Time current curves for typical overcurrent protective
AFC to be marked on the enclosure at the point of supply. When devices
input data is not available from the utility, infinite bus can be • Graphs of maximum AFIE vs % bolted fault current
assumed on the transformer primary to calculate the maximum for select systems.
short circuit current that can be output on the transformer
secondary. NOMENCLATURE
NFPA 70E requires the selection of PPE to protect against arc
flash hazards. Two methods are permitted: PPE category table Nomenclature to be provided.
method, which uses parameters of available short circuit current,
overcurrent protective device trip time, and voltage to determine V. CONCLUSIONS
PPE level; and the arc flash incident energy calculation method,
which calculates the worst case arc flash incident energy based Based on calculated values, the average percentage of infinite
on system inputs and components that is used to choose PPE bus short circuit current that produces worst-case values is
with an arc flash rating greater than or equal to the calculated (TBD). The paper will also take into account variations in the
value. percentage based on secondary voltage and transformer size
range to determine if larger vs smaller transformers have a
III. SAMPLE SYSTEMS significantly different percentage.
10-20 sample systems <1000V will be modeled. Systems will
consist of various size transformers and overcurrent protective
devices. Transformer impedances will be typical for size. Circuit
2
Authorized licensed use limited to: William Brown. Downloaded on March 26,2025 at 20:25:25 UTC from IEEE Xplore. Restrictions apply.
VI. ACKNOWLEDGEMENTS Balasubramanian PE and A. Graham PE, Copyright IEEE,
New York, NY
Thank you to Angel Farias Carrillo, Jaime Mireles, Alex
Ramirez, and Martin Iedema for technical contributions to this VIII. VITAE
paper.
Tracy Roberts graduated from Washington State University in
VII. REFERENCES 2016 with a MSEE degree. She has been an electrical design
engineer for Pacific Northwest National Laboratory since 2021.
[1] IEEE Std 1584-2018, IEEE Guide for Performing Arc-Flash Previously she was an electrical engineer and electrical safety
Hazard Calculations,. subject matter expert at Mission Support Alliance, Hanford. She
[2] NFPA 70, 2023 National Electrical Code, Quincy, MA: is a member of IEEE and EFCOG.
NFPA. Drew Thomas graduated from Washington State University in
[3] NFPA 70E, 2024 Standard for Electrical Safety in the 2015 with a BSEE degree. He is Engineering Director and NFPA
Workplace, Quincy, MA: NFPA. 70 Authority Having Jurisdiction at Hanford Mission Integration
[4] IEEE Paper PCIC-2009-16, “Impact of Available Fault Solutions. He is a member of IEEE and EFCOG.
Current Variations on Arc-Flash Calculations”, by I.
3
Authorized licensed use limited to: William Brown. Downloaded on March 26,2025 at 20:25:25 UTC from IEEE Xplore. Restrictions apply.