0% found this document useful (0 votes)
2 views

random report

Uploaded by

0383
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views

random report

Uploaded by

0383
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

Unit IG2: Risk assessment

Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that the
work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).

Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.

Part 1: Background

You should aim to complete this section in 150 - 200 words.


Topic Comments
Name of organisation* Muhammad shafeq builder
Site location* Near DHQ hospital batkhela district malakand kpk Pakistan
Number of workers 40
Muhammad shafeq builder work inside or out side of district malakand at multiple
locations like Government buildings shopping Mall private hospitals currently working on
the construction of Star market basically Star market basi on basement for cars parking
ground floor shops first floor offices 3rd floor mosque
The area of Star market is 6000 square feet the workers are working single shift. Working
shift are from 9:00AM to 5:00PM
General description of the organisation
The activity which are going on loading unloading carry soil material some electrical
activity are also going on shifting of steel iron and some wooden work be going on other
like cutting drilling mixing etc
The use many equipment heavy machine like excavator dumper mixture for mixing
material drill machine hammer ladder scaffold material which are use an working area
cement sand concrete wood brick plastic sheet
Description of the area to be included in
Risk assessment cover all the construction area
the risk assessment
Safety supervisor responsible person for health and safety how will be answeribal to
Any other relevant information
project manager

Learner number: Learner name: Page 1 of 16


* If you’re worried about confidentiality, you can invent a false name and location for your organisation but, all other information provided must be
factual.

You should aim to complete this section in 100 - 200 words.


Note: this section can be completed after you have competed your risk assessment.
In the start i search for the completion of risk assessment guidance which is provided by
ILO for the purpose to ILO conversation C167 safety and health construction convention

The HSE is also a good source of information i referred HSE-150


Outline how the risk assessment was
carried out this should include:
Which helps us to identify the hazard to giving comfort on work site in work office
 sources of information consulted;
I visit a large and good source of information working area that is covered in the risk
 who you spoke to; and
assessment so I noticed all the hazard substance present in work place
 how you identified: I also meet in interview those workers which are involved in different activities these help
- the hazards; me to identify different hazard's on the work place and control measuring that will be
- what is already being done; and provided by the organization
- any additional controls/actions that The current work condition and current control for hazard that helps me to identify further
may be required. needs interview of workers aslo help me to identify those hazard's which are not clearly
observed
I also checked the previous record of accident and the recurrence capability of the
accident
The previous record like training record equipment maintenance record absentee record
on the basis of this further suggestions

Learner number: Learner name: Page 2 of 16


Part 2: Risk Assessment

Organisation name: Muhammad shafeq builder


Date of assessment: 9/July/2023
Scope of risk assessment: the risk assessment cover all the construction area

Hazard category and Who might be harmed and how? What are you What further Timescales for
hazard already doing? controls/action further actions Responsible
s are required? to be person’s job
completed title
(within …)
Electricity Visitors, workers, supervisor, site manager may 1. The responsible 1. Provid PPEs to
harm person are aware the workers
Damage electrical wire are the workers from
passing through the ground in There are different activities on work site using electric wire time by 2. change all the
working area time damage cables
different equipment and the damage wire of all
2. All the active part
machine are on the ground the can cause shock of electric wire are 3. Giving proper
burns to workers cause minor injurys permanent covered through protection and
disability or even death tape supervision
3. They mainten
electric equipment 4. Provid tools
before installing and equipment
4. All the workers which are totally
are aware about any insulated
danger situation
5.from electric
shock protecting
workers providing
earthling

6. ensure to
Change of wire
with double
insulation cables

Learner number: Learner name: Page 3 of 16


Hazard category and Who might be harmed and how? What are you What further Timescales for
hazard already doing? controls/action further actions Responsible
s are required? to be person’s job
completed title
(within …)
Fire Workers, helper, visitors, supervisor may 1. Provided 1. Separate place
harm training to for inflammable
Worker are smoking near workers on fire material
the inflammable fluid which Worker smoking near the inflammable fluid safety
2. Provid separate
are store in tank tank and the tank is leak the fluid is spell on 2. Safety sign are
place for smoking
the ground if the workers through the butt of in the work place workers
cigarette in spell fluid near the tank they
cause fire 3. Provid fire
Lead to different injury skin burn internal blanket
injury permanent disability damage
equipment construction building and even 4. Installation of
death fire Extinguishers
on working site

5. Provid proper
clothes and PPEs
Vibration Compactor machine operator may harm 1. The operator is 1. Proper
using toe guard checking of
Soil compactor produced worker are use in regular basis due to vibration of during used of equipment and
excessive vibration compactor machine the machine produced 15m/s2 of compactor maintenance
vibration because blood in has hand fingers will not
15m/s2
reach properly the cause hand arm vibration 2. Provided face
syndrome, vibration white fingers.carpeil tunnel mask for protection 2. Use of
syndrome compactor for
3. Routine check up dumping metrial
and maintenance of
equipment 3. Provid PPEs
to the workers
4. All workers are
trained using 4. Provid
vibrating equipment training on use
of equipment
and tool's

Learner number: Learner name: Page 4 of 16


Hazard category and Who might be harmed and how? What are you What further Timescales for
hazard already doing? controls/action further actions Responsible
s are required? to be person’s job
completed title
(within …)

5. Provid proper
gloves which
reduce vibration
capacity

6. Ensure to
provid rotation
for job workers
Working at height Worker's visitors supervisor and near worker 1. Provided 1. organization
may harm training to workers should provide
Worker are working on guard rail on
scaffold with out guard Worker's using scaffold for height work 2. Providing PPEs scaffold to protect
workers
rail and safety net height is about 25 feet absence of guardrail for those workers
and safety net workers work on scaffold can which are working 2. provid a safety
Fall down equipment which are use fall down it hight net around the
metrial etc scaffold
Cause injury fracture permanent disability
even death occur 3. Use of mobile
scaffold for work it
hight

4. Provid proper
PPEs for those
workers which are
work it hight such
as rope system
and fall arrest
Noise Generator operator workers visitors 1. They provided 1. The
supervisor may harm health surveillance generator
Generator are use in open should be
area produces excessive 2. Provided ear place away
noise more than 90db. plugs to workers

Learner number: Learner name: Page 5 of 16


Hazard category and Who might be harmed and how? What are you What further Timescales for
hazard already doing? controls/action further actions Responsible
s are required? to be person’s job
completed title
(within …)
Generator produced a lot of noise during the from working
activities different equipment are operating site to reduce
on generator also over loaded and they sound capacity
produced noise more than 90db
2. Provid
Noise may cause different hearing disability proper
some of them are permanent and some are mentence of
temporary Tinnitus perhaps stress silencer

3. Provid
proper PPEs to
workers

4. Giving
proper health
surveillance

5. Job rotation
provid to
workers

Radiation Worker involved in activitie people working in the 1. Providing 1. Provid shielding
area cleaning and maintenance staff watching the welding clothes for Arc Welding
Welding with drict eye contact activity to worker
of workers produced UV 2. Provid proper
radiation Arc Welding is a hazard for the workers and those PPEs to worker
people who near by due to produces extremely bright face shield gogals
light and UV radiation welding can cause eyes
damage because they produced UV rays and flying 3. Provid curtains
metal particles for welding
The cause eyes injury but some time damage process
permanently the vision of your eyes
Eyes swollen pain and permanent damage

Learner number: Learner name: Page 6 of 16


Hazard category and Who might be harmed and how? What are you What further Timescales for
hazard already doing? controls/action further actions Responsible
s are required? to be person’s job
completed title
(within …)
4. Provid job
rotation to the
workers

5. Change Arc
Welding
equipment with
gas welding
Load handling equipment Worker's visitors supervisor laborers maybe harm 1 before activity 1. Provid proper
workers are aware mentence
Use of crane for load handling The crane activity of load handling is going on Highe about the activity
highe wind and over loading wind can effect the process of load lifting and over 2. Ensure that the
loading drictley effect the activity the crane can be activity are done
unbalanced break of arm any thing happened in this on plan surface
situation
The May cause fracture permanent disability or even 3. Provid proper
death checking and
monitoring of
activity

4. Balancing the
weight before
activity not over
loaded

5. provided proper
PPEs to workers
and operator

6. Provid proper
training

Learner number: Learner name: Page 7 of 16


Hazard category and Who might be harmed and how? What are you What further Timescales for
hazard already doing? controls/action further actions Responsible
s are required? to be person’s job
completed title
(within …)
Work equipment Grinder operator workers nearby labor visitors other 1. Providing PPEs to 1. Ensure that
people which are watching the activity worker grinder are
Giranders are using in open enclosure with
area with out safeguard the grinder machine are not well maintain and use 2. Providing training guard
with out safeguard to workers
Machine produced vibration. Common hazard are 2. Installation of
flying particles iron dust and spark emergency stop
Grinding disk (wheel) is in motion they may cause button
severe injury's to user and other workers nearby
The May cause serious injury's amputation of fingers 3. Proper
fracture cuts to skin head injury foot injury maintenance of
equipment

4. Provided proper
training use of
equipment

5. Provided PPEs
to operator and
workers
Confined spaces Worker's and labor are May be harm 1. Providing PPEs to 1. Provided proper
workers communication
Deep excavation work on The workers who are working in the tunnel oxygen device
basement for water pipe line deficiency the eficiency of other gasses in large 2. Providing first aid
make a tunnel so there will amount the Walls of the tunnel rough they can Fall on kit to workers 2. Provided proper
oxygen deficiency other them the May cause short breathing delighted the lighting system to
gasses generation workers and if the walls fall down cause serious workers
injury's bones fracture permanent disability and even
death occur 3. Air testing other
gasses or oxygen
deficiency

4. Providing
respirators for
workers

Learner number: Learner name: Page 8 of 16


Hazard category and Who might be harmed and how? What are you What further Timescales for
hazard already doing? controls/action further actions Responsible
s are required? to be person’s job
completed title
(within …)
Movement of people and Worker's visitors supervisor and other people maybe 1. Responsible 1. Construction of
vehicle harm person aware all separate routes
In the construction site vehicle and workers use the worker about the for vehicle's or
The workers and vehicle are same way for movement which can lead any accident accident workers
use same path for transfer between workers and vehicle's because they are
material to working site over speeding 2. Speed limit sign 2. Provided
They can cause different injury's fracture permanent are present it work separate walk
disability cuts broken bone and even death occur site way's

3. Constructed
speed breakers
for reducing
speed limit

4. Provided proper
training

5. Provided proper
communication

6. Provided proper
supervision
Hazardous substance Worker visitors supervisor may be harm 1. Water 1. Provided job
suppression on rotation for the
A lot of dust produced with The vehicle are dumping the construction materials working site for workers
dumping of construction like cement blocks Brecks concrete the produced a control of dust
materials lot of dust and the workers are continuesly inhale 2. proper
So the caused different lungs diseases cause 2. Providing training supervision
allergies asthma lungs infection bronchitis lungs to workers
Cancer 3. Provided
3. Providing face respirators to the
mask to workers on workers
working site
4. Provided health
surveillance

Learner number: Learner name: Page 9 of 16


Hazard category and Who might be harmed and how? What are you What further Timescales for
hazard already doing? controls/action further actions Responsible
s are required? to be person’s job
completed title
(within …)

5. Provided proper
training to workers

6. Provided PPEs
to all workers
Manual handling Worker which are involved in activitie and near by
workers maybe harm
Different construction
materials are carrying up and The workers carrying different construction materials
down the slope by workers manually on slope like cement blocks concrete etc if
uses their body force the worker or laod are slept from his hand so the May
cause injury we know that several accident from low
management of work on slope these accident are
happened because of unsafe system of work no
knowledge about slope working
Several injury like back injury muscle pain cuts on
skin shoulder pain and disability

Silps and trips Workers visitors supervisor manger maybe harm 1. Maintenance of
water tank
Water spell from water tank on Water is spell from water tank on floor the way which
floor used by the workers for carrying material 2. Provid separate
Which may cause trip hazard and also cause place for water
different injury's hand Head temporary disability and tank
1. Safety sign are
even bones fracture
use in work site
3. Ensure that
cleaner in working
2. Provided training
site
to workers
4. Responsible
person are check
and monitor

Learner number: Learner name: Page 10 of 16


Hazard category and Who might be harmed and how? What are you What further Timescales for
hazard already doing? controls/action further actions Responsible
s are required? to be person’s job
completed title
(within …)
5. Provid PPEs to
All workers

6. Provid proper
training

Health welfare and Workers visitors supervisor


work environment manger All related people with
work site maybe harm
Rest room wash
room work place is It shows bad culture of the
not completely organization unclean space
clean and hygiene washroom rest room working site
provided stress to the workers
stress weak the immune system
virus and bacteria are drictley
effect the health of workers
Cause different disease skin
diseases also infact internal
organs lungs kidney stomach
diarrhea vomiting etc

Learner number: Learner name: Page 11 of 16


Part 3: Prioritise 3 actions with justification for the selection
Suggested word counts
Moral, general legal and financial arguments for all actions: 300 to 350 words
For EACH action:
Specific legal arguments: 100 to 150 words
Likelihood AND severity: 75 to 150 words
How effective the action is likely to be in controlling the risk: 100 to 150 words

Moral, general legal and financial arguments for ALL actions

Moral, general legal and financial Moral argument.


arguments The main and moral responsibility of the company is that to ensure the health and safety of the workers
organization duty of care must be shown by the company if the company wants the health and safety of the
workers the workers who come to work with they are the source and support of the food and shelter of their
families and dependent if the worker injured not only the worker effected but infact all his dependents effected
if there is unsafe physical and mental condition for the workers in a company it will not only be unacceptable
for the workers but the society as a whole
The unsafe physical and mental condition may lead to an accident to overcome all these things the employer
may ensure his prime responsibility regarding workers health and safety
Legal orgument.

Along with moral responsibilities the company may follow all the national and international rules regulations
and may work according to the legislation ILO general rules and regulations bound the employer of each
company to ensure the safety of the workers
If any of the employer failed to fulfill these legal duties then strict actions can be taken against him if company
Will break the law then prohibition notice may issue against it corrective action may also be taken apart from
this a court prosecution may be started against the employer or the related person may be hugely fine or May
be imprisoned or the company may be closed if the results will be catastrophic
Along with catastrophic result the injured workers may claim for civil compensation and that will also be pay
by the employer and there will be also Court proceeding of the donor of the civil claim and productive time of
the organization will also be lost during court proceedings the bad reputation of the organization may severely
effected the future business of the organization

Learner number: Learner name: Page 12 of 16


Financial Argument

After accident the company faced financial loss the amount which spend by the company prior to avoid
accident if this amount has been utilized to prevent the accident than the financial loss will be not that much
as occur after accident after an accident the company also face the hospitalisation and treatment cost along
with this the repair cost of the damage machineries and equipment the hiring cost of the new workers legal
proceedings and court prosecution cost and apart from this the over time cost are also face by the company
after accident the company reputation may also be effected due to which the company can face problems in
business gaining in future the morale of the workers maybe down and which can cause less productiveness,
the industrial relations of the company may be effected and ultimately these all factor's will play a role in the
financial loss of the company the injured workers may claim for the live compensation which can results in
legal proceedings and a financial cost also All these expenditures will only be face by the company as the
company has made no insurance OR the hospital cost and equipment repair cost may received to company
from insurance but due to it the insurance premiums chances may increase

Justification for action 1

Action (Taken from column 4 of risk


assessment)

Specific legal arguments

Consideration of likelihood AND severity


 types of injury or ill health
 number of workers at risk
 how often the activity is carried
out
 how widespread the risk is

Learner number: Learner name: Page 13 of 16


How effective the action is likely to be in
controlling the risk. This should include:
 the intended impact of the action;
 justification for the timescale that
you indicated in your risk
assessment; and
 whether you think the action will
fully control the risk

Justification for action 2

Action (Taken from column 4 of risk


assessment)

Specific legal arguments

Consideration of likelihood AND severity


 types of injury or ill health
 number of workers at risk
 how often the activity is carried
out
 how widespread the risk is
How effective the action is likely to be in
controlling the risk. This should include:
 the intended impact of the action;
 justification for the timescale that
you indicated in your risk
assessment; and
 whether you think the action will
fully control the risk

Learner number: Learner name: Page 14 of 16


Justification for action 3

Action (Taken from column 4 of risk


assessment)

Specific legal arguments

Consideration of likelihood AND severity


 types of injury or ill health
 number of workers at risk
 how often the activity is carried
out
 how widespread the risk is
How effective the action is likely to be in
controlling the risk. This should include:
 the intended impact of the action;
 justification for the timescale that
you indicated in your risk
assessment; and
 whether you think the action will
fully control the risk

Part 4: Review, communicate and check


Suggested word counts for each section:
 Planned review date or period and reasoning for this: 50 - 100 words
 How the risk assessment findings will be communicated and who needs to know the information: 100 - 150 words
 Follow up on the risk assessment: 100 - 150 words.

Learner number: Learner name: Page 15 of 16


Planned review date/period with I will review this risk assessment after a year because its company's policy to review all the risk
reasoning assessment annually
Apart from annual risk assessment review i will also review this assessment risk from time to time if
there occur any changes in legislation or introduce of New material and also if the work process
modified due to ancident/accident or if any health issues arise and I will also review the annual risk
assessment if the new workers join there may be vulnerable and periodically
I will also review which i had already set for the period of one year
How the risk assessment findings will be After completion of the whole process I will arrange a meeting with the top management
communicated AND who you need to tell designation
In that meeting I will share the intial findings I will also share minutes of meeting with the concern
people
I will also conduct another meeting with the middle management designation in which I will share
the risk assessment document in detail and will discuss the responsibilities regarding further action
The detailed risk assessment document will also be shared with the top management
I will also arrange a toolbox for the workers in which hazard's will be discussed and along with the
toolbox on the notice board of the site
I will share posters related to hazard's
How you will follow up on the risk To ensure my suggestions I will note down those points in diary as a reminder which completely
assessment to check that the actions practiced and MS Excel sheet I will include all the suggestions in detail and if possible I will visit
have been carried out each control before the assigned time or I will call the responsible person to send me photographic
proof and will tell him to notify me through an official email that the control implementation has been
done if there are any control deadline of which has been ended but still the work has been remain
them I will ask the concern person about the reason of delay and then I will try to overcome the
reason if the reason behind delay is financial issue or lackness of work force them i will inform the
concern department to priorities the control

Learner number: Learner name: Page 16 of 16