proj sched gantt

The document outlines a detailed project schedule for the construction of a two-storey multi-purpose hall, spanning from May 2025 to January 2026. It includes various tasks such as pre-construction work, regulatory compliance, site preparation, and construction phases, with specified durations and dependencies for each task. The project concludes with close-out activities, including documentation and a post-project review.

Uploaded by

maabbybroncano60
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views

proj sched gantt

The document outlines a detailed project schedule for the construction of a two-storey multi-purpose hall, spanning from May 2025 to January 2026. It includes various tasks such as pre-construction work, regulatory compliance, site preparation, and construction phases, with specified durations and dependencies for each task. The project concludes with close-out activities, including documentation and a post-project review.

Uploaded by

maabbybroncano60
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Task Name Duration Start Finish Predecessors Resource Names May 2025 June 2025 July 2025

Finish Predecessors Resource Names May 2025 June 2025 July 2025 August 2025 September 2025 October 2025 November 2025 December 2025 January 2026
Mode 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17
1 Proposed Construction of Two Storey Multi 140 days Fri 5/2/25 Mon Proposed
Purpose Hall/SK Hall 11/17/25 Construction of Two
Storey Multi
2 Pre - Construction Work 37 days Fri 5/2/25 Tue 6/24/25 Pre - Construction Work

3 Regulatory Compliance 13 days Fri 5/2/25 Tue 5/20/25 Regulatory Compliance

4 Permits and Legal Requirements 13 days Fri 5/2/25 Tue 5/20/25 Permits and Legal Requirements Permits and Legal Requirements

5 Site Preparation 24 days Wed 5/21/25Tue 6/24/25 Site Preparation

6 Site Clearing 3 days Wed 5/21/25Fri 5/23/25 4 Site Clearing Site Clearing

7 Site Survey 3 days Wed 5/21/25Fri 5/23/25 6SS Site Survey Site Survey

8 Soil Testing 4 days Mon 5/26/25Thu 5/29/25 7,6 Soil Testing Soil Testing

9 Temporary Fencing and Barricades 3 days Fri 5/30/25 Tue 6/3/25 8 Temporary Fencing and Barricades Temporary Fencing and Barricades

10 Access Road and Hauling Path Setup 4 days Wed 6/4/25 Mon 6/9/25 9 Access Road and Hauling Path Setup Access Road and Hauling Path Setup

11 Delivery and Staging Area Preparation 3 days Tue 6/10/25 Fri 6/13/25 10 Delivery and Staging Area Preparation Delivery and Staging Area Preparation

12 Excavation for Temporary Facilities 3 days Mon 6/16/25Wed 6/18/2511 Excavation for Temporary Facilities Excavation for Temporary Facilities

13 Installation of Temporary Utilities 4 days Thu 6/19/25 Tue 6/24/25 12 Installation of Temporary Utilities Installation of Temporary Utilities

14 Substructure Works 29 days Thu 6/19/25 Tue 7/29/25 Substructure Works

15 Earthworks 15 days Thu 6/19/25 Wed 7/9/25 Earthworks

16 Excavation 5 days Thu 6/19/25 Wed 6/25/2512 Excavation Excavation

17 Soil Poisoning 2 days Thu 6/26/25 Fri 6/27/25 16 Soil Poisoning Soil Poisoning

18 Embankment 3 days Mon 6/30/25Wed 7/2/25 17 Embankment Embankment

19 Gravel Bedding 2 days Thu 7/3/25 Fri 7/4/25 18 Gravel Bedding Gravel Bedding

20 Compaction 3 days Mon 7/7/25 Wed 7/9/25 19 Compaction Compaction

21 Foundation Construction 14 days Thu 7/10/25 Tue 7/29/25 Foundation Construction

22 Formwork Installation 4 days Thu 7/10/25 Tue 7/15/25 20 Formwork Installation Formwork Installation

23 Reinforcement Placement 4 days Wed 7/16/25Mon 7/21/2522 Reinforcement Placement Reinforcement Placement

24 Concrete Pouring 3 days Tue 7/22/25 Thu 7/24/25 23 Concrete Pouring Concrete Pouring

25 Backfilling 3 days Fri 7/25/25 Tue 7/29/25 24 Backfilling Backfilling

26 Superstructure Works 37 days Wed 7/30/25Fri 9/19/25 Superstructure Works


27 Structural Works 37 days Wed 7/30/25Fri 9/19/25 Structural Works

28 Column Construction (Formwork and 4 days Wed Mon 8/4/25 25 Column Column Construction (Formwork and Reinforcement)
Reinforcement) 7/30/25 Construction
(Formwork and
29 Column Concrete Pouring and Curing 4 days Tue 8/5/25 Fri 8/8/25 28 Column Concrete Pouring and Curing Column Concrete Pouring and Curing

30 Installation of Scaffolding and Shoring 3 days Mon 8/11/25Wed 8/13/2529 Installation of Scaffolding and Shoring Installation of Scaffolding and Shoring

31 Beam and Slab Formwork and 5 days Thu 8/14/25 Wed 30 Beam and Slab Beam and Slab Formwork and Reinforcement (First Floor)
Reinforcement (First Floor) 8/20/25 Formwork and
Reinforcement (First
32 Concrete Pouring and Curing (First 4 days Thu 8/21/25 Wed 31 Concrete Pouring Concrete Pouring and Curing (First Floor Slab and Beams)
Floor Slab and Beams) 8/27/25 and Curing (First
Floor Slab and
33 Column Rebar Extension for Second Floor
3 days Thu 8/28/25 Mon 9/1/25 32 Column Rebar Extension for Second Floor Column Rebar Extension for Second Floor

34 Beam and Slab Formwork and 5 days Tue 9/2/25 Mon 9/8/25 33 Beam and Slab Beam and Slab Formwork and Reinforcement (Second Floor)
Reinforcement (Second Floor) Formwork and
Reinforcement
35 Concrete Pouring and Curing (Second 4 days Tue 9/9/25 Fri 9/12/25 34 Concrete Pouring Concrete Pouring and Curing (Second Floor Slab and Beams)
Floor Slab and Beams) and Curing (Second
Floor Slab and
36 Staircase Construction 5 days Mon 9/15/25Fri 9/19/25 35 Staircase Construction Staircase Construction

37 Masonry Works 10 days Mon 9/22/25Fri 10/3/25 Masonry Works


38 Wall Construction 10 days Mon 9/22/25Fri 10/3/25 Wall Construction
39 CHB installation 6 days Mon 9/22/25Mon 9/29/2536 CHB installation CHB installation

40 Door and Window Installation 4 days Tue 9/30/25 Fri 10/3/25 39 Door and Window Installation Door and Window Installation

41 External Works 16 days Tue 9/9/25 Tue 9/30/25 External Works


42 Roofing 16 days Tue 9/9/25 Tue 9/30/25 Roofing
43 Truss Work 4 days Tue 9/9/25 Fri 9/12/25 34 Truss Work Truss Work

44 Roof Sheeting Installation 3 days Mon 9/15/25Wed 9/17/2543 Roof Sheeting Installation Roof Sheeting Installation

45 Gutter Installations 2 days Thu 9/18/25 Fri 9/19/25 44 Gutter Installations Gutter Installations

46 Flashing Installation 2 days Mon 9/22/25Tue 9/23/25 45 Flashing Installation Flashing Installation

47 Ridge Roll Installation 2 days Wed 9/24/25Thu 9/25/25 46 Ridge Roll Installation Ridge Roll Installation

48 Canopy Works 3 days Fri 9/26/25 Tue 9/30/25 47 Canopy Works Canopy Works

49 Parapet Wall Finishing 3 days Fri 9/26/25 Tue 9/30/25 47 Parapet Wall Finishing Parapet Wall Finishing

50 Electrical and Plumbing Works 13 days Mon 9/15/25Wed 10/1/25 Electrical and Plumbing Works
51 Electrical 13 days Mon 9/15/25Wed 10/1/25 Electrical

52 Electrical Rough-ins 4 days Mon 9/15/25Thu 9/18/25 35 Electrical Rough-ins Electrical Rough-ins

53 Installation of Panels 3 days Fri 9/19/25 Tue 9/23/25 52 Installation of Panels Installation of Panels

54 Wire Pulling 3 days Wed 9/24/25Fri 9/26/25 53 Wire Pulling Wire Pulling

55 Installation of Switches, Outlets, and 3 days Mon Wed 54 Installation of Installation of Switches,Outlets,and Fixtures
Fixtures 9/29/25 10/1/25 Switches,Outlets,and
Fixtures
56 Plumbing 13 days Mon 9/15/25Wed 10/1/25 Plumbing
57 Pipe Installation 4 days Mon 9/15/25Thu 9/18/25 35 Pipe Installation Pipe Installation

58 Septic Vault and Catch Basin Construction


5 days Fri 9/19/25 Thu 9/25/25 57 Septic Vault and Catch Basin Construction Septic Vault and Catch Basin Construction

59 Installation of Plumbing Fixtures 3 days Fri 9/26/25 Tue 9/30/25 58 Installation of Plumbing Fixtures Installation of Plumbing Fixtures

60 Storm and Sewer Line Installation 4 days Fri 9/26/25 Wed 10/1/2558 Storm and Sewer Line Installation Storm and Sewer Line Installation

61 Finishing Works 26 days Mon 9/22/25Mon 10/27/25 Finishing Works


62 Building Finishes 26 days Mon 9/22/25Mon 10/27/25 Building Finishes
63 Wall Plastering 6 days Tue 9/30/25 Tue 10/7/25 39 Wall Plastering Wall Plastering

64 Ceiling Framing and Installation 4 days Tue 9/30/25 Fri 10/3/25 63SS Ceiling Framing and Installation Ceiling Framing and Installation

65 Wall Tile Laying (CR and Kitchen) 3 days Wed 10/8/25Fri 10/10/25 63 Wall Tile Laying (CR and Kitchen) Wall Tile Laying (CR and Kitchen)

66 Floor Tile Laying 4 days Wed 10/8/25Mon 10/13/2563 Floor Tile Laying Floor Tile Laying

67 Stair Finishing 3 days Mon 9/22/25Wed 9/24/2536 Stair Finishing Stair Finishing

68 Painting Works ( Interior and Exterior) 5 days Tue 10/14/25Mon 10/20/2566 Painting Works ( Interior and Exterior) Painting Works ( Interior and Exterior)

69 Installation of Furnitures 3 days Tue 10/21/25Thu 10/23/2568 Installation of Furnitures Installation of Furnitures

70 Final Touches (Signage) 2 days Fri 10/24/25 Mon 10/27/2569 Final Touches (Signage) Final Touches (Signage)

71 Project Close-Out 15 days Tue 10/28/25Mon 11/17/25 Project Close-Out


72 Completion Activities 11 days Tue 10/28/25Tue 11/11/25 Completion Activities

73 Punch List 3 days Tue 10/28/25Thu 10/30/2570 Punch List Punch List

74 Deficiency Checks 3 days Fri 10/31/25 Tue 11/4/25 73 Deficiency Checks Deficiency Checks

75 Final Cleaning 3 days Wed 11/5/25Fri 11/7/25 74 Final Cleaning Final Cleaning

76 Debris Proposal 2 days Mon 11/10/25Tue 11/11/2575 Debris Proposal Debris Proposal

77 Documentation 4 days Wed 11/12/25


Mon 11/17/25 Documentation
78 Project Turnover and Client Orientation
2 days Wed 11/12/25Thu 11/13/2576 Project Turnover and Client Orientation Project Turnover and Client Orientation

79 Post-Project Review & Lessons Learned2 days Fri 11/14/25 Mon 11/17/2578 Post-Project Review& Lessons Learned Post-Project Review& Lessons Learned

Project: proj sched Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Sun 5/11/25 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress