1 Proposed Construction of Two Storey Multi 140 days Fri 5/2/25 Mon Proposed
Purpose Hall/SK Hall 11/17/25 Construction of Two
Storey Multi
2 Pre - Construction Work 37 days Fri 5/2/25 Tue 6/24/25 Pre - Construction Work
4 Permits and Legal Requirements 13 days Fri 5/2/25 Tue 5/20/25 Permits and Legal Requirements Permits and Legal Requirements
6 Site Clearing 3 days Wed 5/21/25Fri 5/23/25 4 Site Clearing Site Clearing
7 Site Survey 3 days Wed 5/21/25Fri 5/23/25 6SS Site Survey Site Survey
8 Soil Testing 4 days Mon 5/26/25Thu 5/29/25 7,6 Soil Testing Soil Testing
9 Temporary Fencing and Barricades 3 days Fri 5/30/25 Tue 6/3/25 8 Temporary Fencing and Barricades Temporary Fencing and Barricades
10 Access Road and Hauling Path Setup 4 days Wed 6/4/25 Mon 6/9/25 9 Access Road and Hauling Path Setup Access Road and Hauling Path Setup
11 Delivery and Staging Area Preparation 3 days Tue 6/10/25 Fri 6/13/25 10 Delivery and Staging Area Preparation Delivery and Staging Area Preparation
12 Excavation for Temporary Facilities 3 days Mon 6/16/25Wed 6/18/2511 Excavation for Temporary Facilities Excavation for Temporary Facilities
13 Installation of Temporary Utilities 4 days Thu 6/19/25 Tue 6/24/25 12 Installation of Temporary Utilities Installation of Temporary Utilities
17 Soil Poisoning 2 days Thu 6/26/25 Fri 6/27/25 16 Soil Poisoning Soil Poisoning
19 Gravel Bedding 2 days Thu 7/3/25 Fri 7/4/25 18 Gravel Bedding Gravel Bedding
22 Formwork Installation 4 days Thu 7/10/25 Tue 7/15/25 20 Formwork Installation Formwork Installation
23 Reinforcement Placement 4 days Wed 7/16/25Mon 7/21/2522 Reinforcement Placement Reinforcement Placement
24 Concrete Pouring 3 days Tue 7/22/25 Thu 7/24/25 23 Concrete Pouring Concrete Pouring
28 Column Construction (Formwork and 4 days Wed Mon 8/4/25 25 Column Column Construction (Formwork and Reinforcement)
Reinforcement) 7/30/25 Construction
(Formwork and
29 Column Concrete Pouring and Curing 4 days Tue 8/5/25 Fri 8/8/25 28 Column Concrete Pouring and Curing Column Concrete Pouring and Curing
30 Installation of Scaffolding and Shoring 3 days Mon 8/11/25Wed 8/13/2529 Installation of Scaffolding and Shoring Installation of Scaffolding and Shoring
31 Beam and Slab Formwork and 5 days Thu 8/14/25 Wed 30 Beam and Slab Beam and Slab Formwork and Reinforcement (First Floor)
Reinforcement (First Floor) 8/20/25 Formwork and
Reinforcement (First
32 Concrete Pouring and Curing (First 4 days Thu 8/21/25 Wed 31 Concrete Pouring Concrete Pouring and Curing (First Floor Slab and Beams)
Floor Slab and Beams) 8/27/25 and Curing (First
Floor Slab and
33 Column Rebar Extension for Second Floor
3 days Thu 8/28/25 Mon 9/1/25 32 Column Rebar Extension for Second Floor Column Rebar Extension for Second Floor
34 Beam and Slab Formwork and 5 days Tue 9/2/25 Mon 9/8/25 33 Beam and Slab Beam and Slab Formwork and Reinforcement (Second Floor)
Reinforcement (Second Floor) Formwork and
Reinforcement
35 Concrete Pouring and Curing (Second 4 days Tue 9/9/25 Fri 9/12/25 34 Concrete Pouring Concrete Pouring and Curing (Second Floor Slab and Beams)
Floor Slab and Beams) and Curing (Second
Floor Slab and
36 Staircase Construction 5 days Mon 9/15/25Fri 9/19/25 35 Staircase Construction Staircase Construction
40 Door and Window Installation 4 days Tue 9/30/25 Fri 10/3/25 39 Door and Window Installation Door and Window Installation
44 Roof Sheeting Installation 3 days Mon 9/15/25Wed 9/17/2543 Roof Sheeting Installation Roof Sheeting Installation
45 Gutter Installations 2 days Thu 9/18/25 Fri 9/19/25 44 Gutter Installations Gutter Installations
46 Flashing Installation 2 days Mon 9/22/25Tue 9/23/25 45 Flashing Installation Flashing Installation
47 Ridge Roll Installation 2 days Wed 9/24/25Thu 9/25/25 46 Ridge Roll Installation Ridge Roll Installation
48 Canopy Works 3 days Fri 9/26/25 Tue 9/30/25 47 Canopy Works Canopy Works
49 Parapet Wall Finishing 3 days Fri 9/26/25 Tue 9/30/25 47 Parapet Wall Finishing Parapet Wall Finishing
50 Electrical and Plumbing Works 13 days Mon 9/15/25Wed 10/1/25 Electrical and Plumbing Works
51 Electrical 13 days Mon 9/15/25Wed 10/1/25 Electrical
52 Electrical Rough-ins 4 days Mon 9/15/25Thu 9/18/25 35 Electrical Rough-ins Electrical Rough-ins
53 Installation of Panels 3 days Fri 9/19/25 Tue 9/23/25 52 Installation of Panels Installation of Panels
54 Wire Pulling 3 days Wed 9/24/25Fri 9/26/25 53 Wire Pulling Wire Pulling
55 Installation of Switches, Outlets, and 3 days Mon Wed 54 Installation of Installation of Switches,Outlets,and Fixtures
Fixtures 9/29/25 10/1/25 Switches,Outlets,and
Fixtures
56 Plumbing 13 days Mon 9/15/25Wed 10/1/25 Plumbing
57 Pipe Installation 4 days Mon 9/15/25Thu 9/18/25 35 Pipe Installation Pipe Installation
59 Installation of Plumbing Fixtures 3 days Fri 9/26/25 Tue 9/30/25 58 Installation of Plumbing Fixtures Installation of Plumbing Fixtures
60 Storm and Sewer Line Installation 4 days Fri 9/26/25 Wed 10/1/2558 Storm and Sewer Line Installation Storm and Sewer Line Installation
64 Ceiling Framing and Installation 4 days Tue 9/30/25 Fri 10/3/25 63SS Ceiling Framing and Installation Ceiling Framing and Installation
65 Wall Tile Laying (CR and Kitchen) 3 days Wed 10/8/25Fri 10/10/25 63 Wall Tile Laying (CR and Kitchen) Wall Tile Laying (CR and Kitchen)
66 Floor Tile Laying 4 days Wed 10/8/25Mon 10/13/2563 Floor Tile Laying Floor Tile Laying
67 Stair Finishing 3 days Mon 9/22/25Wed 9/24/2536 Stair Finishing Stair Finishing
68 Painting Works ( Interior and Exterior) 5 days Tue 10/14/25Mon 10/20/2566 Painting Works ( Interior and Exterior) Painting Works ( Interior and Exterior)
69 Installation of Furnitures 3 days Tue 10/21/25Thu 10/23/2568 Installation of Furnitures Installation of Furnitures
70 Final Touches (Signage) 2 days Fri 10/24/25 Mon 10/27/2569 Final Touches (Signage) Final Touches (Signage)
73 Punch List 3 days Tue 10/28/25Thu 10/30/2570 Punch List Punch List
74 Deficiency Checks 3 days Fri 10/31/25 Tue 11/4/25 73 Deficiency Checks Deficiency Checks
75 Final Cleaning 3 days Wed 11/5/25Fri 11/7/25 74 Final Cleaning Final Cleaning
76 Debris Proposal 2 days Mon 11/10/25Tue 11/11/2575 Debris Proposal Debris Proposal
79 Post-Project Review & Lessons Learned2 days Fri 11/14/25 Mon 11/17/2578 Post-Project Review& Lessons Learned Post-Project Review& Lessons Learned