Combine PDF
Combine PDF
PROFESSIONAL
PRACTICE I
COC : APPENDIX TO THE CONDITIONS
Chattan filed an arbitration claim concerning an Award dated The judge found that Reigill was not
August 18, 2006, made in arbitration proceedings between obligated to accept the cheque paid by
Chattan and Reigill. Chattan applied under section 80(5) of the Mr. Cattanach. The judge determined
Arbitration Act 1996 for an extension of time to appeal a question that the £16,000 should be treated as
of law in the Award under section 69 of the Act. The arbitration paid when it was credited to the client
claim should have been issued by September 15, 2006, but was account of Kershaw-Abbot at 3:07 pm.
only issued on September 28, 2006. The judge heard the The judge held that Chattan complied
application on January 15, 2007, and extended the time by 13 with the conditions of the order, and the
days with conditions, including the payment of Reigin's costs on extension of time granted by the order
an indemnity basis, assessed at £16,000. Reigill contends that stands. The judge expressed sympathy
the payment was insufficient to meet the condition, leading to for Reigill's position but found that
the dismissal of the appeal as being out of time. Chattan argues Chattan's compliance warranted the
that the payment made on January 29, 2007, fulfilled the extension of time.
condition and the appeal should proceed.
Hanover University
THANK
YOU♡
Dani Martinez
Engineering | 2023
PERFORMANCE
BOND
PAM 2018 (CLAUSE 39.0) PWD 203A (CLAUSE 13.0)
- Contract the Contractor shall either deposit with the
- Contractor shall submit before the date of commencement
Government a performance bond in cash or alternatively by
of the work
way of a Treasury's Deposit or Banker's Draft or approved
Banker's or Insurance Guarantee equal to 5% of the
-Submit for a sum equivalent to the percentage stated in the
Contract Sum as a condition precedent to the
appendix.
commencement of work.
a) not to disturb the object & shall cease work if the continuance of the work would endanger the
object.
b) take all necessary steps to preserve the object in the exact position.
FACTS
The main contract between the Claimant and the Defendant
provided for contract drawings to be signed as part of the
contract documents. However, clause 5.4 of the contract
required the architect, as the Claimant's agent, to provide
further drawings and details as necessary. SIGNIFICANCE
This case clarifies the obligations of parties in a construction
The Claimant argued that the Defendant was obligated to contract regarding the provision of coordination drawings and the
exercise reasonable care and skill to ensure compliance with importance of acting with reasonable care and skill in fulfilling
clause 5.4, as it was in the contemplation of the parties that contractual duties.
failure to provide the drawings would result in the Claimants
suffering damage in the form of liabilities to the contractor for
breach of clause 5.4.
INFORMATION AND
INSTRUCTIONS TO THE
CONTRACTOR
Neodox Ltd v Swinton and Pendelebury (1958)
CASE FACTS