0% found this document useful (0 votes)
3 views

4FDFD

The document is a Bill of Quantities for construction work in the Republic of Maldives, detailing various items, materials, labor rates, and associated costs for different construction phases. It includes sections on preliminaries, excavation, filling, concrete works, and steel work, with specific quantities and rates outlined for each item. The total amounts for each bill are summarized, providing a comprehensive overview of the project costs.

Uploaded by

Sadhooh Naseer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views

4FDFD

The document is a Bill of Quantities for construction work in the Republic of Maldives, detailing various items, materials, labor rates, and associated costs for different construction phases. It includes sections on preliminaries, excavation, filling, concrete works, and steel work, with specific quantities and rates outlined for each item. The total amounts for each bill are summarized, providing a comprehensive overview of the project costs.

Uploaded by

Sadhooh Naseer
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 22

-

ALITHARI N.MAAFARU
Republic of Maldives

BILL OF QUANTITIES
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
1.0.00 Bill №: 01 - PRELIMINARIES

1.1.00 GENERAL NOTES


Abbreviations
m - metre
nr - numbers
m3 - cubic metres
m2 - square metres
m - linear metre
t - tons
inc. - including
mm - millimetre
SS - stainless steel
GI - galvanized iron

1.2.00 SITE MANAGEMENT COSTS


35,000.00 15,000.00 35,000.00 15,000.00 50,000.00
Allow for all on and off site management cost including costs
of foreman and assistants, temporary services, telephone, item 1.00
fax, hoardings & similar.

1.3.00 SIGN BOARD


Allow for sign board. nr 1.00 1,000.00 500.00 1,000.00 500.00 1,500.00

1.4.00 CLEAN-UP
Allow for clean-up upon completion of works. item 1.00 10,000.00 5,000.00 10,000.00 5,000.00 15,000.00

1.5.00 TOTAL OF BILL №: 01 - Carried Over To Summary 46,000.00 20,500.00 66,500.00


2.0.00 Bill №: 02 - EXCAVATION AND FILLING

2.1.00 GENERAL
(a) Rates shall include for: leveling, grading, trimming,
compacting to faces of excavation, keep sides plumb,
backfilling, consolidating, and disposing surplus soil.

2.2.00 SITE CLEARING


ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
2.2.01 Clear the area of site from rubbish and vegetable matters, 50.00 25.00 6,429.00 3,214.50 9,643.50
stumps, roots. Rates shall include for removal of trees and 2
128.58
m
tree stumps and disposal of such materials

2.3.00 EXCAVATION
Excavation quantities are measured to the faces of concrete
members. Rates shall include for all the additional
excavation required to place the formwork. Rates shall
include for backfilling.
2.3.01 Excavation m3 78.44 350.00 50.00 27,454.00 3,922.00 31,376.00

2.4.00 FILLING
Rate shall include for: levelling, grading, trimming,
compacting and similar
2.4.01 Compacted earth filling under ground slab m2 76.44 100.00 50.00 7,644.00 3,822.00 11,466.00

2.5.00 DAMP-PROOF MEMBRANE


Rate shall include for: dressing around and sealing to all
penetrations,laps and turnups.
2.5.01 Polythene damp proof membrane (500 gauge) m2 221.00 100.00 50.00 22,100.00 11,050.00 33,150.00

2.6.00 DE-WATERING
2.7.01 De-watering the excavation until completion of concrete 10,000.00 5,000.00 10,000.00 5,000.00 15,000.00
item 1.00
work as required

2.8.00 TOTAL OF BILL №: 02 - Carried Over To Summary 73,627.00 27,008.50 100,635.50


3.0.00 Bill №: 03 - INSITU CONCRETE WORKS
3.1.00 GENERAL
(a) Rates shall include for: placing in position, making good after
removal of formwork, mortar touch up to all concrete and
casting in all required items; additional concrete required to
conform to structural and excavated tolerances
(b) Mix ratio for reinforced concrete shall be 1:2:3 and lean
concrete shall be 1:2:6.
(c) All structural concrete shall be GRADE M25 and lean
concrete shall be GRADE M15
(d) Rates shall include for: concrete, formwork, reinforcement,
cleaning, fabrication, placing, the provision for all necessary
temporary fixings and supports including tie wires and chair
supports, laps, distribution bars and wastage.
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
(e) Rates shall include for: all necessary boarding, supports,
erecting, framing, temporary cambering, cutting,
perforations for reinforcing bars, bolts, straps, ties, hangers,
pipes and removal of formwork.
(f) Rates shall include for: cleaning, fabrication, placing the
provision for all necessary temporary fixings and supports
including tie wires and chair supports, laps, distribution bars
and wastage.
(g) All reinforcing bars shall be high strength bars.
(h) Slab soffits to be finished fairfaced, use plasteciser and
formwork with reducing agent.
(i) All exposed & external concrete members shall be casted
with Masterpel 777 or equivalent water proofing chemical.
(j) Rate shall include for applying 2 coats of waterproofing
chemical to substructure.(Below ground level)

3.2.00 MASS CONCRETE


Quantity is measured to the edges of concrete foundation
members. Rates shall be inclusive for any additional
concrete required to place the formwork.

3.2.01 50 mm Lean Concrete m3 2.50 2,000.00 - 5,000.00 5,000.00

3.3.00 REINFORCED INSITU CONCRETE

FOUNDATION & FOUNDATION BEAMS


3.3.01 1250 x 1250 Foundation F1 m3 0.94 2,600.00 - 2,437.50 2,437.50
3.3.02 1150 x 1150 Foundation F2 m3 1.19 2,600.00 - 3,094.65 3,094.65
3.3.01 1000 x 1000 Foundation F3 m3 2.10 2,600.00 - 5,460.00 5,460.00
3.3.01 900 x 900 Foundation F4 m3 0.73 2,600.00 - 1,895.40 1,895.40
3.3.01 800 x 800 Foundation F5 m3 0.38 2,600.00 - 998.40 998.40

3.3.08 350 x 200 mm Tie Beam TB m3 6.65 2,600.00 - 17,287.63 17,287.63


3.3.08 200 x 250 mm Foundation Beam FB m3 1.37 2,600.00 - 3,568.50 3,568.50

Stair Starter
3.3.09 900 x 170 mm Stair starter m3 0.18 2,600.00 - 477.36 477.36

PEDASTAL COLUMNS
3.3.10 250 x 200 mm Concrete columns C1 m3 0.26 2,600.00 - 682.50 682.50
3.3.10 225 x 200 mm Concrete columns C2 m3 0.33 2,600.00 - 859.95 859.95
3.3.10 225 x 200 mm Concrete columns C3 m3 0.24 2,600.00 - 614.25 614.25
-
Cement Bag 136.00 135.00 18,360.00 - 18,360.00
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
Coarse Sand Bag 272.00 60.00 16,320.00 - 16,320.00
Aggregate Bag 408.00 60.00 24,480.00 - 24,480.00
Admixture Ltr 13.60 50.00 680.00 - 680.00

3.8.00 FORM WORK


FOUNDATION & FOUNDATION BEAMS
3.8.01 1250 x 1250 Foundation F1 m² 1.50 200.00 - 300.00 300.00
3.8.02 1150 x 1150 Foundation F2 m² 2.07 200.00 - 414.00 414.00
3.8.01 1000 x 1000 Foundation F3 m² 4.20 200.00 - 840.00 840.00
3.8.01 900 x 900 Foundation F4 m² 1.62 200.00 - 324.00 324.00
3.8.01 800 x 800 Foundation F5 m² 0.96 200.00 - 192.00 192.00

3.8.07 350 x 200 mm Tie Beam TB m² 66.49 200.00 - 13,298.18 13,298.18


3.8.07 200 x 250 mm Foundation Beam FB m² 10.98 200.00 - 2,196.00 2,196.00

Stair Starter
3.8.08 900 x 170 mm Stair starter m² 2.57 200.00 - 513.60 513.60

PEDASTAL COLUMNS
3.8.09 250 x 200 mm Concrete columns C1 m² 4.73 200.00 - 945.00 945.00
3.8.09 225 x 200 mm Concrete columns C2 m² 6.25 200.00 - 1,249.50 1,249.50
3.8.09 225 x 200 mm Concrete columns C3 m² 4.46 200.00 - 892.50 892.50
- -
Plywood 12mm flim faced Nos 47.00 450.00 21,150.00 21,150.00
Timber 35x50mm m3 1.18 17,000.00 19,988.19 19,988.19
Timber 50x50mm m3 0.90 17,000.00 15,357.38 15,357.38
Timber Nail 1 1/2" Kg 30.00 50.00 1,500.00 1,500.00
Timber Nail 2" Kg 10.00 50.00 500.00 500.00
3"Wooden Screw Nos 661.55 3.00 1,984.64 1,984.64
4" Wooden Screw Nos 280.00 4.00 1,120.00 1,120.00
10mm Tread Rod 1800mm Nos 17.00 75.00 1,275.00 1,275.00
10mm nut Nos 100.00 3.00 300.00 300.00
10mm washer Nos 100.00 3.00 300.00 300.00
3.13.00 STEEL WORK
FOUNDATION & FOUNDATION BEAMS
3.13.01 6 mm Steel bar in foundation nr 141.00 33.51 8.38 4,725.07 1,181.27 5,906.33
3.13.01 10 mm Steel bar in foundation nr 16.00 93.09 23.27 1,489.38 372.35 1,861.73
3.13.01 12 mm Steel bar in foundation nr 154.00 134.04 33.51 20,642.84 5,160.71 25,803.56

Stair Starter
3.13.05 10 mm in stair starter nr 15.00 93.09 23.27 1,396.30 349.07 1,745.37

pedastal Column
3.13.06 6 mm in pedastal column nr 20.00 33.51 8.38 670.22 167.56 837.78
3.13.07 12 mm in pedastal column nr 47.00 134.04 33.51 6,300.09 1,575.02 7,875.11
3.13.07 16 mm in pedastal column nr 23.00 238.30 59.58 5,480.93 1,370.23 6,851.16
Binding Wire Kg 24.13 40.00 965.12 - 965.12

3.4.00 GROUND FLOOR


ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE

COLUMNS
3.4.01 250 x 200 mm Concrete columns C1 m3 0.65 2,600.00 - 1,690.00 1,690.00
3.4.01 225 x 200 mm Concrete columns C2 m3 0.82 2,600.00 - 2,129.40 2,129.40
3.4.01 225 x 200 mm Concrete columns C3 m3 0.59 2,600.00 - 1,521.00 1,521.00
-
Floor Slab
3.4.04 100 mm slab m3 11.42 2,600.00 - 29,690.70 29,690.70

Stair case
3.3.05 Staircase m3 1.60 2,600.00 - 4,160.00 4,160.00

Beam
3.4.06 400 x 200 mm Beam B1 m3 3.27 2,600.00 - 8,513.86 8,513.86
3.4.07 400 x 200 mm Beam B2 m3 2.72 2,600.00 - 7,064.93 7,064.93
3.4.07 400 x 175 mm Beam B3 m3 0.41 2,600.00 - 1,058.88 1,058.88
3.4.07 400 x 200 mm Beam B1A m3 0.32 2,600.00 - 828.26 828.26
3.4.07 400 x 200 mm Beam B2A m3 0.35 2,600.00 - 911.46 911.46
3.4.07 400 x 200 mm Beam CB1 m3 0.18 2,600.00 - 458.64 458.64
3.4.07 400 x 200 mm Beam CB2 m3 0.16 2,600.00 - 409.76 409.76

Roof Slab
3.4.11 130 mm slab m3 13.46 2,600.00 - 34,989.76 34,989.76

Cement Bag 287.00 135.00 38,745.00 - 38,745.00


Coarse Sand Bag 574.00 60.00 34,440.00 - 34,440.00
Aggregate Bag 861.00 60.00 51,660.00 - 51,660.00
Admixture Ltr 28.70 50.00 1,435.00 - 1,435.00
3.9.00 FORM WORK

COLUMNS -
3.9.01 250 x 200 mm Concrete columns C1 m² 11.70 200.00 - 2,340.00 2,340.00
3.9.01 225 x 200 mm Concrete columns C2 m² 15.47 200.00 - 3,094.00 3,094.00
3.9.01 225 x 200 mm Concrete columns C3 m² 11.05 200.00 - 2,210.00 2,210.00

Floor Slab
3.9.04 100 mm slab m² 11.00 200.00 - 2,200.00 2,200.00

Stair case
3.9.05 Staircase m² 15.00 200.00 - 3,000.00 3,000.00

Beam
3.9.06 400 x 200 mm Beam B1 m² 40.93 200.00 - 8,186.40 8,186.40
3.9.07 400 x 200 mm Beam B2 m² 33.97 200.00 - 6,793.20 6,793.20
3.9.07 400 x 175 mm Beam B3 m² 5.67 200.00 - 1,134.51 1,134.51
3.9.07 400 x 200 mm Beam B1A m² 3.98 200.00 - 796.40 796.40
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
3.9.07 400 x 200 mm Beam B2A m² 4.38 200.00 - 876.40 876.40
3.9.07 400 x 200 mm Beam CB1 m² 2.21 200.00 - 441.00 441.00
3.9.07 400 x 200 mm Beam CB2 m² 1.97 200.00 - 394.00 394.00

Roof Slab
3.9.09 130 mm slab m² 103.52 200.00 - 20,704.00 20,704.00

Plywood 12mm flim faced Nos 101.00 450.00 45,450.00 45,450.00


Timber 35x50mm m3 1.75 17,000.00 29,793.65 29,793.65
Timber 50x50mm m3 1.61 17,000.00 27,346.63 27,346.63
Timber 100x50mm m3 1.06 17,000.00 17,994.97 17,994.97
Timber Nail 1 1/2" Kg 30.11 50.00 1,505.64 1,505.64
Timber Nail 2" Kg 1.94 50.00 96.86 96.86
3"Wooden Screw Nos 960.64 3.00 2,881.91 2,881.91
4" Wooden Screw Nos 700.00 4.00 2,800.00 2,800.00
10mm Tread Rod 1800mm Nos 38.14 75.00 2,860.43 2,860.43
10mm nut Nos 236.36 3.00 709.09 709.09
10mm washer Nos 236.36 3.00 709.09 709.09
Jack Rental Nos 549.00 75.00 41,175.00 41,175.00
3.14.00 STEEL WORK

Column
3.14.01 6 mm in column nr 37.00 33.51 8.38 1,239.91 309.98 1,549.89
3.14.03 12 mm in column nr 47.00 134.04 33.51 6,300.09 1,575.02 7,875.11
3.14.03 16 mm in column nr 23.00 238.30 59.58 5,480.93 1,370.23 6,851.16

Floor Slab
3.14.03 6 mm in Floor slab nr 296.00 33.51 8.38 9,919.29 2,479.82 12,399.11

Stair case
3.14.04 10 mm in staircase nr 30.00 93.09 23.27 2,792.59 698.15 3,490.74

Beam
3.14.05 6 mm in beam nr 123.00 33.51 8.38 4,121.87 1,030.47 5,152.33
3.14.05 10 mm in beam nr 6.00 93.09 23.27 558.52 139.63 698.15
3.14.05 12 mm in beam nr 120.00 134.04 33.51 16,085.33 4,021.33 20,106.67
3.14.05 16 mm in beam nr 45.00 238.30 59.58 10,723.56 2,680.89 13,404.44
-
Roof Slab
3.14.08 10 mm in Roof slab nr 631.00 93.09 23.27 58,737.53 14,684.38 73,421.91
3.14.08 12 mm in Roof slab nr 15.00 134.04 33.51 2,010.67 502.67 2,513.33
Binding Wire Kg 79.63 40.00 3,185.36 - 3,185.36

3.4.00 FIRST FLOOR


COLUMNS
3.4.01 250 x 200 mm Concrete columns C1 m3 0.65 2,600.00 - 1,690.00 1,690.00
3.4.01 225 x 200 mm Concrete columns C2 m3 0.82 2,600.00 - 2,129.40 2,129.40
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
3.4.01 225 x 200 mm Concrete columns C3 m3 0.59 2,600.00 - 1,521.00 1,521.00

Beam
3.4.06 300 x 200 mm Beam RB1 m3 0.62 2,600.00 - 1,602.12 1,602.12
3.4.06 300 x 200 mm Beam RB2 m3 78.62 2,600.00 - 204,419.80 204,419.80
3.4.06 300 x 200 mm Beam RCB1 m3 4.72 2,600.00 - 12,265.19 12,265.19

Cement Bag 688.00 135.00 92,880.00 - 92,880.00


Coarse Sand Bag 1,376.00 60.00 82,560.00 - 82,560.00
Aggregate Bag 2,064.00 60.00 123,840.00 - 123,840.00
Admixture Ltr 68.80 50.00 3,440.00 - 3,440.00
3.9.00 FORM WORK

COLUMNS -
3.9.01 250 x 200 mm Concrete columns C1 m² 11.70 200.00 - 2,340.00 2,340.00
3.9.01 225 x 200 mm Concrete columns C2 m² 15.47 200.00 - 3,094.00 3,094.00
3.9.01 225 x 200 mm Concrete columns C3 m² 11.05 200.00 - 2,210.00 2,210.00

Beam
3.9.06 300 x 200 mm Beam RB1 m² 8.22 200.00 - 1,643.20 1,643.20
3.9.06 300 x 200 mm Beam RB2 m² 62.90 200.00 - 12,579.68 12,579.68
3.9.06 300 x 200 mm Beam RCB1 m² 3.50 200.00 - 700.00 700.00

Plywood 12mm flim faced Nos 10.00 450.00 4,500.00 4,500.00


Timber 35x50mm m3 0.50 17,000.00 8,500.00 8,500.00
Timber 50x50mm m3 0.50 17,000.00 8,500.00 8,500.00
Timber Nail 1 1/2" Kg 21.23 50.00 1,061.35 1,061.35
Timber Nail 2" Kg 0.34 50.00 17.19 17.19
3"Wooden Screw Nos 600.00 3.00 1,800.00 1,800.00
4" Wooden Screw Nos 700.00 4.00 2,800.00 2,800.00
Jack Rental Nos 46.00 75.00 3,450.00 3,450.00
3.14.00 STEEL WORK
Column
3.14.01 6 mm in column nr 37.00 33.51 8.38 1,239.91 309.98 1,549.89
3.14.03 12 mm in column nr 47.00 134.04 33.51 6,300.09 1,575.02 7,875.11
3.14.03 16 mm in column nr 23.00 238.30 59.58 5,480.93 1,370.23 6,851.16

Beam
3.14.05 6 mm in beam nr 95.00 33.51 8.38 3,183.56 795.89 3,979.44
3.14.05 12 mm in beam nr 91.00 134.04 33.51 12,198.04 3,049.51 15,247.56
Binding Wire Kg 16.99 40.00 679.76 - 679.76

3.7.00 OTHER WORKS


Lintel, Sill beams & Mid band
3.7.01 100 x 100 mm Ground Floor m3 1.35 2,600.00 - 3,498.34 3,498.34
3.7.02 100 x 100 mm First Floor m3 1.28 2,600.00 - 3,315.00 3,315.00
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
Cement Bag 22.00 150.00 3,300.00 - 3,300.00
Coarse Sand Bag 44.00 95.00 4,180.00 - 4,180.00
Aggregate Bag 66.00 95.00 6,270.00 - 6,270.00
Admixture Ltr 2.20 50.00 110.00 - 110.00

FORM WORK
3.12.01 100 x 100 mm Ground Floor m² 26.91 200.00 - 5,382.06 5,382.06
3.12.02 100 x 100 mm First Floor m² 25.50 200.00 - 5,100.00 5,100.00

Plywood 12mm flim faced Nos 5.00 550.00 2,750.00 2,750.00


Timber 35x50mm m3 0.25 17,000.00 4,250.00 4,250.00
Timber Nail 1 1/2" Kg 5.00 50.00 250.00 250.00
Concrete Nail 1 1/2" Kg 5.00 75.00 375.00 375.00

STEEL WORK
3.17.01 10 mm Lintel, Sill beams & Mid band Ground Floor Kg 31.00 93.09 23.27 2,885.68 721.42 3,607.10
3.17.02 10 mm Lintel, Sill beams & Mid band First Floor Kg 29.00 93.09 23.27 2,699.51 674.88 3,374.38

Binding Wire Kg 3.48 40.00 139.20 - 139.20

1200 mm dia ground well Nos 1.00 10,000.00 5,000.00 10,000.00 5,000.00 15,000.00

3.9.00 TOTAL OF BILL №: 03 - Carried Over To Summary 985,384.27 525,792.96 1,511,177.23


04.0.00 Bill №: 04 - ROOFING WORKS
04.1.00 GENERAL
(a) Rates shall include for: all labour in framing, notching and
fitting around projections, pipes, light fittings, hatches,
grilles and similar and complete with cleats, packers, wedges
and similar and all nails and screws.

04.1.02 ROOFING TIMBER WORKS

50 x 150 mm Timber Rafters m 306.26 132.00 33.00 40,426.32 10,106.58 50,532.90


50 x 50 mm Timber Battens m 320.00 45.00 11.25 14,400.00 3,600.00 18,000.00

04.2.00 GENERAL
(a) Rates shall include for: fair edges, dressing over angel fillets,
roof sealant, turning into grooves, all other labours, circular
edges, nails, screws and other fixings and laps.

Lysaght roofing sheet 29" Width m 253.97 250.00 100.00 63,492.06 25,396.83 88,888.89
Wool insulation 50mmx0.9m x15m roll 12.00 1,500.00 500.00 18,000.00 6,000.00 24,000.00
PVC black net roll 6.00 950.00 500.00 5,700.00 3,000.00 8,700.00
Fascia Gutter 8' Nos 18.00 472.00 118.00 8,496.00 2,124.00 10,620.00
GI gutter clip Nos 72.00 17.00 4.25 1,224.00 306.00 1,530.00
Gutter strap Nos 72.00 4.50 1.13 324.00 81.00 405.00
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
Ridge capping 8' Nos 12.00 328.00 82.00 3,936.00 984.00 4,920.00
Fascia capping 8' Nos 5.00 328.00 82.00 1,640.00 410.00 2,050.00
Valley Gutter 8' Nos 3.00 328.00 82.00 984.00 246.00 1,230.00
Down spot 3" Nos 6.00 60.00 15.00 360.00 90.00 450.00
Roofing Screw 3" Nos 1,500.00 4.00 1.00 6,000.00 1,500.00 7,500.00
Fascia board Wood plank 4m x 200m x8mm Nos 22.00 180.00 45.00 3,960.00 990.00 4,950.00

04.3.00 DOWN PIPE

82 mm dia rain water pipe item 6.00 1,100.00 500.00 6,600.00 3,000.00 9,600.00

TOTAL OF BILL №: 04 - Carried Over To Summary 175,542.38 57,834.41 233,376.79


5.0.00 Bill №: 05 - DOORS & WINDOWS

GENERAL
(a) Rates shall include for locks, latches, closers, push plates,
pull handles, bolts, kick plates, hinges and all door & window
hardware.
(b) Rates shall include for door frames, mullions, transoms,
trims, glazing, tinting, timber panels, boardings, framing,
lining, fastenings and all fixings.
(c) Sizes are given overall outside dimensions of actual doors
and windows.
(d) Thickness and sizes of glass panels are shown on the
Drawings and doors and windows schedule
(e) Rates shall include for all painting as specified
(f) Rates shall include all items specified in the door schedule
and specification.
(g) Frames and sashes to be 25-60 micron white powder coated
aluminium other wise specified.

5.1.00
GROUND FLOOR
5.1.05 850 x 2200 D1-Timber Door nr 6.00 8,500.00 1,275.00 51,000.00 7,650.00 58,650.00

5.1.05 750 x 2100 D2-Pvc Door nr 2.00 6,500.00 975.00 13,000.00 1,950.00 14,950.00

5.1.05 800 x 2150 D3-Timber sliding Door nr 1.00 9,500.00 1,425.00 9,500.00 1,425.00 10,925.00
5.1.12 2300 x 1550 W1-Aluminium Swing Window nr 1.00 10,695.00 1,604.25 10,695.00 1,604.25 12,299.25
5.1.12 1500 x 1550 W2-Aluminium Swing Window nr 1.00 6,975.00 1,046.25 6,975.00 1,046.25 8,021.25
5.1.12 2500 x 1550 W3-Aluminium Swing Window nr 3.00 11,625.00 1,743.75 34,875.00 5,231.25 40,106.25
5.1.12 2180 x 2450 SD-Aluminium Sliding Door nr 1.00 16,023.00 2,403.45 16,023.00 2,403.45 18,426.45

5.2.00 FIRST FLOOR


ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
5.1.05 850 x 2200 D1-Timber Door nr 3.00 8,500.00 1,275.00 25,500.00 3,825.00 29,325.00

5.1.05 750 x 2100 D2-Pvc Door nr 4.00 6,500.00 975.00 26,000.00 3,900.00 29,900.00
5.1.05 800 x 2150 D3-Timber sliding Door nr 1.00 9,500.00 1,425.00 9,500.00 1,425.00 10,925.00

5.1.12 2500 x 1550 W3-Aluminium Swing Window nr 1.00 11,625.00 1,743.75 11,625.00 1,743.75 13,368.75
5.1.12 2500 x 2450 SD1-Aluminium Sliding Door nr 3.00 18,375.00 2,756.25 55,125.00 8,268.75 63,393.75
5.1.12 1500 x 2450 FG-Aluminium Fixed Window nr 1.00 9,187.50 1,378.13 9,187.50 1,378.13 10,565.63

TOTAL OF BILL №: 05 - Carried Over To Summary 279,005.50 41,850.83 320,856.33


6.0.00 Bill №: 06 - MASONRY

GENERAL
(a) Rates shall include for: cleaning out cavities, forming
rebated reveals and pointing and cleaning down to reveals
where necessary; fractional size blocks, all necessary
machine cutting, cutting or forming chases or edges of floor
slabs, cutting or leavingholes and openings as recesses for
and building in pipes, conduits, sleeves and similar as
required for all trades; leaving surfaces rough or raking out
joints for plastering and flashing, bedding frames or plates,
building in joists, bearers or similar, temporary supports to
openings, templates, reinforcement in walls and for all
necessary making good.

6.1.00 BLOCK WORK

Cement block wall, bricks laid to form alternate courses of


headers and stretchers, laid on and inc. mortar. (EXTERNAL
WALLS)
100 mm thk full height (Full block)
6.1.03 BELOW GROUND FLOOR m2 50.59 150.00 - 7,588.44 7,588.44
6" Solid Bricks Nos 1,163.56 15.00 17,453.41 17,453.41
Cement Bag 11.64 135.00 1,570.81 1,570.81
Coarse Sand Bag 58.18 60.00 3,490.68 3,490.68

6.1.04 GROUND FLOOR m2 97.10 150.00 - 14,564.47 14,564.47


6" Solid Bricks Nos 2,233.22 15.00 33,498.28 33,498.28
Cement Bag 22.33 135.00 3,014.84 3,014.84
Coarse Sand Bag 111.66 60.00 6,699.66 6,699.66

6.1.06 FIRST FLOOR m2 142.19 150.00 - 21,328.35 21,328.35


ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
6" Solid Bricks Nos 3,270.35 15.00 49,055.21 49,055.21
Cement Bag 32.70 135.00 4,414.97 4,414.97
Coarse Sand Bag 163.52 60.00 9,811.04 9,811.04

Cement block wall, bricks laid to form alternate courses of


headers and stretchers, laid on and inc. mortar (INTERNAL
WALLS).
100 mm thk full height (Full block)
6.1.06 BELOW GROUND FLOOR m2 39.56 150.00 - 5,933.81 5,933.81
6" Solid Bricks Nos 909.85 15.00 13,647.77 13,647.77
Cement Bag 9.10 135.00 1,228.30 1,228.30
Coarse Sand Bag 45.49 60.00 2,729.55 2,729.55

6.1.08 GROUND FLOOR m2 85.61 150.00 - 12,840.75 12,840.75


6" Solid Bricks Nos 1,968.92 15.00 29,533.73 29,533.73
Cement Bag 19.69 135.00 2,658.04 2,658.04
Coarse Sand Bag 98.45 60.00 5,906.75 5,906.75

6.1.09 FIRST FLOOR m2 119.83 150.00 - 17,974.53 17,974.53


6" Solid Bricks Nos 2,756.09 15.00 41,341.42 41,341.42
Cement Bag 27.56 135.00 3,720.73 3,720.73
Coarse Sand Bag 137.80 60.00 8,268.28 8,268.28

TOTAL OF BILL №: 06 - Carried Over To Summary 238,043.45 80,230.35 318,273.80


7.0.00 Bill №: 07 - FLOOR, WALL FINISHINGS

GENERAL
(a) Rates shall include for: fixing, bedding, grouting, and
pointing materials; making good around pipes, sanitary
fixtures, and similar; cleaning down and polishing.
(b) "Masterseal 550" or equivalent should be applied on top of
screeds and walls upto 600mm in all toilets.

7.1.00 PLASTERING
20 mm thk cement plaster on external surface as specified on
the drawing. Waterproofed with Masterpel 777 or
equivalent.
7.1.03 BELOW GROUND FLOOR m2 44.78 80.00 - 3,582.30 3,582.30
Cement Bag 7.46 135.00 1,007.52 1,007.52
Coarse Sand Bag 29.85 60.00 1,791.15 1,791.15
Fine Sand Bag 29.85 85.00 2,537.47 2,537.47

7.1.04 GROUND FLOOR m2 129.29 80.00 - 10,342.96 10,342.96


Cement Bag 21.55 135.00 2,908.96 2,908.96
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
Coarse Sand Bag 86.19 60.00 5,171.48 5,171.48
Fine Sand Bag 86.19 85.00 7,326.26 7,326.26

7.1.05 FIRST FLOOR m2 183.78 80.00 - 14,702.33 14,702.33


Cement Bag 30.63 135.00 4,135.03 4,135.03
Coarse Sand Bag 122.52 60.00 7,351.16 7,351.16
Fine Sand Bag 122.52 85.00 10,414.15 10,414.15

16 mm thk cement plaster on internal surface as specified on


7.1.07 the drawing
BELOW GROUND FLOOR m2 101.12 80.00 - 8,089.60 8,089.60
Cement Bag 12.64 135.00 1,706.40 1,706.40
Fine Sand Bag 50.56 85.00 4,297.60 4,297.60

7.1.07 GROUND FLOOR m2 346.98 80.00 - 27,758.21 27,758.21


Cement Bag 43.37 135.00 5,855.25 5,855.25
Fine Sand Bag 173.49 85.00 14,746.55 14,746.55

7.1.09 FIRST FLOOR m2 390.51 80.00 - 31,240.90 31,240.90


Cement Bag 48.81 135.00 6,589.88 6,589.88
Fine Sand Bag 195.26 85.00 16,596.73 16,596.73

7.2.00 CEMENT SCREED

50 mm thk cement screed


7.2.01 GROUND FLOOR m2 114.20 100.00 - 11,419.50 11,419.50
Cement Bag 38.07 135.00 5,138.78 5,138.78
Coarse Sand Bag 152.26 60.00 9,135.60 9,135.60

7.2.02 FIRST FLOOR m2 113.64 100.00 - 11,364.20 11,364.20


Cement Bag 37.88 135.00 5,113.89 5,113.89
Coarse Sand Bag 151.52 60.00 9,091.36 9,091.36

7.3.00 FLOOR TILING

600 x 600 mm Homogenous tiles


7.3.01 GROUND FLOOR m2 107.18 200.00 - 21,436.00 21,436.00
600x600mm Floor tiles Nos 327.49 85.00 27,837.03 27,837.03
Tile adhesive 25kg bag 81.87 200.00 16,374.72 16,374.72
-
7.3.02 FIRST FLOOR m2 100.12 200.00 - 20,023.40 20,023.40
600x600mm Floor tiles Nos 305.91 85.00 26,002.61 26,002.61
Tile adhesive 25kg bag 76.48 200.00 15,295.65 15,295.65
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
-
600 x 100 mm Homogenous skirting tiles - - -
7.3.04 GROUND FLOOR m 107.62 30.00 - 3,228.66 3,228.66
600x600mm Floor tiles Nos 35.87 85.00 3,049.29 3,049.29
Tile adhesive 25kg bag 8.97 200.00 1,793.70 1,793.70
-
7.3.05 FIRST FLOOR m 122.48 30.00 - 3,674.25 3,674.25
600x600mm Floor tiles Nos 40.83 85.00 3,470.13 3,470.13
Tile adhesive 25kg bag 10.21 200.00 2,041.25 2,041.25
-
300 x 300 mm Homogenous tiles - - -
7.3.07 GROUND FLOOR m2 7.02 200.00 - 1,403.00 1,403.00
300x300mm Floor tiles Nos 85.74 30.00 2,572.17 2,572.17
Tile adhesive 25kg bag 7.14 200.00 1,428.98 1,428.98

7.3.07 FIRST FLOOR m2 13.53 200.00 - 2,705.00 2,705.00


300x300mm Floor tiles Nos 165.31 30.00 4,959.17 4,959.17
Tile adhesive 25kg bag 13.78 200.00 2,755.09 2,755.09

7.4.00 WALL TILING

300 x 600 mm Homogenous tiles


7.4.02 GROUND FLOOR m2 42.68 200.00 - 8,535.40 8,535.40
600x300mm Wall tiles Nos 260.80 45.00 11,736.18 11,736.18
Tile adhesive 25kg bag 26.08 200.00 5,216.08 5,216.08

7.4.02 FIRST FLOOR m2 77.41 200.00 - 15,481.44 15,481.44


600x300mm Wall tiles Nos 473.04 45.00 21,286.98 21,286.98
Tile adhesive 25kg bag 47.30 200.00 9,460.88 9,460.88

7.5.00 STAIRCASE TILING

900 x 300 mm Homogenous tiles with strips


7.5.01 GROUND FLOOR - FIRST FLOOR m2 7.00 250.00 - 1,750.00 1,750.00
900x300mm Staircase tiles set Nos 17.00 250.00 4,250.00 4,250.00
Tile adhesive 25kg bag 9.00 200.00 1,800.00 1,800.00

7.7.00 GRANITE WORK


7.7.01 GROUND FLOOR m2 2.75 3,000.00 500.00 8,250.00 1,375.00 9,625.00

TOTAL OF BILL №: 07 - Carried Over To Summary 290,495.10 198,112.15 488,607.25


8.0.00 Bill №: 08 - SUSPENDED CEILING

GENERAL
(a) Rates shall include for: all labour in framing, notching and
fitting around projections, pipes, light fittings, hatches,
grilles and similar and complete with cleats, packers, wedges
and similar and all nails and screws.
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE

8.1.00 PLASTERBOARD CEILING

Fixed plasterboard ceiling system with timber framing


TOILETS
8.1.02 GROUND FLOOR TOILET m2 7.02 200.00 - 1,403.00 1,403.00
6mm cement Board Nos 2.44 350.00 852.52 852.52
35 x 50 mm treated pine wood timber m 42.09 35.00 1,473.15 1,473.15
3" black Screw Nos 52.61 2.00 105.23 105.23
1 1/2" black screw Nos 58.22 1.50 87.34 87.34
1" black screw Nos 58.22 0.50 29.11 29.11
1 1/2" Wall plug Nos 52.61 1.00 52.61 52.61

8.1.02 FIRST FLOOR TOILET m2 13.53 200.00 - 2,705.00 2,705.00


6mm cement Board Nos 4.70 350.00 1,643.66 1,643.66
35 x 50 mm treated pine wood timber m 81.15 35.00 2,840.25 2,840.25
3" black Screw Nos 101.44 2.00 202.88 202.88
1 1/2" black screw Nos 112.26 1.50 168.39 168.39
1" black screw Nos 112.26 0.50 56.13 56.13
1 1/2" Wall plug Nos 101.44 1.00 101.44 101.44

8.1.01 FIRST FLOOR ROOFING AREA m2 146.48 200.00 - 29,295.00 29,295.00


6mm gypsum Board Nos 50.86 350.00 17,800.78 17,800.78
35 x 50 mm treated pine wood timber m 878.85 35.00 30,759.75 30,759.75
3" black Screw Nos 1,098.56 2.00 2,197.13 2,197.13
1 1/2" black screw Nos 1,215.74 1.50 1,823.61 1,823.61
1" black screw Nos 1,215.74 0.50 607.87 607.87
1 1/2" Wall plug Nos 1,098.56 1.00 1,098.56 1,098.56

TOTAL OF BILL №: 08 - Carried Over To Summary 61,900.40 33,403.00 95,303.40


9.0.00 Bill №: 09 - PAINTING & DECORATIONS

GENERAL
(a) Rates shall include for: the provision, erection and removal
of scaffolding, preparation, wall putty application, rubbing
down between coats and similar work, the protection and/or
masking floors, fittings and similar work, removing and
replacing door & window furniture.
(b) All painting work shall be carried in accordance with the
Specifications.

9.1.00 WALL PAINTING

Weatherbound paint finish as specified (EXTERNAL


SURFACES)
9.1.02 GROUND FLOOR m2 129.29 60.00 - 7,757.22 7,757.22
Exterior Wall sealer Ltr 36.94 155.00 5,725.57 5,725.57
Enamel Paint Ltr 36.94 160.00 5,910.26 5,910.26
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE

9.1.03 FIRST FLOOR m2 183.78 60.00 - 11,026.75 11,026.75


Exterior Wall sealer Ltr 52.51 155.00 8,138.79 8,138.79
Enamel Paint Ltr 52.51 160.00 8,401.33 8,401.33

Emulsion paint finish including putty application on brick


walls as specified (INTERNAL SURFACES)
9.1.05 GROUND FLOOR m2 346.98 45.00 - 15,613.99 15,613.99
Interior Wall sealer Ltr 77.11 56.00 4,317.94 4,317.94
Interior Putty Kg 346.98 13.00 4,510.71 4,510.71
Emulsion Paint Ltr 77.11 100.00 7,710.61 7,710.61

9.1.06 FIRST FLOOR m2 313.10 45.00 - 14,089.68 14,089.68


Interior Wall sealer Ltr 69.58 56.00 3,896.41 3,896.41
Interior Putty Kg 313.10 13.00 4,070.35 4,070.35
Emulsion Paint Ltr 69.58 100.00 6,957.87 6,957.87

9.2.00 CEILING PAINTING

Selected paint finish including putty application on ceiling as


specified (CEILING)
9.2.01 GROUND FLOOR m2 114.20 60.00 - 6,851.70 6,851.70
Interior Wall sealer Ltr 25.38 56.00 1,421.09 1,421.09
Interior Putty Kg 114.20 13.00 1,484.54 1,484.54
Emulsion Paint Ltr 25.38 100.00 2,537.67 2,537.67

9.2.02 FIRST FLOOR m2 160.00 60.00 - 9,600.00 9,600.00


Interior Wall sealer Ltr 35.56 56.00 1,991.11 1,991.11
Interior Putty Kg 160.00 13.00 2,080.00 2,080.00
Emulsion Paint Ltr 35.56 100.00 3,555.56 3,555.56

TOTAL OF BILL №: 09 - Carried Over To Summary 72,709.80 64,939.34 137,649.14


10.0.00 Bill №: 10 - STAIRS, WALKWAYS AND BALUSTRADES

GENERAL
(a) Rates shall include for: all fabrication work, welding,
marking, drilling for bolts incl. those securing timbers, steel
plates, bolts, nuts and any type of washer, riveted work,
counter sinking and tapping for bolts or machine screws.

(b) Rates shall include for fabrication and erection and


temporary supports and fixing into position.
10.1.00 STAIRCASE RAILING
50 and 25mm dia GI handrail at 900mm height as per
drawing
10.1.01 GROUND - 1ST FLOOR m 7.00 2,000.00 500.00 14,000.00 3,500.00 17,500.00
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
TOTAL OF BILL №: 10 - Carried Over To Summary 14,000.00 3,500.00 17,500.00
11.0.00 Bill №: 11 - MECHANICAL & ELECTRICAL SERVICES
GENERAL
(a) Design, provide and install electrical network for the entire
building complete in accordance to standards set by the
local governing body STELCO/FENAKA
(b) The following items and description and the drawings are
given as a guidance as to the nature of the information
required to be returned by the contractor. Should they not
be appropriate the contractor should provide a similar BOQ
using the Additions/Ommisions sheets provided at the back
of this BOQ.

(c) The cost shall include for: screws, nails, bolts, nuts, standard
cable fixing or supporting clips, brackets, straps, rivets, plugs
and all incidental accessories.
(d) Rate shall include for necessary chasings, trenching,
conduits, cables, cable trays, fittings and clips, cutting holes
and chases in brick work/ block work/ concrete work
complete with all necessary accessories such as sockets,
connections, cable glands and boxes, hardware clips,
soldering and jointing materials etc., for proper installing
(e) Rates for electrical isolators, conduits, fittings, equipment
and similar items shall include for: all fixings to various
building surfaces.
(f) A light fixture is measured as one point; switch end of wire is
not included in the quantity.
(g) A point wiring for power points is measured (regardless of 1
gang, 2 gang etc) as one point for each socket outlet; other
end of wire is not included in the quantity.

(h) All under ground cables directly buried in ground/run in


trenches to be properly laid and covered with cable
tiles/trench covers. Rate for under ground cables shall
include for all necessary excavation, sand layers, concrete
tiles, warning strips and back filling with approved quality
earth properly compacted, hot dipped galvenized brackets
(i) The contractors are requested to refer Conditions of
Contract, Special Conditions of Contract, Drawings and
Specification and other relevant documents related to this
tender prior to pricing of the following items
(j) The contractor shall provide a schedule of all builder's work
in connection with details of such items as necessary, along
with the tender.
(k) Rates for materials/ plants/ equipments not approved for
duty free facilities to be quoted on duty paid basis.
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
(l) All equipments shall be guaranteed for a period of 12
months from the date of commissioning or date of practical
completion of the project which ever later
(m) The rate shall include for insurance during handling,
rehandling, transport, storage until ready for installation,
delivery of equipments up to the point of installation and
until handing over.
(n) The rates shall include for comprehensive maintenance
during defects liability period of 12 months from the date of
handing
(o) The over shall submit the following information on the
tenderer
items/equipments quoted for together with the tender.

a. make
b. model No.
c. technical data
d. country of manufacture
e. delivery period
f. lead time for manufacturing.
g. port of shipping
h. CIF value of each item in foreign currency.
j. Optional items and their additional cost. (additional
cost

to be submitted separately)
k. Schedule of items to be carried out by others
connected to of generators/transformers/Electrical
installation
panels
such as some builders work and electrical
l. Details of all special features
m. schedule attached to specification.
(p) Rate for all electrical panels shall include for supply and
installation of all necessary MCCBs, MCBS, EFRs, ELCBs,
auxiliary contacts, Voltmeters, ammeters, Digital
analyser,kWh meters, indicator lamps, selector switches,
copper bus bars, inter locks, aligning and grounding of the
panel, inter connectors, internal wiring connections to
switch gear,steel channels and necessary hardware fixing
insulating materials,all in fully enclosed metal clad panels
and distribution boards completed as shown in drawing.
They shall comply with the specifications
andI.E.E.regulations and be complete to working order to
the approval of local authorities.

(q) Rate shall include for supply, installation, maintaining,


testing and commissioning of the system for power and
lighting according to drawings and specifications to working
order.
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
(r) All materials, equipment wiring shall confirm to local codes,
specifications, standards/latest I.E.E. regulations ( BS 7671 ).

11.1.00 MAIN DISTRIBUTION, SUB DISTRIBUTION AND DISTRIBUTION SYSTEM

Distribution Boards ( DB )
Distribution Panel for each floor as shown on the drawing,
complete with all incoming and outgoing MCBs, RCCBs, etc
any other item required to working order, wall mounted wall
mount steel powder coated, IP44 enclouser with neutral
link, earth bar and required accessories, all complete as per

11.1.01 Distribution Boards nr 2.00 1,000.00 - 2,000.00 2,000.00


11.1.02 24 Mod Distribution Board nr 2.00 2,500.00 5,000.00 5,000.00
11.1.03 40A ELCB (2POLE) nr 2.00 500.00 1,000.00 1,000.00
11.1.04 40A MCB (2POLE) nr 2.00 400.00 800.00 800.00
11.1.05 16A MCB nr 10.00 31.00 310.00 310.00
11.1.06 10A MCB nr 46.00 196.00 9,016.00 9,016.00
11.1.07 6A MCB nr 22.00 58.00 1,276.00 1,276.00
-
MAIN / SUB CABLING
All under ground cables directly buried in ground/ in the
trenches as appilcable, to be laid properly and covered with
cable tiles, protection tapes, etc for mechanical protection,
PVC sleeves may use if required. Rate shall include for all
necessary works/accessories such as excavation, sand layers,
cable tiles, warning strips and back filling with approved
quality earth,properly compacted, to the satisfication of the
Engineer.

All above ground cables shall be laid on cable tray/ trucnking


/conduits as appilcable and covered by tray covers, etc. for
mechanical protection. PVC sleeves may use if required. Rate
shall include for all necessary works/ accessories such as
galvernized brackets, supporting materials, fittings, nails,
cable ties, earthing, etc, trays shall be of required sizes, GI
powder coated, and shotted, to the satisfication of Engineer

11.2.00 GENERAL EARTHING


11.2.01 Allow for the total earthing system inclusive of the necessary 1,000.00 500.00 2,000.00 1,000.00 3,000.00
item 2.00
cables from all the DBs

11.3.00 POINT WIRING AND FITTINGS


ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
Rate shall include for supply & installation of cable, conduits
for point wiring in concealed installations including
lights,switches, power outlet,data points,isolators, etc, all as
specified in the drawing

11.3.01 Supply and Installation of 2 x 1C 1.5mm2 PVC/PVC/Cu + 25.00 - 3,500.00 3,500.00


2.5mm2 PVC/Cu earth cable c/w uPVC conduit, junction nr 140.00
boxes etc. for lights and switches point wiring

11.3.02 Supply and Installation of 2 x 1C 2.5mm2 PVC/PVC/Cu + 25.00 - 1,625.00 1,625.00


2.5mm2 PVC/Cu earth cable c/w uPVC conduit, junction nr 65.00
boxes,ethernet cables, RJ45 Connectors, VGA cables etc. for
the Socket outlets point wiring
11.3.03 CAT 6 CABLE Roll 1.00 3,000.00 3,000.00 3,000.00
11.3.04 TV Cable Roll 1.00 2,500.00 2,500.00 2,500.00
11.3.05 6MM 2CORE CABLE ROLL Roll 1.00 6,000.00 6,000.00 6,000.00
11.3.06 6MM GREEN CABLE ROLL Roll 1.00 3,000.00 3,000.00 3,000.00
11.3.07 2MM RED CABLE ROLL Roll 6.00 700.00 4,200.00 4,200.00
11.3.08 2MM BLACK CABLE ROLL Roll 6.00 700.00 4,200.00 4,200.00
11.3.09 2MM GREEN CABLE ROLL Roll 6.00 700.00 4,200.00 4,200.00
11.3.11 1.5MM RED CABLE ROLL Roll 8.00 450.00 3,600.00 3,600.00
11.3.11 1.5MM YELLOW CABLE ROLL Roll 8.00 450.00 3,600.00 3,600.00
11.3.12 1.5MM GREEN CABLE ROLL Roll 8.00 450.00 3,600.00 3,600.00
11.3.13 1.5MM BLACK CABLE ROLL Roll 8.00 450.00 3,600.00 3,600.00

11.4.00 FIXTURES
Rate shall include supply and installation of following
lighting fixtures, socket outlets as specified and detailed,
fixed in position including all fixing accessories, supports and
connect to power, under following conditions

1. All bathrooms, out door light fixtures shall be IP65

2. All switches & sockets shall be ABB or equivalent brand.

LIGHTS AND SWITCHES


11.4.02 Outdoor Wall Light nr 1.00 750.00 50.00 750.00 50.00 800.00
11.4.02 Indoor Wall Light nr 6.00 750.00 50.00 4,500.00 300.00 4,800.00
11.4.03 Mirror light (7W LED light) nr 6.00 600.00 50.00 3,600.00 300.00 3,900.00
11.4.04 150mm Ceiling light 18W LED nr 52.00 500.00 50.00 26,000.00 2,600.00 28,600.00
11.4.04 24w square LED down light nr 9.00 500.00 50.00 4,500.00 450.00 4,950.00
11.4.06 Ceiling fan (52" - 54") nr 9.00 750.00 100.00 6,750.00 900.00 7,650.00
11.4.07 Exhaust Fan nr 6.00 1,500.00 100.00 9,000.00 600.00 9,600.00
11.4.08 Light switch (1 G) nr 18.00 150.00 25.00 2,700.00 450.00 3,150.00
11.4.08 Light switch (2 G) nr 7.00 150.00 25.00 1,050.00 175.00 1,225.00
11.4.08 Light switch (3 G) nr 5.00 150.00 25.00 750.00 125.00 875.00
11.4.09 Light switch (4 G) nr 1.00 150.00 25.00 150.00 25.00 175.00
11.4.09 Light switch (5 G) nr 6.00 150.00 25.00 900.00 150.00 1,050.00
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
11.4.12 Heater switch nr 5.00 150.00 25.00 750.00 125.00 875.00
11.4.13 Fan Switch nr 9.00 250.00 25.00 2,250.00 225.00 2,475.00

SOCKETS
11.4.14 13 A twin sockets nr 36.00 300.00 50.00 10,800.00 1,800.00 12,600.00
11.4.15 13 A sockets nr 10.00 300.00 50.00 3,000.00 500.00 3,500.00
11.4.16 13 A sockets(WP) nr 5.00 300.00 50.00 1,500.00 250.00 1,750.00
11.4.17 15 A Sockets nr 5.00 300.00 50.00 1,500.00 250.00 1,750.00
11.4.18 15 A Sockets(WP) nr 5.00 300.00 50.00 1,500.00 250.00 1,750.00
11.4.19 Fiber Socket nr 2.00 500.00 100.00 1,000.00 200.00 1,200.00
11.4.20 Cable TV Socket nr 2.00 500.00 100.00 1,000.00 200.00 1,200.00

TOTAL OF BILL №: 11 - Carried Over To Summary 144,852.00 18,050.00 162,902.00


12.0.00 Bill №: 12 - PLUMBING

GENERAL
(a) Rates shall include for sockets, running joints, connectors,
elbows, junctions, valves, reducers, expansion joints,
backnuts and similar, incidental fitting, clips saddles,
brackets, straps, hangers, screws, nails and fixing complete,
including cutting and forming holes, excavating, laying pipes
and backfilling trenches.

(b) All pipe work and fittings shall be high pressure PVC.
(c) Rates shall include for supply and fixing of all pipes.
(d) All sanitary fixtures used shall be of superior quality and
approved by the architect/consultant on submission of
samples.

12.1.00 WATER SUPPLY


Provide and fix UPVC high pressure pipes including piping,
connections, fittings, valves, excavations, ducting, fixing with
brackets and leak testing.

INTERNAL PLUMBING - FRESH WATER SUPPLY PIPE


12.1.01 Note: Internal plumbing to all toilets and kitchen including 1,500.00 - 6,000.00 6,000.00
item 4.00
supply and laying of pipes.

EXTERNAL PLUMBING
12.1.02 All pipe works under groundfloor screed/slab to be laid for 2,500.00 - 2,500.00 2,500.00
Waste water, sewage, fresh water and well water item 1.00
connection.
12.1.03 Waste water and sewage connection from all the toilets 2,500.00 - 5,000.00 5,000.00
including the necessary catch pits and manholes as item 2.00
necessary. Rates shall include for supply and laying of pipes
including clean-outs as necessary.
12.1.04 Water connection to all toilets. Rate shall include for supply 1,500.00 - 6,000.00 6,000.00
item 4.00
and laying of pipes.
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE

12.2.00 DISCHARGE WORK


12.2.01 Provide and fix UPVC pipes including vent pipes, vent cowls, 2,000.00 - 4,000.00 4,000.00
cleaning eye, connections, fittings, valves, excavations, item 2.00
ducting, fixing with brackets, connecting to proposed septic
tank and leak testing.
12.2.02
12.2.03 4" Pvc Elbow Medium Pressure nr 8.00 79.50 636.00 636.00
12.2.04 4" 45degree Pvc Elbow Medium Pressure nr 8.00 68.90 551.20 551.20
12.2.05 4" Pvc Y Joint Medium Pressure nr 4.00 185.50 742.00 742.00
12.2.06 4" pvc R Tee medium pressure nr 4.00 185.50 742.00 742.00
12.2.07 4" pvc T joint medium pressue nr 4.00 137.80 551.20 551.20
12.2.08 4" Pvc Joint Socket Medium Pressure nr 12.00 31.80 381.60 381.60
12.2.09 4" Pvc pipe medium pressure 20 feet nr 8.00 842.70 6,741.60 6,741.60
12.2.10 3" Pvc P trap nr 4.00 686.00 2,744.00 2,744.00
12.2.12 3" Pvc Y joint medium pressure nr 8.00 84.80 678.40 678.40
12.2.12 3" Pvc T joint medium pressure nr 8.00 47.70 381.60 381.60
12.2.13 3" Pvc Elbow medium pressure nr 8.00 47.70 381.60 381.60
12.2.14 3" 45 degree Elbow Medium pressure nr 8.00 31.80 254.40 254.40
12.2.15 3" pvc joint socket medium pressure nr 12.00 26.50 318.00 318.00
12.2.16 3" x2" staight and two side Y joint (blue colour) nr 8.00 169.60 1,356.80 1,356.80
12.2.17 3"x2" pvc y joint medium pressure nr 8.00 90.10 720.80 720.80
12.2.18 3" pvc clip nr 23.00 19.08 438.84 438.84
12.2.19 3" x 2" Pvc Reducer Medium Pressure nr 16.00 26.50 424.00 424.00
12.2.20 3" Pvc pipe medium pressure 20 feet nr 4.00 561.80 2,247.20 2,247.20
12.2.21 2" Pvc Elbow Medium Pressure nr 16.00 15.90 254.40 254.40
12.2.22 2" 45degree Pvc Elbow Medium Pressure nr 16.00 16.96 271.36 271.36
12.2.23 2" Pvc T joint Medium Pressure nr 16.00 16.96 271.36 271.36
12.2.24 2" Pvc joint socket nr 16.00 10.60 169.60 169.60
12.2.25 2" Pvc pipe medium pressure 20 feet nr 11.00 307.40 3,381.40 3,381.40
12.2.26 2" pvc clip nr 23.00 15.00 345.00 345.00
12.2.27 1"x1/2" Pvc Reducer nr 12.00 25.00 300.00 300.00
12.2.28 1"x1/2" Pvc Reducer Elbow nr 16.00 9.54 152.64 152.64
12.2.29 1-1/2" pvc foot valve nr 4.00 50.00 200.00 200.00
12.2.30 1-1/2" x 1" pvc Reducer socket nr 4.00 35.00 140.00 140.00
12.2.31 1" pvc union joint nr 11.00 35.00 385.00 385.00
12.2.32 1" pvc Elbow nr 20.00 9.54 190.80 190.80
12.2.33 1" pvc T joint nr 20.00 15.00 300.00 300.00
12.2.34 1" pvc ball valve nr 8.00 42.40 339.20 339.20
12.2.35 1" Pvc pipe medium pressure 20 feet nr 4.00 116.60 466.40 466.40
12.2.36 1" pvc End cap nr 16.00 50.00 800.00 800.00
12.2.37 1" pvc Joint socket nr 20.00 6.36 127.20 127.20
12.2.38 1/2" pvc stop valve nr 12.00 250.00 3,000.00 3,000.00
12.2.39 1/2" pvc elbow nr 23.00 5.30 121.90 121.90
12.2.40 1/2" pvc inside tread elbow nr 11.00 6.36 69.96 69.96
12.2.41 1/2" pvc inside tread T joint nr 16.00 6.36 101.76 101.76
12.2.42 1/2" pvc T joint nr 16.00 6.36 101.76 101.76
12.2.43 1/2" pvc female adapter (FTA) nr 12.00 4.24 50.88 50.88
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
12.2.44 1/2" pvc male adapter (MTA) nr 12.00 4.24 50.88 50.88
12.2.45 1/2" pvc joint socket nr 12.00 4.24 50.88 50.88
12.2.46 1/2" outside tread end cap nr 12.00 4.24 50.88 50.88
12.2.47 1/2" Pvc pipe 20 feet medium pressure nr 8.00 68.90 551.20 551.20
12.2.48 1/2" pvc clip nr 16.00 2.12 33.92 33.92
12.2.49 1/2" pvc end cap nr 16.00 3.71 59.36 59.36
12.2.50 Pvc Solvent 500ml nr 4.00 68.90 275.60 275.60
12.2.51 Treadseal nr 4.00 10.60 42.40 42.40

12.3.00 FIXTURES
Complete installation, cleaning and testing of:
12.3.01 Wash basin nr 4.00 2,500.00 500.00 10,000.00 2,000.00 12,000.00
12.3.02 Wash basin tap nr 4.00 1,000.00 100.00 4,000.00 400.00 4,400.00
12.3.03 Muslim shower with stop valve nr 4.00 1,000.00 100.00 4,000.00 400.00 4,400.00
12.3.04 Soap holder nr 4.00 1,000.00 100.00 4,000.00 400.00 4,400.00
12.3.05 Floor Drain nr 7.00 500.00 100.00 3,500.00 700.00 4,200.00
12.3.06 510 x 1110 mm Face Mirror nr 4.00 500.00 100.00 2,000.00 400.00 2,400.00
12.3.07 Water Closet nr 4.00 3,500.00 1,000.00 14,000.00 4,000.00 18,000.00
12.3.08 1600 x 600 mm Counter top with tile finish nr 4.00 3,000.00 1,000.00 12,000.00 4,000.00 16,000.00
12.3.09 Water booster pump item 1.00 8,000.00 150.00 8,000.00 150.00 8,150.00
12.3.10 Shower set nr 4.00 2,500.00 500.00 10,000.00 2,000.00 12,000.00
12.3.10 Kitchen Sink nr 1.00 2,500.00 500.00 2,500.00 500.00 3,000.00

TOTAL OF BILL №: 12 - Carried Over To Summary 106,946.98 38,450.00 145,396.98

You might also like