4FDFD
4FDFD
ALITHARI N.MAAFARU
Republic of Maldives
BILL OF QUANTITIES
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
1.0.00 Bill №: 01 - PRELIMINARIES
1.4.00 CLEAN-UP
Allow for clean-up upon completion of works. item 1.00 10,000.00 5,000.00 10,000.00 5,000.00 15,000.00
2.1.00 GENERAL
(a) Rates shall include for: leveling, grading, trimming,
compacting to faces of excavation, keep sides plumb,
backfilling, consolidating, and disposing surplus soil.
2.3.00 EXCAVATION
Excavation quantities are measured to the faces of concrete
members. Rates shall include for all the additional
excavation required to place the formwork. Rates shall
include for backfilling.
2.3.01 Excavation m3 78.44 350.00 50.00 27,454.00 3,922.00 31,376.00
2.4.00 FILLING
Rate shall include for: levelling, grading, trimming,
compacting and similar
2.4.01 Compacted earth filling under ground slab m2 76.44 100.00 50.00 7,644.00 3,822.00 11,466.00
2.6.00 DE-WATERING
2.7.01 De-watering the excavation until completion of concrete 10,000.00 5,000.00 10,000.00 5,000.00 15,000.00
item 1.00
work as required
Stair Starter
3.3.09 900 x 170 mm Stair starter m3 0.18 2,600.00 - 477.36 477.36
PEDASTAL COLUMNS
3.3.10 250 x 200 mm Concrete columns C1 m3 0.26 2,600.00 - 682.50 682.50
3.3.10 225 x 200 mm Concrete columns C2 m3 0.33 2,600.00 - 859.95 859.95
3.3.10 225 x 200 mm Concrete columns C3 m3 0.24 2,600.00 - 614.25 614.25
-
Cement Bag 136.00 135.00 18,360.00 - 18,360.00
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
Coarse Sand Bag 272.00 60.00 16,320.00 - 16,320.00
Aggregate Bag 408.00 60.00 24,480.00 - 24,480.00
Admixture Ltr 13.60 50.00 680.00 - 680.00
Stair Starter
3.8.08 900 x 170 mm Stair starter m² 2.57 200.00 - 513.60 513.60
PEDASTAL COLUMNS
3.8.09 250 x 200 mm Concrete columns C1 m² 4.73 200.00 - 945.00 945.00
3.8.09 225 x 200 mm Concrete columns C2 m² 6.25 200.00 - 1,249.50 1,249.50
3.8.09 225 x 200 mm Concrete columns C3 m² 4.46 200.00 - 892.50 892.50
- -
Plywood 12mm flim faced Nos 47.00 450.00 21,150.00 21,150.00
Timber 35x50mm m3 1.18 17,000.00 19,988.19 19,988.19
Timber 50x50mm m3 0.90 17,000.00 15,357.38 15,357.38
Timber Nail 1 1/2" Kg 30.00 50.00 1,500.00 1,500.00
Timber Nail 2" Kg 10.00 50.00 500.00 500.00
3"Wooden Screw Nos 661.55 3.00 1,984.64 1,984.64
4" Wooden Screw Nos 280.00 4.00 1,120.00 1,120.00
10mm Tread Rod 1800mm Nos 17.00 75.00 1,275.00 1,275.00
10mm nut Nos 100.00 3.00 300.00 300.00
10mm washer Nos 100.00 3.00 300.00 300.00
3.13.00 STEEL WORK
FOUNDATION & FOUNDATION BEAMS
3.13.01 6 mm Steel bar in foundation nr 141.00 33.51 8.38 4,725.07 1,181.27 5,906.33
3.13.01 10 mm Steel bar in foundation nr 16.00 93.09 23.27 1,489.38 372.35 1,861.73
3.13.01 12 mm Steel bar in foundation nr 154.00 134.04 33.51 20,642.84 5,160.71 25,803.56
Stair Starter
3.13.05 10 mm in stair starter nr 15.00 93.09 23.27 1,396.30 349.07 1,745.37
pedastal Column
3.13.06 6 mm in pedastal column nr 20.00 33.51 8.38 670.22 167.56 837.78
3.13.07 12 mm in pedastal column nr 47.00 134.04 33.51 6,300.09 1,575.02 7,875.11
3.13.07 16 mm in pedastal column nr 23.00 238.30 59.58 5,480.93 1,370.23 6,851.16
Binding Wire Kg 24.13 40.00 965.12 - 965.12
COLUMNS
3.4.01 250 x 200 mm Concrete columns C1 m3 0.65 2,600.00 - 1,690.00 1,690.00
3.4.01 225 x 200 mm Concrete columns C2 m3 0.82 2,600.00 - 2,129.40 2,129.40
3.4.01 225 x 200 mm Concrete columns C3 m3 0.59 2,600.00 - 1,521.00 1,521.00
-
Floor Slab
3.4.04 100 mm slab m3 11.42 2,600.00 - 29,690.70 29,690.70
Stair case
3.3.05 Staircase m3 1.60 2,600.00 - 4,160.00 4,160.00
Beam
3.4.06 400 x 200 mm Beam B1 m3 3.27 2,600.00 - 8,513.86 8,513.86
3.4.07 400 x 200 mm Beam B2 m3 2.72 2,600.00 - 7,064.93 7,064.93
3.4.07 400 x 175 mm Beam B3 m3 0.41 2,600.00 - 1,058.88 1,058.88
3.4.07 400 x 200 mm Beam B1A m3 0.32 2,600.00 - 828.26 828.26
3.4.07 400 x 200 mm Beam B2A m3 0.35 2,600.00 - 911.46 911.46
3.4.07 400 x 200 mm Beam CB1 m3 0.18 2,600.00 - 458.64 458.64
3.4.07 400 x 200 mm Beam CB2 m3 0.16 2,600.00 - 409.76 409.76
Roof Slab
3.4.11 130 mm slab m3 13.46 2,600.00 - 34,989.76 34,989.76
COLUMNS -
3.9.01 250 x 200 mm Concrete columns C1 m² 11.70 200.00 - 2,340.00 2,340.00
3.9.01 225 x 200 mm Concrete columns C2 m² 15.47 200.00 - 3,094.00 3,094.00
3.9.01 225 x 200 mm Concrete columns C3 m² 11.05 200.00 - 2,210.00 2,210.00
Floor Slab
3.9.04 100 mm slab m² 11.00 200.00 - 2,200.00 2,200.00
Stair case
3.9.05 Staircase m² 15.00 200.00 - 3,000.00 3,000.00
Beam
3.9.06 400 x 200 mm Beam B1 m² 40.93 200.00 - 8,186.40 8,186.40
3.9.07 400 x 200 mm Beam B2 m² 33.97 200.00 - 6,793.20 6,793.20
3.9.07 400 x 175 mm Beam B3 m² 5.67 200.00 - 1,134.51 1,134.51
3.9.07 400 x 200 mm Beam B1A m² 3.98 200.00 - 796.40 796.40
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
3.9.07 400 x 200 mm Beam B2A m² 4.38 200.00 - 876.40 876.40
3.9.07 400 x 200 mm Beam CB1 m² 2.21 200.00 - 441.00 441.00
3.9.07 400 x 200 mm Beam CB2 m² 1.97 200.00 - 394.00 394.00
Roof Slab
3.9.09 130 mm slab m² 103.52 200.00 - 20,704.00 20,704.00
Column
3.14.01 6 mm in column nr 37.00 33.51 8.38 1,239.91 309.98 1,549.89
3.14.03 12 mm in column nr 47.00 134.04 33.51 6,300.09 1,575.02 7,875.11
3.14.03 16 mm in column nr 23.00 238.30 59.58 5,480.93 1,370.23 6,851.16
Floor Slab
3.14.03 6 mm in Floor slab nr 296.00 33.51 8.38 9,919.29 2,479.82 12,399.11
Stair case
3.14.04 10 mm in staircase nr 30.00 93.09 23.27 2,792.59 698.15 3,490.74
Beam
3.14.05 6 mm in beam nr 123.00 33.51 8.38 4,121.87 1,030.47 5,152.33
3.14.05 10 mm in beam nr 6.00 93.09 23.27 558.52 139.63 698.15
3.14.05 12 mm in beam nr 120.00 134.04 33.51 16,085.33 4,021.33 20,106.67
3.14.05 16 mm in beam nr 45.00 238.30 59.58 10,723.56 2,680.89 13,404.44
-
Roof Slab
3.14.08 10 mm in Roof slab nr 631.00 93.09 23.27 58,737.53 14,684.38 73,421.91
3.14.08 12 mm in Roof slab nr 15.00 134.04 33.51 2,010.67 502.67 2,513.33
Binding Wire Kg 79.63 40.00 3,185.36 - 3,185.36
Beam
3.4.06 300 x 200 mm Beam RB1 m3 0.62 2,600.00 - 1,602.12 1,602.12
3.4.06 300 x 200 mm Beam RB2 m3 78.62 2,600.00 - 204,419.80 204,419.80
3.4.06 300 x 200 mm Beam RCB1 m3 4.72 2,600.00 - 12,265.19 12,265.19
COLUMNS -
3.9.01 250 x 200 mm Concrete columns C1 m² 11.70 200.00 - 2,340.00 2,340.00
3.9.01 225 x 200 mm Concrete columns C2 m² 15.47 200.00 - 3,094.00 3,094.00
3.9.01 225 x 200 mm Concrete columns C3 m² 11.05 200.00 - 2,210.00 2,210.00
Beam
3.9.06 300 x 200 mm Beam RB1 m² 8.22 200.00 - 1,643.20 1,643.20
3.9.06 300 x 200 mm Beam RB2 m² 62.90 200.00 - 12,579.68 12,579.68
3.9.06 300 x 200 mm Beam RCB1 m² 3.50 200.00 - 700.00 700.00
Beam
3.14.05 6 mm in beam nr 95.00 33.51 8.38 3,183.56 795.89 3,979.44
3.14.05 12 mm in beam nr 91.00 134.04 33.51 12,198.04 3,049.51 15,247.56
Binding Wire Kg 16.99 40.00 679.76 - 679.76
FORM WORK
3.12.01 100 x 100 mm Ground Floor m² 26.91 200.00 - 5,382.06 5,382.06
3.12.02 100 x 100 mm First Floor m² 25.50 200.00 - 5,100.00 5,100.00
STEEL WORK
3.17.01 10 mm Lintel, Sill beams & Mid band Ground Floor Kg 31.00 93.09 23.27 2,885.68 721.42 3,607.10
3.17.02 10 mm Lintel, Sill beams & Mid band First Floor Kg 29.00 93.09 23.27 2,699.51 674.88 3,374.38
1200 mm dia ground well Nos 1.00 10,000.00 5,000.00 10,000.00 5,000.00 15,000.00
04.2.00 GENERAL
(a) Rates shall include for: fair edges, dressing over angel fillets,
roof sealant, turning into grooves, all other labours, circular
edges, nails, screws and other fixings and laps.
Lysaght roofing sheet 29" Width m 253.97 250.00 100.00 63,492.06 25,396.83 88,888.89
Wool insulation 50mmx0.9m x15m roll 12.00 1,500.00 500.00 18,000.00 6,000.00 24,000.00
PVC black net roll 6.00 950.00 500.00 5,700.00 3,000.00 8,700.00
Fascia Gutter 8' Nos 18.00 472.00 118.00 8,496.00 2,124.00 10,620.00
GI gutter clip Nos 72.00 17.00 4.25 1,224.00 306.00 1,530.00
Gutter strap Nos 72.00 4.50 1.13 324.00 81.00 405.00
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
Ridge capping 8' Nos 12.00 328.00 82.00 3,936.00 984.00 4,920.00
Fascia capping 8' Nos 5.00 328.00 82.00 1,640.00 410.00 2,050.00
Valley Gutter 8' Nos 3.00 328.00 82.00 984.00 246.00 1,230.00
Down spot 3" Nos 6.00 60.00 15.00 360.00 90.00 450.00
Roofing Screw 3" Nos 1,500.00 4.00 1.00 6,000.00 1,500.00 7,500.00
Fascia board Wood plank 4m x 200m x8mm Nos 22.00 180.00 45.00 3,960.00 990.00 4,950.00
82 mm dia rain water pipe item 6.00 1,100.00 500.00 6,600.00 3,000.00 9,600.00
GENERAL
(a) Rates shall include for locks, latches, closers, push plates,
pull handles, bolts, kick plates, hinges and all door & window
hardware.
(b) Rates shall include for door frames, mullions, transoms,
trims, glazing, tinting, timber panels, boardings, framing,
lining, fastenings and all fixings.
(c) Sizes are given overall outside dimensions of actual doors
and windows.
(d) Thickness and sizes of glass panels are shown on the
Drawings and doors and windows schedule
(e) Rates shall include for all painting as specified
(f) Rates shall include all items specified in the door schedule
and specification.
(g) Frames and sashes to be 25-60 micron white powder coated
aluminium other wise specified.
5.1.00
GROUND FLOOR
5.1.05 850 x 2200 D1-Timber Door nr 6.00 8,500.00 1,275.00 51,000.00 7,650.00 58,650.00
5.1.05 750 x 2100 D2-Pvc Door nr 2.00 6,500.00 975.00 13,000.00 1,950.00 14,950.00
5.1.05 800 x 2150 D3-Timber sliding Door nr 1.00 9,500.00 1,425.00 9,500.00 1,425.00 10,925.00
5.1.12 2300 x 1550 W1-Aluminium Swing Window nr 1.00 10,695.00 1,604.25 10,695.00 1,604.25 12,299.25
5.1.12 1500 x 1550 W2-Aluminium Swing Window nr 1.00 6,975.00 1,046.25 6,975.00 1,046.25 8,021.25
5.1.12 2500 x 1550 W3-Aluminium Swing Window nr 3.00 11,625.00 1,743.75 34,875.00 5,231.25 40,106.25
5.1.12 2180 x 2450 SD-Aluminium Sliding Door nr 1.00 16,023.00 2,403.45 16,023.00 2,403.45 18,426.45
5.1.05 750 x 2100 D2-Pvc Door nr 4.00 6,500.00 975.00 26,000.00 3,900.00 29,900.00
5.1.05 800 x 2150 D3-Timber sliding Door nr 1.00 9,500.00 1,425.00 9,500.00 1,425.00 10,925.00
5.1.12 2500 x 1550 W3-Aluminium Swing Window nr 1.00 11,625.00 1,743.75 11,625.00 1,743.75 13,368.75
5.1.12 2500 x 2450 SD1-Aluminium Sliding Door nr 3.00 18,375.00 2,756.25 55,125.00 8,268.75 63,393.75
5.1.12 1500 x 2450 FG-Aluminium Fixed Window nr 1.00 9,187.50 1,378.13 9,187.50 1,378.13 10,565.63
GENERAL
(a) Rates shall include for: cleaning out cavities, forming
rebated reveals and pointing and cleaning down to reveals
where necessary; fractional size blocks, all necessary
machine cutting, cutting or forming chases or edges of floor
slabs, cutting or leavingholes and openings as recesses for
and building in pipes, conduits, sleeves and similar as
required for all trades; leaving surfaces rough or raking out
joints for plastering and flashing, bedding frames or plates,
building in joists, bearers or similar, temporary supports to
openings, templates, reinforcement in walls and for all
necessary making good.
GENERAL
(a) Rates shall include for: fixing, bedding, grouting, and
pointing materials; making good around pipes, sanitary
fixtures, and similar; cleaning down and polishing.
(b) "Masterseal 550" or equivalent should be applied on top of
screeds and walls upto 600mm in all toilets.
7.1.00 PLASTERING
20 mm thk cement plaster on external surface as specified on
the drawing. Waterproofed with Masterpel 777 or
equivalent.
7.1.03 BELOW GROUND FLOOR m2 44.78 80.00 - 3,582.30 3,582.30
Cement Bag 7.46 135.00 1,007.52 1,007.52
Coarse Sand Bag 29.85 60.00 1,791.15 1,791.15
Fine Sand Bag 29.85 85.00 2,537.47 2,537.47
GENERAL
(a) Rates shall include for: all labour in framing, notching and
fitting around projections, pipes, light fittings, hatches,
grilles and similar and complete with cleats, packers, wedges
and similar and all nails and screws.
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
GENERAL
(a) Rates shall include for: the provision, erection and removal
of scaffolding, preparation, wall putty application, rubbing
down between coats and similar work, the protection and/or
masking floors, fittings and similar work, removing and
replacing door & window furniture.
(b) All painting work shall be carried in accordance with the
Specifications.
GENERAL
(a) Rates shall include for: all fabrication work, welding,
marking, drilling for bolts incl. those securing timbers, steel
plates, bolts, nuts and any type of washer, riveted work,
counter sinking and tapping for bolts or machine screws.
(c) The cost shall include for: screws, nails, bolts, nuts, standard
cable fixing or supporting clips, brackets, straps, rivets, plugs
and all incidental accessories.
(d) Rate shall include for necessary chasings, trenching,
conduits, cables, cable trays, fittings and clips, cutting holes
and chases in brick work/ block work/ concrete work
complete with all necessary accessories such as sockets,
connections, cable glands and boxes, hardware clips,
soldering and jointing materials etc., for proper installing
(e) Rates for electrical isolators, conduits, fittings, equipment
and similar items shall include for: all fixings to various
building surfaces.
(f) A light fixture is measured as one point; switch end of wire is
not included in the quantity.
(g) A point wiring for power points is measured (regardless of 1
gang, 2 gang etc) as one point for each socket outlet; other
end of wire is not included in the quantity.
a. make
b. model No.
c. technical data
d. country of manufacture
e. delivery period
f. lead time for manufacturing.
g. port of shipping
h. CIF value of each item in foreign currency.
j. Optional items and their additional cost. (additional
cost
to be submitted separately)
k. Schedule of items to be carried out by others
connected to of generators/transformers/Electrical
installation
panels
such as some builders work and electrical
l. Details of all special features
m. schedule attached to specification.
(p) Rate for all electrical panels shall include for supply and
installation of all necessary MCCBs, MCBS, EFRs, ELCBs,
auxiliary contacts, Voltmeters, ammeters, Digital
analyser,kWh meters, indicator lamps, selector switches,
copper bus bars, inter locks, aligning and grounding of the
panel, inter connectors, internal wiring connections to
switch gear,steel channels and necessary hardware fixing
insulating materials,all in fully enclosed metal clad panels
and distribution boards completed as shown in drawing.
They shall comply with the specifications
andI.E.E.regulations and be complete to working order to
the approval of local authorities.
Distribution Boards ( DB )
Distribution Panel for each floor as shown on the drawing,
complete with all incoming and outgoing MCBs, RCCBs, etc
any other item required to working order, wall mounted wall
mount steel powder coated, IP44 enclouser with neutral
link, earth bar and required accessories, all complete as per
11.4.00 FIXTURES
Rate shall include supply and installation of following
lighting fixtures, socket outlets as specified and detailed,
fixed in position including all fixing accessories, supports and
connect to power, under following conditions
SOCKETS
11.4.14 13 A twin sockets nr 36.00 300.00 50.00 10,800.00 1,800.00 12,600.00
11.4.15 13 A sockets nr 10.00 300.00 50.00 3,000.00 500.00 3,500.00
11.4.16 13 A sockets(WP) nr 5.00 300.00 50.00 1,500.00 250.00 1,750.00
11.4.17 15 A Sockets nr 5.00 300.00 50.00 1,500.00 250.00 1,750.00
11.4.18 15 A Sockets(WP) nr 5.00 300.00 50.00 1,500.00 250.00 1,750.00
11.4.19 Fiber Socket nr 2.00 500.00 100.00 1,000.00 200.00 1,200.00
11.4.20 Cable TV Socket nr 2.00 500.00 100.00 1,000.00 200.00 1,200.00
GENERAL
(a) Rates shall include for sockets, running joints, connectors,
elbows, junctions, valves, reducers, expansion joints,
backnuts and similar, incidental fitting, clips saddles,
brackets, straps, hangers, screws, nails and fixing complete,
including cutting and forming holes, excavating, laying pipes
and backfilling trenches.
(b) All pipe work and fittings shall be high pressure PVC.
(c) Rates shall include for supply and fixing of all pipes.
(d) All sanitary fixtures used shall be of superior quality and
approved by the architect/consultant on submission of
samples.
EXTERNAL PLUMBING
12.1.02 All pipe works under groundfloor screed/slab to be laid for 2,500.00 - 2,500.00 2,500.00
Waste water, sewage, fresh water and well water item 1.00
connection.
12.1.03 Waste water and sewage connection from all the toilets 2,500.00 - 5,000.00 5,000.00
including the necessary catch pits and manholes as item 2.00
necessary. Rates shall include for supply and laying of pipes
including clean-outs as necessary.
12.1.04 Water connection to all toilets. Rate shall include for supply 1,500.00 - 6,000.00 6,000.00
item 4.00
and laying of pipes.
ITEM MATERIAL LABOUR RATE MATERIAL AMOUNT LABOUR AMOUNT AMOUNT
DESCRIPTION UNIT QTY
RATE
12.3.00 FIXTURES
Complete installation, cleaning and testing of:
12.3.01 Wash basin nr 4.00 2,500.00 500.00 10,000.00 2,000.00 12,000.00
12.3.02 Wash basin tap nr 4.00 1,000.00 100.00 4,000.00 400.00 4,400.00
12.3.03 Muslim shower with stop valve nr 4.00 1,000.00 100.00 4,000.00 400.00 4,400.00
12.3.04 Soap holder nr 4.00 1,000.00 100.00 4,000.00 400.00 4,400.00
12.3.05 Floor Drain nr 7.00 500.00 100.00 3,500.00 700.00 4,200.00
12.3.06 510 x 1110 mm Face Mirror nr 4.00 500.00 100.00 2,000.00 400.00 2,400.00
12.3.07 Water Closet nr 4.00 3,500.00 1,000.00 14,000.00 4,000.00 18,000.00
12.3.08 1600 x 600 mm Counter top with tile finish nr 4.00 3,000.00 1,000.00 12,000.00 4,000.00 16,000.00
12.3.09 Water booster pump item 1.00 8,000.00 150.00 8,000.00 150.00 8,150.00
12.3.10 Shower set nr 4.00 2,500.00 500.00 10,000.00 2,000.00 12,000.00
12.3.10 Kitchen Sink nr 1.00 2,500.00 500.00 2,500.00 500.00 3,000.00