Tutorial 02
Tutorial 02
6CN011HK Tutorial 2
Assignment 1
Task 1 - Identify the necessary contract documents for
procuring a building using the NEC4 Engineering and
Construction Contract (Option B), and explain the purpose of
each document. (Word limit: 1000)
1
Tender Document component Tender Document component
HK Practice HK Practice
The typical tender documents to be issued with invitations to tender After award of contract, the contract document will be :
include the following:
1. Instructions to tenderer (Conditions of Tender)
The above item 1 to 10 (i.e. the tender document with priced BQ)
2. Form of tender
3. Conditions of Contract (refer to the Standard Form of Contract)
Agreement of Schedule of Conditions of Building Contract
4. Special Conditions of Contract
5. Specification Preliminaries
Letter of Award
6. General Specification
7. Particular Specification
Contract Correspondences
8. Preambles
9. Bill of quantities / Schedule of Rates
10. Schedule of tender drawings
2
NEC 4 Contents NEC 4 : Core Clause
1. Core Clauses – are used for definition of the contractual relationship. NEC 4 Core Clause No. HK Standard Form
They apply to each of the six main Options 1. General
e.g. defined terms, communications, PM and supervisor, early warning, corrupt
2. Resolving and Avoiding Disputes acts, prevention, contractor’s proposal, requirements for instructions
Option W1, W2, W3 2. The Contractor’s main responsibilities Clause 2
3
Comparison of
Comparison of common terminologies
tender document components
NEC Engineering and construction Traditional HKIA/ GCC tender
contract (ECC) document
General Condition of Tender General Condition of Tender
Special Conditions of Tender Special Conditions of Tender
Form of Tender Form of Tender
Articles of Agreement and its Schedule Articles of Agreement
Contract Data Part 1 & Part 2 Conditions of Contract / Appendix
Conditions of Contract / Additional conditions of contract
Additional conditions of contract
The Scope Specification, Particular Specification
Site Information Drawings
Activity Schedule/Bill of Quantities/ Bills of Quantities / Schedule of Rates
Price list
PREPARING THE TENDER 6. Bills of quantities (Option B and D) OR Activity Schedules (Option A and C)
7. General preambles to the bills of quantities
DOCUMENT FOR NEC CONTRACT 8. Scope
9. General particulars and preambles to Specification for the Works
Information
10. Site information
11. A pre-tender health and safety plan is normally required in UK contracts
4
Tender Document component Tender Document component
1. Instructions to tenderers (HK practice) For NEC ECC, the documents which tenderers will be required to submit
In HK practice, some may refer to “Conditions of Tender” will depend on which of the main options A to F and of the secondary
The Invitation to Tender Letters are short and simple, and all information relating options have been incorporated
to the tender should be included in the separate Instructions to Tenderers
a completed Form of Tender will be required together with part 2 of
the Contract Data
For example, the instruction to tenderers will stated which documents are
required to be submitted by tenderers
When it is intended that the Contractor will carry out design work (D&B), the
Employer may wish tendering contractors to submit information about their
For example, the instruction to tenderers will stated that no unauthorized
proposed design with their tenders
alteration or erasure to the text of the tender documents will be permitted.
It is then included in part 2 of the Contract Data
For example, the instruction to tenderers will stated that the Employer reserves If they do, the Notes to Tenderers must include particulars of the information
the right to reject any tender where these Conditions of Tender are not complied required
with
The Notes to Tenderers must also state which management functions are to be
For example, the instruction to tenderers will stated the Employer is not bound to covered by the people who are to be identified in the Contract Data as “key
accept the lowest or any tender which may be received people”
2. Form of Tender
Project title
No standard form of tender has been included in the NEC ECC
Employer’s name
as many employer have standard forms containing their own We offer to Provide the Works in accordance
with the Contract Data part one and the
requirements attached Contract Data Part Two for a sum
to be determined in accordance with the
conditions of contract.
Formalization of contract
You may accept this offer on or before [date
Tender (a Form of Tender) submitted by a contractor constitutes an of last day for acceptance]
offer
In practice, the Employer/consultant will issue tender queries/ tender
clarification / post-tender addendum to tenderers (contract Contractor’s info
correspondence)
5
Tender Document: Tender Document component
2. Contract Data Part Two
The Contract Data is a key document in any contract using the ECC
6
Tender Document component Tender Document component
5. Bill of quantities (option B) 5. Bill of quantities (option B)
Bill of quantities: This document provides a detailed The bill of quantities is to be priced and extended by tenderers, to
breakdown of the quantities of work that the contractor is produce the tendered total of the Prices
required to carry out. It is used to manage the contractor's
payments and to monitor progress. The method of measurement, on which the bill of quantities is
based, is identified in part one of the Contract Data (e.g. using
SMM7 or NRM2). This should also include identification of any
amendment or additions to the standard method of measurement
(similar to special preambles)
In accordance with NEC clause 11.2(16), Scope is “information The document contain the Scope provided by the Employer are
which either specifics and describes the works or states any identified in Part 1 of the Contract Data
constraints on how the Contractor provides the Works”
Any Scope for the Contractor’s design submitted by tenderers with
their tenders is to be identified in Part 2 of the Contract Data
It should represent a complete and precise Employer’s
requirements on the works to be provided Most of this information will be given in a specification and on
drawings in the traditional manner
7
Tender Document component
Clause 20.1 – Providing the Works 6. Scope
The Scope in Part 1 of the Contract Data (to be incorporated into tender
Clause 20.1 - “The Contractor Provides the Works in document) should include the following item:
accordance with the Scope.”
a) Description of works
The Scope in Part 1 of the Contract Data (to be incorporated into tender document) The Scope in Part 1 of the Contract Data (to be incorporated into tender document)
should include the following item: should include the following item:
Material and workmanship specification Core Clause 27.4 – “The Contractor acts in accordance with the health
and safety requirements stated in the Scope”
Requirement for delivery and storage before the incorporation of Any particular health and safety requirements, such as the safety
plan and materials in the works, provision of spares and the regulations for the factory within which the Site is located
specification of the vendor data required.
Any health and safety plan for the project (as may be required by
This can be included in the specification statute)
8
Tender Document component Tender Document component
6. Scope 6. Scope
The Scope in Part 1 of the Contract Data (to be incorporated into tender The Scope in Part 1 of the Contract Data (to be incorporated into tender document)
document) should include the following item: should include the following item:
Core Clause 21.2 – “The Contractor submits the particulars of its design as the Scope The form of this statement will depend on the extent of the Contractor’s
requires to the Project Manager for acceptance. A reason for not accepting the design responsibility
Contractor’s design is that it does not comply with either the Scope or the applicable
law. For contract with little contractor’s design, a list of what is left to be designed by the
The Contractor does not proceed with the relevant work until the Project Manager has Contractor should be provided
accepted its design”
For more comprehensive design & build contract, a list of what has been designed
Core Clause 21.3 – “The Contractor may submit its design for acceptance in parts if by the Employer should be given, with the Contractor being made responsible for
the design of each part can be assessed fully” designing the remainder
The Scope in Part 1 of the Contract Data (to be incorporated into tender document)
The Scope in Part 1 of the Contract Data (to be incorporated into tender document) should include the following item:
should include the following item:
e) Completion [Core Clause 11.2(2)]
d) Contractor’s Design [Clause 21.1]
“Completion is when the Contractor has
A design brief / performance specification for those works to be designed by the
Contractor: Done all the work which the Scope states is to be done by the Completion Date
and
Size or space limitation
Design standards and code of practice Corrected notified defects which would have prevented the Client from using the
works or Others from doing their work
Material and workmanship specification (include reference to relevant standards, e.g. B.S.)
Procedures which the Contractor is to follow in carrying out his design If the work which the Contractor is to do by the Completion Date is not stated in the
Scope, Completion is when the Contractor has done all the work necessary for the
Client to use the works and for Others to do their work
The purpose for which the Employer may require to use and copy the Contractor’s
design
9
Tender Document component Tender Document component
6. Scope 6. Scope
The Scope in Part 1 of the Contract Data (to be incorporated into tender document)
The Scope in Part 1 of the Contract Data (to be incorporated into tender document)
should include the following item:
should include the following item:
e) Completion [Clause 11.2(2)] f) Working with the Employer and Others [Clause 25.1 & 25.2]
The work required to be done by the Completion Date for the whole of the Core Clause 25.1 -“The Contractor co-operates with Others, including in
works and, if Option X5 [Sectional Completion] is used, for each of the obtaining and providing information which they need in connection with the
sections works. The Contractor shares the Working Areas with Others as stated in the
Scope”
Alternatively, this could be in the form of a list of work which can remain
undone at the Completion Date Core Clause 25.2 -“The Client and the Contractor provide services and other
things as stated in the Scope. Any cost incurred by the Client as a result of
the Contractor not providing the services and other things which it is to
provide is assessed by the Project Manager and paid by the Contractor”
f) Working with the Employer and Others [Clause 25.1 & 25.2] g) Subcontracting [Clause 26]
Core Clause 26 – “The Contractor submits the name of each proposed Subcontractor to
Details of Others who will be occupying the Working Areas during the the Project Manager for acceptance. A reason for not accepting the Subcontractor is
contract period indicating which parts they will occupy and for what periods that the appointment will not allow the Contractor to Provide the Works. The
Contractor does not appoint a proposed Subcontractor until the Project Manager has
The services and other things which the Employer and the Contractor are to accepted the Subcontractor and, to the extent these conditions of contract
provide to each other and to Others while the Contractor has access to and requires,
use of the Site accepted the subcontract documents
10
Tender Document component Tender Document component
6. Scope 6. Scope
The Scope in Part 1 of the Contract Data (to be incorporated into tender document) The Scope in Part 1 of the Contract Data (to be incorporated into tender document)
should include the following item: should include the following item:
h) Programme [Clause 31.2]
h) Programme [Clause 31.2]
Core Clause 31.2 – The Contractor shows on each programme submitted for acceptance
The starting date, access dates, Key Dates and Completion Date, Any information which the Contractor is required to include in the
Planned Completion,
programme in addition to that already stated in Clause 31.2
The order and timing of the operations which the Contractor plans to do in order to Provide the
Works,
The order and timing of the work of the Client and Others as last agreed with them by the On multi-contract projects, it will probably be necessary for the Contractor
Contractor or, if not so agreed, as stated in the Scope, to provide boundary data, foundation design data and similar information
The dates when the Contractor plans to meet each Condition stated for the Key Dates and to relating to his design for the use of the Employer and other contractors
complete other work needed to allow the Client and Others to do their work,
Provision for
Float, The times when this information is to be submitted should be stated in
Time risk allowances, accordance with the overall programme for the project
Health and safety requirements and
The procedures set out in the contract Alternatively this can be achieved by the use of the Key Dates
The accepted programme is a crucial document for managing the contract Details of materials, facilities and samples to be provided by the Contractor
and enabling the Project Manager and the Contractor to monitor the progress and the Employer for tests
of the project and assess the effect of compensation events under the NEC
Details of plants and materials which are to be inspected or tested before
delivery to the Working Areas, including details of the inspection or test
The programme submitted by tenderers, or information related to sequencing
of the work, will form part of the tender submission
Definition of tests of Equipment, Plant and Materials outside the Working
Areas which have to be passed before marking by the Supervisor
11
Tender Document component Tender Document component
6. Scope 6. Scope
The Scope in Part 1 of the Contract Data (to be incorporated into tender document) The Scope in Part 1 of the Contract Data (to be incorporated into tender document)
should include the following item: should include the following item:
The Contractor may propose an alternative guarantor who is also owned by the ultimate
holding company for acceptance by the Project Manager. A reason for not accepting the
guarantor is that its commercial position is not strong enough to carry the guarantee.
Core Clause X13.1 – The Contractor gives the Client a performance bond, provided by a
bank or insurer which the Project Manager has accepted, for the amount stated in the
Contract Data and in the form set out in the Scope. A reason for not accepting the bank
or insurer is that its commercial position is not strong enough to carry the bond. If the
bond was not given by the Contract Date, it is given to the Client within four weeks of n) Performance test [Clause 31.2]
the Contract Date.
If Option X17.1 is used – details of any test to be used to measure the performance of the
works or an item of Plant for which low performance damages are specified
12
Tender Document component
6. Scope Tender Document component
When prepare the Scope, some of the important points to note : 7. Site Information
Clarity and effective project management
Site Information forms part of the contract under the ECC
To state the requirements as clear as possible to avoid misinterpretation
and unnecessary disputes.
In accordance with NEC clause 11.2(18), Site Information is
For example, the expression such as “in the opinion of the project
manager” or “to the satisfaction of the Supervisor” should be replaced
“information which describes the Site and its surroundings”
by more definitive standards
NEC Clause 60.2 lists the information, including the Site
Information, which the Contractor is assumed to have taken into
Time for reply
account for the physical conditions within the Site for the purpose
As the project manager, the Supervisor and the Contractor are required of assessing a compensation event. As such, the Employer cannot
to reply within the period of reply unless otherwise stated in the contract specify in the Site Information that the information is provided “for
according to NEC clause 13.3, the use of expressions such as “…within a
information only”
reasonable time…” should be avoided
The documents in which the Site Information is contained are Clause 60.3 states the inconsistencies in the Site Information, for which
identified in Part 1 of the Contract Data the Employer is responsible”
Site Information may include the following: The Site Information plays an important role in assessing compensation
1. Subsoil investigation borehole records and test results events. In preparing tender documents, the Employer are reminded to
2. Reports obtained by the Employer concerning the physical conditions within the include as much relevant information as possible, including geotechnical
Site or its surroundings. This may include mapping, hydro-graphic data and baseline report, site investigation records, existing utilities records, etc.
hydrological information for tenderers to prepare their tender submissions.
3. Reference to publicly available information about the Site and its surroundings,
such as published papers and interpretations of the Geological Survey
4. Information about plant and services below the surface of the Site The Site Information will form one of the basis in judging the physical
5. Information about piped and other services (existing utilities records)
conditions for the purpose of assessing a compensation event
6. Information about buildings, structures, plant adjacent to and on the Site
13
Tender Document component Tender Document component
Normally only factual information (e.g. about physical conditions on the Site Any particular health and safety requirements, such as the safety
and its surroundings) is included in the Site Information regulations for the factory within which the Site is located
Interpretation is a matter for the Contractor
Any health and safety plan for the project (as may be required by
Some documents may contain both the Scope and Site Information. For
statute)
example, a drawing show a foundation and related borehole information.
Such a document should be identified in the Contract Data both as a
document containing the Scope and as a document containing Site
Information
14