Tutorial 03
Tutorial 03
1
Offer and Acceptance Formalization of contract HK Practice
In practice , a Form of Tender submitted by a contractor constitutes an Tender (a Form of Tender) submitted by a contractor
offer the Employer will issue tender queries post-tender addendum to constitutes an offer
tenderers, if any (contract correspondence) Finally, the Employer will
issue Letter of Award/ Letter of Acceptance to contractor which form a The creation of a contract can be by means of
legally binding contract
acceptance of a tender or a revised tender
A binding contract is thus created, although some Employers may require
such acceptance being subject to a formal agreement to record the core In practice, the Employer/consultant will issue tender
obligations of the parties involved.
queries/ tender clarification / post-tender addendum to
tenderers (contract correspondence)
A suitable form of agreement can be included in tender document, but
Employers often have their own standard forms
Employer will issue Letter of Award/ Letter of
Acceptance to contractor which form a legally binding
contract
A binding contract is thus created, although some Standard form of contract consist of :
Employers may require such acceptance Articles of Agreement
being subject to a formal agreement to record the Terms of contract (Clauses)
core obligations of the parties involved. Appendix
2
HK Standard Form 1. Enter “the contract date”
3
HK Standard Form HK Standard Form
Articles of Agreement Articles of Agreement
Hong Kong Standard Form of
Article 1 – The Contractor will Contract
carry out and complete the
Works in accordance with and
subject to the Contract for the Article 6 - If a dispute arises
consideration stated in Article 2 under or in connection with the
Contract, the parties agree to
Article 2 – The Employer will pay resolve the dispute in accordance
the Contractor the sum of with the dispute settlement
HK$ ____________________ procedures in clause 41
[Awarded Contract Sum]
4
JCT –Articles of Agreement 1. Enter “the contract date” JCT – Articles of Agreement
3. Describe the works
1) “This Agreement is made the 2. Enter Employer Name and Contractor Name 3&4) Whereas the Employer wishes 4. site address
_____ day of _____ 20___ ” to have the following work carried
out ___________________ at
___________”
2) “between the Employer
_____________ and the
Contractor __________” 5) The Contractor has supplied the
Employer with a fully priced copy of
bills of quantities, which for
identification has been signed or
initialed by or on behalf of each
Party (“the Contract Bills”)
5
JCT – Articles of Agreement JCT – Articles of Agreement
Article 3 : Architect/Contract Purpose of Articles of Agreement
Administrator Describes the work required by the employer, identifies the site, confirms the
preparation of the design and bill of quantities
Article 4 : Quantity Surveyor
Confirms that a priced copy of the bill of quantities has been supplied by
“or, if he ceases to be the
the contractor to the employer, with a priced activity schedule where
Architect/Contract Administrator, required
such other person as the Employer
nominates in accordance with Identifies the contract drawings
Clause 3.5 of the Conditions”
Identifies whether the employer is to be considered a contractor
for tax deduction purposes under the Construction Industry Scheme
Remark:
So, it is similar to HK standard form
of contract, the names of both the Clarifies whether the works are to be carried out in sections
Architect and the Quantity Surveyor
appointed by the employer will be Where the contractor is obliged to complete design works under the
recorded provisions for a contractor’s designed portion
JCT – Articles of Agreement NEC 4 2. Enter Employer Name and Contractor Name
6
NEC 4 NEC 4
7
Form of Tender NEC 4
[Clause 12.3] serves as a precaution against accidental or unintentional
Project title creation of change in the terms of the contract :
Employer’s name
We offer to Provide the Works in accordance “No change to the contract, unless provided for by these conditions of
with the Contract Data part one and the
attached Contract Data part two for a sum to contract, has effect unless it has been agreed, confirmed in writing and
be determined in accordance with the signed by the Parties”
conditions of contract.
You may accept this offer on or before [date
of last day for acceptance] [Clause 12.4] The Contract is the entire agreement between the Parties
Contractor’s info
8
NEC 4 – Contract Data Part One
e.g. W1
NEC 4 – Contract Data Part One NEC 4 – Contract Data Part One
9
NEC 4 – Contract Data Part One NEC 4 – Contract Data Part One
e.g Section 4 of the tender document
e.g. 2 weeks
e.g. English
It is generally easier to show the boundary of the site on a The period for reply must be sufficient for the parties to
drawing plan respond
NEC 4 – Contract Data Part One NEC 4 – Contract Data Part One
e.g. 52 weeks
e.g. Portion A as shown on drawing X e.g. 3 January 2025
e.g. Remainder of the Site e.g. 31 August 2025
e.g. 3 months
10
NEC 4 – Contract Data Part One NEC 4 – Contract Data Part One
e.g. HK Observatory
e.g. pound sterling
e.g. 4 weeks
09:00
e.g. The X Office….
To ensure a reasonable cash flow for the Contractor, the
assessment interval should not be too long e.g. Kowloon Kong
e.g. HK Observatory
In practice most payment procedures will be based on For consistency, it is generally an advantage to have the weather data and
weather measurement recorded at the same place
calendar months
NEC 4 – Contract Data Part One NEC 4 – Contract Data Part One
e.g. arbitration
11
NEC 4 – Contract Data Part One NEC 4 – Contract Data Part One
NEC 4 – Contract Data Part One NEC 4 – Contract Data Part One
e.g. Portion A
e.g. $400 pounds
e.g. Portion A e.g. $250 pounds e.g.Western Roundabout
12
NEC 4 – Contract Data Part One NEC 4 – Contract Data Part One
e.g. $75,000
e.g. one million pound e.g. $20 weeks after
the Contract Date
EW1
CONTRACT DATA -
PART TWO
13
投影片 51
If the Contractor is not required to carry out any design or if the Employer
The statements to be given by the tenderer in part 2 of the Contract :
does not wish the Contractor to submit any pre-tender design, there will be
Key people no entry under this heading
A list of name, job descriptions, responsibilities, qualifications and experience of key
people is required
If the Contractor is required to submit a large part of the design, the entry
will comprise a list of drawings and specifications accompanying the tender
14
Returned Tender Document Returned Tender Document
Contract Data Part Two (pro-forma for completion by tenderers) Contract Data Part Two (pro-forma for completion by tenderers)
e.g. $30,000,000
15