User-Requirement-Specification-for-Vial-filling-machine (1)
User-Requirement-Specification-for-Vial-filling-machine (1)
PRODUCTION DEPARTMENT
PROTOCOL No. :
PHARMA DEVILS
PRODUCTION DEPARTMENT
S.No. Description
Production
Production
Quality Assurance
Engineering
Head Engineering
Head Manufacturing
Head Quality
PHARMA DEVILS
PRODUCTION DEPARTMENT
3.0 Responsibilities:
In accordance with the document, following functions shall be responsible for initiation and
finalization of Equipment user requirement specification. When the work is carried by contract/
consulting staff, all the work is to be performed under the oversight of ………………...
4.2 Purpose:
For the filling of Dry powder injection in sterile filling area.
PHARMA DEVILS
PRODUCTION DEPARTMENT
13. Requirements for any power failure To be backed up by installed in-house DG set. After any
backup’s (In case of Equipment
power failure PLC show continuous counting of all filled &
/Instrument)
sealed vials.
14. Gear box specifications(In case of As per cGMP model
Equipment /Instrument)
PHARMA DEVILS
PRODUCTION DEPARTMENT
6.1 Training
S.No. Specification
8.1 In accordance with cGMP guidelines the units must be easy to clean, to disinfect, and where necessary,
to sterilize.
8.2 The Supplier should guarantee that, if required, a service team can be on site within one working day.
8.3 The design should be such as to allow mechanical cleaning of the surface and that the cleanliness of the
surface can be checked easily.
8.4 All machine parts, in particular instrumentation, should be constructed so that they can be easily
removed and calibrated.
8.5 All special tools required for running and maintenance should be best.
8.6 A spare parts delivery guarantee with in time.
10.1 Units described in the specific system requirements including all YES
necessary controls and instrumentation.
10.2 The complete mechanical and electrical installation. YES
10.3 The Connections to all the necessary utilities, exhaust, and waste lines Yes
necessary for its operation.
10.4 All piping and cabling of the units itself. YES
10.5 Wiring and cable run…………. will supply the main power switches to be YES
located in correspondence to the electrical and control cabinets delivered
by the equipment supplier.
10.6 All internal contacts of the supplied equipment for the required utilities. YES
10.7 Unload on site of the equipment: the supplier is required to define all the YES
necessary handling devices required to the unloading operation.
The supplier will inform at least 4 weeks in advance the day of delivery
and the list of required handling devices.
10.8 Assembling operation: the required consumable, the internal YES
transportation, the assembling tools and the required personal are part of
the supply.
10.9 A complete set of commissioning spare parts. YES
10.10 All special tools necessary for use and maintenance of the supplied YES
equipment.
10.11 A complete set of two years spare parts should be listed quoted and YES
offered as option.
10.12 All test activities as specified in this document. YES
10.13 Training in the use and maintenance of the equipment. YES
10.14 A complete set of documentation as specified in this document. YES
PHARMA DEVILS
PRODUCTION DEPARTMENT
11.1 General
11.2.1 The commissioning tests will be carried out in accordance with a written test YES
plan developed by the supplier with clearly stated test procedures and
acceptance criteria.
11.2.2 The contractor will approve successfully completed tests and will specify YES
items requiring additional work. Representatives from ……….will attend and
participate in the commissioning tests as required.
11.2.3 The installation and commissioning of the system will be performed at the YES
…………facility by the contractor.
11.2.4 The commissioning can only start once all the foreseen documents have been YES
delivered by the supplier to ……………….
11.2.5 All equipment should be properly installed, adjusted, leveled, tagged, and YES
connected with utilities.
11.2.6 Point to point checks on wiring and pneumatic should be performed. YES
11.2.8 A equipment (instrument) used for qualification must be listed and approved YES
by ……………..
11.2.9 The calibration equipment must have all the necessary documents to YES
demonstrate their maintenance & use.
11.2.10 The last calibration of all this equipment must be less than 6 months old, and YES
evidenced by certificate.
PHARMA DEVILS
PRODUCTION DEPARTMENT
11.2.11 Verification that the interior surfaces of equipment are free of practices and YES
dirt and all points of product contact meet the specified material requirements.
11.2.12 All the clearances and tolerances specified in the drawing or recommended YES
by component manufacturers are correct.
11.2.13 On site verification that valves and other equipment with moving parts are in YES
their normal position if in a power down condition and move in the correct
direction with the correct speed and precision.
11.2.14 Verification that all the Input and Output points are connected and labeled YES
according to the documentation and that all the along the input values have
been scaled in accordance with the system specification and process
requirements. That all equipment components requiring configuration
11.2.15 The commissioning should demonstrate that the system supplied by the YES
contractor has been properly installed and that the functions are in accordance
with …………... User Requirements specifications, Vendors System
specifications Manuals and other Documentation.
13.0 GAURANTEE/WARRANTEE