This daily progress report for the EPC project at the Oil Field Protection Force Brigade HQ Camp and South Entry Check Point details the manpower, construction activities, and planned work for March 11, 2025. The report indicates the involvement of various personnel and outlines tasks related to engineering, project control, quality control, and health, safety, and environment (HSE) management. It also notes the weather conditions and provides a summary of work disruptions and safety records.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views10 pages

8015 0150 BWBT 50 500 PM RP 00055 - 00

This daily progress report for the EPC project at the Oil Field Protection Force Brigade HQ Camp and South Entry Check Point details the manpower, construction activities, and planned work for March 11, 2025. The report indicates the involvement of various personnel and outlines tasks related to engineering, project control, quality control, and health, safety, and environment (HSE) management. It also notes the weather conditions and provides a summary of work disruptions and safety records.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 10

ENGINEERING, PROCUREMENT & CONSTRUCTION

FOR OIL FIELD PROTECTION FORCE BRIGADE HQ


CAMP
& SOUTH ENTRY CHECK POINT-WQ-2

DAILY PROGRESS REPORT FOR 11/Mar/25


Report No:00056

00 11/03/2025 IFI Issued For Infromation YAR ALLAH ALI SHAFQAT NAWAR RIYADH

REV DATE STATUS ISSUE PURPOSE ISSUED BY REVIEWED BY APPROVED BY

COMPANY DOCUMENT ATTRIBUTES

Contract Territory Sequence


Company Code Originator Code Facility Code System Code Discipline Document Type
Code Number

8015 0150 BWBT 50 500 PM RP 00056

This document is property of the OPERATOR and it shall not be disclosed to third parties, or reproduced, without permission of the OPERATOR.
This document is tracked by Integrated Document Management System (IDMS). When it is printed, it shall be considered as "For information only".
The controlled copy is the IDMS version, and thus, it is the document holder’s responsibility to make sure that the latest version is in use.
EPC FOR OIL FIELD PROTECTION FORCE
BRIGADE HQ CAMP
& SOUTH ENTRY CHECK POINT-WQ-2

DAILY PROGRESS REPORT FOR 11/Mar/25 Rev.: 00 Status:


Company No.: 8015-0150-BWBT-50-500-PM-RP-00056 Page: 2 of 09

DOCUMENT REVISION HISTORY SHEET

REV STATUS DATE ISSUED UPDATE/AMENDMENT DETAILS

00 IFI 11-Mar-2025 Issued For Information


IFI
2 of 09
PROJECT TITLE: EPC - OIL FIELD PROTECTION FORCE BRIGADE HQ CAMP
& SOUTH ENTRY CHECK POINT-WQ-2

DAILY SITE REPORT AS OF


Report No:00056 Page No.: 03 of 09
Company: Lukoil Mid-East Limited
Contractor: Bawabat AL-Rumaila General Contracting Company
Contract No.: CY-24-8015-0288
Location.: Facility 1 - Oil Field Force Protection HQ Camp
1) SUMMARY OF CONTRACTOR PERSONNEL
Direct Manpower
Indirect Manpower Off-Site Manpower
Facility 1 - OPF HQ Camp
Working Working Working
Job Title Nos. IRAQ/Expat. Job Title Nos. IRAQ/Expat. Job Title Nos. IRAQ/Expat.
hours hours hours
Project Manager 0 Iraq HSE Advisor 1 8 Iraq Project's Manager 1 8 Pakistan
HSE Manager 0 Expat Surveyor 0 Iraq QC Engineer 0 Iraq
Permit coordinator 1 8 Iraq Civil Supervisor 0 Iraq Engineering Manager 1 8 Iraq
QC Engineer 0 Survey helper 0 Iraq Cost Control Manager 2 16 Pakistan
Construction Manager 0 Iraq Driver 0 Iraq HSE Manager 1 8 Pakistan
PTW Holder 0 Iraq Planning Engineer 1 8 Iraq
Lead Architect Engineer 1 8 Iraq
0 Architect Engineer 1 8 Iraq
Drafting Engineer 2 16 Iraq
DCC 1 8 Pakistan
Security Officer 1 8 Iraq
Project Manager 1 8 Iraq
construction Mnanger 1 8 Iraq
QC Engineer 0 Iraq
Total 1 8 Iraq Total 1 8 0 Total 14 112

2) Description of work performed Today


Sr. No. Dicipline Area Construction Activities
2.1 Engineering General -
Construction General -
General Working on Progress Measurement Procedure
2.3 Project Control and planning
General working on MDR-PMS Comment with DCC
2.4 QC General Work on ITP for concrete,reinforcement,coating and grouting work
General Work on the Regulatory Compliance & Environmental Management Plan.
2.5 HSE General -
General -

3) Tests, samples, examination, inpection and NDT Today


Sr. No. Dicipline Area Construction Activities
3.1 QC/QA
3.2
3.3

4) Planned work for next day


Sr. No. Dicipline Area Construction Activities
4.1 Engineering General -
4.2 Construction General -
General Invoice Template
4.3 Project Control General Working on PMS
General -
General Work on ITP for concrete,reinforcement,coating and grouting work
4.4 QC
General -
General Work on the Regulatory Compliance & Environmental Management Plan continues
4.5 HSE
General -

5) Engineering
Manpower
5.1
Disruption Time
Description Disruption Hours Number of units Reason for Disruption Time
(Start - Finish)

Equipment
5.2
Disruption Time
Description Disruption Hours Number of units Reason for Disruption Time
(Start - Finish)

6) Area of Concern (If any)


1
2
7) Security
1
2
8) Progress (Construction & Commissioning)
Sr. No. Facility Plan Actual Variance Remarks
8.1 OPF HQ Camp

885976786.xlsx Page 4 of 10
PROJECT TITLE: EPC - OIL FIELD PROTECTION FORCE BRIGADE HQ CAMP
& SOUTH ENTRY CHECK POINT-WQ-2

DAILY SITE REPORT AS OF


Report No:00056 Page No.: 04 of 09
Company: Lukoil Mid-East Limited
Contractor: Bawabat AL-Rumaila General Contracting Company
Contract No.: CY-24-8015-0288
Location: Facility 2 - South Entry Check Point
1) SUMMARY OF CONTRACTOR PERSONNEL
Direct Manpower
Indirect Manpower Off-Site Manpower
Facility 2 - South Entry Check point
Working Working Working
Job Title Nos. IRAQ/Expat. Job Title Nos. IRAQ/Expat. Job Title Nos. IRAQ/Expat.
hours hours hours
Project Manager 0 Iraq HSE Advisor 0 Iraq Project's Manager 1 8 Pakistan
HSE Manager 0 Expat Surveyor 0 Iraq Engineering Manager 1 8 Iraq
Permit coordinator 0 Iraq Civil Supervisor 0 Iraq Cost Control Manager 2 16 Pakistan
QC Engineer 0 Survey helper 0 Iraq HSE Manager 1 8 Pakistan
Construction Manager 0 Iraq Driver 0 Iraq Planning Engineer 1 8 Iraq
PTW Holder 0 Iraq Lead Architect Engineer 1 8 Iraq
Architect Engineer 1 8 Iraq
Drafting Engineer 0 Iraq
DCC 1 8 Pakistan
Security Officer 1 8 Iraq
Project Manager 1 8 Iraq
QC Engineer 1 8 Iraq
construction Mnanger 1 8 Iraq
Total 0 0 0 Total 0 0 0 Total 13 104

2) Description of work performed Today


Sr. No. Dicipline Area Construction Activities
2.1 Engineering General SITE CIVIL 3D WORK 40%
Construction General -
General Working on Progress Measurement Procedure
2.3 Project Control and planning
General working on MDR-PMS Comment with DCC
2.4 QC General Work on ITP for concrete,reinforcement,coating and grouting work
General Work on the Regulatory Compliance & Environmental Management Plan.
2.5 HSE General -
General -

3) Tests, samples, examination, inpection and NDT Today


Sr. No. Dicipline Area Construction Activities
3.1

4) Planned work for next day


Sr. No. Dicipline Area Construction Activities
4.1 Engineering General SITE CIVIL 3D WORK 65%
4.2 General Invoice Template
4.3 Project Control General Working on PMS
General -
Construction car parking survey work
4.4 General Work on ITP for concrete,reinforcement,coating and grouting work
QC
General -
General Work on the Regulatory Compliance & Environmental Management Plan continues
HSE
4.5 General -

5) Work Disruption (If any)


Manpower
5.1
Disruption Time
Description Disruption Hours Number of units Reason for Disruption Time
(Start - Finish)

Equipment
5.2
Disruption Time
Description Disruption Hours Number of units Reason for Disruption Time
(Start - Finish)

6) Area of Concern (If any)


1
2
7) Security
1
2
8) Progress (Construction & Commissioning)
Sr. No. Facility Plan Actual Variance Remarks
8.1 South Entry Check Point

885976786.xlsx Page 5 of 10
PROJECT TITLE: EPC - OIL FIELD PROTECTION FORCE BRIGADE
HQ CAMP & SOUTH ENTRY CHECK POINT-WQ-2

DAILY SITE REPORT AS OF


Report No:00056 Page No.: 07 of 09
Company: Lukoil Mid-East Limited
Contractor: Bawabat AL-Rumaila General Contracting Company Weather Condition: Sunny
Contract No.: CY-24-8015-0288 Temperature: 25 °C
4) HSE Record

No.
Sr. No. Activity
Facility 1 Facility 2
1 New arrival orientation

2 Pre-job safety meetings

3 Pre-task JSA reviews conducted

4 New or revised JSA’s created

5 Weekly Safety Talk

6 Active Work Permits 0 0

7 Permit Audits Completed 0

8 Safety Stand Downs (Alerts/Corrections) 0

9 Weekly management walkthrough 0

10 Site induction

11 BBSO Cards submitted 0

12 Near Misses 0

13 Drills 0

14 Work Management System Assessment 0

15 Training

Incident Report(If any)


Date
Sr. No. Incident Type Brief Description Rmarks
(XX-XX-2023)
1

Related Incident Photos


PROJECT TITLE: EPC - OIL FIELD PROTECTION FORCE BRIGADE HQ CAMP
& SOUTH ENTRY CHECK POINT-WQ-2

DAILY SITE REPORT AS OF

Report No:00056 Page No.: 05 of 09


Company: Lukoil Mid-East Limited Location: BWBT Head Office Basra
Contractor: Bawabat AL-Rumaila General Contracting Company Weather Condition: Sunny
Contract No.: CY-24-8015-0288 Temperature: 25 °C
2) Manpower Report

Cumulative
Discipline / Facility 1- OPF Facility 2 South Previous Numbers of
NO Group Job Title Local Expat (including
Type of works Camp ECP Cumulative Today Workers
today)

1 2 3 4 5 6 7 8 9 10 11

1 Project Management Indirect Project's Manager 1 0 1 55 1 56

2 Project Management Indirect Project Manager 1 0 1 0 52 1 53

3 Engineering Indirect Engıneerıng Manager 1 1 0 54 1 55

4 Project Management Indirect Project Control Manager 0 2 57 2 59

5 Project Management Indirect Planning Engineer 1 1 0 53 1 54

6 Project Management Indirect Construction Manager 1 1 23 1 24

7 Project Management Indirect DCC 1 0 1 54 1 55

8 QA/QC Indirect QA/QC Manager 49 0 49

9 HSE Indirect HSE Manager 1 0 1 47 1 48

10 Engineering Indirect Civil Drafter 0 214 0 214

11 Engineering Indirect Lead Architect 1 1 57 1 58

12 Engineering Indirect Architect Engineer 1 1 55 1 56

13 Security Indirect Security Officer 1 1 0 54 1 55

14 Construction Indirect PTW Holder 8 0 8

15 HSE Indirect HSE Supervisor 1 1 7 1 8

Construction Indirect Surveyor 10 0 10

Construction Indirect Surveyor Helper 10 0 10

16 QA/QC Direct QA/QC 9 0 9

17 Construction Direct Civil Foreman 5 0 5

18 Construction Direct Earthwork / Concrete Workers 2 0 2

20 Construction Direct Operator 9 0 9

21 Construction Direct Vehicle Driver 17 0 17

23 Construction Direct Skilled Labor 11 0 11

TOTAL 10 1 8 5 912 13 925

LOCAL/EXPAT Daıly Dırect / Indırect


SUMMARY

Project Expat
Group Totals Engineering HSE QA/QC 38%
Management
Local
62%
Direct 0 0 0 0 0

Indirect 13 7 3 2 0 Indirect
100%

TOTAL 13 7 3 2 0
Direct Indirect

Cumulative Man-Day (including Number of Work


Numbers of Total Workers Average Manpower Man/Day Workhours Man-hours/Day
today) Days*

13 925 7 132 8 104


PROJECT TITLE: EPC - OIL FIELD PROTECTION FORCE BRIGADE HQ CAMP
& SOUTH ENTRY CHECK POINT-WQ-2

DAILY SITE REPORT AS OF


Report No:00056 Page No.: 06 of 09
Company: Lukoil Mid-East Limited Location: BWBT Head Office Basra
Contractor: Bawabat AL-Rumaila General Contracting Company Weather Condition: Sunny
Contract No.: CY-24-8015-0288 Temperature: 25 °C
3) Equipment Report

Discipline / Facility 1- OPF Previous Numbers of Today Cumulative


NO Equipment IDLE Facility 2 South ECP
Type of works Camp Cumulative Equipments (including today)

1 2 3 4 5 6 7 8 9

1 Civil Bore Hole Drilling Machine 15 0 15

2 Civil Pickup 0 9 0 9

3 Civil Water Tanker 0 4 0 4

4 Civil Shovel 15 0 15

5 0 0

6 0 0

7 0 0

8 0 0

9 0 0

15 0

16 0

17 0

18 0

19 0

20 0

21 0

TOTAL 43 0 43
PROJECT TITLE: EPC - OIL FIELD PROTECTION FORCE BRIGADE HQ CAMP
& SOUTH ENTRY CHECK POINT-WQ-2

DAILY SITE REPORT AS OF

Report No:00056 Page No.: 08 of 09

5.1 Photos From Site - Facility 1 - Oil Field Protection Force HQ Camp ( Standard Horizontal camera 16:9 )
Photo-1 Photo-2 Photo-3

Photo-4 Photo-5 Photo-6

885976786.xlsx Page 9 of 10
PROJECT TITLE: EPC - OIL FIELD PROTECTION FORCE BRIGADE HQ CAMP
& SOUTH ENTRY CHECK POINT-WQ-2

DAILY SITE REPORT AS OF

Report No:00056 Page No.: 09 of 09

5.2 Photos from Site - Facility 2 - South Entry Check Point ( Standard Horizontal camera 16:9 )
Photo-1 Photo-2 Photo-3

Photo-4 Photo-5 Photo-6

885976786.xlsx Page 10 of 10